Exposing)the)Poten.al)of)Heavy)Timber)Construc.on))
Presented(by:(
((
“The(Wood(Products(Council”(is(a(Registered(Provider(with(The(American(Ins?tute(of(Architects(Con?nuing(Educa?on(Systems((AIA/CES),(Provider(#G516.(
(
!Credit(s)(earned(on(comple?on(of(this(course(will(be(reported(to(AIA(CES(for(AIA(members.(Cer?ficates(of(Comple?on(for(both(AIA(members(and(nonOAIA(members(are(available(upon(request.(((
This(course(is(registered(with(AIA(CES(for(con?nuing(professional(educa?on.(As(such,(it(does(not(include(content(that(may(be(deemed(or(construed(to(be(an(approval(or(endorsement(by(the(AIA(of(any(material(of(construc?on(or(any(method(or(manner(of(handling,(using,(distribu?ng,(or(dealing(in(any(material(or(product.(________________________________ Ques?ons(related(to(specific(materials,(methods,(and(services(will(be(addressed(at(the(conclusion(of(this(presenta?on.((
(
Course)Descrip.on)
Offering(a(mix(of(both(the(prac?cal(and(inspira?onal,(
this(presenta?on(focuses(on(the(use(of(heavy(?mber(in(
applica?ons(such(as(offices(and(schools,(as(well(as(
civic,(industrial,(midOrise/mul?Oresiden?al(and(other(
building(types.(Included(will(be(a(review(of(nonO
structural(provisions(in(the(Interna'onal*Building*Code*and(a(discussion(of(structural(component(and(
connec?on(methods(available.(Example(projects(
ranging(from(typical(to(unique(will(be(used(to(illustrate(
the(range(of(modern(?mber(design(solu?ons(available(
and(their(ability(to(provide(unlimited(aesthe?c(
opportuni?es(for(almost(any(building(type.(
(
Learning)Objec.ves)
1. Iden?fy(opportuni?es(available(through(nonOstructural(provisions(of(the(Interna'onal*Building*Code((IBC),(including(maximum(height(and(area(for(
exposed(heavy(?mberOframe(structures.((((
2. Discover(the(common(design(elements(and(
connec?on(op?ons(for(heavy(?mber(framing.(
3. Examine(the(commonali?es(and(differences(of(awardO
winning(heavy(?mber(structures.((
4. Become(aware(of(nonOtradi?onal(uses(for(heavy(
?mber(that(offer(unique(design(solu?ons.(
(
Outline)
• Heavy(Timber(Code(Requirements(
• Design(Elements(
• Unique(Design(Solu?ons(• Case(Studies(• Technical(Resources((
• ))One)of)the)oldest)known)forms)))))of)construc.on))
• ))Post)&)Beam)or)Timber)Framed)))))structures)date)back)before)the))))))early)Greeks.)))• ))Increased)interest)because)of)the)))))allowable)height/area)and)fire))))))resistance)advantages.)))))• ))Offers)innova.ve)commercial))))))building)solu.ons)
Timber)Frame)Construc.on)
Butler)Building)Built)in)1906)
Benefits)of)Timber)Framing)
• HandPcraQed)buildings)that)are)known)for)their)))warmth,)beauty)and)Intriguing)Shapes.))
Layton(Petro(Mart,(Greenfield,(WI(
Photo(Credit:(Arquitectura,(Inc.(
Outline)
• Heavy(Timber(Code(Requirements(
• Design(Elements(
• Unique(Design(Solu?ons(• Case(Studies(• Technical(Resources((
Why)is)heavy).mber)in)the)code?)• Historical)Prac.ce)
• Fire)Resistance)
Photos(provided(by:((
Structural(Wood(Corpora?on(
Type)IV)–)Heavy)Timber)Code)Requirements)
Type)IV)Construc.on)–)IBC)602.4)(Exterior(walls(are(of(noncombus?ble(materials(and(interior(
building(elements(are(of(solid(or(laminated(wood(without(
concealed(spaces.(FRT(wood(or(Cross(Laminated(
Timber*O2015IBC(is(permiced(in(exterior(walls,(where(2hr(fire(
ra?ng(or(less(is(required(
(
(
• Non(combus?ble(((((((((((((
Exterior(walls(
• Interior(wallsOsolid(without(concealed(spaces(
• Fire(Retardant(Treated(exterior(walls(or(Cross(laminated(
Timber((CLT)O2015(IBC((are(
allowed(if(fire(ra?ng(is(2hr(or(
less(
((
• Heavy(Timber(((
(*Exterior(surface(of(CLT(is(protected(by(FRT(
sheathing,(½”(gypsum,(or(other(nonO
combus?ble(materials(
(
(
))))HT)Minimum)Sizes)–)Floor)Framing)
Column(Suppor?ng(
Floor(Load(
>)8x8)nominal)
Beam(Suppor?ng(
Floor(Load(
>)6x10)nominal)
)IBC)Sec.on)602.4)(Table)602.4))address)minimum)sizes))
Columns)and)beams)can))be)sawn)or)GluPlaminated)
))))HT)Minimum)Sizes)–)Floor)Decking)
Column(Suppor?ng(
Floor(Load(
>)8x8)nominal)
Beam(Suppor?ng(
Floor(Load(
>)6x10)nominal)
Columns)and)beams)can))be)sawn)or)GluPlaminated)
3x(nominal(splined(or(T&G(decking(with(1”(
nominal(T&G(flooring((or(½”(par?cleboard)(OR(
4x)planks)with)1”)nominal)flooring)(or)15/32”)WSP)or)½”)par.cleboard))New)in)2015)IBC:)CLT)not)less)than)4”)thick)
The(Bullic(Center,(Seacle,(WA((((((Photo(Credit:(John(Stamets(
HT)Minimum)Sizes)–)Roof)Framing)
Column(Suppor?ng(
Roof(Load(
>)6x8)nominal)Beam(Suppor?ng(
Roof(Load(
>)4x6)nominal)
Anderson(Japanese(Gardens(Visitor's(Center,(Rockford,(IL,(Photo(Credit:(Daniel(G.(Saavedra(
HT)Minimum)Sizes)–)Roof)Decking)
Truss(Framing(
>(4x6(
The(Pepper(Planta?on(Pavilion,(Awendaw,(SC,(Photo(Credit:(SGA(Architecture)
Roof(Decking(
>(2x(T&G(Deck(
! 1O1/8”(WSP(
! 3x((on(edgeOplanks(! New(in(2015(IBC:(CLT(not(less(than(3”(thick(
Ooen(7/16”(sheathing(may(be(applied(over(2x(deck(to(increase(diaphragm(strength)
Arch)Sprung)From)the)Ground)
Timber(Arches(suppor?ng(roof(
loads(and(springing(from(floor(>(6x8(at(bocom(&(6x6(at(top(
Arches(suppor?ng(roof(loads(
from(top(of(wall(shall(be(>(4x6)Photo(Credit:(Structural((Wood(Corpora?on( St.(Edward(Catholic(Church,(Keizer,(OR(
Photo(Credit:(George(King(
Interior)Walls)in)Type)IV)Type)IV)interior)par..on)wall)op.ons:)• Solid(wood(construc?on(–(min.(2(layers(of(1Oinch(matched(boards(
• Laminated(construc?on(min.(4(inches(
• 1Ohour(fireOresistanceOrated(construc?on(
Photo(Credit:(FP(Innova?ons(
Exterior)Walls)in)Type)IV)Type)IV)exterior)wall)op.ons:)• Non(combus?ble(materials(
• Fire(Retardant(Treated(Wood(framing(in(assemblies(with(2(hour(ra?ng(
or(less(
• New(in(2015(IBC:(CLT((min.(6”(thick)(in(exterior(wall(assemblies(is(
permiced(where(ra?ng(is(2(hours(or(less(and(when(exterior(surface(is(
covered(with(min.(15/32”(FRT(sheathing,(min.(½”(gypsum,(or(other(
noncombus?ble(material((
Sauter(Timber(Produc?on(Facility,(Rockwood,(TN(
Photo(Credit:(Andreas(Sauter;(Tim(Clay(Photography(
Exterior)Curtain)Walls)in)Type)IV)
Fire(retardant(treated(curtain(walls(are(an(op?on(when(glass(
façades(are(u?lized(in(type(IV(construc?on(
LCT(One((Leo)(
Illwerke(Zentrum(Montafon((Above)(
Photo(Credit:(Norman(A.(Müller(
Heights)and)Areas)–)IBC)Table)503)
IBC)Building)Size)Limits)
Construc.on)Type)Allowable)Limit)
IIA) IIB) IV)
Stories( 5 3 5 Height((o)( 65 55 65 Building(Area/Story((o2)( 37.5k 23k 36k Total(Building(Area*((o2)( 112.5k 69k 108k
IBC(2012(Table(503(Tabular(Values(
Business((B)(Occupancies(
*(Assuming(max(stories(built(
ICC)Building)Valua.on)Data)
170.32(
155.49(
80(
100(
120(
140(
160(
180(
200(
IA( IB( IIA( IIB( IV(
$(per(Square(Foot(
IBC(Construc?on(Type(
Interna?onal(Code(Council,(Feb(2015(Data(
B(Occupancy(
Height)Modifica.on)–)IBC)504)
IBC)504.2)))Where(a(building(is(equipped(throughout(with(an(
approved(sprinkler(system…((NFPA(13)(
" (((maximum(height(is(increased(by(20(feet((
" (((maximum(number(of(stories(is(increased(by(one.(
" EXCEPT(for(IO2(occupancy(of(Type(IIB,(III(and(V(construc?on(and(H(occupancies(or(where(sprinklers(are(used(as(subs?tu?on(for(1hr(fire(resistance.(
Can)be)combined)w/)frontage)area)increase)P)506.2)Can)be)combined)w/)sprinkler)area)increase)P)506.3)*
Area)Modifica.on)–)IBC)506)(Equa?on(5O1)((
Aa(=(A
t((+([A
t(x(I
f](+([A
t(x(I
s]((
Aa(=(Allowable(area(per(story((sq.(o.)(
At(=(Tabular(area(per(story((sq.(o.)(
If(=(Area(increase(factor(due(to(frontage(((IBC(506.2)(
Is(=(Area(increase(factor(due(to(sprinkler(protec?on(((IBC(506.3)(
Is=2(if(2(stories(or(more,(Is=3(for(1(story(
(
Sprinkler(Increases(
" Up(to(3x(the(tabulated(area(for(building(w/(more(than(one(story((
" Up(to(4x(the(tabulated(area(for(a(building(no(more(than(one(story(
" The(larger(increased(area(might(allow(excluding(sprinklers(in(a(
project(
IBC)506.3)–)Floor(Areas(in(Table(503(is(permiced(to(be(
increased(by(an(addi?onal(:(
• Is(=(2(for(buildings(with(more(than(one(story(above(grade(
plane([(Aa(=(A
t(+(2A
t(+(I
f((A
t)(=(3At(+(If((At
)(](
• Is(=(3(for(buildings(with(no(more(than(one(story(above(
grade(plane.([(Aa(=(A
t(+(3A
t(+(I
f((A
t)(=(4At(+(If((At
)(](
Can)be)combined)with)height)and)story)increases)P)504.2.)Excep?on((
• Not(permiced(for(HO1,(HO2,(and(HO3(occupancies((
• Not(permiced(where(sprinklers(subs?tute(for(1hr(
construc?on((
Automa.c)Sprinkler)Increase)–)506.3)
Frontage)Increase)for)AreaP)IBC)506.2))(
(Equa?on(5O2)(
If(=([F/P(O(0.25](W/30(
F(=(Building(perimeter(that(fronts(on(a(public(way(or(open(space(having(20(feet((
(((((((open(minimum(width((feet).)P(=(Perimeter(of(en?re(building((feet).(
W(=(Width(of(public(way(or(open(space,(not(to(exceed(30(feet((
Allowable(size(of(building(may(increase(where(open(frontage(is(provided.(
Total)Building)Area–)IBC)506.4)
(
Aba(=(A
a(x(S
a((
Aba(=(Total(allowable(building(area((sq.(o.)(
Aa(=(Allowable(area(per(story((sq.(o.)(
Sa(=(Actual(number(of(stories(above(grade(plane(
(Note:(for(NFPA(13R(sprinklered(buildings,(Sa(shall(not(
(exceed(4;(for(all(other(buildings,(Sa(shall(not(exceed(3(
(
" No(single(story(area(shall(exceed(Aa(
" Unlimited(area(buildings(do(not(apply(
Using(the(Allowable(Area(per(Story,(Aa,(we(can(determine(
the(Allowable(Building(area(for(single(occupancy(buildings:(
IBC)Building)Size)Limits)w/Increases)
Construc.on)Type)Allowable)Limit)
IIA) IIB) IV)
Stories( 6 4 6 Height((o)( 85 75 85 Building(Area/Story*((o2)( 70.3k 64.6k 67.5k Total(Building(Area**((o2)( 421.8k 258.7k 405k
IBC(2012(Table(503(values(adjusted(for(fully(sprinkled(
with(an(NFPA(13(system,(100%(frontage(
Business((B)(Occupancies((
*(Assuming(all(stories(are(equal(area(
**Assuming(max(stories(built(
Opportunity)for)Office)Occupancy)(B))
85’*(
(6(stories)(
Type(IV(
(
(
(
Occupancy) Maximum)Story)area)(Q2)*)
B( 108,000(+27,000(max(frontage)(
*ASCE7(12.2O1(limits(wood(shear(wall(seismic(systems(to(65’(in(height((in(SDC(D,E,F(
(
(
(
NFPA13(
(
(
(
With(Sprinkler(&(Frontage(
increases,(Type(IV(Group(B(
building(can(be(405,000)sf)(
(
Butler)Brothers)Building,)1906,)9)stories,)500,000)sf)
Architect:)Harry)W.)Jones)Renovated)1974)
• Atrium(created(to(open(the(interior(and(provide(natural(ligh?ng(
• The(Atrium(was(the(key(to(marketability(of(the(project(
6)Story)Heavy)Timber)Structure)
Office)Building)Quebec,)QC)Dimensions:(65(o(x(170(o(Height:(6(storey,11050(sf.(Completed:(2009(
HT)Outside)of)Type)IV)Construc.on))
Type)IB,)IIA,)IIB:)Heavy(?mber(roofs(can(be(
used(where(the(required(
fire(resistance(ra?ng(is(1(
hour(or(less((IBC(Table(601(
footnote(c)(
c.(In(all(occupancies,(heavy(?mber(shall(be(allowed(where(a(1Ohour(or(less(fireOresistance(
ra?ng(is(required(
HT)Outside)of)Type)IV)Construc.on))
Type)I)&)II:))IBC)603.1.19)permits)Heavy)Timber)per)IBC)602.4.7:)Where(a(horizontal(separa?on(of(20(feet(or(more(is(provided,(
wood(columns(and(arches(conforming(to(heavy(?mber(sizes(
shall(be(permiced(to(be(used(externally(
Edgewater(at(Michaels(Landing(Canopy,(West(Des(Moines,(IA(Photo(Credit:(AG(Architecture(
HT)Roofs:)AWC)Reference)Chart)
AWC(FAQ:(Allowable(uses(of(wood(roofs(in(construc?on(types(I(
through(IV((
(
(
(
(
(
(
(
(
(
(
hcp://www.awc.org/pdf/Wood%20Roof%20Systems%20per
%202009%20IBC%20FAQ.pdf(
(
HT)Outside)of)Type)IV)Construc.on))
In)Type)III)&)V)Construc.on)Requiring)Fire)Resistance)Ra.ng:)IBC(722.1(permits(calcula?on(of(fire*resistance(for(exposed(wood(members(and(wood(decking(performed(in(accordance(
with(NDS(Chapter(16.)
Federal(Center(South(–(Building(1202(,(Seacle,(WA((
Photo(Credit:(Benjamin(Benschneider(
• Common(applica?ons(
are(exposed(?mber(
floors(and(roofs(in(IIIA,(
VA(construc?on(
• Reduced((nonOcharred)(
sec?on(is(used(for(
structural(calcula?ons(
• Protec?on(of(
connec?ons(required(
per(IBC(722.6.3.3(
(
HT)Outside)of)Type)IV)Construc.on))
In)Type)III)&)V)Construc.on)Not)Requiring)Fire)Resistance)Ra.ng:)Exposed(heavy(?mber(of(any(size(can(be(used.(Full(sec?on(is(
used(for(structural(calcula?ons.(Min.(HT(sizes(in(IBC(602.4(do(
not(need(to(be(met.(
Duke(School,(Durham,(NC,(Photo(Credit:(Jerry(Markatos(
Sprinkler)Subs.tu.on)Op.on)
IBC)Table)601,)footnote)d:)NFPA(13(sprinkler(system(can(be(
subs?tuted(for(a(1hr(fire(ra?ng(
• For(Type((IIA,(IIIA,(and(VA(• Subs?tu?on(can(NOT(be(used((
• if(sprinkler(is(used(for(allowable(height(or(area(increase(
• for(exterior(wall(fire(ra?ng(requirements(
• for(required(occupancy(separa?on(
Radiator(Building,(Portland,(OR,(Photo(Credit:(Josh(Partee(
Concealed)Space)Limita.ons)on)HT)
Type)IV)Construc.on)requires)that)interior)elements)be)without)concealed)spaces:)• Concealed(spaces(include(dropped(ceilings,(aÇcs,(
chases,(others(
Concealed(space(requirement(does(not(apply(to(any(other(
construc?on(type.(If(using(heavy(?mber(elements(in(non(
type(IV(construc?on,(concealed(spaces(are(permiced(but(
may(be(required(to(be(sprinklered(
Example(of(concealed(space(
created(by(dropped(ceiling((
Source:(US(CLT(Handbook(
Fire)Resistance)Ra.ng)PIBC)Table)601)
Type)IV)–)Heavy)TimberPFire)Requirements)
In(a(variety(of(ways(the(building(code(does(recognize(the(
ability(for(Heavy(Timber(to(resist(fires(through(charring.(
Achieving)One)Hour)Equivalency)for)Protected)Construc.on)
TR(10(
NDS(Chapter(16(
Fire(Design(of(Wood(Members(
Available(from(AWC(website(
(OR(
Equa.ons)for)Calcula.ng)Fire)Endurance)
Wood((
Beam(
Charring)of)Wood)3)sides)
Charring)of)Wood)4)sides)
• Assump?ons(
• Nominal(assumed(char(rate=1.5”/hr.(
• Uses(ul?mate(strength(for(design(check(
• Reduced(sec?on(checked( (for(capacity(vs.(demand(
Source:(AWC’s(TR(10(
Key)Component)1)–)Char)Rate)
CHAR(SLOWS(
WITH(TIMEO(
NON(LINEAR(
βeff( (=(( (Effec?ve(char(rate((in/hr),(adjusted(
(((((((((((( (for(exposure(?me,(t(
βn((=(( (Nominal(char(rate((in/hr),(linear((
((((((((((((char(rate(based(on(a(1Ohour(exposure((1.5”/hr.)(
t( (=( (Exposure(?me((hrs)(
(
187.0
2.1t
neff
ββ =
ACCOUNTS(FOR(
NONOCHARRED(
STRENGTH(RED’N(
Protec.ng)Steel)Connec.ons)
TR)10))EXCERPTS)
• 1)hr.)Protec.onP1)½”)wood,)approved))))))))covering)or)coa.ng)
Structural)Requirements)
• Columns(IBC+2304.10.1+• Con?nuous(or(superimposed(throughout(all(stories((
• Intersec?ng(beams(shall(be(closely(ficed(to(column(faces(
• Adjoining(beams(shall(be(cross(?ed(to(each(other((across(joints(
• Wood(bolsters(shall(not(be(placed(on(tops(of(columns(unless(the(
columns(support(roof(loads(only(
Bolster)
Structural)Requirements)
• Floor(framingOIBC(2304.10.2(
• Approved(wall(plate(boxes(or(hangers(are(required(where(
beams,(girders(or(trusses(rest(on(masonry(or(concrete(
walls((
• Intermediate(beams(suppor?ng(floors(shall(rest(on(the(
tops(of(girders(or(shall(be(supported(by(ledgers(securely(
fastened(to(the(girder(or(by)approved)metal)hangers)• Roof(framingOIBC(2304.10.3(
• Every(girder(and(at(least(every(other(alternate(roof(beam(
shall(be(anchored(to(its(suppor?ng(member((
• Anchors(shall(be(steel(or(iron(bolts(of(sufficient(strength(to(
resist(ver?cal(roof(uplio(loads(
Structural)Requirements)
• Floor(deckingOIBC(2304.10.4(• A(min.(½”(gap(shall%be%provided%between%the%decking%
and%wall%to%allow%for%expansion%of%the%decking • Molding(acached(to(the(wall(shall(cover(the(gap(and(shall(
not(obstruct(the(movement(of(the(decking(
• Diaphragm(connec?ons(to(perimeter(elements(should(
account(for(gap(
• Roof(deckingOIBC(2304.10.5(• Where(roof(decks(are(supported(by(walls,(the(decks(shall(
be(anchored(to(the(walls(to(resist(uplio(forces(per(Chapter(
16.(
• Anchors(shall(be(steel(or(iron(bolts(of(sufficient(strength(to(
resist(ver?cal(roof(uplio(loads(
Building)Acous.cs)Overview)
AirPborne)sound:)• Sound(Transmission(Class(
(STC)(
Measures(how(effec?vely(an(assembly(isolates(airOborne(sound(and(reduces(the(level(that(passes(from(one(side(to(the(other((
(
StructurePborne)sound:)• Impact(Insula?on(Class(
(IIC)(
Evaluates(how(effec?vely(an(assembly(blocks(impact(sound(from(passing(through(it(
(
Acous.cal)Code)Requirements)
IBC(Sec?on(1207:(
(
Min.)STC)of)50)(FSTC)of)45))for:)• All(Walls,(Par??ons,(and(Floor/Ceiling(Assemblies(
which(separate(adjacent(dwelling(units(or(a(
dwelling(unit(from(an(adjacent(public(area((
(
Min.)IIC)of)50)(FIIC)of)45))for:)• All(Floor/Ceiling(Assemblies(which(separate(
adjacent(dwelling(units(or(a(dwelling(unit(from(an(
adjacent(public(area((
Acous.cal)Performance)of)HT)Floors)
Source:(Maxxon.com(
FSTC:(50((FIIC:(45()
Acous.cal)Performance)of)HT)Floors)
ASTC:(49((FIIC:(48()
Source:(kine?csnoise.com(
Interior)Walls)in)Type)IV:)Acous.cs)
Source:(Gypsum(Associa?on(Fire(Resistance(Design(Manual(
• 1Ohour(fireOresistanceOrated(construc?on(
CLT)Acous.cs)
Number of layers
Thickness (in. ) Assembly type STC IIC
3 3-3/4 to 4-1/2 Wall 32-34 N.A.
5 5-1/3 Floor 39 23
5 5-3/4 Floor 39 24
Measured on field bare CLT wall and floor
Number of layers
Thickness in. Assembly type FSTC FIIC
3 4-1/8 Wall 28 N.A.
7 8-1/5 Floor N.A 25-30
Sound Insulation of Bare CLT Floors and Walls
Source:(US(CLT(Handbook(
Acous.cal)Performance)of)CLT)Floors)
Source:(US(CLT(Handbook(
Acous.cal)Performance)of)CLT)Floors)
Note:(dropped(ceiling(
creates(concealed(space(
which(is(not(permiced(in(
type(IV(construc?on(
Source:(US(CLT(Handbook(
Acous.cal)Performance)of)CLT)Walls)
Source:(US(CLT(Handbook(
Acous.cal)Performance)of)CLT)Walls)
Source:(US(CLT(Handbook(
More)CLT)Acous.cs)Info)
US)CLT)Handbook,)Chapter)9)• Acous?c(proper?es(of(CLT(• STC(and(IIC(rated(assemblies(
• FSTC(and(FIIC(rated(assemblies(
• Recommenda?ons(for(mee?ng(IBC(requirements(
Outline)
• Heavy(Timber(Code(Requirements(
• Design(Elements(
• Unique(Design(Solu?ons(• Case(Studies(• Technical(Resources((
Glued(Laminated(Timber( Structural(Composite(Lumber(
BeamsPSolid)Sawn)&)Engineered)Lumber)Products)))
Glued)Laminated)Beams)Available)in:))))))Framing/Industrial)Grades)–))• Intended)for)nonPexposed)condi.ons)• Architectural))Grade–)Intended)for)exposed))members.)
• Premium)Grade)also)available))
• Bonded(wood((
((((((veneers((
• Plies(
• Strands(
Equivalent)Glued)Laminated)Net)Size)
Minimum)Nominal)Solid)Sawn)Size)
Minimum)GluedPlaminated)Net)Size)
Minimum)Structural))Composite)Lumber)Net))Size)
IBC)Table)602.4)Wood)member)Size)Equivalents)
Width,)Inch) Width,)Inch)Width,)Inch)Depth,)Inch) Depth,)Inch)Depth,)Inch)
8)
6)
6)
6)
4)
10)
8)
8)
6)
6)
6)¾))
5)
5)
5)
3)
8)¾))
10)½))
8)¼)))
6))
6)7/8))
7))
5)¼)))
5)¼)))
5)¼))
9)½))
7)½))
3)½))
5)½))
7)½))
5)½))
ColumnsPSolid)Sawn)&)Mul.PPly)Sec.ons))
Mul.PPly)Columns)OK)for))unprotected)Construc.on)
Mul.PPly)Nailed)Columns)≠)Solid)Sec.on))
• IBC(sec?on(602.4.3OColumnsO(solid(sawn(or(
glueOlaminated(members(only.(
• Nailed(builtOup(columns(in(accordance(with(
NDS(Commentary(sec?on(15.3(are(not(allowed(
Heavy(?mber(framework(at(entries(serve(as(focal(points.(((
Photo(by(Universal(Forest(Products(
Heavy)Timber)Roof)
Tongue)and)Groove)Decking)
• AWC:WCD2PHorizontally)applied)tongue)and)groove)decking)
Simple)span)SimpleP2)span)Con.nuous)3)or)more)spans)Con.nuous)Controlled)random)layPup)
Diaphragm)Op.ons)
• Horizontally(applied(tongue(and(groove(decking((((((((((Low(allowable(diaphragm(shear(values,(Aspect(Ra?o(
((A/R)=2:1(
• Diagonally(applied(tongue(and(groove(decking(((((((((((((Single(layerO(moderate(shear(values,(A/R=3:1(
((((((((((((Double(layerO(high(shear(values,(A/R=4:1(
• Wood(Structural(Panel(Sheathing(Over(Decking(
((((((((((Acts(as(blocked(diaphragm,(can(achieve(high(shear( (
((((((values:(600+(plf((seismic)(900+(plf((wind)((ASD,(8d( (((
((((((nails);(A/R=4:1((SDPWS(Tables(4.2.4(&(4.2A)(
Structural)Panels)Over)Decking)
Panel(Installa?on(Requirements(
• ((Panel(Edges(must(not(coincide(with(decking((joints(
• Panel(edges(must(be(acached(to(common(member(
• Minimum(fastener(penetra?on(must(be(provided((1O3/8”(
for(8d,(1O1/2”(for(10d(per(SDPWS(Table(4.2A)(
• Maximum(4:1(aspect(ra?o(is(allowed.((
• A(complete(load(path(must(be(provided(for(forces(
Addi.onal)informa.on)can)also)be)found)in:))• APA(Form(TTO097(Designing(Diaphragms(Over(Exis?ng(
Board(Floors(or(Roofs(
• ATC(7(Guidelines(For(The(Design(of(Horizontal(Wood(
Diaphragms((available(for(purchase(at(atcouncil.org)(
HT)Decking)with)WSP)Diaphragm)
Radiator(Building,(Portland,(OR,(Photo(Credit:(Josh(Partee(
Timber)Connec.ons)
• Steel(Plate/Bolted(Connec?ons(
• Split(Rings(
• Shear(Plates(
• Timber(Rivets(
• Modern(Joinery(
• Modern/innova?ve(Heavy(Timber(
Connec?ons(
Heavy)Timber)Standard)Prescrip.ve)Details)
IBC)sec.on)2304.10PHeavy)Timber)Split)rings)
WCD5)
Exposed)Steel)Plate/Bolted)Connec.ons)
Solid)sawn)members))w/)bolted)steel)plate))members)connec.ons))• Avoid)cross)grain)shrinkage)))))))))by)using)sloued)holes))• Provide)drainage)holes)in)))))))))bucket)type)connec.ons)(
Steel)Plate)Connec.ons)
• Use)the)steel)plates)as))))))))bolt)hole)templates)
• Shop)layout)of)en.re)assembly))
Split)RingsPWood)to)Wood)Connec.ons)
• Act)as)large)diameter)bolts)(bearing)area))• Split)in)ring)allows)for)shrinkage)• NotePmalleable)iron)washer)for)bolt)to)wood)connec.on))
Shear)PlatesPSteel)to)Wood)Connec.ons)
• Act)as)large)diameter)bolts)(bearing)area))• Commonly)used)in)steel)plated)gluePlam)trusses)
Timber)Rivets)
• Oval)shaped)nails)with)narrow)side)parallel)to)grain)• Allows))closer)spacing)of)rivetsPreduces)splivng)
Modern)Joinery)
• Computer)program)downloads)cuts)to)saw)• Allows))precision)joints)
Joinery)
• CraQsmanship)provides)the)true))))))))beauty)of)Timber)frame)structures)
• Some)joints)s.ll)require)handcraQing)
JoineryPTypical)Tradi.onal)Examples)
HALFPLAP)DOVETAIL)COLLAR)TIE( COMMON)RAFTERS)AT)RIDGE(
Modern)Heavy)Timber)Connec.ons)
S-958
Connections: • Easy to design • Aesthetically attractive • Good serviceability (e.g.,
shrinkage, ductility, etc.) • Cost-effective & availability • Fire resistant (as required) (
Compe..veness)of)a).mber)structure)may)be)determined)by)the)efficiency)of)the)connec.ons)used.))
Use)of)CNC)Technology)for)Connec.ons)
• Computer)Numerically)Controlled)(CNC))connec.ons))
• Ability)to)fabricate)joints)with)precision)
Innova.ve/Proprietary)Connec.on)Systems))
• Grid)plates)
• Embedded)kerf)plates)• Embedded)end)
connec.ons)
• Long)selfPtapping)screws))
Innova.ve!Lag!Screw!Bolt!(LSB)!Connec.on!System!Developed in 1994 & has been modified in various forms�
Source: Komatsu/Japan
hcp://www.ewpa.com/Archive/2004/jun/Paper_083.pdf((O(theory)(
hcp://www.?mberdesign.org.nz/files/00155%20Makoto%20Nakatani.pdfO((tes?ng)((
LagScrewBolt!(LSB)!System!
By inserting LSBs from both surfaces of a post, a two way semi-rigid connection can be achieved�
(d=8�12mm)fire protec ting c over
slit t= 11mm
beam
(d= 8�12mm)
(d= 8�12mm)
drift8 pins
beam
c olum n
beam
steel plate
lagscrew bolt
drift8 pins
drift8 pins
Source: Komatsu/Japan
• LSB)extend)full)width)and)depth)of)column)• Short)end)bolts)allow)for)installa.on)in).ght)
places)• ShaQ)provides)bearing)capacity)of)a)bolt)• Threads)provide)pullPout)capacity)of)a)screw)))
Alterna.ve)System)for)Large)Scale)Timber)Construc.on �)
Source: Komatsu/Japan
• LSB)can)create)semiPrigid)connec.onsPsimilar)to)a)moment)frame)
• Easy)to)install)onPsite)
LagScrewBolt)(LSB))System)
Source: Komatsu/Japan
• SemiPrigid)connec.ons)can)also)be)achieved)at)the)column)base)
• LSB)allow)installa.on)of)bolts)in).ght)spaces)
Innova.ve)Connec.on)Systems))
Shear((
transfer((
strip( Hybrid system- composite wood and concrete slabs �
Shear((
transfer((
strip(
Outline)
• Heavy(Timber(Code(Requirements(
• Design(Elements(
• Unique(Design(Solu?ons(• Case(Studies(• Technical(Resources((
Outline)
• Heavy(Timber(Code(Requirements(
• Design(Elements(
• Unique)Design)Solu.ons)• Wood(Podiums(
• Gas(Sta?ons(
• Historic(Restora?on/Seismic(Retrofits(
• Heavy(Timber(Braced(Frames(
• Post(Frame(Construc?on(
• CLTOMass(Timber(
• Case(Studies(
• Technical(Resources(
Horizontal)Separa.on)
• Horizontal)Wood)Assemblies)are)effec.vely)used)to)transi.on)from)Residen.al)units)above)to)Retail/Parking)below)
Parking)Beneath)Group)R)–)IBC)510.4)
Possibility(of(a(Type(IV(podium(where(number(
of(stories(starts(above(parking(when:(
• Occupancy(above(is(R(and(below(is(SO2(
• Lower(floor(is(open(Type(IV(parking(
with(grade(entrance(
• Horizontal(assembly(between(1st(and(
2nd(floor(shall(be(
" Type(IV(
" Have(1(hr(fire(resistance(ra?ng(
when(sprinklered(
" Have(2(hr(fire(resistance(ra?ng(
when(not(sprinklered(
• Overall(height(is(s?ll(limited(to(
occupancy(
(
5)story)Type)III)Building)On)Top)of)a)Type)IV)
Type
!IV!
2Hr!
Case)Study:)Horizontal)Separa.on)
Galt)Place)Apartments)Loca?on:(Galt,(CA(
Mixed(Use(Residen?al(over(
Retail(and(Parking(
Architect:(Applied(Architecture(
Outline)
• Heavy(Timber(Code(Requirements(
• Design(Elements(
• Unique(Design(Solu?ons(
• Unique)Design)Solu.ons)• Wood(Podiums(
• Gas(Sta?ons(
• Historic(Restora?on/Seismic(Retrofits(
• Heavy(Timber(Braced(Frames(
• Post(Frame(Construc?on(
• CLTOMass(Timber(
• Case(Studies(
• Technical(Resources(
Canopies(O(Shall(be(of(noncombus?ble(materials:((
• FireOretardantOtreated(wood(((
• Wood(of(Type(IV(sizes(((
• or,(construc?on(providing(1Ohour(fire(resistance.(
((
Combus?ble(materials(used(in(or(on(a(canopy(shall(be:((
• Shielded(from(the(pumps(by(a(noncombus?ble(element(of(
the(canopy((
• or,(wood(of(Type(IV(sizes((
Gas)Sta.on)Canopies)–)IBC)406.7.2)
Gas)Sta.ons)
• Shielded)condi.on)
• Heavy).mber)condi.on)
Outline)
• Heavy(Timber(Code(Requirements(
• Design(Elements(
• Unique(Design(Solu?ons(
• Unique)Design)Solu.ons)• Wood(Podiums(
• Gas(Sta?ons(
• Historic(Restora?on/Seismic(Retrofits(
• Heavy(Timber(Braced(Frames(
• Post(Frame(Construc?on(
• CLTOMass(Timber(
• Case(Studies(
• Technical(Resources(
))
Hard Spot, no tie
URM overhangs
Unreinforced parapets and projections
Seismic)Retrofit)of)Unreinforced)Masonry)Buildings)(URM))
Jacksonville Tavern, Jacksonville, Oregon
• Tall,)slender)unreinforced)piers)• Weak)lime)mortar)• Con.nuous)block)long)building)sec.ons)• Heavy).mber)is)oQen)used)to)seismically)
retrofit)these)buildings)for)lateral)forces)and)for)outPofPplane)wall)forces)
Lateral))Instability)
Hard spot
Low roof
Open)Front)Eleva.on)
Modeled with steel moment frame
Outline)
• Heavy(Timber(Code(Requirements(
• Design(Elements(
• Unique(Design(Solu?ons(
• Unique)Design)Solu.ons)• Wood(Podiums(
• Gas(Sta?ons(
• Historic(Restora?on/Seismic(Retrofits(
• Heavy(Timber(Braced(Frames(
• Post(Frame(Construc?on(
• CLTOMass(Timber(
• Case(Studies(
• Technical(Resources(
Heavy)Timber)Braced)Frames)(HTBF))
Heavy(?mber(braced(frames(are(becoming(a(
preferred(alterna?ve(ver?cal/lateral(resis?ng(
system(due(to(cost,(performance(and(
aesthe?cs.(
" R=3,)Ie=1.25)for)this)project)" OverPstrength,)system=2.0,)braces=2.5)" Overall)effect)))))))))))R=1)(remains)elas.c,)no)duc.lity)))
Simpson)Strong)Tie)Materials)Demo)Lab)–)1st)approved)HTBF)approved)under)2007)CBC)and)ASCE)7P05)
" SEAOC(2010(Conven?on(paper:((
hcp://www.arce.calpoly.edu/newsO
events/documents/heavyO?mberObracedO
frames.pdf((
" Structure(Magazine(Ar?cle:(
hcp://www.structuremag.org/
ar?cle.aspx?ar?cleID=1221((
" 5000)sf.)facility)u.lizing)HT)braced)frames)as)the)primary)LFRS)
Outline)
• Heavy(Timber(Code(Requirements(
• Design(Elements(
• Unique(Design(Solu?ons(
• Unique)Design)Solu.ons)• Wood(Podiums(
• Gas(Sta?ons(
• Historic(Restora?on/Seismic(Retrofits(
• Heavy(Timber(Braced(Frames(
• Post(Frame(Construc?on(
• CLTOMass(Timber(
• Case(Studies(
• Technical(Resources(
Post)Frame)Construc.on)
Features)" Wood(side(wall(posts(
" Pitched(Trusses(" Wide(bay(spacing((8o(to(12o(+)(
" Large(clear(spans((100(o(+)(" Embedded(wood(posts(or(concrete(piers(
" Walls,(roof(usually(type(V(construc?on(
" Previously)used)in)agricultural)buildings)
" Adapted)and)commonly)used)in)commercial)structures)
Concept)of)Post)Framing)
" Common)bearing)condi.ons)
• 2x(purlins(and(girts((at(
((((((16”(o.c.(to(24”(o.c.((
• Single(or(double(
trussesODepending(on(
span(
• Asphalt(and(polyethylene(wrap(• PouredOinOplace(concrete(pier(• BlowOmolded(plas?c(
• PreOcast(reinforce(concrete(columns(
• HDPE(plas?c(barrier(• Polyethylene(post(sleeve(More)informa.on:)
www.posxrameadvantage.com)
(
Innova.ve)Founda.on)
Structural)features)of)HT)Construc.on)Large)openings/Tall)walls)Large)roof)overhangs)
Posts)allow)nonPstructural)infill)
Outline)
• Heavy(Timber(Code(Requirements(
• Design(Elements(
• Unique(Design(Solu?ons(
• Unique)Design)Solu.ons)• Wood(Podiums(
• Gas(Sta?ons(
• Historic(Restora?on/Seismic(Retrofits(
• Heavy(Timber(Braced(Frames(
• Post(Frame(Construc?on(
• CLTOMass(Timber(
• Case(Studies(
• Technical(Resources(
CLT)is)part)of)a)new)class)of)product…)“Mass”ive)Timber)
• CLT,(LVL,(LSL(and(glulam(beams(
• Plate(elements(of(mass(?mber(
O(less(surface(area(to(volume(
ra?o(
• Improved(fire(performance(
characteris?cs(
• Efficient(u?liza?on(of(smaller(
diameter(trees(
• Mass(Timber(elements(can(be(
used(for(both(ver?cal(and(
lateral((resis?ng(system(
The(Brief(Open(Academy,(Norfolk(England((
Design(Team:(Sheppard(Robson,(Romboll(uK(
Photo(credit:(KLH(
(
What)is)Cross)Laminated)Timber)(CLT)?))
Photos(provided(by(FPInnova?ons(
4(1/8”(to(19(1/2”(
10’X40’(
8’X64’(
• 3(layers(min.(of(solid(
sawn(lams(
• 90(deg.(crossOlams(
• Similar(to(pw.(sht’g.(
Minor Axis
MassP”Timber”PForte’,)Melbourne,)Australia))
Architect:(Lendlease(
Photo(credit:(Lendlease(
(
• Tallest(modern(?mber(building(
(((((((O(10(stories(total(
• 9(stories(of(CLT(over(1(story(
concrete(podium(
• Prefabricated(CLT(panels(
• All(CLT(loadObearing(walls,(floor(
slabs,(and(elevator(and(stair(
shaos((
MassP”Timber”PTreet,)Bergen,)Norway))
Architect:(Arco(
Engineer:(Sweco(
(
• Currently(under(
construc?on(
• Once(complete(will(be(
tallest(modern(?mber(
building(
(((((((O(14(stories(total,(173(
(feet(tall(
• Scheduled(comple?on(
Autumn(2015(
• Unique(glulam(and(CLT(
module(construc?on(
(
Structural)Flexibility)
• Large(clear(spans(
• Curved(shapes(
• Solid(CLT(shaos(
• Wood(podiums(
• Can?lever(stairsOno(posts(
• Long(can?lever(roof(
overhangs(
Office)Buildings)using)CLT)Construc.on)
• Short)construc.on).me)• Similar)to)concrete).ltPup)buildings)
Case)StudyPCLT)Milestone)in)Montana)
The)Long)Hall)• First(CLT(project(in(the(US,(using(a(US(
CLT(supplier.((
• Type(VB–CLT(walls(and(floor,(glueOlam(
roof(beams(and(decking(
• 2(stories,(mixed(use(
• 5(days(to(erect,(3(months(from(
founda?on(to(occupancy(
• Cost(effec?venessO(short(construc?on(
?me(and(keeping(CLT(panels(as(
interior(finish(
Designer:(Datum(Design(Draoing(
Engineer:(CLT(Solu?ons(
Photo:(gravityshots.com(
Loca?on:(Whitefish,(MT(
Solid)Timber)ShaQ)Walls)
• Eliminates(using(concrete(or(masonry((
• Short(construc?on(?me(
• Saves(money(
Enhancing)Structural)Flexibility)with)CLT)
Concrete(cores(to(resist(
lateral(loads(
Glulam(post((
&(beams(
6-storey glulam post-and-beam structure with reinforced concrete cores (CSN FondAction)
Heavy)Timber)Frame)MidPrise))Building,)Quebec)City))• Posts(and(beams(support(gravity(loads(
• Concrete(cores(resist(lateral(loads(((
CLT)shaQs)could)be)subs.tuted)for)the)concrete)cores)(
CLT)floor)and)roof)panels)could)be)used)as)solid)rigid)diaphragm)elements)
Is)CLT)recognized)by)the)building)Code?)
Addi.onal)detailed)informa.on)is)available)at)www.woodworks.org))
Sec?on(602.4OHeavy(Timber((
and(sec?on(2303.1.4.(
2015(IBC?(YES!(
Fire)Performance)• ASTM E119 Fire Endurance
Test • 5-Ply CLT (6-7/8” thick) • 5/8” Type X GWB each side • 2 hour target • Actual 3 hours 6 minutes
• 2015 NDS Chapter 16 includes char rates for CLT to achieve up to 2 hour fire rating
Product)Standardiza.on)
US)CLT)Handbook)
1. Introduc?on(2. Manufacturing(
3. Structural(4. Lateral(5. Connec?ons(6. DOL(and(Creep(7. Vibra?on(8. Fire(9. Sound((
10. Enclosure(11. Environmental(
12. Lioing(
www.mass?mber.com(
Outline)
• Heavy(Timber(Code(Requirements(
• Design(Elements(
• Unique(Design(Solu?ons(• Case(Studies(• Technical(Resources(
Outline)–)Case)Studies)
• Commercial,(Offices(
• Airports(• HealthCare(• Schools(• Apartments/Lodges(
• Churches(• Performing(Arts(Centers(
• Aqua?c(Centers/Arenas(
Case)Study:)Greenest)Building)in)the)World)
Bulliu)Center))• Loca?on:(Seacle,(WA.(
• Type(IV(construc?on(
• 4(stories(of(wood(over(a(
(((((((2(story(concrete(podium(
• Net(Zero(Building(
• Construc?on(cost($360/sf.(
• GoalO(250(year(life(expectancy(
Architect:(Miller(Hull(Partnership(
Photo(Credit:((Miller(Hull(Partnership(
Case)Study:)1st)US)Commercial)Bldg.)“w/)NA)CLT”)
Promega)GMP)FacilityOclient(&(staff(recep?on(area)• Loca?on:(Madison,(WI.(
• Type(IV(construc?on(
• 2(stories(of(heavy(?mber(and(CLT(
• 52,000(sf.(addi?on(
(Architect:(Uihlein(Wilson(Architects(
(
Case)Study:)Heavy)Timber)Office)Building)
Radiator)Building)• Portland,(OR(
• 5(stories(
• 36,000(sf(
• Completed(2015(
Photo(Credit:(Josh(Partee(
Case)Study:)Wood)Innova.on)Design)Center)
Wood)Innova.on)Design)Center)• Loca?on:(Prince(George,(BC(
• Glulam,(LVL,(and(CLT(structure((
• 8(stories,(97(feet(tall(
(Architect:(Michael(Green(Architecture(
(
Winery)Fermenta.on)Barn)
Nickel)&)Nickel)Winery)• Loca?on:(Oakville,(CA(
• U?lizes(tradi?onal(post(and(beam(
joinery(
Design(Team:(Taylor(Lombardo(Architects(LLP,(JVA(
Incorporated(
Photo(Credit:(Adrian(GregoruÇ(
Airports)
Jackson)Hole)Airport)• Loca?on:(Jackson(Hole,(WY(
• LEED(Silver(
• Completed(2010(
Design(Team:(Gensler,(Mar?n,(Mar?n(
Photo(Credit:(Machew(Millman,(Tim(Griffith(
(
Case)Study:)Portland)Interna.onal)Jetport)
Portland)Interna.onal)Jetport)• Loca?on:(Portland,(ME(
• LEED(Gold(
• Completed(2012(
Design(Team:(Gensler,(Oest(Associates(
Photo(Credit:(DeStafano(&(Chamberlain,(Inc,(Robert(Benson(Photography(
Airport:)Hybrid)Glulam)Trusses)
Raleigh)Durham)Interna.onal)Terminal)2)• Loca?on:(Morrisville,(NC(
• Hybrid(Glulam(Trusses(up(to(136(o(spans(
• Completed(2010(
Design(Team:(Fentress(Architects,(ARUP(
Photo(Credit:(Structurlam(Products(
Healthcare)
Willson)Hospice)House)Loca?on:(Albany,(GA(
• LEED(Silver(
• Completed(2010(
Design(Team:(Perkins+Will,(Uzun(&(Case(
Photo(Credit:(Jim(Roof(Crea?ve(Photography(
Case)StudyPHerrington)Recovery)Center)
Photo:(Tom(Davenport(
Architect:(TWP(Architecture(
Photo:(Cur?s(Waltzrington(
(
• 3(story,(21,000(sf.(
• Exposed(gluOlam(beams(and(decking(
• Wood(selected(for(its(warmth,(and(healing(effects(
Loca.on:)Okonomowoc,)WI)
Heavy(Timber(as(defined(in(
Sec?on(602(of(the(IBC(may(be(
used.(
Example(Project;(
• Fayeceville,(NC(• Type(V(w/firewall(• 110,000sf(• Heavy(Timber(Roof(System(
Schools)
Case)Study:)CLT)Framed)School)
Franklin)Elementary)School)• Loca?on:(Franklin,(WV(
• 2(storiesO(45,200(sf.(((
• Structure(erected(in(less(than(3(
months(
• 1st(CLT(School(in(US(
• Completed(2015(
Architect:(MSES(Architects(
Case)Study:)Natural)School)Sevng)Indian)Mountain)Student)Arts)&)Innova.on)Center)• Loca?on:(Lakeville,(CT(
• Exposed(wood(chosen(for(warmth(and(to(reflect(school’s(natural(
seÇng(
• Glulam(beams(&(columns,(salvaged(wood(flooring(
Design(Team:(Flansburgh(Architects,(
Roome(&(Guarracino(
Photo(Credit:(Robert(Benson(
Photography(
Case)Study:)Earth)Sciences)Building)
Earth)Sciences)Building,)University)of)Bri.sh)Columbia)• Loca?on:(Vancouver,(BC(
• 5(storiesO(158,770(sf.(((
• Exposed(CLT(roof(panel(and(glulam(
column(exterior(canopy(
• Wood(chevron(braces(are(lateral(frame((
Architect:(Perkins(+(Will(
Photos:(www.naturallywood.com(
Duke)Lower)&)Middle)School)• Loca?on:(Durham,(NC.(
• Type(VB(
• 1(story(–(79,204(sf.((
• 5(new(wood(buildings,(4(exis?ng(
Case)Study:)Posi.ve)Learning)Environment))
Architect:(DTW(Architects(
• GlueOlam(columns,(girders,(and(arches((
• exposed(T&G(decking((
• Reason(for(using(exposed(wood(framing(
" (aesthe?cs((
" How(the(warmth(and(beauty(of(wood(
could(influence(the(students.((
Burr)&)Burton)Academy)–)Mountain)Campus)• Loca?on:(Peru,(VT(
• 1(story(–(4,000(sf.((
• LEED(Pla?num((83(points)(
• Net(Zero(
• Has(won(3(Sustainable(Design(
Awards(
Case)Study:)Integra.ng)Nature)with)Mass)Timber))
Architect:(Bensonwood(
Albert)Lea)High)School)• Loca?on:(Albert(Lea,(MN(
• Type(IV(roof(system(in(type(II(building(
• 2(storiesO(270,000(sf.((
• Wood(provided(the(warmth(and(
beauty(desired((
Case)Study:)Learning)With)Natural)Wood)
Photo(courtesy(of(APAOThe(Engineered(Wood(Associa?on(
• Architect:(DLR(Group(
El)Dorado)High)School)Gym)• Loca?on:(El(Dorado,(AR(
• Type(IV(heavy(?mber(trussesO165’(span(
• Using(barrel(roof(and(pw(sheathing(as(
opposed(to(flat(roof(with(parapets(and(
decking(saved($60,000(
.((
Case)Study:)Cost)savings)and)Aesthe.cs)
Photos(courtesy(of(APAOThe(Engineered(Wood(Associa?on(
Architect:(CADM(Architects(
Mul.PFamily)Housing)
1201)Mercer/Rivet)• Loca?on:(Seacle,(WA(
• Completed(2014(
• 145,000(sf(
• 5(Stories(Type(VA(over(2(story(
podium,(some(exposed(HT(
Design(Team:(Ankrom(Moisan(
Architects,(YT(Engineers((
Photo(Credit:(Casey(Braunger,(CBPhoto(
(exterior);(Conor(Musgrave((interior)(
Lodging)
The)Cedar)House)Sport)Hotel)• Loca?on:(Truckee,(CA(
• U?lized(local(cedar,(exposed(PSL(
Design(Team:(Ken(Meffan(Architect,(
Baird(Structural(Design(Inc.(
Photo(Credit:(Donna(Reid(
Case)Study:)Bridport)House,)London,)UK))
Architect(and(photo(credit:(
Karakusevic(Carson(Architects(
(
• Two(blocks:(5(and(8(stories,(41(
apartments(total(
• All(CLT(loadObearing(walls,(floor(
slabs,(and(elevator(and(stair(
shaos((
• Light(weight(CLT(structure(
accommodated(exis?ng(storm(
sewer(under(site(
• CLT(construc?on(?me(was(12(
weeks:(50%(faster(than(with(
other(materials(
• Carbon(benefit:(each(apartment(
stores(more(than(30(tons(of(CO2(
• Heavy(?mber(is(a(common(theme(in(churches(and(religious(centers(
• Provides(warmth(and(beauty(and(a(harmony(with(nature(
Churches)
Hinsdale)United)Methodist)Church,)Hinsdale,)IL)Design(Teram:(Saavedra(Gehlhausen(Architects,(Hanson(Professional(Consultants(
Photo(Credit:(McShaneOFleming(Studios(
Churches)
Architect:(CDH(Partners,(Inc.(
Engineer:(KSI(Structural(Engineers(
Christ)the)King)Catholic)Church)PHamilton,)GA)
• Heavy(?mber(trusses(and(wood(decking(
• Spire(created(unique(skylight(effect(
Churches)
St.)Martha)Catholic)Church)–)Porter,)TX)Design(Team(:(Turner(Duran(Architects,(Pinnacle(
Structural(Engineers(
Photo(Credit:(G.(Lyon(Photography,(Inc.((
)
• 45,000(sf(
• Glulam(trusses(&(columns,(T&G(decking(
Case)Study)–)Oakland)Cathedral)
Design(Team:((Skidmore(Owings(&(Merrill,(Craig(W.(Harman,(Webcore(Buildiers(
Photo(Credit:(Timothy(Hursley,(Cesar(Rubio,(and(John(Blaustein(
Cathedral)of)Christ)the)Light)–Oakland,)CA) • 108(o(high(DF(Glulam(arches(
Case)Study:)Arena)Stage)at)the)Mead)Center)
Photo:(Nic(Lehoux(
Architect:(Bing(Thom(
Architects(
(
• Loca?on:(Washington,(D.C.(
• Expansion(and(renova?on(of(a(200,000(sf.(theater((
((((((((complex(((
• PSL(?mber(columns(suppor?ng(roof(and(glass(facade(
• Column(capacity(is(400(kips(
(
.((
Aspen)Art)Museum)
Aspen)Art)Museum))• Loca?on:(Aspen,(CO(
• Completed(2014(
• Exterior(woven(wood(screen,(interior(HT(trusses(
Design(Team:(Shigeru(Ban(Architects,(Turner(Construc?on(
Photo(Credit:(Michael(Moran,(Derek(Skalko(
(
Biomass)Facility)Biomass)Hea.ng)Plant,)Hotchkiss)School)Loca?on:(Lakeville,(CT(
• Completed(2012(
• LEED(Gold(Cer?fied(
Design(Team:(Centerbrook(Architects(and(Planners,(
DeStafano(&(Chamberlain,(Inc.(
Photo(Credit:(David(Sundberg/Esto(
Aqua.c)Centers)
• 66,500(sf.(aqua?c(center(
• (10(½”x41(½”(glueOlams(spanning(130(o.,(
spaced(at(12’(oc.(
• 2(½”(T&G(decking(overlaid(w/(pw(sheathing(
• 130(o.(span,(the(glulam(columns(and(beams(
had(to(be(assembled(onOsite.(
.((
Aqua.c)Centers)
• Curved(glulam(beams(
and(wishbone(columns(
provide(ver?cal(and(
lateral(support(
• $7.5(Million(total(cost(
West)Vancouver)Aqua.c)Centre)Design(Team:(Hughes(Condon(Marler(
Architects,(Fast(and(Epp(Engineers(
Photo(Credit:(Nic(Leboux,(Gary(Oce,(
Mar?n(Tessler(
(
Buffalo)HarborCenter)Rink)1)
Buffalo)HarborCenter,)Rink)1)• Loca?on:(Buffalo,(NY(
• 140(o(span(Hybrid(Glulam(Truss(
• Completed(2014(
• 2(rinks(part(of(a($163M(project(
Photo(Credit:(harborcenter.com(
Anaheim)Ice)Arena)))
116’)Span)Glulam)Arches)
Arch)splice))connec.on)
Architect:(Frank(Gehry(
Photo(Credit:(Western(Wood(Structures(
University)Laval)Soccer)Stadium,)Quebec)City))
Typical)concealed)hinge))(pinned))connec.ons))
Richmond)Olympic)Oval,)Richmond,)B.C.)
• Mul?Opurpose(arena(with(500,000(sf.(floor(area(
• 330’(clear(span(arches(w/(2(way(curvature(roof(
covering(6(acres(
• Proprietary(Woodwave(panel(roof(system(
spanned(between(the(composite(glueOlam(
arches(
Credit:(naturallywood.com((
Design(team:(CannonDesign(
Owner:(City(of(Richmond(
Outline)
• Heavy(Timber(Code(Requirements(
• Design(Elements(
• Unique(Design(Solu?ons(• Project(Examples(
• Technical(Resources((
WoodWorks(–(Resources(for(You((
Technical)Assistance)[email protected]))
• Code(issuesOH/A,(fire(protec?on(
• Design(assistance(
• Wood(design,(use,(and(proper?es(
• Product(informa?on(
Case)Studies)
Wood)Solu.ons)Fairs)Educa.on)and)Design)Tools)• OnPline)webinars)• Design)guides)and)standards)• Design)soQware)• CAD)&)REVIT)details)• OnPline)calculators)• Span)Tables)
…and(more(at(woodworks.org(((
• American)Wood)Council)P)www.awc.org)
• www..mberframeengineeringcouncil.org/)
• Timber)Framers)GuildP)www.xguild.org/)
• Timber)Frame)Business)CouncilP)))))))))www..mberframe.org)
Other(Resources((
• APAPEngineered)Wood)Associa.onP)www.apawood.org)
For)more)informa.on)
www.mass0mber.com!
Ques.ons?)
This(concludes(The(
American(Ins?tute(of(
Architects(Con?nuing(
Educa?on(Systems(
Course(
Speaker)Name)Speaker(organiza?on(
Speaker(email(address(
This(presenta?on(is(protected(by(US((
and(Interna?onal(Copyright(laws.((
Reproduc?on,(distribu?on,(display(and(use(of((
the(presenta?on(without(wricen(permission((
of(the(speaker(is(prohibited.(
(
©(The(Wood(Products(Council(2015(
Copyright)Materials)