ENGINEERING PROJECTS: PROGRESS REPORT July 9, 2021 Hurricane Mahew Recovery Project Devonwood Lower Dam Current Status: The Pre-Construction Meeting was conducted on April 6, 2021 with the contractor, Fred Smith Company. The NTP for this project is July 8, 2021 and estimated Substantial Completion is July 6, 2022.. This project will consist of the installation of a double box culvert across McFadyen Drive and utility work on Poland Court. This work is estimated to begin Monday, July 12, 2021. Normal construction will occur Monday thru Friday during daytime hours between 7 a.m. and 5 p.m. Facts: Project: Devonwood Lower Dam Status: Notice to Proceed 7/8/2021 Spillway and Embankment Damaged by Hurricane Matthew on October 8, 2016 Design approved by Dam safety on 3/24/2020 Budget: $1.9 M

Upload: others

Post on 01-Oct-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Facts: Devonwood Lower Dam

ENGINEERING PROJECTS: PROGRESS REPORT

July 9, 2021

Hurricane Matthew Recovery Project

Devonwood Lower Dam Current Status: The Pre-Construction Meeting was conducted on April 6,

2021 with the contractor, Fred Smith Company. The NTP for this project is

July 8, 2021 and estimated Substantial Completion is July 6, 2022..

This project will consist of the installation of a double box culvert across

McFadyen Drive and utility work on Poland Court. This work is estimated to

begin Monday, July 12, 2021. Normal construction will occur Monday thru

Friday during daytime hours between 7 a.m. and 5 p.m.

Facts:

Project: Devonwood

Lower Dam

Status: Notice to

Proceed 7/8/2021

Spillway and

Embankment Damaged

by Hurricane Matthew

on October 8, 2016

Design approved by

Dam safety on

3/24/2020

Budget: $1.9 M