fabric form concrete
DESCRIPTION
PARA WEB SOIL RETENTIONTRANSCRIPT
![Page 1: fabric form concrete](https://reader036.vdocument.in/reader036/viewer/2022081715/54603e0eb1af9f16598b51fc/html5/thumbnails/1.jpg)
F IB E R F O R M F O R M E D O F C A R B O N F IB E R C O M P O S IT E
C O N C R E T E IS P O U R E D IN A N D T H E S E V O ID S A R E F IL L E D .
FABRIC FORMED CONCRETE MATS FOR EROSION
CONTROL SYSTEM INTRODUCTION: This is a technique in which fiber forms of nylon, composite fiber and other different
type of polymers are made in factory. Selection of the materials required for the
fabrication of forms depends upon the site conditions and durability aspect required of
the fabric form according to the need.
These fabric forms are fabricated in such a pattern that different packets are
interconnected to each other forming a continuous mat.
These fabric forms also contain capillary pores for reduction of uplift pressure.
These fabric forms are transported to the site, soil is compacted and leveled on site
and these mat of fabric forms are laid on the surface. After laying, concrete is poured
in these mats through concrete pump into the packets.
Flow of concrete within the mats takes place on its own. Fine aggregate concrete is
used with little higher w/c ratio.
Mats can be designed with different size and shapes ranging from
Average thickness of mat with concrete filled inside (from 56mm to 350mm)
Mass per unit area with concrete filled inside (from 121 kg/m2 to 661 kg/m2)
Concrete quantity required (from 16.6 m2/m3 to 3m2/m3)
C/C spacing (from 127mm to 406 mm)
![Page 2: fabric form concrete](https://reader036.vdocument.in/reader036/viewer/2022081715/54603e0eb1af9f16598b51fc/html5/thumbnails/2.jpg)
CAPILLARY PORES
SOIL SAMPLEUP LIFT WATER PRESSURE
FABRIC FORM
G.LG.L
sectional elevation
Practical application of this fabric formed concrete
These fabric formed concrete has a wide variety of application such as follows:
Drainage ditches
Channels and canals
Streams, river, and bayous
Lakes and reservoirs
Coastal and intercostals shorelines
Jetties and groins
Dikes and levees
Dune protection
Beach renourishment
Seawall and bulkhead scour protection
Boat launching ramps
Wildlife crossings
Low-water stream, crossings
Embankments
Underwater pipeline
bridge abutments and piers
Check dams
Dams and spillways
Ponds and holding basins
Landfill caps
Down chutes
Water control structures
![Page 3: fabric form concrete](https://reader036.vdocument.in/reader036/viewer/2022081715/54603e0eb1af9f16598b51fc/html5/thumbnails/3.jpg)
REDUCE UPLIFT PRESSURE: Unlike traditional method, fabrics formed concrete are manufactured with built in filter drains
that reduce the mean phreatic level and pore pressures within the underlying soil, and thus
provide for the relief of hydrostatic uplift pressure, increasing the system stability.
The groves seen within are pores which are prefabricated in
the fabric form for release of pore uplift pressure.
MANAGEMENT OF HYDRALIC FLOW: Fabric formed concrete can be constructed with deeply patterned surfaces. These patterns
create a high coefficient of hydraulic friction, which result in reduced flow velocity and
reduced wave run-up. These surface characteristics impart stability to the system by reducing
velocities and also mean that the designer can affect the flow characteristics of a channel,
creating the opportunity for an “engineered” hydraulic system. By choosing the correct style
of form, in-channel flow can be slowed, reducing downstream velocities and discharge
turbulence. Or a hydraulic-efficient, smooth form (such as uniform section) can be chosen to
maximize drainage from a given area.
These fiber form concrete creates interconnected, tubular
concrete elements that are separated by large, interwoven
fiber form. These tubular elements create two directional-
determined coefficients of hydraulic friction.
ADAPTATION TO SOIL CONTOURS: Filled-in-place forms accommodate uneven contours, cures, and sub grades at the time that
they are filled. Consequently, the soil and the concrete protection are in intimate contact,
reducing the chance of under scour. Some forms create discrete concrete units, attached to
each other with fabric perimeters and/or embedded cables. As a result, the concrete mats can
articulate to adapt to uneven settlement.
![Page 4: fabric form concrete](https://reader036.vdocument.in/reader036/viewer/2022081715/54603e0eb1af9f16598b51fc/html5/thumbnails/4.jpg)
These are specially designed for adaptation of uneven soil
topography, these are also designed for plantation of
different varieties of plantation according to the
surrounding environment which may comprise of grass
and shrubs, the (X) marks shown in the figure indicated
those part of the fiber form in which concrete is not filled
and after concreting the fabric form on site, these parts
are teared open for growing plantation, seedlings.
EASE TO INSTALLATION: Fabric forms are delivered to the job site ready-to-fill and require no additional forming
materials. Installation consists of preparing the area, laying out the fabric forms, and filling
them with concrete through a small line concrete pump. Wood or steel forming is not
required. The fabric forms themselves assure that the concrete assumes the proper
configuration, contours, dimensions and thickness. These mats do not require steel
reinforcement or concrete finishing. A small crew can be installed without dewatering the
site.
SIMPLE JOB MOBILIZATION: Fabric forms are extremely lightweight, so they can be rapidly shipped anywhere in the
world. The weight component of a fabric-formed system, the fine aggregate concrete, is
readily available from concrete suppliers worldwide. Once the site is prepared, simple hand
tools and concrete pump are all that is needed to fill the forms. And in area with difficult or
restricted access, the concrete can be pumped to the forms as far away as 800 feet (250
meters). Because of the low mobilization costs, it is practical to install fabric forms on jobs as
small as a hundred square feet (10 square meters). Regardless of the job size, the ease of
mobilization and transportation and the reduced equipment and labor requirements mean that
the hob goes in faster and at less cost per square unit of protected area.
![Page 5: fabric form concrete](https://reader036.vdocument.in/reader036/viewer/2022081715/54603e0eb1af9f16598b51fc/html5/thumbnails/5.jpg)
ENVIRONMENTAL COMPATIBILITY: Fabric forms are designed to provide the least possible environmental impact. The fabric used
in the forms allows excess mixing water to escape while retaining the cement solids, fine
aggregate, and sand. These fabric forms have been designed to provide defined areas that can
be cut out after installation so that native vegetation can be planted or seeded to create a more
natural appearance. More over this linings and mats are free of hazardous projections that
could endanger pedestrians, animal’s vehicles, or boats.
This is a picture where the fabric form is used; the photo graph
was taken 6 months later after construction. Grass and shrubs
have developed in such a way that it becomes hard to see the
underlying fabric formed concrete lining, thus this technique
provides hydraulic, ecological, and aesthetic features.
HIGH STRENGTH CABLE REINFORCED FABRIC FORM
CONCRETE MATS: Articulation block mats form cable-reinforced concrete block mattresses that resist erosive
force. They are often installed where fiber form concrete mats are exposed to attack by wave
action and are used to protect shorelines, canals, rivers, lakes, reservoirs, underwater
pipelines, bridge piers, and other civil and marine structures from propeller wash, ship wakes,
waves, currents, and high velocity flows. Articulation block fabric consists of series of
compartments linked by interwoven perimeters. Grout ducts interconnect the compartments.
High strength revetment cables are installed between and through the compartments and
grout ducts. Once filled, these mats become a mattress of pillow-shaped, rectangular concrete
block. The interwoven perimeters between the blocks serve as hinges to permit articulation.
The cables remain embedded in the concrete blocks to link the blocks together and facilitate
articulation.
![Page 6: fabric form concrete](https://reader036.vdocument.in/reader036/viewer/2022081715/54603e0eb1af9f16598b51fc/html5/thumbnails/6.jpg)
PARA WEB SOIL RETENTION SYSTEM INTRODUCTION: It is a fast and economical method of building an earth retaining
structure in a variety of environments including industrial, highway, marine and river work
and is based on Websol system. WEBSOL-SYSTEM: This system is based upon the use of polyethylene encased
polyester fiber multicards which act as a frictional anchor under compacted earth fill and tied
with pre-cast reinforced concrete panels through anchor bars, in short it is based on use of
polymeric products to reinforce and control drainage of soils.
COMPONENTS OF WEBSOL SYSTEM (PARAWEB SYSTEM)
FACING PANELS: These are cladding units in precast concrete. Precast concrete facing
units are 2 m wide by 1.6 m high and are normally 160 mm thick. They are lightly reinforced
with mesh. Units incorporate attachment loops and two lifting lugs are cast into the top of
each unit for handling.
PARAWEB ANCHOR TIES: The straps comprise
polyester tendons encased in a polyethylene sheath,
and are manufactured in three grades 30, 50, 10
Grade Minimum
short term
Minimum
long term
Maximum
design loads
Nominal
width (mm)
Nominal
thickness
![Page 7: fabric form concrete](https://reader036.vdocument.in/reader036/viewer/2022081715/54603e0eb1af9f16598b51fc/html5/thumbnails/7.jpg)
breaking
loads (kn)
breaking
loads (kn)
(kn) (mm)
30 30 22.5 7.5 85 2.2
50 50 37.5 12.5 90 3.5
100 100 75.00 25.0 90 6.6
HORIZONTAL JOINT FILLER: Horizontal joint filler is required to be used to
avoid damage of concrete during placing of panels and for proper sealing of horizontal joints
between precast panels. Normally resin bonded cork is used for this purpose. VERTICAL JOINT FILLER: To close the vertical joints between pre-cast facing
panels flexible closed cell expanded polyethylene foam strips of 254 mm x 25 mm are used, DOWEL RODS: Vertical polypropylene dowel rods are fitted in to the units shoulders to
guide for placement of subsequent layer of precast panels. Dowel rods are of 25 mm dia.
STEEL ‘S’ CLAMP: The connection between the straps is made easily
using the temporary mild steel ‘S’ clamp. DESIGN LIFE: If constructed in accordance with the guidelines as
suggested by British board of agreement for roads & bridges (1983), the
estimated design life for such structures is 120 years. EXCAVATION AND FOUNDATION
CONSTRUCTION: Excavation is required be done
to provide for nominal base, which may be stepped
wherever necessary in the longitudinal direction
depending upon the topography of the area. depth of
foundation below finish ground level at the foot of the
wall should not be less than 800 mm. the concrete facing
panels at the base of the wall shall be placed on a level
footing of PC concrete M-20 within the tolerance of + 5
mm of the top level. Footing should be cured for a
minimum of 7 days prior to placing the bottom
![Page 8: fabric form concrete](https://reader036.vdocument.in/reader036/viewer/2022081715/54603e0eb1af9f16598b51fc/html5/thumbnails/8.jpg)
panels.
BACKFILL MATERIAL: Following grading limits have been defined for use of back fill soil;
Maximum particle size may be increase in accordance
with site requirements.
Compaction within end 2 meters should only be done
with a light manually controlled machine without any
vibration. No heavy machinery having weight more than
1000kg should be brought in the vicinity of the width.
Minimum density achieved by compaction should be
95% of the maximum dry density as per IS:2720 PART VIII.
BENEFITS:
The principal reinforcement element of the system of the system, being made of
polyester fibers covered with a polyethylene sheath, is absolutely corrosion free and
inert to chemical.
The use of polymeric rear anchors
provides additional safety to the structure
by providing passive resistance in addition
to the active resistance provided by the
friction between the backfill soil and the
strips, thus the failure stress of reinforced
soil will be more then that of unreinforced
as shown in figure.
The structure is rigid and hence difficult to
be pulled out because of its continuous length, as also is the case with the rear
anchors.
Sieve Size Percentage Passing
150 mm 100
90mm 85-100
10mm 25-100
600 microns 10-65
63 microns 0-8
![Page 9: fabric form concrete](https://reader036.vdocument.in/reader036/viewer/2022081715/54603e0eb1af9f16598b51fc/html5/thumbnails/9.jpg)
The system is very flexible and especially suited for areas susceptible to seismic
conditions.
Owing to their flexibility and interlocking system, the structure is very well able to
adapt to differential settlements and yet maintain its integrity.
SPEED: The speed of construction is at least 5 times much higher as compared to
reinforced concrete walls. The average rate of construction for Para web walls in
typical conditions would be approximately 20Sq.m per location per day (i.e.5 to 10 m
wall length/day).
SIMPLICITY & APPEARANCE: only three
main components are
required: panels, frictional
anchors and soil.
Construction may be
carried out with unskilled labour & light plant & the walls can be cast in variety of
attractive paterns & colours
ECONOMY: cost comparison has been carried out with the websol construction on
approach walls of road over-bridge at phagwara. Four approach walls (two on either
side) with websol system have been constructed. Total length of each wall is 326 m
with height varying from 1.5 m to 9.0 m. imported ‘paraweb’ material has been used
for this purpose. Panel casting has been done at a separate yard about 15 km away
from the site of erection. Total cost incurred for all the four walls is Rs. 145.00 lacks.
Net saving over R.C.C. walls with same height and length works out to Rs. 162.00
lacks. Net saving over R.C.C. walls thus works out to the extent of 10.5 per cent.
It has been noticed that for a height up to 2.m websol construction is not
economical as compared to the R.C.C. walls. With subsequent increase in height,
saving is effected.
INSTALLATION:
![Page 10: fabric form concrete](https://reader036.vdocument.in/reader036/viewer/2022081715/54603e0eb1af9f16598b51fc/html5/thumbnails/10.jpg)
Panels are transported from the casting yard to the site of work with the help of light crane or
by any other convenient method. Bottom row of panels which is always a half panel are
placed on the foundation beam. The majority of the panels in any wall are a standard t shape
in elevation with edges shaped to interlock each panel with those adjacent to it.
Each panel is joined with the other in the
recommended sequence of drawing but
without any filler in between in the bottom
layer so as to ensure the flow of percolated
rain water. Panels are placed in the
required place with an inclination of 1 in
150 toward inner side to compensate for
subsequent movement due to filling
operations. Panels are temporarily
supported with the help of steel struts from outside to keep them in position with the fill
pressure is fully taken by ‘paraweb’ strips. Fill is then placed in layers with at least 95 percent
compaction leaving end 60cms near the panel where filler material is placed simultaneously.
Fill and filter material is brought to the level of first layer of frictional anchor. Paraweb layer
is then placed in position. Paraweb reinforcement is placed to the alignment shown in the
drawing in horizontal layers. It is looped between panel anchors and outer fixing bar. The
ends of paraweb are sealed using bitumen based sealant and at least 2 m overlap is provided
by means of a temporary wooden buckle. After laying each anchor, layer is hand tightened to
remove any slack before placing of filter materials. As fill
reaches top row of panels, next row of panels with the help
of plastic dowel rod (to be used as guidance) is placed by
maintaining line and level. At the top of first panel resin
bonded cork is placed which works as horizontal joint filler.
Plastozote foam is placed in the vertical joints to ensure the
joints to be watertight so that percolated rain water out
![Page 11: fabric form concrete](https://reader036.vdocument.in/reader036/viewer/2022081715/54603e0eb1af9f16598b51fc/html5/thumbnails/11.jpg)
flows only through bottom layer. Sequence is then repeated till desired height is achieved.
Top panels are covered by casting in-suit caping beam to ensure one mass behavior of panels.
MECHANICAL PROPERTIES: (1) TENSILE STRENGTH: minimum long term breaking
loads of paraweb multicords after application of factor of
safety are given in figure:
(2) MODULUS OF ELASTICITY: short term stress/strain
graph is shown actual strain at break is app 0.6% after one
year with zero increase thereafter.
(3) EFFECT OF TEMPERATURE: mechanical properties of
geostrip vary very little within the temperature of -20o to + 65o C
(4) EFFECT OF WATER: there is no significant loss in strength when ‘paraweb’ is
immersed in water with ends sealed. Long term strength takes into account the effects
of hydrolysis due to local drainage.(i.e. dehydration)
(5) COEFFICIENT OF FRICTION: the coefficient of friction between paraweb and
the fill can be obtained from shear box tests conducted during execution.
(6) The black grade of polyethylene used as a protective sheath of paraweb multicord
suffers no deterioration from normal exposure to sunlight or from burial under wet
soil conditions.
(7) Paraweb has very good resistance to biodegradation.
(8) The principal of dehydration of paraweb polyester fibers is water.