figure 1 : typical cross section (ch. 0.030 km to ch. 0
TRANSCRIPT
AMEN
DM
ENT
- 1C
L
Figure 1 : Typical Cross section(Ch. 0.030 km to Ch. 0.119 km)
BC
DBM
Granular Base
Granular Sub Base as Drainage Layer
Granular Sub Base as Separation Layer
500mm Thick Selective Sub-grade
Selected Fill for Embankment
R
O
W
R
O
W
R
O
W
R
O
W
R
O
W
R
O
W
2mVariable Variable
RCC Retaining Wall
PCC Wall
Lined Drain (Approach Slab
should be provided where
Cross road exists)
2.0m
Space for Maintenance Office, Bus bay, etc
Space for Medical Assistance Booth, Bus Bay, etc.
Safety Barrier as per Codal Provision
Conc. Block Pavement as required
C
L
Figure 2A : Typical Cross section at RE Wall Portion(Ch: 0.119Km to Ch:0.213Km)
R
O
W
R
O
W
R
O
W
11.5m11.5m 1.5m
0.5m 0.5m
BC
DBM
Granular Base
Granular Sub Base as Drainage Layer
Granular Sub Base as Separation Layer
500mm Thick Selective Subgrade
Fill Materials
Main Carriageway
Main Carriageway
9m 2m9m2m
Slip Road
Slip Road
RCC Retaining Wall
PCC Wall
Lined Drain (Approach Slab
should be provided where
Cross road exists)
Safety Barrier as per Codal Provision
PROJECT
Construction of proposed 6 lane Elevated connector between Belghoria Expressway and Kalyani
Expressway including widening of Kalyani Expressway to 6 lane from Nimta to Muragacha (total length 4.565
km) (Phase - I) on EPC mode in the district of North 24 Parganas in West Bengal
AUTHORITY
WEST BENGAL HIGHWAY DEVELOPMENT
CORPORATION LIMITED
Revision No.:
Not to Scale
September 2018
R0
Dwg. No.:DBKE/Ph-I/SA-PA/TCS/01
SEGMENT A
PART A
Scale:
Date:
AMEN
DM
ENT
- 1
BC
DBM
Granular Base
Granular Sub Base as Drainage Layer
Granular Sub Base as Separation Layer
500mm Thick Selective Sub-grade
Figure 3A : Typical Cross section at Viaduct Portion (variable height)(Ch:0.213Km To Ch:0.433Km )
R
O
W
R
O
W
R
O
W
R
O
W
R
O
W
R
O
W
Pile Cap
11.5m 11.5m0.50m
1.50m
0.50m
Main CarriagewayMain Carriageway
7.5m
Clear height atleast 5.5m
Clear height atleast 5.5m
7.5m1.5m 1.5m 2.0m2.0m
Pier Cap
Slip Road
Slip Road
Granular Sub Base as Separation Layer
500mm Thick Selective Sub-grade
BC
DBM
Granular Base
Granular Sub Base as Drainage Layer
BC
DBM
Granular Base
Granular Sub Base as Drainage Layer
Granular Sub Base as Separation Layer
Selective Subgrade
Pile Cap
Figure 4A : Typical Cross Section Viaduct Portion (Full Height)(Ch: 0.433 km to 1.200 km)
11.5m 11.5m0.50m
1.50m
0.50m
Cle
ar h
eig
ht a
tle
ast 5
.5
m
Cle
ar h
eig
ht a
tle
ast 5
.5
m
8m4m2m 8m 4m 2m
R
O
W
R
O
W
R
O
W
R
O
W
R
O
W
R
O
W
Slip Road
Slip Road
Service Road
Service Road
Main CarriagewayMain Carriageway
PROJECT
Construction of proposed 6 lane Elevated connector between Belghoria Expressway and Kalyani
Expressway including widening of Kalyani Expressway to 6 lane from Nimta to Muragacha (total length 4.565
km) (Phase - I) on EPC mode in the district of North 24 Parganas in West Bengal
AUTHORITY
WEST BENGAL HIGHWAY DEVELOPMENT
CORPORATION LIMITED
Revision No.:
Not to Scale
September 2018
R0
Dwg. No.:DBKE/Ph-I/SA-PA/TCS/02
SEGMENT A
PART A
Scale:
Date:
AMEN
DM
ENT
- 1
Granular Sub Base as Separation Layer
500mm Thick Selective Sub-grade
BC
DBM
Granular Base
Granular Sub Base as Drainage Layer
BC
DBM
Granular Base
Granular Sub Base as Drainage Layer
Granular Sub Base as Separation Layer
Selective Subgrade
Pile Cap
Figure 4B : Typical Cross Section Viaduct Portion (Full Height)(Ch: 1.200 km to 1.493 km)
11.5m 11.5m0.50m
1.50m
0.50m
Clear height atleast 5.5m
Clear height atleast 5.5m
8m4m2m 8m 4m 2m
R
O
W
R
O
W
R
O
W
R
O
W
R
O
W
R
O
W
Slip Road
Slip Road
Service Road
Service Road
Main CarriagewayMain Carriageway
BC
DBM
Granular Base
Granular Sub Base as Drainage Layer
Granular Sub Base as Separation Layer
500mm Thick Selective Sub-grade
Figure 3A : Typical Cross section at Viaduct Portion (variable height)(Ch:0.213Km To Ch:0.433Km )
R
O
W
R
O
W
R
O
W
R
O
W
R
O
W
R
O
W
Pile Cap
11.5m 11.5m0.50m
1.50m
0.50m
Main CarriagewayMain Carriageway
7.5m
Cle
ar h
eig
ht a
tle
ast 5
.5
m
Cle
ar h
eig
ht a
tle
ast 5
.5
m
7.5m1.5m 1.5m 2.0m2.0m
Pier Cap
Slip Road
Slip Road
PROJECT
Construction of proposed 6 lane Elevated connector between Belghoria Expressway and Kalyani
Expressway including widening of Kalyani Expressway to 6 lane from Nimta to Muragacha (total length 4.565
km) (Phase - I) on EPC mode in the district of North 24 Parganas in West Bengal
AUTHORITY
WEST BENGAL HIGHWAY DEVELOPMENT
CORPORATION LIMITED
Revision No.:
Not to Scale
September 2018
R0
Dwg. No.:DBKE/Ph-I/SA-PA/TCS/03
SEGMENT A
PART A
Scale:
Date:
AMEN
DM
ENT
- 1C
L
Figure 2B : Typical Cross section at RE Wall Portion(Ch: 1.688 km to 1.792 km)
R
O
W
R
O
W
R
O
W
11.5m11.5m 1.5m
0.5m 0.5m
BC
DBM
Granular Base
Granular Sub Base as Drainage Layer
Granular Sub Base as Separation Layer
500mm Thick Selective Subgrade
Fill Materials
Main Carriageway
Main Carriageway
9m 2m9m2m
Slip Road
Slip Road
BC
DBM
Granular Base
Granular Sub Base as Drainage Layer
Granular Sub Base as Separation Layer
500mm Thick Selective Sub-grade
C
L
Figure 5 : Typical Cross section(Ch: 1.792Km to Ch: 2.00Km)
BC
DBM
R
O
W
R
O
W
R
O
W
R
O
W
R
O
W
R
O
W
11.5m 11.5m
0.5m 0.5m
Main Carriageway
Main Carriageway
2m 8.5m 8.5m 2m
Variable Variable
Slip Road
Slip Road
Granular Base
Granular Sub Base as Drainage Layer
Granular Sub Base as Separation Layer
500mm Thick Selective Sub-grade
PROJECT
Construction of proposed 6 lane Elevated connector between Belghoria Expressway and Kalyani
Expressway including widening of Kalyani Expressway to 6 lane from Nimta to Muragacha (total length 4.565
km) (Phase - I) on EPC mode in the district of North 24 Parganas in West Bengal
AUTHORITY
WEST BENGAL HIGHWAY DEVELOPMENT
CORPORATION LIMITED
Revision No.:
Not to Scale
September 2018
R0
Dwg. No.:DBKE/Ph-I/SA-PA/TCS/04
SEGMENT A
PART A
Scale:
Date:
AMEN
DM
ENT
- 1
BC
DBM
Granular Base
Granular Sub Base for Drainage &
Separation layers
Figure: 7 - Typical Cross section at Viaduct Portion (Full Height) (Ch: 3+240
to Ch: 3+515 & Ch. 3+620 to Ch. 3+895)
BC
DBM
Granular Base
Granular Sub Base for Drainage &
Separation Layers
7.5m7.5m1.5m
5.5m1.5m
2m 7.5m
8m 0.5m0.5m
Cra
sh
B
arrie
r
Cra
sh
B
arrie
r
Subgrade
1.5m
5.5m 1.5m
2m
RO
WR
OW
RO
W
RO
W
RO
WR
OW
Safety Barrier as per Codal Provision
RCC Retaining Wall
PCC Wall
Lined Drain (Approach Slab
should be provided where
Cross Road exists)
Safety Barrier as per Codal Provision
RCC Retaining Wall
PCC Wall
Lined Drain (Approach Slab
should be provided where
Cross Road exists)
BC
DBM
Granular Base
Granular Sub Base for Drainage &
Separation layers
Figure: 6 - Typical Cross section at Viaduct Portion (Full Height) &
Intersection with Kalyani Expressway (Ch: 3+515 to Ch: 3+620)
BC
DBM
Granular Base
Granular Sub Base for Drainage &
Separation Layers
7.5m7.5m1.5m
5.5m1.5m
2m 7.5m
8m 0.5m0.5m
Cra
sh
B
arrie
r
Cra
sh
B
arrie
r
Subgrade
RO
WR
OW
RO
W
Safety Barrier as per Codal Provision
RCC Retaining Wall
PCC Wall
Lined Drain (Approach Slab
should be provided where
Cross Road exists)
PROJECT
Construction of proposed 6 lane Elevated connector between Belghoria Expressway and Kalyani
Expressway including widening of Kalyani Expressway to 6 lane from Nimta to Muragacha (total length 4.565
km) (Phase - I) on EPC mode in the district of North 24 Parganas in West Bengal
AUTHORITY
WEST BENGAL HIGHWAY DEVELOPMENT
CORPORATION LIMITED
Scale:
Revision No.:
Date:
Not to Scale
September 2018
R0
Dwg. No.:DBKE/Ph-I/SA-PB/TCS/01
SEGMENT A
PART B
AMEN
DM
ENT
- 1
BC
DBM
Granular Base
Granular Sub Base as Drainage &
Separation Layers
BC
DBM
Granular Base
Granular Sub Base as Drainage &
Separation layers
7.5m 8m 7.5m7.5m1.5m 1.5m
1.5m
1.5m
2m
5.5m
1.5m
2m
RO
WR
OW
RO
W
RO
W
RO
WR
OW
Figure: 9 - Typical Cross section before Tapering Portion
(Ch: 3+050 to Ch: 3+100 & Ch. 4+050 to Ch. 4+100)
Safety Barrier as per Codal Provision
RCC Retaining Wall
PCC Wall
Lined Drain (Approach Slab
should be provided where
Cross Road exists)
BC
DBM
Granular Base
Granular Sub Base as Drainage &
Separation Layers
BC
DBM
Granular Base
Granular Sub Base as Drainage &
Separation layers
0.5m 8m 0.5m
Cra
sh
B
arrie
r
Cra
sh
B
arrie
r
7.5m7.5m1.5m 7.5m 1.5m 5.5m
1.5m
5.5m
1.50
2m2m
RO
W
RO
W
RO
W
RO
W
RO
WR
OW
Figure: 8 - Typical Cross section at RE wall Portion
(Ch: 3+100 to Ch: 3+240 & Ch. 3+895 to Ch. 4+050)
Safety Barrier as per Codal Provision
RCC Retaining Wall
PCC Wall
Lined Drain (Approach Slab
should be provided where
Cross Road exists)
PROJECT
Construction of proposed 6 lane Elevated connector between Belghoria Expressway and Kalyani
Expressway including widening of Kalyani Expressway to 6 lane from Nimta to Muragacha (total length 4.565
km) (Phase - I) on EPC mode in the district of North 24 Parganas in West Bengal
AUTHORITY
WEST BENGAL HIGHWAY DEVELOPMENT
CORPORATION LIMITED
Scale:
Revision No.:
Date:
Not to Scale
September 2018
R0
Dwg. No.:DBKE/Ph-I/SA-PB/TCS/02
SEGMENT A
PART B
AMEN
DM
ENT
- 1
BC
DBM
Granular Base
Granular Sub Base as Drainage Layer
Granular Sub Base as Separation Layer
BC
DBM
Granular Base
Granular Sub Base as Drainage Layer
Granular Sub Base as Separation Layer
500mm Thick Selective Subgrade
Figure 10: Typical Cross Section at RE Wall portion(Ch. 2.000 to Ch. 2.495 & Ch. 3.775 to Ch. 4.238)
Fill Materials
Selective Subgrade
R
O
W
R
O
W
R
O
W
R
O
W
R
O
W
R
O
W
1.5m 11.5m 0.5m11.5m0.5m
8.5m 2m8.5m2m
Main CarriagewayMain Carriageway
Slip Road
Slip Road
Drain C
um
F
ootpath
Drain C
um
F
ootpath
2m
S
pace for U
tilities
2m
S
pace for U
tilities
BC
DBM
Granular Base
Granular Sub Base as Drainage Layer
Granular Sub Base as Separation Layer
500mm Thick Selective Subgrade
Existing Subgrade
BC
DBM
Granular Base
Granular Sub Base as Drainage Layer
Granular Sub Base as Separation Layer
500mm Thick Selective Subgrade
Proposed Selective Subgrade
R
O
W
R
O
W
R
O
W
2m
S
pace for U
tilities
R
O
W
R
O
W
R
O
W
2m
S
pace for U
tilities
2m 7m 11m2m 11m 2m 2m7m
Drain C
um
F
ootpath
Drain C
um
F
ootpath
Service Road
Service Road
Main Carriageway
Main Carriageway
Paved S
houlder
Paved S
houlder
Figure 11: Typical Cross Section before & after RE Wall portion(Ch. 2.495 to Ch. 3.775 & Ch. 4.238 to Ch. 4.565)
Concrete B
lock
Protection as per
Codal P
rovision
Concrete B
lock
Protection as per
Codal P
rovision
PROJECT
Construction of proposed 6 lane Elevated connector between Belghoria Expressway and Kalyani
Expressway including widening of Kalyani Expressway to 6 lane from Nimta to Muragacha (total length 4.565
km) (Phase - I) on EPC mode in the district of North 24 Parganas in West Bengal
AUTHORITY
WEST BENGAL HIGHWAY DEVELOPMENT
CORPORATION LIMITED
Scale:
Revision No.:
Date:
Not to Scale
September 2018
R0
Dwg. No.:DBKE/Ph-I/SB/TCS/01
SEGMENT B
AMEN
DM
ENT
- 1Construction of proposed 6 lane Elevated Connector between Belghoria Expressway & Kalyani Expressway including widening of Kalyani Expressway to 6 lane from Nimta to Muragacha (Length – 4.565) (Phase-I) in the district of North 24 Parganas on EPC Mode
SCHEDULE – D
SCHEDULE – C
(See Clause 2.1)
PROJECT FACILITIES
The following modifications shall be read concurrently with Schedule C 2. Description of Project Facilities
c) Electrical Illumination
Section Location Design Requirements
As per the applicable project stretches falling under definitions of 12.3.3, Section 12 of Manual
1 High mast Lighting between Ch. 0.000 – 0.200
& street lighting over the entire project highway
As per paragraph 12.3 of Section -12 of Manual &
as stated below
Design Requirements & Specifications:
Specification of LED Street Light Luminaries
Sl No.
Criteria Desired Specification Test to be carried Out
1 LED Street Light Luminaries Configuration
Side entry suitable for mounting on 40-60 mm OD pipe bracket
N/A
2 Make of Offered Luminaries
Philips/Schreder Lighting/ Lighting Technology
N/A
3 Make/Logo of offered Luminaries
Name shall be embossed/engraved on the luminaries
N/A
4 Make of Offered Driver
Driver shall be of same manufacturer as of luminaries and on each driver its part no., technical details and logo of luminaire manufacture shall be embossed
N/A
5 Housing / Body of luminaire with cover
Pressure die-cast aluminium / Stainless steel housing & frame with corrosion resistance powder coated with Poly Carbonate/HT Glass Cover with manufacturers name embossed on the die cast housing
NABL Acc. Lab / Test report as per IS: 10322 part 5 Sec-3
6 IP Rating Minimum IP rating of 66 IEC: 60598-2-3
7 Operating Voltage & Surge Protection
140-270 Volt to universal electronic driver with inbuilt surge protection of minimum 4KV
NABL Acc. Lab / report
8 Operational Frequency
50Hz (+/- 5%) NABL Acc. Lab / report
9 Operating Temperature
Temp: 5 - 50 deg C
NABL Acc. Lab report/* As per IS 10322 Part 5 sec-3 sample will be tested at ambient temperature + 10 Deg C. Hence 60Deg C in this case
AMEN
DM
ENT
- 1Construction of proposed 6 lane Elevated Connector between Belghoria Expressway & Kalyani Expressway including widening of Kalyani Expressway to 6 lane from Nimta to Muragacha (Length – 4.565) (Phase-I) in the district of North 24 Parganas on EPC Mode
SCHEDULE – D
10 Power Factor Greater than 0.9 NABL Acc. Lab / report
11 System Luminous Efficacy
Minimum 100 lumens/watt LM79/IS 16106
12 Driver Type Constant Current NABL Acc. Lab / report
13 Color Temperature
Between 5000K and 6000K LM 80/IS 16105
14 CRI > 70 LM 80/IS 16105
15 Thermal Management
LED must be mounted on Al heat sink with suitable large surface area with fins to dissipate the heat to ambient air. Luminaire body temperature shall not exceed 30 Deg C from the ambient even after continuous operation of luminaire for 24 hours
NABL Acc. Lab / report accreditation agency Lab report
16 Reported Lumen Maintenance L70
> 50000 hrs, at highest test case temperature
LM 80/IS 16105 methodology
17 Electrical and Photometric measurement
Test report of offered LED luminaire for CCT, CRI, luminous flux and luminous efficacy (Luminaire)
LM 79/IS 16106 from NABL Acc. Lab/ report. The report shall be of within 5 years from the date of issue of RFQ.
18 Driver Specification with protections
140-270 Volt universal electronic drivers with protection of minimum 4KV internal surge, Under Voltage, Over Voltage, Short Circuit
NABL Acc. Lab / report, BIS approval
19
THD (Total Harmonic Distortion) for Current
< 20% NABL Acc. Lab / report IEC: 610003-2
20 Make of LED chip
Lumileds/CREE/NICHIA/OSRAM/Bridgelux/LG
Manufacturer of Luminaire shall submit proof of Procurement of LEDs and LM80/ IS 16105 Test reports of Specific LED.
21 Confirmation to standards
The luminaire should conform to IEC 60598/ IS: 10322. The luminaire should be tested as per IEC 60598-2-3:2002/ IS:10322 Part 5 Sec-3 standards and following test reports should be submitted: Heat Resistance Test, Thermal Test, Insulation Resistance Test
NABL Acc. Lab / as per IS:10322 part 5 Sec-3/IEC:60598-2-3
22 Electrical Safety as per IEC
As per IEC safety standard. (IEC 60598/IS: 10322)
NABL Acc. Lab/report as per IS: 10322 part 5 Sec-3/IEC: 60598-2-3
23 Warranty The party shall provide warranty of 5 years from Delivery
NA
Specification of LED Flood Light Luminaries
Sl No.
Criteria Desired Specification Test to be carried Out
AMEN
DM
ENT
- 1Construction of proposed 6 lane Elevated Connector between Belghoria Expressway & Kalyani Expressway including widening of Kalyani Expressway to 6 lane from Nimta to Muragacha (Length – 4.565) (Phase-I) in the district of North 24 Parganas on EPC Mode
SCHEDULE – D
1 LED Flood Light Luminaries Mounting
Universal bracket N/A
2 Make of Offered Luminaries
Philips/Schreder Lighting/ Lighting Technology
N/A
3 Make/Logo of offered Luminaries
Name shall be embossed/engraved on the luminaries
N/A
4 Make of Offered Driver
Driver shall be of same manufacturer as of luminaries and on each driver its part no., technical details and logo of luminaire manufacture shall be embossed
N/A
5 Housing / Body of luminaire with cover
Pressure die-cast aluminum / Stainless steel housing & frame with corrosion resistance powder coated with Poly Carbonate/HT Glass Cover with manufacturers name embossed on the die cast housing
NABL Acc. Lab / Test report as per IS: 10322 part 5 Sec-3
6 IP Rating Minimum IP rating of 66 IEC: 60598-2-3
7 Operating Voltage & Surge Protection
140-270 Volt to universal electronic driver with inbuilt surge protection of minimum 4KV
NABL Acc. Lab / report
8 Operational Frequency
50Hz (+/- 5%) NABL Acc. Lab / report
9 Operating Temperature
Temp: 5 - 50 deg C
NABL Acc. Lab report/* As per IS 10322 Part 5 sec-3 sample will be tested at ambient temperature + 10 Deg C. Hence 60Deg C in this case
10 Power Factor Greater than 0.9 NABL Acc. Lab / report
11 System Luminous Efficacy
Minimum 100 lumens/watt LM79/IS16106
12 Driver Type Constant Current NABL Acc. Lab / report
13 Color Temperature
Between 5000K and 6000K LM 80/IS 16105
14 CRI > 70 LM 80/IS 16105
15 Thermal Management
LED must be mounted on Al heat sink with suitable large surface area with fins to dissipate the heat to ambient air. Luminaire body temperature shall not exceed 30 Deg C from the ambient even after continuous operation of luminaire for 24 hours
NABL Acc. Lab / report accreditation agency Lab report
16 Reported Lumen Maintenance L70
> 50000 hrs, at highest test case temperature
LM 80/IS 16105 methodology
17 Electrical and Photometric measurement
Test report of offered LED luminaire for CCT, CRI, luminous flux and luminous efficacy (Luminaire)
LM 79/IS 16106 from NABL Acc. Lab/ report. The report shall be of within 5 years from the date of issue of
AMEN
DM
ENT
- 1Construction of proposed 6 lane Elevated Connector between Belghoria Expressway & Kalyani Expressway including widening of Kalyani Expressway to 6 lane from Nimta to Muragacha (Length – 4.565) (Phase-I) in the district of North 24 Parganas on EPC Mode
SCHEDULE – D
RFQ.
18 Driver Specification with protections
140-270 Volt universal electronic drivers with protection of minimum 4KV internal surge, Under Voltage, Over Voltage, Short Circuit
NABL Acc. Lab / report, BIS approval
19
THD (Total Harmonic Distortion) for Current
< 20% NABL Acc. Lab / report IEC: 610003-2
20 Make of LED chip
Lumileds/CREE/NICHIA/OSRAM/Bridgelux/LG
Manufacturer of Luminaire shall submit proof of Procurement of LEDs and LM80/ IS 16105 Test reports of Specific LED.
21 Confirmation to standards
The luminaire should conform to IEC 60598/ IS: 10322. The luminaire should be tested as per IEC 60598-2-3:2002/ IS:10322 Part 5 Sec-3 standards and following test reports should be submitted: Heat Resistance Test, Thermal Test, Insulation Resistance Test
NABL Acc. Lab / as per IS:10322 part 5 Sec-3/IEC:60598-2-3
22 Electrical Safety as per IEC
As per IEC safety standard. (IEC 60598/IS: 10322)
NABL Acc. Lab/report as per IS: 10322 part 5 Sec-3/IEC: 60598-2-3
23 Warranty
The party shall provide warranty of 5 years from Delivery
NA
The contractor shall install these electrical installations and secure electrical connection from the concerned service provider (WBSEDCL / CESC etc.) as per Schedule H. However, the electricity usage charges after connection from the concerned service provider shall be paid by the contractor until the end of maintenance period & Authority shall reimburse the same upon receipt of the proof of payment. Any late payment by the contractor to the utility provider shall not be entertained in any manner, whatsoever.
f) Medical Assistance & Booth Office The contractor shall in consultation with the Authority finalize the drawings as per the design requirements stated in Schedule C
g) Maintenance office for WBHDCL The contractor shall in consultation with the Authority finalize the drawings as per the design requirements stated in Schedule C
h) Bus Parking slots
Section Location Design Requirements
Segment A Part A
(direction towards Kalyani Expressway from Belghoria
Expressway)
0.140 (on LHS & RHS) nearby passenger shelters
Fully paved & marking for slots of atleast 10Nos. buses & signage with road marking paint
AMEN
DM
ENT
- 1Construction of proposed 6 lane Elevated Connector between Belghoria Expressway & Kalyani Expressway including widening of Kalyani Expressway to 6 lane from Nimta to Muragacha (Length – 4.565) (Phase-I) in the district of North 24 Parganas on EPC Mode
SCHEDULE – H
SCHEDULE – H
(See Clause 10.1.4 & 19.3)
CONTRACT WEIGHT PERCENTAGES
1.1. The Contract Price for this Agreement is Rs. ******
1.2. Proportions of the Contract Price for different stages of Construction of the Project Highway
shall be as specified below:
Section Weightage w.r.t Contract Price
Stage for Payment Percentage Weightage
Segment A 85.15% Part A 73.55%
Part B 26.45%
Segment B 14.85% Segment B 100%
Segment A – Part A
Description % Weightage w.r.t Section
Stage for Payment Percentage Weightage
Road Works 12.95%
Main Carriage Way 19.23%
Service Roads 10.68%
Slip Roads 41.32%
Cross Drainage Works 4.62%
R C Retaining Wall 2.54%
Surface Drain 16.44%
Protective Work 0.03%
Miscellaneous Works1 5.14%
Bridge Works (Elevated Corridor)
86.26%
Foundation 57.77%
Sub Structure 9.08%
Super Structure 27.19%
Approach Ramp 5.69%
Miscellaneous Works 0.27%
Electrical & Illumination Works
0.79% Electrical & Illumination Works 100%
Segment A – Part B
Description Weightage w.r.t
Section Stage for Payment
Percentage Weightage
Road Works 41.08%
Main Carriage Way 35.42%
Service Roads 19.08%
Slip Roads -
Cross Drainage Works 8.06%
R C Retaining Wall 24.04%
Surface Drain 9.60%
Protective Work 0.02%
Miscellaneous Works2 3.78%
Bridge Works (Elevated Corridor)
56.97%
Foundation 51.88%
Sub Structure 7.16%
Super Structure 22.83%
Approach Ramp 17.01%
1 Miscellaneous works shall include a) tree cutting, transportation, stacking, watch & ward until disposal by
Authority b) road signage, road marking, painting, turfing / slope pitching & other finishing works 2 Miscellaneous works shall include a) tree cutting, transportation, stacking, watch & ward until disposal by
Authority b) road signage, road marking, painting, turfing / slope pitching & other finishing works
AMEN
DM
ENT
- 1Construction of proposed 6 lane Elevated Connector between Belghoria Expressway & Kalyani Expressway including widening of Kalyani Expressway to 6 lane from Nimta to Muragacha (Length – 4.565) (Phase-I) in the district of North 24 Parganas on EPC Mode
SCHEDULE – H
Miscellaneous Works 1.12%
Electrical & Illumination Works
1.95% Electrical & Illumination Works 100%
Segment B
Description Weightage w.r.t
Section Stage for Payment
Percentage Weightage
Road Works 51.38%
Main Carriage Way 40.29%
Service Roads 21.69%
Slip Roads 15.49%
Cross Drainage Works 5.19%
R C Retaining Wall -
Surface Drain 7.57%
Protective Work 4.15%
Miscellaneous Works3 5.62%
Bridge Works (LVUP & PUP)
43.70%
LVUP 6.68%
PUP 11.53%
Approach Ramp 81.79%
Electrical & Illumination Works
4.93% Electrical & Illumination Works 100%
3 Miscellaneous works shall include a) tree cutting, transportation, stacking, watch & ward until disposal by
Authority b) road signage, road marking, painting, turfing / slope pitching & other finishing works
AMEN
DM
ENT
- 1Construction of proposed 6 lane Elevated Connector between Belghoria Expressway & Kalyani Expressway including widening of Kalyani Expressway to 6 lane from Nimta to Muragacha (Length – 4.565) (Phase-I) in the district of North 24 Parganas on EPC Mode
SCHEDULE – H
1.3. Procedure of estimating the value of work done shall be as follows:-
Segment A – Part A
Stage Stage Stage for Payment Percentage Weightage
Payment Procedure
Road Works
Main Carriage Way
Earth Work up to Top of the Subgrade
39.12% Unit of measurement is linear Length. Payment of each
stage shall be made on pro rata basis on completion of a stage in a length not less than 10 (ten) percent of the total
length.
Sub-Base Course 16.16%
Non Bituminous Base Course 15.98%
Bituminous Base Course 24.63%
Wearing Coat 4.11%
Service Roads
Earth Work up to Top of the Subgrade
48.29% Unit of measurement is linear Length. Payment of each
stage shall be made on pro rata basis on completion of a stage in a length not less than 10 (ten) percent of the total
length.
Sub-Base Course 12.48%
Non Bituminous Base Course 12.13%
Bituminous Base Course 22.16%
Wearing Coat 4.94%
Slip Roads
Earth Work up to Top of the Subgrade
51.26% Unit of measurement is linear Length. Payment of each
stage shall be made on pro rata basis on completion of a stage in a length not less than 10 (ten) percent of the total
length.
Sub-Base Course 12.63%
Non Bituminous Base Course 12.12%
Bituminous Base Course 20.13%
Wearing Coat 3.86%
Cross Drainage Works
Cross Drainage Works 100% Cost of completed culvert shall be determined pro rata basis with respect to the total no of culvert. The payment shall be
made on completion of at least 1 (One) Culvert.
R C Retaining Wall
R C Retaining Wall 100% Payment shall be made on completion of all Works,
Complete in all respects as specified.
Surface Drain Surface Drain 100% Payment shall be made on completion of all Works,
Complete in all respects as specified.
Protective Work Protective Work 100% Payment shall be made on completion of all Works,
Complete in all respects as specified.
Miscellaneous Works
Tree cutting, transporting, stacking, watch & ward
7.43% Payment shall be made on completion of works as specified
road signage, road marking, painting, turfing / slope pitching &
other finishing works 92.57% Payment shall be made on completion of works as specified
AMEN
DM
ENT
- 1Construction of proposed 6 lane Elevated Connector between Belghoria Expressway & Kalyani Expressway including widening of Kalyani Expressway to 6 lane from Nimta to Muragacha (Length – 4.565) (Phase-I) in the district of North 24 Parganas on EPC Mode
SCHEDULE – H
Bridge Works (Elevated Corridor)
Foundation - 57.77%
Cost of each structure shall be determined on pro rata basis with respect to the total linear length (m) of the structures.
Payment against foundation shall be made on pro rata basis on completion of a stage i.e. not less than 10% of the scope
of foundation of the structure subject to completion of at least 2 (two) foundations of the structure. In case of where
load testing is required for foundation, the trigger of first payment shall include load testing also where specified.
Sub Structure - 9.08%
Payment against Sub-Structure shall be made on pro rata basis on completion of a stage i.e. not less than 10% of the
scope of Sub-Structure of the structure subject to completion of at least 2 (two) Sub-Substructures of abutment/piers up to
abutment /pier cap level of the structure.
Super Structure - 27.19% Payment shall be made on pro rata basis on completion of a stage i.e. completion of super structure including bearing of
at least 1 (one) span is all respect in specified.
Approach Ramp - 5.69% Payment shall be made on completion of both approaches including RE Walls, Protection Works, etc. Complete in all
respects as specified.
Miscellaneous Works
- 0.27% Payment shall be made on completion of all miscellaneous
works.
Electrical & Illumination
Works
Electrical & Illumination Works
- 100% Payment shall be made on completion of all Works,
Complete in all respects as specified.
Segment A – Part B
Stage Stage Stage for Payment Percentage Weightage
Payment Procedure
Road Works
Main Carriage Way
Earth Work up to Top of the Subgrade
46.82% Unit of measurement is linear Length. Payment of each
stage shall be made on pro rata basis on completion of a stage in a length not less than 10 (ten) percent of the total
length.
Sub-Base Course 16.34%
Non Bituminous Base Course 16.11%
Bituminous Base Course 18.21%
Wearing Coat 2.52%
Service Roads
Earth Work up to Top of the Subgrade
29.16% Unit of measurement is linear Length. Payment of each
stage shall be made on pro rata basis on completion of a stage in a length not less than 10 (ten) percent of the total Sub-Base Course 16.87%
AMEN
DM
ENT
- 1Construction of proposed 6 lane Elevated Connector between Belghoria Expressway & Kalyani Expressway including widening of Kalyani Expressway to 6 lane from Nimta to Muragacha (Length – 4.565) (Phase-I) in the district of North 24 Parganas on EPC Mode
SCHEDULE – H
Non Bituminous Base Course 15.18% length.
Bituminous Base Course 26.67%
Wearing Coat 12.12%
Slip Roads
- -
-
- -
- -
- -
- -
Cross Drainage Works
Cross Drainage Works 100% Cost of completed culvert shall be determined pro rata basis with respect to the total no of culvert. The payment shall be
made on completion of at least 1 (One) Culvert.
R C Retaining Wall
R C Retaining Wall 100% Payment shall be made on completion of all Works,
Complete in all respects as specified.
Surface Drain Surface Drain 100% Payment shall be made on completion of all Works,
Complete in all respects as specified.
Protective Work Protective Work 100% Payment shall be made on completion of all Works,
Complete in all respects as specified.
Miscellaneous Works
Tree cutting, transporting, stacking, watch & ward
6.21% Payment shall be made on completion of works as specified
road signage, road marking, painting, turfing / slope pitching &
other finishing works 93.79% Payment shall be made on completion of works as specified
Bridge Works (Elevated Corridor)
Foundation - 51.88%
Cost of each structure shall be determined on pro rata basis with respect to the total linear length (m) of the structures.
Payment against foundation shall be made on pro rata basis on completion of a stage i.e. not less than 10% of the scope
of foundation of the structure subject to completion of at least 2 (two) foundations of the structure. In case of where
load testing is required for foundation, the trigger of first payment shall include load testing also where specified.
Sub Structure - 7.16%
Payment against Sub-Structure shall be made on pro rata basis on completion of a stage i.e. not less than 10% of the
scope of Sub-Structure of the structure subject to completion of at least 2 (two) Sub-Substructures of abutment/piers up to
abutment /pier cap level of the structure.
Super Structure - 22.83% Payment shall be made on pro rata basis on completion of a stage i.e. completion of super structure including bearing of
at least 1 (one) span is all respect in specified.
AMEN
DM
ENT
- 1Construction of proposed 6 lane Elevated Connector between Belghoria Expressway & Kalyani Expressway including widening of Kalyani Expressway to 6 lane from Nimta to Muragacha (Length – 4.565) (Phase-I) in the district of North 24 Parganas on EPC Mode
SCHEDULE – H
Approach Ramp - 17.01% Payment shall be made on completion of both approaches including RE Walls, Protection Works, etc. Complete in all
respects as specified.
Miscellaneous Works
- 1.12% Payment shall be made on completion of all miscellaneous
works.
Electrical & Illumination
Works
Electrical & Illumination Works
- 100% Payment shall be made on completion of all Works,
Complete in all respects as specified.
Segment B
Stage Stage Stage for Payment Percentage Weightage
Payment Procedure
Road Works
Main Carriage Way
Earth Work up to Top of the Subgrade
41.14% Unit of measurement is linear Length. Payment of each
stage shall be made on pro rata basis on completion of a stage in a length not less than 10 (ten) percent of the total
length.
Sub-Base Course 15.16%
Non Bituminous Base Course 14.96%
Bituminous Base Course 22.61%
Wearing Coat 6.13%
Service Roads
Earth Work up to Top of the Subgrade
46.18% Unit of measurement is linear Length. Payment of each
stage shall be made on pro rata basis on completion of a stage in a length not less than 10 (ten) percent of the total
length.
Sub-Base Course 13.14%
Non Bituminous Base Course 13.09%
Bituminous Base Course 21.43%
Wearing Coat 6.16%
Slip Roads
Earth Work up to Top of the Subgrade
48.16% Unit of measurement is linear Length. Payment of each
stage shall be made on pro rata basis on completion of a stage in a length not less than 10 (ten) percent of the total
length.
Sub-Base Course 12.64%
Non Bituminous Base Course 12.55%
Bituminous Base Course 22.48%
Wearing Coat 4.17%
Cross Drainage Works
Cross Drainage Works 100% Cost of completed culvert shall be determined pro rata basis with respect to the total no of culvert. The payment shall be
made on completion of at least 1 (One) Culvert.
R C Retaining Wall
R C Retaining Wall 100% Payment shall be made on completion of all Works,
Complete in all respects as specified.
Surface Drain Surface Drain 100% Payment shall be made on completion of all Works,
Complete in all respects as specified.
AMEN
DM
ENT
- 1Construction of proposed 6 lane Elevated Connector between Belghoria Expressway & Kalyani Expressway including widening of Kalyani Expressway to 6 lane from Nimta to Muragacha (Length – 4.565) (Phase-I) in the district of North 24 Parganas on EPC Mode
SCHEDULE – H
Protective Work Protective Work 100% Payment shall be made on completion of all Works,
Complete in all respects as specified.
Miscellaneous Works
Tree cutting, transporting, stacking, watch & ward
1.26% Payment shall be made on completion of works as specified
road signage, road marking, painting, turfing / slope pitching &
other finishing works 98.74% Payment shall be made on completion of works as specified
Bridge Works (LVUP &
PUP)
LVUP
Foundation 31.74%
Cost of each LVUP shall be determined on pro rata basis with respect to the total linear length (m) of the LVUP.
Payment against foundation + sub structure shall be made on pro rata basis on completion of a stage i.e. not less than 25 % of foundation+ substructure of each LVUP subject to
completion of at least two foundations along with sub structure up to abutment/ pier cap level each LVUP. In case of where load testing is required for foundation, the trigger of first payment shall include load testing also where specified.
Sub Structure 7.60%
Super Structure 50.37%
Payment of each stage shall be made on pro rata basis on completion of a stage i.e. completion of super structure of at least one span in all respects as specified in the column of
“stage of payment" in this sub clause.
Wearing Coat 3.87% Payment shall be made of completion of wearing coat including expansion joints complete in all respect as
specified.
Miscellaneous Works 6.42% Payment shall be made on completion of all miscellaneous
works.
PUP
Foundation 30.21%
Cost of each PUP shall be determined on pro rata basis with respect to the total linear length (m) of the PUP. Payment
against foundation + sub structure shall be made on pro rata basis on completion of a stage i.e. not less than 25 % of
foundation+ substructure of each PUP subject to completion of at least two foundations along with sub structure up to abutment/ pier cap level each PUP. In case of where load
testing is required for foundation, the trigger of first payment shall include load testing also where specified.
Sub Structure 7.58%
Super Structure 50.66%
Payment of each stage shall be made on pro rata basis on completion of a stage i.e. completion of super structure of at least one span in all respects as specified in the column of
“stage of payment" in this sub clause.
AMEN
DM
ENT
- 1Construction of proposed 6 lane Elevated Connector between Belghoria Expressway & Kalyani Expressway including widening of Kalyani Expressway to 6 lane from Nimta to Muragacha (Length – 4.565) (Phase-I) in the district of North 24 Parganas on EPC Mode
SCHEDULE – H
Wearing Coat 4.33% Payment shall be made of completion of wearing coat including expansion joints complete in all respect as
specified.
Miscellaneous Works 7.22% Payment shall be made on completion of all miscellaneous
works.
Approach Ramps - 100% Payment shall be made on completion of both approaches including RE Walls, Protection Works, etc. Complete in all
respects as specified.
Electrical & Illumination
Works
Electrical & Illumination Works
- 100% Payment shall be made on completion of all Works,
Complete in all respects as specified.
2. Procedure for payment for maintenance 2.1 The cost for maintenance shall be as stated in clause 14.1.1 2.2 Payment for maintenance shall be made in quarterly installments in accordance with the provisions of clause 19.7