fha 203(k) loan draw request guide - · pdf filefha 203(k) loan draw request guide ... bank of...

17
See page 2 for a list of terms. FHA 203(k) Loan Draw Request Guide How to access the funds from your home improvement loan Congratulations on closing your home improvement loan. Bank of America is dedicated to helping our customers become successful homeowners. We’re committed to providing the tools and information you need to efficiently draw funds from your FHA 203(k) loan. This guide is designed to make the draw process as clear and straightforward as possible. If you have questions at any time, please contact the Bank of America Disbursement Management Group at 1.800.293.8155, and we will be happy to help. Draw Request Overview Each time you request a “draw,” you are simply requesting a portion of funds from your FHA 203(k) Rehabilitation Loan. The draw request process has five basic steps, which are outlined below. You will be responsible for completing the first three steps, with the help of your contractor and HUD-approved inspector, and Bank of America will be responsible for the final two steps. This guide will cover each step in detail. A few important things to note about the Draw Request Process: 1. Bank of America must receive a Draw Request Package no later than 30 days after a loan closing and, at a minimum, every 30 days thereafter. 2. Once you and your contractor have determined that a draw should be made it is your responsibility to schedule an inspection with your HUD-approved home inspector. You and your contractor should be present during the inspection in case any questions arise. If you need the name or contact information of your HUD-approved inspector, please contact your originating lender. 3. You can submit up to five draw requests as part of your 203(k) loan; please work with your contractor and inspector to ensure that you are appropriately requesting your home loan funds. 4. You must complete all your home improvements within six months, in compliance with your Rehabilitation Loan Agreement. STEP 1: Submit a Draw Request Package STEP 3: Submit a Final Draw Request Package STEP 2: Request a Change Order (if applicable) STEP 4: Release of Holdback Funds STEP 5: Payment of Interest from the Repair Escrow Account Our responsibility Your responsibility

Upload: dinhtu

Post on 11-Mar-2018

212 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: FHA 203(k) Loan Draw Request Guide - · PDF fileFHA 203(k) Loan Draw Request Guide ... Bank of America is dedicated to helping our customers become successful ... Order (if applicable)

See page 2 for a list of terms.

FHA 203(k) Loan Draw Request GuideHow to access the funds from your home improvement loanCongratulations on closing your home improvement loan. Bank of America is dedicated to helping our customers become successful homeowners. We’re committed to providing the tools and information you need to efficiently draw funds from your FHA 203(k) loan. This guide is designed to make the draw process as clear and straightforward as possible. If you have questions at any time, please contact the Bank of America Disbursement Management Group at 1.800.293.8155, and we will be happy to help.

Draw Request OverviewEach time you request a “draw,” you are simply requesting a portion of funds from your FHA 203(k) Rehabilitation Loan. The draw request process has five basic steps, which are outlined below. You will be responsible for completing the first three steps, with the help of your contractor and HUD-approved inspector, and Bank of America will be responsible for the final two steps. This guide will cover each step in detail.

A few important things to note about the Draw Request Process:

1. Bank of America must receive a Draw Request Package no later than 30 days after a loan closing and, at a minimum, every 30 days thereafter.

2. Once you and your contractor have determined that a draw should be made it is your responsibility to schedule an inspection with your HUD-approved home inspector. You and your contractor should be present during the inspection in case any questions arise. If you need the name or contact information of your HUD-approved inspector, please contact your originating lender.

3. You can submit up to five draw requests as part of your 203(k) loan; please work with your contractor and inspector to ensure that you are appropriately requesting your home loan funds.

4. You must complete all your home improvements within six months, in compliance with your Rehabilitation Loan Agreement.

STEP 1: Submit a Draw Request Package

STEP 3:Submit a Final Draw Request Package

STEP 2:Request a Change Order (if applicable)

STEP 4:Release of Holdback Funds

STEP 5:Payment of Interest from the Repair Escrow Account

Our responsibilityYour responsibility

BRO-02-10-0645_FHA 203k Draw Request Guide.indd 1 7/26/10 5:34 PM

Page 2: FHA 203(k) Loan Draw Request Guide - · PDF fileFHA 203(k) Loan Draw Request Guide ... Bank of America is dedicated to helping our customers become successful ... Order (if applicable)

1 Important Terms FHA 203(k) Loan Draw Request Guide | 02

Originating Lender — This guide will occasionally refer to your “originating lender.” This is the lender from whom you originally obtained your loan. Although Bank of America now owns your mortgage and will be responsible for its disbursement, you may need to contact your originating lender if you need information about the terms of your loan.

HUD-Approved Inspector — Also referred to as a cost-consultant, fee-consultant or rehab consultant, your HUD-approved inspector is the person who processed your Initial Work Write-Up/Specification of Repairs. It is your responsibility to contact your inspector when you require an inspection; he or she will help guide you throughout your loan process. If you need the name or contact information of your HUD-approved inspector, please contact your originating lender.

Repair Escrow Account — Funds for your home improvement project are held in an interest-bearing escrow account1 insured by the FDIC. These funds are released to you and your contractor(s) for repairs based on the original appraisal and contractor bid. Included in this account are funds to pay for planned repairs, contingencies, inspection, title and other miscellaneous improvement fees.

Property Lien — A lien is a form of collateral that ensures payment ofa debt. Contracts for home improvement work often allow contractors to place a lien against the title of the property in the event they are notpaid. If your property has a lien against it, you will not be able to sell orrefinance the property until the lien has been cleared. Bank of America willensure your title is clear of any liens before issuing your final disbursement.

Holdback Funds — As indicated in your Borrower Acknowledgement form, 10% of the total draw request amount will be deducted and held in the repair escrow account until the entire project is complete. For example, if $1,000 is requested, Bank of America will issue a check for $900. The $100 difference will remain in the repair escrow account. All monies held back will be released after all work is complete and Bank of America has ensured that the property’s title is clear of any liens.

Contingency Fund — This reserve of funds is held in the repair escrow account for the purpose of covering unplanned repairs that become necessary due to health or safety issues. No portion of this money may be used for building material changes or repairs. Be sure to contact Bank of America before authorizing your contractor to make repairs that will cost more than the estimate provided in the original contractor bid. Unused contingency funds will be applied toward the principal balance on your loan. Note that contingency funds are not part of the holdback funds.

Inspector/Lender Modification of the Draw Request — When the inspector submits the Draw Request Package (reviewed in Step 1), both the inspector and Bank of America may adjust the amount requested, if appropriate. You will be notified of any modification to the draw request. Modification may occur if a contractor requests payment for materials prior to installation or requests payment in excess of the previously agreed-upon amount but does not submit a Change Order Request for approval.

Please familiarize yourself with the following terms that you will need to know about the FHA 203(k) Draw Request process:

1 As required by the IRS, a 1099-INT form will be issued for taxable interest paid.

BRO-02-10-0645_FHA 203k Draw Request Guide.indd 2 7/26/10 5:34 PM

Page 3: FHA 203(k) Loan Draw Request Guide - · PDF fileFHA 203(k) Loan Draw Request Guide ... Bank of America is dedicated to helping our customers become successful ... Order (if applicable)

1 STEP 1: Submit a Draw Request Package FHA 203(k) Loan Draw Request Guide | 03

Each time your contractor requires payment for finished work, the HUD-approved inspector must submit a complete Draw Request Package. As previously stated, you may submit a maximum of five Draw Request Packages (including the Final Request, Step 3 of this guide). A complete package must contain the following documentation:

A) Draw Request Form. (HUD 9746-A, Page 1) Signed by you, the contractor and the inspector.

B) Lien Releases. Signed by the general contractor and all subcontractors.

C) Borrower Receipts (self help only). If you signed a Self Help Agreement, you must submit paid receipts for all building materials and supplies for which you need to be reimbursed.

A) Draw Request Form (HUD 9746-A, Page 1)

The Draw Request Form needs to be completed by you, your contractor and your inspector. In order to help you better understand how this form must be completed, we will review the one form in four separate sections. These sections can best be described as:

Section 1 – Borrower Information Section 2 – Draw Request Information Section 3 – Consent and Signatures

Section 4 – Rehabilitation Inspection Report

Sample Draw Request Form

BRO-02-10-0645_FHA 203k Draw Request Guide.indd 3 7/26/10 5:34 PM

Page 4: FHA 203(k) Loan Draw Request Guide - · PDF fileFHA 203(k) Loan Draw Request Guide ... Bank of America is dedicated to helping our customers become successful ... Order (if applicable)

1 STEP 1: Submit a Draw Request Package (continued) FHA 203(k) Loan Draw Request Guide | 04

Section 1 - Borrower InformationThe first section of the Draw Request Form contains general information about you and your 203(k) loan.

Borrower’s Name & Property Address Please type or print your name and the complete address of the property.

Lender’s Name & Address Bank of America

1800 Tapo Canyon Road Simi Valley, CA 93063

FHA Case Number Leave blank if you do not know this number.

This Draw Number If this is the first draw, indicate #1, if it is the second, indicate #2, and so forth.

Date The date you completed the form.

1

2

4

3

5Cross section of sample Draw Request Form

BRO-02-10-0645_FHA 203k Draw Request Guide.indd 4 7/26/10 5:34 PM

Page 5: FHA 203(k) Loan Draw Request Guide - · PDF fileFHA 203(k) Loan Draw Request Guide ... Bank of America is dedicated to helping our customers become successful ... Order (if applicable)

1 STEP 1: Submit a Draw Request Package (continued) FHA 203(k) Loan Draw Request Guide | 05

Section 2 - Draw Request InformationThis section contains the specific details of your draw request. It will be completed with the help of your contractor and inspector.

6 Total Escrow, Column 1 This will be completed by your HUD-approved inspector.

Total Cost of Rehabilitation/Previous Draw Totals, Column 2 If it is the first draw, leave this column blank. Otherwise, indicate the total cost of previous draws for each item, including amounts held back. You should be able to copy this directly from your previous Draw Request. Your contractor or inspector will be able to assist you, if needed.

Total Cost of Rehabilitation/Previous Draw Totals, Column 2, PercentageThe inspector will help you determine the percentage of work completed for each line item. You, the contractor and the inspector may complete this column jointly if all are present during the inspection.

Total Cost of Rehabilitation/Request for this Draw, Column 3The inspector will help you determine the dollar amount for each line item request. You, the contractor and the inspector may complete this column jointly if all are present during the inspection.

8

7

9

Cross section of sample Draw Request Form

BRO-02-10-0645_FHA 203k Draw Request Guide.indd 5 7/26/10 5:34 PM

Page 6: FHA 203(k) Loan Draw Request Guide - · PDF fileFHA 203(k) Loan Draw Request Guide ... Bank of America is dedicated to helping our customers become successful ... Order (if applicable)

Total Cost of Rehabilitation/Request for this Draw, Column 3, PercentageThe inspector will help you determine the percentage of work completed for each line item. You, the contractor and the inspector may complete this column jointly if all are present during the inspection.

Item #36 Totals/Request for this Draw, Column 3 Add all of the line item dollar amounts under Column 3. The total is the amount of money you should receive for this draw, providing your inspector agrees with this amount. (Please see the note below for further details.) As referenced earlier in this guide, 10 percent of the total will be held back. You will receive a check for 90 percent of the amount requested, made payable to you and your contractor.

Note: If the inspector does not agree with the amount requested in Column 3, he or she will indicate an adjusted amount in Column 4. The inspector may also request additional documentation, such as subcontractor lien waivers, copies of permits or signed inspection cards. If this occurs you will receive the total amount indicated in Column 4, rather than Column 3 for this draw, minus the 10 percent, which will be held back.

11

1 STEP 1: Submit a Draw Request Package (continued) FHA 203(k) Loan Draw Request Guide | 06

Section 2 - Draw Request Information (continued)

10

Cross section of sample Draw Request Form

BRO-02-10-0645_FHA 203k Draw Request Guide.indd 6 7/26/10 5:34 PM

Page 7: FHA 203(k) Loan Draw Request Guide - · PDF fileFHA 203(k) Loan Draw Request Guide ... Bank of America is dedicated to helping our customers become successful ... Order (if applicable)

STEP 1: Submit a Draw Request Package (continued) FHA 203(k) Loan Draw Request Guide | 07

Section 3 - Consent and SignaturesThis section of the Draw Request Guide is where you, the contractor and the inspector will sign and date to indicate that all work has been completed in a workmanlike manner.

Borrower’s Signature & DateCheck the appropriate box to indicate whether you will live in the home or if you will rent to a tenant. Sign and date on the line indicating satisfaction with work completed and agreement to the amount to be released. Only individuals who have signed the mortgage note may sign this form authorizing release of funds.

Note: Before signing the Draw Request Form, make sure that your contractor has acquired the necessary permits from local building authorities. This is the responsibility of both you and your contractor.

General Contractor’s Signature & DateThe contractor will sign and date on the line provided. If you use more than one contractor, all contractors that require payment for work completed during that draw period must sign and date the form. If you are not completing this form with your inspector, you will need to submit the form to the HUD-approved inspector after completing steps 1-13.

12 13

Cross section of sample Draw Request Form

Inspector’s Signature & Date — Do not fill in this area.The inspector will sign and date the form once he or she has completed a review to determine if the amount requested is appropriate for your home improvement project.

Approved for Release — Do not fill in this area.The totals will be filled in on the right side of this section by Bank of America.

14 15

BRO-02-10-0645_FHA 203k Draw Request Guide.indd 7 7/26/10 5:34 PM

Page 8: FHA 203(k) Loan Draw Request Guide - · PDF fileFHA 203(k) Loan Draw Request Guide ... Bank of America is dedicated to helping our customers become successful ... Order (if applicable)

1 STEP 1: Submit a Draw Request Package (continued) FHA 203(k) Loan Draw Request Guide | 08

Section 4 - Rehabilitation Inspection ReportThe inspection report is on the second page of the Draw Request Form, shown below for reference, and must be completed by the inspector. Draw funds cannot be released without an approved inspection.

Cross section of sample Draw Request Form

BRO-02-10-0645_FHA 203k Draw Request Guide.indd 8 7/26/10 5:34 PM

Page 9: FHA 203(k) Loan Draw Request Guide - · PDF fileFHA 203(k) Loan Draw Request Guide ... Bank of America is dedicated to helping our customers become successful ... Order (if applicable)

1 STEP 1: Submit a Draw Request Package (continued) FHA 203(k) Loan Draw Request Guide | 09

B) Lien WaiversLien waivers prevent contractors from placing liens against your property when they have already been paid. You must submit a signed lien waiver for every contractor for whom you’re requesting a full or partial payment. There are two types of lien waivers and two forms for each.

Note: Contact your contractor or inspector for the proper lien waiver forms. You may also contact Bank of America for sample forms.

Conditional Lien WaiverIf the requested funds will pay your contractor directly (i.e., you have not paid your contractor out of pocket), you will use a Conditional Lien Waiver. In signing this waiver, the contractor agrees to refrain from putting a lien on your property on the condition that they will be paid.

There are two forms for the Conditional Lien Waiver.

Progress Waiver Form: If you are submitting multiple draw requests while work is in progress, you’ll need a Progress Waiver Form.

Final Waiver Form: If you are submitting one draw request for the entire loan amount and/or you are submitting a request after all work is complete, you’ll need a Final Waiver Form.

CONDITIONAL WAIVER RELEASE UPON PROGRESS PAYMENT

Upon receipt by the undersigned of a check from BANK OF AMERICA, N.A.

(Maker of Check)

in the sum of $ 1,200 payable to Fox Construction (Amount of Check) (Payee or Payees of Check)

and when the check has been paid properly endorsed and has been paid by the bank upon which it is drawn, this document shall become effective to release pro tanto any mechanic's lien, stop notices, or bond right the undersigned has on the job of John Smith (Owner) located at 1234 Main Street, Anytown, CA to the following extent. (Address or Legal Description) This release covers a progress payment for labor, services, equipment or materials furnished to Fox Construction through to 4/20/10 . (Your Customer) (Date) only and does not cover any retention or items after said date. Before any recipient of this document relies on it, the party should verify evidence of payment to the undersigned.

Dated: 4/20/10 Fox Construction

(Company Name)

By: Bill Brown, Owner

Federal Tax Payer ID # 00-0000 Address: 1234 Circle Lane City, State: Los Angeles, CA Telephone Number: LA0000

CONDITIONAL WAIVER AND RELEASE UPON FINAL PAYMENT

Upon receipt by the undersigned of a check from BANK OF AMERICA, N.A.

(Maker of Check)

in the sum of $ 1,200 payable to Fox Construction (Amount of Check) (Payee or Payees of Check)

and when the check has been paid by the bank upon which it is drawn, this document shall become effective to release any mechanic's lien, stop notice, or bond right the undersigned has on the job of John Smith located at 1234 Main Street, Anytown, CA (Owner) (Job Description) The undersigned does hereby certify that all laborers, material, equipment, and services used for The above referenced job have been paid in full. This release covers a progress payment to the undersigned for all labor, services, equipment or material furnished on the job, except for disputed claims against extra work in the amount of $ -0- . Before any recipient of this document relies on it, the party should verify evidence of payment to the undersigned.

Dated: 4/20/10 Fox Construction

(Company Name)

By: Bill Brown, Owner

Federal Tax Payer ID # 00-0000 Address: 1234 Circle Lane City, State: Los Angeles, CA Telephone Number: LA0000

Sample Conditional Waiver Release Forms

BRO-02-10-0645_FHA 203k Draw Request Guide.indd 9 7/26/10 5:34 PM

Page 10: FHA 203(k) Loan Draw Request Guide - · PDF fileFHA 203(k) Loan Draw Request Guide ... Bank of America is dedicated to helping our customers become successful ... Order (if applicable)

1 STEP 1: Submit a Draw Request Package (continued) FHA 203(k) Loan Draw Request Guide | 10

Unconditional Lien WaiverIf you have paid a contractor with your own money and need to be reimbursed, you will use an Unconditional Lien Waiver. As they have already received payment, when contractors sign this waiver, they agree to refrain from putting a lien on your property unconditionally. This situation is uncommon and in most cases you should not pay contractors out of pocket.

As with the Conditional Lien Waiver, the Unconditional Lien Waiver has both a Progress Waiver Form and a Final Waiver Form.

Progress Waiver Form: If you are submitting multiple draw requests while work is in progress, you’ll need a Progress Waiver Form.

Final Waiver Form: If you are submitting one draw request for the entire loan amount and/or if you are submitting a request after all work is complete, you’ll need a Final Waiver Form.

UNCONDITIONAL WAIVER RELEASE UPON PROGRESS PAYMENT

The undersigned has been paid and has received a progress payment in the sum of $ 1,200 for labor, services, equipment or material furnished to 1234 Main Street, Anytown, CA on the job of John Smith (Job Description) (Owner) and does hereby release pro tanto any mechanic's lien, stop notice or bond right that the undersigned has on the above referenced job to the following extent. This release covers a progress payment for labor, services, equipment, or material furnished to Fox Construction through 4/20/2010 (Your customer) (Date) DATED 4/20/10 Fox Construction (Company Name)

By: Bill Brown, Owner

Federal Tax Payer ID # 00-0000 Address: 1234 Circle Lane City, State: Los Angeles, CA Telephone Number: LA0000 NOTICE: THIS DOCUMENT WAIVES RIGHTS UNCONDITIONALLY AND STATES THAT YOU HAVE BEEN PAID FOR GIVING UP THOSE RIGHTS. THIS DOCUMENT IS ENFORCEABLE AGAINST YOU IF YOU SIGN IT, EVEN IF YOU HAVE NOT BEEN PAID. IF YOU HAVE NOT BEEN PAID, USE A CONDITIONAL RELEASE FORM.

UNCONDITIONAL WAIVER RELEASE UPON FINAL PAYMENT

The undersigned has been paid in full for labor, services, equipment, or material furnished to Fox Construction on the job of John Smith (Your Customer) (Owner) located at 1234 Main Street, Anytown, CA (Job Description) and does hereby waive and release any right to a mechanic’s lien, stop notice, or any right against a labor or material bond on the job, except for disputed claims against extra work in the amount of $ 2,000 . The undersigned does hereby certify that all suppliers, laborers, services and equipment used on the above noted job has been paid in full. DATED 4/20/10 Fox Construction (Company Name)

By: Bill Brown, Owner

Federal Tax Payer ID # 00-0000 Address: 1234 Circle Lane City, State: Los Angeles, CA Telephone Number: LA0000 NOTICE: THIS DOCUMENT WAIVES RIGHTS UNCONDITIONALLY AND STATES THAT YOU HAVE BEEN PAID FOR GIVING UP THOSE RIGHTS. THIS DOCUMENT IS ENFORCEABLE AGAINST YOU IF YOU SIGN IT, EVEN IF YOU HAVE NOT BEEN PAID. IF YOU HAVE NOT BEEN PAID, USE A CONDITIONAL RELEASE FORM.

Sample Unconditional Waiver Release Forms

C) Borrower Receipts (self help only)If you have signed a Self Help Agreement, you must submit paid receipts for all materials and supplies in order to be reimbursed. (Remember, you will not be reimbursed for your labor under this agreement.) Please keep copies of your receipts for your records.

Submitting the Draw Request PackageThe inspector will send the completed Draw Request Package, including all required documentation, directly to Bank of America. Once Bank of America receives a completed Draw Request Package, a check will be sent within five business days, via express carrier. Checks will be payable to both you and your contractor. Please make arrangements with your contractor to endorse and cash the check.

BRO-02-10-0645_FHA 203k Draw Request Guide.indd 10 7/26/10 5:34 PM

Page 11: FHA 203(k) Loan Draw Request Guide - · PDF fileFHA 203(k) Loan Draw Request Guide ... Bank of America is dedicated to helping our customers become successful ... Order (if applicable)

1 STEP 2: Request a Change Order (if applicable) FHA 203(k) Loan Draw Request Guide | 11

Prior approval by Bank of America is required for any cost overruns or changes involving the contractor, type of work, quality of materials or amount of materials. In the event of such a change, you must complete a Request for Acceptance of Changes in Approved Drawings and Specifications (HUD Form 92577), which is also known as a Change Order Request. This form must be signed by you, the contractor and the inspector and then sent to Bank of America for review and approval.

Note: Change orders are usually submitted with the draw request and are processed at the same time.

Change of a Contractor — Please notify Bank of America before changing contractors. If you change contractors, we will complete a property inspection to document how much work the original contractor completed and the payment amount owed. In addition to a Change Order Request, you must submit a new Homeowner/Contractor Agreement form before approval can be given for any future draw requests from a new contractor. Bank of America will pay only the contractor who has signed a Homeowner/Contractor Agreement for Work and Materials as shown on the approved Specification of Repairs.

Sample Change Order Request Form

BRO-02-10-0645_FHA 203k Draw Request Guide.indd 11 7/26/10 5:34 PM

Page 12: FHA 203(k) Loan Draw Request Guide - · PDF fileFHA 203(k) Loan Draw Request Guide ... Bank of America is dedicated to helping our customers become successful ... Order (if applicable)

1 STEP 2: Request a Change Order (continued) FHA 203(k) Loan Draw Request Guide | 12

Complete your Change Order Request.A Change Order Request should be completed as follows:

Property Address Type or print your name and complete property address, including street, city, state and zip code.

Case(s) No. Include the FHA Case Number(s).

Request No.Indicate how many change order requests you have submitted to date. For example, enter “1” if this is the first change order and “2” if it is the second.

Mortgagee’s Name and Address Bank of America 1800 Tapo Canyon Rd. MS: CA6-914-01-91 Simi Valley, CA 93063

We Request Leave this blank. Put an “X” in the checkbox labeled “We Do Not Request.”

1

2

4

3

5

Cross section of sample Change Order Request Form

BRO-02-10-0645_FHA 203k Draw Request Guide.indd 12 7/26/10 5:34 PM

Page 13: FHA 203(k) Loan Draw Request Guide - · PDF fileFHA 203(k) Loan Draw Request Guide ... Bank of America is dedicated to helping our customers become successful ... Order (if applicable)

1 STEP 2: Request a Change Order (continued) FHA 203(k) Loan Draw Request Guide | 13

Complete your Change Order Request. (continued)

DescriptionList the changes you would like to request. Indicate new expenses and savings from line items by placing the funds in [brackets] and additions to line items without brackets. For example, if you saved $1,000 on a particular item, list it as: [$1,000]; however, if you went over budget by $1,000, list it as: $1,000.

Builder’s Estimate of cost on each changeEnter the contractor’s estimated cost for the change next to each item discussed in the description box.

HUD/VA Estimate of effect on cost of each changeThis is the same as #7, except it is the inspector’s estimate.

Cross section of sample Change Order Request Form

6

7

8

BRO-02-10-0645_FHA 203k Draw Request Guide.indd 13 7/26/10 5:34 PM

Page 14: FHA 203(k) Loan Draw Request Guide - · PDF fileFHA 203(k) Loan Draw Request Guide ... Bank of America is dedicated to helping our customers become successful ... Order (if applicable)

1 STEP 2: Request a Change Order (continued) FHA 203(k) Loan Draw Request Guide | 14

Complete your Change Order Request. (continued)

Borrower Signature/DateSign and date indicating your approval of the Change Order Request.

Builder or Sponsor Contractor signs and dates the form indicating approval of the Change Order Request.

For Mortgagee Your inspector will sign and date the form indicating approval of the Change Order Request.

Cross section of sample Change Order Request Form

9

10

11

Submit your Change Order Request. Send the signed form to the Bank of America Disbursement Management Department at:

Fax: 1.805.306.7041Email: [email protected]: Bank of America 1800 Tapo Canyon Rd. MS: CA6-914-01-91 Simi Valley, CA 93063

BRO-02-10-0645_FHA 203k Draw Request Guide.indd 14 7/26/10 5:34 PM

Page 15: FHA 203(k) Loan Draw Request Guide - · PDF fileFHA 203(k) Loan Draw Request Guide ... Bank of America is dedicated to helping our customers become successful ... Order (if applicable)

1 STEP 3: Submit a Final Draw Request Package FHA 203(k) Loan Draw Request Guide | 15

Please contact Bank of America when your home improvement project is complete. At that time, we will send you a Mortgagor’s Letter of Completion, which you will complete and send back to us for processing. (Please see sample below.) In the meantime, you may call your inspector and contractor to schedule the final Draw Request inspection.

Sample Mortgagor’s Letter of Completion

Within approximately five business days of receipt of the final Draw Request Package, including your signed Mortgagor’s Letter of Completion, Bank of America will send you a check in the amount of the remaining funds, minus the 10 percent holdback amount, via express carrier.

BRO-02-10-0645_FHA 203k Draw Request Guide.indd 15 7/26/10 5:34 PM

Page 16: FHA 203(k) Loan Draw Request Guide - · PDF fileFHA 203(k) Loan Draw Request Guide ... Bank of America is dedicated to helping our customers become successful ... Order (if applicable)

1 STEP 4: Release of Holdback Funds FHA 203(k) Loan Draw Request Guide | 16

Before issuing a check for the balance of your loan, Bank of America must conduct a title search to be sure your title is clear of liens. (The highlighted text in the sample form to the right indicates that this property is clear of all liens.) For properties in most states, we will check the title 35 days after we receive your final draw request. This is because most states allow contractors 35 days after work is complete to file a lien on your property. In some states this time period is longer and in these instances we may wait the extra time before checking your title. If you do not know the timeframe for your state, please consult your contractor, inspector or originating lender.

If a title search indicates that a lien has been placed on your property, Bank of America will notify you and assist you in removing the lien. Once we verify that your title is clear, you will be sent a check, payable to both you and your contractor, within 5 business days, via express carrier. Funds cannot be sent through a bank wire transfer; a check must be issued. Please make arrangements with your contractor to endorse and cash the check.

Note: If you have paid out-of-pocket funds to a contractor, please submit a signed Unconditional Lien Waiver for each contractor you’ve paid, along with all cancelled checks or paid receipts. Please see page 9 for more information about Unconditional Lien Waivers.

TITLE COMPANY

PHONE: (000) 000-0000 FAX: (000) 000-0000

1234 1st Street

Anytown, CA 00000

TO: Bank of America 1800 Tapo Canyon Rd

MS: CA6-914-01-91 Simi Valley, CA 93063

PHONE: 800-293-8155 FAX: 805-306-7041 ATTENTION: Disbursement Management Group LOAN NUMBER: 123456789

MORTGAGE INFORAMTION

BORROWER: John Smith COUNTY: Any County, CA ORIGINATION DATE: 03/01/2010 PROPERTY ADDRESS: 1234 Main Street RECORDING DATE: LENDER: Bank of America Inst.#/CFN: SEARCH REQUESTED: Mechanics Liens COMMENTS: No mechanics liens found

Sample title free of liens

BRO-02-10-0645_FHA 203k Draw Request Guide.indd 16 7/26/10 5:34 PM

Page 17: FHA 203(k) Loan Draw Request Guide - · PDF fileFHA 203(k) Loan Draw Request Guide ... Bank of America is dedicated to helping our customers become successful ... Order (if applicable)

1 STEP 5: Payment of Interest from the Repair Escrow Account FHA 203(k) Loan Draw Request Guide | 17

Once Bank of America has released the final balance of funds including holdback funds, any amount remaining in the repair escrow account will be applied toward the balance of the loan. This includes any unused contingency funds, inspection fees or mortgage payments. These funds are interest-bearing and interest is accounted for and distributed to you based on your given instructions at the time of loan processing.

Credit and collateral are subject to approval. Terms and conditions apply. This is not a commitment to lend. Programs, rates, terms and conditions are subject to change without notice. Bank of America, N.A., Member FDIC. Equal Housing Lender. © 2010 Bank of America Corporation. –ARG4V1J6–BRO-02-10-0645– 07-2010

Bank of AmericaDisbursement Management Group

Phone:1.800.293.8155

Fax: 1.805.306.7041

Email: [email protected]

Mail: Bank of America

1800 Tapo Canyon Rd.MS: CA6-914-01-91

Simi Valley, CA 93063

If you have any questions regarding your rehabilitation loan, please contact:

BRO-02-10-0645_FHA 203k Draw Request Guide.indd 17 7/26/10 5:34 PM