fermilab pmg jan 20, 2000 reconsideration of the installation at d0 overview major constraints ...
TRANSCRIPT
DD
Fermilab PMGJan 20, 2000
Reconsideration of the Installation
at D0
Overview Major constraints Basics of old, new schemes Some details on each Cost/benefit Proposed plan Conclusions
Jon KotcherBrookhaven National Laboratory
D0 Collaboration
Fermilab PMG January 20, 2000
DD
Fermilab PMGJan 20, 2000
Overview
Have worked out two new approaches to detector installation
many options considered has grown out of detailed discussions
among principals and beyond: Project Management Sub-Project Managers (esp. Forward
Muon, Trackers, Calorimeter) Project Engineers Technical Supervisor, Forward Muon
survey coordinator,... a number of details remain that may
color how one thinks about each option none have any significant likelihood of
influencing feasibility Primary goals:
uninterrupted detector commissioning during end game
was very severe - breakdown of LHe ~ Nov 1 for 6 weeks
introduce contingency for the silicon was none
relieve pressure on end game by doing things early whenever possible
DD
Fermilab PMGJan 20, 2000
Overview
Primary Goals (cont’d) strive for plan that offers forgiving
contingency scheme, fallback possibilities for as many detectors as possible
flexibility New (any) scheme driven largely
by two primary constraints: Forward Muon installation
huge system that dictates position/movement of major pieces: end irons, trusses
logistics of Silicon and Fiber Tracker installation
DD
Fermilab PMGJan 20, 2000
Major Installation Constraints
South calorimeter must be on platform if platform is to be moved
At some point, north and south sidewalks must be clear to allow assembly of EMC trusses prior to rolling them into Collision Hall
Requires end toroids on platform For south end, also requires south
calorimeter on platform Must move platform to pick up end
irons
In order to install either inner tracker:
both south calorimeter and south end toroid must be on sidewalk to allow access to inner bore
Bringing down either truss from the Hi Bay, with its detectors mounted, requires LHe engines be disconnected
Without detectors, can be avoided
DD
Fermilab PMGJan 20, 2000
Basics
Previously: No movement of any of the large pieces
(N/S truss, end irons, detector platform) until both fiber tracker and silicon are installed and checked out
~ Nov 1, 2000 End game paced/driven by movements
of these pieces thereafter
Two new schemes: Both have shield wall coming down to
install north truss in Collision Hall immediately after commissioning run
Nov 1, 2000 Scheme I:
Install south truss in Collision Hall during Aug, 2000 window
platform goes in last Scheme II (fallback):
platform follows north truss south truss installed in Collision Hall last
Advantages, disadvantages to each Both are better than previous version...
DD
Fermilab PMGJan 20, 2000
Old vs. New Installation
Scheme Have learned much in process:
can probably install B-layer MDTs and pixels while detector is in Collision Hall if need be
may be possible to reassemble south truss in pit without breaking helium (remove detectors)
north truss can go onto sidewalk anytime, independent of rest of end game
entire wall does not have to come down to install trusses
various positions of collision wall, surveying, positioning low beta quads, air handler interferences, ...
What we’ve learned has greatly facilitated our ability to change course as project evolves
DD
Fermilab PMGJan 20, 2000
Cost/Benefit Gains derived from new schemes:
Helium interruptions end Sep (Jul) 2000 for early (late) south truss installation
Extended, uninterrupted commissioning of full experiment - including VLPC-based detectors - for at least last 4 months
6 months in case of late truss Commissioning of CFT was perilously
close to vanishing in old scheme Went from 0 to ~ 6-8 weeks contingency for
silicon in both schemes can arrive at D0 as late as mid-Nov
without delaying roll in (currently mid-Sep)
gained 2 months over next 9 - non-trivial must be willing to cable south end
detectors (CAL, FPS-S, ICD-S, LUM-S) in Collision Hall
Major installation task - south truss installation - done early in Scheme I
a large job we can put behind us - relieve some heat during end game
do they fit? Nice to know this early as possible in case modifications are needed
helps motivate/target completion of major component of Forward Muon system
DD
Fermilab PMGJan 20, 2000
Cost/Benefit Gains (cont’d):
Early scheme gives 2+ month window (6/22 -8/23) for B-layer south MDT and pixel installation while south end iron is on platform
very user-friendly configuration obviates the need for significant amount of
engineering, technical work needed otherwise
Forward Muon schedule says this is doable Survey of south truss in Collision Hall
greatly facilitated by Aug roll in (done in November)
Cost: 1 (early truss) - 2 (late truss) weeks at end
ready for beam was 2/6/01, now 2/13 (2/21) for early (late) truss
can relieve this by rolling in earlier if sensible (partially cable south detectors in CH)
early truss: one additional move of platform (south EF), shield wall (partially) broken down extra time
partially interrupts some installation and hookup
– electronics in platform can proceed: a bit hampered, but not seriously
diverts manpower from other DAB work at important time
DD
Fermilab PMGJan 20, 2000
Cost/Benefit
Cost (cont’d) early truss: significant interruption to
CFT hookup (Jul-Sep) - helium, detector access
part of cost for 4 months of full detector commissioning at end
Requires re-shuffling priorities of Forward Muon production
Significant impact to this effort (not always a bad thing!)
Priorities: A-layer installation, C-layer mounted to south truss
Filling calorimeter delayed ~ 2 weeks due to platform movement in Scheme I
CC cosmic running starts ~ Oct 1 (was Sep 20)
early test fill still feasible (Jul-Aug) Need additional week (3 week
window total) in Aug for truss installation
Accelerator Division’s estimates taken into account (roll out low beta quads,...)
believe this should pose no problems, but another week of contingency would probably make sense
DD
Fermilab PMGJan 20, 2000
Relevant Details for Scheme I
Detector back in configuration where it can accept either tracker on 9/8/00
earliest it can be back in position after truss installation
At present, silicon ready to install 9/19/00 If accelerator schedule slips, it will cost us
to install south truss early
Fiber Tracker must be at D0 by 6/26/00 or its installation will be delayed until 9/8/00
will delay south truss assembly on south sidewalk - late for Aug roll in
compete with silicon installation/hookup delays (delicate) hookup of clear
waveguides leaves 3 weeks contingency from current
date decision on whether to pursue early south
truss installation must be made before end June; earlier to prepare
DD
Fermilab PMGJan 20, 2000
Our Plan
Are aggressively pursuing early south truss installation (Scheme I)
accomplishing large task early is worth cost in other areas
have shifted priorities in Forward Muon to accomplish this
pushing on Fiber Tracker production We will move platform ~ late spring
under any circumstances currently mid-June for early truss right now paced by arrival/installation of
Fiber Tracker installation of A-layer MDTs and pixels
should be complete (not necessary, in any case)
Will either pick up north end iron only (late truss), or both end irons (early truss), depending on scheme chosen
Decision on which way to go will be made as late as possible, but early enough to prepare:
by June 1 earlier if circumstances allow consistent with Accelerator Division’s
needs?
DD
Fermilab PMGJan 20, 2000
Conclusions
Reconsideration of installation sequence has provided significant gains where they matter most
Both preferred scheme (I) and fallback (II) far more flexible than previous version
Decision-making branch point for early south truss installation identified If scheme is adopted, need at least
1 additional week during August shutdown (2 preferred)
Installation organization in place, implementing collaboration-wide procedures, safety requirements for work in Hall, etc.
%d0%a4%d0%93%d0%9e%d0%a1%203 %20%d0%9b%d0%b5%d1%87%d0%b5%d0%b1%d0%bd%d0%be%d0%b5%20%d0%b4%d0%b5%d0%b
%d0%9d%d0%b0%d0%b2%d1%87%d0%b0%d0%bb%d1%8c%d0%bd%d0%be %d0%bc%d0%b5%d1%82%d0%be%d0%b4%d0%b8%d1%87%d0
1060204 %d0%bb%d0%b8%d1%81%d1%82%d0%be%d0%b2%d0%ba%d0%b0 %d0%bf%d0%be %d1%82%d0%b5%d0%bf%d0%bb%d0%be