Activities:
1) RFQ cold model end flange inserts
2) RFQ cold model couplers
3) FETS support stand rail system
4) Laserwire beam profile measurement tank
![Page 3: F.E.T.S. Mechanical Engineering Update By P. Savage 7th September 2007](https://reader036.vdocument.in/reader036/viewer/2022062422/56649f2f5503460f94c49eb5/html5/thumbnails/3.jpg)
1) RFQ cold model end flange inserts
Due for delivery on September 3rd but anticipate a delay of approx. one week.
![Page 4: F.E.T.S. Mechanical Engineering Update By P. Savage 7th September 2007](https://reader036.vdocument.in/reader036/viewer/2022062422/56649f2f5503460f94c49eb5/html5/thumbnails/4.jpg)
Activities:
1) RFQ cold model end flange inserts
2) RFQ cold model couplers
3) FETS support stand rail system
4) Laserwire beam profile measurement tank
![Page 5: F.E.T.S. Mechanical Engineering Update By P. Savage 7th September 2007](https://reader036.vdocument.in/reader036/viewer/2022062422/56649f2f5503460f94c49eb5/html5/thumbnails/5.jpg)
![Page 6: F.E.T.S. Mechanical Engineering Update By P. Savage 7th September 2007](https://reader036.vdocument.in/reader036/viewer/2022062422/56649f2f5503460f94c49eb5/html5/thumbnails/6.jpg)
Activities:
1) RFQ cold model end flange inserts
2) RFQ cold model couplers
3) FETS support stand rail system
4) Laserwire beam profile measurement tank
![Page 7: F.E.T.S. Mechanical Engineering Update By P. Savage 7th September 2007](https://reader036.vdocument.in/reader036/viewer/2022062422/56649f2f5503460f94c49eb5/html5/thumbnails/7.jpg)
The FETS support stands in R8
![Page 8: F.E.T.S. Mechanical Engineering Update By P. Savage 7th September 2007](https://reader036.vdocument.in/reader036/viewer/2022062422/56649f2f5503460f94c49eb5/html5/thumbnails/8.jpg)
The FETS support stand with rails
![Page 9: F.E.T.S. Mechanical Engineering Update By P. Savage 7th September 2007](https://reader036.vdocument.in/reader036/viewer/2022062422/56649f2f5503460f94c49eb5/html5/thumbnails/9.jpg)
Beam
•Floor to centre of beam = 1650mm
•Rail diameter = 50mm
•Rail spacing = 800mm
•Floor to centre of rail = 800mm
The FETS support stands main parameters
![Page 10: F.E.T.S. Mechanical Engineering Update By P. Savage 7th September 2007](https://reader036.vdocument.in/reader036/viewer/2022062422/56649f2f5503460f94c49eb5/html5/thumbnails/10.jpg)
The FETS support stands vee blocks
Corner vee block – 4 per stand
Mid vee block – where needed
Due for delivery on September 10th.
![Page 11: F.E.T.S. Mechanical Engineering Update By P. Savage 7th September 2007](https://reader036.vdocument.in/reader036/viewer/2022062422/56649f2f5503460f94c49eb5/html5/thumbnails/11.jpg)
Activities:
1) RFQ cold model end flange inserts
2) RFQ cold model couplers
3) FETS support stand rail system
4) Laserwire beam profile measurement tank
![Page 12: F.E.T.S. Mechanical Engineering Update By P. Savage 7th September 2007](https://reader036.vdocument.in/reader036/viewer/2022062422/56649f2f5503460f94c49eb5/html5/thumbnails/12.jpg)
Design concept of the laserwire beam profile measurement tank
Layout of four ALIO linear/rotary stages
Beam pipe
Beam
![Page 13: F.E.T.S. Mechanical Engineering Update By P. Savage 7th September 2007](https://reader036.vdocument.in/reader036/viewer/2022062422/56649f2f5503460f94c49eb5/html5/thumbnails/13.jpg)
Design concept of the laserwire beam profile measurement tank
Solenoid
Faraday cup
![Page 14: F.E.T.S. Mechanical Engineering Update By P. Savage 7th September 2007](https://reader036.vdocument.in/reader036/viewer/2022062422/56649f2f5503460f94c49eb5/html5/thumbnails/14.jpg)
Post acceleration conceptual design
![Page 15: F.E.T.S. Mechanical Engineering Update By P. Savage 7th September 2007](https://reader036.vdocument.in/reader036/viewer/2022062422/56649f2f5503460f94c49eb5/html5/thumbnails/15.jpg)
![Page 16: F.E.T.S. Mechanical Engineering Update By P. Savage 7th September 2007](https://reader036.vdocument.in/reader036/viewer/2022062422/56649f2f5503460f94c49eb5/html5/thumbnails/16.jpg)