facts: devonwood lower dam
TRANSCRIPT
ENGINEERING PROJECTS: PROGRESS REPORT
July 9, 2021
Hurricane Matthew Recovery Project
Devonwood Lower Dam Current Status: The Pre-Construction Meeting was conducted on April 6,
2021 with the contractor, Fred Smith Company. The NTP for this project is
July 8, 2021 and estimated Substantial Completion is July 6, 2022..
This project will consist of the installation of a double box culvert across
McFadyen Drive and utility work on Poland Court. This work is estimated to
begin Monday, July 12, 2021. Normal construction will occur Monday thru
Friday during daytime hours between 7 a.m. and 5 p.m.
Facts:
Project: Devonwood
Lower Dam
Status: Notice to
Proceed 7/8/2021
Spillway and
Embankment Damaged
by Hurricane Matthew
on October 8, 2016
Design approved by
Dam safety on
3/24/2020
Budget: $1.9 M