external financing an energy efficiency project is easier
TRANSCRIPT
Strategic Energy Management For Resilience
External financing an Energy Efficiency Project is easier than ever!
A case study: Panasonic and SDCL
Prepared for National Energy Efficiency Conference 2015
By: Peter Lau and Mohamed Shahril Bin Hj Jaffar
6 October 2015
2
Part 1:
• Sustainable Development Capital (Asia) Limited (“SDCL”) by Peter Lau,Director of SDCL
• Introduction of the Programme
• Investment Criteria
• Investment Process
• SDCL’s Value Added to the Project
Part 2:
• Panasonic Appliances Refrigeration Devices Singapore (“PAPRDSG”) byMohamed Shahril Bin Hj Jaffar, Manager of PAPRDSG
• Introduction of PAPRDSG and the ECO ideas factory
• Current Challenges
• Solutions
• Project Timeline
• Benefits of SDCL’s External Financing Programme
Agenda
4
“Given Singapore’s limited access torenewable energy, energy efficiency isour core strategy to reduce emissions.”
https://www.nccs.gov.sg/nccs-2012/singapores-approach-to-reducing-emissions.html
6
SDCL’s Energy Efficiency Programme Worldwide
Singapore Energy Efficiency Investments Group Limited
Up to SGD $200 millioncollaboration with
Economic Development Board
Manager
First close March 2014
UK Ireland Singapore
Investment Focus
Public Sector BuildingsFood and AgricultureHotels and Data-centresStreet Lighting
Investment Focus
Buildings RetrofitCombined Heat & PowerRenewable HeatUrban Infrastructure
Investment Focus
Manufacturing SectorHeat RecoveryLightingIndustrial Efficiency
UK Energy Efficiency Investments Fund
GBP £104 million£50 million committed from UK Green Investment Bank
Manager
Closed 2014
Ireland Energy Efficiency Investments PLC
Euro €70 million€35 million committed from
Irish Government
Manager
First close May 2014
7
SDCL’s Energy Efficiency Programme in Singaporewww.e2singapore.gov.sg/Incentives/Finance_Programme_for_Energy_Efficiency_Projects.aspx
• Selected by EDB to establish a finance led pilot programme;
• The program (up to S$200 million) is to finance the transformation ofIndustrial/Manufacturing facilities;
• Provide for up to 100% of upfront capital investment to finance theproject;
• Establish a professional team in Singapore to work with EDB toimplement, manage and finance projects;
• Aim to structure financing to achieve off balance sheet treatment underinternational accounting standards;
• Generate significant positive environmental and social impact.
8
Investment Criteria of the Programme
Guideline Note
StructureFinance up to 100% of
project costs
• Equipment• Labour and Installation• Annual operating cost (if required)• Regular measurement and verification
costs (if required)• All three levels of Energy Assessment
cost (if required)
Project Investment Size SGD 1 – 40 million Project with lower project size is considered on a case by case basis
Payback period Up to 5 years This can be a blended average of the proposed interventions
Typical contract term Up to 10 years This can be customised to the extent supported by the project economics
10
Value Added from SDCL’s Involvement in the Project*
• Best lifecycle costs rather than the lowest project cost (i.e. shortestpayback);
• SDCL’s network in the Industry (ESCOs, Technology Partners, Developersetc.);
• Project management assistance;
• A clear measurement and verification process;
• Economic life left in the equipment (i.e. client enjoys the free use of theequipment after contract expires);
• Risk Transfer.
*Based on a typical project or requested by the Host
11
Selected Projects in Singapore
Country Client Project Size (up to, local currency)
Interventions Status
Singapore Manufacturing SGD 3.3m Chiller System Closed
Singapore Manufacturing SGD 1m Air Compressors Closed
Singapore Manufacturing SGD 0.1m Air Compressors Closed
Singapore Semi-Conductor SGD 1.0m Heat Pumps Documentation
Singapore Manufacturing SGD 0.2m LED Lighting Documentation
Singapore Waste Management SGD 1.3m Heat Recovery MOU signed
Singapore Manufacturing SGD 2.2m Heat Recovery MOU signed
*As at 30 Sep 2015
13
Part 1:
• Sustainable Development Capital (Asia) Limited (“SDCL”) by Peter Lau,Director of SDCL
• Introduction of the Programme
• Investment Criteria
• Investment Process
• SDCL’s Value Added to the Project
Part 2:
• Panasonic Appliances Refrigeration Devices Singapore (“PAPRDSG”) byMohamed Shahril Bin Hj Jaffar, Manager of PAPRDSG
• Introduction of PAPRDSG and the ECO ideas factory
• Current Challenges
• Solutions
• Project Timeline
• Benefits of SDCL’s External Financing Programme
Agenda
Introduction of Panasonic Appliances Refrigeration Devices Singapore (“PAPRDSG”)
• Manufacturing of Refrigeration Compressor
Application of our product
• Casting Parts • Metal Stamping
Panasonic’s 1st ECO Ideas Factory Outside Japan
Implement high efficient lighting
LED High Bay LED Tubes
Implement high efficiency air compressor
Centrifugal type Inverter type
Change to high efficiency air dryers
Convert to High Efficiency Dryer Use VSD to regulate Cooling Tower & Water Pumps
Implement VSD for pumps & cooling towers
15
16
Meter Gauges for Air Compressors Operation Monitoring
SE-Navi Data
750 kwh/day
1400 kwh/day
Reduce unloading loss > 650 kwh/day
reduction is achieved
Mar-Apr 14
Implement BioOil for Boiler
Diesel supply
during change
over
BioOil supply to
Boiler for steam
generation
Elimination of Water pump & Cooling tower
Convert water
cool package
air con to air
cool condenser.
Water pump
and cooling
tower removed.
17
Current Challenges of ECO Programme
Other Investment Priorities
Run Out of Ideas
Project Justification
High Investment
No Plan Budget
Return of Investment Too Long
Source for Collaboration Partners
Identification of the Project
Energy Mapping
Finding Conclusion:
1) Under capacity
2) Aged compressor
3) Efficiency unknown
28% of the total electricity usage
19
Overview of the Compressed Air System
1
2
3
5
4
Base line setting:
1) 16 Units of Air Compressor
2) Size range from 55kW to
330kW
3) Age between 1 to 24 years
4) All compressors are
connected to same main
pipelines linked in a closed
loop system
5) M&V were done to measure all
air compressor :-
a) Power (kW)
b) Air flow (m3/h)
c) Pressure ( bar )
20
Measurement and Verification (M&V)
Power Meter
Air Flow Meter
Pressure Meter
Data logger
Existing efficiency : 0.119 kW / (m3/hr)
(Base line )
21
Proposed Replacement Project
Power Air Flow
(kW) (m3/h)
3 F 1 Compressor 1 58 562
8 F 3 Compressor 2 72 729
9 F 3 Compressor 3 63 562
13 F 4 Compressor 4 90 427
7 F 3 Compressor 5 195 1983
14 F 5 Compressor 6 158 1300
15 F 5 Compressor 7 133 896
16 F 5 Compressor 8
769 6459
Efficiency of Selected Air Compressors0.119
COP (Existing System)
Total Capacity of Selected Air Compressors
Breakdown
Existing Air Compressors Selected for Replacement
Comp
No.Location Make
Operation Data
Power Air Flow
(kW) (m3/h)
F3 New Compressor 3 180.4 2010
F5 New Compressor 4 176.3 1645
F5 New Compressor 5 180.4 2010
F5 New Compressor 6 180.4 2010
1078.3 11695
Efficiency of Proposed Air Compressors0.092
COP (Proposed System)
F2 New Compressor 2 180.4 2010
Total Capacity of Proposed Air Compressors
Design Operating Data
F2 New Compressor 1 180.4 2010
Proposal of High Efficeincy Air Compressor at Selected Location
Location Make
Achieved 22.6% improvement in COP
8 Units of Air Compressor with COP of 0.119 kW/(m3/h)
Replace with 6 Units of New Air Compressor with COP of
0.092 kW/(m3/h)
22
Pictures of Air Compressor Scrapped
Air Compressor : No 16 Scrapped
Air Compressor : No 7 Scrapped
23
Pictures of Selected New Air Compressor
New Air Compressor : No 2 Installed on 28 July 15
New Air Compressor : No 4 Installed on 20 Aug 15
Waiting for the next 4 units
24
Key Milestones of the Project
2014• May - Signed term sheet 1 with SDCL• May - Energy audit started
• Aug / Sep - Drafted audit report available• Oct to Nov - Due diligence on suppliers• Nov to Dec - Finalised commercial terms with SDCL• Dec – Signed term sheet 2 with SDCL
2015• Jan to Mar – Contract discussion and negotiation• Mar – Contract signed• Apr to Dec – Procurement and construction
2016• Jan - Expected commission date
25
Benefits of SDCL’s Programme to PAPRDSG
• SDCL provided 100% capital including the audit costs and M&Vcosts;
• SDCL assisted PAPRDSG throughout the project including:• Introduced and assisted in selection of technology partners
for energy audit• Undertook due diligence for each equipment supplier• Assisted in selection of equipment supplier• Provided a number of funding options• Facilitated and arranged to meet with EDB officers
• Contractual documentation was executed efficiently;
• Ownership of the compressors after contract expires;
• The process was transparent to PAPRDSG.
26
Peter Lau,
Director of SDCL
Tel: +65 8232 2753
Mohamed Shahril Bin Hj Jaffar
Manager of PAPRDSG
Tel: +65 6577 0763
Key
Contacts:
http://www.e2singapore.gov.sg/Incentives/Finance_Programme_for_Energy_Efficiency_Projects.aspx