fidic2 lecture eot related costs in construction
TRANSCRIPT
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 1/39
Extension of Time (EOT) and Related Costsin Construction
www.cspk.org
Presented at theFIDIC Middle East Contract Users’ Conference
February 2013 – Dubai, UAE
ByKhalil T. Hasan
Construction Solutions (www.cspk.org )
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 2/39
www.cspk.org
•Time is of Essence
•Delays are inevitable on construction projects
•The only project to have completed on time is a Mosque. Divine
intervention (or God’s help) was understood to be the force behind the
timely completion of this Mosque.
•Time and Money go hand-in-hand. When projects get late, additional
costs are incurred.
•This makes it imperative to take control of project delays; timely and
effectively.
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 3/39
www.cspk.org
•Majority of construction projects worldwide are administered by the
FIDIC forms of contract.
•FIDIC recognises delay and related costs and has provisions related
thereto. For example;
Sub-Clauses 8.4 & 20.1 (FIDIC 1999 Edition)
Clauses 44 & 53 (FIDIC 1987 Edition)
FIDIC
FIDIC
FIDIC
FIDIC
FIDIC
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 4/39
www.cspk.org
The FIDIC Provisions define the conditions where delay may beclaimed as the basis for an Extension of Time (EOT). Some examples are;
Late provision of design or drawings
Unforeseeable Physical Conditions encountered on Site
Inclement Weather
Variations instructed by the Engineer (Additional Works etc.)
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 5/39
www.cspk.org
Meanwhile the principles of how delay and relatedcosts should be calculated are not defined by FIDIC.This leads to issues; issues which are usually
contentious due to various 'schools of thoughts' andvaried interpretations existing worldwide.
Disputes are the usual outcome.
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 6/39
Contentious Issues in Delay Analysisresulting in Disputes
– Critical Path
– Who owns the Float?
– Concurrent (or Contractor) Delays and how these effectEntitlement
– EOT and its relation with Compensation for Delay
– Which is the best Method of Delay Analysis?
» As-Planned Vs. As-Built Comparison
» Impacted As-Planned
» Collapsed As-Built / But-For
» Time Slice / Sub-Networks / Time-Impact
» Etc.
www.cspk.org
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 7/39
www.cspk.org
In order to eliminate disputes or facilitate settlement ofdisputes, there are now certain standards used worldwide.The leading standards are;
Society of Construction Law’sDelay and Disruption Protocol (SCL Protocol)
AACE 29R-03 (Forensic Schedule Analysis)
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 8/39
www.cspk.org
The SCL Protocol wasfinalized in October 2002 afterseveral years of deliberations
and considerable debate andagreement between expertsfrom different backgrounds
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 9/39
www.cspk.org
The objective of the SCL Protocolwas to bring reasonableness and
fairness into the delay assessment
process and to eliminatewidespread manipulation of
complex delay issues
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 10/39
www.cspk.org
The SCL Protocol tried to standardize
the issues such that disputes would be
reduced or eliminated
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 11/39
www.cspk.org
It is recommended that;
should be adopted as a Standardand should be, where possible,
incorporated in the Construction
Contracts
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 12/39
www.cspk.org
The SCL Protocol can be downloaded from:
www.eotprotocol.com
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 13/39
www.cspk.org
The remaining slides of this lecture will
review and discuss the basic Principlessuggested and recommended by the
SCL Protocol
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 14/39
www.cspk.org
Basic Principlessuggested and recommended by
the SCL Protocol
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 15/39
www.cspk.org
The Principles suggested by theSCL Protocol are simple.
Some of the key principles suggestedby the Protocol are;
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 16/39
www.cspk.org
RULE NO. 1
If there is an Employer’s delay, which is beyond the Contractor’scontrol, and if this delay impacts the Completion Date of the Works,
the Contractor should be entitled to receive an
Extension of Time (EOT).[This will effectively result in an extended Time for Completion and will
relieve the Contractor from having to pay penalties for delay (orDelay Damages under FIDIC)]
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 17/39
www.cspk.org
RULE NO. 2
For the case of recovery of delay (or prolongation) costs incurred due tothe Employer delays, the Contractor must be able to prove that there hasbeen no other delay, which is in his own control, and which is equally
(or partly) contributing for delaying the Time for Completion.
This category of delay is called a ‘Concurrent’(or Contractor’s) Delay
[In order to win a Delay Costs Claim, the Contractor must be able toprove that he has not been responsible for Concurrent Delays to
the Time for Completion]
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 18/39
www.cspk.org
RULE NO. 3
Where Contractor’s Delay to Completionoccurs concurrently with Employer’s Delayto Completion, the Contractor’s concurrent
delay should NOT reduce anyExtension of Time (EOT), which is due.
[Result of Rule No. 1 will not change and is irrespective of the resultof Rule No. 2]
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 19/39
www.cspk.org
The foregoing Rules proposed by the SCL Protocol aremeant to bring fairness and reasonableness into the
delay assessment process.
[The emphasis of the SCL Protocol is that no one Partyshould benefit from default of the other Party]
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 20/39
www.cspk.org
The Illustrations demonstrating the principles of the SCLProtocol are contained in the following Figures A to G
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 21/39
www.cspk.org
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
Path 1 Float = 3.5 Weeks
Path 2 Float = 5.5 Weeks
Path 2
Figure A - Accepted Contract Programme
Weeks
Path 1
Contract Start
Date
Contract
Completion Date
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 22/39
www.cspk.org
1 2 3 4 5 6 7 8 9 10 1112 13 14 1516 17 181920 2122
PRIORTOEXCUSABLEDELAY(UPDATEWITHACTUALPROGRESS)
Path1 Float =3.0 Weeks
Path2 Float =5.5 Weeks
AFTEREXCUSABLEDELAY
Excusable Delay
Path1 Float =1.0 Week
Path2 Float =5.5 Weeks
(a) 2.0 Weeks (a) 5.5 Weeks
(b) 1.0 Weeks (b) 0 Weeks
(c) 0 Weeks (c) 1.0Weeks
d) 5.5Weeks d) 2.0Weeks
(a) 2.0 Weeks (a) 0.1%of Contract Price
(b) 1.0 Weeks (b) Direct Costs of Excusable Delay
(c) 0 Weeks (c) NIL
d) 5.5Weeks d) (a) plus (b)
<=Date of Excusable Delay
Figure B- DelayImpact 1
Weeks
Path1
Contract StartDate
ContractCompletionDate
Path2
(3) Compensationfor Delayto
Progress
(1) EOTEntitlement (2) Periodof ProlongationCosts
(4) Other Compensation
Contract
CompletionDate
Impact onPath1
=2.0Weeks
Path2
Path1
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 23/39
www.cspk.org
Principles & Provisions of the SCL Protocolrelevant to Figure B
Core Principle No. 7 - Float as it relates to timeUnless there is express provision to the contrary in the contract, where there is remaining float in the programme at the time of an Employer Risk Event, an EOT should only begranted to the extent that the Employer Delay is predicted to reduce to below zero the total
float on the activity paths affected by the Employer Delay.
Guidance Section 1.12.1If as a result of an Employer Delay, the Contractor is prevented from completing the worksby the Contractor’s planned completion date (being a date earlier than the contractcompletion date), the Contractor should in principle be entitled to be paid the costs
directly caused by the Employer Delay, notwithstanding that there is no delay to thecontract completion date (and therefore no entitlement to an EOT), provided also that atthe time they enter into the contract, the Employer is aware of the Contractor’s intention tocomplete the works prior to the contract completion date, and that intention is realistic andachievable.
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 24/39
www.cspk.org
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 2122
PRIORTOEXCUSABLEDELAY(UPDATEWITHACTUALPROGRESS)
Path1Float =3.0Weeks
Path2Float =5.5Weeks
AFTEREXCUSABLEDELAY
Excusable Delay
Float =-0.5Week
(a) 0.5 Weeks (a) 5.5 Weeks(b) 3.5 Weeks (b) 0.5 Weeks
(c) 0 Weeks (c) 3.5 Weeks
d) 5.5 Weeks d) 0 Weeks
(a) 3.5 Weeks (a) 0.15%of Contract Price
(b) 0.5 Weeks (b) Direct Costs of Excusable Delay
(c) 0 Weeks (c) (a) plus (b)
d) 3.0 Weeks d) NIL
Contract
CompletionDate
Impact onPath1
=3.5Weeks
Path2
Path1
Path2
(3) Compensationfor Delayto
Progress
(1) EOTEntitlement (2) Periodof ProlongationCosts
(4) Other Compensation
<=Date of Excusable Delay
Figure C- DelayImpact 2
Weeks
Path1
Contract StartDate
ContractCompletionDate
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 25/39
www.cspk.org
Core Principle No. 4 - Procedure for granting extension of timeThe EOT should be granted to the extent that the Employer Risk Event isreasonably predicted to prevent the works being completed by the thenprevailing contract completion date…..The goal of the EOT procedure isthe ascertainment of the appropriate contractual entitlement to an EOT; theprocedure is not to be based on whether or not the Contractor needs anEOT in order not to be liable for liquidated damages.
Core Principle No. 5 – Effect of delayFor an EOT to be granted, it is not necessary for the Employer Risk Eventalready to have begun to affect the Contractor’s progress with the works,or for the effect of the Employer Risk Event to have ended.
Principles & Provisions of the SCL Protocolrelevant to Figure C
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 26/39
www.cspk.org
1 2 3 4 5 6 7 8 9 10 111213 14 15 1617 18 19 202122
PRIORTOEXCUSABLEDELAY(UPDATEWITHACTUALPROGRESS)
Path1 Float =3.0 Weeks
Path2 Float =5.5 Weeks
AFTEREXCUSABLEDELAY
Float =-0.5Week
Excusable DelayImpact onPath2=6.0Weeks
(a) 0 Weeks (a) 5.5Weeks(b) 6.0 Weeks (b) 0 Weeks
(c) 0.5Weeks (c) 6.0Weeks
d) 5.5Weeks d) 0.5Weeks
(a) 3.5Weeks (a) (d) minus (c)
(b) 0.5 Weeks b) NIL
(c) 6.0Weeks (c) Direct Costs of Excusable Delay
d) 3.0Weeks d) 0.2%of Contract Price
<=Date of Excusable Delay
Figure D- DelayImpact 3
Weeks
Path1
Contract Start
Date
Contract
CompletionDate
Path2
Path1
Contract
CompletionDate
Path2
(3) Compensationfor Delayto
Progress
(1) EOTEntitlement (2) Periodof ProlongationCosts
(4) Other Compensation
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 27/39
www.cspk.org
Core Principle No. 4 - Procedure for granting extension of timeThe EOT should be granted to the extent that the Employer Risk Event isreasonably predicted to prevent the works being completed by the thenprevailing contract completion date…..The goal of the EOT procedure isthe ascertainment of the appropriate contractual entitlement to an EOT; the
procedure is not to be based on whether or not the Contractor needs anEOT in order not to be liable for liquidated damages.
Core Principle No. 5 – Effect of delayFor an EOT to be granted, it is not necessary for the Employer Risk Eventalready to have begun to affect the Contractor’s progress with the works,
or for the effect of the Employer Risk Event to have ended.
Principles & Provisions of the SCL Protocolrelevant to Figure D
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 28/39
www.cspk.org
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 2122
PRIORTOEXCUSABLEDELAY(UPDATEWITHACTUALPROGRESS)
Contract CompletionDate
Float =-1.5 Weeks
AFTEREXCUSABLEDELAY
Contract CompletionDate
Excusable DelayImpact onPath1 =2.0 Weeks
Float =-3.5Weeks
(a) 3.5 Weeks (a) 2.0 Weeks
(b) 2.0 Weeks (b) 0 Weeks(c) 1.5 Weeks (c) 3.5 Weeks
d) 0 Weeks d) 1.5 Weeks
(a) 3.5 Weeks (a) (c) plus (d)
(b) 2.0 Weeks b) NIL
(c) 3.0 Weeks (c) Direct Costs of Excusable Delay
d) 0 Weeks d) 0.1%of Contract Price
Figure E- DelayImpact 4
Weeks
Path1
Contract Start
Date
<=Date of Excusable Delay
Path2
Path1
Path2
(3) Compensationfor Delayto
Progress
(1) EOTEntitlement (2) Periodof ProlongationCosts
(4) Other Compensation
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 29/39
www.cspk.org
Guidance Section 1.2.11…an EOT should be granted to the extent that the Employer Risk Event ispredicted to prevent the works being completed by the then prevailing contract completion date. This process requires consideration of theavailable float…
Guidance Section 1.4.12…Where there has been Employer Delay, this may prevent the Employercharging the Contractor with LDs for failure to achieve a contractcompletion date…
Principles & Provisions of the SCL Protocolrelevant to Figure E
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 30/39
www.cspk.org
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 2122
PRIORTOEXCUSABLEDELAY(UPDATEWITHACTUALPROGRESS)
<=Date of Excusable Delay
Contract CompletionDate
Float =-1.5 Weeks
AFTEREXCUSABLEDELAY
Contract CompletionDate
Impact onPath1 =2.0 Weeks
Excusable Delay
Float =-3.5Weeks
(a) 2.0 Weeks (a) 0 Weeks
(b) 3.5 Weeks (b) 2.0 Weeks
(c) 1.5 Weeks (c) 3.5 Weeks
d) 0 Weeks d) 1.5 Weeks
(a) 3.5 Weeks (a) (c) plus (d)
(b) 2.0 Weeks b) NIL
(c) 3.0 Weeks (c) Direct Costs of Excusable Delay
d) 0 Weeks d) 0.1%of Contract Price
Figure F - Delay Impact 5
Weeks
Path1
Contract Start
Date
Path2
Path1
Path2
(3) Compensationfor Delay to
Progress
(1) EOTEntitlement (2) Periodof ProlongationCosts
(4) Other Compensation
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 31/39
www.cspk.org
Guidance Section 1.4.8 Where an Employer Risk Event occurs after the contract completion date, in asituation where failure to complete by the contract completion date has been causedby Contractor Delays, the principle set out in Section 1.4.7 above should apply,
except where the Employer Risk Event is a non-compensable Employer Risk Event.In such an event, no EOT (or compensation) should be due. Where an EOT is dueafter the contract completion date, the Employer Risk Event does not exonerate theContractor for all its delays prior to the Employer Risk Event occurring. The effectof the Employer Risk Event should be assessed as described above and any EOTfound due should simply be added to the contract completion date.
Principles & Provisions of the SCL Protocolrelevant to Figure F
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 32/39
www.cspk.org
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 2122
PRIORTOEXCUSABLEDELAY(UPDATEWITHACTUALPROGRESS)
<=Date of Excusable Delay
Contract CompletionDate
Float =-1.5 Weeks
Path2Float =2.5Weeks
AFTEREXCUSABLEDELAY
Contract CompletionDate
Float =-1.5 Weeks
Excusable Delay=3.5Weeks
(a) 2.5 Weeks (a) 0 Weeks
(b) 3.5 Weeks (b) 2.5 Weeks(c) 1.0 Weeks (c) 3.5 Weeks
(d) 1.5 Weeks (d) 1.5 Weeks
(a) 0 Weeks (a) (b) plus (d)
(b) 2.0 Weeks (b) Direct Costs of Excusable Delay
(c) 3.0 Weeks (c) NIL
(d) 3.5 Weeks (d) 0.2%of Contract Price
Path1
Path2
(3) Compensationfor Delayto
Progress
(1) EOTEntitlement (2) Periodof ProlongationCosts
(4) Other Compensation
Figure G- DelayImpact 6
Weeks
Path1
Contract Start
Date
Path2
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 33/39
www.cspk.org
Guidance Section 1.4.1 Where Contractor Delay to Completion occurs concurrently with Employer Delay toCompletion, the Contractor’s concurrent delay should not reduce any EOT due.
Guidance Section 1.4.7 Where Employer Risk Events and Contractor Risk Events occur sequentially buthave concurrent effects, here again any Contractor Delay should not reduce the
amount of EOT due to the Contractor as a result of the Employer Delay.
Concurrency (Appendix A – Definations and Glossary)True concurrent delay is the occurrence of two or more delay events at the sametime, one an Employer Risk Event, the other a Contractor Risk Event and the effectsof which are felt at the same time. The term ‘concurrent delay’ is often used to
describe the situation where two or more delay events arise at different times, butthe effects of them are felt (in whole or in part) at the same time. To avoidconfusion, this is more correctly termed the ‘concurrent effect’ of sequential delayevents.
Principles & Provisions of the SCL Protocolrelevant to Figure G – Slide 1/2
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 34/39
www.cspk.org
Core Principle No. 9 - Concurrent delay – its effect on entitlement to extension of time Where Contractor Delay to Completion occurs or has effect concurrently with EmployerDelay to Completion, the Contractor’s concurrent delay should not reduce any EOTdue.
Core Principle No. 14 - Link between extension of time and compensationEntitlement to an EOT does not automatically lead to entitlement to compensation (and
vice versa).
Core Principle No. 10 - Concurrent delay – its effect on entitlement to compensation forprolongationIf the Contractor incurs additional costs that are caused both by Employer Delay andconcurrent Contractor Delay, then the Contractor should only recover compensation to
the extent it is able to separately identify the additional costs caused by the EmployerDelay from those caused by the Contractor Delay. If it would have incurred theadditional costs in any event as a result of Contractor Delays, the Contractor will not beentitled to recover those additional costs.
Principles & Provisions of the SCL Protocolrelevant to Figure G – Slide 2/2
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 35/39
www.cspk.org
Guidance Section 3.2.13Although the programme should be the primary tool for guiding theCA in his determination of EOT, it should be used in conjunctionwith the contemporary evidence to ensure that the resulting EOT isfair and reasonable. It will also be necessary for the parties to apply
common sense and experience to the process to ensure that allrelevant factors are taken into account, and that any anomalousresults generated by the programme analysis are managed properly.
Key Guideline, Suggestion and Advice of theSCL Protocol
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 36/39
www.cspk.org
Figure No. Question 1 Question 2 Question 3 Question 4
B (c) (b) (a) (b)
C (a) (b) (d) (b)
D (c) (d) (d) (c)
E (b) (a) (d) (c)
F (a) (b) (d) (c)
G (c) (a) (a) (b)
Correct Responses for Figures B to G
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 37/39
Congratulations wehave come to the end of
the Lecture.
You are now a
Qualified and CertifiedDelay Claims Analyst
and Expert.
www.cspk.org
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 38/39
FIDIC and Construction Solutionsthank you for your attendance and contribution.
We wish you all Good Luck.
www.cspk.org
7/23/2019 FIDIC2 Lecture EOT Related Costs in Construction
http://slidepdf.com/reader/full/fidic2-lecture-eot-related-costs-in-construction 39/39
We urge all participants to review the SCL Protocol on their own.Construction Solutions’ Claims Management Division
(www.cspk.org ) will remain available for further discussions on theforegoing and any other relevant issue.
This Lecture was delivered by the Managing Partner of Construction Solutions,Mr. Khalil Tayab Hasan. For any queries and clarifications, please feel free to
contact Mr. Hasan at;
+971 50 8861709
+92 345 8500195
k