feb 17, 2005 [email protected] talking operations
TRANSCRIPT
Feb 17, [email protected]
Talking Operations
INITIAL TMP’s INITIAL TMP’s -- Major Planned Events-- Major Planned Events
OLYMPIAD XXIII - 1984 -- TMP mitigated:
Projections of Huge Traffic Jams Images of Stranded Tourists Missing Events Residents “Scared” into Leaving Town
CONSTRUCTION progress remained a high priority - Motorist inconvenience was secondary..
Travel Info for Motorists was not an organized effort -- Motorists were left to their own resources ..
ConstructionSomewhere
UpAhead
CMS located approximately 12 mi. from the bridge.
Napa River
Bridge
Repaving of a bridge approach section at the Napa River Bridge required the nightly closure of the bridge at 9 p.m. each night.
Desired route Detour
San Francisco
Sacramento
8 of 15 of the Most Congested Cities are in
California
Caltrans’ Caltrans’ MissionMission
To Improve To Improve MobilityMobilityand Safetyand SafetyAcross CaliforniaAcross California
Objective: Minimize motorist delays for ALL activities on the State highway system without compromising public or worker safety, or the quality of the work being performed.
ConstructionMotoristInconvenience
• Key featuresKey features
– A policy based approach to institutionalize work zone processes and procedures, and
– Emphasis on both the broader safety and mobility impacts of work zones
• How it worksHow it works
– Advance work zone considerations as early as possible in project delivery
– Adopt policy and procedures to support systematic consideration and management of work zone impacts
– Develop and implement strategies to manage impacts
– Monitor and assess work zone performance
– Use work zone safety and mobility data to improve policy, processes and procedures
• FHWA support effortsFHWA support efforts
– Develop and provide implementation guidance that addresses every aspect of the new rule by summer 2005
– Contact: Scott Battles, FHWA Office of Operations, 202-366-4372, Contact: Scott Battles, FHWA Office of Operations, 202-366-4372, [email protected]@fhwa.dot.gov
FHWA published the final rule on Work Zone Safety and Mobility in the Federal Register on Sep 9, 2004 -- Effective date of Oct 12, 2007. -- New Rule will affect all State and local governments that receive Federal-Aid Highway funding. -- Purpose of the update is to address the changing times of more traffic, more congestion, greater safety issues, and more work zones
URL: http://dms.dot.gov/docimages/p79295783.pdf
FIRST FIRST STEPSSTEPS1. WE SET UP TWO NEW POSITIONS
• TMP Manager (each of 12 Districts)
• District Traffic Manager (each District)
• WE DEVELOPED TMP GUIDELINES
• WE SET UP A STATEWIDE TMP TRAINING PROGRAM for all involved:
• Traffic Operations
• Project Management
• Design
• Construction
• Maintenance
• We improved coordination by working through our Transportation Management Centers - the Communications “hub” (CMS, Lane Closure …)
TMP PROCESS
Conceptual Planning and Design
Request TMP Data Sheet
What Kind of TMP is
required?
Establish TMP Team (Ops, Design, Traffic, Const, CHP)
START
MAJOR
Prepare Data
Sheet
Arrange forFunding ofTMP Strategies
Detailed Plans & Specs (inc.TMP)
Modify Strategies as
Needed
Start early TMP elements
Begin Construction
Implement TMP
Minor
Maintenance and Permits activities
Blanket
** Modify TMP Strategies as Needed / Monitor traffic initially / Provide Lessons Learned
Six TMP StrategiesSix TMP Strategies
• PP
• MM
• II
• CC
• DD
• AA
ublic Information
otorist Information
ncident Management
onstruction Strategies
emand Management
lternate Routes
TMPs: TMPs: Required for all highway workRequired for all highway work
“ “Blanket” TMPBlanket” TMP ““Major” TMP Major” TMP (~5% (~5% of Projects)of Projects)
No expected delays Off peak Low volume roads Moving lane closures
Significant impacts Significant impacts caused by work caused by work
Multiple TMP Multiple TMP strategies strategies
Multiple contractsMultiple contracts
Minimal impacts caused by work
Lane closure charts required
Some mitigation measures required
“Minor” TMP(Majority)
Portable CMS, FSP, TMT,Off-peak hours
Public Awareness Campaigns, Fixed CMS,
Extended Closures, Moveable Barriers, COZEEP, Detours,
Reduced Lane Widths, Website, Helicopter..
Night Work, Portable& Fixed CMS, COZEEP, TMT, HAR, FSP, “Gawk”
Screens..
Categories and Strategies
PUBLIC AWARENESS STRATEGIESPUBLIC AWARENESS STRATEGIES
Leave Earlieror Later ..
“If you drive I-80, you might want to consider
an alternate route or telecommute this morning…”
Telecommute ..
“Improve Your Driveon the Five!”
Slogans are Easy to Remember..
Advance Awareness of Central Freeway Closure
2%
4%
5%
6%
7%
10%
11%
15%
32%
37%
40%
42%
50%
63%
78%
0% 10% 20% 30% 40% 50% 60% 70% 80% 90%
Public Meetings
Other
Radio "Man in the Street"
Banners
One--Page Flyers
Billboards
Newsletters
Newspaper Ads
Fold-Out Brochures
Word of Mouth
Radio News Reports
Radio Traffic Reports
Freeway Signs
TV News
Newspaper Articles
Percent Remembering
What Did the Public Notice?What Did the Public Notice?
PercentagePercentage
District 04Central Freeway Replacement Project
Metro Traffic
511
Project Characteristics- Full-freeway Closure- On- and Off-Ramps Closed- Extensive Public Info Campaign
Newspaper
TV News
Freeway Signs
Radio Traffic Reports
Radio News Reports
Word of Mouth
Fold-out Brochures
Newspaper Ads
Newsletters
Billboards
One-Page Flyers
Banners
“Man in the Street”
Other
Public Meetings
- - Based on “Based on “00” delay (Const.)” delay (Const.)
- 5 -15 minutes Delay (Maint.)- 5 -15 minutes Delay (Maint.)
- According to District Traffic - According to District Traffic Managers - eliminates about Managers - eliminates about 90%90% of potential delay of potential delay
PROBLEMSPROBLEMS
- Const. windows reduced- Const. windows reduced
- More Night work (Urban/Rural)- More Night work (Urban/Rural)
- Comparative Quality?- Comparative Quality?
- Comparative Safety?- Comparative Safety?
Location:
Remarks:
Legend:
Chart No. _Lane Requirements and Hours of Work
a.m. p.m.
FROM HOUR TO HOUR 12 1 2 3 4 5 6 7 8 9 1011 12 1 2 3 4 5 6 7 8 9 10 11 12Mondays through Thursdays
Fridays
Saturdays
Sundays
1 Provide at least one through freeway lane open in direction of travel
2 Provide at least two adjacent through freeway lanes open in direction of travel
3 Provide at least three adjacent through freeway lanes open in direction of travel
4 Provide at least four adjacent through freeway lanes open in direction of travel
5 Provide at least five adjacent through freeway lanes open in direction of travel
S No lane closure permitted; work permitted anywhere that does not require lane closure
No lane closure permitted; no work permitted
Effective Construction StrategiesEffective Construction Strategies
LANE REQUIREMENT LANE REQUIREMENT CHARTSCHARTS
Assume 1500 vphpl
Other Construction Other Construction Strategies Strategies (Cont.)(Cont.)
• CONSTRUCTION STAGINGCONSTRUCTION STAGING
• DELAY PENALTY --DELAY PENALTY -- “Hammer” for the “Hammer” for the RE to charge the Contractor RE to charge the Contractor ($$$)($$$) for late for late pick-up of the closure .pick-up of the closure .
• EXTENDED CLOSURESEXTENDED CLOSURES (e.g. 55-Hour (e.g. 55-Hour Weekends or 72-Hour Weekdays)Weekends or 72-Hour Weekdays)
• NARROW LANE WIDTHS or USE OF NARROW LANE WIDTHS or USE OF SHOULDERS (PEAK PERIOD) SHOULDERS (PEAK PERIOD)
• MOVEABLE BARRIERSMOVEABLE BARRIERS
• CONTRAFLOWCONTRAFLOW (“Crossovers”)(“Crossovers”)
• CONTINGENCY PLANSCONTINGENCY PLANS (Redundancy)(Redundancy)
Traffic Characteristics
Public Awareness
Motorist Information
Incident Management
Examples of Performance MeasuresExamples of Performance Measures
Personal or Mail-inSurveys, No. of Calls or
Website Hits, PublicMeeting Attendance ..
Personal or Mail-inSurveys, TrafficObservations ..
Accident Response /Removal Time,
Pre- / Post- AccidentRates ..
Traffic Volume Counts,Floating Car Runs,
Queue Lengths, Transit Ridership,
Video Surveillance ..
District 08 I-15 Devore Pavement Reconstruction EXTENDED CLOSURE EXTENDED CLOSURE
- Schedule, Cost & - Schedule, Cost & Delay ComparisonDelay Comparison
Project Characteristics- Pavement Reconstruction - both directions- 3.4-mile segment of I-15 (heavy commute)- Continuous closure
Total Closures
Closure Hours
User Delay
Construction Traffic Handling Total
72-Hour Weekday
8 512 5.6 10.5 2.1 18.2 75
55-Hour Weekend
10 550 14.2 12.5 2.6 29.3 196
1 Roadbed Continuous
2 400 6.9 8.9 1.0 16.8 196
10-Hour Night-time 220 2,200 4.9 19.1 1.3 25.3 36
Est.Delay(Min)
ConstructionScenario
Schedule Comparison Cost Comparison ($Millions)
Construction took ONE MONTH instead of eight, and cost $16 million instead of $22 million. It also put down concrete that will last 30 YEARS instead of 15.
Even commuters who were inconvenienced by traffic tie-ups are telling Caltrans in an online survey that they'd support the approach on future freeway projects, versus traditional nighttime-only closures that take months longer and result in inferior concrete.
How much delay did you experience during the extended closures (SB)?
Do you support the “Rapid Rehab” Approach for future projects?
No 25%
Yes 75%
No 31%
Yes 69%
Asked DuringConstruction
Asked AfterConstruction
None
13%
15 min
18%
30 min
22%
45 min
20%
60+ min
27%
Others11%
PreferNight-time or
weekend64%
Cancel project14%
Add lane4%
Continuous7%
Negative Public Reaction to 72-hour Weekday Closures (Victorville Public Mtg)
District 08 I-15 Devore Pavement Reconstruction
• PUBLIC AWARENESS • Newspapers and TV spots (“low-cost”)• Traffic Reporting Services
• ADVANCE SIGNAGE • Before Decision Point / Monitor Route • Test on Preceding Week/Weekend
• ADHERE TO LANE REQ’MT CHARTS • Use Updated Charts / Volumes on shelved projects• New Lane Closure System assists in providing Real-Time conditions
• KEEP LANES OPEN• Narrow Lane Widths / Shoulder Use• Night versus Day Closures? • Extended Closures?
LESSONS LESSONS LEARNEDLEARNED
PUBLIC AWARENESS:
Trav InfoMakes Decisions
Easier
ControlConstruction
Windows
• MONITOR & DEBRIEF PROJ ENGR AFTER CONSTRUCTION
• TMP TRAINING goes a long way • Train all participants• Educate re: Traffic Ops Role - improves coordination
• UPDATE TRAFFIC PROJECTIONS
• Recheck Volumes for “Benched” projects before Bid• Check for other changed conditions (e.g. new shopping mall)
• STREAMLINE TMP PROCESS (“Cookbook” method)
• Blanket / Minor Projects (Standardized Forms)• Major Projects (More strategies!.. Public info blitz)
• INCLUDE $$ FOR MONITORING• Delay Runs to determine inconvenience to motorists• Traffic counts of main segments AND possible detours
RECOMMENDATIONSRECOMMENDATIONS
Sample Unit Costs for Sample Unit Costs for TMP StrategiesTMP Strategies
• Hiring Consultant to do TMP• Billboards• Radio Ad • Newspaper Ad (1/2 page, color)• Open House
• TV Commercial (Local)• Permanent Changeable Message Sign• Portable CMS• Portable Highway Advisory Radio• Ground-mounted signs
• Extra Enforcement (State Police)• Moveable Concrete Barrier (Transport Machine Rental)• Temporary Signal
$250,000+$3,500/month$800/minute$14,000/day$3,000
$4,000+$300,000$10,000$60,000/unit$300 each
$1000/night$100,000/6 months$30,000
EA
PROJECT LIMIT
PROJECT DESCRIPTIONTYPE OF WORK
LENGTH OF JOB
A) The project includes the following:(Check all applicable type of facility closures.)
Highway or Freeway LanesHighway or Freeway ShouldersFreeway ConnectorsFreeway Off-rampsFreeway On-rampsLocal Streets
B) Are there any construction strategies that can restore existing number of lanes?Yes___ No___ (Check all applicable strategies.)
Temporary Roadway WideningStructure Involvement ?Yes ___ No ___ If "Yes", notify Project Manager.Lane Restriping ( Temporary narrow lane widths)Roadway Realignment (Detour around work area)Median and/or Right Shoulder UtilizationUse of HOV lane as a Temporary Mixed Flow LaneStaging Alternatives ( Explain Below)
Most of the time, work is off the travell way
C) Calculated Delay (To be performed if construction strategies in Item B do not mitigate
congestion resulting from Item A or on all projects along Interstate 5 and Route 99).
1. Estimated Maximum Individual Vehicle Delay Minutes
2. Existing or Acceptable Individual Vehicle Delay Minutes
3. Estimated Individual Vehicle Delay Requiring Mitigation [(1)-(2)] Minutes
4. Estimated Delay Cost ( Most Applicable ) Extended Weekend Closure $
Weekly ( 7 days ) $5. Estimated Duration of Project Related Delays # of Days
6. Cost of Construction Related Delays [(4) x (5)] $7 Delay Calculation for Damage Clause $
CO/RTE/PM-KP
Operation: Multilane Closure
RTE Location:
Percent Truck: 0.0% Cost per Truck: $24/Veh-HrPercent Passenger Cars: 100.0% Cost per Passenger Car: $9/Veh-Hr
Number of Lanes Existing:4 Lanes Cost for Mixed Flow Traffic: $9/Veh-HrNumber of Lanes Open: 2 Lanes Single-Lane Capacity: 1500 Veh/Hr
Open-Lane Capacity: 3000 Veh/Hr
TimeDemand
(Veh)
Cml Demand
(Veh)
Cml Capacity
(Veh)
Difference (Veh)
Area (Veh-Hr)
Queue Length (mile)
Indiv. Delay (min)
6 AM 0 0 0 0 0 0
7 AM 5309 5309 3000 2309 1154 2.7 46
8 AM 6945 12254 6000 6254 4281 7.4 125
Count Date: 5-3-2001
Max. Individual Delay: 125 minutes
Vehicle Delay Hours:5,436 veh-hrTotal Cost of Delay: $48,924Delay Cost/10min: $4,077
Sample Delay Calculations Sample Delay Calculations (“Moskovitz Curve”)(“Moskovitz Curve”)
0.0
Demand vs. Capacity
0
2000
4000
6000
8000
10000
12000
14000
6 A
M
7 A
M
8 A
M
TIME
CU
MU
LA
TIV
E V
EH
ICLES
Demand Capacity
No. of Veh.In QueueNo. of Veh.In Queue
IndividualVeh. DelayIndividualVeh. Delay