5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Faith Duncan, PE & Greg Hasbrouck, PE Society of Women Engineers Region H Conference US 52 / IL 64 OVER THE MISSISSIPPI RIVER Project Overview US 52 / IL 64 over the Mississippi River Connecting Savanna, IL to Sabula, IA Illinois DOT Led Project Replacing Existing Cantilever Truss Bridge 520 ft main span Extensive Coordination Environmental and Permitting Railroads and Utilities Proposed 546 ft Main Span Tied Arch Steel Plate Girder Approaches Drilled Shafts with Coffercell Footings 2

Upload: others

Post on 26-Mar-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

1

Replacing the Aging US 52Mississippi River Bridge

February 27, 2016

Faith Duncan, PE & Greg Hasbrouck, PE

Soci

ety

of W

omen

Eng

inee

rs R

egio

n H

Con

fere

nce

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Project Overview

• US 52 / IL 64 over the Mississippi River• Connecting Savanna, IL to Sabula, IA• Illinois DOT Led Project• Replacing Existing Cantilever Truss Bridge

– 520 ft main span

• Extensive Coordination– Environmental and Permitting– Railroads and Utilities

• Proposed 546 ft Main Span Tied Arch– Steel Plate Girder Approaches– Drilled Shafts with Coffercell Footings

2

Page 2: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

2

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Project Location

W I S C O N S I N

I L L I N O I S

I O WA

3

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Aerial View

• Sabula, IA– “Iowa’s only

island city”– Pop. 576

• Savanna, IL– “Sportman’s

Paradise”– Pop. 2,945

4

Page 3: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

3

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 5

Iowa Causeway

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 6

National Fish & Wildlife Refuge

Page 4: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

4

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

BNSF Railway

7

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Mississippi Palisades State Park & Bluffs

8

Bluffs along IL 84

Page 5: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

5

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 9

Mississippi River & Barges

The Upper Mississippi River System is theonly waterbody in the nation that has beenrecognized by Congress as a “nationallysignificant ecosystem and a nationallysignificant commercial navigation system.”(Section 1103 of the Water ResourcesDevelopment Act of 1986, PL 99-662)

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 10

History

• Constructed in 1932• Savanna-Sabula

Bridge Company• Private Toll Bridge

before being turned over to Iowa

• Illinois took over jurisdiction in 1987

• Listed as a Historic Structure in 1999

Page 6: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

6

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 11

Existing Bridge

• 947 ft Iowa Approach• 282 ft Simple Span Truss• 1,160 ft Cantilever Truss

• 520 ft main span• 78 ft Illinois Approach• 2,468 ft in total length

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Existing Bridge

12

Page 7: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

7

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 13

Open Deck Grate

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Repairs

• Major repairs in 1985• Minor repairs in 1999• Partial replacement of steel

grid deck in 2008– 28 day road closure and $2.9M– Major out cry from public

• Identified more repairs in 2009– $8M repairs + $8M user cost– 9 month closure, 37 mile detour

• Future repairs?

14

Page 8: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

8

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Key Issues

• Structurally Deficient– Entire Iowa approach substructure– Repairs needed for truss spans– Weight Limit

• Functionally Obsolete– 2 narrow 10 ft lanes– Trucks encroach into lane– Tight turning radius– Steel grid deck

• Remaining Service Life– 8 to 10 years in current state

15

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Average Daily Traffic (ADT) over the Mississippi

W I S C O N S I N

I L L I N O I S

I O WA

Dubuque, IAUS 20: 14,600US 61: 20,700

Savanna, IL US 52: 2,400

Fulton, IL & Clinton, IA IL 136: 10,500US 30: 12,600

Quad CitiesI-80: 37,200I-74: 76,700US 67: 30,300I-280: 19,800

16

• Vital Transportation Link– Education, Emergency & Jobs

– Nearest Alternate Crossingo Clinton, IA – 20 miles southo Dubuque, IA – 45 miles north

Page 9: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

9

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Cost & Schedule

17

$5 Million

Phase I

$5 Million

Phase II

$80.6 Million

Phase III

Identified for Replacement

Preliminary Concepts

Public Meeting(June 27, 2012)

Project Initiation

Data Collection

Existing StructureDemolished(Nov, 17 – Jan, 18)

Proposed Bridge Fully Open to Traffic(October 31, 2017)

Letting – Contractor Bids (September 19, 2015)

Plan Submittal(July , 2015)

Approved Project Report

(March 23, 2015)

Approved Environmental Assessment

(October 7, 2014)

Public Hearing(November 19, 2014)

Construction Begins(Mid January, 2016)

Proposed RetainingWall Completed(November 18, 2016)

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 18

Coordination & PartnersPartnersIllinois Department of Transportation (Lead Agency)Iowa Department of TransportationFederal Highway AdministrationParsons Team

Parsons Transportation Group – Prime Wang Engineering – Geotechnical Images – Public Involvement Snyder & Associates – Drainage Dan Brown & Associates – Foundations Michael Baker International – independent check of Tied Arch Design

CoordinationFederal Federal Aviation Administration* Federal Highways Administration US Fish & Wildlife Services US Army Corps of Engineers* US Coast Guard* Tribal Council

State IL & IA State Historic Preservation Office IL & IA Department of Natural Resources* IL & IA Environmental Protection Agency* Upper Mississippi Port District*

Local City of Savanna Savanna Park District Property Owners

Private BNSF Railway* River Industry Utilities (Windstream & JoCarroll Electric) Engineering & Construction Experts*Permitting Agencies

Page 10: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

10

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 19

Little Brown Bats

• Roosting under the bridge and in trees

• USFWS recommended restrictions

• October 1 – March 31

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 20

Shadflies (aka Mayflies)

• Attracted to light

• Males die after mating

• Females die after laying eggs

• Smell like dead fish

• Short adult life

• Swarms

Page 11: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

11

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 21

Bridge for Sale

• Free!• Half mile long steel truss

bridge• Must be kept “in its historical

significance in perpetuity”• Pay moving cost up to the

cost of demolishing it

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 22

Scope of Work

• Phase I– Preliminary Geotech– Geometric Design– Hydraulic Reports– Bridge Condition Report– Bridge Type Study– Public Involvement– Environmental Assessment– Project Report– TS&L Bridge Plans

• Phase II– Final Geotech– Final Roadway Plans– Final Structure Plans– Cost & Time Estimates– Load Rating– Public Communication

• Phase III– Public Communication– Shop Drawing Review– Construction Coordination

Page 12: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

12

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Constraints

• Iowa Causeway– Minimize Environmental Impacts– Minimize Causeway Construction

• Illinois Intersection– Between bluff and railroad– Minimal change to existing IL 84– Tie-in at highpoint– Limit ROW Impact

• Minimize grades to 4% if possible

23

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 24

Navigation Clearance

• Maintain Existing Clearances– Channel near Illinois bank– Steep grade with existing tie-in (> 4%)– Minimal Superstructure Depth

Page 13: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

13

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 25

Navigation Channel Shift

• Approach USCG with Channel Shift– Proposed 200 ft shift to west– Agreed to 150 ft shift to west– Maintain 350 ft channel during construction– 7.5 ft superstructure depth and 4% max grade

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Bridge Type Study

• Evaluated 3 Types– Tied Arch, Cable-stayed, Plate Girder

• Plate Girder abandoned due to structure depth– No supports in navigation channel

• Tied Arch– Basket-handle, vertical w/ bracing, vertical w/o bracing, single

arch– Carried forward basket-handle and vertical w/ bracing

• Cable-stayed– Evaluated various configurations– Carried forward 3 span w/ composite steel girder concrete deck

26

Page 14: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

14

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 27

Bridge Type Study

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Bridge Type Study Evaluation

Criteria– Initial Cost– Inspection & Maintenance– Aesthetics– Durability– Constructability– Environmental Impacts– Structure Depth– Geotech– Hydraulics– Future Widening

Results• Tied Arch

– Float-in Erection– Replaceable Deck

• Cable-stayed– Not fracture critical

• Similar costs• Selected Tied Arch

– Less length of complex structure

– IDOT familiarity

28

Page 15: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

15

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Preliminary Design Development

• Advance Structural Decisions before Final Design– Vessel Collision Study– Approved Design Criteria– Optimized Span Layout / Pier Locations– Foundation Type Study

• Tied Arch Concepts Advanced– Sections defined and sized (H, I, Box)– Floor beam sized and spacing optimized– Hanger arrangement and spacing– Floating deck concept advanced– Stringer fixities defined

• Final Design completed in 12 months to meet schedule29

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 30

Geotechnical

Page 16: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

16

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 31

Geotechnical

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 32

Proposed Structure

Iowa

Illinois

546 ft Tied Arch

8-span Steel Plate Girder = 1420 ft

3-span Steel Plate Girder = 488 ft

Page 17: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

17

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

River Pier Foundations

• Minimal cost aesthetic enhancement for arch piers

• Rock close to surface in IL• 130 ft of sand + on IA side• Deep river pool• Waterline footings

33

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 34

Drilled Shaft with Coffercell

Page 18: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

18

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 35

Tied Arch

• 546 ft span, 100 ft rise, span to rise ~ 5.5:1• Floor Beam Spacing – 31’-9”

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 36

Cross Section

Page 19: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

19

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Floating Floor System

• Replaceable deck with 1 lane of traffic• Stringers spanning over floor beams

– Bearings at center span fixed– Elastomeric bearings elsewhere– Deck full length of span– Allows deck replacement half at a time– Deck connected to tie at center

• Lower lateral K bracing for wind– Braces floor beam at mid-span

• Galvanized floor system– Lengths under 60 ft– Corrosion protection

37

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Tie Girder and Lower Hanger

• Bolted Box Tie full length– Tab plates– 6 ft deep– HPS50W

• Hanger connection offset from Floor beam

– Simplifies detailing

• Connection precompressed• 4 anchor rods provide

redundancy• Shim plates for length

adjustment38

Page 20: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

20

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Arch Rib and Upper Hanger

• Welded Box Rib– Longitudinal stiffener– 5 ft deep

• Hanger connection offset from bracing connection

– Simplifies detailing

• Two hangers – minimize strand size– easier replacement

• Hanger connections bolted to rib

39

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Upper Bracing

40

• X-bracing chosen– Smaller members than Vierendeel– Tension & Compression only– More modern look than K-bracing

• HSS 16x16– Efficient member section– Consistent box section

• Galvanized– Corrosion protection on inside of box– Distinct contrast with blue rib– Low maintenance / impact to traffic

Page 21: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

21

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Redundancy

• Tie Girder– HPS50W and bolted box provides internal member redundancy– Limits propagation of fracture– Still Fracture Critical– Designed for loss of tie web or flange plate

• Hangers– Two hangers per location– Loss of one hanger with fracture dynamic force (FDF)– Loss of both hangers without dynamic force

• Fracture Load Case– 1.1 DC + 0.75 (LL+IM) + 1.1 FDF– LL+IM for 2 striped lanes

41

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Constructability Review

• Provided IDOT a constructability review– During preliminary design phase

• Parsons Construction Group– Experience in Large River Bridge Construction– Identified staging and access areas– Identified potential construction issues

• Provided IDOT a contractor style estimate– Preliminary and Final Design

• In house construction estimating team

42

Page 22: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

22

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

3D Printing Model for Public Communication

• In house capability for conveying signature or complex details

43

On client’s desk!

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 44

Drivers’ Perspective Along IL 84

Page 23: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

23

US 52 / IL 64 OVER THE MISSISSIPPI RIVER 45

Drivers’ Perspective Approaching Arch

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Construction Update

• Sept. 18, 2015 Letting– 5 Bids, Low Bid $80.6M to Kraemer, NA

• Construction Started Mid January 2016 – Clearing & Work Causeway work

• Reviewing Shop Drawings– Tied Arch Steel– Hangers– Bearings

• Reviewing Construction Drawings– Coffercell Construction Details– Tied Arch Cantilever Erection

• Scheduled Bridge Completion – December 2018

46

Page 24: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

24

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Construction Update – West Abutment & Pier 1

47

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Construction Update – Pier 2

48

Page 25: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

25

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Construction Update – Pier 4

49

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Construction Update – Pier 6

50

Page 26: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

26

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Construction Update – Temp Access Illinois Side

51

US 52 / IL 64 OVER THE MISSISSIPPI RIVER

Summary

• Aging Bridge key to local economy• Extensive Coordination

– Environmental and Permitting– Railroads and Utilities

• Replace with new Steel Tied Arch– Improved geometrics

• Keys to Success– Strong Community Support– Early Client Involvement– Preliminary Design Development– Constructability Review from Contractor– Led to efficient Final Design phase

52

Page 27: Faith Duncan, PE & Greg Hasbrouck, PE Replacing …...5/13/2016 1 Replacing the Aging US 52 Mississippi River Bridge February 27, 2016 Society of Women Engineers Region H Conference

5/13/2016

27

Questions?