1) Which of the following CANNOT be changed from within the Change Working Time dialog box?
A A Resource Availability Profile's Available From and Available To dates.
B Working and nonworking time for the Standard calendar.
C Working and nonworking time for a resource's Base Calendar.
D Setting all Mondays as Nonworking time.
E Don't know
2) With a Gantt Chart view currently displayed, the option to show a Project Summary Task is set where?
A In the Show/Hide group of the Format tab.
B Within the Properties dialog box (selected in the Backstage view).
C Within the Project Information dialog box (Project tab, Properties group).
D The Task Information dialog box for the task on row 1 of a Gantt Chart.
E Don't know
3) You have created additional bar styles to display Free Slack and Total Slack. How do you hide the display of Dependency Links whilst retaining the newly-created bar styles?
A Edit the newly-created bar styles in the Bar Styles dialog box and prefix their name with
the * symbol.
B
Use the Select All button to select every task, and then click the Unlink Tasks button.
C Use the Layout dialog box (Format tab, Format group).
D Use the Gridlines dialog box (Format tab, Format group).
E Don't know
4) You have a 10 day Fixed Work task with one assignment of 80 hours at 100% units. If you subsequently assign an additional resource to the task, what will happen to the Assigned Units, Assigned Work and Task Duration values?
A The task will be set as 50% complete.
B Each assignment would be at 50% peak units to perform 40 hours of work per person.
The task's duration remains unchanged.
C The total work for the task will increase to 160 hours and each resource will have 80
hours of work to perform. The task's duration remains unchanged.
D The task's duration will halve and each assignment will be for 40 hours of work at 100%
units.
E Don't know
5) Start No Earlier Than constraints can be created by which of the following methods?
A Entering an appropriate Constraint Type and Constraint Date within a Task Information
dialog box.
B Dragging a task's bar on a Gantt Chart to the right, changing the task's start and finish
date.
C Typing a date or selecting a date within the Start field against a task.
D All of the above.
E Don't know
6) You have an project that is in progress. How would you select milestone tasks that have been completed?
A Apply the Completed Tasks filter, then apply the Milestones filter.
B Apply the Milestones filter, then use AutoFilter on the % complete column (within the
Tracking table), selecting a % complete value of 100%.
C Apply the Milestones filter, then apply the Completed Tasks filter.
D Apply the Completed Tasks filter, then use AutoFilter on the Duration column, selecting
a duration value of 0 days.
E Don't know
7) In the Leveling Options dialog box, there is an option to 'Level only within available slack'. If this check box is selected, what effect will it have?
A Leveling will delay tasks as appropriate, to ensure that ALL resource conflicts are
removed, extending the project's Critical Path if necessary.
B
Leveling will delay tasks and modify assignments (by editing work and unit values), to ensure that ALL resource conflicts are removed, extending the project's Critical Path if necessary.
C Leveling will delay tasks, attempting to remove all resource conflicts without extending
the project's Critical Path.
D
Leveling will delay tasks and modify assignments (by editing work and unit values), attempting to remove all resource conflicts without extending the project's Critical Path.
E Don't know
8) By default, saving a Baseline will copy which of the following task fields?
A Start will be copied into Baseline Start.
B Early Start will be copied into Baseline Start.
C Late Start will be copied into Baseline Start.
D Preleveled Start will be copied into Baseline Start.
E Don't know
9) In the Variance table, which of the following would indicate an early-starting task that is due to finish later than planned?
A A positive value in the Start Variance Field and a negative value in the Finish Variance
Field.
B A negative value in the Start Variance Field and a positive value in the Finish Variance
Field.
C A Baseline Finish date earlier than a scheduled Finish date.
D A Baseline Start date later than a scheduled Start date.
E Don't know
10) Which of the following statements about consolidated projects (subprojects inserted within master projects) is TRUE?
A
Inserted subproject tasks are scheduled by the Base Calendar of the master project.
B Inserting subprojects into a master project will automatically share resources between the
inserted subprojects.
C WBS codes for inserted subproject tasks are overwritten with the task's position within
the master project's Outline structure.
D The Gantt Chart view in the master project can have different Bar Styles to the Gantt
Chart view within the subprojects.
E Don't know
Answers
1 A 2 A 3 C 4 D 5 D 6 B 7 C 8 A 9 B 10 D