f5 progref5_progress_test_answer_question_4ss test answer question 4

Upload: yasir-shahzad

Post on 07-Jul-2018

212 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/19/2019 F5 ProgreF5_Progress_Test_Answer_Question_4ss Test Answer Question 4

    1/4

    Question 4 Farmseeds

    Tutorial help and key points

    Part (a) is fairly a simple variance question requiring your basic understanding

    in developing variance formulae, (keeping in mind S for standard and A for

    actual results) and all numbers should work out from the formulae. Then you

    must convert budgeted contribution to actual simply by adding favourable

    variances to budgeted contribution and deducting any adverse ones. Make sure

    you only show fixed overheads expenditure variance under marginal costing

    approach.

    In part (b)  you have to explain the variances calculated in part (a) simply

    relating to the company details, make sure you discuss it briefly as only 6 marks

    are allocated and there will be quite a few variances. So do not run over the

    time scale.

    Marking scheme

    (a)  Budgeted contribution (1 mark)

    Sales price (1 mark)

    Sales volume contribution: (1 mark)

    Price (1 mark)

    Usage (1 mark)

    Rate (1 mark)

    Efficiency (1 mark)

    Idle time variance (1 mark)

    Rate or Expenditure (1 mark)

    Efficiency (1 mark)Actual contribution (1 mark)

    Less: Budgeted fixed costs (1 mark)

    Adjustment of fixed OH expenditure variance (1 mark)

    Actual profit (1 mark)

    (Total 14 marks)

    (b)  Performance measurement 2 marks each for three valid assessments

    discussed/max 6

    (Total 6 marks)

    TOTAL = 20 marks 

  • 8/19/2019 F5 ProgreF5_Progress_Test_Answer_Question_4ss Test Answer Question 4

    2/4

    (a)

    Operating statement

    $Budgeted contribution (8,400 units x $50) 420,000

    Adjustment of sales variances:

    Sales price 120,000 ASales volume contribution: 20,000 A

    Budgeted contribution at actual sales 280,000

    Adjustment of cost variance:

    Direct Materials Variances:

    Price 60,000 FUsage 0

    Direct Labour Variances:

    Rate 18,960 AEfficiency 20,000 F

    Idle time variance 15,600 F

    Variable Overheads variances:

    Rate or Expenditure: 30,000 A

    Efficiency 30,000 FActual contribution 356,640 

    Less: Budgeted fixed costs (210,000)

    Adjustment of fixed OH expenditure variance 10,000 F

    Actual profit 156,640

    Workings: Variances: $ 

    Sales price: Revenues should have been $240 x 8,000 tonnes 1,920,000

    Actual Revenues 1,800,000Variance 120,000 A

    Sales volume contribution:

    (Budget volume – actual volume) x Standard contribution $20,000 A

    Direct Materials Variances:

    Price should have spent $60 x 12,000 tonnes 720,000Actual cost was 660,000

    60,000 F

    Usage should have used 1.5 tonnes x 8,000 t 12,000 t*Actual usage 12,000 t

    0

    x Standard price $60 0 

    Direct Labour Variances:Rate should have cost $18 x 15,800 hours paid 284,400

  • 8/19/2019 F5 ProgreF5_Progress_Test_Answer_Question_4ss Test Answer Question 4

    3/4

    actual paid 303,360$

    18,960 A

    Efficiency should have worked 2 hours x 8,000 tonnes 16,000hrshours

    Have actually worked 15,000hrsVariance x standard rate of $18/0.9 per hour 20,000 F

    Excess Idle time variance Budgeted idle time – actual idle time)

    X standard rate per hour(1,580 – 800) x $20 15,600 F

    Variable Overheads variances:

    Rate or Expenditure : should have incurred 15,000 hrs x $30 450,000Have actually incurred 480,000

    30,000 A

    Efficiency should have worked for 16,000 hrsActually worked for 15,000 hrs

    At standard rate $30 per hour 30,000 F

    Fixed Overheads expenditure variance

    Budgeted fixed overheads 210,000Actual fixed overheads 200,000

    10,000F

    t* stands for tonnes

    (b)

    From the results in part (a) it is apparent that FS has had a poor performance over the

    period and actual profit achieved was only $156,640 as compared with budgeted profit

    figure of $210,000. This can be explained as below considering all the factors involved.

    Sales

    Both sales price and sales volume variances were adverse by $120,000 and $20,000

    respectively, which shows that despite reducing the selling prices, sales demand could not

    be boosted up. It might be due to general economic downfall, or due to product quality

    being poor, or poor marketing. Sales area was the main concern in profits being down from

    the budgeted figures.

    Direct materials

    Price variance is favourable and usage is nil, which reflects a positive performance from the

    purchasing and production side, they controlled the cost by buying from right sources and

    producing within budget parameters of wastage. Overall it improved the profits.

  • 8/19/2019 F5 ProgreF5_Progress_Test_Answer_Question_4ss Test Answer Question 4

    4/4

    Direct Labour

    Labour rate variance shows an adverse result, which is due to the company paying higher

    rate than expected, and right results were achieved in efficiency and cutting down idle time.

    Overall it improved the profits.

    Variable overheadsOverall the variance is nil. The rate variance is adverse like labour rate, reflecting general

    rise in cost of resources in the society, where as efficiency variance is favourable showing

    better internal controls in production process.

    Fixed overheads

    Fixed overheads were $10,000 more than budgeted, again reflecting a rise in general costs

    in the economy, like variable overheads and labour.