factsheet windmarkt duitsland

Upload: energiemedia

Post on 04-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 Factsheet Windmarkt Duitsland

    1/10

    STATUS OF WIND ENERGYDEVELOPMENT IN GERMANY

    Calendar

    Year 2012

    On behalf of:

    Deutsche WindGuard GmbH - Oldenburger Strae 65 - 26316 Varel0049-4451/95150 - [email protected] - www.windguard.de

  • 7/29/2019 Factsheet Windmarkt Duitsland

    2/10

  • 7/29/2019 Factsheet Windmarkt Duitsland

    3/10

    aSTATUS OF WIND ENERGYDEVELOPMENT IN GERMANY

    The data for CY 2012 were determined based on inquirieswith industry players and additional research.Data Basis 1992-2011: DEWI

    1

    CalendarYear 2012

    Statistics onbehalf of:

    STATUS OF WIND ENERGY DEVELOPMENT AS OF 31 DECEMBER 2012

    In the course of calendar year 2012, 1,008 wind turbine generators with a total capacity of

    2,439.46 MW were installed in Germany. As of 31 December 2012, there were a total of 23,040

    operational wind turbine generators. The total installed capacity was 31,331.90 MW.

    Table 1 shows an overview of the status of the wind energy development as of 31 December 2012.

    Table 1 Status of Wind Energy Development as of 31 December 2012

    Status of wind energy development Capacity (MW) No. of turbines

    New installations 2012 2.439,46 1.008

    share of repowering (non-binding) 431,63 161

    share of offshore wind energy (first feed-in) 80,00 16

    dismantling(non-binding) 178,56 252

    Installed total capacity - December 31, 2012 31.331,90 23.040

    share of repowering (non-binding) 1.442,51 626

    share of offshore wind energy 280,30 68

    accountzed for dismantling(non-binding) 626,77 998Totalcapacity,

    D

    ec.

    31,

    2012

    New

    installatio

    ns

    2012

    Additions to land-based wind energy comprise of new and repowering projects, along with offshore

    wind projects. Individual components of these additions are described in more detail in their respective

    sections.

    It should be noted that the values for repowering and dismantling of wind turbine generators are non-

    binding, since a central turbine registry that would correctly report such values does not exist. The

    provided trend values were determined within the framework of a statistical data collection. This subject

    matter is examined more closely in the section titled Repowering.

    Figure 1 shows the development of the annual newly installed capacity, differentiated between new

    projects and repowering projects onshore as well as offshore wind energy projects. Also shown is the

    annual dismantled capacity.

  • 7/29/2019 Factsheet Windmarkt Duitsland

    4/10

    aSTATUS OF WIND ENERGYDEVELOPMENT IN GERMANY

    The data for CY 2012 were determined based on inquirieswith industry players and additional research.Data Basis 1992-2011: DEWI

    2

    CalendarYear 2012

    Statistics onbehalf of:

    -400

    0

    400

    800

    1.200

    1.600

    2.000

    2.400

    2.800

    3.200

    3.600

    4.000

    AnnualinstalledCapacity(MW)

    Decommissioning (MW)

    Offshore-Wind Energy - Installed Capacity (MW)

    Repowering - Installed Capacity (MW)

    Onshore - only new Installations (MW)

    Data 1992-2011: DEWI

    Figure 1 Development of the Annual Installed Caapcity from Wind Energy in Germany (in MW),Status 31 December 2012

    Figure 2 shows the cumulative development of new construction with regard to the total installed

    capacity from wind energy in Germany on 31 December 2012. The diagram differentiates betweennew projects onshore, repowering onshore and offshore wind energy projects.

    0

    5.000

    10.000

    15.000

    20.000

    25.000

    30.000

    35.000

    40.000

    CumulativeCapacity(MW)

    Cumulative Offshore Wind Energy Capacity (MW)

    Cumulative Repowering Capacity (MW)

    Onshore - only new Installations, Cumulative Capacity (MW)

    Data 1992-2011: DEWI

    31.332 MW

    Figure 2 Development of New Wind Energy Construction in Germany Cumulative Capacity

    Turbine Inventory (in MW), Status 31 December 2012

  • 7/29/2019 Factsheet Windmarkt Duitsland

    5/10

    aSTATUS OF WIND ENERGYDEVELOPMENT IN GERMANY

    The data for CY 2012 were determined based on inquirieswith industry players and additional research.Data Basis 1992-2011: DEWI

    3

    CalendarYear 2012

    Statistics onbehalf of:

    STATUS OF OFFSHORE-WIND ENERGY DEVELOPMENT

    Within 2012, 16 offshore wind

    turbine generators with a combined

    capacity of 80 MW fed into the

    grid for the first time. At the end of

    2012, a total capacity of

    280.3 MW from offshore wind

    turbines was connected to the grid.

    109 foundation structures were

    installed out at sea.

    Table 2 provides an overview of new construction in the area of

    offshore wind energy.

    Table 2 Newly Constructed Offshore Wind Energy in Germany

    Status of offshore wind energy development Capacity (MW) No. of turbines

    New Installations 2012

    (Turbines first feeding-in)80,00 16

    Total Installed Capacity, Dec. 31, 2012

    (Turbines feeding-in)280,30 68

    Substructures 109

    0

    50

    100

    150

    200

    250

    300

    350

    0

    20

    40

    60

    80

    100

    120

    140

    CumulativeCapacity(MW)

    Capacity(MW)

    Cumulative Offshore WindEnergy Capacity (MW)

    Offshore-Wind Energy -Installed Capacity (MW)

    Figure 3 Development of Offshore Wind Energy in Germany(Capacity from Initially Feeding-In Turbines per Year andCumulative Capacity in MW), Status 31 December 2012

    Figure 3 illustrates the development of

    offshore wind energy in the North and

    Baltic Sea (point of first feed-in).

    In the second half of 2012,

    construction on four additional

    offshore wind energy projects

    commenced.

    Now six German offshore wind

    energy projects are under

    construction, which totals over 350

    turbines with a total capacity of about

    1,800 MW. All projects are located in

    the North Sea.

    The following map (Figure 4)

    gives an overview of all

    offshore wind projects currently

    under construction.

    The map illustrates the large

    potential in view of the

    installations expected in 2013.

    The projects are being

    completed in stages, parts ofthem in 2013.

    Bard Offshore I

    since 2011, 400 MW

    Meerwind Sd / Ost

    since 2nd half 2012,

    288 MW

    Global Tech I

    since2 nd half 2012,

    400 MW

    Borkum Riffgat,

    since 2nd half 2012,

    220 MW

    Borkum West II Phase 1,

    since 2011, 200 MW

    Nordsee Ost

    since2nd half 2012,

    295 MW

    Map Resource:Bundesamt fr Seeschifffahrt und Hydrographie (BSH)

    Figure 4 Offshore Wind Farms Under Construction, 31 December 2012

  • 7/29/2019 Factsheet Windmarkt Duitsland

    6/10

    aSTATUS OF WIND ENERGYDEVELOPMENT IN GERMANY

    The data for CY 2012 were determined based on inquirieswith industry players and additional research.Data Basis 1992-2011: DEWI

    4

    CalendarYear 2012

    Statistics onbehalf of:

    TENDENCIES IN REPOWERING AND DISMANTLING OF WIND TURBINE GENERATORS

    No binding values exist for the development of repowering in Germany. This is due to the absence of a

    central turbine registry that would allow for these projects to be accounted for separately. Because of

    this reason, only tendencies can be identified in the area of repowering and dismantling.

    In the framework of the statistical data collection, construction of 140 repowering turbines with a total

    capacity of around 355 MW could be identified for 2012. At the same time, the dismantling of 224

    wind turbine generators with a total capacity of 235 MW was identified.

    The available data shows that during 2012, repowering occurred mainly in Schleswig-Holstein and

    Lower Saxony, because the majority of turbines that had come into their repowering age were located

    here. But, repowering was also realized in federal states located in the central and the south regions of

    Germany.

    The data basis for the numbers cited here is information provided by manufacturers and larger

    planning bureaus, as well as own research primarily of press releases. This approach allowed several

    paths of information gathering to be taken. Still, it must be assumed that not all realized repowering

    projects in 2012 were identified this way. Considering these circumstances, a larger number of turbines

    were dismantled than previously determined.

    The following circumstances complicate the identification of repowering projects:

    Change of manufacturer between the old and the new project, resulting in the manufacturer ofthe turbines for new project having no knowledge about the details of the old project.

    Old turbines may be located in counties adjacent to the new project, by which a repowering isnot readily apparent and also often unbeknownst to the permitting agencies.

    Based on the current regulations of the Renewable Energy Law 2012 (EEG 2012), in many casesone old turbine is replaced by one new turbine. This means that old turbines are being partially

    brokered to adjacent projects, if the number of dismantled turbines is larger than the number of

    new ones. Hence, two or more repowering projects can come out of one old project.

    Many of the repowering activities currently in progress are being realized by local operatorsand so-called citizens wind farms (Brgerwindparks) and thus are unknown on a national

    level.

    Lack of a central turbine registry, including capturing repowering information.To analyze the situation around the area of repowering and with that the dismantling of old turbines

    more comprehensively, further research is planned.

  • 7/29/2019 Factsheet Windmarkt Duitsland

    7/10

    aSTATUS OF WIND ENERGYDEVELOPMENT IN GERMANY

    The data for CY 2012 were determined based on inquirieswith industry players and additional research.Data Basis 1992-2011: DEWI

    5

    CalendarYear 2012

    Statistics onbehalf of:

    AVERAGE TURBINE CONFIGURATION

    Turbines newly installed in 2012 had an

    average capacity of about 2,420 kW.

    The average capacity per wind turbine

    generator in the total inventory on

    31 December 2012 was about 1,360 kW.

    Table 3 Average Turbine Configuration 2012

    Average turbine configuration 2012

    Average capacity of wind turbines 2.420 kW

    Average rotor diameter 88,5 m

    Average hub height 109,8 m

    Figure 5 graphically shows the development of average turbine capacity in relation to annual new

    construction, as well as the inventory.

    1.360

    2.420

    0

    300

    600

    900

    1.200

    1.500

    1.800

    2.100

    2.400

    2.700

    3.000

    Capacity(kW)

    Average capacity of wind turbines -

    Germany-wide inventory

    Average capacity of annual installed

    wind turbines

    Data 1992-2011: DEWI

    Figure 5 Development of the Average Capacity (in kW) of the Annual New Construction, as well asthe Countrywide Turbine Inventory, Status 31 December 2012

    Wind energy generators installed during 2012 had an average rotor diameter of 88.5 meters and anaverage hub height of 109.8 meters.

    Comparing the individual federal states, a significant variation in turbine configuration for 2012 was

    found, which is particularly applicable to hub height. This variation is examined in more detail in the

    following sections.

  • 7/29/2019 Factsheet Windmarkt Duitsland

    8/10

    aSTATUS OF WIND ENERGYDEVELOPMENT IN GERMANY

    The data for CY 2012 were determined based on inquirieswith industry players and additional research.Data Basis 1992-2011: DEWI

    6

    CalendarYear 2012

    Statistics onbehalf of:

    REGIONAL DISTRIBUTION OF WIND ENERGY DEVELOPMENT

    During 2012, the northern federal states had the largest number of new constructions. Lower Saxony

    with about 15 % and Schleswig-Holstein with around 14 % occupy first and second place, followed by

    Mecklenburg-West Pomerania with about 13 %. Together, the northern federal states make up more

    than 40 % of the newly installed capacity.

    Rhineland-Palatinate, a federal state in the south of Germany, comes in at fourth place in relation to

    the total installed capacity, about 12 % of the all new construction happened there. The state is

    followed by Brandenburg in fifth place with about 10 %.

    The detailed analysis according to all federal states is shown in Table 4. Next to the new construction

    data for 2012, the average turbine configuration installed in the individual federal states for thetimeframe in question is also shown.

    Table 4 Wind Energy New Construction in Calendar Year 2012 in the German Federal States

    Rank State / Region Installed

    capacity

    (MW)

    No. of wind

    turbines

    (WT)

    Share of 2012

    installations

    Average

    capacity

    of turbines

    (kW)

    Average

    Rotor

    diameter

    (m)

    Average

    Hub

    height (m)

    1 Lower Saxony 360,58 154 14,8% 2.341 84,9 105,5

    2 Schleswig-Holstein 332,65 135 13,6% 2.464 84,2 81,7

    4 Mecklenburg-Western Pomerania 307,92 124 12,6% 2.483 90,7 108,2

    3 Rhineland-Palatinate 287,50 100 11,8% 2.875 96,0 129,1

    5 Brandenburg 248,06 110 10,2% 2.255 88,0 113,4

    6 Bavaria 200,50 81 8,2% 2.475 94,3 133,9

    7 Saxony-Anhalt 180,75 84 7,4% 2.152 86,7 110,6

    8 North Rhine-Westphalia 133,55 65 5,5% 2.055 79,8 101,7

    9 Hesse 122,40 53 5,0% 2.309 86,8 127,5

    10 Thuringia 102,30 47 4,2% 2.177 91,9 114,8

    11 Saarland 31,60 15 1,3% 2.107 89,7 102,7

    12 Saxony 27,05 13 1,1% 2.081 82,2 97,9

    13 Baden-Wuerttemberg 18,90 9 0,8% 2.100 82,9 129,9

    14 Bremen 5,70 2 0,2% 2.850 93,0 113,0

    15 Hamburg 0,00 0 0,0% - - -

    15 Berlin 0,00 0 0,0% - - -

    North Sea 80,00 16 3,3% 5.000 120,0 90,0

    Baltic Sea 0,00 0 0,0% - - -

    Gesamt 2.439,46 1.008 100% 2.420 88,5 109,8

    Installed capacity

    2012

    Average turbine configuration

    2012

    Table 5 shows the cumulative installed capacity for each of the federal states. The states are

    subdivided into the North, Central, South and Sea regions. This allows for the formulation of

    statements about the regional distribution of the existing total turbine inventory in the Federal Republic

    of Germany.

  • 7/29/2019 Factsheet Windmarkt Duitsland

    9/10

    aSTATUS OF WIND ENERGYDEVELOPMENT IN GERMANY

    The data for CY 2012 were determined based on inquirieswith industry players and additional research.Data Basis 1992-2011: DEWI

    7

    CalendarYear 2012

    Statistics onbehalf of:

    Attention must be paid to the fact that, because

    of variations compared to the statistical databasis of previous years, the cumulative total

    capacity and number of turbines in the

    individual federal states was determined

    based on the states percentage share of the

    total installed capacity Germany-wide.

    Figure 6 graphically illustrates the distribution

    of the installed total capacity across the

    North, Central, South and Sea regions

    with respect to development over time.

    Especially during the 90's, a clear shift of new

    construction from region "North" to region

    "Central" can be observed.

    Since about 2006, the northern share in the

    Germany-wide installed total capacity has

    remained relatively constant at 42-44 %.

    Table 5 Cumulative Installed Capacity and No.

    of Turbines in the Federal States

    State / Region Total capacity,

    Dec. 31, 2012

    (MW)

    Total no. of

    turbines,

    Dec. 31, 2012

    (WT)

    Lower Saxony 7.337,92 5.479

    Schleswig-Holstein 3.588,18 2.926

    Mecklenburg-Western Pomerania 1.950,33 1.507

    Bremen 145,62 76

    Hamburg 52,75 58

    Brandenburg 4.814,39 3.135

    Saxony-Anhalt 3.813,14 2.413

    North Rhine-Westphalia 3.178,74 2.899

    Saxony 1.002,54 844

    Thuringia 899,59 641

    Hesse 802,24 705

    Berlin 2,00 1

    Rhineland-Palatinate 1.923,07 1.243

    Bavaria 881,36 559

    Baden-Wuerttemberg 501,56 383

    Saarland 158,15 103

    North Sea 229,50 46

    Baltic Sea 50,80 22

    Gesamt 31.331,90 23.040

    Sea

    South

    Installed total capacity

    North

    Central

    42%

    46%

    11%

    1%

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    Shareofinstalledtotalcapacity(%)

    Sea

    South

    Central

    North

    Daten 1992-2011: DEWI

    Figure 6 Distribution of the Countrywide Installed Total CapacityAcross the Regions, Status 31 December 2012

    The south of Germany has

    continuously gained shares and in

    2012 owned more than 11 % of

    the Germany-wide installed total

    capacity.

    Offshore wind energy shares in

    the installed total capacity were

    about 1% in 2012.

    The following section examines in

    more detail the aspect of the

    average hub height of all wind

    turbine generators installed

    Germany-wide in 2012.

  • 7/29/2019 Factsheet Windmarkt Duitsland

    10/10

    aSTATUS OF WIND ENERGYDEVELOPMENT IN GERMANY

    The data for CY 2012 were determined based on inquirieswith industry players and additional research.

    8

    CalendarYear 2012

    Statistics onbehalf of:

    AVERAGE HUB HEIGHT ACROSS THE FEDERAL STATES

    Figure 7 shows the average hub height of wind turbine generators installed Germany-wide,

    differentiated by individual federal states. Only those states that actually had turbines installed during

    2012 are listed.

    81,7

    97,9

    101,7

    102,7

    105,5

    108,2

    110,6

    113,0

    113,4114,8

    127,5

    129,1

    129,9

    133,9

    0,0 50,0 100,0 150,0

    Schleswig-Holstein

    Saxony

    North Rhine-Westphalia

    Saarland

    Lower Saxony

    Mecklenburg-Western Pomerania

    Saxony-Anhalt

    Bremen

    BrandenburgThuringia

    Hesse

    Rhineland-Palatinate

    Baden-Wuerttemberg

    Bavaria

    Hub Height (m)

    Figure 7 Average Hub Height of Wind Turbine Generators installed in 2012 acrossthe Federal States of Germany

    When comparing federal states, the value for Schleswig-Holstein is particularly conspicuous: The

    average hub height of turbines installed in this state during 2012 is 81.7 m. This number significantly

    influences the Germany-wide average value: When leaving Schleswig-Holstein out of the calculation,

    the average hub height of all wind turbine generators installed in Germany in 2012 equates to

    114.1 meters. The average hub height of wind turbines installed in Schleswig-Holstein is thus about

    32 meters less than the Germany-wide average without Schleswig-Holstein.

    It is apparent that the largest average hub heights are being installed in the southern federal states,

    namely Bavaria, Baden-Wuerttemberg and Rhineland-Palatinate. These locations have comparatively

    low wind speeds, so turbine technology with large hub heights and large rotor diameters are being

    employed to optimize energy yields.

    Data Collection and Preparation:

    Deutsche WindGuard GmbH

    Anna-Kathrin Wallasch,

    Martha Ekkert, Dr. Knud Rehfeldtwww.windguard.com