factsheet windmarkt duitsland
TRANSCRIPT
-
7/29/2019 Factsheet Windmarkt Duitsland
1/10
STATUS OF WIND ENERGYDEVELOPMENT IN GERMANY
Calendar
Year 2012
On behalf of:
Deutsche WindGuard GmbH - Oldenburger Strae 65 - 26316 Varel0049-4451/95150 - [email protected] - www.windguard.de
-
7/29/2019 Factsheet Windmarkt Duitsland
2/10
-
7/29/2019 Factsheet Windmarkt Duitsland
3/10
aSTATUS OF WIND ENERGYDEVELOPMENT IN GERMANY
The data for CY 2012 were determined based on inquirieswith industry players and additional research.Data Basis 1992-2011: DEWI
1
CalendarYear 2012
Statistics onbehalf of:
STATUS OF WIND ENERGY DEVELOPMENT AS OF 31 DECEMBER 2012
In the course of calendar year 2012, 1,008 wind turbine generators with a total capacity of
2,439.46 MW were installed in Germany. As of 31 December 2012, there were a total of 23,040
operational wind turbine generators. The total installed capacity was 31,331.90 MW.
Table 1 shows an overview of the status of the wind energy development as of 31 December 2012.
Table 1 Status of Wind Energy Development as of 31 December 2012
Status of wind energy development Capacity (MW) No. of turbines
New installations 2012 2.439,46 1.008
share of repowering (non-binding) 431,63 161
share of offshore wind energy (first feed-in) 80,00 16
dismantling(non-binding) 178,56 252
Installed total capacity - December 31, 2012 31.331,90 23.040
share of repowering (non-binding) 1.442,51 626
share of offshore wind energy 280,30 68
accountzed for dismantling(non-binding) 626,77 998Totalcapacity,
D
ec.
31,
2012
New
installatio
ns
2012
Additions to land-based wind energy comprise of new and repowering projects, along with offshore
wind projects. Individual components of these additions are described in more detail in their respective
sections.
It should be noted that the values for repowering and dismantling of wind turbine generators are non-
binding, since a central turbine registry that would correctly report such values does not exist. The
provided trend values were determined within the framework of a statistical data collection. This subject
matter is examined more closely in the section titled Repowering.
Figure 1 shows the development of the annual newly installed capacity, differentiated between new
projects and repowering projects onshore as well as offshore wind energy projects. Also shown is the
annual dismantled capacity.
-
7/29/2019 Factsheet Windmarkt Duitsland
4/10
aSTATUS OF WIND ENERGYDEVELOPMENT IN GERMANY
The data for CY 2012 were determined based on inquirieswith industry players and additional research.Data Basis 1992-2011: DEWI
2
CalendarYear 2012
Statistics onbehalf of:
-400
0
400
800
1.200
1.600
2.000
2.400
2.800
3.200
3.600
4.000
AnnualinstalledCapacity(MW)
Decommissioning (MW)
Offshore-Wind Energy - Installed Capacity (MW)
Repowering - Installed Capacity (MW)
Onshore - only new Installations (MW)
Data 1992-2011: DEWI
Figure 1 Development of the Annual Installed Caapcity from Wind Energy in Germany (in MW),Status 31 December 2012
Figure 2 shows the cumulative development of new construction with regard to the total installed
capacity from wind energy in Germany on 31 December 2012. The diagram differentiates betweennew projects onshore, repowering onshore and offshore wind energy projects.
0
5.000
10.000
15.000
20.000
25.000
30.000
35.000
40.000
CumulativeCapacity(MW)
Cumulative Offshore Wind Energy Capacity (MW)
Cumulative Repowering Capacity (MW)
Onshore - only new Installations, Cumulative Capacity (MW)
Data 1992-2011: DEWI
31.332 MW
Figure 2 Development of New Wind Energy Construction in Germany Cumulative Capacity
Turbine Inventory (in MW), Status 31 December 2012
-
7/29/2019 Factsheet Windmarkt Duitsland
5/10
aSTATUS OF WIND ENERGYDEVELOPMENT IN GERMANY
The data for CY 2012 were determined based on inquirieswith industry players and additional research.Data Basis 1992-2011: DEWI
3
CalendarYear 2012
Statistics onbehalf of:
STATUS OF OFFSHORE-WIND ENERGY DEVELOPMENT
Within 2012, 16 offshore wind
turbine generators with a combined
capacity of 80 MW fed into the
grid for the first time. At the end of
2012, a total capacity of
280.3 MW from offshore wind
turbines was connected to the grid.
109 foundation structures were
installed out at sea.
Table 2 provides an overview of new construction in the area of
offshore wind energy.
Table 2 Newly Constructed Offshore Wind Energy in Germany
Status of offshore wind energy development Capacity (MW) No. of turbines
New Installations 2012
(Turbines first feeding-in)80,00 16
Total Installed Capacity, Dec. 31, 2012
(Turbines feeding-in)280,30 68
Substructures 109
0
50
100
150
200
250
300
350
0
20
40
60
80
100
120
140
CumulativeCapacity(MW)
Capacity(MW)
Cumulative Offshore WindEnergy Capacity (MW)
Offshore-Wind Energy -Installed Capacity (MW)
Figure 3 Development of Offshore Wind Energy in Germany(Capacity from Initially Feeding-In Turbines per Year andCumulative Capacity in MW), Status 31 December 2012
Figure 3 illustrates the development of
offshore wind energy in the North and
Baltic Sea (point of first feed-in).
In the second half of 2012,
construction on four additional
offshore wind energy projects
commenced.
Now six German offshore wind
energy projects are under
construction, which totals over 350
turbines with a total capacity of about
1,800 MW. All projects are located in
the North Sea.
The following map (Figure 4)
gives an overview of all
offshore wind projects currently
under construction.
The map illustrates the large
potential in view of the
installations expected in 2013.
The projects are being
completed in stages, parts ofthem in 2013.
Bard Offshore I
since 2011, 400 MW
Meerwind Sd / Ost
since 2nd half 2012,
288 MW
Global Tech I
since2 nd half 2012,
400 MW
Borkum Riffgat,
since 2nd half 2012,
220 MW
Borkum West II Phase 1,
since 2011, 200 MW
Nordsee Ost
since2nd half 2012,
295 MW
Map Resource:Bundesamt fr Seeschifffahrt und Hydrographie (BSH)
Figure 4 Offshore Wind Farms Under Construction, 31 December 2012
-
7/29/2019 Factsheet Windmarkt Duitsland
6/10
aSTATUS OF WIND ENERGYDEVELOPMENT IN GERMANY
The data for CY 2012 were determined based on inquirieswith industry players and additional research.Data Basis 1992-2011: DEWI
4
CalendarYear 2012
Statistics onbehalf of:
TENDENCIES IN REPOWERING AND DISMANTLING OF WIND TURBINE GENERATORS
No binding values exist for the development of repowering in Germany. This is due to the absence of a
central turbine registry that would allow for these projects to be accounted for separately. Because of
this reason, only tendencies can be identified in the area of repowering and dismantling.
In the framework of the statistical data collection, construction of 140 repowering turbines with a total
capacity of around 355 MW could be identified for 2012. At the same time, the dismantling of 224
wind turbine generators with a total capacity of 235 MW was identified.
The available data shows that during 2012, repowering occurred mainly in Schleswig-Holstein and
Lower Saxony, because the majority of turbines that had come into their repowering age were located
here. But, repowering was also realized in federal states located in the central and the south regions of
Germany.
The data basis for the numbers cited here is information provided by manufacturers and larger
planning bureaus, as well as own research primarily of press releases. This approach allowed several
paths of information gathering to be taken. Still, it must be assumed that not all realized repowering
projects in 2012 were identified this way. Considering these circumstances, a larger number of turbines
were dismantled than previously determined.
The following circumstances complicate the identification of repowering projects:
Change of manufacturer between the old and the new project, resulting in the manufacturer ofthe turbines for new project having no knowledge about the details of the old project.
Old turbines may be located in counties adjacent to the new project, by which a repowering isnot readily apparent and also often unbeknownst to the permitting agencies.
Based on the current regulations of the Renewable Energy Law 2012 (EEG 2012), in many casesone old turbine is replaced by one new turbine. This means that old turbines are being partially
brokered to adjacent projects, if the number of dismantled turbines is larger than the number of
new ones. Hence, two or more repowering projects can come out of one old project.
Many of the repowering activities currently in progress are being realized by local operatorsand so-called citizens wind farms (Brgerwindparks) and thus are unknown on a national
level.
Lack of a central turbine registry, including capturing repowering information.To analyze the situation around the area of repowering and with that the dismantling of old turbines
more comprehensively, further research is planned.
-
7/29/2019 Factsheet Windmarkt Duitsland
7/10
aSTATUS OF WIND ENERGYDEVELOPMENT IN GERMANY
The data for CY 2012 were determined based on inquirieswith industry players and additional research.Data Basis 1992-2011: DEWI
5
CalendarYear 2012
Statistics onbehalf of:
AVERAGE TURBINE CONFIGURATION
Turbines newly installed in 2012 had an
average capacity of about 2,420 kW.
The average capacity per wind turbine
generator in the total inventory on
31 December 2012 was about 1,360 kW.
Table 3 Average Turbine Configuration 2012
Average turbine configuration 2012
Average capacity of wind turbines 2.420 kW
Average rotor diameter 88,5 m
Average hub height 109,8 m
Figure 5 graphically shows the development of average turbine capacity in relation to annual new
construction, as well as the inventory.
1.360
2.420
0
300
600
900
1.200
1.500
1.800
2.100
2.400
2.700
3.000
Capacity(kW)
Average capacity of wind turbines -
Germany-wide inventory
Average capacity of annual installed
wind turbines
Data 1992-2011: DEWI
Figure 5 Development of the Average Capacity (in kW) of the Annual New Construction, as well asthe Countrywide Turbine Inventory, Status 31 December 2012
Wind energy generators installed during 2012 had an average rotor diameter of 88.5 meters and anaverage hub height of 109.8 meters.
Comparing the individual federal states, a significant variation in turbine configuration for 2012 was
found, which is particularly applicable to hub height. This variation is examined in more detail in the
following sections.
-
7/29/2019 Factsheet Windmarkt Duitsland
8/10
aSTATUS OF WIND ENERGYDEVELOPMENT IN GERMANY
The data for CY 2012 were determined based on inquirieswith industry players and additional research.Data Basis 1992-2011: DEWI
6
CalendarYear 2012
Statistics onbehalf of:
REGIONAL DISTRIBUTION OF WIND ENERGY DEVELOPMENT
During 2012, the northern federal states had the largest number of new constructions. Lower Saxony
with about 15 % and Schleswig-Holstein with around 14 % occupy first and second place, followed by
Mecklenburg-West Pomerania with about 13 %. Together, the northern federal states make up more
than 40 % of the newly installed capacity.
Rhineland-Palatinate, a federal state in the south of Germany, comes in at fourth place in relation to
the total installed capacity, about 12 % of the all new construction happened there. The state is
followed by Brandenburg in fifth place with about 10 %.
The detailed analysis according to all federal states is shown in Table 4. Next to the new construction
data for 2012, the average turbine configuration installed in the individual federal states for thetimeframe in question is also shown.
Table 4 Wind Energy New Construction in Calendar Year 2012 in the German Federal States
Rank State / Region Installed
capacity
(MW)
No. of wind
turbines
(WT)
Share of 2012
installations
Average
capacity
of turbines
(kW)
Average
Rotor
diameter
(m)
Average
Hub
height (m)
1 Lower Saxony 360,58 154 14,8% 2.341 84,9 105,5
2 Schleswig-Holstein 332,65 135 13,6% 2.464 84,2 81,7
4 Mecklenburg-Western Pomerania 307,92 124 12,6% 2.483 90,7 108,2
3 Rhineland-Palatinate 287,50 100 11,8% 2.875 96,0 129,1
5 Brandenburg 248,06 110 10,2% 2.255 88,0 113,4
6 Bavaria 200,50 81 8,2% 2.475 94,3 133,9
7 Saxony-Anhalt 180,75 84 7,4% 2.152 86,7 110,6
8 North Rhine-Westphalia 133,55 65 5,5% 2.055 79,8 101,7
9 Hesse 122,40 53 5,0% 2.309 86,8 127,5
10 Thuringia 102,30 47 4,2% 2.177 91,9 114,8
11 Saarland 31,60 15 1,3% 2.107 89,7 102,7
12 Saxony 27,05 13 1,1% 2.081 82,2 97,9
13 Baden-Wuerttemberg 18,90 9 0,8% 2.100 82,9 129,9
14 Bremen 5,70 2 0,2% 2.850 93,0 113,0
15 Hamburg 0,00 0 0,0% - - -
15 Berlin 0,00 0 0,0% - - -
North Sea 80,00 16 3,3% 5.000 120,0 90,0
Baltic Sea 0,00 0 0,0% - - -
Gesamt 2.439,46 1.008 100% 2.420 88,5 109,8
Installed capacity
2012
Average turbine configuration
2012
Table 5 shows the cumulative installed capacity for each of the federal states. The states are
subdivided into the North, Central, South and Sea regions. This allows for the formulation of
statements about the regional distribution of the existing total turbine inventory in the Federal Republic
of Germany.
-
7/29/2019 Factsheet Windmarkt Duitsland
9/10
aSTATUS OF WIND ENERGYDEVELOPMENT IN GERMANY
The data for CY 2012 were determined based on inquirieswith industry players and additional research.Data Basis 1992-2011: DEWI
7
CalendarYear 2012
Statistics onbehalf of:
Attention must be paid to the fact that, because
of variations compared to the statistical databasis of previous years, the cumulative total
capacity and number of turbines in the
individual federal states was determined
based on the states percentage share of the
total installed capacity Germany-wide.
Figure 6 graphically illustrates the distribution
of the installed total capacity across the
North, Central, South and Sea regions
with respect to development over time.
Especially during the 90's, a clear shift of new
construction from region "North" to region
"Central" can be observed.
Since about 2006, the northern share in the
Germany-wide installed total capacity has
remained relatively constant at 42-44 %.
Table 5 Cumulative Installed Capacity and No.
of Turbines in the Federal States
State / Region Total capacity,
Dec. 31, 2012
(MW)
Total no. of
turbines,
Dec. 31, 2012
(WT)
Lower Saxony 7.337,92 5.479
Schleswig-Holstein 3.588,18 2.926
Mecklenburg-Western Pomerania 1.950,33 1.507
Bremen 145,62 76
Hamburg 52,75 58
Brandenburg 4.814,39 3.135
Saxony-Anhalt 3.813,14 2.413
North Rhine-Westphalia 3.178,74 2.899
Saxony 1.002,54 844
Thuringia 899,59 641
Hesse 802,24 705
Berlin 2,00 1
Rhineland-Palatinate 1.923,07 1.243
Bavaria 881,36 559
Baden-Wuerttemberg 501,56 383
Saarland 158,15 103
North Sea 229,50 46
Baltic Sea 50,80 22
Gesamt 31.331,90 23.040
Sea
South
Installed total capacity
North
Central
42%
46%
11%
1%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Shareofinstalledtotalcapacity(%)
Sea
South
Central
North
Daten 1992-2011: DEWI
Figure 6 Distribution of the Countrywide Installed Total CapacityAcross the Regions, Status 31 December 2012
The south of Germany has
continuously gained shares and in
2012 owned more than 11 % of
the Germany-wide installed total
capacity.
Offshore wind energy shares in
the installed total capacity were
about 1% in 2012.
The following section examines in
more detail the aspect of the
average hub height of all wind
turbine generators installed
Germany-wide in 2012.
-
7/29/2019 Factsheet Windmarkt Duitsland
10/10
aSTATUS OF WIND ENERGYDEVELOPMENT IN GERMANY
The data for CY 2012 were determined based on inquirieswith industry players and additional research.
8
CalendarYear 2012
Statistics onbehalf of:
AVERAGE HUB HEIGHT ACROSS THE FEDERAL STATES
Figure 7 shows the average hub height of wind turbine generators installed Germany-wide,
differentiated by individual federal states. Only those states that actually had turbines installed during
2012 are listed.
81,7
97,9
101,7
102,7
105,5
108,2
110,6
113,0
113,4114,8
127,5
129,1
129,9
133,9
0,0 50,0 100,0 150,0
Schleswig-Holstein
Saxony
North Rhine-Westphalia
Saarland
Lower Saxony
Mecklenburg-Western Pomerania
Saxony-Anhalt
Bremen
BrandenburgThuringia
Hesse
Rhineland-Palatinate
Baden-Wuerttemberg
Bavaria
Hub Height (m)
Figure 7 Average Hub Height of Wind Turbine Generators installed in 2012 acrossthe Federal States of Germany
When comparing federal states, the value for Schleswig-Holstein is particularly conspicuous: The
average hub height of turbines installed in this state during 2012 is 81.7 m. This number significantly
influences the Germany-wide average value: When leaving Schleswig-Holstein out of the calculation,
the average hub height of all wind turbine generators installed in Germany in 2012 equates to
114.1 meters. The average hub height of wind turbines installed in Schleswig-Holstein is thus about
32 meters less than the Germany-wide average without Schleswig-Holstein.
It is apparent that the largest average hub heights are being installed in the southern federal states,
namely Bavaria, Baden-Wuerttemberg and Rhineland-Palatinate. These locations have comparatively
low wind speeds, so turbine technology with large hub heights and large rotor diameters are being
employed to optimize energy yields.
Data Collection and Preparation:
Deutsche WindGuard GmbH
Anna-Kathrin Wallasch,
Martha Ekkert, Dr. Knud Rehfeldtwww.windguard.com