1) Which of the following CANNOT be changed from within the Change Working Time dialog box? A A Resource Availability Profile's Available From and Available To dates. B Working and nonworking time for the Standard calendar. C Working and nonworking time for a resource's Base Calendar. D Setting all Mondays as Nonworking time. E Don't know 2) With a Gantt Chart view currently displayed, the option to show a Project Summary Task is set where? A In the Show/Hide group of the Format tab. B Within the Properties dialog box (selected in the Backstage view). C Within the Project Information dialog box (Project tab, Properties group). D The Task Information dialog box for the task on row 1 of a Gantt Chart. E Don't know 3) You have created additional bar styles to display Free Slack and Total Slack. How do you hide the display of Dependency Links whilst retaining the newly-created bar styles? A Edit the newly-created bar styles in the Bar Styles dialog box and prefix their name with the * symbol. B Use the Select All button to select every task, and then click the Unlink Tasks button. C Use the Layout dialog box (Format tab, Format group). D Use the Gridlines dialog box (Format tab, Format group). E Don't know 4) You have a 10 day Fixed Work task with one assignment of 80 hours at 100% units. If you subsequently assign an additional resource to the task, what will happen to the Assigned Units, Assigned Work and Task Duration values? A The task will be set as 50% complete. B Each assignment would be at 50% peak units to perform 40 hours of work per person. The task's duration remains unchanged. C The total work for the task will increase to 160 hours and each resource will have 80 hours of work to perform. The task's duration remains unchanged. D The task's duration will halve and each assignment will be for 40 hours of work at 100% units. E Don't know

Upload: naeemfaysal

Post on 12-Dec-2015

212 views

Category:

Documents


0 download

DESCRIPTION

features development

TRANSCRIPT

Page 1: features

1) Which of the following CANNOT be changed from within the Change Working Time dialog box?

A A Resource Availability Profile's Available From and Available To dates.

B Working and nonworking time for the Standard calendar.

C Working and nonworking time for a resource's Base Calendar.

D Setting all Mondays as Nonworking time.

E Don't know

2) With a Gantt Chart view currently displayed, the option to show a Project Summary Task is set where?

A In the Show/Hide group of the Format tab.

B Within the Properties dialog box (selected in the Backstage view).

C Within the Project Information dialog box (Project tab, Properties group).

D The Task Information dialog box for the task on row 1 of a Gantt Chart.

E Don't know

3) You have created additional bar styles to display Free Slack and Total Slack. How do you hide the display of Dependency Links whilst retaining the newly-created bar styles?

A Edit the newly-created bar styles in the Bar Styles dialog box and prefix their name with

the * symbol.

B

Use the Select All button to select every task, and then click the Unlink Tasks button.

C Use the Layout dialog box (Format tab, Format group).

D Use the Gridlines dialog box (Format tab, Format group).

E Don't know

4) You have a 10 day Fixed Work task with one assignment of 80 hours at 100% units. If you subsequently assign an additional resource to the task, what will happen to the Assigned Units, Assigned Work and Task Duration values?

A The task will be set as 50% complete.

B Each assignment would be at 50% peak units to perform 40 hours of work per person.

The task's duration remains unchanged.

C The total work for the task will increase to 160 hours and each resource will have 80

hours of work to perform. The task's duration remains unchanged.

D The task's duration will halve and each assignment will be for 40 hours of work at 100%

units.

E Don't know

Page 2: features

5) Start No Earlier Than constraints can be created by which of the following methods?

A Entering an appropriate Constraint Type and Constraint Date within a Task Information

dialog box.

B Dragging a task's bar on a Gantt Chart to the right, changing the task's start and finish

date.

C Typing a date or selecting a date within the Start field against a task.

D All of the above.

E Don't know

6) You have an project that is in progress. How would you select milestone tasks that have been completed?

A Apply the Completed Tasks filter, then apply the Milestones filter.

B Apply the Milestones filter, then use AutoFilter on the % complete column (within the

Tracking table), selecting a % complete value of 100%.

C Apply the Milestones filter, then apply the Completed Tasks filter.

D Apply the Completed Tasks filter, then use AutoFilter on the Duration column, selecting

a duration value of 0 days.

E Don't know

7) In the Leveling Options dialog box, there is an option to 'Level only within available slack'. If this check box is selected, what effect will it have?

A Leveling will delay tasks as appropriate, to ensure that ALL resource conflicts are

removed, extending the project's Critical Path if necessary.

B

Leveling will delay tasks and modify assignments (by editing work and unit values), to ensure that ALL resource conflicts are removed, extending the project's Critical Path if necessary.

C Leveling will delay tasks, attempting to remove all resource conflicts without extending

the project's Critical Path.

D

Leveling will delay tasks and modify assignments (by editing work and unit values), attempting to remove all resource conflicts without extending the project's Critical Path.

E Don't know

8) By default, saving a Baseline will copy which of the following task fields?

A Start will be copied into Baseline Start.

B Early Start will be copied into Baseline Start.

C Late Start will be copied into Baseline Start.

D Preleveled Start will be copied into Baseline Start.

E Don't know

Page 3: features

9) In the Variance table, which of the following would indicate an early-starting task that is due to finish later than planned?

A A positive value in the Start Variance Field and a negative value in the Finish Variance

Field.

B A negative value in the Start Variance Field and a positive value in the Finish Variance

Field.

C A Baseline Finish date earlier than a scheduled Finish date.

D A Baseline Start date later than a scheduled Start date.

E Don't know

10) Which of the following statements about consolidated projects (subprojects inserted within master projects) is TRUE?

A

Inserted subproject tasks are scheduled by the Base Calendar of the master project.

B Inserting subprojects into a master project will automatically share resources between the

inserted subprojects.

C WBS codes for inserted subproject tasks are overwritten with the task's position within

the master project's Outline structure.

D The Gantt Chart view in the master project can have different Bar Styles to the Gantt

Chart view within the subprojects.

E Don't know

Answers

1 A 2 A 3 C 4 D 5 D 6 B 7 C 8 A 9 B 10 D