  • 7/21/2019 Fans Testing & Commissioning Format-r0

    1/13

    CITI EON WING 4 5THFLOOR

    Fans Testing & Commissioning Format

    Document ID: IBS/HVAC/AHU/01

    Testing & Commissioning Consultants:IBS Gulf Design Pvt Ltd

    11, Amirthavanam, Temple View Road

    Srinagar Colony, Saidapet

    Chennai 600 015.

  • 7/21/2019 Fans Testing & Commissioning Format-r0

    2/13

    FANS TESTING & COMMISSIONING FORMAT

    IBS/HVAC/Fan/001

    DOCUMENT CONTROL

    Project Title: Citi EON Wing 4 5 FloorDocument Title: Fans Testing & CommissioningFormat-R0

    Document ID: IBS/HVAC/Fans/001VERSIONVersion No. DescriptionR0 Document prepared for circulation to Project Team.

    Date: Prepared By Checked By Approved By29.12.2014 HS LR LR

    Version No. Description

    Date Prepared By Checked By Approved By

    Version No. Description

    Date Prepared By Checked By Approved By

  • 7/21/2019 Fans Testing & Commissioning Format-r0

    3/13

    FANS TESTING & COMMISSIONING FORMAT

    IBS/HVAC/Fan/001

    CONTENTS

    1.0. INTRODUCTION ..................................................................................................... 4

    2.0. INSTRUMENTS AND DOCUMENTS REQUIRED .................................................. 5

    3.0. METHODOLOGY ..................... ......................................... ...................................... 7

    4.0. TEST REPORT FORMATS ..................................................................................... 8

    5.0. FINDINGS ............................................................................................................. 12

    6.0. SIGNOFF .............................................................................................................. 13

  • 7/21/2019 Fans Testing & Commissioning Format-r0

    4/13

    FANS TESTING & COMMISSIONING FORMAT

    IBS/HVAC/Fan/001

    1.0. INTRODUCTION

    1.1 The Fans commissioning work shall be taken up after completion of installation, ,associated ductwork and necessary electrical cabling works.

    1.2 The fansshall be tested for various performance parameters such as air flow, static

    pressure, noise vibration etc.,

    1.3 Operation of the starters through BMS system shall alsotested.

    1.4 The HRW units, Kitchen exhaust fan, Battery exhaust fan, Pantry exhaust are also be

    tested in similar fashion.

    1.5 All instruments, documents, tools, tackles, ladders, access platforms, personnel,required for the purpose of testing are to bemade available by the vendor.

  • 7/21/2019 Fans Testing & Commissioning Format-r0

    5/13

    FANS TESTING & COMMISSIONING FORMAT

    IBS/HVAC/Fan/001

    2.0. INSTRUMENTS AND DOCUMENTS

    2.1 Documents:

    a. Fan design details such as air quantity, static pressure.

    b. GA drawing of Fans.

    c. Floor plan showing the fan installation location with clearances etc.,

    d. Power and control wiring diagrams of starters.

    e. Preliminary checks to be carried out by vendor as per enclosed format.

    f. Commissioning report test sheets as per enclosed formats with details such as

    Fan ID, Design data duly filled up.

    2.2 Instruments &Equipments Required:

    a. Multimeter, Clamp on meter.b. Digital Thermometer, Sling Psychrometer.

    c. Vane type anemometer, Pitot tube connected to a digital display directly

    displaying velocity and Static pressure measuring probe.

    d. Digital tachometer, preferably non-contact type.

    e. Sound Level meter, Vibration meter.

    f. Set of pre-commissioning filters..

    g. Other tools and tackles required for commissioning as prescribed by the

    manufacturer.

    2.3 All devices shall have a calibration certificatesat the date of test.

  • 7/21/2019 Fans Testing & Commissioning Format-r0

    6/13

    FANS TESTING & COMMISSIONING FORMAT

    IBS/HVAC/Fan/001

    Multimeter Clamp on MeterDigital

    Thermometer Sling Psychrometer

    Vane TypeAnemometer Pitot Tube

    Static measuringprobe.

    Digital Non-ContactTachometer

    Sound Level Meter Vibration Meter

  • 7/21/2019 Fans Testing & Commissioning Format-r0

    7/13

    FANS TESTING & COMMISSIONING FORMAT

    IBS/HVAC/Fan/001

    3.0. METHODOLOGY

    3.1 The Fans have to be commissioned after completion of installation, necessary ducting

    connections, electrical work and pre-commissioning checks.

    3.2 Pre-Commissioning checks included:

    a. Checking that the Fan is installed as per the room layout.

    b. The Fan has been fitted out with pre-commissioning filters(if required).

    c. Ductwork with outlet damper and flexible connections is completed.

    d. Pulley diameters are as per design.

    e. Motor and fan blower rotate freely without touching any unintended surfaces.

    f. All clearances for accessing the filters, motors, damperselectrical panels exist as

    per manufacturers recommendations.g. Starter panel with bypass is installed.

    h. Over load current settings are made appropriately in the starter.

    i. Cabling and earthing for the motor, bulkhead lamp, control wiring for door limit

    switch is completed(for cabinet type fans).

    3.3 Carryout insulation resistance test on the motor and cable.

    3.4 Verify the operation of the door limit switch, bulkhead lamp.

    3.5 Verify the fan motor and fan blower rotate freely without touching any other surfaces.

    3.6 After verifying the incoming voltage,kick start the motor with the belts removed. Verify

    the motor rotation direction. Note down the motor current drawn.

    3.7 Fix the belts, inspect its tightness and then re-start the fan with the outlet damper open to

    50%. Observ for any abnormal noise or vibration.

    3.8 Gradually open the outlet damper while ensuring that the motor current does not exceed

    the rated full load current.

    3.9 Review the recorded parameters critically and lookout if there are any abnormalities in

    the parameters observed.

    3.10 All exhaust and fresh air fans would be tested in a similar fashion with applicable tests

    and parameters.

    3.11 While testing the HRW unit, air DBT and WBT were be measured at fresh air in&out,

    exhaust air in&out. These readings would be verified with the HRW performance

    curves/software.

  • 7/21/2019 Fans Testing & Commissioning Format-r0

    8/13

    FANS TESTING & COMMISSIONING FORMAT

    IBS/HVAC/Fan/001

    4.0. TEST REPORT FORMATS

    A. Pre Commissioning Check List

    Fan ID: Serial No:

    Parameter / Status Yes/NoInstalled as per room layoutVibration isolators providedPre Commissioning filters fixedDuctwork with outlet damper and canvass connection doneMotor pulley and fan pulley are as per designMotor rotates freely without rubbing against other parts

    Fan blower rotates freely without rubbing against other partsAll controls , access doors are accessible and with adequate service spaceStarter panel installed.Cabling and earthing between starter panel and motor completedCabling for bulkhead lamps and control wiring with door limit switch completedOverload set in starter

    Vendors Comments:

    Prepared By:

    Date:

    Signature:

  • 7/21/2019 Fans Testing & Commissioning Format-r0

    9/13

    FANS TESTING & COMMISSIONING FORMAT

    IBS/HVAC/Fan/001

    B. Insulation Resistance Check

    Fan ID: Motor Serial No:

    Description Resistance MegaOhmsCableR-YY-BB-RR-EY-EB-E

    Motor

    W1 W2W2-W3W3-W1W1-EW2-EW3-E

    Vendor:PMC:Testing Consultant

  • 7/21/2019 Fans Testing & Commissioning Format-r0

    10/13

    FANS TESTING & COMMISSIONING FORMAT

    IBS/HVAC/Fan/001

    C. Fan Commissioning Report

    Fan ID:

    Parameter ValueIncoming Voltage R-Y, Y-B, B-RFrequency Hz

    Motor Pulley DiaFan Pulley DiaBelt DetailsStarter overload set atFan working in Auto modeFan working in Manual modeMotor no load currentMotor no load r.p.mAir qty at set static pressureMotor r.p.mMotor currentBulkhead lamp coming On when door is

    opened and cuts off when door is closed.Motor trips when door is opened.Noise level at 1m distance around theFan(pls mark the locations in a separatesketch and enclose)

    Vendor:PMC:Testing Consultant:

    D. HRW TEST REPORT

    HRW ID: SERIAL NO:

    S.No Parameter Value1 Fan installed as per drawing2 Incoming voltage3 Fans working properly in Auto mode4 Fans working properly in Manual mode5 Fan motor currents6 Overload settings8 Design / Actual air quantities9 Desssitant rotor rotation checked.10 Fresh air in/out conditions DBT/RH11 Exhaust air in/out conditions DBT/RH

    Vendor Testing Consultant

  • 7/21/2019 Fans Testing & Commissioning Format-r0

    11/13

    FANS TESTING & COMMISSIONING FORMAT

    IBS/HVAC/Fan/001

    E. BATTERY EXHAUST FAN TEST REPORT

    FAN ID: SERIAL NO:

    S.No Parameter Value1 Fan installed as per drawing

    2 Incoming voltage3 Fan working properly in Auto mode4 Fan working properly in Manual mode5 Hydrogen sensor set at % of LEL6 Fan working on increase in Hydrogen Level7 Fan motor current8 Overload setting9 Fan speed setting19 Design / Actual air quantity

    Vendor Testing Consultant

    PMC

  • 7/21/2019 Fans Testing & Commissioning Format-r0

    12/13

    FANS TESTING & COMMISSIONING FORMAT

    IBS/HVAC/Fan/001

    5.0. FINDINGS

    Testing and Commissioning has to be carried out on the HRW , Fans and the major findingsof the tests are furnished below:

    FINDINGS

    ACTION PROPOSED

    VENDOR PMC TESTING CONSULTANTS

  • 7/21/2019 Fans Testing & Commissioning Format-r0

    13/13

    FANS TESTING & COMMISSIONING FORMAT

    IBS/HVAC/Fan/001

    6.0. SIGNOFF

    We hereby confirm that this report is a true record of the testing and commissioning activitycarried out on the system:

    TestingConsultant

    HVACConsultant

    ProjectManagementConsultant

    HVAC Vendor

    OrganisationName

    IBS Gulf Design

    Witnessed By:

    Signature

    Date