experience on technical solutions -...
TRANSCRIPT
Experience on Technical Solutions for Grid Integration of Offshore Windfarms
18 June 2007, DTI Conference Centre, London
Liangzhong Yao
Programme ManagerAREVA T&D Technology Centre
Experience on Offshore Windfarms3 3
Agenda
The 90MW Barrow Offshore Wind Farm
The 400MW Sandbank 24 Offshore Wind Farm
Experience on Offshore Windfarms5 5
The 90MW Barrow Offshore Wind Farm
Offshore Platform
132kV Cable
Wind farm
Experience on Offshore Windfarms6 6
The 90MW Barrow Offshore Wind Farm
Connect 30, VESTAS V-90 3MW Wind Turbines (DFIGs) to the Grid System via an offshore sub-stationVoltages: 1kV/33kV/132kVCables
Offshore (3-core)
33kV 120mm2, 300mm2, 22.3kM
132kV 300mm2, 27km, offshore
Onshore (1-core)
132kV 400mm2, 2.6km, onshore
Ensure the connection meets the requirements of the connection agreement
Experience on Offshore Windfarms7 7
The Key Connection Requirements
The steady state reactive power flow at the Heyshamsubstation connection point shall be unity power factor+/- 5MVAr for active power flow in the range of 0 and 90MW into the NGT system.
Voltage Operation Range33kV 95% - 105%
132kV 80% - 110%
The system shall remain stable and connected to the system without tripping for a solid three phase fault or any unbalanced short circuit for a total fault clearance time of up to 140ms
Wind turbine may trip
GridQ =0<±5MVAr
Experience on Offshore Windfarms8 8
Design Solution
Reactive Power Capability Designed by Vestas V-90
Voltage Control120MVA Transformer with a tap changer range: -18% / +12%
Reactive Power Compensation Installation of a 132kV 24MVAr permanently connected reactor at Heysham Grid connection point
Installation of 2x5MVAr switchable shunt capacitors on the 33kV offshore substations
Pg
-Qg
Cosph=-0.96
Cosph=0.98+Qg
Reactive Power Capability Considered for Vestas V-90
1p.u.
+Qg
-Qg
Pg1p.u.
Experience on Offshore Windfarms9 9
Design Solution
Other Issues Considered/StudiedCable Rating
Load Flow
Losses
Three Phase and Single Phase Fault Levels
Transient Stability and Fault Ride Through Capability
Insulation Co-ordination
Ferro Resonance
Transients Due to Capacitor Switching
Circuit Energisation/De-Energisation
Harmonic
Cable Thermal Study, etc
Experience on Offshore Windfarms10 10
Some of Case Studies
Pgneration=100%
Less than +/- 5MVAr
A Example of Reactive Power Compensation
Experience on Offshore Windfarms11 11
Some of Case Studies
(a) Voltage Dip
(c) WTG Speed(b) P and Q at the Connection Point
P
Q
Wind Farm “ Ride through” the Fault
Dynamic Responses for a 3-Phase Fault at the Connection Point
Fault Ride Through
Experience on Offshore Windfarms13 13
Offshore SubstationModularised equipment
33kV Board - including protection B
33/132kV 120MVA Transformer with OLTC
132kV GIS
Relay and control panel suite room A
LVAC and DC plant room (incs UPS for navigation lights) C
225kVA standby diesel generator
Refuge, mess and workshop module D
5MVAr Shunt Capacitor bank modules E
HVAC systems
INERGEN/Water mist fire suppression system. A
OverviewLength – 23m
Width – 15m
Height – 10m
Weight – 440 tonnes
Experience on Offshore Windfarms14 14
2. The 400MW Sandbank 24 Offshore Wind Farm
in North Sea, Germany
Experience on Offshore Windfarms15 15
Introduction
Sandbank 24 Offshore Wind Farm80 Turbine Generators (5MW per turbine,DFIG, Repower)
400MW Wind Generation
Estimated Circuit Length
approximately 80kM offshore cable for wind farm, and
190kM Offshore + 50kM Onshore cables for connection
Water Depth: 25m to 30m
Connection Point: E.ON Brunsbüttel
7 phase projects in the region, and maximum WTGs to be installed=
900
Experience on Offshore Windfarms17 17
Introduction
Wind Farm LayoutGrid ConnectionPoint
Offshore substation
Experience on Offshore Windfarms18 18
Introduction
Scope of Grid Connection Option Studies
Technical feasibility and availability in terms of
manufacturing feasibility & availability and
meeting the E.ON connection requirements
Costing optimisation of each connection, including a
summarised cost breakdown for each solution
Experience on Offshore Windfarms19 19
Grid Code Requirements for Connection
Some Key Technical RequirementsReactive Power /Voltage Control Range
For example, 0.925 pf lagging to 0.95 leading depending on voltage level
Fault Ride Through CapabilitySolid grid fault up to 150ms
Power / Frequency CharacteristicFrequency Control Power Quality – Harmonics, FlickerOthers
Ref: E.ON Netz GmbH, "Grid Code: High and Extra High Voltage", August 2003
Wind turbine may trip
Experience on Offshore Windfarms20 20
Connection Options
AC Connection + Switchable/Permanently Connected Capacitors/Reactors
Fixed shunt inductors to compensate for Cable CapacitanceTransformer tap changer to control Q and V
AC Connection + Dynamic Reactive Compensation
(FACTS)SVCSTATCOM
Voltage Source HVDC (VS HVDC)Line Commutated HVDC (LC HVDC)
Needs Synchronous Compensator or STATCOM
Experience on Offshore Windfarms21 21
Connection Options
DFIG Wind Farm Connection
Connection type Doubly Fed Induction Generator orDirect Drive Synchronous Generator
AC
Risk of Harmonic resonanceHigh charge current for long cables
☺ V & Q control depending on WTG converter rating
AC +SVC or
STATCOM
Risk of Harmonic resonanceHigh AC charge current for long cables
☺ V & Q control depending on WTG converter & SVCor STATCOM rating
VS HVDC
Switching Losses ☺ P, V & Q control☺ No AC charge current
LC HVDC
P Control but needs STATCOM or Synchronous Compensator for V&Q control☺ No AC charge current☺ Lowest losses
Experience on Offshore Windfarms22 22
Option Proposals and Case Studies
Proposed Connection Options
150kV AC
220kV AC
450kV Mono-Polar HVDC
±240kV Bi-Polar HVDC
±150kV VSC HVDC
AC Connection
Conventional HVDC Connection
Experience on Offshore Windfarms23 23
Option Proposals and Case Studies
An Example of 150kV HVAC Connection OptionOne of Problems with HVAC Connection
0.920.930.940.950.960.970.980.99
11.011.021.031.041.051.061.071.081.091.1
1.111.121.131.141.15
B18
B19
B20
B21
B22
B23
B24
B25
B26
B27
B28
B29
B30
B31
B32
B33
B34
B35
B36
B37
B38
B39
B40
B41
B42
B43
B44
B45
B46
B47
B48
B49
B50
B51
B52
B53
B54
B55
B56
B57
B58
B59
B60
B61
B62
B63
B64
B65
Bus Name (Location)
Volta
ge M
agni
tude
in p
.u.
(150
kV H
VAC
Con
nect
ion )
0% Wind Generation50% Wind Generation100% Wind Generation
190kM Offshore Cable 50kM OnshoreCable
190kM Offshore Cable 50kM OnshoreCable
0.920.930.940.950.960.970.980.99
11.011.021.031.041.051.061.071.081.091.1
1.111.121.131.141.15
B18
B19
B20
B21
B22
B23
B24
B25
B26
B27
B28
B29
B30
B31
B32
B33
B34
B35
B36
B37
B38
B39
B40
B41
B42
B43
B44
B45
B46
B47
B48
B49
B50
B51
B52
B53
B54
B55
B56
B57
B58
B59
B60
B61
B62
B63
B64
B65
Bus Name (Location)
Volta
ge M
agni
tude
in p
.u.
(150
kV H
VAC
Con
nect
ion )
0% Wind Generation50% Wind Generation100% Wind Generation
190kM Offshore Cable 50kM OnshoreCable
190kM Offshore Cable 50kM OnshoreCable
BrunsbuttelGrid
10kM
10kM
ConnectionPoint
Group 1: 50MW
Group 2: 50MW
Group 3: 50MW
Group 4: 50MW
Group 5: 50MW
Group 6: 50MW
Group 7: 50MW
Group 850MW
33kV
150kV
150kV
150kV 380kV
150kV
190kM Offshore cable 50kM Onshore cable
Offshore Substation Onshore/Grid Substation
6kV
6kV
SVC/STATCOM
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
42 43 44
61
605958 62 63 64 65
18 19 20
37
363534 38 39 40 4166
21
45
67
250MVA18%
250MVA18%
250MVA18%
250MVA18%
L18
L42
L37
L61
170kV3x1x1200mm2 KQ
170kV3x1x1200mm2 KQ
BrunsbuttelGrid
10kM
10kM
ConnectionPoint
Group 1: 50MW
Group 2: 50MW
Group 3: 50MW
Group 4: 50MW
Group 5: 50MW
Group 6: 50MW
Group 7: 50MW
Group 850MW
33kV
150kV
150kV
150kV 380kV
150kV
190kM Offshore cable 50kM Onshore cable
Offshore Substation Onshore/Grid Substation
6kV
6kV
SVC/STATCOM
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
42 43 44
61
605958 62 63 64 65
18 19 20
37
363534 38 39 40 4166
21
45
67
250MVA18%
250MVA18%
250MVA18%
250MVA18%
L18
L42
L37
L61
170kV3x1x1200mm2 KQ
170kV3x1x1200mm2 KQ
Voltage Rise along with Cable Circuit
It is the same as 220KV HVAC connection
Experience on Offshore Windfarms24 24
Option Proposals and Case Studies
An Example of HVDC Connection Option- 450kV Mono-Polar HVDC
Group7
Group87475767778 737980
5556575859 546061 53 52 51
3435363738 333940 32 31 30
1415161718 1319 12 11 10 56789 4 3 2 1
2324252627 222829 21 20
4445464748 434950 42 41
6566676869 647071 63 6272
190kM Offshore Cable
50kM Onshore Cable
33kV
500MVA18%
1kM
450kV 1x800 mmsq Cu Cable24kV 1x800mmsq Return Cable400MW, 915A
Connection Point
Group1
Group2
Group3
Group4
Group5
Group6
5MW
6/33kV
500MVA18%
AC Filter
AC Filter
Brunsbuttel380kV Grid
Reactive Power Compensator
Reactive Power Compensator
450kV 1x800/1390 mmsq Offshore Cable with Integrated Return
Monopolar HVDC Link
Group7
Group874747575767677777878 737379798080
5556575859 546061 53 52 5155555656575758585959 545460606161 5353 5252 5151
3435363738 333940 32 31 3034343535363637373838 333339394040 3232 3131 3030
1415161718 1319 12 11 1014141515161617171818 13131919 1212 1111 1010 56789 4 3 2 15566778899 44 33 22 11
2324252627 222829 21 2023232424252526262727 222228282929 2121 2020
4445464748 434950 42 4144444545464647474848 434349495050 4242 4141
6566676869 647071 63 6265656666676768686969 646470707171 6363 62627272
190kM Offshore Cable
50kM Onshore Cable
33kV
500MVA18%
1kM
450kV 1x800 mmsq Cu Cable24kV 1x800mmsq Return Cable400MW, 915A
Connection Point
Group1
Group2
Group3
Group4
Group5
Group6
5MW
6/33kV
5MW
6/33kV
500MVA18%
AC FilterAC Filter
AC FilterAC Filter
Brunsbuttel380kV Grid
Reactive Power CompensatorReactive Power CompensatorReactive Power Compensator
Reactive Power CompensatorReactive Power CompensatorReactive Power Compensator
450kV 1x800/1390 mmsq Offshore Cable with Integrated Return
Monopolar HVDC Link
Experience on Offshore Windfarms25 25
Technical Performance Comparison
Losses Comparison of Various Options
Assume:Transformer copper loss: 0.5% @400MWTransformer iron (no-load) loss: 0.1% @400MWLCC HVDC Converter loss: 0.75% @400MW per converter (CIGRE)VSC HVDC Converter loss: 2% @400MW per converter (CIGRE)
1% @0MW per converter (CIGRE)
0%
10%
20%
30%
40%
50%
60%
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Wind Generation Level (%)
Pow
er L
osse
s (%
) of V
ario
us O
ptio
ns
VSC HVDCBi-Polar HVDCMono-Polar HVDC150kV HVAC220kV HVAC
P Loss (%)
Pg
AC and VSC HVDC
HVDC
Experience on Offshore Windfarms26 26
Conclusions
Technical solutions for large wind farm connection can be
AC Connection
AC + FACTS
LCC HVDC Connection
VSC HVDC connection
For 400MW Sandbank 24 offshore wind farm, both LCC HVDC and VSC HVDC technical solutions are very attractive options
LCC HVDC - low power losses, increased availability, and large power transfer capability
VSC HVDC – Capability of P &Q control to meet the gridcode requirement
To reach an engineering design solution for a wind farm connection with a grid, a number of further studies need to be done to identify the best technical and cost-effective solution