Page 1: Fairfax County Pre-Disaster Recovery Planning: Project Launch

1

Fairfax County Pre-Disaster Recovery Planning:

Community-wide Project Launch

August 4, 2010

Page 2: Fairfax County Pre-Disaster Recovery Planning: Project Launch

2

Pre-Disaster Recovery Planning Workshop• Project Purpose and Introduction• Recovery Overview• Facilitated Discussion of Disaster Scenario and

Recovery Issues• How do we compare nationally? • Timeline and Next Steps• Vision and Goals for “Disaster Recovery”• Wrap-up and Q&A

Agenda

Page 3: Fairfax County Pre-Disaster Recovery Planning: Project Launch

3

Fairfax Co. Pre-Disaster Recovery Plan:

Project Purpose and Introduction

Page 4: Fairfax County Pre-Disaster Recovery Planning: Project Launch

4

Project History• Project DHS grant-funded by the Urban Areas

Security Initiative (UASI)• Project Kick-off (internal): December 2009• Expansion of planning to include private sector,

non-profits, neighboring jurisdictions, and interested members of the public: today

• Approximate Project Completion Date: Fall 2011

Purpose and Introduction

Page 5: Fairfax County Pre-Disaster Recovery Planning: Project Launch

5

Project Purpose• Streamline Fairfax County’s recovery from

disaster• Solidify four-phase emergency management

approach (mitigation, preparation, response, and recovery)

• Support the NCR in recovery planning efforts

Purpose and Introduction

Page 6: Fairfax County Pre-Disaster Recovery Planning: Project Launch

6

Recovery Overview

Page 7: Fairfax County Pre-Disaster Recovery Planning: Project Launch

7

Definitions• Response: how we manage a disaster• Continuity: what we do despite a disaster• Recovery: how we return to normal (or arrive

at a “new normal”) after a disaster

Recovery Overview

Page 8: Fairfax County Pre-Disaster Recovery Planning: Project Launch

8

Emergency Response• Short-term• Established funding

sources with clear utility

• Trained personnel available (Fire/EMS, public works)

Recovery Overview

Long-Term Recovery• Can last years• Need to use many

sources, often not designed for recovery

• Few trained personnel, new roles, resource strain, no established management structures

Page 9: Fairfax County Pre-Disaster Recovery Planning: Project Launch

9

Emergency Response• Operational goals

fairly obvious• Limited number of

players• Few question

resource needs• Limited political

issues (at least until later!)

Recovery Overview

Long-Term Recovery• Needs are subjective

and agenda-driven• Different and more

Stakeholders• Limited resources, less

clarity on benefits• Substantial political

issues

Page 10: Fairfax County Pre-Disaster Recovery Planning: Project Launch

10

A disaster (or catastrophe) is not just “Business as usual, but more of it.”

Recovery Overview

Page 11: Fairfax County Pre-Disaster Recovery Planning: Project Launch

11

Disaster recovery is not just “Response, only more of it.”

Recovery Overview

Page 12: Fairfax County Pre-Disaster Recovery Planning: Project Launch

12

Disaster recovery is not just “Business as usual, only after a disaster.”

Recovery Overview

Page 13: Fairfax County Pre-Disaster Recovery Planning: Project Launch

13

Not every hazard needs disaster recovery planning …

Recovery Overview

Page 14: Fairfax County Pre-Disaster Recovery Planning: Project Launch

14

Recovery Overview

Getting it done right vs.

Getting it done fast

Reduces the fundamental tension of disaster recovery:

Page 15: Fairfax County Pre-Disaster Recovery Planning: Project Launch

15

Recovery Overview

Flexibility to improvise + Structure to let it work

Page 16: Fairfax County Pre-Disaster Recovery Planning: Project Launch

16

Discussion Scenario: Radiological Dispersion Device (“Dirty Bomb”)

Page 17: Fairfax County Pre-Disaster Recovery Planning: Project Launch

17

Incident• A medium-sized explosion observed from a

van parked in front of the National Geospatial-Intelligence Agency’s (NGA) New Campus East facility, in Springfield

• Radiation identified; scene turned over to hazmat team

• No deaths or injuries • Driver quickly

apprehended

Discussion Scenario

Page 18: Fairfax County Pre-Disaster Recovery Planning: Project Launch

18

Discussion Scenario

Incident + 1 to 4 hours• Hazmat team establishes hot zone and

exclusion zone based on EPA standards• Multiple state and federal partners arrive• Evacuation and shelter-in-place guidance

issued

Page 19: Fairfax County Pre-Disaster Recovery Planning: Project Launch

19

Discussion Scenario

• Hot zone• Exclusion zone• Shelter in place

Page 20: Fairfax County Pre-Disaster Recovery Planning: Project Launch

20

Discussion Scenario

Realty Check:• Americium (typical source amount from oil

surveying equipment) detonated via 1 lb. of TNT

• Rings show increase in cancer rate: 1. 5% (1 in 100)2. 0.5% (1 in 1000)3. 0.05% (1 in 10,000)

(Journal of the Federation of American Scientists, April 2002)

12

3

Page 21: Fairfax County Pre-Disaster Recovery Planning: Project Launch

21

Springfield area

Housing units within affected area

6000

Persons within affected area 750 920 7700

Potential radiation-related illnesses

8 1 1

Schools within affected area Lee HS, Key MS, several elementary schools

Property value within affected area

$1.7 billion

Discussion Scenario

Page 22: Fairfax County Pre-Disaster Recovery Planning: Project Launch

22

Discussion Scenario

The day after• All citizens evacuate from exclusion zone• Some evacuate from shelter-in-place zone as

well, others from even further away• Evacuations, mass care

and sheltering take place smoothly

• Many people check themselves into hospitals

Page 23: Fairfax County Pre-Disaster Recovery Planning: Project Launch

23

Discussion Scenario

Recovery Issues• Where does temporary housing get set up, if

needed?• Where do students who had attended

impacted schools go?• What if county or

regional parks are needed for debris?

• How would the public weigh in on these issues?

Page 24: Fairfax County Pre-Disaster Recovery Planning: Project Launch

24

Discussion Scenario

Recovery Issues• Who will determine “how clean is clean,” and

by what process? Whose data will be used?• Will thresholds be the same all uses

(residential, commercial, infrastructure)• When can repopulation begin? Where will

repopulation be allowed? • What are the implications of declaring areas

to be “permanently closed”? • How do federal and state partners plug in? • How are stakeholders and the public heard?

Page 25: Fairfax County Pre-Disaster Recovery Planning: Project Launch

25

Discussion Scenario

The weeks after• Repopulation is OK’d for lowest-impacted

areas, but exclusion zone are permanently closed

...

.

.....

..

.....

.

.

..

. ..

..

...

• Buy-outs set up for within exclusion zone

• Uncertainty grows for neighborhoods nearby

• Contributions of housing labor and material pour in

Page 26: Fairfax County Pre-Disaster Recovery Planning: Project Launch

26

Discussion Scenario

Recovery Issues• How will major land-use impacts be managed

– relocation of infrastructure or housing– the “jack-o-lantern” effect– land acquisition

• How are stakeholders/ the public plugged in?• How will contributions of time, personnel, and

materials be coordinated?– Need to ensure continuity over time– Need to prevent gaps and overlaps

Page 27: Fairfax County Pre-Disaster Recovery Planning: Project Launch

27

Discussion Scenario

The months after• “Fairfax,” “dirty bomb,” “radiation,” and

“Chernobyl” are constantly linked in print, internet, TV, social media

• Although Springfield Mall, Lee Center, etc. are mostly beyond the exclusion zone, several large companies announce they will leave the county

Page 28: Fairfax County Pre-Disaster Recovery Planning: Project Launch

28

Discussion Scenario

Recovery Issues• Will there be a business retention strategy?

Who will define and manage it?• How will Fairfax County regain its reputation

as place to live and do business?• How will Fairfax County convince residents

and businesses that the event is over?• What role does the private sector play in

this?

Page 29: Fairfax County Pre-Disaster Recovery Planning: Project Launch

29

Discussion Scenario

The months after• Where repopulation is in doubt, developers

propose large-scale warehousing and light industrial projects

• Others argue for open space or community facilities

• Pressure builds for recovery planning to change the Comp Plan, zoning, and transportation and infrastructure priorities

SPRINGFIELD REDEVELOPMENT MASTER PLAN

Page 30: Fairfax County Pre-Disaster Recovery Planning: Project Launch

30

Discussion Scenario

Recovery Issues• How will conflicting community interests in

the redevelopment be mediated? • Will mitigation be applied to rebuilt/

relocated housing, infrastructure, and other facilities?

Page 31: Fairfax County Pre-Disaster Recovery Planning: Project Launch

31

Discussion Scenario

We deliberately went “small” for this scenario, but what if it were BIG? …

• What if supply chains were compromised county- or region-wide?

• What if recovery-critical firms (Home Depot, Wal-Mart, gas stations) couldn’t reopen?

• What if childcare, salaries, benefits were held up for weeks?

• What if construction labor was unavailable?• What if personal decisions were overwhelming

or impossible to make?

Page 32: Fairfax County Pre-Disaster Recovery Planning: Project Launch

32

National Context & Comparison

Page 33: Fairfax County Pre-Disaster Recovery Planning: Project Launch

33

National Context

DHS “National Disaster Recovery Framework” (Draft Feb. 5, 2010)• Establishes six “Recovery Support Functions”

(RSFs) at the federal level• Establishes federal and state leads and defines

responsibilities across agencies• Reinforces role of local leads• Fairfax will be among the first to do a local plan

that is designed to coordinate with the emerging federal framework

Page 34: Fairfax County Pre-Disaster Recovery Planning: Project Launch

34

National Context

There are currently a handful of disaster recovery plans (or “reconstruction plans”) in the US• Mainly in coastal cities and resort areas

– Hurricane– Tsunami– Earthquake

• No federal mandate; only draft federal guidance to-date

Fairfax is way ahead of the curve

Page 35: Fairfax County Pre-Disaster Recovery Planning: Project Launch

35

National Context

(Note that this survey was not exhaustive – there may be additional Disaster Recovery/Reconstruction Plans)

Page 36: Fairfax County Pre-Disaster Recovery Planning: Project Launch

36

Timeline and Next Steps

Page 37: Fairfax County Pre-Disaster Recovery Planning: Project Launch

37

Timeline and Next Steps

Kick-off & document research (12/09-3/10)• Preliminary work with OEM, deputy county

execs• Research (best practices, EOP, HMP, NCR HIRA,

etc., etc.)• County Agency orientation event

County Agency Interviews (3/10-6/10):• Identifying planning issues • Existing resources and capabilities• Beginning to think about goals and objectives

Page 38: Fairfax County Pre-Disaster Recovery Planning: Project Launch

38

Timeline and Next Steps

Expanding/ Establishing the planning groups (now):

• Working with private and non-profit sectors, regional partners

• Additional interviews

Roles• Recovery Planning Working Group:

– Steering Committee– Subject Matter/ Technical Experts

• Reviewers

Page 39: Fairfax County Pre-Disaster Recovery Planning: Project Launch

39

Timeline and Next Steps

Reviewers

Steering Committee

Working Group

Technical Expertise

Page 40: Fairfax County Pre-Disaster Recovery Planning: Project Launch

40

Timeline and Next Steps

• Intent is to provide conduits for information flow

• The process needs representation of technical and subject-matter expertise

Working Group will utilize existing organizational relationships

Page 41: Fairfax County Pre-Disaster Recovery Planning: Project Launch

41

Timeline and Next Steps

Further out (now through summer ‘11):• Internet Survey• Working Group Meetings to Develop the Plan

– Apply our experience, national best practices– Apply your local knowledge and understanding of

how Fairfax works– Open to public whenever appropriate

• Review and revise Plan • Tabletop Exercise

Page 42: Fairfax County Pre-Disaster Recovery Planning: Project Launch

42

(Draft) Recovery Support Functions• Command and Coordination• Economic Development• Health, Social, and Community Services • Housing• Infrastructure and Capital Repairs• Natural and Cultural Resources

Timeline and Next Steps

Page 43: Fairfax County Pre-Disaster Recovery Planning: Project Launch

43

Vision and Goals for a Pre-Disaster Recovery Plan

Page 44: Fairfax County Pre-Disaster Recovery Planning: Project Launch

44

Recovery Vision & Goals

Vision: What would Fairfax be aiming for after a

disaster?

Goals: How will Fairfax achieve that?

Page 45: Fairfax County Pre-Disaster Recovery Planning: Project Launch

45

Vision: Getting back to “regular” life, but Safer, Stronger, Smarter• Maximize long-term benefits• Recognize new risks/ realities• Leverage “catalyst” projects with recovery,

social, and economic development benefits• Holistic approach: Economic, Social, Cultural,

Environmental• Mitigation, risk-reduction, and resiliency

Recovery Vision & Goals

Page 46: Fairfax County Pre-Disaster Recovery Planning: Project Launch

46

Goals: Be Prepared/ Be Proactive• Inventory resources (agencies, entities, funds)• Set up for local lead role, while being able to

work with your neighbors• Set up streamlined

procedures and rules – and triggers to activate them

• Keeping it “close to normal”

Recovery Vision & Goals

Page 47: Fairfax County Pre-Disaster Recovery Planning: Project Launch

47

Goals: Be Prepared/ Be Proactive• Clear out obstacles in advance by pre-

establishing ... – Leadership structures, potentially outside of

normal governance– Priorities and direction to guide difficult

decisions– Decision-making processes– Legal authorities– Includes NGOs

Recovery Vision & Goals

Page 48: Fairfax County Pre-Disaster Recovery Planning: Project Launch

48

Recovery Vision & Goals

Goal: Ensure Legitimacy and Credibility through Stakeholder Outreach and Community Participation • Work with private, non-profit sectors and other

jurisdictions• Balance interests• Safeguard equity• Long-term community

gains and short-term individual wellbeing

Page 49: Fairfax County Pre-Disaster Recovery Planning: Project Launch

49

Goal: Recognize Key Roles of the Private- and Non-Profit Sectors• Unlike during emergency management …• Non-government sectors do the “heavy lifting”

of disaster recovery • Government participates as a “facilitating

stakeholder”

Recovery Vision & Goals

Page 50: Fairfax County Pre-Disaster Recovery Planning: Project Launch

50

Goal: Build on Existing Deliberative Planning and Organizational Relationships

• Comprehensive Plan• Area and Neighborhood Plans• Mitigation and Flood Management Plans• Economic Development Strategies• Transportation and Capital

Improvement Plans• VOAD Planning• Volunteer/ Donations Mgt.

Planning

Recovery Vision & Goals

Page 51: Fairfax County Pre-Disaster Recovery Planning: Project Launch

51

Closing thoughts and Q&A