Facility Condition Assessment For Carson City Library 900 N. Roof Street Carson City, NV 89701 Date of Report: May 13, 2020 Provided By: Faithful+Gould, Inc. Provided For: Carson City, NV

Upload: others

Post on 16-Oct-2021

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Facility Condition Assessment For Carson City Library 900

Facility Condition Assessment For Carson City Library 900 N. Roof Street Carson City, NV 89701

Date of Report: May 13, 2020

Provided By:

Faithful+Gould, Inc.

Provided For:

Carson City, NV

Page 2: Facility Condition Assessment For Carson City Library 900

5/13/2020

2 Carson City

Table of Contents

Executive summary ................................................................................................................................................3 Introduction ...........................................................................................................................................................3 Limiting Conditions ...............................................................................................................................................3 Project Details .......................................................................................................................................................4 Building Details .....................................................................................................................................................4 Building Description ..............................................................................................................................................5 Property Executive Summary ...............................................................................................................................5 Architectural Executive Summary .........................................................................................................................6 Mechanical Executive Summary ..........................................................................................................................7 Electrical Executive Summary ..............................................................................................................................7 Site Executive Summary .......................................................................................................................................8 Summary of Findings ............................................................................................................................................9 Building Expenditure Summary ............................................................................................................................9 Distribution of Immediate (Year 1) Needs by Building System ...........................................................................12 Distribution of Future (Year 2 – Year 10) Needs by Building System ................................................................13 Energy Conservation Measures .........................................................................................................................14 Facility Condition Needs Index ...........................................................................................................................15 Needs Sorted by Prioritization of Work ...............................................................................................................17 Needs Sorted by Plan Type ................................................................................................................................18

Page 3: Facility Condition Assessment For Carson City Library 900

5/13/2020

3 Carson City

Executive summary

Introduction

In accordance with the contract held between Carson City, NV and Faithful+Gould Inc, this completed report provides a comprehensive Facility Condition Assessment of the Library located at 900 N. Roof Street, Carson City, NV, 89701 (The Property).

This report provides a summary of the facility information known to us at the time of the study, the scope of work performed, an equipment inventory, evaluation of the visually apparent condition of The Property together with a forecast of capital expenditures anticipated over the next 10 years. The expenditure forecast does not account for typical preventative maintenance items such as changing filters to fan coil units.

Our cost rates to produce life cycle and replacement cost estimates are based on our knowledge of the local regional market rates and the RS Means Cost Database benchmarking. Our line item costs assume that the work will be procured through public general contractor bids.

This report provides a summary of the anticipated primary expenditures over the 10-year study period. Further details of these expenditures are included within each respective report section and within the 10-year expenditure forecast, in Appendix A.

The report also calculates the Current Facility Condition Needs Index (FCNI) which is used in Facilities Management to provide a benchmark to compare the relative condition of a group of facilities. The FCNI is a snapshot of the current condition of the building. Future conditions of the building, known as the FCI are also presented. The FCNI and FCI scores are primarily used to support asset management initiatives of federal, state, and local government facilities organizations.

Limiting Conditions

This report has been prepared for the exclusive and sole use of the Carson City . The report may not be relied upon by any other person or entity without the express written consent of Faithful+Gould.

Any reliance on this report by a third party, any decisions that a third party makes based on this report, or any use at all of this report by a third party is the responsibility of such third parties. Faithful+Gould accepts no responsibility for damages, if any, suffered by any third party as a result of decisions made, or actions taken, based on this report.

The assessment of the building/site components was performed using methods and procedures that are consistent with standard commercial and customary practice as outlined in ASTM Standard E 2018-015 for PCA assessments. As per this ASTM Standard, the assessment of the building/site components is based on a visual walk-through site visit, which captured the overall condition of the site at that specific point in time only.

No legal surveys, soil tests, environmental assessments, geotechnical assessments, detailed barrier-free compliance assessments, seismic assessments, detailed engineering calculations, or quantity surveying compilations have been made. No responsibility, therefore, is assumed concerning these matters. Faithful+Gould did not design or construct the building(s) or related structures and therefore will not be held responsible for the impact of any design or construction defects, whether or not described in this report. No guarantee or warranty, expressed or implied, with respect to the property, building components, building systems, property systems, or any other physical aspect of The Property is made.

The recommendations and our opinion of probable costs associated with these recommendations, as presented in this report, are based on walk-through non-invasive observations of the parts of the building which were readily accessible during our visual review. Conditions may exist that are not as per the general condition of the system being observed and reported in this document. Opinions of probable costs presented in this report are also based on information received during interviews with operations and maintenance staff. In certain instances, Faithful+Gould has been required to assume that the information provided is accurate and cannot be held responsible for incorrect information received during the interview process. Should additional information become

Page 4: Facility Condition Assessment For Carson City Library 900

5/13/2020

4 Carson City

available with respect to the condition of the building and/or site elements, Faithful+Gould requests that this information be brought to our attention so that we may reassess the conclusions presented herein.

The opinions of probable costs are intended for global budgeting purposes only. Faithful+Gould has no control over the cost of labor and materials, general contractor’s or any subcontractor’s method of determining prices, or competitive bidding and market conditions. The data in this report represent an opinion of probable cost of construction and is made on the basis of the experience, qualifications, and best judgment of the professional consultant familiar with the construction industry. Faithful+Gould cannot and does not guarantee that proposals, bids, or actual construction costs will not vary from this or subsequent Cost Estimates. The scope of work and the actual costs of the work recommended can only be determined after a detailed examination of the site element in question, understanding of the site restrictions, understanding of the effects on the ongoing operations of the site/building, definition of the construction schedule, and preparation of tender documents.

Project Details

On 10/8/2019, Robbie Dalziel of Faithful+Gould visited The Property to observe and document the condition of the building and site components. During our site visit, Faithful+Gould was assisted by Dan Stucky (City Engineer) who is associated with Carson City.

Building Details

Item Description

Project Name Library

Property Type LIB

Full Address

900 N. Roof Street

Carson City,

NV 89701

Onsite Date 10/8/2019

Historic District No

Historic Building No

Year Built 1975

Occupancy Status Occupied

Number of Stories 2

Gross Building Area (GSF) 31,068

Current Replacement Value (CRV) $7,280,000

CRV/GSF ($/Sq Ft) $234.32 / Sq Ft

Page 5: Facility Condition Assessment For Carson City Library 900

5/13/2020

5 Carson City

Building Description

Property Executive Summary The Carson City Library (“the Property”) is located at 900 N.

Roop Street, Carson City, Nevada 89706. The building

consists of a two-story structure, which has a total approximate

gross square footage of 31,068 square feet. The building is

understood to have originally been constructed circa 1975,

with a two-story extension added circa 1982.

In consideration of the age and condition of the structure, we

anticipate the following major replacement expenditures over

the 10-year study period: BUR roof coverings, aluminum

glazed exterior doors, aluminum window units, repainting of

exterior walls, fire alarm system, HVAC equipment (including

packaged rooftop units, MAU and exhaust fans), electrical

equipment (including switchboards, panelboards, and full

rewire), plumbing fixtures (including water closets, urinals,

lavatories, service sinks and drinking fountains), elevator cab,

interior finishes (including acoustic ceiling tiles, carpets, vinyl

composite tiles, resealing of concrete floors and repainting of

internal walls/ceilings) and site systems (including resurfacing

of asphalt roadway and crack fill, seal coat and restripe of

asphalt parking lot).

The following non-major replacement expenditures are

anticipated over the 10-year study period: roof hatches, and

electronic entrance sign.

It was reported that there is a drainage issue to the asphalt

paved roadway which runs along the north side of the building.

As there was no rainfall on the day of the assessment, there

was no visible evidence of this issue, however, the asphalt was

showing signs of deterioration and appeared to be older than

the asphalt paved parking lot to the south of the building.

Based on the reported issue and the observed condition,

resurfacing of the asphalt roadway is recommended.

An LED energy efficient upgrade is recommended for all

lighting that is scheduled to be replaced in the 10-year study

period. A like-for-like replacement for the lighting has been

included within the 10-year capital expenditure for this building,

with an independent Energy Conservation Measures (ECM)

Page 6: Facility Condition Assessment For Carson City Library 900

5/13/2020

6 Carson City

capital expenditure report providing the energy efficient lighting

upgrade costs.

It should also be noted, a liquid membrane was applied to the

lower roof section in 2014, however, there has been water

ingress issues since this was applied. Due to this issue, it

reported that the roof is scheduled to be recovered in 2021,

with the upper section of the roof scheduled to be recovered

in 2023 albeit no reported leak issues to this section noted.

Carson City provided Faithful+Gould with the roof quotes for

the work and these have both been included within the 10-year

capital expenditure.

The elevator at the building was installed in 1982 and therefore

has exceeded the typical estimated useful life (EUL) for this

type of elevator. It was however, reported that the current

elevator pump was upgraded in 2014 and therefore a full

elevator replacement is not anticipated during the 10-year

study period and only replacement of the elevator cab has

been included within the capital expenditure.

It was also reported, that there is ongoing plumbing issue with

the urinals to the restrooms. Although the urinals appeared to

be in fair condition aesthetically, replacement has been

recommended to resolve the issue.

Architectural Executive Summary The building foundations consist of a combination of cast-in-

place reinforced concrete strip footings and a cast-in-place

reinforced concrete slab on grade, which provide support to

what is assumed to be a combination of concrete and steel

structure above grade. The roof to the building is provided with

a low-sloped flat roof structure, which is assumed to be

constructed of structural steel beams supporting corrugated

metal roof deck with concrete topping and is clad with a

modified bitumen built-up roof (BUR) roof finish. The flat roof

is provided with an internal drainage system.

The exterior walls to the building consist of a combination of

stucco and composite wall panels. Fenestration to the building

consists of aluminum window units, with exterior doors across

the Property consisting of a combination of single leaf

aluminum glazed, single leaf hollow metal and double

aluminum bi-parting automatic sliding doors.

Page 7: Facility Condition Assessment For Carson City Library 900

5/13/2020

7 Carson City

Interior floor finishes to the building consist of a combination of

vinyl composite tile, broadloom carpet, carpet tile, terrazzo tile,

ceramic tile, polished concrete and exposed concrete. Wall

finishes to the building consist of a combination of painted

gypsum wall board and ceramic tile. Ceiling finishes to the

building consist of a combination of suspend acoustical ceiling

tiles and painted gypsum wall board. Internal doors consist of

wood throughout.

Mechanical Executive Summary Heating and cooling to the building is provided via numerous

packaged rooftop air conditioning with heat units to the original

lower section of the building and one multi-zone packaged air

conditioning with heat unit to the extended upper section of the

building. The packaged units circulate the warm and cool air

around the building through the internal ducting system.

Domestic hot water to the building is provided via one gas-fired

hot water heater which has a capacity of 40-gallons.

Ventilation to the building is provided via one rooftop make-up

air unit (MAU) with an estimated capacity of 2,000-CFM and

three centrifugal roof exhaust fans with estimated capacities of

500-CFM.

The restrooms contain a combination of vitreous china floor

and wall mounted water closets, wall hung and stall type

urinals and vanity top and wall hung lavatories. Additional

plumbing fixtures to the building include multiple floor mounted

service sinks and one wall mounted drinking fountain.

Additional mechanical equipment to the building includes one

hydraulic passenger elevator, which has a capacity of 2,500-

lbs and serves both levels to the extended side of the building.

Electrical Executive Summary The building’s electrical equipment consists of two Main

Distribution Panel (MDP) switchboards, both rated at 120/208-

volts, with amperages of 800-amps and 400-amps. The

electrical system is also provided with multiple sub-panels

rated at 120/208-volts, with amperages ranging from 100-

amps to 200-amps.

Page 8: Facility Condition Assessment For Carson City Library 900

5/13/2020

8 Carson City

Lighting at the building consists of internal fluorescent light

fixtures throughout and external LED wall pack light fixtures

running the building perimeter. The branch wiring including

receptacles, switches and other devices appear to be standard

non-décor commercial grade.

Site Executive Summary Immediate site systems at the Property consist of one

aluminum flag pole, multiple site lighting poles with LED light

fittings, an asphalt paved parking lot, asphalt paved roadway,

cast-in-place concrete sidewalks, one cast-in-place concrete

access ramp with metal railing to the east of the building and

one electronic entrance sign located to the site entrance.

Page 9: Facility Condition Assessment For Carson City Library 900

5/13/2020

9 Carson City

Summary of Findings

This report represents summary-level findings for the Facility Condition Assessment. The deficiencies identified in

this assessment can be combined to develop an overall Long-Term Capital Needs Plan that can be the basis for a

facility wide capital improvement funding strategy. Key findings from the Assessment include:

Key Findings Metric

Current Year Facility Condition Needs Index 5.43 %

Immediate Capital Needs (Year 1)

(included in FCNI) $395,650

Future Capital Needs (FCI) (Year 2 to Year 10) $1,563,736

Building Expenditure Summary

The building expenditure summary section provides an executive overview of the findings from the assessment.

The chart below provides a summary of yearly anticipated expenditures over the study period for the Library

building. In addition, we have scheduled key findings highlighting items greater than $5,000 and their anticipated

failure year. Further details of these expenditures are included within each respective report section and within

the expenditure forecast, in Appendix A of this report. The results illustrate a total anticipated expenditure over

the study period of approximately $1,959,386.

Page 10: Facility Condition Assessment For Carson City Library 900

5/13/2020

10 Carson City

Key Findings

B Shell: Replace Double Bi-Parting Automated Sliding Doors at an estimated cost of $16,269 in year

2021

B Shell: Replace Single Aluminum Glazed Doors at an estimated cost of $12,438 in year 2021

B Shell: Replace Galvanized Steel Hatch at an estimated cost of $5,408 in year 2021

B Shell: Replace Aluminum Window Units - Fixed or Single Hung at an estimated cost of $201,873 in

year 2021

B Shell: Replace BUR (Built-up Roofing) Covering (Lower Section) at an estimated cost of $225,056 in

year 2021

B Shell: Replace BUR (Built-up Roofing) Covering (Upper Section) at an estimated cost of $57,000 in

year 2023

B Shell: Repaint Exterior Wall Surfaces at an estimated cost of $88,500 in year 2024

C Interiors: Replace Broadloom Standard without Padding at an estimated cost of $12,442 in year 2021

C Interiors: Replace Vinyl Composite Tile (VCT) at an estimated cost of $8,363 in year 2021

C Interiors: Replace Acoustic Ceiling System - Standard at an estimated cost of $170,484 in year 2022

C Interiors: Replace Painted Finish - Standard at an estimated cost of $185,000 in year 2026

C Interiors: Replace Seal Floor Coating at an estimated cost of $96,807 in year 2026

C Interiors: Replace Carpet Tiles - Standard at an estimated cost of $24,919 in year 2027

C Interiors: Replace Monument Sign - Electronic at an estimated cost of $9,000 in year 2029

D Services: Replace Multi-zone Package A/C Unit at an estimated cost of $233,440 in year 2020

D Services: Replace Packaged Rooftop A/C With Heat, Under 20 Tons - AC-1 at an estimated cost of

$15,773 in year 2020

D Services: Replace Packaged Rooftop A/C With Heat, Under 20 Tons - AC-5 at an estimated cost of

$15,773 in year 2020

D Services: Replace Packaged Rooftop A/C With Heat, Under 20 Tons - AC-2 at an estimated cost of

$15,773 in year 2020

D Services: Replace Packaged Rooftop A/C With Heat, Under 20 Tons - AC-6 at an estimated cost of

$15,773 in year 2020

D Services: Replace Packaged Rooftop A/C With Heat, Under 20 Tons - AC-8 at an estimated cost of

$15,773 in year 2020

D Services: Replace Packaged Rooftop A/C With Heat, Under 20 Tons - AC-7 at an estimated cost of

$15,773 in year 2020

D Services: Replace Packaged Rooftop A/C With Heat, Under 20 Tons - AC-4 at an estimated cost of

$15,773 in year 2020

D Services: Replace Packaged Rooftop A/C With Heat, Under 20 Tons - AC-9 at an estimated cost of

Page 11: Facility Condition Assessment For Carson City Library 900

5/13/2020

11 Carson City

$15,773 in year 2020

D Services: Replace Make-up Air Unit at an estimated cost of $8,050 in year 2020

D Services: Replace Service Sink Floor Mounted at an estimated cost of $7,245 in year 2021

D Services: Replace Wall Mounted Water Closets at an estimated cost of $6,440 in year 2021

D Services: Replace Floor Mounted Water Closets at an estimated cost of $14,490 in year 2021

D Services: Replace Vanity Top Lavatories at an estimated cost of $7,547 in year 2021

D Services: Replace Elevator Cab Finishes at an estimated cost of $28,842 in year 2022

D Services: Replace Switchboard - 120/208volts, 400 to 2000amp at an estimated cost of $35,328 in

year 2022

D Services: Replace Switchboard - 120/208volts, 400 to 2000amp at an estimated cost of $17,664 in

year 2022

D Services: Replace Panelboard - 120/208volts, 400 to 1200amp at an estimated cost of $11,776 in

year 2022

D Services: Replace Wiring Systems (Inc. Receptacles & Switches) at an estimated cost of $281,538 in

year 2022

D Services: Replace Packaged Rooftop A/C With Heat, Under 20 Tons - AC-3 at an estimated cost of

$15,773 in year 2029

G Building Sitework: Replace Asphalt Roadway (Full Depth) at an estimated cost of $26,027 in year

2020

G Building Sitework: Crack Repair, Seal Coating and Restriping to Parking Lots at an estimated cost of

$5,318 in year 2025

1. All costs presented in present day values

2. Costs represent total anticipated values over the 10-year study period

3. The Key Findings above represent expenditures of $5,000 or above only. For a full list of expenditures, please refer to Appendix A of this report

Page 12: Facility Condition Assessment For Carson City Library 900

5/13/2020

12 Carson City

Distribution of Immediate (Year 1) Needs by Building System

Building System Estimated Cost Percentage of Total Cost

Air Distribution Systems $8,050 2.0%

Bases and Sub-Bases $26,027 6.6%

Exhaust Ventilation Systems $1,949 0.5%

Package Units $359,624 90.9%

Total $395,650 100%

Page 13: Facility Condition Assessment For Carson City Library 900

5/13/2020

13 Carson City

Distribution of Future (Year 2 – Year 10) Needs by Building System

Building System Estimated Cost Percentage of Total Cost

B20 Exterior Enclosure $319,080 20.4%

B30 Roofing $287,464 18.4%

C10 Interior Construction $9,000 0.6%

C30 Interior Finishes $498,015 31.9%

D10 Conveying Systems $28,842 1.8%

D20 Plumbing $48,981 3.1%

D30 HVAC $15,773 1.0%

D50 Electrical Systems $351,263 22.5%

G20 Site Improvements $5,318 0.3%

Total $1,563,736 100%

Page 14: Facility Condition Assessment For Carson City Library 900

5/13/2020

14 Carson City

Energy Conservation Measures

Energy Conservation opportunities have been identified through an assessment of the systems and equipment during the Facility Condition Assessment (FCA) and provide simple payback in years and the annual cost avoidance for each ECM. The physical assessment consisted of a limited, non-intrusive visual assessment of the building and its components. It was expected that generally all aspects of the buildings were made assessable, including provision to gain access to the roof, interior areas, mechanical, electrical rooms and common areas. Confined spaces or hazardous areas were not expected to be assessed. Low-sloped roofs with safe access were accessed; however, high-sloped, inaccessible roofs or roofs that were considered unsafe without the use of personal protective equipment were not accessed. The assessment techniques followed the ASTM standards for property condition assessments (ASTM E2018-15) and consisted of a visual assessment of those components that are readily accessible and visible. The building assessment was limited to those components that affected energy usage, which typically include:

• Building Envelope, material description, construction type, windows and doors

• Lighting, type and approximate coverage by type

• Heating, type and area serviced

• Cooling, type and area serviced

• Ventilation, type

• Domestic Hot Water, method of heating, capacity, storage

• Miscellaneous Equipment, motors, solar panels, pools etc. We have focused our assessment of energy conservation opportunities on measures that have realistic payback periods of 10 years or less. Our experience tells us that major architectural and mechanical system upgrades are almost never justified based on energy savings alone. We recommend specifying suitable high efficiency replacements for systems that are at the end of their useful life in an effort to lower long term cost of ownership. Some typical examples of energy conservation opportunities that are justified based on energy savings alone include, but are not limited to the following:

• Lighting lamp and ballast retrofits

• Variable Frequency Drive (VFD) upgrades on motors with variable loads greater than 20 horsepower

• HVAC system retrocommissioning and/or controls upgrades

• Instantaneous domestic water heaters

• Heat recovery on 100% fresh air HVAC systems

• Economizer / free cooling upgrades on suitable HVAC systems

• Attic insulation upgrades

Projected Expenditures

Energy Conservation Measures (ECM) are included in a separate report.

Page 15: Facility Condition Assessment For Carson City Library 900

5/13/2020

15 Carson City

Facility Condition Needs Index

In this report we have calculated the Current Year Facility Condition Needs Index (FCNI) for the facility;

illustrating the likely condition of the systems, equipment and building needs should the required funding not be

expended over the cost study period. The FCNI is used in Facilities Management to provide a benchmark to

compare the relative condition and needs of a group of facilities. The FCNI is primarily used to support asset

management initiatives of federal, state, and local government facilities organizations.

The FCNI is the ratio of accumulated Deferred Maintenance (DM) (total sum of immediate required and

recommended works) to the Current Replacement Value (CRV) for a constructed asset. Calculated by dividing

DM and Needs by CRV. The range is from zero for a newly-constructed building, to 100% for a constructed asset

with a Deferred Maintenance value equal to its CRV. Acceptable ranges vary by Building Type, but as a general

guideline, the FCNI scoring system is as follows:

If the FCNI rating is 60% or greater then replacement of the asset/building should be considered instead of renewal.

The chart below indicates the current FCNI ratio of the Library building.

Library, FCNI: 5.43%

Condition Definition Percentage Value

GOOD In a new or well-maintained condition with no visual evidence of wear,

soiling or other deficiencies. 0% to 5%

FAIR Subject to wear and soiling but is still in a serviceable and functioning

condition. 5% to 10%

POOR Subjected to hard or long-term wear. Nearing the end of its useful or

serviceable life. Greater than 10%

V-POOR Subjected to hard or long-term wear. Has reached the end of its

useful or serviceable life. Renewal now necessary. Greater than 60%

Page 16: Facility Condition Assessment For Carson City Library 900

5/13/2020

16 Carson City

The chart below indicates the effects of the FCNI ratio per year, assuming the required funds and expenditures

ARE made to address the identified actions each year.

The Chart below indicates the cumulative effects of the FCI ratio over the study period assuming the required

funds and expenditures are NOT provided to address the identified works and deferred maintenance each year.

Page 17: Facility Condition Assessment For Carson City Library 900

5/13/2020

17 Carson City

Needs Sorted by Prioritization of Work

Faithful+Gould has prioritized the identified work in order to assist with analyzing the deficiencies found during the

assessment. The following Priorities are shown below:

The chart below illustrates the breakdown of expenditure according the priority coding providing an opportunity to

strategically plan and effectively direct funding to the highest priority.

Building System Priority 1 Priority 2 Priority 3 Total

B Shell $0 $0 $606,544 $606,544

C Interiors $0 $0 $507,015 $507,015

D Services $4,957 $369,623 $439,902 $814,482

G Building Sitework $0 $26,027 $5,318 $31,345

Totals $4,957 $395,650 $1,558,779 $1,959,386

• Systems requiring immediate action that have failed, compromises staff or public safety or requires to be upgraded to comply with current codes and accessibility

Priority 1 Currently Critical

• A system or component is nearing end of useful life, if not addressed will cause additional deterioration and added repair costs

Priority 2 Potentially Critical:

• Lifecycle replacements neccessary but not critical or mid-term future replacements to maintain the integrity of the facility or component

Priority 3Necessary / Not Critical:

Page 18: Facility Condition Assessment For Carson City Library 900

5/13/2020

18 Carson City

Needs Sorted by Plan Type

Faithful+Gould has prioritized the identified work according to the Plan Type or deficiency categories in order to

assist with analyzing the deficiencies found during the assessment. The following Plan Types are shown below:

The chart below illustrates the breakdown of expenditure according to the Plan Type or deficiency categories

providing an opportunity to strategically plan and effectively direct funding.

Building System Total Cost

Deferred Maintenance $395,650

Capital Renewal $1,188,111

Routine Maintenance $375,625

Total $1,959,386

Page 19: Facility Condition Assessment For Carson City Library 900

5/13/2020

19 Carson City

Appendices

Appendix A: Capital Expenditures

Appendix B: Photographic Record

Appendix C: Document review and Warranty Information

Appendix D: Equipment Tables

Appendix E: Glossary of Terms

Page 20: Facility Condition Assessment For Carson City Library 900

5/13/2020

20 Carson City

Appendix A

Capital Expenditures

Page 21: Facility Condition Assessment For Carson City Library 900

LibraryGSF: 20,800

Year Built: 1975

Replacement Cost: $7,280,000

Materials

Year $ ID CSI Type Name Description Qty Units Cost Assessed Cost

Estimate $

2020 $395,650 328114 D3040 Deferred Maintenance

Replace Make-up Air Unit 2000 CFM $4.03 $8,050 $8,050

328116 D3040 Deferred Maintenance

Replace Centrifugal Roof Exhaust Fan System 500 CFM $1.30 $650 $650

328113 D3040 Deferred Maintenance

Replace Centrifugal Roof Exhaust Fan System 500 CFM $1.30 $650 $650

328115 D3040 Deferred Maintenance

Replace Centrifugal Roof Exhaust Fan System 500 CFM $1.30 $650 $650

328117 D3050 Deferred Maintenance

Replace Packaged Rooftop A/C With Heat, Under 20 Tons - AC-6

5 TON $3,154.60 $15,773 $15,773

328122 D3050 Deferred Maintenance

Replace Packaged Rooftop A/C With Heat, Under 20 Tons - AC-8

5 TON $3,154.60 $15,773 $15,773

328125 D3050 Deferred Maintenance

Replace Packaged Rooftop A/C With Heat, Under 20 Tons - AC-7

5 TON $3,154.60 $15,773 $15,773

328118 D3050 Deferred Maintenance

Replace Packaged Rooftop A/C With Heat, Under 20 Tons - AC-4

5 TON $3,154.60 $15,773 $15,773

328119 D3050 Deferred Maintenance

Replace Packaged Rooftop A/C With Heat, Under 20 Tons - AC-9

5 TON $3,154.60 $15,773 $15,773

328120 D3050 Deferred Maintenance

Replace Multi-zone Package A/C Unit 30 TON $7,781.34 $233,440 $233,440

328121 D3050 Deferred Maintenance

Replace Packaged Rooftop A/C With Heat, Under 20 Tons - AC-1

5 TON $3,154.60 $15,773 $15,773

328124 D3050 Deferred Maintenance

Replace Packaged Rooftop A/C With Heat, Under 20 Tons - AC-5

5 TON $3,154.60 $15,773 $15,773

328123 D3050 Deferred Maintenance

Replace Packaged Rooftop A/C With Heat, Under 20 Tons - AC-2

5 TON $3,154.60 $15,773 $15,773

5/13/2020 8:34:29 PM Page 1 of 3FGould FCA Reports

Deficiency Report

Page 22: Facility Condition Assessment For Carson City Library 900

Materials

Year $ ID CSI Type Name Description Qty Units Cost Assessed Cost

Estimate $

2020 $395,650 328133 G2010 Deferred Maintenance

Replace Asphalt Roadway (Full Depth) 384 SY $67.78 $26,027 $26,027

2021 $530,829 328091 B2020 Capital Renewal Replace Aluminum Window Units - Fixed or Single Hung

2550 SF $79.17 $201,873 $201,873

328092 B2030 Capital Renewal Replace Double Bi-Parting Automated Sliding Doors

1 EACH $16,268.69 $16,269 $16,269

328093 B2030 Capital Renewal Replace Single Aluminum Glazed Doors 2 EACH $6,219.06 $12,438 $12,438

328094 B3010 Capital Renewal Replace BUR (Built-up Roofing) Covering (Lower Section)

20800 SF $10.82 $225,056 $225,056

328096 B3020 Capital Renewal Replace Galvanized Steel Hatch 2 EACH $2,703.94 $5,408 $5,408

328099 C3020 Capital Renewal Replace Broadloom Standard without Padding 349 SY $35.65 $12,442 $12,442

328100 C3020 Capital Renewal Replace Vinyl Composite Tile (VCT) 1010 SF $8.28 $8,363 $8,363

328106 D2010 Capital Renewal Replace Service Sink Floor Mounted 2 EACH $3,622.50 $7,245 $7,245

328107 D2010 Capital Renewal Replace Vanity Top Lavatories 5 EACH $1,509.38 $7,547 $7,547

328109 D2010 Capital Renewal Replace Wall Mounted Standard Drinking Fountain (Dual/Bi-Level)

1 EACH $4,226.25 $4,226 $4,226

328110 D2010 Capital Renewal Replace Stall Type Urinals 1 EACH $3,964.27 $3,964 $3,964

328108 D2010 Capital Renewal Replace Wall Hung Urinals 1 EACH $2,597.29 $2,597 $2,597

328112 D2010 Capital Renewal Replace Wall Mounted Water Closets 2 EACH $3,220.00 $6,440 $6,440

328111 D2010 Capital Renewal Replace Floor Mounted Water Closets 6 EACH $2,415.00 $14,490 $14,490

328105 D2010 Capital Renewal Replace Wall Hung Lavatories 1 EACH $2,471.10 $2,471 $2,471

2022 $545,632 328103 C3030 Capital Renewal Replace Acoustic Ceiling System - Standard 29068 SF $5.87 $170,484 $170,484

328104 D1010 Capital Renewal Replace Elevator Cab Finishes 1 EACH $28,842.00 $28,842 $28,842

328129 D5010 Capital Renewal Replace Panelboard - 120/208volts, 400 to 1200amp

400 AMP $29.44 $11,776 $11,776

328127 D5010 Capital Renewal Replace Switchboard - 120/208volts, 400 to 2000amp

800 AMP $44.16 $35,328 $35,328

5/13/2020 8:34:29 PM Page 2 of 3FGould FCA Reports

Deficiency Report

Page 23: Facility Condition Assessment For Carson City Library 900

Materials

Year $ ID CSI Type Name Description Qty Units Cost Assessed Cost

Estimate $

2022 $545,632 328128 D5010 Capital Renewal Replace Switchboard - 120/208volts, 400 to 2000amp

400 AMP $44.16 $17,664 $17,664

328130 D5020 Capital Renewal Replace Wiring Systems (Inc. Receptacles & Switches)

31068 SF $9.06 $281,538 $281,538

2023 $57,000 328095 B3010 Capital Renewal Replace BUR (Built-up Roofing) Covering (Upper Section)

5268 SF $10.82 $57,000 $57,000

2024 $88,500 328090 B2010 Routine Maintenance

Repaint Exterior Wall Surfaces 17700 SF $5.00 $88,500 $88,500

2025 $5,318 328134 G2020 Routine Maintenance

Crack Repair, Seal Coating and Restriping to Parking Lots

3039 SY $1.75 $5,318 $5,318

2026 $281,807 328098 C3010 Routine Maintenance

Replace Painted Finish - Standard 37000 SF $5.00 $185,000 $185,000

328102 C3020 Routine Maintenance

Replace Seal Floor Coating 23000 SF $4.21 $96,807 $96,807

2027 $24,919 328101 C3020 Capital Renewal Replace Carpet Tiles - Standard 320 SY $77.87 $24,919 $24,919

2029 $29,730 328097 C1030 Capital Renewal Replace Monument Sign - Electronic 1 EACH $9,000.00 $9,000 $9,000

328126 D3050 Capital Renewal Replace Packaged Rooftop A/C With Heat, Under 20 Tons - AC-3

5 TON $3,154.60 $15,773 $15,773

328131 D5030 Capital Renewal Replace Fire Alarm Control Panel (FACP) - Up to 10 Zone

1 EACH $4,626.74 $4,627 $4,627

328132 D5030 Capital Renewal Replace Manual Pull Stations 1 EACH $330.18 $330 $330

Total Total: $1,959,386

5/13/2020 8:34:29 PM Page 3 of 3FGould FCA Reports

Deficiency Report

Page 24: Facility Condition Assessment For Carson City Library 900

5/13/2020

21 Carson City

Appendix B

Photographic Record

Page 25: Facility Condition Assessment For Carson City Library 900

5/13/2020

22 Carson City

View of Slab-on-Grade Reinforced Concrete

B1014 Ramp(s) :- View of Ramp(s) - Concrete Construction

View of Cladding - Composite Wall Panels

B2011 Exterior Wall Construction :- View of Stucco over CMU Walls

Page 26: Facility Condition Assessment For Carson City Library 900

5/13/2020

23 Carson City

View of Metal Capping

B2021 Windows :- View of Aluminum Window Units - Fixed or Single

Hung

View of Double Bi-Parting Automated Sliding Doors

B2031 Glazed Doors & Entrances :- View of Single Aluminum Glazed Doors

Page 27: Facility Condition Assessment For Carson City Library 900

5/13/2020

24 Carson City

View of Single HM Doors

B3011 Roof Finishes :- View of BUR (Built-up Roofing) Covering (Lower

Section)

View of BUR (Built-up Roofing) Covering (Upper Section)

B3022 Roof Hatches :- View of Galvanized Steel Hatch

Page 28: Facility Condition Assessment For Carson City Library 900

5/13/2020

25 Carson City

View of Toilet Partition

C1017 Interior Windows & Storefronts :- View of Internal Windows

View of Interior Double Wood Door(s)

C1021 Interior Doors :- View of Interior Single Wood Door(s)

Page 29: Facility Condition Assessment For Carson City Library 900

5/13/2020

26 Carson City

View of Monument Sign – Electronic

C2011 Regular Stairs :- View of Regular Stairs - Steel Construction

View of Ceramic Wall Tiles

C3012 Wall Finishes to Interior Walls :- View of Painted Finish - Standard

Page 30: Facility Condition Assessment For Carson City Library 900

5/13/2020

27 Carson City

View of Seal Floor Coating

C3024 Flooring :- View of Ceramic Tile

View of Terrazzo Tile

C3024 Flooring :- View of Vinyl Composite Tile (VCT)

Page 31: Facility Condition Assessment For Carson City Library 900

5/13/2020

28 Carson City

View of Broadloom Standard without Padding

C3025 Carpeting :- View of Carpet Tiles - Standard

View of Gypsum Wall Board Ceilings

C3032 Suspended Ceilings :- View of Acoustic Ceiling System - Standard

Page 32: Facility Condition Assessment For Carson City Library 900

5/13/2020

29 Carson City

View of Elevator Cab Finishes

D1011 Passenger Elevators :- View of Hydraulic Elevator - Standard

View of Floor Mounted Water Closets

D2011 Water Closets :- View of Wall Mounted Water Closets

Page 33: Facility Condition Assessment For Carson City Library 900

5/13/2020

30 Carson City

View of Stall Type Urinals

D2012 Urinals :- View of Wall Hung Urinals

View of Vanity Top Lavatories

D2013 Lavatories :- View of Wall Hung Lavatories

Page 34: Facility Condition Assessment For Carson City Library 900

5/13/2020

31 Carson City

View of Service Sink Floor Mounted

D2018 Drinking Fountains and Coolers :- View of Wall Mounted Standard Drinking Fountain

(Dual/Bi-Level)

View of Domestic Hot Water Heater – Gas

D3041 Air Distribution Systems :- View of Make-up Air Unit

Page 35: Facility Condition Assessment For Carson City Library 900

5/13/2020

32 Carson City

View of Centrifugal Roof Exhaust Fan System

D3042 Exhaust Ventilation Systems :- View of Centrifugal Roof Exhaust Fan System

View of Centrifugal Roof Exhaust Fan System

D3052 Package Units :- View of Multi-zone Package A/C Unit

Page 36: Facility Condition Assessment For Carson City Library 900

5/13/2020

33 Carson City

View of Packaged Rooftop A/C With Heat, Under 20 Tons - AC-1

D3052 Package Units :- View of Packaged Rooftop A/C With Heat, Under 20

Tons - AC-2

View of Packaged Rooftop A/C With Heat, Under 20 Tons - AC-3

D3052 Package Units :- View of Packaged Rooftop A/C With Heat, Under 20

Tons - AC-4

Page 37: Facility Condition Assessment For Carson City Library 900

5/13/2020

34 Carson City

View of Packaged Rooftop A/C With Heat, Under 20 Tons - AC-5

D3052 Package Units :- View of Packaged Rooftop A/C With Heat, Under 20

Tons - AC-6

View of Packaged Rooftop A/C With Heat, Under 20 Tons - AC-7

D3052 Package Units :- View of Packaged Rooftop A/C With Heat, Under 20

Tons - AC-8

Page 38: Facility Condition Assessment For Carson City Library 900

5/13/2020

35 Carson City

View of Packaged Rooftop A/C With Heat, Under 20 Tons - AC-9

D5012 Low Tension Service & Dist :- View of Panelboard - 120/208volts, 400 to 1200amp

View of Switchboard - 120/208volts, 400 to 2000amp

D5012 Low Tension Service & Dist :- View of Switchboard - 120/208volts, 400 to

2000amp

Page 39: Facility Condition Assessment For Carson City Library 900

5/13/2020

36 Carson City

View of Exterior LED Wall Pack Light Fixtures

D5022 Lighting Equipment :- View of Interior Light Fixtures - LED

View of Fire Alarm Control Panel (FACP) - Up to 10 Zone

G2011 Bases and Sub-Bases :- View of Asphalt Roadway (Full Depth)

Page 40: Facility Condition Assessment For Carson City Library 900

5/13/2020

37 Carson City

View of Asphalt Parking (Full Depth)

G2031 Paving & Surfacing :- View of Concrete 3' - 4' Wide

View of Railings

G2048 Flagpoles :- View of Flag Pole(s), Aluminum - 70' High

Page 41: Facility Condition Assessment For Carson City Library 900

5/13/2020

38 Carson City

View of 10' High Site Lighting

G4021 Fixtures & Transformers :- View of 20' High Site Lighting

Page 42: Facility Condition Assessment For Carson City Library 900

5/13/2020

39 Carson City

Appendix C

Document Review and Warranty Information

Page 43: Facility Condition Assessment For Carson City Library 900

5/13/2020

40 Carson City

The following documents were reviewed as part of the facility condition assessment of the Library

facility:

No documents were reviewed as part of this assessment.

Page 44: Facility Condition Assessment For Carson City Library 900

5/13/2020

41 Carson City

Appendix D

Equipment Tables

Page 45: Facility Condition Assessment For Carson City Library 900

5/13/2020

42 Carson City

Table D10 Summary of Elevators and Lifts

Equipment Type

Manufacturer

Model No.

Serial No.

Tag Capacity (Pounds

)

Speed (FPM)

No. Of Landin

gs

Year of Install

Hydraulic DELTA Unknown C3481N8151

001085 2,500-lbs 115 2

1982

Table D20 Summary of Domestic Water Heating Equipment

Location Equipment Type

Manufacturer

Model No.

Serial No.

Tag Capacity/ Rating

Fuel Type

Year

Interior Domestic

Water Heater Bradford

White RG240T

6N

PM4062543

0 001049

40 Gallons

Natural Gas

2017

Table D30 Summary of HVAC Equipment

Location Equipment Type

Manufacturer

Model No.

Serial No.

Tag Capacity/ Rating

Fuel Type

Year

Interior Exhaust Fan Unknown Unknown Unknown Unknown 500-CFM

(Estimated) Electric 1981

Interior Make-up air

unit E-Z-Aire Unknown Unknown Unknown

2,000-CFM (Estimated)

Natural Gas and Electric

1975

Interior Exhaust Fan Unknown Unknown Unknown Unknown 500-CFM

(Estimated) Electric 1981

Interior Exhaust Fan Unknown Unknown Unknown Unknown 500-CFM

(Estimated) Electric 1981

Interior

Packaged Rooftop Unit Heating And

Cooling

Trane Unknown Unknown AC-9 5-Ton

(Estimated)

Natural Gas and Electric

1995

Interior

Packaged Rooftop Unit Heating And

Cooling

Trane Unknown Unknown AC-1 5-Ton

(Estimated)

Natural Gas and Electric

1995

Interior

Packaged Rooftop Unit Heating And

Cooling

Trane Unknown Unknown AC-7 5-Ton

(Estimated)

Natural Gas and Electric

1995

Interior

Packaged Rooftop Unit Heating And

Cooling

Trane Unknown Unknown AC-4 5-Ton

(Estimated)

Natural Gas and Electric

1995

Page 46: Facility Condition Assessment For Carson City Library 900

5/13/2020

43 Carson City

Interior

Packaged Rooftop Unit Heating And

Cooling

Trane Unknown Unknown AC-6 5-Ton

(Estimated)

Natural Gas and Electric

1995

Interior

Packaged Rooftop Unit Heating And

Cooling

Trane Unknown Unknown AC-8 5-Ton

(Estimated)

Natural Gas and Electric

1995

Interior

Packaged Rooftop Unit Heating And

Cooling

Trane Unknown Unknown AC-5 5-Ton

(Estimated)

Natural Gas and Electric

1995

Interior

Packaged Rooftop Unit Heating And

Cooling

Lennox DMS4-

185-350

5181K83137D

001047 30-Ton

Natural Gas and Electric

1981

Interior

Packaged Rooftop Unit Heating And

Cooling

Trane Unknown Unknown AC-2 5-Ton

(Estimated)

Natural Gas and Electric

1995

Interior

Packaged Rooftop Unit Heating And

Cooling

Carrier 48TCEA06A2A5A0

A0A0

1609G10312

AC-3 5-Ton

Natural Gas and Electric

2009

Page 47: Facility Condition Assessment For Carson City Library 900

5/13/2020

44 Carson City

Appendix E

Glossary of Terms

Page 48: Facility Condition Assessment For Carson City Library 900

5/13/2020

45 Carson City

Acronyms & Glossary of Terms

ABC Aggregate Base Course

BUR Built-Up Roof

CIP Cast-In-Place

CMU Concrete Masonry Unit

EIFS Exterior Insulation and Finish System

EPDM Ethylene Propylene Diene Monomer

HM Hollow Metal Doors

MH Man Holes

SC Solid Core Doors

TPO Thermoplastic Polyolefin

AHU Main Air Handling Units

EF Exhaust Fan

EMC Electrical Metallic Conduit

EMT Electrical Metallic Tubing

FACP Fire Alarm Control Panel

FCC Fire Command Center

FCU Fan Coil Unit

FSS Fuel Supply System

MDP Main Distribution Panel

NAC Notification Appliance Circuit

RTU Roof Top Unit

SES Service Entrance Switchboards

VAV Variable Air Volume

VFD Variable Frequency Drives

CRV Current Replacement Value

DM Deferred Maintenance

EOL End of Life

EUL Estimated Useful Life

FCI Facility Condition Index

HVAC Heating Ventilating and Air Conditioning

RUL Recommended Useful Life

AMP Amperage

BTU/HR British Thermal Units per Hour

FPM Feet per Minute (Elevator Speed)

GPF Gallons Per-Flush

HID High-Intensity Discharge

HP Horse Power

KVA Kilovolt-Ampere

kW Kilowatt

PSF Pounds-Per-Square-Foot

PSI Pounds-Per-Square-Inch

RO Reverse Osmosis

SF Square Foot

SY Square Yards

NEMA National Electrical Manufactures Association

NFPA National Fire Protection Association

Page 49: Facility Condition Assessment For Carson City Library 900

5/13/2020

46 Carson City

Acronyms & Glossary of Terms

BTU – British Thermal Unit; the energy required to raise the temperature of one pound of water by one degree.

Building Envelope – The enclosure of the building that protects the building’s interior from the outside elements,

namely the exterior walls, roof, and soffit areas.

Building Systems – Interacting of independent components or assemblies, which from single integrated units,

that comprise a building and its site work, such as, pavement and flatwork, structural frame, roofing, exterior

walls, plumbing, HVAC, electrical, etc.

Caulking – Soft, putty-like material used to fill joints, seams, and cracks.

Codes – See building codes.

Component – A fully functional portion of a building system, piece of equipment, or building element.

Deferred Maintenance – Physical deficiencies that cannot be remedied with routine maintenance, normal

operating maintenance, etc., excluding de minimis conditions that generally do not present a material physical

de3ficiency to the subject property.

Expected Useful Life (EUL) – the average amount of time in years that an item, component of system is

estimated to function when installed new and assuming routine maintenance is practiced.

Facility – All of any portion of buildings, structures, site improvements, complexes, equipment, roads, walks,

passageways, parking lots, or other real or personal property located on site.

Flashing – A think, impervious sheet of material placed in construction to prevent water penetration or to direct

the flow of water. Flashing is used especially at roof hips and valleys, roof penetrations, joints between a roof and

a vertical wall, and in masonry walls to direct the flow of water and moisture.

Remaining Useful Life (RUL) – A subjective estimate based upon observations, or average estimates of similar

items, components, or systems, or a combination thereof, of a number of remaining years that an item,

component, or system is established to be able to function in accordance with its intended purpose before

warranting replacement. Such period of time is affected by the initial quality of an item, component, or system,

the quality of the initial installation, the quality and amount of preventative maintenance exercised, climatic

conditions, extend of use, etc.

Structural Frame – the components or building systems that support the building’s non-variable forces or

weights (dead loads) and variable forces or weights (live loads).

Thermal Resistance (R) – A unit used to measure a material’s resistance to heat transfer. The formula for

thermal resistance is: R=Thickness (in inches)/K.

Warranty – Legally enforceable assurance of quality or performance of a product or work, or of the duration of

satisfactory performance. Warranty guarantee and guaranty are substantially identical in meaning; nevertheless,

confusion frequently arises from supposed distinctions attributed to guarantee (or guaranty) being exclusively

indicative of duration of satisfactory performance or of a legally enforceable assurance furnished by a

manufacturer or other third party. The uniform commercial code provisions on sales (effective in all states except

Louisiana) use warranty but recognize the continuation of the use of guarantee and guaranty.

Page 50: Facility Condition Assessment For Carson City Library 900