FEMA-1505-DRFEMA-1505-DRSan Simeon EarthquakeSan Simeon Earthquake
Santa Barbara CountySanta Barbara County
Dave Rickard Dave Rickard
Inspection Team Inspection Team
Building “C” Superior Court Building “C” Superior Court
Building “C” Superior CourtBuilding “C” Superior Court
Typical Concrete Sidewalk DamageTypical Concrete Sidewalk Damage
Building “B” ExampleBuilding “B” Example
Cracking
Cracking
Cracking
Building “G” Main CourthouseBuilding “G” Main Courthouse
CrackingCracking
Cracking
Building “G” South Wall Building “G” South Wall
Concrete Damage
Cracking
Building “G” Basement Floor Building “G” Basement Floor
1/8” Crack
Crack
Crack
Building “G” Basement Floor Building “G” Basement Floor Cracking ExampleCracking Example
1/8” open cracking 15 LF in File Room
Building “G” Jail Holding SpotBuilding “G” Jail Holding Spot
Sceam Cracking
Building “G” Basement Cont’ Building “G” Basement Cont’ ExampleExample
Wall Cracking
Entire Length of
Wall
Building “G” Jail Area Typical Building “G” Jail Area Typical Cracking – Patch and Paint Cracking – Patch and Paint
Crack
Planter in front of Courthouse Planter in front of Courthouse
Quake punched out concrete and broke paint
Laguna Sanitation Wastewater Laguna Sanitation Wastewater Treatment Plant Treatment Plant
Repairs to fiberglass baffles
Repairs to primary digester and feed piping
County Insurance – Self InsuredCounty Insurance – Self Insured
The County's deductible for Earthquake The County's deductible for Earthquake [EQ] coverage is 5% of the total values [EQ] coverage is 5% of the total values per "Unit" per occurrence subject to a per "Unit" per occurrence subject to a $500,000 minimum. A "Unit" is defined $500,000 minimum. A "Unit" is defined as a separate building, contents within a as a separate building, contents within a separate building, property in the open separate building, property in the open (yard), or time element coverage at a (yard), or time element coverage at a separate building.separate building.
List of Projects & Dollar AmountList of Projects & Dollar Amount
Laguna Sanitation Wastewater Treatment Plant $50,000Laguna Sanitation Wastewater Treatment Plant $50,000 Public Defender Build. Interior Bathrooms and Exterior Public Defender Build. Interior Bathrooms and Exterior
Cracking $30,000Cracking $30,000 Court House “Facility G” Exterior and Interior $125,000Court House “Facility G” Exterior and Interior $125,000 Building “B” 312 Cook St Exterior Cracking = $5,000Building “B” 312 Cook St Exterior Cracking = $5,000 Sidewalks and Planter repairs – $5,000Sidewalks and Planter repairs – $5,000 Juvenile Hall (SB) = $20,000Juvenile Hall (SB) = $20,000 HMGP Grant Request = Retrofit All Courthouses to HMGP Grant Request = Retrofit All Courthouses to
Required Codes and Standards = $4,000,000Required Codes and Standards = $4,000,000 Total Requested – Public Assistance = $235,000Total Requested – Public Assistance = $235,000
– Hazard Mitigation Proposal = $4,000,000Hazard Mitigation Proposal = $4,000,000
Any QuestionsAny Questions
“Here’s Your $4 Million”