Expo Light Rail Line
Expo Line Project Westside/Central Metro Service Council
November 2014
![Page 2: Expo Light Rail Linemedia.metro.net/board/Items/2014/11_november/20141112othersect… · Expo Light Rail Line . Palms . Westwood/ Rancho Park Expo/ Sepulveda . Station Progress thru](https://reader036.vdocument.in/reader036/viewer/2022071022/5fd640c50d592e792f55045a/html5/thumbnails/2.jpg)
Expo Light Rail Line
6.6 mile corridor
7 new Stations
64,000 Daily Riders by 2030
Estimated Travel Time (Downtown LA to Santa Monica): 46 minutes
Estimated Cost: $1.5 billion
Final design in now complete
Project is 75% complete
Major construction started in 2012
Expo Line Project Description
Phase 2 Expo Line from Culver City to Santa Monica:
2
![Page 3: Expo Light Rail Linemedia.metro.net/board/Items/2014/11_november/20141112othersect… · Expo Light Rail Line . Palms . Westwood/ Rancho Park Expo/ Sepulveda . Station Progress thru](https://reader036.vdocument.in/reader036/viewer/2022071022/5fd640c50d592e792f55045a/html5/thumbnails/3.jpg)
Expo Light Rail Line Expo Light Rail Line Construction Progress
Expo Phase 2 Construction Progress at a Glance
2014 Construction Highlights:
• Station construction is more than 68% complete
• All 7 bridges have been completed
• All 7 stations are under construction
• Track installation to be completed by fall
• Roadway widening work and final paving continues
3
![Page 4: Expo Light Rail Linemedia.metro.net/board/Items/2014/11_november/20141112othersect… · Expo Light Rail Line . Palms . Westwood/ Rancho Park Expo/ Sepulveda . Station Progress thru](https://reader036.vdocument.in/reader036/viewer/2022071022/5fd640c50d592e792f55045a/html5/thumbnails/4.jpg)
Expo Light Rail Line Construction Update ROW Construction Progress
Venice Boulevard Median Construction
Sidewalk Concrete Pour at Overland Avenue
Rail Welding at the I-10 Box
OCS Pole Installation at Northvale Trench
4
![Page 5: Expo Light Rail Linemedia.metro.net/board/Items/2014/11_november/20141112othersect… · Expo Light Rail Line . Palms . Westwood/ Rancho Park Expo/ Sepulveda . Station Progress thru](https://reader036.vdocument.in/reader036/viewer/2022071022/5fd640c50d592e792f55045a/html5/thumbnails/5.jpg)
Expo Light Rail Line Palms Station
Street view from Exposition Boulevard looking west
5
![Page 6: Expo Light Rail Linemedia.metro.net/board/Items/2014/11_november/20141112othersect… · Expo Light Rail Line . Palms . Westwood/ Rancho Park Expo/ Sepulveda . Station Progress thru](https://reader036.vdocument.in/reader036/viewer/2022071022/5fd640c50d592e792f55045a/html5/thumbnails/6.jpg)
Expo Light Rail Line Westwood/Rancho Park Station
Street view from Exposition Boulevard looking east
6
![Page 7: Expo Light Rail Linemedia.metro.net/board/Items/2014/11_november/20141112othersect… · Expo Light Rail Line . Palms . Westwood/ Rancho Park Expo/ Sepulveda . Station Progress thru](https://reader036.vdocument.in/reader036/viewer/2022071022/5fd640c50d592e792f55045a/html5/thumbnails/7.jpg)
Expo Light Rail Line Expo/Sepulveda Station
Street view from Exposition Boulevard looking west
7
![Page 8: Expo Light Rail Linemedia.metro.net/board/Items/2014/11_november/20141112othersect… · Expo Light Rail Line . Palms . Westwood/ Rancho Park Expo/ Sepulveda . Station Progress thru](https://reader036.vdocument.in/reader036/viewer/2022071022/5fd640c50d592e792f55045a/html5/thumbnails/8.jpg)
Expo Light Rail Line Expo/Bundy Station
Street view from Exposition Boulevard looking east
8
![Page 9: Expo Light Rail Linemedia.metro.net/board/Items/2014/11_november/20141112othersect… · Expo Light Rail Line . Palms . Westwood/ Rancho Park Expo/ Sepulveda . Station Progress thru](https://reader036.vdocument.in/reader036/viewer/2022071022/5fd640c50d592e792f55045a/html5/thumbnails/9.jpg)
Expo Light Rail Line 26th Street/Bergamot Station
Street view from looking east
9
![Page 10: Expo Light Rail Linemedia.metro.net/board/Items/2014/11_november/20141112othersect… · Expo Light Rail Line . Palms . Westwood/ Rancho Park Expo/ Sepulveda . Station Progress thru](https://reader036.vdocument.in/reader036/viewer/2022071022/5fd640c50d592e792f55045a/html5/thumbnails/10.jpg)
Expo Light Rail Line 17th Street/SMC Station
Street view looking east
10
![Page 11: Expo Light Rail Linemedia.metro.net/board/Items/2014/11_november/20141112othersect… · Expo Light Rail Line . Palms . Westwood/ Rancho Park Expo/ Sepulveda . Station Progress thru](https://reader036.vdocument.in/reader036/viewer/2022071022/5fd640c50d592e792f55045a/html5/thumbnails/11.jpg)
Expo Light Rail Line Downtown Santa Monica Station
Street view from Colorado Avenue looking east
11
![Page 12: Expo Light Rail Linemedia.metro.net/board/Items/2014/11_november/20141112othersect… · Expo Light Rail Line . Palms . Westwood/ Rancho Park Expo/ Sepulveda . Station Progress thru](https://reader036.vdocument.in/reader036/viewer/2022071022/5fd640c50d592e792f55045a/html5/thumbnails/12.jpg)
Expo Light Rail Line
Expo/ Bundy
Expo/ Sepulveda
Westwood/ Rancho Park
Station Progress thru December 2014
• Platform foundation work completed • Track installation completed • Elevator installation nearing
completion • On-going electrical, train control
systems installation • Canopy and archway installation
Construction Progress
Palms
Palms Station Platform Paver Installation
12
![Page 13: Expo Light Rail Linemedia.metro.net/board/Items/2014/11_november/20141112othersect… · Expo Light Rail Line . Palms . Westwood/ Rancho Park Expo/ Sepulveda . Station Progress thru](https://reader036.vdocument.in/reader036/viewer/2022071022/5fd640c50d592e792f55045a/html5/thumbnails/13.jpg)
Expo Light Rail Line
Expo/ Bundy
Expo/ Sepulveda
Palms
Station Progress thru December 2014
Westwood/ Rancho Park
Construction Progress
• Platform foundation work completed
• Track installation completed • Electrical and train control
systems installation on-going • Canopy installation
Westwood Rancho Park Station Platform Pavers
13
![Page 14: Expo Light Rail Linemedia.metro.net/board/Items/2014/11_november/20141112othersect… · Expo Light Rail Line . Palms . Westwood/ Rancho Park Expo/ Sepulveda . Station Progress thru](https://reader036.vdocument.in/reader036/viewer/2022071022/5fd640c50d592e792f55045a/html5/thumbnails/14.jpg)
Expo Light Rail Line
Palms
Westwood/ Rancho Park
Expo/ Bundy
Station Progress thru December 2014 Construction Progress
Expo/ Sepulveda
• Platform foundation work completed • Track installation completed • Elevator installation nearing completion • Electrical and train control systems installation • Canopy and Archway installation • Utility Room construction
Sepulveda Station Plaza Progress
14
![Page 15: Expo Light Rail Linemedia.metro.net/board/Items/2014/11_november/20141112othersect… · Expo Light Rail Line . Palms . Westwood/ Rancho Park Expo/ Sepulveda . Station Progress thru](https://reader036.vdocument.in/reader036/viewer/2022071022/5fd640c50d592e792f55045a/html5/thumbnails/15.jpg)
Expo Light Rail Line
Palms
Westwood/ Rancho Park
Expo/ Sepulveda
Station Progress thru December 2014 Construction Progress
Expo/ Bundy
• Platform foundation work completed • Track installation completed • Elevator installation nearing completion • Electrical and train control systems installation • Canopy and Archway installation • Utility Room construction
Bundy Station Elevator Installation Progress
15
![Page 16: Expo Light Rail Linemedia.metro.net/board/Items/2014/11_november/20141112othersect… · Expo Light Rail Line . Palms . Westwood/ Rancho Park Expo/ Sepulveda . Station Progress thru](https://reader036.vdocument.in/reader036/viewer/2022071022/5fd640c50d592e792f55045a/html5/thumbnails/16.jpg)
Expo Light Rail Line Construction Progress
Venice Blvd to Motor Ave
• Venice bridge track installation completed • Venice Blvd roadway improvements
continue on the north side • Traffic signal and street light installation
Construction Activities thru December 2014 – Los Angeles
Motor Ave to Military Ave
• Complete roadway improvements at Overland Ave and Westwood Blvd • Traffic signal and street light installation
Westwood Boulevard Bus Pad Construction
Military Ave to Centinela Ave
• On-going track installation on ROW • Roadway improvements at Pico Blvd and
Barrington Ave • Traffic signal and street light installation
Pico Roadway Improvements
• Lane closures on Pico Blvd • Scheduled to begin:
Friday, December 5, 2014
16
![Page 17: Expo Light Rail Linemedia.metro.net/board/Items/2014/11_november/20141112othersect… · Expo Light Rail Line . Palms . Westwood/ Rancho Park Expo/ Sepulveda . Station Progress thru](https://reader036.vdocument.in/reader036/viewer/2022071022/5fd640c50d592e792f55045a/html5/thumbnails/17.jpg)
Expo Light Rail Line Construction Update
Expo Right-of-Way (ROW) Construction Progress – Santa Monica
Maintenance Facility Building Progress Rail Installation at 19th Street
TPSS Installation at Olympic and Cloverfield
Downtown Santa Monica Station Concrete Pour
17
![Page 18: Expo Light Rail Linemedia.metro.net/board/Items/2014/11_november/20141112othersect… · Expo Light Rail Line . Palms . Westwood/ Rancho Park Expo/ Sepulveda . Station Progress thru](https://reader036.vdocument.in/reader036/viewer/2022071022/5fd640c50d592e792f55045a/html5/thumbnails/18.jpg)
Expo Light Rail Line
Downtown Santa Monica
17th Street/ SMC
• Foundation work nearing completion
• On-going electrical and systems installation
• Canopy and archway installation
• Platform paver installation has been completed
• Track installation was completed in June
Station Progress thru December 2014
26th Street/ Bergamot
Construction Progress
26th Street /Bergamot Station Paver Installation
18
![Page 19: Expo Light Rail Linemedia.metro.net/board/Items/2014/11_november/20141112othersect… · Expo Light Rail Line . Palms . Westwood/ Rancho Park Expo/ Sepulveda . Station Progress thru](https://reader036.vdocument.in/reader036/viewer/2022071022/5fd640c50d592e792f55045a/html5/thumbnails/19.jpg)
Expo Light Rail Line
Downtown Santa Monica
26th Street/ Bergamot
Station Progress thru December 2014
• On-going electrical and systems installation
• Canopy and archway installation • Paver installation has been
completed • Foundation work is complete • Track installation was completed
in July
17th Street/ SMC
Construction Progress
17th Street /SMC Station Tactile Warning Paver Installation
19
![Page 20: Expo Light Rail Linemedia.metro.net/board/Items/2014/11_november/20141112othersect… · Expo Light Rail Line . Palms . Westwood/ Rancho Park Expo/ Sepulveda . Station Progress thru](https://reader036.vdocument.in/reader036/viewer/2022071022/5fd640c50d592e792f55045a/html5/thumbnails/20.jpg)
Expo Light Rail Line
17th Street/ SMC
26th Street/ Bergamot
• Foundation work on-going • Utility work on-going • Electrical Systems Installation • Platform paver installation to start
in November • Track installation to be completed
in October
Station Progress thru December 2014
Downtown Santa Monica
Construction Progress
Downtown Santa Monica Station Concrete Pour
20
![Page 21: Expo Light Rail Linemedia.metro.net/board/Items/2014/11_november/20141112othersect… · Expo Light Rail Line . Palms . Westwood/ Rancho Park Expo/ Sepulveda . Station Progress thru](https://reader036.vdocument.in/reader036/viewer/2022071022/5fd640c50d592e792f55045a/html5/thumbnails/21.jpg)
Expo Light Rail Line Construction Progress
Centinela Ave to 4th Street
• Continue with track installation on ROW
• Traffic signal, street light and train control systems installation
• Final street improvements
• Sidewalk installation between Stewart and Cloverfield
• Irrigation and permanent fence installation
• OCS Pole and Catenary Wire installation
Ongoing Construction Activities thru December 2014 – Santa Monica
Olympic Bridge Rail Installation Progress
6th Street Track Installation
• 6th Street is the only remaining Expo 2 track crossing
• Scheduled to begin:
Wednesday, November 12, 2014
21
![Page 22: Expo Light Rail Linemedia.metro.net/board/Items/2014/11_november/20141112othersect… · Expo Light Rail Line . Palms . Westwood/ Rancho Park Expo/ Sepulveda . Station Progress thru](https://reader036.vdocument.in/reader036/viewer/2022071022/5fd640c50d592e792f55045a/html5/thumbnails/22.jpg)
Expo Light Rail Line
• Soil removal and grading
• Irrigation, drainage systems, and curb and gutter
• Electrical and lighting conduits
Maintenance Facility • On-going installation of building pre-cast
panels
• Installation of Main building interior utilities and walls
• On-site rail installation to start in mid-October
• Foundation construction for secondary and third buildings continues
Expo Bikeway Design/Construction
Bikeway and Maintenance Facility
Maintenance Facility Building Foundation Progress
Typical Bike Path Design
22
![Page 23: Expo Light Rail Linemedia.metro.net/board/Items/2014/11_november/20141112othersect… · Expo Light Rail Line . Palms . Westwood/ Rancho Park Expo/ Sepulveda . Station Progress thru](https://reader036.vdocument.in/reader036/viewer/2022071022/5fd640c50d592e792f55045a/html5/thumbnails/23.jpg)
Expo Light Rail Line Expo Light Rail Line Construction Timeline
Construction Progress and Timeline
Construction Timeline
2011 Pre-Construction Activities
2012 Bridge Construction, Utility Relocation and Guideway Excavation, and Soundwalls
2013 Bridge and Station Construction, Utility Relocation, Soundwalls, Track Installation and Street/Roadway Improvements
2014 Continue Street/Roadway Improvements, Track Installation, Utility Relocation Station Finishes, Electrical System, Train Control, and Landscaping Installation
2015 Continue Street/Roadway Improvements and Landscaping Installation, Systems Testing and Pre-Revenue Operations
23
![Page 24: Expo Light Rail Linemedia.metro.net/board/Items/2014/11_november/20141112othersect… · Expo Light Rail Line . Palms . Westwood/ Rancho Park Expo/ Sepulveda . Station Progress thru](https://reader036.vdocument.in/reader036/viewer/2022071022/5fd640c50d592e792f55045a/html5/thumbnails/24.jpg)
Expo Light Rail Line
How to Reach Us
Contacts
Project Website: www.BuildExpo.org
Sign-up on our homepage to be added to the project database and receive notices via email.
Project Hotline: 213-922-EXPO (3976)
www.Facebook.com/ExpoLine www.Twitter.com/ExpoLine
Social Media:
Email: [email protected]
Community Relations Contacts: Torri Hill
SRJV Community Relations Manager 310-500-1485 or [email protected]
Heather Rozman SRJV Community Relations Coordinator 310-500-1487 or [email protected]
24