final-corrected calculation (concrete)

6
Estimating Seminar: Calculation (Chapter 7) Question 5: Concrete Note: Strip foundation is on a solid ground thus no blinding needed FORMWORK Note: Formwork needed for this strip foundation only includes 4 sides of t he rectangle, front back and left right excluding bottom and top. Step 1 : Material cost Item Description Calculation Unit RM A. 1m 2 of 18mm plywood m 2  36.00 B. Allowance for cutting 15% waste RM 36.00 x   m 2  5.40 C. 0.03m3 of struts/m2 at Rm400/m3 Rm400/m3 x 0.03m2 m2 12.00 Total cost of timber m 2  53.40 D. Allow 4 uses for timber formwork  m 2  13.35 E. 10% wastage on each use RM 13.35 x  m 2  1.34 F. Allow for nail, bolts, mould oil m 2  1.50 Total cost for formwork per usage m 2  16.19 1.00m 0.30m

Upload: chunghuiping

Post on 05-Nov-2015

50 views

Category:

Documents


0 download

DESCRIPTION

Sem4 Estimating-Taylor's University (BQS)

TRANSCRIPT

  • Estimating Seminar: Calculation (Chapter 7)

    Question 5: Concrete

    Note:

    Strip foundation is on a solid ground thus no blinding needed

    FORMWORK

    Note:

    Formwork needed for this strip foundation only includes 4 sides of the rectangle, front back and left

    right excluding bottom and top.

    Step 1 : Material cost

    Item Description Calculation Unit RM

    A. 1m2 of 18mm plywood m2 36.00

    B. Allowance for cutting 15% waste RM 36.00 x

    m2 5.40

    C. 0.03m3 of struts/m2 at Rm400/m3 Rm400/m3 x 0.03m2 m2 12.00

    Total cost of timber m2 53.40

    D. Allow 4 uses for timber formwork

    m

    2 13.35

    E. 10% wastage on each use RM 13.35 x

    m2 1.34

    F. Allow for nail, bolts, mould oil m2 1.50

    Total cost for formwork per usage m2 16.19

    1.00m

    0.30m

  • Step 2 : Labour Cost

    I. Total quantity of formwork

    = [(1.0m x 2) + (30.0m x 2)] x 0.30m x 4 nos

    = 74.40m2

    To erect and strike 1m2 of formwork takes 1 hour

    Item Description Calculation Unit RM

    A. 1 Joiner RM8.00/hr x 1 hr/m2 m2 8.00

    B. 1 Labourer RM5.00/hr x 1 hr/m2 m2 5.00

    Total cost of labour m2 13.00

    Step 3 : Total Unit Rate

    Item Description Unit RM

    A. Material m2 16.19

    B. Labour m2 13.00

    Total unit rate m2 29.19

    Step 4 : Total Cost

    Total quantity of formwork x total unit rate = 74.40m2 x RM 29.19/m2

    = RM 2171.74

  • REINFORCEMENT BARS

    Step 1 : Material Cost (Tonnes)

    Item Description Calculation Unit RM

    A. High yield steel rebar deliver to site ton 1480.00

    B. Allow labour for stacking and loading ton 5.00

    C. Allow wastage 7% on rebar RM 1480 x

    ton 103.60

    D. Tie wire 0.66kg/100kg @ RM 4.80/kg

    x 1000 x RM4.80/kg

    ton 31.68

    E. Spacer ton 4.00

    F. Rolling Margin ton 22.00

    Total Material Cost ton 1646.28

    Step 2 : Labour Cost (per Tonne)

    Item Description Calculation Unit RM

    A. 1 skilled labour hr 6.00

    B. 1 unskilled labour hr 4.80

    Total hr 10.80

    C. Allow 10% idling time

    x 1000

    hr 1.08

    Total Cost of Labour hr 11.88

    Time required for 100kg

    = (28 + 32 + 35 + 23 + 7) mins/60 mins

    = 2.08 hours / 100kg

    = 0.0208 hour/kg

    = 20.8 hour/tonne

    Hence, labour cost per tonne = 20.80 hour/tonne x RM11.88

    = RM 247.10

  • Step 3 : Total Unit Rate

    Item Description Unit RM

    A. Material ton 1646.28

    B. Labour ton 247.10

    Total unit rate per tonne ton 1893.38

    Step 4 : Total Cost

    Total Volume of Concrete used for Strip Foundation

    = 0.30m x 1.0m x 30.0m

    = 9m3

    Since given allowance for rebar = 80kg/m3,

    Hence, for 1m3 the allowance for rebar will be

    = 9 m3 x

    = 720kg / 1000

    = 0.72 tonne

    Thus, total cost

    = RM 1893.38 x 0.72 tonne x 4 nos

    = RM 5452.93

  • CONCRETE

    Ratio 1 : 2 : 3

    Cement : Fine Aggregate : Coarse Aggregate

    Step 1 : Material Cost

    Item Description Calculation Unit RM

    A. OPC of 1420kg/m3 at RM 10.00/50kg

    x RM10.00 m3 284.00

    B. Fine aggregate 2m3 at 1600kg/m3 at

    RM30/tonne

    x RM30.00 x

    2m3

    m3

    96.00

    C. Coarse aggregate 3m3 at 1400kg/m3 at

    RM40/tonne

    x RM40.00 x

    3m3

    m3

    168.00

    m3 548.00

    D. Allow 20% placing wastage Rm548x0.12 m3 109.60

    Total m3 657.60

    E. Allow 50% shrinkage, consolidation,

    wastage

    Rm657.60x0.50 m3 328.80

    Total Cost for 6m3 of Concrete Mix 6m3 986.40

    Total Cost for 1m3 of Concrete Mix RM986.40/6m3 m3 164.40

  • Step 2 : Labour and Mix Plant

    Item Description Calculation Unit RM

    A. One mixer at 1.2m3/hr

    x RM5.00/hr m3 4.17

    B. Cost of labour

    x RM3.50

    x 5 people

    m3

    14.58

    C. Cost of labour placing concrete into

    foundation

    RM 5.00 x 0.66hr m3 3.00

    D. Cost of labour working around rebar RM 5.00 x 0.55hr m3 2.75

    E. Cost of vibrator RM 6.30/ 1.50m3 m3 4.20

    Total Cost m3 28.70

    Step 3 : Total unit rate

    Item Description Unit RM

    A. Material m3 164.40

    B. Labour m3 28.70

    Total unit rate m3 193.10

    Step 4 : Total Cost

    Total quantity of concrete = 0.30m x 1.0m x 30.0m x 4 nos

    = 36 m3

    Hence, total cost

    = 36 m3 x RM 193.10

    = RM 6951.60

    FINAL ANSWER

    Total Estimated cost for strip foundation = RM 2171.74 + RM 5452.93 + RM 6951.60

    = RM 14576.27