FACILITIES COUNCIL MEETING DATE: September 8, 2016 SUMMARY: Facilities Master Plan 2011-2030 – Annual update for 2016 is
submitted for the information of the Council. COMMENTS: • The Facilities Master Plan 2011-2030 (FMP) maps and
spreadsheets serve as primary reference materials for the FMP ad hoc implementation committees, the Facilities Council, Facilities Advisory Committee, Architecture Landscape Review Board, campus leadership, staff, project architectural/engineering teams, public-private partnerships, and as general information about University plans.
• Annual updates, as part of the University’s Capital Budget
process, will ensure that the maps and spreadsheets are current.
• This annual update for 2016 reflects UMD’s FY 2018-2027 Capital Improvement Program and FY 2017-2026 System Funded Construction Program and includes the following changes:
o Projects Completed:
- CC_T4 Zagster Bikeshare system installed (Transportation).
o Renovation Projects Completed: - Tawes Hall (141) - Relocation of Innovation District and Physical
Distribution facilities into Severn Building (810).
o Buildings Demolished: - Police Substation / Yale Avenue (018).
o Projects Added
- Period 1 Renovation: Central Animal Research Facility (087 – convert to
storage facility) Chemistry Building (091 – Partial) A.V. Williams (115 – Partial: space vacated due to
Iribe program) Biomolecular Sciences Building (296 – Partial)
- Period 2 Renovation: H.J. Patterson (073 – Partial) Main Administration (077 – Partial) Van Munching Hall (039 – Partial space vacated due
to new School of Public Policy)
o Projects moved from Period 2 to Period 1 New Construction: - School of Public Policy (S2 became CC5).
o Projects moved from Period 1 to Period 2 New Construction:
- Campus Farm Master Plan – New Buildings, Renovations, and Pastures (NE1 and NE _L8).
o Projects moved from Period 1 to Period 2 Renovations:
- Horse, Sheep and Cattle barns (108-10)
o Projects moved from Period 1 to Period 2 Demolition: - Motor Transportation Building (011) - Preinkert Field House (054) - Institute for Physical Sciences & Technology (085) - Central Animal Research Facility (087) - Chemistry Building – Wing 1 (091) - Agriculture Shed (102) - Animal Science Service Building (103) - Poultry Barn (119) - Varsity Sports Team House (158) - Ellicott Area Dining Hall (257).
o Project Name Changes:
- Chemistry Wing 1 Replacement in lieu of Chemistry Renovation (NE14)
- Academic Building in lieu of School of Public Policy (replace S2).
• The annual update for 2016 is available on the University website
https://www.facilities.umd.edu/sitepages/FPmasterplan.aspx as well as in print version, by request.
AREA AFFECTED: UMD Campus ATTACHMENTS: Background Information SUBMITTED BY: Daniel FC Hayes, Department of Facilities Planning
P:\Campus Development\FMP\2011-2030 FMP-Annual Updates\FMP_Update_2016\FMP-FC-cover_16s15.doc Page 2 of 2
Completed since last update (Projects completed from July 2015 to June 2016)
Number GSFNew Construction 0 0Building Renovations 4 141,760Building Demolitions 1 (3,853)Landscape and Transportation Improvements 1 N/A
Total 6
Completed since Plan Approved (Projects completed from January 2011 to June 2016)
Number GSFNew Construction 8 655,290Building Renovations 16 748,061Building Demolitions 19 (126,088)Landscape and Transportation Improvements 4 N/A
Total 47
Summary for All Planning PeriodsNumber GSF
New Construction 57 8,680,357Building Renovations 56 3,014,408Building Demolitions 49 (724,173)Landscape and Transportation Improvements 65 N/A
Total 227
Planning Period 1 (July 2016- December 2020)Number GSF
New Construction 13 2,626,082Building Renovations 13 592,729Building Demolitions 10 (155,993)Landscape and Transportation Improvements 39 N/A
Total 75
Planning Period 2 (January 2021- December 2030)Number GSF
New Construction 44 6,054,275Building Renovations 43 2,421,679Building Demolitions 39 (568,180)Landscape and Transportation Improvements 26 N/A
Total 152
Building # Site # Project Building Type GSF
039 S4Van Munching Hall Addition/Renovation
Academic 15,282
419 NW2 Oakland Hall Auxiliary 233,436164 W1 University House Non-Academic 15,133424 N1 Shuttle Bus Facility Auxiliary 10,947
426 N3Heavy Equipment Building
Non-Academic 7,136
415 NE4Physical Sciences Complex -Phase 1
Academic 172,986
428 N12 Wye Oak Building Non-Academic 13,520425 S6 Prince Frederick Hall Auxiliary 186,849
Total 655,290
Building # District GSFDate
CompletedComments
059 CC 22,647 2012089 NE 5,800 2012 Partial
099 NE 20,090 2012To provide air conditioning
115 NE 114,118 2012 Partial171 E 10,445 2012176 E 11,833 2012
810 OP 53,677 2012For Innovation District relocations
007 E 30,346 2013For Department of Public Safety
091 NE 40,500 2013 Partial
098 NW 139,888 2013To provide air conditioning
254 NW 115,658 2013To provide air conditioning
077 CC 41,299 2014 Partial
810 OP 38,900 2015
Partial - For Physical Distribution Warehouse relocation
141 W 31,550 2015Convert theater to offices / classrooms
Pocomoke Building
Chemistry Building
Centreville Hall
Main Administration Building
Severn Building - Phase 3
Tawes Hall
Bel Air Hall
A.V. Williams BuildingPhi Sigma Sigma Sorority
Alpha Phi SororitySevern Building - Phase 1 And
1A
Elkton Hall
Engineering Laboratory
Project
Chincoteague Hall
FMP 2016 Update - Projects Completed Since Plan Approved January 2011 - June 2016
Renovation
New ConstructionDate Completed
2011
2011
20122012
2012
2013
20132014
FMP 2016 Update - Projects Completed Since Plan Approved January 2011 - June 2016
810 Severn BuildingOP 22,080
2016For Remote Library Storage
810 Severn Building - Phase 2OP 49,230
2016
For Innovation District Relocations
Total 748,061
Building # District Building GSFDate
CompletedReason for Demolition
050 N 3,244 2012 Site for new facility
066 S 2,572 2012 Site for new facility
002 E 56,246 2014East District Redevelopment
012 E 11,832 2014East District Redevelopment
013 E 5,862 2014East District Redevelopment
055 E 680 2014East District Redevelopment
075 CC 22,315 2014 Site for new facility
100 E 1,829 2014East District Redevelopment
101 E 1,840 2014East District Redevelopment
112 E 603 2014East District Redevelopment
208 E 666 2014East District Redevelopment
212 E 1,874 2014East District Redevelopment
215 E 3,342 2014East District Redevelopment
216 E 3,267 2014East District Redevelopment
217 E 682 2014East District Redevelopment
343 E 4,225 2014East District Redevelopment
Harrison Laboratory
Shuttle Bus Trailer
Temporary Building
Plant Operations & Maintenance Shop
Building Services Operations
Heavy Equipment Building
Solid Waste Storage
Campus Mail Facility
Plant Operations & Maintenance Shop
Demolition
Project
Grounds Office Building
West Education Annex
Plant Operations & Maintenance Shop
Shuttle Bus Facility
Plant Operations & Maintenance Storage
Shriver Laboratory
Plant Operations & Maintenance Shop
FMP 2016 Update - Projects Completed Since Plan Approved January 2011 - June 2016
385 E 610 2014East District Redevelopment
410 E 546 2014East District Redevelopment
018 E 3,853 2015 Site for new facility
Total 126,088
Project_ID Project TypeDate
CompletedW_L1 Auxiliary 2012
CC_T3 Transportation 2013
E_L3 Landscape 2014
CC_T4 Transportation 2016Zagster BikeshareJoint Venture project installed on
Campus and in City of College Park
Maryland Stadium Field Sports Field
Landscape and Transportation
Project Comments
Sharrows & Signage Signage
Centennial Garden (Fraternity Row) Partial
Police Substation (7505 Yale Avenue)
Pest Control Trailer
Shuttle Bus Trailer
Campus Core Site Building GSF Floors Project Type
CC1Edward St. John Learning and Teaching Center
180,744 3 Academic
CC5School of Public Policy Building and Site Development
69,700 4 Academic
CC2Benjamin Building/Center for Young Children
95,700 5 Academic
CC3Administrative Office Building
57,100 4 Academic
East
E1East District Mixed-use Development: Hotel and Garage
775,450 varies East District
E2
East District Mixed-use Development: Innovation District: Phase 2
279,400 varies East District
E3 Day Care Facility 13,500 2 Auxiliary
E4
East District Mixed-use Development: Leonardtown-Physical Distribution Center: Phase 3
2,080,800 varies East District
Golf CoursePlanning Period 1 GC1 Indoor Driving Range 1,000 1 Auxiliary
GC2Golf Course Maintenance
10,400 1 Auxiliary
GC3B&LM Grounds Maintenance Replacement
20,000 1 Academic Support
FMP 2016 Update New ConstructionJuly 2016 - December 2030
Planning Period 2
Planning Period 1
Planning Period 2
Planning Period 2
Planning Period 1
FMP 2016 Update New ConstructionJuly 2016 - December 2030
North
Planning Period 1 N2Paint Branch Parking Garage - Phase 1 (1,000 spaces)
300,0005 (4-Story "Read")
Auxiliary
N4 Electric Substation 5,400 1 Utility
N2aPaint Branch Parking Garage - Phase 2 (1,000 spaces)
300,0005 (4-Story "Read")
Auxiliary
N2b Paint Branch Parking Garage - Phase 3 (1,000 spaces)
300,0005 (4-Story "Read")
Auxiliary
N5Environmental Service Facility Expansion
10,100 2 Academic Support
N6Xfinity Center Office Expansion
7,020 1 Auxiliary
N7Field Hockey and Lacrosse Complex Expansion
5,800 1 Auxiliary
N8Xfinity Center Addition (Basketball Practice Facility)
22,500 1 Auxiliary
N9Xfinity Center Addition (Gymnastics Practice Facility)
15,000 1 Auxiliary
N10Robert E. Taylor Stadium Expansion
2,640 1 Auxiliary
N11 New Energy Plant 60,000 2 Utility
Outlying Properties
Planning Period 2 OP1
Chesapeake Bay Mesocosm (near Avrum Gudelsky Veterinary Center)
8,000 1 Academic
Off Campus
Planning Period 2 N/AMIFRI Western MD Regional Training Center Upgrade
13,100 TBD Academic Support
Planning Period 2
FMP 2016 Update New ConstructionJuly 2016 - December 2030
NortheastNE6 A. James Clark Hall 184,239 6 Academic
NE8Brendan Iribe Center for Computer Science and Innovation
215,600 9 Academic
NE14Chemistry - Wing 1 Replacement - Phase 2A NMR
3,750 1 Academic
NE1Campus Farm Master Plan - New Buildings and Renovations
41,800 2 Academic
NE2Brain and Behavior Research Building Phase 1
113,775 5 Academic
NE3Brain and Behavior Research Building Phase 2
102,000 5 Academic
NE5Physical Sciences Complex - Phase 2
106,300 6 Academic
NE7Nutrition & Food Sciences
94,000 6 Academic
NE9Physical Sciences Complex - Phase 3
102,400 7 Academic
NE10 Div IT Building 100,000 4 Academic Support
NE11A. James Clark Hall - Phase 2
54,500 6 Academic
NE12 Aerospace Engineering 106,800 6 Academic
NE13Chemistry - Wing 1 Replacement
88,300 5 Academic
NE15 SCUB Expansion 8,540 2 AuxiliaryNE16 Engineering Annex 182,000 9 Academic
Planning Period 1
Planning Period 2
FMP 2016 Update New ConstructionJuly 2016 - December 2030
Northwest
NW1School of Public Health - Addition/Conversion - Phase 2
27,299 3 Academic
NW3Undergraduate Housing 1 (515 Beds)
169,950 9 Auxiliary
NW6Replace Ellicott Dining Hall
57,750 2 Auxiliary
NW4Undergraduate Housing 2 (515 Beds)
169,950 9 Auxiliary
NW5
Replacement Housing (650 Beds) + Residential Facilities Office Relocation
240,300 8 Auxiliary
South
S1Architecture Building Additions
122,250 3 Academic
S2 Academic 79,800 4 Academic
S3
Public Protection and Security Research Building, SCUB Expansion and Site Development
134,000 5 Academic
S5Visual Arts and Cultures Building
112,300 4 Academic
S7South Campus Recreation Building
70,000 3 Auxiliary
S8
Worcester Hall Replacement (450 beds), SCUB Expansion and Site Development
135,000 4 Auxiliary
S9Behavioral and Social Sciences Research Building
120,000 5 Academic
S10Expand and Renovate Annapolis Hall
32,900 3 Auxiliary
Planning Period 1
Planning Period 2
Planning Period 2
FMP 2016 Update New ConstructionJuly 2016 - December 2030
WestPlanning Period 1 W3 New Cole Fieldhouse 281,400 2 Auxiliary/ Academic
W2Ludwig Soccer Stadium Upgrades (12,000 to 18,000 seats)
105,700 1 Auxiliary
W4 Shipley Field Upgrades 16,900 1 Auxiliary
W5Gossett Football Team House Addition
7,500 1 Auxiliary
W6Campus Drive Parking Garage (2,200 spaces)
660,0006 (5-story
"read")Auxiliary
GSF Planning Period 1 (July 2016 -December 2020)
2,626,082
GSF Planning Period 2 (January 2021 - December 2030)
6,054,275
8,680,357
Planning Period 2
NOTES:
Worcester Hall (051) Replacement: Building is 77,600 GSF plus 7,000 GSF for half of existing SCUB II.Public Protection and Security Research: Building is 120,000 GSF plus 7K GSF for half of existing SCUB II and 7K GSF for future SCUB expansion for future development.
Benjamin Building (143): Building is 85,000 GSF plus 10,700 GSF for CYC replacement.
New Electric Sub-station: Footprint is 10% larger than footprint of Mowatt sub-station.
New Energy Plant: 30K footprint plus 10K outside area for trucks/storage if this becomes bio-mass.
New SCUB Expansion is 8,540 GSF on site to be determined. East District Mixed-use Development Hotel and Garage (site E1): GSF includes parking garage, GSF from Real Estate Office. GSFs for sites E2 and E4 were calculated assuming same land use density as site E1.
Building # Building District GSF Comments034 Jimenez Hall CC 63,200064 Dorchester Hall CC 35,436073 H.J. Patterson Hall CC 56,600 Wing 1 Renovation074 Holzapfel CC 27,400 Renovated as part of St. John Center001 Energy Plant E 39,655 Upgrade
011Building 011 (Motor Transportation Building) E
9,016East District Redevelopment
096 Cambridge Hall NE 55,792147 Hornbake Library NE 7,500 Ground and Fourth Floor renovations256 Ellicott Hall NW 123,247091 Chemistry Building NE 53,500 Partial
087Central Animal Research Facility NE
7,163Temporary Use
296Biomolecular Sciences Building NE 12450 Partial (3rd Floor)
115 A.V. Williams NE 101,770 Partial (Iribe)Total 592,729
FMP 2016 Update Building Renovations Planning Period 1 (July 2016 - December 2020)
Building Number
Building District GSF Comments
009 Memorial Chapel CC 25,776040 Morrill Hall CC 16,277042 Tydings Hall CC 101,945043 Taliaferro Hall CC 47,870046 Marie Mount Hall CC 114,757047 Woods Hall CC 24,055048 Francis Scott Key Hall CC 24,804 Ground and First Floors052 Mitchell Building CC 19,840 Partial071 Lee Building CC 20,662 Partial073 H.J. Patterson Hall CC 62372 Wing 2 Renovation076 Symons Hall CC 54,753 Center and North wings
077Main Administration Building CC 41,299 Partial
078 Reckord Armory CC35,541
Ground Floor: convert lecture halls to other uses
079 Turner Hall CC 25,666080 Rossborough Inn CC 8,963143 Benjamin Building CC 112,505
309 Indoor Practice Facility GC20,963
Convert to multi-purpose sport practice
081 Wind Tunnel Building NE 31,567
082John S. Toll Physics Building NE
163,093North Wing renovation
084 William E. Kirwan Hall NE25,981
Ground Floor: Classroom up-grades108 Horse Barn NE 4,188 Per Farm Master Plan109 Sheep Barn NE 6,152 Per Farm Master Plan110 Cattle Barn NE 6,105 Per Farm Master Plan115 A.V. Williams Building NE 134,274 Partial (Rest of building)
142
Animal Sciences/Agriculture Engineering Building NE
62,462Wing 1 Renovation
144Biology-Psychology Building NE
250,240
231 Microbiology Building NE 88,285237 Geology Building NE 24,390121 Chestertown Hall NW 29,090122 Cumberland Hall NW 124,486252 Denton Hall NW 117,468253 Easton Hall NW 117,473258 Hagerstown Hall NW 124,241259 La Plata Hall NW 137,723017 Cecil Hall S 20,096
FMP 2016 Update Building Renovations Planning Period 2 (January 2021 - December 2030)
Building Number
Building District GSF Comments
FMP 2016 Update Building Renovations Planning Period 2 (January 2021 - December 2030)
039 Van Munching Hall S34,900
Partial: School of Public Policy wing145 Architecture Building S 67,163
362Maryland Stadium Concessions 1 W
4,620
363Maryland Stadium Concessions 2 W
2,663
364Maryland Stadium Concessions 3 W
2,705
365Maryland Stadium Concessions 4 W
11,193
367Maryland Stadium Concessions 5 W
9,159
379Gossett Football Team House W
63,914
Total 2,421,6793,014,408Total Planning Period 1 and 2
Building # Building District GSF Reason for Demolition
020Motorcycle Storage Building
E416
East District Redevelopment
210Plant Operations & Maintenance Storage
E499
East District Redevelopment
239 Leonardtown ApartmentE
12,582East District Redevelopment
240 Leonardtown ApartmentE
10,152East District Redevelopment
241 Leonardtown ApartmentE
6,291East District Redevelopment
332 Anacostia Building N 1,787 Site for new facility
091Chemistry Building - Wing 1
NE115,847 Site for new facility
803Adelphi Road Office Annex (8701 Adelphi Rd)
OP4,818
Site for new facility
811Knox Road Building (4218 Knox Road)
S3,332
Site for new facility
200 Storage Facility W 269 Site for new facilityTotal 155,993
FMP 2016 Update Building DemolitionsPlanning Period 1 (July 2016 - December 2020)
Building # Building District GSF Reason for Demolition003 Service Building E 84,029 East District Redevelopment
006Plant Operations & Maintenance Building
E 20,165 East District Redevelopment
011 Building 011 E 9,016 Site for new facility
116 Temporary Building (South Of 201) E 1,440 East District Redevelopment
201 Leonardtown Office Building E 10,018 East District Redevelopment
204 Temporary Building (West Of 201) E 869 East District Redevelopment
207 Temporary Building (West Of 201) E 733 East District Redevelopment
238 Leonardtown Apartment E 10,152 East District Redevelopment242 Leonardtown Apartment E 10,152 East District Redevelopment243 Leonardtown Apartment E 5,076 East District Redevelopment244 Leonardtown Apartment E 13,452 East District Redevelopment245 Leonardtown Apartment E 13,452 East District Redevelopment246 Leonardtown Apartment E 13,452 East District Redevelopment247 Leonardtown Apartment E 13,452 East District Redevelopment248 Leonardtown Apartment E 13,452 East District Redevelopment249 Leonardtown Apartment E 13,452 East District Redevelopment
250 Leonardtown Community Center E 3,660 East District Redevelopment
124Grounds Material And Equipment Building
N 7,372 Site for new facility
327Grounds Herbicide/Pesticide Storage Building
N 235 Site for new facility
328Grounds Operations And Maintenance Building
N 3,157 Site for new facility
344 Environmental Service Facility N 7,752 Replaced by new facility
045 Instructional Television Building NE 3,082 Site development project
085Institute For Physical Sciences & Technology
NE28,534
Site for new facility
087Central Animal Research Facility
NE7,163
Site for new facility
093 Engineering Annex NE 10,888 Site for new facility102 Agriculture Shed NE 2,322 Per Farm Master Plan
103Animal Science Service Building
NE1,397
Per Farm Master Plan
119 Poultry Barn NE 1,026 Per Farm Master Plan227 Jull Hall NE 17,574 Site for new facility257 Ellicott Area Dining Hall NW 48,280 Site for new facility381 Center For Young Children NW 10,645 Site for new facility
FMP 2016 Update Building DemolitionsPlanning Period 2 (January 2021 - December 2030)
Building # Building District GSF Reason for Demolition
FMP 2016 Update Building DemolitionsPlanning Period 2 (January 2021 - December 2030)
051 Worcester Hall S 33,541 Site for new facility054 Preinkert Field House S 28,237 Site for new facility065 Carroll Hall S 26,470 Site for new facility
067Satellite Central Utilities Building (SCUB 2)
S 13,664 Site for new facility
069 Wicomico Hall S 27,684 Site for new facility070 Caroline Hall S 26,959 Site for new facility158 Varsity Sports Team House W 22,857 Site for new facility
369Maryland Stadium Maintenance Building
W 3,319 Site for new facility
Total 568,180724,173Total Planning Period 1 and 2
Campus Core Site Project Project Type
CC_L1Rossborough Inn Gardens Improvements
Landscape
CC_L2McKeldin Library Hardscape and Landscape
Landscape
CC_L3McKeldin Mall Improvements (phased)
Landscape
CC_L4 South Chapel Lawn Enhancements Landscape
CC_L5 Chapel Fields Improvements Landscape
CC_L6South Gate Landscape Improvements
Landscape
CC_T1Campus Drive at Anne Arundel: Create Pedestrian/Bike Paths
Transportation
CC_T2Purple Line and Streetscape / Landscape Improvements
Transportation
CC_L7Garden of Reflection and Remembrance - Phase 2
Landscape
CC_L8 Morrill Hall Quad Improvements Landscape
CC_L9 Anne Arundel Green Landscape
CC_L10Lot Y Conversion and Landscape Improvements
Landscape
CC_L12 Tawes Plaza Improvements Landscape
East
E_L1
Route 1 Pedestrian Median Improvements (to be implemented by Maryland State Highway Administration)
Landscape
E_L2Fraternity Row - multi-field layout, artificial turf (4 fields, 270' x 660' overall)
Sports Field
E_L3Centennial Garden (Fraternity Row)
Landscape
E_T1Purple Line and Streetscape/Landscape Improvements
Transportation
Planning Period 2 E_L4 East Campus - Phase 2 Park Landscape
2016 FMP Update Landscape and Transportation
Planning Period 2 January 2021 -
December 2030
Planning Period 1
Planning Period 1 July 2016 -December
2020
2016 FMP Update Landscape and TransportationGolf Course
Planning Period 1 GC_L1 Holman Short Game Expansion Sports Field
GC_L2Golf Course Ponds and Storm Water Management Improvements
Landscape
GC_L3Perimeter Landscape Improvements University Boulevard and Adelphi Road
Landscape
North
N_L1Paint Branch Drive Gateway Enhancements
Landscape & Transportation
N_T1Pedestrian/Bicycle Improvements at Xfinity Center
Transportation
N_L2Recreation Fields on Paint Branch Parking Garage Roof
Sports Field
N_L3Terrapin Trail Retention Pond Improvements
Landscape
N_L4Paint Branch Drive Wooded Wetlands Improvements
Landscape
N_L5
Wooded Hillock Conservation Garden and Perimeter Landscape Improvements University Boulevard
Landscape
N_L6Relocate Kehoe Track and Throwing Area
Sports Field
N_L7 ICA/RecWell Field (Infield of Track) Sports Field
NortheastNE_L1 Hornbake Plaza Improvements Landscape
NE_L2Bioretention Garden Improvements (Technology Drive)
Landscape
NE_L3Northgate Park (West) Landscape Improvements
Landscape
NE_L8 Farm Master Plan Fields/Pastures Landscape
NE_T1 Regents Drive Improvements Transportation
Planning Period 2
Planning Period 1
Planning Period 1
Planning Period 2
2016 FMP Update Landscape and TransportationNortheast
NE_T2Pedestrian/Bicycle Improvements at Stadium Drive East
Transportation
NE_T3 Paint Branch Drive Improvements Transportation
NE_T4Bicycle Connection and Pedestrian Bridge at A.V. Williams Building, North
Transportation
NE_L4Animal Sciences Building Courtyard Improvements
Landscape
NE_L5Kim Engineering Building Plaza Improvements
Landscape
NE_L6William E. Kirwan Hall Courtyard Improvements
Landscape
NE_L7Outdoor Volleyball Courts (4 sand or artificial turf, 50'x80' each, including buffer space)
Sports Field
Northwest
NW_L1School of Public Health Building Garden
Landscape
NW_L2 Hagerstown Woods Improvements Landscape
NW_L6Relocation of Tennis Courts from New Cole Fieldhouse
Sports Field
NW_L3Campus Creek Trail and Ecosystem Enhancements
Landscape
NW_L4Multi-Sport Recreation Field (220' x 150', artificial turf)
Sports Field
NW_L5 Volleyball and/or Basketball Courts Sports Field
Planning Period 2
Planning Period 1
Planning Period 2
Planning Period 1
2016 FMP Update Landscape and TransportationOutlying Properties
Planning Period 1 OP_L2 Campus Tree Nursery Landscape
OP_L1Greenmead Drive Entry Enhancements
Landscape
OP_L3Avrum Gudelsky Veterinary Center Retention Pond Improvements
Landscape
OP_L4
Wetland Marsh Nature Walk and Perimeter Landscape Improvements University Boulevard
Landscape
OP_T1 Bicycle Trail Improvements Transportation
South
S_L1Lehigh Road Gateway and Pedestrian Enhancements
Landscape & Transportation
S_T1East-West Pedestrian Boulevard Improvements
Transportation
West
W_L2
Garden Walk at Clarice Smith Performing Arts Center and Perimeter Landscape Improvements University Boulevard
Landscape
W_L3Garden of Peace and Friendship - Phase 2
Landscape
W_L4Botanical Garden and Landscape Improvements - Phase 1
Landscape
W_L5Arboretum Outreach Center Landscape Improvements
Landscape
W_L6Field Turf Extension and Site Improvements
Sports Field
W_T1Lot 1 Road/Pedestrian/Bicycle Safety Improvements
Transportation
W_T2Campus Drive West Gateway Enhancements
Landscape & Transportation
W_T3Stadium Drive and Golf Course Gateway Enhancements
Landscape & Transportation
W_T4Purple Line and Streetscape/Landscape Improvements
Transportation
Planning Period 1
Planning Period 1
Planning Period 2
2016 FMP Update Landscape and TransportationWest
W_L7 Botanical Garden - Phase 2 Landscape
W_T5Stadium and Farm Drives Enhancements
TransportationPlanning Period 2
Buildings Under Construction
Date: 9/8/2016EXISTING CAMPUS
ATTACHMENT
AFacilities Planning
2016 UPDATEFACILITIES MASTER PLAN 2011-2030:
0 ¼Miles
ExistingProjects Completed Post - FMP 2011- 2030Approval (January 2011 - June 2016)
Legend
Date: 9/8/2016
ATTACHMENT
BFacilities Planning
2016 UPDATEFACILITIES MASTER PLAN 2011-2030:
PLANNING PERIOD 1(JULY 2016 - DECEMBER 2020) 0 ¼
Miles
LegendExistingPlanning Period 1
Date: 9/8/2016
ATTACHMENT
CFacilities Planning
2016 UPDATEFACILITIES MASTER PLAN 2011-2030:
PLANNING PERIOD 2 (JANUARY 2021 - DECEMBER 2030)
0 ¼Miles
LegendExistingPlanning Period 1 July 2016 - December 2020Planning Period 2 January 2021 - December 2030