featuring results from 2013 public opinion/construction

18
Featuring results from 2013 public opinion/construction surveys April 2014 – Statewide Work Zone Safety Committee Donna Koren, Market Research Director, MnDOT Customer Relations

Upload: others

Post on 09-Feb-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Featuring results from 2013 public opinion/construction

Featuring results from 2013 public opinion/construction surveys

April 2014 – Statewide Work Zone Safety Committee

Donna Koren, Market Research Director, MnDOT Customer Relations

Page 2: Featuring results from 2013 public opinion/construction

Respondents were travelers who signed up for MnDOT’s construction email updates (through Constant Contacts)

I-94 St. Cloud/Clearwater and I-35 Elko/Eagan. Not demographically representative of all

Minnesotans. Experience and opinions likely reflect population segments, and to some extent, travelers in general.

Surveys were web-based, each fielded approx. two weeks.

Page 3: Featuring results from 2013 public opinion/construction

Amount of time spent in construction WZ

Driver Stress

Page 4: Featuring results from 2013 public opinion/construction

Pre-construction, respondents surveyed (February) anticipated a high stress level

Perceived that traffic levels already high (2/3 rated traffic levels “7” or higher)

Didn’t see how it would be workable

Suggested significant mitigation, such as:

Turning the median into a temporary lane (“It’s just grass.”)

Opening up MnPASS lane to all drivers at no cost

Page 5: Featuring results from 2013 public opinion/construction

8% 14% 20% 29% 25% 4%

0% 20% 40% 60% 80% 100%

Completely unacceptable (n=45)

Unacceptable (n=75)

Somewhat unacceptable (n=110)

Somewhat acceptable (n=162)

Acceptable (n=138)

Completely acceptable (n=20)

How acceptable or unacceptable was this delay? N=550)acc

58%

3%

8%

16%

35%

19%

4%

15%

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Typically, how much longer did your trips on weekdays (Monday-Friday) take each way, because of the I-35/I-35E construction? (n=671)

Over 45 minutes longer than usual eachway (n=18)31-45 minutes longer than usual eachway (n=54)21-30 minutes longer than usual eachway (n=110)About 11-20 minutes longer than usualeach way (n=237)Up to 10 minutes longer than usual eachway (n=129)My trip did not take any longer thanusual each way (n=24)I did not travel this route on weekdays(n=99)

58%

Page 6: Featuring results from 2013 public opinion/construction

Life in Minnesota: Strong majority (70%) encountered construction

on the detours or alternate routes that they took at least “sometimes”

Non-compliance with Zipper Merge and HOV

Potential improvements: More signage leading through detours Signage placed far enough for alternate route

decision-making More detailed closure, delays, and alt. route

information in CC emails and on project websites Accuracy is key (roadway signage and website)

Presenter
Presentation Notes
Accuracy – real-time travel time info on roadway and website, accurate start and end times of projects
Page 7: Featuring results from 2013 public opinion/construction

Information (TT, advisories, detour, project)

Driver Stress

Page 8: Featuring results from 2013 public opinion/construction

Perceive that more information enhances roadway safety

Allows them to choose alternative routes Lets them call ahead to business or other

appointments if they will be late.

“I often used the ‘Time to I-35W split’ to gauge the traffic when driving N on CR 2 in Elko. If it said ‘12 minutes,’ that was normal and I stayed on 35. If it had 17 or more, I knew that there was traffic and took the exit to the frontage road. It took the guesswork out of it = less stress. Thanks!” “Useful information I can see without taking my eyes off of the road.”

Page 9: Featuring results from 2013 public opinion/construction

I-94 Survey

I-35 Survey

48%

87%

20%

15% 9%

47%

3%

0%

20%

40%

60%

80%

100%

% of

resp

onse

s

How was the travel time information helpful to you, if at all? (Check all that

apply.) (n=579) I felt less stressedbecause I had informationabout the delays (n=275)

I could take an alternateroute to avoid the delaysor back-ups (n=503)

I could call ahead topersonal appointments tolet them know I would bedelayed (n=116)

I could call ahead tobusiness appointments tolet them know I would bedelayed (n=87)

I could plan when to exitfor a meal or otherneeded travel breaks(n=53)

I felt that having driversinformed of constructionzone delays and alternateroutes enhanced roadwaysafety (n=274)

0%

10%

20%

30%

40%

50%

60%

70%

I felt less stressedbecause I had

information about thedelays

I could take analternate route to

avoid the delays orback-ups

I could call ahead topersonal

appointments to letthem know that Iwould be delayed

I could call ahead tobusiness

appointments to letthem know that Iwould be delayed

I could plan when toexit for a meal or

other needed travelbreaks

I felt that havingdrivers informed ofconstruction zone

delays and alternateroutes enhancedroadway safety

Other

How was the travel time information helpful to you, if at all? (n=258)Note: Respondents could select multiple responses (percent total does not

equal 100%).

Page 10: Featuring results from 2013 public opinion/construction

3% 8% 28% 38% 19% 4%

0% 20% 40% 60% 80% 100%

How frequently did you change your travel route when you saw signs that displayed travel advisories, such as "Stopped Traffic Ahead"? (n=670)

Never (n=23) Rarely (n=54)

Sometimes (186) Often (n=254)

Always (n=129) Don't know/don't remember (n=24)

5%

12%

29%

37%

16%

0% 20% 40% 60% 80% 100%

How frequently did you choose an alternative route to your destination based on the travel times displayed

on roadway signs? (n=597)

Never (n=30)

Rarely (n=73)

Sometimes(n=173)

Often (n=221)

Always (n=93)

Don't know/don'tremember (n=7)

I-35 Post-Construction Survey

85% changed route at least sometimes

82% chose alt. route at least sometimes

Page 11: Featuring results from 2013 public opinion/construction

Most respondents got their information to plan alternate routes either from MnDOT construction email updates (n=337), from MnDOT signage along the route (n=269) or they figured it out as they drove (n=265)

Other common sources of information included mapping/travel web applications (n=183) and MnDOT’s project website (n=135)

35

337 269

135

31

183 265

65 0

50

100

150

200

250

300

350

400

# of

resp

onse

s

Response types

Where did you get your information to plan alternate

routes?

I-35 Post-Construction Survey

Page 12: Featuring results from 2013 public opinion/construction

Over half of respondents (61%) said they always or often had the information they needed in time to plan an alternate route.

9%

29%

46%

15%

0% 20% 40% 60% 80% 100%

How often did you have the information needed in time to plan an alternate route to avoid

construction congestion? (n=668)

Don't know/don't remember (n=7) Never (n=5)Rarely (n=57) Sometimes (n=194)Often (n=308) Always (n=97)

I-35 Post-Construction Survey

Page 13: Featuring results from 2013 public opinion/construction

A sizable minority indicated that there may not be enough signage in the construction zone to guide them through the detour routes.

In addition, 88% said it would be helpful to have information about the length of the detour, (the number of miles).

4%

8%

6%

22%

35%

7%

18%

0% 20% 40% 60% 80% 100%

Regarding detours, to what extent do you agree or disagree that there was enough signage on I-35/I-35E to guide you through the detour

routes? (n=660) Strongly disagree (n=25)

Disagree (n=52)

Somewhat disagree (n=43)

Somewhat agree (n=147)

Agree (n=229)

Strongly agree (n=46)

I did not take MnDOT-designated detours (n=118)

I-35 Post-Construction Survey

Page 14: Featuring results from 2013 public opinion/construction

All on the higher end of the usefulness scale: “Stopped traffic ahead” (84%) Travel time information (64%) Potential delays posted in advance (69%) Zipper Merge instructions (57%) I35 survey 5,6 on 6-pt. scale

Safety messages – not so much. (35%)

Presenter
Presentation Notes
40% on I94 survey, 7-pt. scale
Page 15: Featuring results from 2013 public opinion/construction

2%

7%

17%

32%

35%

6%

0% 20% 40% 60% 80% 100%

1 - Not helpful at all (n=9)

2 (n=16)

3 (n=44)

4 (n=115)

5 (n=217)

6 - Extremely helpful (n=235)

I didn't notice that the signage in this construction zone wasdifferent from any other construction zone (n=36)

For this project, MnDOT used a different approach to inform the public. We posted additional and larger roadway signage, earlier in the project, to explain the upcoming delays and impacts. On a scale of 1-6, how helpful was this information to you? (n=672)

84%

Page 16: Featuring results from 2013 public opinion/construction

I-94 Survey (2013) I-35 Survey (2013)

0% 20% 40% 60% 80% 100%

66%

27%

6%

Very important

Important

Somewhat important

Somewhat not important

Not important

Not important at all

Don't know

As MnDOT makes resource decisions, how important do you think it is to include travel timeand alternate route information signage in construction work zones? (n=278)

6% 33% 60%

0% 20% 40% 60% 80% 100%

As MnDOT makes resource decisions, how important do you think it is to include

travel time and alternate route information signage in construction work

zones? (n=676)

Don't know (n=1)

Very unimportant (n=2)

Unimportant (n=1)

Somewhat unimportant(n=6)

Page 17: Featuring results from 2013 public opinion/construction

Email updates greatly appreciated Suggestions.. Website URL on signage Progress bar on project website with

milestone dates Specific lane closures with times of day Alternate route suggestions

38% used 511 to check traffic conditions

Page 18: Featuring results from 2013 public opinion/construction

Approx. 20 percent telecommuted, and over a quarter worked a flexible work schedule, at least sometimes to avoid congestion.

As possible.. coordinate with county and city construction projects, so that travelers do not take alternate routes into additional construction, are boxed in, or become lost.

More information, well in advance. (Wednesdays before for email updates; signage four weeks in advance, if possible)