No of segments 1001 Concrete / segment 28.18182 TOTAL CONCRTE QUANTITY = 456 * 57 = 28210 Project duration 24 months Mobilisation period 4 months Post casting period 2 months So, casting period 18 months Segments / month to be cast 55.61111 nos Item Unit Qty Design fees. LS 1 ton 180 Resale as scrap @ 20000/ton ton 180 Machined items for the moulds LS 1 Load 40% in this project LS 0.4 cum 28210 Gantry foundations cum 280 rebar for them ton 28 Stacking foundations cum 266.4 rebar for them ton 26.64 Electrical and plumbing lines at yard LS 1 LS 1 100ton & 20 ton gantries 25m span, 8.5mLS 1 Load 40% in this project LS 0.4 LS 2 Load 40% in this project LS 0.4 Diesel for yard 2 casting beds comprising of 2 pier segment moulds & 4 typ seg moulds will be provided in 1 long line 350m long. jigs excluding rebar but with consumables (high frequency & form vibrators not included) including, curing, repairing (grout material not included), handling and loading for transportation staff Cost of 2 125 Kva DG sets to be taken to give 24 hrs supply from 2 Dg sets to whole yard area.

Upload: rohit-bali

Post on 17-Dec-2015

212 views

Category:

Documents


0 download

DESCRIPTION

file

TRANSCRIPT

estimate

No of segments1001Concrete / segment28.1818181818TOTAL CONCRTE QUANTITY = 456 * 57 = 28210

Project duration24monthsMobilisation period4monthsPost casting period2monthsSo, casting period18monthsSegments / month to be cast55.6111111111nos2 casting beds comprising of 2 pier segment moulds & 4 typ seg moulds will be provided in 1 long line 350m long.

ItemUnitQtyRateAmount

Design fees.LS12,000,0002,000,0002 set moulds with lifting beam, rebar jigston18080,00014,400,000Resale as scrap @ 20000/tonton180(20,000)(3,600,000)Machined items for the mouldsLS1Load 40% in this projectLS0.4600,000240,000Labor rate for casting of the beams excluding rebar but with consumables (high frequency & form vibrators not included) including, curing, repairing (grout material not included), handling and loading for transportationcum282102,10059,241,000

Gantry foundationscum2805,5001,540,000rebar for themton2853,0001,484,000

Stacking foundationscum266.45,5001,465,200rebar for themton26.6453,0001,411,920

Electrical and plumbing lines at yardLS12,000,0002,000,000Office, accommodation for 100 labor & staffLS13,000,0003,000,000

100ton & 20 ton gantries 25m span, 8.5m clear height & 2 nos DG setsLS10.0Load 40% in this projectLS0.415,000,0006,000,000

Cost of 2 125 Kva DG sets to be taken to give 24 hrs supply from 2 Dg sets to whole yard area.LS2600,000Load 40% in this projectLS0.4600,000480,000

Diesel for yardDiesel for gantries (10 hrs running / day x 30days x 19 mnths x 7ltr/hr) x 2 dgsltr79800554,389,000Diesel for yard (20 hrs x79ltr/hr x 30days x 25 months)ltr105000555,775,000Concrete with pouring to be loaded.99,826,120Rate / cum3,538.68RATE MARKED IN YELLOW ARE ASSUMPTIONS. KINDLY GET ACTUAL RATES.NOTE: 1 Batching plant will be at casting yard. 2nd BP will be for site near the site.