Building Our Future Together
Feasibility Study Presentation IntroductionSouth Kingstown School Committee
Work Session
January 14, 2020
School Building Committee Project Update
• Vestibule Project Update
All of the vestibules have been approved as substantially complete. This allows us to be approved for our reimbursement. There are still some parts of the project that are being worked on but it is important to know that we have met all requirements and are on track with our timeline. (more to be shared during Sub-committee Reports)
• Feasibility Study Update
Tonight we will have a complete presentation of the results of the feasibility study.
2https://www.skschools.net/district/facilities_improvement_program
Building Our Future Together
Agenda from Special School Committee Meeting 10.28.2019
• Essential VALUES of our EDUCATIONAL PROGRAMMING
• Community: Equity, Excellence & the Environment
• District: Professional Learning Community
• Classroom: Deeper Learning & How People Learn
• Assessing our Buildings based upon these VALUES
• Learning from Others
• Current Facilities Improvement Program: Stage 2
• Reconsideration of Our Current Facilities Improvement Program
SC Work Session January 14, 2020 3
Link to October School Committee Meeting Review of Stage 2
Link to October Special School Committee Meeting Asking for Feasibility Study
School Building Information (based up Jacobs Report)
PDES 19246.2 acres574 students$9.6m/$5.1m
WES19648 acres189 students$6.6m/$4.2m
WKES197513 acres242 students$7.1m/$5.7m
MES197514 acres246 students$7.3m/$6.2m
Key1. Number of students is based upon aspirational size
2. Cost is 5 year needs / current year needs
Based upon Jacobs Report
BRMS2001150 acres409 students$8.2m/$3.4m
CCMS196451 acres570 students$15.6m/$10.3m ADMIN
Hazard
SKHS195411 acres1270students$24.7m/$19.4m
Gr Prek-4
Gr Prek-4
Gr k-4Gr k-4
Gr 7-8Gr 5-6
Gr 9-12
4SC Work Session January 14, 2020
Initial Stage 2
PDES WES WKES MES
BRMS CCMS
ADMIN
Hazard
SKHS
$ 12 million Elementary Schools
$ 17 million Broad
Rock
CLOSE
Approx $ 50 million HS
Gr 6-8
Gr Prek-5
Gr Prek-5
Gr k-5 Gr k-5
Gr 9-12
SC Special Meeting, October 28, 2019 5
Does the facility project a special
signature in the local community?
• How does the planning concept relate to our district’s commitment and approach to education?
• How does the design relate to a variety of learning modalities?
• What is the connection between interior and outside space like?
• How is daylight used?
• What kind of views to the outside and interior vistas are present?
SC Work Session January 14, 2020
Innovative Student Centered Learning Grounded in a Collaborative Culture Where ALL MEANS ALL
Community
DistrictClassroom
7SC Work Session January 14, 2020
Learning From Others : Forest Avenue Elementary School
8SC Work Session January 14, 2020
https://www.youtube.com/watch?v=1oH-BURVsGQ
Learning From Others : Forest Avenue Elementary School
9SC Work Session January 14, 2020
PDES WES WKES MES
BRMS CCMS
ADMIN
Hazard
SKHS
Provide upgrades to elementary schools to
support grades Pre K - 5
Same Middle School
Plan: Update to be able
to have the building
support grades 6-8
CLOSE
Use the Stage 2 High
School portion to put an
addition on CCMS and
renovate the remaining
building (as much as
possible)
Gr 6-8
Gr Prek-5
Gr Prek-5
Gr k-5 Gr k-5
Gr 9-12
Reconsideration for Our Facilities Planning: Is it Feasible?
10SC Work Session January 14, 2020
Building Our Future Together
• On November 12, 2019 the School Committee voted to pause the Building Committee’s work on Stage 2 and asked that we instead do a feasibility study to see if Curtis Corner Middle School could be renovated and added on to support South Kingstown High School.
11SC Work Session January 14, 2020
https://www.ride.ri.gov/FundingFinance/SchoolBuildingAuthority/NecessityofSchoolConstruction.aspx
RI Department of Education
12SC Work Session January 14, 2020
Feasibility Study
Presentation
RGB Architects and Peregrine worked together with School Department Leadership and the School Building Committee to:
1. Develop a DRAFT hypothetical site plan
2. Develop a DRAFT hypothetical floor plan
3. Consider the budget with maximum amount in the range of where we were in our initial Stage 2
4. Hire a consultant to perform a traffic study and make recommendations
SC Work Session January 14, 2020
Building Our Future Together
IMPORTANT DATES
• January 8, 2020 9 AM Town Hall
School Building Committee Meeting (includes DRAFT Site Plan Presentation of Curtis Corner SKHS)
• January 14, 2020 6 PM SKHS
School Committee Work Session & Presentation of Curtis Corner SKHS Feasibility Study (followed by Business Meeting)
• January 22, 2020 6:30 PM Curtis Corner Middle School
School Building Committee Meeting (includes tour of Curtis Corner and public comment)
• January 28, 2020 7:00 PM SKHS
School Committee Work Session (Budget Work Session that will begin with vote on Feasibility Study and the direction to provide to the School Building Committee)
• January 14 through January 27
Survey Available for Comment: https://docs.google.com/forms/d/e/1FAIpQLSfhsoXWHfCR0WtCWghfwXYCqIBPKOFdFSfGiI9d8LN5_vLvBQ/viewform
14SC Work Session January 14, 2020
Reminder of the RI Department of EducationHousing Aid Information
15
35% +5%+5%+5%
As of today, we have worked with RI Department of
Education to understand that we
could take advantage of state
funding in the amount of 50% reimbursement.
SC Work Session January 14, 2020
Learning Together.
Growing Together.
Building Our Future
Together.
SC Work Session January 14, 2020
COMMUNITY FEEDBACK FORM Due by Jan 27
LINKS
Town CIP 2019-2020 through 2025-2026 https://www.southkingstownri.com/DocumentCenter/View/2704/FY-2019-2020-FINAL-CIP
Facilities Improvement Program Information http://www.skschools.net/district/facilities_improvement_program
School Building Committee Information https://clerkshq.com//Content/SouthKingstown-ri/Boards/SchoolBldg.htm
Jacob’s Report from ride.ri.gov (http://www.eride.ri.gov/SBA/analysis/combined/South_Kingstown_Combined_LEA_Reports.pdf )
October 2019 Enrollment Report http://go.boarddocs.com/ri/soki/Board.nsf/goto?open&id=BGRLXT58BD4D
Facilities Stage 2 Application: http://go.boarddocs.com/ri/soki/Board.nsf/goto?open&id=BFXJRN4E5CF6
OPM (Organizational Project Management) Peregrine about our Stage II application. This presentation can be founded here:
https://go.boarddocs.com/ri/soki/Board.nsf/files/BGXSYM74FAB9/$file/SK%20Stage%20II%20Evaluation%209.27.pdf
Schools 2.0 Documentary https://www.youtube.com/watch?v=1oH-BURVsGQ
Superintendent’s Goals https://create.piktochart.com/output/40458119-books?presentation=true
Superintendent’s SBC Update for School Committee (Oct 2019)
https://go.boarddocs.com/ri/soki/Board.nsf/files/BGXTBT769C72/$file/SK_SBC_Oct2019_SuperintendentReport.pdf
How People Learn: Taken From http://www.nisl.org/nisl-insights/how-people-learn-an-education-revolution-two-decades-delayed17
Reminder of the RI Department of Education Timeline
18
Reminder of the RI Department of Education Timeline
19