faq no. 4 precast

Upload: sdagnihotri

Post on 03-Mar-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/26/2019 FAQ no. 4 precast

    1/2

    Q ;i Frequently Asked Questions

    Slab On Ground

    Construction

    Answers from the PTI Slab On Ground Committee

    QUESTION

    When converting a ribbed

    slab to a uniform thickness slab, does the ribbed

    slab have to satisfy soil bearing stressrequirements

    based upon the bearing area of the ribs alone before

    the conversion can be made?

    ANSWER No, the ribbed slab must

    satisfy moment, shear and

    diff

    erential deflection

    criteria before being converted (see Section 6.12),

    but it need not satisfy soil bearing stress

    requirements that are based upon the rib widths

    only. Bearing stress requirements under the

    uniform thickness slab must, of course, be satisfied

    based upon the full plan area

    of

    the slab.

    QUESTION Why does Section 7.3 of

    PTI' s Design nd Construction

    of

    Post-Tensioned

    Slabs-On-Ground

    nd

    edition, require the use of

    encapsulated systems when the sulfate levels in the

    soil are considered high?

    ANSWER

    The requirement for

    encapsulation of tendons in elevated soil sulfate

    conditions was incorrect. This oversight was

    addressed during the PTI Slab-on-Ground seminar

    series presented shortly after the publication of the

    nd

    Edition. Since sulfates are not known to cause

    corrosion in steel , the presence

    of

    elevated levels

    of

    sulfates in the so il does n

    ot

    require the use

    of

    an

    encapsulated (aggressive environment) post

    tensioning syste

    m.

    Elevated levels of chlorides in

    the soil,

    or

    environments in which the concrete is

    ex

    po

    sed to direct

    or

    indirect applications

    of

    deicing

    chemicals, seawater, brackish water, or spray from

    these sources, would qualify as an aggressive

    environment , requiring the use of encapsulated

    systems in post-tensioned slab-on-ground

    construction.

    Please note that elevated levels

    of

    sulfates

    in

    the

    soil may require the use of higher strength concrete

    and sulfate resistant cements.

    October

    2 3

    Issue No. 4

    QUESTION

    How much bare stra

    nd

    is

    allowed on a tendon before it needs to be repaired?

    What are the acceptable methods and materials that

    are to be used when repairs are required?

    ANSWER

    The purpose

    of

    the sheathing

    material is two-fold. First, it prevents the concrete

    from bonding to the prestressing steel so that it can

    be tensioned after concrete placement. Second, it

    contains the P-T coating (grease) and serves as a

    barrier against corrosion.

    In an aggressive environment, where the designer

    has specified an encapsulated system, the

    requirements call for the tendon to be completely

    waterti

    ght

    from end anchor to end anchor. T

    hi

    s is

    strictly interpreted that Q prestressing steel is to be

    exposed and that a ll rips, tears, or

    gaps

    in

    the

    tendon sheathing are to be repaired using one of the

    methods described below.

    In a non-aggressive environment, where the

    designer has specified the use of a standard system

    as is the case with

    mo

    st slab-on-ground

    construction, the requirements are typically not as

    stringent as those referenced above for aggressive

    environments. T

    yp

    ically, for standard system

    applications, a maximum of 1 inch of exposed

    prestressing steel is allowed behind the stressing

    end anchors and a maximum of 12 inches is

    allowed at the fixed-end anchors.

    n

    addition, rips

    and tears I inch

    or

    less in length may be l

    eft

    un

    repaired; however, all gaps in the sheathing should

    be repaired as described below. In some non

    aggressive environment applications, the engineer

    may specify more or less stringent requirements

    than those noted above.

    Rips and tears in the sheathing greater than 1 inch

    in length should be repaired according to method 1

    or 2 (described below) in order to protect the

    strand and prevent excess friction during stressing.

  • 7/26/2019 FAQ no. 4 precast

    2/2

    All gaps (total discontinuities) in the sheathing

    should be repaired using only method 1 described

    below.

    Repair Method 1:

    1.

    Restore tendon P-T coating in damaged area

    if

    needed.

    2. Place a section

    of

    split tubing

    or

    a piece of the

    original tendon sheathing over the damaged

    area.

    It

    should overlap approximately 3 inches

    (75 mm) past each end of the original tendon s

    sheathing.

    3. Spirally wrap the entire length

    of

    the repair area

    with tape and extend the tape past the end

    of

    the

    repair section by 3 inches (75 rnm) in both

    directions.

    Repair Method

    2

    Taping can be used in place

    of

    method 1 to repair

    small rips and tears in the sheathing where no

    significant portion

    of the original sheathing is

    missing. Spirally wrap a minimum

    of

    two layers

    of

    repair tape extending a minimum

    of

    3 inches (75

    mm) past the damaged area in both directions.

    3

    (7Smm)

    3

    (75mm)

    Acceptable Material

    PTI s

    pecification or Unbonded ingle trand

    Tendons states that the tape used should:

    be self-adhesive and moisture proof

    be non-reactive with sheathing, P-T

    coating, and prestressing steel

    have elastic properties

    have a minimum width

    of

    2 inches

    have a contrast ing color to the tendon

    sheathing.

    Tests run by PTI have shown that various materials,

    including

    PVC

    pipe

    wrap

    tape, waterproof duct

    tape, and other

    PVC

    and polyethylene tapes, meet

    these requirements and perform as required. The

    testing revealed that the most important factor in

    the performance

    of

    any tape repair is that the

    application of the tape is smooth and that seams,

    joints, and tape wrinkles are kept to a minimum.

    Testing showed that tapes wider than 3 inches were

    very difficult to properly apply without wrinkles

    and still maintain the watertight seal that is

    required.

    3

    SPRI L WR PPED

    T PE

    3

    (7Smm)

    COPYRIGHT

    2003 BY POST-TENSIONING INSTITUTE

    ALL

    RIGHTS RESERVED

    d i

    POST TENSIONING

    llaiiiNSTITUT

    requently Asked

    Questions

    8601

    North Black Canyon Highway, Suite 103

    Phoenix,

    Arizona

    85021

    (602) 8707540

    Fax

    (602) 8707541

    www

    .

    posttensioning

    .

    org

    October 2003

    This

    document is

    intended

    for the use of professionals competent to evaluate the significance and limitations of its

    contents

    and

    who

    will accept

    responsibility

    for the

    application

    of the

    materials

    it

    contains.The

    Post

    Tensioning Institute reports the foregoing material as

    a

    matter

    of

    infonnation

    and

    therefore disclaims any and

    all

    responsib

    tor

    application

    of

    the stated principals

    or tor

    the accuracy

    of the

    sources other than material developed by the Institute. The PostTensioning

    Institute

    in publishing these

    Technical

    Notes makes no warranty regarding the recommendations

    contained

    herein, including warranties

    of quality,

    workmansh

    ip or

    safety

    ,

    express or

    implied, further

    including, but not limited to,

    imolied

    warranties

    ormerchantabilitY

    and fitness for oarticular

    purpose

    THE POST-TENSIONING INSTITUTE SHALL NOT BE LIABLE

    FOR

    ANY

    DAMAGES,

    NCLUDING CONSEQUENTIAL DAMAGES BEYOND REFUND OF

    THE

    PURCHASE PRICE OF THIS ISSUE OF FREQUENTLY

    ASKED QUESTIONS

    The incorporation by reference or quotation

    of

    material

    in

    the Frequently Asked Questions

    in

    any

    specifications, contract

    documents, purchase orders, drawings

    ,or job

    det

    shall

    be done at the

    risk

    of those

    making such reference

    or

    quotation and shall

    not subject

    the Post-Tensioning

    Institute to

    any

    liability,direct or

    indirect, and

    those

    making

    such

    reference or

    quotation shall

    waive any

    claims against

    the

    Post Tensioning

    Institute.

    PRINTED IN