federal democratic republic of ethiopia...
TRANSCRIPT
FEDERAL DEMOCRATIC REPUBLIC OF ETHIOPIA
URBAN WATER SUPPLY AND SANITATION
PROJECTS: SOCIAL AUDIT of
Hawassa Water Supply and Sanitation Project
AND
Jimma Water Supply and Sanitation Projects
FEKADU ADUGNA (PhD)
March 2012
E1566 v2 P
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
edP
ublic
Dis
clos
ure
Aut
horiz
ed
Contents Acronyms ............................................................................................................................................................. 3
Acknowledgments ................................................................................................................................................ 4
1 Social Audit for Ambowuha Spring Development at Hawassa Water Supply and Sanitation and Jimma
Water Supply and Sanitation Project ................................................................................................................... 5
1.1 Background .......................................................................................................................................... 5
1.2 Objectives of social audit ..................................................................................................................... 6
1.3 Expected output .................................................................................................................................... 6
1.4 Methods of data collection ................................................................................................................... 6
2 Field report ................................................................................................................................................... 7
2.1 Ambowuha Spring Development at Hawassa Water Supply and Sanitation Project ........................... 7
2.1.1 Land acquisition/expropriation .................................................................................................... 7
2.1.2 Land acquisition at the spring site ................................................................................................ 7
2.1.3 Land acquisition on the transmission line .................................................................................... 7
2.1.4 Land acquisitions at the reservoir site.......................................................................................... 8
2.1.5 Affected Fences .......................................................................................................................... 10
2.1.6 Consultations and grievance addressing mechanisms ............................................................... 10
2.1.7 Adverse livelihood impacts ........................................................................................................ 10
2.1.8 Adverse social impacts ............................................................................................................... 11
2.1.9 Lesson learned ............................................................................................................................ 11
2.2 Jimma Water supply and Sanitation Project ...................................................................................... 11
2.2.1 Land acquisition/expropriation .................................................................................................. 11
2.2.2 Loss of other assets ..................................................................................................................... 12
2.2.3 Consultations and grievance addressing mechanisms ................................................................ 13
2.2.4 Adverse livelihood impact .......................................................................................................... 13
2.2.5 Adverse social impact ................................................................................................................ 13
2.2.6 Lesson learned ............................................................................................................................ 14
3 Legal Framework for Expropriation and Compensation ............................................................................ 14
4 Concluding remarks ................................................................................................................................... 15
5 Recommendations ...................................................................................................................................... 16
References .......................................................................................................................................................... 16
Page 3
ACRONYMS
ESIAS Environmental and Socio-economic Impact Assessments and Safeguards
ESMF Environmental and Social Management Framework
FGD Focus Group Discussion
PAP Project Affected People
UWSSP Urban water supply and sanitation programs
Page 4
ACKNOWLEDGMENTS
A number of individuals contributed to the successful completion of this social audit. First and for
most, I am grateful to the project affected peoples (PAPs) who shared with me their views and
attitudes about the water projects. I am also thankful to Ato Letta Yetamo, manager of Hawassa
Water Supply and Sanitation Enterprise, and his colleagues Ato Demissie and Yohannis who
accompanied me during my visits to the water construction sites and for collecting all relevant
documents respectively. I am highly indebted to Abdu Mohammed Abba Fogi, manager of Jimma
water supply and sanitation project and his affectionate staff members: Ismael Abba Jihad, Ahmed
Kedir, and Awal Mohamed. Abdu accompanied me to all the water construction sites, to some of
them two times, exhaustively explained to me all the details and socialized me in Jimma when my
health was rather flimsy.
Page 5
1 SOCIAL AUDIT FOR AMBOWUHA SPRING DEVELOPMENT AT HAWASSA WATER SUPPLY AND SANITATION AND JIMMA WATER SUPPLY AND SANITATION PROJECT
1.1 Background
Ambowuha Spring Development at Hawassa Water Supply and Sanitation and Jimma Water Supply
and Sanitation Projects are two of the five World Bank funded urban water supply and sanitation
programs (UWSSP) in Ethiopia. The remaining three are Addis Ababa, Mekele and Gonder. The
main objectives of the project are (i) to increase access to sustainable water supply and sanitation
services for the dwellers; (ii) improve the lives and health of the people living in the town; and (iii)
promote investment and economic development oriented interventions. This includes increasing
water production, expand distribution network to un-served and low-income areas (ESIA, 2010).
The following is brief introductory information on the projects of the two cities included in this
social audit: Hawassa and Jimma. Hawassa is a capital city of Southern Nations Nationalities and
Peoples Regional State (SNNPRS). It is a flourishing and expanding city that recently witnessed new
public institutions and numerous private businesses. This has caused shortage of water. The selected
source of water is Ambowuha spring and other two smaller springs: Tunto and Shallo. While the first
two are very close to each other (less than one hundred meters), Shallo is located at about one
kilometer and a half from the two. According to the initial study, Ambowuha, Tunto and Shallo yield
57 liters per second, 5 liters per second and 10 liter per second respectively (ESIA, 2010). All the
three springs are located in Shasha Kekele kebele of Wondo woreda, Oromia National Regional
State. The kebele had been part of the Hawassa Zuria woreda, Sidama Zone of the SNNPRS until the
referendum that took place in 2008. The water project built three cattle troughs and two washing
basins that can accommodate eight people at a time on Shallo spring for the people around the source
of the spring. Two communal water tabs have also been constructed for the nearby village. Initially
the plan was to give 5 liters per second for the people around the source of the spring from the 10
liters per second the Shallo spring can produce. Currently, they are negotiating on increasing the
amount of water and expanding the communal water tabs to the other nearby villages.
Jimma is situated in southwestern Ethiopia in Oromia National Regional State at 352 kilometers from
Addis Ababa. Jimma water supply and sanitation project is a big project that includes rehabilitation
of intake structures, replacement of old water pumps, numerous constructions at the new water
treatment plant, and three reservoirs. An old water pump that conveys raw water from intake
structures on Gilgel Gibe River to the new water treatment plant located at Boye has been replaced
by new ones. A new pipeline that conveys clean water from the new water plant at Boyye to two big
reservoirs at Jiren Kella and then to the Ginjo booster station and a small reservoir at Abba Jifar site
is under construction.
Page 6
1.2 Objectives of social audit
The objective of this social audit is to validate the extent of the impact of the Ambowuha spring
development at Hawassa water supply and sanitation project and Jimma water supply and sanitation
project on land and/or people (land acquisition, resettlement and livelihood restoration of the affected
people) and to confirm and corroborate whether farmers and other households have had land
acquired, been resettled, and if so have been compensated for the loss of land and other assets as
detailed in the Environmental and Social Impact assessment of the two projects. Specifically the
audit will establish:
What compensations and livelihood restoration packages were provided to all affected
persons including the farmers whose land has been acquired;
What percentage of land was acquired from each of the farmers;
Was there loss of any other assets such as trees, tukuls, water source, grazing land, etc.
Were any of the farmers or other households, tenants or businesses affected and, if so what
assets have been lost and have they received compensation for these assets?
Whether farmers or other households were satisfied with the compensation packages offered
(with particular focus on female headed households and other vulnerable groups);
Whether farmers or other households were consulted in the process of determining the
compensations;
Whether grievance mechanisms and procedures are put in place and affected persons are
adequately aware of;
Whether there have been adverse impacts on livelihood of farmers as a result of the land
acquisition; and
Whether there are potential adverse social impacts that could be caused by the project.
1.3 Expected output
A short report of key findings regarding the points outlined above, key lessons learned and
recommendations.
1.4 Methods of data collection
The data for this report was collected both from secondary and primary sources. Secondary
documents such as ESMF, RPF, ESIA and other official documents, minutes of meetings concerning
project affected people and the compensations they received are properly consulted. On top of that a
brief semi-structured and in-depth interviews, focus group discussions (FGDs) and site observations
were used. In Hawassa, the consultant conducted six detailed interviews with PAPs, four with
relevant officials from Kebele chairman up to the mayor, and two focus group discussions: one with
representatives of the affected religious institutions and one with affected households. In Jimma, the
Page 7
consultant interviewed five of the seven PAPs, the water project officials, the relevant administration
officials and the consultant undertook one FGD with the Jimma city administration’s compensation
committee members.
2 FIELD REPORT
2.1 Ambowuha Spring Development at Hawassa Water Supply and Sanitation Project
2.1.1 Land acquisition/expropriation
Plots of land belonging to 24 households and institutions have been acquired by the Ambowuha
water project: 1 at the spring development site and 23 at the Eredo reservoir site. The transmission
line also acquired some land from ELFORA Agro-Industry PLC. This social audit describes the land
acquisitions; mitigation measures taken; checks whether the mitigation measures were consistent
with the provisions given in the RPF of the project and ESIA; and summarizes the PAPs’
compensation. A separate appendix (not disclosed) provides specific details of individual PAPs by
comparing the matrix of actual compensation paid with the estimated compensation in ESIA.
2.1.2 Land acquisition at the spring site
Of the three springs that constitute Ambowuha water project one spring (Ambowuha) is situated
within a privately owned plot. The area was owned by an individual.. The water project expropriated
968m2 out of his total 12000m2 plot of land. He lost less than 9% of his farmland. This spring side
plot has been used for crops such as cabbage, potato, maize, pepper and some perennial trees
specifically eucalyptus trees. The owner is a young entrepreneur engaged in multiple businesses and
diverse income generating activities. He has a lorry; houses in Wondo, Shashemene and Hawassa,
and he is a salaried civil servant. The loss of the plot of land did not affect his livelihood, and even he
did not claim compensation. However, based on estimation report from Wondo Woreda Agriculture
Office, Oromia Regional State, to which the spring area belongs, he was paid 15,000 Birr
compensation, which is in line with the environmental and social impact assessment as well as the
provisions of the RPF.
2.1.3 Land acquisition on the transmission line
A 9.3 kilometers long transmission pipeline is constructed from the spring source at Ambowuha to a
reservoir station situated on Eredo hill, at the periphery of Hawassa city. Around 80% of this (7.4
kilometers) are situated within ELFORA Agro Industries PLC, a private investment venture. The
investor uses most of the land for grazing and only insignificant part is cultivated. The impact of the
transmission pipeline on ELFORA Agro Industry PLC was mostly temporary as after the pipe was
buried underground the land can serve whatever purpose it was meant for. The owner of ELFORA
Agro-Industry allowed the water project without claim to any compensation. During the brief
fieldwork, the consultant visited a culvert where the pipeline crosses Tikurwuha River partly situated
within the ELFORA site (see the picture below). The consultant also spoke to a tractor driver who
Page 8
was on duty and he said he was instructed by the ELFORA authorities to make a maximum care for
the pipeline around the culvert where it is laid above the ground. That shows the attitude of the staff
of ELFORA Agro Industry PLC towards the water project. The remaining pipeline passes through
public land including the Tikurwuha swamp, which is in fact consistent with ESIA.
Picture1: The transmission line crossing the ELFORA field (left), and the Tikurwuha swamp and the
river (right)
2.1.4 Land acquisitions at the reservoir site
The reservoir was built on the top of Eredo hill. The main selection criterion of the area for building
the reservoir there was its elevation which makes it suitable to pump down the water by gravity to
supply the eastern part of Hawassa city where important institutions such as Hawassa University are
located. It was built in a compound of 32,000m2 wide out of which 17,457m2 was expropriated from
three churches (Catholic, Hiwot Birhan and Mekane Yesus), a mosque and 17 households and a land
held by a kebele youth association. Of these three churches, Hiwot Birhan and Mekane Yesus had
two plots of land in the compound. Catholic Church lost 3600m2. Two churches under the name
Hiwot Birhan each of them lost 3294m2 and 1848m2 and two churches of Mekane Yesus each of
them lost 1848m2 and 1925m2 . The mosque lost 716m2. Their properties on the land range from a
simple wooden fence to a medium size house. Only Mekane Yesus church had constructed a medium
size mud house to use as a church on one of the plots and the mosque started a construction of a
small size house. Compensations were properly calculated for fences, crops and the mud house in
adherence to the law of the land, which is also in line with the approved RPF. The calculations were
made by construction and agricultural experts and paid as per the ESIA.
While Catholic Church, the two churches of Hiwot Birhan and one of Mekane Yesus churches
satisfied with the compensation arrangements, the other Mekane Yesus church which built a small
house and the mosque filed their complaints following the grievance airing mechanism of the project.
They filed their complaint at the Hawassa water and sanitation enterprise office and the city
administration. Their complaint was that they prefer land for land substitution to cash for land, and in
the absence of that they asked to raise the amount of compensation. The original amount of
Page 9
compensation calculated by the experts and recorded in ESIA was 44,064 Birr and 4560 Birr for the
Mekane Yesus church and mosque respectively. The mayor of Hawassa city was involved in the case
and had set up a special committee to investigate their complaints. After protracted negotiations
between the church and the mosque officials on one side and the especial committee established by
the mayor on the other side for more than six months, they agreed on raising the amount of cash
compensation. Accordingly, compensation for Mekanne Yesus raised to 95,200 Birr and that of the
mosque to 20,686 Birr. Officials of the Mekane Yesus church and the mosque agreed on the new
amount and received the money while I was in Hawassa for this fieldwork.
Picture2: The Mekane Yesus Church (left) and the construction begun on the land given to a mosque
(right)
As mentioned above, besides these religious institutions, 17 households and the kebele Youth
association have lost plots of land and properties at the reservoir site. The land lost ranges from 24m2
to 640m2. One of them is a female headed household. None of them built a house on the land. These
are farmers who came from rural areas and were given land in the periphery of Hawassa by the
lowest level administration, the kebele chairman, and all of them have no ownership certificate and
any other document that shows the plot of land belongs to them. Most of them fenced the plots and
cultivated maize and haricot bean for one or two seasons. Actually, that site had been allocated for
the water reservoir and the occupation by these farmers was a misunderstanding from the kebele
administration. Notwithstanding the fact that none of them produced any ownership certificate, the
water project paid them appropriate compensation for the properties they had on the plot of land
based on the estimation done by the construction and agricultural experts. All compensations were in
cash. Although some PAPs would have preferred land for land compensation to cash for land, the
Hawassa city administration could not do that because based on the decision of the council of
SNNPRS urban land allocation for any purpose has been temporarily banned in the region. All of
them have received their cash compensation, which is consistent with ESIA, without filing any
complaint. Both for the religious institutions and the individual household the calculations and
compensations have been made as per the procedures put in place by the GOE and the World Bank’s
safeguard requirements in line with the provisions of the approved RPF of the project.
Page 10
2.1.5 Affected Fences
The road from the main highway to the reservoir site expanded by the water project for the
transportation of construction materials during the construction of the reservoir damaged 27
households’ fences. All of them are adequately compensated for the damages. The compensation was
calculated based on the market price of the damaged fence and the labour it requires to construct the
fences again consistent with the ESIA study and the provisions in the RPF. Six of these were
mentioned in the ESIA, and the remaining were affected during the construction phase.
2.1.6 Consultations and grievance addressing mechanisms
Hawassa Water Project and City Administration officials put in place a consultation and grievance
addressing mechanisms as per the RPF. Consultations are made at different levels between the PAPs
and the Project officials. The water project officials first of all contacted the PAPs either through
personal contacts (that was how they discussed with the PAP at the spring site) or officially through
kebeles. In both cases the initial contacts were to inform the PAPs about the project, its positive and
adverse impacts and about the expected compensations. The next step in both cases was writing
letters to the concerned offices (Tula sub-city and Hawassa city administration) about the calculation
of compensation. For instance, a letter was sent to Wondo woreda administration, Oromia regional
state, to calculate compensation for a PAP at the source of the spring. Another letter with the list of
PAPs and the type and amount of loss was sent to Tula sub-city administration and the Hawassa city
administration. A compensation committee that included experts of agriculture and construction was
set up to calculate the appropriate compensation. It was this committee that calculated all the
compensations. The Committee made a number of discussions with the PAPs. In case of complaints,
the committee informs the PAPs that they have the right to file their grievances to the higher city
administration offices. Officials of Mekane Yesus church and a Mosque insisted on their complaints,
as discussed above, and finally appealed to the mayor. The mayor established a special committee to
address their grievances and that committee actually negotiated with the PAPs and reached on
solutions that satisfied both sides. All the PAPs the consultant spoke to are at least informed about
the fact that they can present their complaints to higher officials.
2.1.7 Adverse livelihood impacts
The Ambowuha water project did not cause any physical household displacement. No settlement is
affected. In terms of proportion, no significant loss has been registered, and they are properly
compensated for the losses: mostly fences, crops and cropland, and trees. Thus, no adverse livelihood
impact has been observed. To the contrary, people residing around the spring are going to benefit
from the water project. The project has built cattle troughs, washing basins and road that enormously
impact on the livelihood of the cattle rearing surrounding communities. The local communities are
also negotiating with the officials of the project on the way to use the electricity line recently
extended up to the source of the spring.
Page 11
2.1.8 Adverse social impacts
Some of the project’s affected are religious institutions. This is more related to the socio-cultural
sphere rather than livelihood. That could have evoked OP 4.11 in the World Bank safeguard policy.
However, most of them simply fenced it and cultivated crops for one season, and only one church
constructed a mud house, which has not started to serve as a religious centre. The water project and
the municipality have managed to settle the difference with the affected churches and mosque
peacefully and smoothly through flexible compensation arrangements and grievance addressing
mechanisms as per the approved RPF. Thus, no adverse social impact has been observed.
2.1.9 Lesson learned
Hawassa water supply and sanitation enterprise in collaboration with the Hawassa city administration
has been working on the Ambowuha water project affected people for more than one year. Now all
the affected PAPs and the religious institutions have accepted the compensation arrangements and
received the cash compensation. The water project officials have acquired enormous experience from
the processes. The big lesson they have learned is the value of engaging the concerned people in the
process and making intensive and all inclusive consultations. In the consultations the PAPs, the water
project officials and the city administration officials from the kebele up to the mayor involved.
Especially the grievance addressing mechanism through which they solved the complaints of the
Mekane Yesus and the Mosque is the best instruction they acquired for the future endeavors. The
continuous reshuffling of administrators (since the start of the water project many relevant officials
have been changed including the mayor and the sub-city administrator) has been mentioned by the
water project officials as a major difficulty they faced in the process of dealing with the PAPs.
2.2 Jimma Water supply and Sanitation Project
2.2.1 Land acquisition/expropriation
A total of seven households have been affected by the Jimma water supply and sanitation project.
Four households lost plots of land permanently at two reservoir areas: three of them at the Jiren Kella
reservoir and one at the Abba Jifar reservoir sites. The loss ranges from 25m2 to 200m2. Assets of
three individuals are affected by pipeline and constructions without permanently expropriating their
land. All PAPs have been appropriately compensated based on the suggestions of the ESIA and the
provisions given in the PRF for the project. In this part too, the land acquisition, mitigation measures,
and cross-check with the ESIA and the approved RPF will be described. The Jiren Kella reservoirs
are under construction within state owned forest on 2800m2 the water project was given from the
municipality. Thus, the Jimma water supply and sanitation project and the municipality officials did
not expect any PAP there. In fact, the ESIA also did not mention any PAP at these reservoirs site.
However, in the course of implementation, three people who live in the neighbouring Sarbo woreda
claimed that their plots of land (100m2, 80m2, and 25m2) have been expropriated at the site of the
reservoir. According to the PAPs they used to live there until they were displaced by the Derg
villagization program in the late 1980s, and they have continued to harvest coffee and use some
Page 12
remnants of trees existing on the plots of land. From the municipality officials point of view these
individuals are illegal encroachers on state forest. Regardless of these divergent views on their
ownership rights, based on World Bank’s safeguard policies all the three households are properly
compensated for the properties they lost as a result of the land acquisition. They were compensated
for perennial crops they had over the plots of land, such as coffee, chat (qhat), and trees. The PAPs
were paid, respectively ten thousand Birr, seven thousand Birr, and two thousand Birr, based on their
losses.
At Abba Jifar reservoir site the project acquired 200m2 land belongs to an individual. This man, a
descendant of Abba Jifar II, the last monarch of Jimma, had some old coffee trees and banana trees
on the land. He was compensated 11715 Birr for the properties. In an interview with him, the owner
told me that he has another large plot of land and two houses other than the one near the reservoir.
“Though the money buys very little thing in the current market”, as he said, “the coffee trees are also
getting older and older and yield very little”, which he mentioned to tell me his relative satisfaction
with the compensation he was paid. As it can be seen from the picture below the reservoir is
constructed very close to his house, and as the person has another two houses, one in the same village
and the other one at five kilometers distance, he is currently negotiating with the water project
officials to sell the house to the project. In that case, the water project would get a relaxed space, and
partly use it for office.
Picture 3: A reservoir under construction at Abba Jifar site
2.2.2 Loss of other assets
The PAPs in Jimma water supply and sanitation project are compensated for loss of assets mostly
perennial crops and trees. Other than the four individuals affected at the Jiren Kella and Abba Jifar
reservoirs sites, assets of three individuals are affected by pipeline and constructions without
permanently expropriating their land. They lost coffee trees, chat, banana and eucalyptus trees. All
the three are properly compensated per the requirements of the RPF. In general more than 300 coffee
trees; 1 banana tree; 28 chat; 133 cypress and 100 eucalyptus trees belonging to private owners are
damaged and the owners are compensated. All the PAPs are compensated for the loss of assets as per
the provisions of the approved RPF. Besides, the pipeline from the Boye new water treatment plant
Page 13
to the reservoir in Jiren kella and a 0.9 km new road constructed on the same line damaged about 170
eucalyptus trees and cypress trees from the state owned Jiren forest. The trees are properly collected
and handed over to the Oromia Forest Management, which officially administers the forest. These
are consistent with the details mentioned in ESIA.
2.2.3 Consultations and grievance addressing mechanisms
The Jimma Water Supply and Sanitation Project officials and the city administration are consistent in
conducting consultations with the project affected people. The project usually reports in advance to
the kebele the sites where they are going to construct, for instance, a reservoir or design of a pipeline.
Then, the kebele officials inform individuals whose property will be potentially impacted. This
initiates consultations between the project and the PAPs. Based on the consensus of the PAPs the
project requests the city administration’s compensation standing committee to calculate their losses.
The compensation committee is constituted by representatives from the Mayor’s office (construction
department), land administration, urban agriculture, security and the kebele administration. An
agricultural expert and a construction expert are always part of the compensation committee and play
a pivotal role in the calculation of the property lost. The PAPs and the compensation committee visit
the impacted site together and agree on the type and amount of losses, share views on the calculation
of compensation.
In case they disagree with the compensation committee’s suggestions, the PAPs are informed the
way to air their grievances. In that case, the PAPs file their complaints at the mayor’s office, and the
mayor establishes a special committee to address a specific grievance. So far, this did not happen.
The compensation procedures have been handled smoothly.
2.2.4 Adverse livelihood impact
Notwithstanding the various constructions underway, Jimma water supply and sanitation project has
no adverse livelihood impact. To date, seven individuals have been affected by the project. There is
no physical displacement of a dwelling unit. In terms of proportion, the loss by each of them is less
than 10% of what they have. Most of them lost commercial crops such as coffee, chat, and trees. All
of them are dully compensated. Besides, the individual who lost more than 200 coffee trees at the
Jiren Kella reservoir site (which is the major loss in terms of cash crop) was given an employment
opportunity by the project, in addition to cash compensation, to support his household. Therefore, so
far there is no adverse livelihood impact. All the compensation procedures took place with great
consensus.
2.2.5 Adverse social impact
The pipeline from Ginjo to Abba Jifar is designed to pass fairly close to a burial site. Based on the
ESIA recommendation the contractor and the water project planned to use only human labour rather
than machine during the construction of the pipeline, and that would mitigate any impact on the
burial ground. Thus, no adverse socio-cultural impact has been observed and foreseen in the future.
Page 14
2.2.6 Lesson learned
Officials of Jimma Water Supply and Sanitation Project have been effective in searching for options
to mitigate adverse impacts of the project. For instance the ESIA mentioned that the pipeline from
Boye to Jiren Kella cross the main asphalt road causing a significant damage to the road (ESIA,
2011:89). However, during construction phase the project innovatively passed the pipeline under the
asphalt road culvert without affecting the road. The project officials also worked in identifying the
PAPs in advance, contacting and negotiating with them, and processing their compensation with the
compensation standing committee. The project facilitated for the individual PAPs to go to their
impacted site with the compensation committee and measure or count the losses. Of the seven PAPs
they have paid compensation so far; they identified the poorest household and gave the head of the
household employment opportunity within the project, besides the cash compensation he received.
According to the manager of the project, this is the kind of lesson they acquired from working with
the PAPs. So far there was no complaint. In fact, all the PAPs contacted by the consultant expressed
their satisfaction. This experience would help the project officials in their future efforts.
3 LEGAL FRAMEWORK FOR EXPROPRIATION AND
COMPENSATION
Land expropriation and compensations were conducted based on relevant laws of the land as agreed
upon in the Resettlement Policy Framework. As land is state property compensations have been
calculated for property situated on landholdings and not for the land. The 1995 Constitution of the
Federal Democratic Republic of Ethiopia states:
“The right to ownership of rural and urban land, as well as of all natural resources, is
exclusively vested in the State and in the peoples of Ethiopia…” (Article 40, sub article
3).
“Every Ethiopian shall have the full right to immovable property he builds and to the
permanent improvements he brings about on the land by his labour or capital This right
shall include the right to alienate, to bequeath, and, where the right of use expires, to
remove his property, transfer his title, or claim compensation for it. Particulars shall be
determined by law”. (Art. 40, sub article 7)
Furthermore, Article 8 states:
“Without prejudice to the right to private property, the government may expropriate private
property for public purposes subject to payment in advance of compensation commensurate
to the value of the property”.
Also and more specifically, Article 44, sub article 2 states:
“All persons who have been displaced or whose livelihoods have been adversely affected as
a result of State programmes have the right to commensurate monetary or alternative means
of compensation, including relocation with adequate State assistance.”
Page 15
Subsequent proclamations and directives have become the instruments to implement the provisions
of the Federal Constitution pertaining to land. Accordingly, Proclamation no 455/2005 clarifies and
defines who has the power to expropriate land holdings, in urban or rural areas. Article 3, sub article
1 of the proclamation states:
“A woreda or an urban administration shall, upon payment in advance of the compensation
in accordance with this proclamation, have the power to expropriate rural or urban
landholdings for public purposes where it believes that it should be used for a better
development project to be carried out by public entities, private investors, cooperative
societies or other organs, or where such expropriation has been decided by the appropriate
higher regional or federal government organ for the same purpose.”
Displacement compensation for rural landholdings is governed by provision of Article 8, sub article
three of the proclamation:
“A rural landholder whose land has been permanently expropriated shall, in addition to the
compensation payable under article 7 of this proclamation, be paid displacement
compensation which shall be equivalent to ten times the average annual income he secured
during the five years preceding the expropriation of the land.”
The above legal provisions constitute the basis for the expropriation of landholdings and
commensurate compensations for all lands expropriated for public purposes. The Ambowuha Spring
Development Project at Hawassa Water Supply and Sanitation Project and Jimma Water Supply and
Sanitation projects are also governed by these legal provisions. In view of this, the Resettlement
Policy Framework (January 2007) for the UWSSP proposes “permanent loss of land” will be
compensated with “replacement by a similar piece of land (…) OR cash compensation at
replacement value…” (page d)
In line with the above stated legal provisions and the resettlement policy framework of the UWSSP,
the regional/city administrations determine the value of the property affected by the project and rate
at which the damage will be compensated. Variables taken into account when compensations are
calculated for the expropriated landholdings include production per hectare, market price of a given
type of crop produced on that land, types and values of fences or other structures on the land.
4 CONCLUDING REMARKS
In both water projects the project affected people and institutions have been properly compensated in
line with the GOE compensation procedures and the World Bank’s safeguard policies as per the RPF
provisions. In Jimma a very good experience others have to share is the presence of a standing
compensation committee. It is an experienced committee that has developed trust from the people.
The Hawassa water project officials and the city administration officials have put in place grievance
addressing mechanisms and smoothly addressed the complaints from the religious institutions.
Moreover, the Hawassa water project has to be commended for its works to benefit the people around
the source of the spring. It has constructed cattle troughs, washing places and communal drinking
tabs in the nearby villages. That obviously supports the sustainability of the use of the water.
Page 16
5 RECOMMENDATIONS
Since the procedures in both projects run with at most care, smoothly and successfully there is little
practical thing to recommend. Hawassa water supply and sanitation project has successfully handled
the cases of many PAPs. Legally, they have cleared everything in relation to the PAPs. Yet, the
project can take further constructive roles in collaboration with other relevant offices in supporting
some of the PAPs such as the single female household head and some of the poor households through
micro-finances or other employment opportunities.
Another point, Hawassa water supply and sanitation project is doing very well in supporting people
around the source of the spring. That is an area where they should do more in expanding the
communal watering tabs that makes the people part of the project and work together on the
sustainability of the water.
In Jimma, the pipeline from the Jiren Kella to Abba Jifar is under construction. It is recommended
that the Government use their established experience in smoothly approaching and handling the
PAPs.
REFERENCES
Council of Ministers Regulations No. 135/2007, on The Payment of Compensation for Property
Situated on Landholdings Expropriated for Public Purposes.
ESIA (2010) ESIA Report of Hawassa water supply and sanitation Project
ESIA (2011) ESIA Report for Jimma water supply and sanitation project environmental and
social impact assessment study (ESIA Report)
FDRE 2007 Urban Water Supply and Sanitation Project Environmental and Social
Management Framework.
FDRE 2007 Urban Water Supply and Sanitation Project Resettlement Framework