Board of Water Supply Beretania Complex Redevelopment FACT SHEET Project Overview The Honolulu Board of Water Supply (BWS) will be issuing a Request for Proposal(s) to redevelop a portion of its Beretania Complex. The purpose of this action is to provide a revenue stream for BWS. 9 Project area will be leased to third party. 9 Lessee will implement the redevelopment. 9 Revenue stream to help offset a portion of operating and capital improvement costs for BWS. South Beretania Street Lauhala Street Street Lusitana Alapai Street Lisbon Street Project Area 128,100 sf TMK (1) 2-1-036:001 and 005 (por) Existing Public Service Building Beretania Complex Existing Engineering Building Existing Pump Station Site Map Zoning: A2, Medium Density Apartment Source: Google Earth Beretania Complex Redevelopment Process Develop 3 Alternative Concept Plans Identify Allowable/ Appropriate Uses A2 Zoning • Adjacent Land Use Compatibility • Market Studies Select Lessee/Developer and Enter Lease Agreement Evaluate Developer Proposals Issue Request for Proposals (RFP) Lessee Obtain Land Use Entitlements Developer/ Lessee Finalize Plans for Site Lessee Redevelops Site Environmental Review Process (Evaluate 3 Alternatives)

Upload: truongngoc

Post on 29-Apr-2019

216 views

Category:

Documents


0 download

TRANSCRIPT

Board of Water SupplyBeretania Complex Redevelopment

F A C T S H E E T

Project OverviewThe Honolulu Board of Water Supply (BWS) will be issuing a Request for Proposal(s) to redevelop a portion of its Beretania Complex. The purpose of this action is to provide a revenue stream for BWS.

99 Project area will be leased to third party.

99 Lessee will implement the redevelopment.

99 Revenue stream to help offset a portion of operating and capital improvement costs for BWS.

South Beretania Street

Lauhala Street

Street

Lusitana

Alap

ai

Stre

et

Lisbon Street

Project Area128,100 sfTMK (1) 2-1-036:001 and 005 (por)

ExistingPublic Service

Building

Beretania Complex

ExistingEngineering Building

ExistingPump Station

Site MapZoning: A2, Medium Density Apartment

Source: Google Earth

Beretania Complex Redevelopment Process

Develop 3 Alternative

Concept Plans

Identify Allowable/Appropriate Uses

A2 Zoning • Adjacent Land Use Compatibility • Market Studies

Select Lessee/Developer and Enter Lease

Agreement

Evaluate Developer Proposals

Issue Request for Proposals

(RFP)

Lessee Obtain Land Use

Entitlements

Developer/Lessee Finalize Plans for Site

Lessee Redevelops Site

Environmental Review Process

(Evaluate 3 Alternatives)

Potential Redevelopment Concepts (Potential Redevelopment Concepts are based on current A-2 Zoning, compatibility with surrounding land uses, and a BWS market analysis on the most appropriate uses for the property. Final project design is subject to change by selected developer/lessee. Additional environmental review may be required if proposed concept is different from those presented below).

BWS is currently initiating theEnvironmental Review Process

99Environmental review in accordance with Chapter 343 Hawaii Revised Statutes (HRS).

99EIS will evaluate environmental impacts of three alternatives on natural and human environment.

99EIS will recommend minimization and mitigation of any environmental impacts.

Scenario 1: Assisted Care Living Facility and Office Building

Scenario 3: Parking Structure and Office Building

Scenario 2: Affordable Senior Rental Apartments and Office Building

Environmental Impact Statement Preparation Notice

(EISPN)November 23, 2018

Public MeetingsNeighborhood Board and

Community Meetings

Draft EIS

June 2019 (Estimate)

Final EIS

November 2019 (Estimate)

30-day

Public Review

45-day Public Review