final environmental impact assessment and...
TRANSCRIPT
![Page 1: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/1.jpg)
FFFIIINNNAAALLL
EEENNNVVVIIIRRROOONNNMMMEEENNNTTTAAALLL IIIMMMPPPAAACCCTTT AAASSSSSSEEESSSSSSMMMEEENNNTTT
AAANNNDDD
EEENNNVVVIIIRRROOONNNMMMEEENNNTTTAAALLL MMMAAANNNAAAGGGEEEMMMEEENNNTTT PPPLLLAAANNN
OOOFFF
RRRAAAIIIPPPUUURRR AAARRRAAAIIIAAANNN SSSAAANNNDDD MMMIIINNNIIINNNGGG PPPRRROOOJJJEEECCCTTT
Village: Raipur Araian, Tehsil: Phillor, District: Jalandhar, State: Punjab
Area: 17.98 ha, Proposed Capacity: 1, 61,800 TPA
AAAPPPPPPLLLIIICCCAAANNNTTT
GM-CUM-MINING OFFICER
DEPARTMENT OF INDUSTRIES AND COMMERCE
JALANDHAR, PUNJAB
PPPrrreeepppaaarrreeeddd BBByyy
GRASS ROOTS RESEARCH & CREATION INDIA (P) LTD. (An ISO 9001:2008 Certified Co.: Accredited by QCI / NABET: Approved by MoEF, GoI)
F-374-375, Sector-63, Noida, U.P.
Ph.: 0120- 4044630, Telefax: 0120- 2406519 Email: [email protected], [email protected]
Website: http://www.grc-india.com
GRC INDIA TRAINING & ANALYTICAL LABORATORY (Accredited by NABL & Recognized by MoEF, GoI)
A unit of GRC India
![Page 2: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/2.jpg)
INDEX
Serial No. CONTENTS Page No.
INTRODUCTION
1.0 PURPOSE OF THE REPORT 2/I
1.1 IDENTIFICATION OF PROJECT PROPONENT 2/I
1.2 BRIEF DESCRIPTION OF PROJECT 2/I
1.3 REGULATORY COMPLIANCES & APPLICABLE
LAWS/REGULATIONS
3/I
1.4 SCOPE OF THE STUDY 4/I
PROJECT DESCRIPTION
2.0 GENERAL 2/II
2.1 TYPE OF PROJECT 2/II
2.2 NEED FOR THE PROJECT 2/II
2.3 LOCATION DETAILS 2/II
2.4 LEASE HOLD AREA 3/II
2.5 GEOLOGY 4/II
2.6 RESERVES 4/II
2.7 MINING 5/II
2.8 GENERAL FEATURES 7/II
DESCRIPTION OF ENVIRONMENT
3.0 INTRODUCTION 2/III
3.1 LAND ENVIRONMENT 2/III
3.2 AIR ENVIRONMENT 3/III
3.3 WATER ENVIRONMENT 7/III
3.3 (a) GROUND WATER 8/III
3.3 (b) SURFACE WATER 13/III
3.4 SOIL ENVIRONMENT 17/III
3.5 NOISE ENVIRONMENT 19/III
3.6 TRAFFIC STUDY 20/III
3.7 BIOLOGICAL ENVIRONMENT 20/III
3.7(a) BIOLOGICAL ENVIRONMENT : FLORA 22/III
3.7(b) BIOLOGICAL ENVIRONMENT : FAUNA 23/III
ANTICIPATED ENVIRONMENTAL IMPACT AND MITIGATION MEASURES
4.0 GENERAL 2/IV
4.1 LAND ENVIRONMENT 2/IV
![Page 3: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/3.jpg)
4.2 WATER ENVIRONMENT 7/IV
4.3 AIR ENVIRONMENT 8/IV
4.4 NOISE ENVIRONMENT 11/IV
4.5 BIOLOGICAL ENVIRONMENT 12/IV
4.6 TRAFFIC ANALYSIS 16/IV
4.7 STATUATORY REQUIREMENTS 17/IV
4.8 MATRIX OF EIA 18/IV
ANALYSIS OF ALTERNATIVES (TECHNOLOGY & SITE)
5.0 GENERAL 2/V
ADDITIONAL STUDIES
6.0 PUBLIC CONSULTATION 2/VI
6.1 HAZARD IDENTIFICATION AND RISK ASSESSMENT METHOLODOGY
4/VI
6.2 POTENTIAL HAZARD & ‘ALARP’ CONDITION
9/VI
6.3 RISK PRIORITISATION BASED ON HAZARDS 9/VI
6.4 ADDITIONAL MITIGATION MAJORS TO BRING HAZARDS UNDER “ALARP” ZONE
12/VI
6.5 NATURAL RESOURCE CONSERVATION 13/VI
6.6 SOCIAL IMPACT ASSESMENT, REHABILITATION & RESETTLEMENT (R&R) ACTION PLAN
14/VI
6.7 SUGGESTIONS 27/VI
6.8 CONCLUSIONS 28/VI PROJECT BENEFITS
7.0 GENERAL 2/VII
7.1 BENEFIT OF MINING 2/VII
7.2 EMPLOYMENT 2/VII
7.3 IMPROVEMENTS IN PHYSICAL AND SOCIAL
INFRASTRUCTURE 2/VII
7.4 HEALTH 3/VII
ENVIRONMENTAL MANAGEMENT PLAN 8.0 INTRODUCTION 2/VIII
8.1 ENVIRONMENTAL MANAGEMENT PLAN (BIOLOGICAL
ENVIRONMENT) 2/VIII
8.2 ENVIRONMENTAL MANAGEMENT PLAN IMPLEMENTATION 3/VIII
8.3 PROPOSED SET UP 4/VIII
![Page 4: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/4.jpg)
8.4 BUDGET ALLOCATION FOR EMP IMPLEMENTATION 4/VIII
8.5 MONITORING SCHEDULE AND PARAMETERS 5/VIII
8.6 DIVISION OF RESPOSIBILITY OF VARIOUS ACTIVITIES FOR
A SAND MINE PROJECT 6/VIII
EXECUTIVE SUMMARY
9 SUMMARY 1/IX-12/IX
DISCLOSURE OF CONSULTANTS ENGAGED
10 DISCLOSURE OF CONSULTANTS ENGAGED 1/X-5/X
![Page 5: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/5.jpg)
LIST OF TABLES
Table No. TITLE OF TABLE Page No.
3.1 Land Use cover of the project study area 2/lll
3.2 Methods adopted for PM2.5, PM10, SO2 and NOX (as NO2) 4/lll
3.2 (i) Ambient air quality monitoring stations 6/III
3.2 (ii) Ambient Air Quality Status 7/III
3.2 (iii) Silica Contents in dust of air samples collected 8/III
3.3 (i) Ground water sampling locations 8/III
3.3 (ii) Physico-chemical properties of ground water 9/III-11/III
3.3 (iii) Surface water sampling locations 13/III
3.3 (iv) Physico-chemical properties of surface water 14/III-16/III
3.4 (i) Description of soil sampling locations 17/III
3.4 (ii) Physico-chemical properties of soil 18/III
3.5 (i) Noise quality monitoring stations 19/III
3.5 (ii) Noise level status 19/III
3.6 (i) Flora of the core zone 13/III
3.6 (ii) Fauna of the buffer zone 24/III
3.6(iii) Fauna of the core zone 26/III
3.6(iv) Fauna in buffer zone
4.1 Sand Budget Calculation and replenishment capacity of
river 4/IV
4.2 Noise Impact 11/IV
4.3 Anticipated impact and mitigation measures for biological
environment: 12/IV
4.4 (i) Existing Traffic Scenario & LOS 16/IV
4.4 (ii) Modified Traffic Scenario & LOS 17/IV
4.5(i) Qualitative Matrix 18/IV
4.5(ii) Quantitative Matrix 19/IV
5.1 Monitoring Schedule and Parameters 4/VI
6.1 Broad Land use pattern in Study Area 18/VI
6.2 Type and number of Educational Institutions located in the
study area 21/VI
6.3 Availability of Health Facilities in the study area and average
number people served 22/VI
![Page 6: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/6.jpg)
6.4 Availability of drinking water facilities in the Study area 23/VI
6.5 Weekly Household Consumption Cereal and Non-cereal
items 25/VI
8.1 Cost of EMP 5/VIII
9.1 Baseline Environmental Status 3/X
9.2 Anticipated impact and mitigation measures for biological environment
5/IX
9.3 Cost of EMP 11/IX
9.4 Monitoring Schedule and Parameters 12/IX
![Page 7: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/7.jpg)
LIST OF FIGURES
Fig. No. TITLE OF FIGURE Page No.
2.1 Mining Process 6/II
3.1 Windrose diagram 3/III
3.2 Ambient air quality monitoring near village Raipur Araian 5/III
3.3 Ground Water Sampling near village Raipur Araian 12/III
3.4 Surface Water Sampling in the Study Area 13/III
3.5 Soil sampling near Project Site 19/III
3.6 Trees grown along the river bank 21/III
3.7 Scattered annual grasses near the mine area 21/III
4.1 Graph showing Concentration of Fugitive dust vs Distance 10/IV
5.1 Organisation for implementation of control measures 3/V
6.1 Socio Economic survey of study area 17/VI
6.2 Broad Land Use pattern in study area 18/VI
6.3 Sources of drinking water in villages in study area 23/VI
![Page 8: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/8.jpg)
LIST OF ANNEXURES
S. No. TITLE OF ANNEXURE
I Surface Plan/ Khasra Nos
II Ambient Air Quality data
III Public Hearing Proceedings
IV Approved Mine Plan
V Data on Population, Literacy rate, Main & Marginal Workers
in respect of identified villages/towns in the Study Area
VI NOC of water from Gram Panchayat
![Page 9: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/9.jpg)
![Page 10: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/10.jpg)
![Page 11: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/11.jpg)
![Page 12: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/12.jpg)
![Page 13: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/13.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - I: Introduction
Page 1/I
SECTION-I
INTRODUCTION
INDEX
S. No. CONTENTS Page No.
1.0 PURPOSE OF THE REPORT 2/I
1.1 IDENTIFICATION OF PROJECT PROPONENT 2/I
1.2 BRIEF DESCRIPTION OF PROJECT 2/I
1.3 REGULATORY COMPLIANCES & APPLICABLE
LAWS/REGULATIONS 3/I
1.4 SCOPE OF THE STUDY 4/I
![Page 14: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/14.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - I: Introduction
Page 2/I
1.0 PURPOSE OF THE REPORT
Environmental Impact Assessment (EIA) is a decision making tool, which guides the
Authorities in arriving at an appropriate conclusions for the proposed projects to retain them,
if environmentally sound and reject, if found having deleterious effect. EIA identifies the
extent of the environmental, social and economic impacts of a project prior to decision-
making. EIA systematically examines both beneficial and adverse impacts of the proposed
project over and above the prevailing conditions and ensure that these combined impacts
are taken into account during the project designing.
A Environmental Impact Assessment report was prepared to comply with the Terms of
Reference (TOR) received under EIA notification of the MoEF dated 14-9-2006, as amended
on 1st Dec 2009 & 4th April 2011 and also the EIA Guidance Manual for Mining of Minerals
(Feb, 2010) of MoEF, Govt. of India, for seeking environmental clearance for mining of sand
in the applied mining lease area measuring 17.98 hectares falling under category “B” near
Village: Raipur Araian, Taluka: Phillor, District: Jalandhar, Punjab. This final EIA report has
incorporated the points raised in the public hearing held on 6th Aug, 2014 along with
compliance of the project proponent by amending the draft EIA report.
1.1 IDENTIFICATION OF PROJECT PROPONENT
The project is being proposed by the Department of Industries and Commerce (DIC). GM-
cum-Mining Officer, District Industries Centre, Jalandhar, is incharge of mining of minor
minerals on behalf of the Govt. of Punjab. The EIA-EMP report was prepared as per the
TOR granted under the EIA Notification. In order to assess the impact on environment due
to proposed mine, it is necessary to ascertain present status of environment prevailing at
the project site and identification and assessment of impacts on the environment of the
proposed operations.
1.2 BRIEF DESCRIPTION OF PROJECT
As per the approved mine plan, it is a proposed project to mine sand and the estimated
project cost is Rs. 1.5 lacs. GM-cum-Mining Officer, Jalandhar, Punjab has identified the
mining lease in the name of Raipur Araian Sand Mine.
The mining plan of sand Mine is approved by State Geologist, Punjab.
The proposed mine site on Satluj River bed with approx. 4,85,460 tonnes of sand deposit in
it, which is replenishable due to sediment inflow.
![Page 15: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/15.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - I: Introduction
Page 3/I
Project Nature, Size & Location
Nature
The proposed project is river bed sand mining project.
Size
It has been proposed to collect approximately 1, 61,800 tonnes of river bed material
annually over an area of 17.98 Hectare.
Location
The mining area is located in Village: Raipur Araian, Taluka: Phillor, District: Jalandhar
Punjab. The mining lease / proposed project area falls in Survey of India Toposheet No.
44M/16. The mine lease area is located between:
Latitude 31° 0'56.09"N to 31° 1'7.46"N
Longitude 75°53'38.43"E to 75°54'8.92"E
Nearest Railway Station Phillor R.S (about 11 km in North-West direction)
Nearest Airport Ludhiana Airport (about 19 km in SSE direction)
Nearest Highway NH-1 (about 11 km in West direction)
Project’s importance to the country and the region
The project involves collection of river bed material. This is very essential to prevent
widening of the riverbed due to the deposition of sediments which if not mined out will
cause flooding and damage to the adjoining areas. This can only be prevented by
maintaining the existing width and course of the river. If riverbed sand is not mined, the
widening of river banks will result in excessive erosion; causing further damage to flora,
agricultural land and settlements situated in close proximity.
This project operation will generate employment to the people residing in vicinity for about
250 days annually and approximately 100 people will be benefited directly and indirectly by
the project.
1.3 REGULATORY COMPLIANCES & APPLICABLE LAWS/REGULATIONS
a) There is no legal case against the project and project proponent.
b) There is no national park / Sanctuary notified under the Wildlife Protection Act in the study
area.
![Page 16: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/16.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - I: Introduction
Page 4/I
1.4 SCOPE OF THE STUDY
The Expert Appraisal Committee (EAC) for mining projects considered the project during its
meeting. Based on the information contained in the documents submitted and the
presentation made, the EAC-MoEF prescribed the Terms of Reference (TOR). The points
raised by the MoEF in the TOR and its compliance are as under:-
Point Wise Compliance of TOR
S. No. TOR Compliance
1 All documents including approved
mine plan (Eco friendly Mine Plan),
EIA report and public hearing should
be compatible with one another in
terms of the mine lease area,
production levels, waste generation
& its management and mining
technology and should be in the
name of the lessee.
EIA report includes all the documents
compatible with approved mine plan. Public
hearing has been conducted for the same
mining lease area, production levels, waste
generation and its management and mining
technology which have been detailed in the
EIA report and the approved mine plan.
2 A copy of the document in the
support of the fact that the
proponent is the rightful lessee of
the mine should be given.
Presently GM-cum-Mining Officer, DIC is
the rightful owner of the minor minerals.
3 The terms and conditions imposed,
if any, by the Competent Authority in
the State Government while
granting mining lease/ permit/
contract should be built into the
mine plan (Eco friendly Mine Plan)
as well as the EIA report. It may
inter-alia include; area of working
(length and breadth of the river
stretch), mode of working, working
shift, transportation of mineral,
restriction, if any imposed for
working etc.
All the terms and conditions imposed by the
authorities have been incorporated into the
approved mine plan and the final EIA report
has been prepared with complying with
those terms. All other relevant information
is given in Section -II.
![Page 17: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/17.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - I: Introduction
Page 5/I
4 Involvement of the forest land, if
any, in the project and status of
forestry clearance should be given.
There is no forest land involved; hence no
forest clearance will be required.
The entire lease hold area of 17.98 ha, lies
in Satluj River bed. The present breakup of
the land use for ancillary feature around the
mining area is given below and Surface
Plan along with Khasra nos is attached as
Annexure I :
S. No. Land type Area (in ha)
1. Govt. waste land -
2. Agriculture land -
3. Grazing land -
4. Forest land -
5. Others (River
Bed)
17.98
Total 17.98
5 The study area will comprise of 10
km zone around the mine lease
from lease periphery and the data
contained in the EIA such as waste
generation etc should be for the life
of the mine/ lease period.
The EIA study has been carried out for 10
km radius zone from the periphery of ML
area. All the data e.g. production are
incorporated in EIA/EMP reports in Section
-II. The topographical map showing the 10
km study area is attached at the end of
section-II.
It is a river bed sand mining project and no
waste will be generated.
6 Land use of the study area
delineating forest area, agricultural
land, grazing land, wildlife sanctuary
and national park, migratory routes
of fauna, water bodies, human
settlements and other ecological
features.
The landuse details are discussed in
Section III, para 3.1 and the landuse map is
attached at the end of chapter.
7 Land use plan of the mine lease
area should be prepared to
encompass preoperational,
operational and post operational
phases.
Total lease area is 17.98 ha and through
pre-operational, operational and post
operational stages it remains a floodplain.
![Page 18: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/18.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - I: Introduction
Page 6/I
8 Impact of the project on the wildlife
in the surrounding and any other
protected area and accordingly
detailed mitigation measures
required should be worked out with
cost implications.
Details regarding wildlife & protected areas
and mitigative measures are mentioned in
para 3 of Section III and in Section IV.
9 The vegetation in the RF/PF in the
study area, if any.
A detailed study is given in Section-III.
10 A study shall be got done to
ascertain the impact of the mining
project on wildlife of the area
including on the elephant
population.
Details regarding wildlife & protected areas
and mitigative measures are mentioned in
Section III and Section IV.
11 Location of National Parks,
Sanctuaries, Biosphere Reserves,
Wildlife Corridors, Tiger/Elephant
Reserves (existing as well as
proposed) within 10 KM of the mine
lease should be clearly indicated. A
location map duly authenticated by
Chief Wildlife Warden should be
provided in this regard. Necessary
clearance from the Chief Wildlife
Warden for operating the mine
within 10 KM of the National
Park/Sanctuary, if any, should also
be obtained and furnished.
There is no National Park, Sanctuary,
Biosphere Reserve, Wildlife Corridor,
Tiger/Elephant Reserve (existing as well as
proposed) within 10 km radius of the mine
lease.
12 A detailed biological study for the
study area [core zone and buffer
zone (10 KM radius of the periphery
of the mine lease)] including the
aquatic fauna in the riverine system
shall be carried out. Details of flora
and fauna, duly authenticated,
separately for core and buffer zone
should be furnished based on field
A detailed biological study is given in
Section-III.
![Page 19: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/19.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - I: Introduction
Page 7/I
survey clearly indicating the
Schedule of the fauna present. In
case of any scheduled-I fauna found
in the study area, the necessary
plan for their conservation should be
prepared in consultation with State
Forest and Wildlife Department and
details furnished. Necessary
allocation of funds for implementing
the same should be made as part of
the project cost.
13 Impact of the project on land use
including change of river course, if
any should be given.
No changes are anticipated in river course.
The flow of the river depends on the
dynamics of various parameters involved.
Sediment deposition is also one of the
parameter. These sediments are deposited
in the main stream channel bed and along
the banks. Extraction of deposited sediment
will help in maintaining the course of the
river. The details are covered in Section IV.
14 Impact on topography, drainage,
agricultural fields, wildlife, water
logging leading to water borne
diseases, if any. It may also be
shown whether it will lead to change
of water course of the river.
Modeling exercise should also be
carried out through an expert
agency to show the change in river
flow dynamics, if any.
The impacts have been described in
Section-IV.
15 Collection of one season (non-
monsoon) primary baseline data on
ambient air quality (PM10, SO2, and
NOx), water quality, noise level, soil
and flora and fauna. Site-specific
meteorological data should also be
Baseline data on ambient air quality, water
quality, noise level, soil and flora and fauna
have been collected. Site-specific
meteorological data have been collected for
non monsoon season from March, 2011 to
May, 2011. (Section-III of EIA report)
![Page 20: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/20.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - I: Introduction
Page 8/I
collected. The location of the
monitoring stations should be
justified. Date wise collected
baseline AAQ data should form part
of EIA and EMP report. The
mineralogical composition of PM10
particularly for free silica should be
given. There should be at least one
AAQ monitoring station within 500 m
of the mine lease in the pre-
dominant downwind direction.
Date wise baseline data collected is given
in Annexure-II.
The composition of free silica in PM10 is
shown in Section III
Source: GRC India Training & Analytical
Laboratory.
16 Air quality modeling should be
carried out for prediction of impact
of the project on the air quality of the
area. It should also take into
account the impact of movement of
vehicles for transportation of
mineral. The details of the model
used and input parameters used for
modeling should be provided. The
air quality contours may be shown
on a location map clearly indicating
the location of the site, location of
sensitive receptors, if any and the
habitation. The wind roses showing
pre-dominant wind direction may
also be indicated on the map.
Air quality modeling has been carried out
for prediction of impact due to proposed
project activities on the present air quality
of the area as shown in Section IV.
The windrose diagram indicating
predominant wind direction is shown in
Figure 3.1 of EIA report. The required
details are given in Section-III.
17 The water requirement for the
project, its availability and source to
be furnished. A detailed water
balance should also be provided.
Fresh water requirement for the
project should also be indicated.
The water requirement for the project is 1.7
KLD which includes both for dust
suppression and for drinking purpose.
18 Necessary clearance from the
Competent Authority for drawl of
requisite quantity of water for the
NOC for drawl of water from the Gram
Panchayat has been obtained.
![Page 21: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/21.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - I: Introduction
Page 9/I
project should be provided.
19 Impact of the project on the water
quality should be assessed and
necessary safeguard measures, if
any required should be provided.
The proposed mining will not intercept the
ground water table. No foreign materials
would be added to surface water due to
mining and hence no water pollution is
predicted.
The detailed impact and control measure
w.r.t. the quality of water in the surrounding
area is discussed under Section-IV,
20 Information on site elevation,
working depth, groundwater table
should be provided both in AMSL
and bgl. A schematic diagram may
also be provided for the same.
site elevation Highest-240m AMSL
Lowest- 238m AMSL
working depth 3 m bgl
groundwater table
pre-monsoon
8-15 m bgl
groundwater table
post monsoon
5-10 m bgl
21 Quantity of solid waste generation, if
any, to be estimated and details for
its disposal and management be
provided.
No solid waste will be generated.
22 Impact on local transport
infrastructure due to the project,
Projected increase in truck traffic as
a result of the project in the present
road network (including those
outside the project area) and
whether it is capable of handling the
increased load. Arrangement for
improving the infrastructure, if
contemplated including action to be
taken by other agencies such as
State Government, if any, should be
covered.
Vehicular Traffic Density
The connecting road from the mine to
National Highway 1. This will be reinforced
to facilitate easy and smooth movement of
heavy duty trucks.
On this Highway 18 trucks/trolleys ply
regularly and this can easily accommodate
additional 4 trucks per hour as anticipated
for the project.
23 Details of the infrastructure facilities
to be provided for the mine workers.
The site services like rest shelter, first aid
box, drinking water facilities will be provided
to workers at the mine site.
![Page 22: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/22.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - I: Introduction
Page 10/I
24 Phase-wise plan of greenbelt
development, plantation and
compensatory afforestation clearly
indicating the area to be covered
under plantation and the species to
be planted.
Plantation will be done along the road sides
and near civic amenities, which will be
allotted by Government bodies as it is not
feasible to plant trees near the mine lease
area.
25 Occupational health impact of
project should be anticipated and
prevention measures initiated.
Details in this regard should be
provided.
The details of Occupational health impact
are given in Section VI.
All safety measures prescribed under
mining laws will be followed. All workers will
be medically examined in pre-placement
phase and also periodically, as per Rule 29
(A) and (B) of Mines Rule 1955 Medical
Examination of Persons Employed or to be
employed.
26 Occupational health impact of
project. Details of pre-placement
medical examination and periodical
medical examination schedules and
medical facilities proposed to be
provided should be incorporated in
the EMP.
All safety measures prescribed under
mining laws as applicable for the project will
be followed. All workers will be medically
examined initially and also periodically as
per Rule 29 (A) and (B) of Mines Rule
1955- Medical Examination of Persons
Employed or to be employed.
27 Measures of socio economic
influence to the local community
proposed to be provided by project
proponent. As far as possible,
quantitative dimension to be given.
Measures of socio-economic influence to
the local community have been furnished
and described under Section-VI
• The activity creates employment for
local persons directly and indirectly
depending upon their skill.
• Development activities will be taken up
in consultation with local bodies.
• Education, safety and health
campaigns will be carried out in nearby
villages. Initial and Periodical medical
examination / checking of workers will be
carried out as per requirement under Mines
Rules, 1955.
![Page 23: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/23.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - I: Introduction
Page 11/I
28 Detailed environmental
management plan to mitigate the
environmental impacts. Specific
safeguard measures to control
PM10 as well as pollution due to
transportation should be given.
Detailed Environmental Management Plan
is discussed under Section-VIII. The
proposed project provides for measures to
control PM10 during transportation; like
covering the vehicles with tarpaulin, wetting
of sand if need be, regular water spray on
road, occasional scraping of the road to
keep it levelled to prevent spillage of sand
from moving vehicles and ward off any
stagnating dust on road to the sides.
29 Public hearing points raised and
commitment of the project
proponent on the same along with
time bound action plan to implement
the same should be provided.
Issues raised in the Public Hearing and
their compliance is attached as Annexure-
III .The extract of salient features of the PH
are detailed in Section VI.
30 Details of litigation pending against
the project, if any, with direction/
order passed by any Court of Law
against the project should be given.
There is no litigation with this project.
31 The cost of the project (capital cost
and recurring cost) as well as the
cost towards implementation of
EMP should clearly be spelt out.
Detailed Environmental Management Plan
cost is discussed under Section-VIII.
II. Besides the above, the below mentioned general points will also to be followed:-
a All documents to be properly referenced with
index, page numbers and continuous page
numbering.
Complied.
b Where data are presented in the report especially
in tables, the period in which the data were
collected and the sources should be indicated.
Complied whenever
applicable.
c Where the documents provided in a language
other than English, an English translation should
be provided.
Complied.
d The questionnaire for environmental appraisal of
mining projects as devised earlier by the ministry
shall also be filled and submitted.
The completed questionnaire
is attached as Appendix.
![Page 24: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/24.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - I: Introduction
Page 12/I
e Approved mine plan along with copy of the
approval letter for the proposed capacity should
also be submitted.
The approved Mine Plan has
been already submitted in
MoEF. Receiving of the same
is attached as Annexure V.
f While preparing the EIA report, the instructions
for the proponents and instructions for the
consultants issued by MoEF vide O.M. No. J-
11013/41/2006-IA.II(I) dated 4th August , 2009,
which are available on the website of this ministry
should also be followed.
The EIA report has been
prepared complying with the
circulars issued by MoEF vide
O.M. No. J-11013/41/2006-
IA.II (I) dated 4th August,
2009.
III. The EIA report should also include surface plan of
the area indication contours of main topographic features,
drainage and mining area.
Complied.
(The surface plan is attached
as Annexure I)
*********
![Page 25: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/25.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section -II: Project Description
Page 1/II
SECTION-II
PROJECT DESCRIPTION
INDEX
S. No. CONTENTS Page No.
2.0 GENERAL 2/II
2.1 DESCRIPTION OF THE PROJECT 2/II
2.2 NEED FOR THE PROJECT 2/II
2.3 LOCATION DETAILS 2/II
2.4 LEASE HOLD AREA 3/II
2.5 GEOLOGY 3/II
2.6 RESERVES 3/II
2.7 MINING 4/II
2.8 GENERAL FEATURES 6/II
![Page 26: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/26.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section -II: Project Description
Page 2/II
2.0 GENERAL
The Environmental Impact Assessment report has been prepared in terms of EIA notification
of the MoEF dated 14-9-2006, as amended on 1st Dec 2009 & 4th April 2011 and the EIA
Guideline Manual for Mining of Minerals (Feb, 2010) of MoEF, Govt. of India, for seeking
environmental clearance for mining in the existing area of sand mining lease measuring
17.98 hectares falling under category “B”.
2.1 DESCRIPTION OF THE PROJECT
The mine plan is approved by the State Geologist, Punjab. As per the mine plan, it is a
proposed project to mine sand. The estimated project cost is Rs 1.5 lacs. GM-cum-Mining
Officer, Jalandhar, Punjab has applied for mining lease in the name of Raipur Araian Sand
mine over an area of 17.98 ha at Village: Raipur Araian, Taluka: Phillor, District: Jalandhar,
Punjab.
The mine plan of sand mine is approved by the competent authority. The proposed
production of the mine is 1,61,800 Tonnes per year.
2.2 NEED FOR THE PROJECT
The river carries with it huge quantity of sediment consisting of stones and sand during every
monsoon. The sediment in the form of river bed material (RBM) deposited from the time
immemorial had changed the shape of the river bed from a mere valley to a raised land.
Because of this, every year during the monsoon, heavy and devastating floods damage
large tracts of land lying on both the banks of the river. Hence, it is necessary to remove the
materials so that the river gets channelized.
2.3 LOCATION DETAILS
The mining area is located in Village: Raipur Araian, District: Jalandhar, Punjab.. The mine
lease area is located between:
Latitude 31° 0'56.09"N to 31° 1'7.46"N
Longitude 75°53'38.43"E to 75°54'8.92"E
Nearest Railway Station Phillour R.S (about 11 km in North-West direction)
Nearest Airport Ludhiana Airport (about 19 km in SSE direction)
Nearest Highway NH-1 (about 11 km in West direction)
A 10 km radius buffer map is attached in the end of this section.
![Page 27: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/27.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section -II: Project Description
Page 3/II
2.4 LEASE HOLD AREA
The entire lease hold area of 17.98 ha lies in the river bed of Satluj. The breakup of the land
use for ancillary feature around the mining area is given below: -
S. No. Land type Area in ha
1. Govt. waste land -
2. Agriculture land -
3. Grazing land -
4. Forest land -
5. Others (river bed of Satluj) 17.98
Total 17.98
2.5 GEOLOGY
Geomorphology and soils
The district forms a part of Beas sub basin of Indus basin. The district is part of the bits doab
tract, which is interring alluvial plain between Beas and Satluj River. Physiographical the district
is characterized by two distinct features i.e vast upland plain and Satluj floodplain. The width of
the floodplain varies according to the amount of shift experienced by the river. It is widest in the
Phillor Tehsil. The district is mainly drained by the river Satluj and its tributaries east (white) and
west (black).
Jalandhar district has two types of soils tropical arid brown and arid brown soils. Tropical brown
soils are found on the major part of the district whereas arid brown soils are found in the
southwestern part of the district especially in Lohian and part of Shahtok block. Along the river
Satluj fluent type of soil is found.
2.6 RESERVES
As much of the lease area is covered with water catchment area, only the middle area is considered
for reserve estimation. The sand which is exposed in all the three dimensions (3.0m on an average)
is considered as proved. From the field trials conducted in the sector and information gathered from
the applicant, the bulk density is found to be 1.8 t/cum.
Category wise updated reserves with grade are as follows:
Category Total (in Tonnes) UNFC Code
Proved 4,85,460 Tonnes 111
![Page 28: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/28.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section -II: Project Description
Page 4/II
Annual sediment deposition at the place of mining:
This is accomplished by taking the converted dimensionless ratio flow-duration curve and
multiplying increments/duration of time in days by the sediment yield associated with that flow. The
computations for total annual suspended and bed load sediment yield are given below:
Sediment yield:
Formula
For Q < 2 in:
S = 1280 Q 0.46 [1.43-0.26 log (A)]
For Q > 2 in:
S = 1965 e -0.055Q [1.43-0.26 log (A)]
Here:
Q (in) = Mean Annual run off =156.63 mm
= 6.17 in
A (mi2) = Catchment area= 23,815.09 km2
= 9195.06 mi2
Sediment yield S= (tons/yr)
S= 1965 e-0.055x6.17[1.43 - 0.26 log (9195.06)] S = 11,07,812.51 tons/year
Thus, 11,07,812.51 tons/year sediment will be regenerated every year in the catchment
area increasing the mineable reserves.
*source: - Calculation of sediment yield by the Dendy-Bolton formula
2.7 MINING
Sand Mining
The salient features of sand mining method are:
Mining of sand is proposed to be carried out by the excavators. The mining involve following
steps-
I. River Bed Mining activities do not involve top soil.
II. Excavation of sand is done by excavators.
III. Drilling and blasting is not required.
Working Depth (below ground level)
The deposits occur in the middle/bottom of the river. During the entire lease period, the
deposit will be worked from the top surface to 3 m bgl. The ultimate depth of the open cast
pits will be 3 m below ground level.
![Page 29: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/29.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section -II: Project Description
Page 5/II
Process:
Refer to Figure 2.1; mining will be started at the centre of cross section of the river bed from
the farthest downstream end, moving upstream and to the sides alternating in 3 steps of 1 m
depth each.
Fig. 2.1 Mining Process
![Page 30: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/30.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section -II: Project Description
Page 6/II
Restriction of mining:
• The mining should be prohibited to distance of 500 m on upstream and downstream from the
high level bridge and 250 m form the other bridges on upstream and down stream
• If width of the river is less than 120 m the mining will be restricted within the bed of river. If
higher than 120 m the mining will be restricted after leaving the area of 30 m from the edge of
embankment on either side of the river bed.
• The mining will not be allowed below the water table.
• No mining operation will be allowed in forest area.
• Unless benches are formed in accordance with regulation 106 of Metalliferrous Mine
Regulations, 1961, the max. permissible depth of the quarry pit will be 3 m.
• The contractors will abide by various provisions laid down under Mines Act, 1952, Mines &
Minerals (Regulation and Development) Act, 1957, Forest (Conservation) Act, 1980, MMR,
1961.
• The contractor will abide by the provisions of Mines Act, 1952, Interstate Migrant Workman
Act. The contractor with the satisfaction of competent authority will provide drinking water, rest
shelter, first aid box, welfare facilities as per Central and State Govt. labor laws
• The contractor will not do any quarry operations within the distance of 75m from railway line,
60m from national highway and 50m from reservoir tank, canal roads, public works or
buildings and in-habitat sites etc.
• The river bed areas dug during one season i.e. other than rainy season will get refilled Sand
deposit in rainy season in which the material so deposited will be available for fresh quarrying.
• The contractors will abide by the State Minor Mineral Concession Rules, Punjab,1964.
Details of Machinery (per day)
1 Dumper/truck 4
2 Excavator On hire basis
2.8 GENERAL FEATURES
Topography:
The proposed area is a river bed which is flat except the banks. The Land profile adjoining the river
bank is also flat.. The difference of the highest & the lowest elevation of the area is about 2 to 3
meter. The surrounding area is devoid of any thick vegetation except for patched agricultural lands.
Surface Drainage Pattern
It is a river bed mining project. The total lease area is located in the Satluj river catchment/water
shed area.
![Page 31: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/31.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section -II: Project Description
Page 7/II
Vehicular Traffic Density
The connecting road from the mine to National Highway No.1 is 12 m wide. These may be
reinforced to facilitate easy and smooth movement of heavy duty trucks.
The National Highway has traffic density of 18 trucks per hour ply regularly and these will easily
accommodate addition 4 trucks/trolleys per hour.
Township
Since this mining is intermittent and labour employed would be mostly from adjoining areas, no
colony is proposed.
Power, Water Supply and other Infrastructure requirement
Power
All the activities will be carried out by semi-mechanized method i.e. loading the
trucks/trolley/carrying vehicles manually by the working people, excavators will be used for
excavation. There is no power requirement for the project because excavators will run on diesel.
Water Supply
In the river bed mining projects there is as such no need of water to carry out operations, except for
dust suppression. The number of working people is 12 so the water requirement for workers will be
around 1 KLD for drinking purpose & 0.7 KLD for the dust suppression, the total water requirement
will be around 1.7 KLD. This water will be supplied from the nearby area.
Infrastructure:
The site services like rest room shelter, first aid box, drinking water & facilities will be provided to
workers at the mine site.
Manpower Requirement:
The manpower requirement for the proposed project will be around 12. This does not include
manpower required for transportation and unloading of Sand in dumpers/trucks/trolleys but includes
the manpower required for loading the vehicles through excavators. It also does not include the
unskilled manpower in case the entire loading of vehicles is resorted through manual labour.
Daily Water Demand 1.7 KLD
Drinking use 1 KLD
Dust suppression 0.7 KLD
![Page 32: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/32.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section -II: Project Description
Page 8/II
Manpower requirement
********
S. No. Category Numbers
1. Administrative 1
2. Supervisory 2
3. Skilled 3
4 Semi skilled 3
5 Unskilled 3
TOTAL 12
![Page 33: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/33.jpg)
![Page 34: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/34.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP-Section - III Description of Environment
Page 1/III
SECTION-III
DESCRIPTION OF ENVIRONMENT
INDEX
S. No. CONTENTS Page No.
3.0 INTRODUCTION 2/III
3.1 LAND ENVIRONMENT 2/III
3.2 AIR ENVIRONMENT 3/III
3.3 WATER ENVIRONMENT 7/III
3.3 (a) GROUND WATER 8/III
3.3 (b) SURFACE WATER 13/III
3.4 SOIL ENVIRONMENT 17/III
3.5 NOISE ENVIRONMENT 19/III
3.6 TRAFFFIC STUDY 20/III
3.7 BIOLOGICAL ENVIRONMENT 20/III
3.7(a) BIOLOGICAL ENVIRONMENT : FLORA 22/III
3.7(b) BIOLOGICAL ENVIRONMENT : FAUNA 23/III
![Page 35: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/35.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP-Section - III Description of Environment
Page 2/III
3.0 INTRODUCTION
This section contains the description of baseline studies of the area within 10 Km radius
surrounding the Raipur Araian Sand Mine, Jalandhar, Punjab. The study was undertaken for
prevailing environment in respect of land, air, water (both ground and surface), soil, noise,
biological (both flora and fauna). The data collected has been used to understand the
existing environment scenario around the proposed mining project against which the
potential impacts of the proposed project can be assessed.
3.1 LAND ENVIRONMENT
This section includes the study of natural features like topography, climate etc. Land use/
Land cover map.
Topography
The proposed area is a river bed which is very flat except the banks. The Land profile
adjoining the river bank is also flat. The difference of the highest & the lowest elevation of
the area is about 2 to 3 meter. The surrounding area is devoid of any thick vegetation except
for patched agricultural lands.
Climate:
The climatic conditions are Semi-arid. The maximum and minimum temperature during the
year varies from 37 0C in summer to 7 0C in winter on the basis of past years observations.
The average rainfall in the area is 677 mm per year. Solar radiations are available for about
nine months per year. Average humidity is 40 %.
Land use / Land cover statistics of project study area
The land use of the study area is tabulated below:
Table 3.1: Land Use cover of the project study area
Serial
No.
Description Area in
Hectares
Percentage
share in
total area
1 Open/Wasteland 500.22 1.48
2 Agriculture 31756.29 94.22
3 River 311.53 0.92
4 Settlement 717.54 2.13
5 Vegetation 340.58 1.01
6 Water bodies 79.35 0.24
Total 33705.54 100
The 10 km radius land use map is attached in the end of the section.
![Page 36: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/36.jpg)
Ambient air quality monitoring stations were selected primarily on the basis of surface influence,
demographic influence and meteorological influence. From the meteorological data already
available at the near-most site the frequency and duration of wind is preliminary determined, from
which the likely wind rose diagram is first drawn. Three monitoring stations are selected in the
direction of the most predominant wind direction; one in the leeward (downwind) side , one closer to
the project site and one in the windward (upwind)side. Two more stations are selected across this
direction.
24 hourly monitoring was carried out for SO2, NO2, & PM10 twice a week at each station for a study
period of 3 months (March’11, April’11 and May’11).
a. Wind rose diagram
Figure 3.1 : Wind Rose Diagram
Observations:
The prominent seasonal wind direction is NW & W contributing more than / approximately 25 % of
the total.
Methods for monitoring
The Central Pollution Control Board (CPCB) has published comprehensive document on emission
testing regulations (“Emission Regulations Part-3, 1985”). Those procedures relevant to the
![Page 37: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/37.jpg)
Parameters Technique Technical
Protocol
Minimum
Detectable Limit
PM2.5 Gravimetric method US EPA Method 5 (µg/m3)
PM10 Gravimetric method IS 5182 (Part-
XXIII) 5 (µg/m3)
Sulphur Dioxide West and Gaeke IS-5182 (Part-II) 3 (µg/m3)
Nitrogen Oxide Jacob & Hochheiser IS-5182 (Part-VI) 7 (µg/m3)
i. Particulate Matter (PM):-
The CPCB method and IS 5182 (Part-XXIII) adopt a very similar approach to particulate sampling.
There are some differences in the expressions used, but they are generally of no practical
significance. It is recommended that CPCB method is adapted.
ii. Equipment calibration:
For accurate testing of emission sources, the components of the sampling train is calibrated by
outsource and supplier (Master Calibrator) standards and solutions are used, calibrated under
certified reference material.
The ambient air quality data were collected to find the existing emissions / conditions. The data is
given in Table No. 3.2 (i)
![Page 38: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/38.jpg)
Ambient air quality monitoring stations
S.No. Location Station name Distance and direction
from the lease area (km)
Zone (Core/
Buffer)
1. AQ1 Ashour W 3.30 Buffer zone
2. AQ2 Raur E 6.00 Buffer zone
3. AQ3 Near Site E 0.50 Core zone
4. AQ4 Raipur N 2.60 Buffer zone
5. AQ5 Chuharwala S 1.80 Buffer zone
![Page 39: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/39.jpg)
me: Raipur Araian Sand Mine, Punjab. Final EIA/EMP-Section – III Description of Environment
Table 3.2(ii)
Ambient Air Quality Status
S.
No. Pollutant Locations
No. of
observa
tion
Minimum Maximum Average 98th
Percentile
CPCB
Standards
1. SO2
(µg/m3)
AQ1
24
6.9 13.4 9.5 12.6
80.0
AQ2 8.8 15.2 10.9 14.8
AQ3 6.9 14.8 9.3 13.9
AQ4 8.4 14.2 10.3 13.5
AQ5 9.2 15.0 11.1 14.3
2. NO2
(µg/m3)
AQ1
24
14.0 25.4 20.3 24.8
80.0
AQ2 14.6 29.4 22.6 28.5
AQ3 13.7 24.7 18.0 23.9
AQ4 15.2 28.5 21.6 27.6
AQ5 15.0 30.2 23.3 29.5
3. PM10
(µg/m3)
AQ1
24
75.5 94.6 83.2 93.7
100.0
AQ2 77.5 99.4 86.0 98.6
AQ3 73.7 89.3 80.2 88.0
AQ4 76.8 94.0 84.2 93.7
AQ5 78.0 100.0 86.9 99.7
4. PM2.5
(µg/m3) AQ3 24 30.7 39.0 34.2 38.4 60.0
![Page 40: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/40.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP-Section – III Description of Environment
Page 7/III
Observations:
Ambient Air Quality Monitoring reveals that the minimum & maximum concentrations of PM10
for all the 5 AQ monitoring stations were found to be 73.7 µg/m3 at AQ3 and 100/m3 at AQ5,
respectively.
As far as the gaseous pollutants SO2 and NO2 are concerned, the prescribed CPCB limit of
80 µg/m3 for residential and rural areas has never surpassed at any station. The maximum &
minimum concentrations of SO2 were found to be 15.2 µg/m3 at AQ2 & 6.9 µg/m3 at AQ1
and AQ3, respectively. The maximum & minimum concentrations of NO2 were found to be
30.2 µg/m3 at AQ5 & 13.7 µg/m3 at AQ3, respectively.
Free SiO2:
Table 3.2 (iii)
SiO2 AQ1 AQ2 AQ3 AQ4 AQ5
Minimum 1.51 1.55 1.47 1.54 1.56
Maximum 1.89 1.99 1.79 1.88 2.0
The standard for Respirable dust is 3mg/m3 for 8 hour of working period where Free silica
content should not exceed 5% as prescribed by Directorate General of Mines Safety
Observations:
The minimum & maximum concentrations of SiO2 were found to be 1.47 µg/m3 at AQ3 & 2.0
µg/m3 at AQ5 respectively.
3.3 WATER ENVIRONMENT
3.3 (a) Ground Water
Three water samples were collected from the study area. The location of sampling points is
shown in Table 3.3 (i) and the physico-chemical analysis of the water samples is given in the
Table 3.3 (ii).
Table 3.3 (i)
Ground water sampling locations
Station
No. Location Direction
Distance
(km)
Project area/
study area
GW1 Ashour W 3.30 Buffer zone
GW2 Near Site E 0.50
Near Project
Site
GW3 Raur E 6.00 Buffer zone
![Page 41: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/41.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP-Section- III Description of Environment
Page 8/III
Table 3.3 (ii)
Physico-chemical properties of ground water Study Period – March 2011
S. No. Parameter Unit
Limit (as per IS:10500)
GW1 GW2 GW3
desirable permissible
1 Colour Hazen 5 25 <2 <2 <2
2 Odour - Un - Un Un Un
3 Taste - Agreeable - Agreeable Agreeable Agreeable
4 Turbidity NTU 5 10 <1 <1 <1
5 pH - 6.5-8.5 No
Relaxation 7.42 7.6 7.71
6 Total Hardness (as CaCO3)
mg/l 300 600 165 178 202
7 Iron (as Fe) mg/l 0.3 1 0.07 0.07 0.08
8 Chlorides (as Cl) mg/l 250 1000 25 31 29
9 Fluoride (as F ) mg/l 1 1.5 0.6 0.5 0.8
10 TDS mg/l 500 2000 304 339 357
11 Calcium(as Ca2+) mg/l 75 200 40 43 49
12 Magnesium (as Mg2+) mg/l 30 100 16 17 19
13 Copper (as Cu) mg/l 0.05 1.5 0.01 0.01 0.01
14 Manganese(as Mn) mg/l 0.1 0.3 <0.01 0.01 0.01
15 Sulphate (as SO4) mg/l 200 400 16 19 25
16 Nitrate(as NO3) mg/l 45 No
Relaxation 6 7 8
17 Phenolic Compounds (as C6H5OH)
mg/l 0.001 0.002 <0.001 <0.001 <0.001
18 Mercury (as Hg) mg/l 0.001 No
Relaxation <0.001 <0.001 <0.001
19 Cadmium (as Cd) mg/l 0.01 No
Relaxation <0.01 <0.01 <0.01
20 Selenium ( as Se ) mg/l 0.01 No
Relaxation <0.01 <0.01 <0.01
21 Arsenic (as As) mg/l 0.01 No
Relaxation <0.005 <0.005 <0.005
22 Cyanide (as CN ) mg/l 0.05 No
Relaxation <0.01 <0.01 <0.01
23 Lead (as Pb) mg/l 0.05 No
Relaxation <0.01 <0.01 <0.01
24 Zinc (as Zn) mg/l 5 15 0.04 0.03 0.04
25 Anionic Detergent (as MBAS)
mg/l 0.2 1 <0.01 <0.01 <0.01
26 Chromium (as Cr6+) mg/l 0.05 No
Relaxation <0.01 <0.01 <0.01
27 Mineral oil mg/l 0.01 0.03 <0.01 <0.01 <0.01
28 Alkalinity as CaCO3 mg/l 200 600 170 183 191
29 Aluminium (as Al) mg/l 0.03 0.2 <0.02 <0.02 <0.02
30 Boron (as B) mg/l 1 5 <0.1 <0.1 <0.1
Microbiological Parameter
31 Total Coliform MPN/100ml 10 , Max - <2 <2 <2
32 E.coli E.coli /100ml
Absent - Absent Absent Absent
Note: Un- Unobjectionable
![Page 42: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/42.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP-Section- III Description of Environment
Page 9/III
Study Period - April 2011
S. No. Parameter Unit
Limit (as per IS:10500)
GW1 GW2 GW3
desirable permissible
1 Colour Hazen 5 25 <2 <2 <2
2 Odour - Un - Un Un Un
3 Taste - Agreeable - Agreeable Agreeable Agreeable
4 Turbidity NTU 5 10 <1 <1 <1
5 pH - 6.5-8.5 No Relaxation 7.53 7.68 7.79
6 Total Hardness (as CaCO3)
mg/l 300 600 179 191 217
7 Iron (as Fe) mg/l 0.3 1 0.09 0.08 0.06
8 Chlorides (as Cl) mg/l 250 1000 27 34 36
9 Fluoride (as F ) mg/l 1 1.5 0.7 0.6 0.5
10 TDS mg/l 500 2000 327 369 394
11 Calcium(as Ca2+) mg/l 75 200 43 46 52
12 Magnesium (as Mg2+) mg/l 30 100 17 18 21
13 Copper (as Cu) mg/l 0.05 1.5 0.01 <0.01 0.01
14 Manganese(as Mn) mg/l 0.1 0.3 <0.01 <0.01 0.01
15 Sulphate (as SO4) mg/l 200 400 14 21 27
16 Nitrate(as NO3) mg/l 45 No Relaxation 7 8 7
17 Phenolic Compounds (as C6H5OH)
mg/l 0.001 0.002 <0.001 <0.001 <0.001
18 Mercury (as Hg) mg/l 0.001 No Relaxation <0.001 <0.001 <0.001
19 Cadmium (as Cd) mg/l 0.01 No Relaxation <0.01 <0.01 <0.01
20 Selenium ( as Se ) mg/l 0.01 No Relaxation <0.01 <0.01 <0.01
21 Arsenic (as As) mg/l 0.01 No Relaxation <0.005 <0.005 <0.005
22 Cyanide (as CN ) mg/l 0.05 No Relaxation <0.01 <0.01 <0.01
23 Lead (as Pb) mg/l 0.05 No Relaxation <0.01 <0.01 <0.01
24 Zinc (as Zn) mg/l 5 15 0.07 0.06 0.07
25 Anionic Detergent (as MBAS)
mg/l 0.2 1 <0.01 <0.01 <0.01
26 Chromium (as Cr6+) mg/l 0.05 No Relaxation <0.01 <0.01 <0.01
27 Mineral oil mg/l 0.01 0.03 <0.01 <0.01 <0.01
28 Alkalinity as CaCO3 mg/l 200 600 187 198 205
29 Aluminium (as Al) mg/l 0.03 0.2 <0.02 <0.02 <0.02
30 Boron (as B) mg/l 1 5 <0.1 <0.1 <0.1
Microbiological Parameter
31 Total Coliform MPN/100ml 10 , Max - <2 <2 <2
32 E.coli E.coli /100ml
Absent - Absent Absent Absent
Note: Un- Unobjectionable
![Page 43: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/43.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP-Section- III Description of Environment
Page 10/III
Study Period - May 2011
S. No. Parameter Unit
Limit (as per IS:10500)
GW1 GW2 GW3
desirable permissible
1 Colour Hazen 5 25 <2 <2 <2
2 Odour - Un - Un Un Un
3 Taste - Agreeable - Agreeable Agreeable Agreeable
4 Turbidity NTU 5 10 <1 <1 <1
5 pH - 6.5-8.5 No Relaxation 7.61 7.81 7.98
6 Total Hardness (as CaCO3)
mg/l 300 600 188 201 231
7 Iron (as Fe) mg/l 0.3 1 0.06 0.09 0.08
8 Chlorides (as Cl) mg/l 250 1000 29 37 41
9 Fluoride (as F ) mg/l 1 1.5 0.6 0.7 0.7
10 TDS mg/l 500 2000 350 388 417
11 Calcium(as Ca2+) mg/l 75 200 45 48 54
12 Magnesium (as Mg2+) mg/l 30 100 18 19 23
13 Copper (as Cu) mg/l 0.05 1.5 <0.01 0.01 0.01
14 Manganese(as Mn) mg/l 0.1 0.3 0.01 <0.01 <0.01
15 Sulphate (as SO4) mg/l 200 400 18 20 23
16 Nitrate(as NO3) mg/l 45 No Relaxation 7 10 9
17 Phenolic Compounds (as C6H5OH)
mg/l 0.001 0.002 <0.001 <0.001 <0.001
18 Mercury (as Hg) mg/l 0.001 No Relaxation <0.001 <0.001 <0.001
19 Cadmium (as Cd) mg/l 0.01 No Relaxation <0.01 <0.01 <0.01
20 Selenium ( as Se ) mg/l 0.01 No Relaxation <0.01 <0.01 <0.01
21 Arsenic (as As) mg/l 0.01 No Relaxation <0.005 <0.005 <0.005
22 Cyanide (as CN ) mg/l 0.05 No Relaxation <0.01 <0.01 <0.01
23 Lead (as Pb) mg/l 0.05 No Relaxation <0.01 <0.01 <0.01
24 Zinc (as Zn) mg/l 5 15 0.06 0.05 0.05
25 Anionic Detergent (as MBAS)
mg/l 0.2 1 <0.01 <0.01 <0.01
26 Chromium (as Cr6+) mg/l 0.05 No Relaxation <0.01 <0.01 <0.01
27 Mineral oil mg/l 0.01 0.03 <0.01 <0.01 <0.01
28 Alkalinity as CaCO3 mg/l 200 600 196 210 221
29 Aluminium (as Al) mg/l 0.03 0.2 <0.02 <0.02 <0.02
30 Boron (as B) mg/l 1 5 <0.1 <0.1 <0.1
Microbiological Parameter
31 Total Coliform MPN/100ml 10 , Max - <2 <2 <2
32 E.coli E.coli /100ml Absent - Absent Absent Absent
Note: Un- Unobjectionable
![Page 44: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/44.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP-Section- III Description of Environment
Page 11/III
Observation:
Analysis of results of ground water reveal the following: -
• pH varies from 7.42 at GW1 in the month of March, 2011 to 7.98 at GW3 in the
month of May, 2011.
• Total hardness varies from 165 mg/l at GW1 in the month of March, 2011 to 231 mg/l
at GW3 in the month of May, 2011.
• Total dissolved solids vary from 304 mg/l at GW1 in the month of March, 2011 to 417
mg/l at GW3 in the month of May, 2011.
Results show that the, samples taken from GW3 have the maximum values for most of the
parameters.
The ground water from all sources remains suitable for drinking purposes as all the
constituents are within the limits prescribed by drinking water standards promulgated by
Indian Standards IS: 10500.
Fluorides and nitrates are within the permissible limits.
Fig.3.3 Ground water sampling at village Raipur Araian
![Page 45: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/45.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP-Section- III Description of Environment
Page 12/III
3.3 (b) Surface Water
Three surface water samples were collected from the study area. The location of surface
water samples is given in Table 3.3 (iii). The physico-chemical analysis of the samples is
given in the Table 3.3 (iv).
Fig.3.4 Surface water sampling from the river Satluj.
Table 3.3 (iii)
Surface water sampling locations
Station No. Location Direction Distance
(km)
Project area/
study area
SW1 Panddrawal E 4.80 Buffer zone
SW2 Near Site E 0.50 Project Site
SW3 Near Fatehgarh
Lakha W 3.50 Buffer zone
![Page 46: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/46.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP-Section- III Description of Environment
Page 13/III
Table 3.3 (iv) Physico-chemical properties of surface water (March 2011)
S. No. Parameter Unit S.W. 1 S.W. 2 S.W. 3
Upstream Centre Downstream
1 pH - 7.65 7.54 7.46
2 Dissolved oxygen mg/l 7.5 7.2 7.1
3 BOD (3 Days at 27°C) mg/l 1 2 2
4 Free Ammonia (as N) mg/l <0.1 <0.1 <0.1
5 Sodium Adsorption Ratio - 1.6 1.1 1.3
6 Boron mg/l 0.1 0.1 0.1
7 Conductivity µmhos/cm 280 272 323
8 Turbidity NTU 8 10 12
9 Magnesium Hardness ( as CaCO3) mg/l 22 28 30
10 Total Alkalinity (as CaCO3) mg/l 102 92 120
11 Chloride (as Cl) mg/l 16 18 20
12 sulphate (as SO4) mg/l 12 14 11
13 Nitrate (as NO3) mg/l 1.4 1.6 1.6
14 Fluoride (as F) mg/l 0.4 0.4 0.4
15 Sodium (as Na) mg/l 31 22 30
16 Potassium (as K) mg/l 3.1 2.8 3.3
17 TKN mg/l 0.8 1.1 1.2
18 Total Phosphorous (as P) mg/l 0.36 0.32 0.43
19 COD mg/l 7 10 12
20 Phenollic compounds (as C6H5OH) mg/l <0.001 <0.001 <0.001
21 Iron (as Fe) mg/l 0.6 0.4 0.4
22 Zinc (as Zn) mg/l 0.02 0.02 0.02
23 Arsenic (as As) mg/l <0.005 <0.005 <0.005
24 Mercury (as Hg) mg/l <0.001 <0.001 <0.001
25 Total Coliform MPN/100ml 500 1100 1300
26 Faecal Coliform MPN/100ml 220 500 500
![Page 47: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/47.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP-Section- III Description of Environment
Page 14/III
Physico-chemical properties of surface water (April 2011)
S. No. Parameter Unit S.W. 1 S.W. 2 S.W. 3
Upstream Centre Downstream
1 pH - 7.61 7.66 7.72
2 Dissolved oxygen mg/l 7.6 7.5 7.3
3 BOD (3 Days at 27°C) mg/l 2 2 3
4 Free Ammonia (as N) mg/l <0.1 <0.1 <0.1
5 Sodium Adsorption Ratio - 1.4 1.8 1.7
6 Boron mg/l 0.1 0.1 0.1
7 Conductivity µmhos/cm 280 332 350
8 Turbidity NTU 10 14 12
9 Magnesium Hardness ( as CaCO3) mg/l 24 26 28
10 Total Alkalinity (as CaCO3) mg/l 112 126 132
11 Chloride (as Cl) mg/l 12 18 14
12 sulphate (as SO4) mg/l 10 12 16
13 Nitrate (as NO3) mg/l 1.4 1.6 1.5
14 Fluoride (as F) mg/l 0.4 0.5 0.4
15 Sodium (as Na) mg/l 29 38 36
16 Potassium (as K) mg/l 3.4 2.9 3.1
17 TKN mg/l 0.9 1.1 1.1
18 Total Phosphorous (as P) mg/l 0.36 0.41 0.42
19 COD mg/l 10 14 18
20 Phenollic compounds (as C6H5OH) mg/l <0.001 <0.001 <0.001
21 Iron (as Fe) mg/l 0.79 0.56 0.48
22 Zinc (as Zn) mg/l 0.01 0.02 0.02
23 Arsenic (as As) mg/l <0.005 <0.005 <0.005
24 Mercury (as Hg) mg/l <0.001 <0.001 <0.001
25 Total Coliform MPN/100ml 900 1700 2200
26 Faecal Coliform MPN/100ml 320 800 900
![Page 48: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/48.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP-Section- III Description of Environment
Page 15/III
Physico-chemical properties of surface water (May 2011)
S.No. Parameter Unit S.W. 1 S.W. 2 S.W. 3
Upstream Centre Downstream
1 pH - 7.64 7.68 7.72
2 Dissolved oxygen mg/l 7.9 7.2 7.5
3 BOD (3 Days at 27°C) mg/l 2 3 3
4 Free Ammonia (as N) mg/l <0.1 <0.1 <0.1
5 Sodium Adsorption Ratio - 1.67 1.64 1.99
6 Boron mg/l 0.1 0.1 0.1
7 Conductivity µmhos/cm 315 350 373
8 Turbidity NTU 12 16 14
9 Magnesium Hardness ( as CaCO3) mg/l 26 30 28
10 Total Alkalinity (as CaCO3) mg/l 120 128 134
11 Chloride (as Cl) mg/l 16 20 22
12 sulphate (as SO4) mg/l 12 14 16
13 Nitrate (as NO3) mg/l 1.2 1.4 1.1
14 Fluoride (as F) mg/l 0.4 0.5 0.5
15 Sodium (as Na) mg/l 34 36 42
16 Potassium (as K) mg/l 3.2 3.4 3.1
17 TKN mg/l 1.1 1.5 1.3
18 Total Phosphorous (as P) mg/l 0.42 0.41 0.42
19 COD mg/l 12 16 20
20 Phenolic compounds (as C6H5OH) mg/l <0.001 <0.001 <0.001
21 Iron (as Fe) mg/l 0.96 0.78 0.89
22 Zinc (as Zn) mg/l 0.01 0.01 0.02
23 Arsenic (as As) mg/l <0.005 <0.005 <0.005
24 Mercury (as Hg) mg/l <0.001 <0.001 <0.001
25 Total Coliform MPN/100ml 1400 2600 3300
26 Faecal Coliform MPN/100ml 700 1100 1300
![Page 49: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/49.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP-Section- III Description of Environment
Page 16/III
Observation:
The analysis results indicate that the pH ranges between 7.46 and 7.72.
Dissolved Oxygen (DO) was observed in the range of 7.1 to 7.9 mg/l against the minimum
requirement of 4 mg/l. BOD values were observed to be in the range of 1-3 mg/l.
The chlorides and Sulphates were found to be in the range of 12-22.0 mg/l and 10-16.0 mg/l
respectively.
Bacteriological examination of surface water samples revealed the presence of total coliform in
range of 500MPN/100 ml to 3300 MPN/100 ml
Based on the results it is evident that most of the parameters of the samples comply with
‘Category ‘C’ standards of CPCB indicating their suitability for Drinking water source after
conventional treatment and disinfection.
3.4 SOIL ENVIRONMENT
Soil may be defined as a thin layer of earth’s crust, medium for the growth of plants. The soil
characteristics include both physical and chemical properties. The soil survey and soil
samples were carried out / collected to assess the soil characteristics of the study area. Soil
samples were collected from 3 locations (project site, one upstream & one downstream side)
as shown in Table 3.4(i) and analyzed as per CPCB norms.
The physico-chemical characteristics of these soil samples are given in Table No. 3.4(ii).
.
Table No. 3.4 (i)
Description of soil sampling locations
Station No. Location Direction Distance
(km)
Project area/
study area
SQ1 Ashour W 3.30 Buffer zone
SQ 2 Site - - Project Site
SQ 3 Panddrawal E 4.80 Buffer zone
![Page 50: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/50.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP-Section- III Description of Environment
Page 17/III
Table 3.4 (ii)
Physico-chemical properties of soil
S.No. Parameter Unit SQ-1 SQ-2 SQ-3
1
Texture - Sandy Clay loam Sandy loam Sandy Clay loam
Silt % 21.42 19.12 15.34
clay % 28.84 10.05 26.71
Sand % 49.74 70.83 57.95
2 pH - 7.62 7.58 8.36
3 Electrical Conductivity µmhos/cm 128 103 147
4 Cation- exchange capacity meq/100 gm 12.98 8.14 15.32
5 Potassium mg/kg 62.34 74.34 82.34
6 Sodium mg/kg 206.87 185.87 172.87
7 Calcium mg/kg 1191.35 1236.95 1365.95
8 Magnesium mg/kg 101.61 114.21 100.61
9 Sodium Absorption Ratio - 1.54 1.35 1.21
10 Water Holding Capacity % 27.56 23.6 25.66
11 Porosity % 47.25 54.79 51.23
12 Avl.Phosphorus (as P) mg/kg 19.32 6.7 14.65
13 Avl.Nitrogen mg/kg 78.87 61.23 88.26
14 Total Nitrogen % 0.045 0.028 0.031
15 Carbon % 1.07 0.95 1.21
16 Sulphur % 0.035 0.027 0.048
Observations:
Samples collected from identified locations indicate the soil is sandy type and the pH value
ranging from 7.58 to 8.36, which shows that the soil is alkaline in nature. Potassium is found
to be from 62.34 mg/kg to 82.34 mg/kg. The water holding capacity is found between 23.6%
to 27.56%.
![Page 51: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/51.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP-Section- III Description of Environment
Page 18/III
Fig.3.5 Soil sampling near village Raipur Araian
3.5 NOISE ENVIRONNENT
The noise levels within the study area were recorded using Sound Level Meter and noise
monitoring results were compared with the Ambient Noise Quality Standard notified under
Environment Protection Act, 1986.
Table 3.5 (i)
Noise quality monitoring stations
S.No. Location Station name Distance and direction
from the lease area (km)
Zone (Core/
Buffer)
1. NQ1 Ashour W 3.30 Buffer zone
2. NQ2 Raipur N 2.60 Buffer zone
3. NQ3 Site - 0.00 Core Zone
4. NQ4 Raur E 6.00 Buffer zone
Table No. 3.5 (ii) Noise level status
S.No. LOCATION ZONE
LIMIT (as per CPCB Guidelines),dB(A)
Monitored value dB(A)
DAY* NIGHT* DAY* NIGHT*
1 NQ1
Residential Zone 55 45 53.8 43.8
2 NQ2
Residential Zone 55 45 54.3 44.1
3 NQ3
Industrial zone 75 70 56.2 44.7
4 NQ4
Silence zone 50 40 49.2 39.4
* Day time dB(A)(6.00AM TO 10.00PM)
Night time dB(A)(10.00PM TO 6.00AM)
![Page 52: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/52.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP-Section- III Description of Environment
Page 19/III
Results
Noise monitoring reveals that the maximum & minimum noise levels at day time were
recorded as 56.2 dB (A) at NQ3 & 49.2 dB(A) at NQ4, respectively. The maximum &
minimum noise levels at night time were found to be 44.7 dB(A) at NQ3 Village & 39.4
dB(A) at NQ4.
There are several other sources in the 10 km radius of study area, which contributes to the
local noise level of the area. Traffic activities as well as activities in nearby villages and
agricultural fields add to the ambient noise level of the area.
3.6 THE TRAFFIC STUDY
The connecting road from the mine to NH-1 is 12 m wide. This may be reinforced to facilitate
easy and smooth movement of heavy duty trucks.
During mine operation
Total capacity of mine : 1, 61,800 TPA
No. of working days : 250 days
Per day capacity of mine : 668 tonnes
Truck capacity : 20 tonnes
No. of trucks deployed : 33 trucks
Working hours per day : 8 hours
No. of trucks deployed/hr : 4 trucks
At present the traffic load at highway is 18 trucks per hour, in particular. Due to the proposed
project there will be addition in the existing trucks having the capacity of 20 tonnes load that
is 4 trucks/hr, hence the changes will be at small level and will not affect the existing
environment.
3.7 BIOLOGICAL ENVIRONMENT
Ecological Environment:
The State of Punjab can be divided physiographically in to two broad regions viz. Shivalik
Himalayan region and alluvial plain region. Satluj, Beas, Ravi and Ghagghar are four main
rivers of the State, which after traversing through Shivalik region, irrigate the plain areas and
make them fertile. The State is consisting of many fragile ecosystems of international
importance and many Protected and Reserved forests. As far as the study area is concerned
it falls under the alluvial plain regions of Punjab. It mainly comprises of non-forest areas such
as agricultural land, river beds, human settlements and barren land.
![Page 53: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/53.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP-Section- III Description of Environment
Page 20/III
Forest cover in Jalandhar district:
The recorded forest area in Punjab State is 3,058 sq km, which constitute about 6.07% of
total geographic area of the State. The Jalandhar district has only 4 km2 forest cover out of
which 2 km2 is moderately dense forest and 2 km2 is open forest. (India State of Forests
Report, 2009). As far as study area is concerned there is no forest area at all. The area
comprises of agricultural land and riverine vegetation. Due to high temperature and humidity
the area comprises of tropical dry deciduous vegetation. Wild life protected area declared
protected under “Wildlife Protection Act-1972” located within 10 km radius of the proposed
mining area is Mattwara RF. Forest occurring in the district is typically topical dry deciduous
type. The forest is dominated by Acacia nilotica, Dalbergia sissoo, Bombax cieba etc.
Methodology for Floral & Faunal study:
Detailed survey was conducted to evaluate floral and faunal composition of the study area.
Primary data on floral and faunal composition was recorded during site visit and secondary
data was collected from the Forest department and published relevant literatures to get the
correct picture of the study area. Inventory of flora and fauna is prepared on the basis of
collected data. Forest type and vegetation of the study area is discussed on the basis of
plant species recorded from the area.
General vegetation of the study area:
The study area comprise of tropical dry deciduous vegetation. Several tropical elements can
be seen scattered in the area. Species of Achyranthes, Calotropis, Lantana, Ricinus,
Ziziphus, etc. are of common occurrence. Tree species viz. Acaccia nilotica, Eucalyptus
umbellata, Populus deltoids, Melia azadirachta, etc. are found planted along the boundary of
the agricultural lands and along the road sides.
Ground vegetation mainly consists of grasses and small shrubs. Useful fodder grasses,
Cynodon dactylon, Eleusine indica, Trifolium alexandrinumt, etc. can be seen growing in the
area.
The large weeds which infest uncultivated tracts are aak (Calotropis procera), castor
(Ricinus communis), dhatura (Datura metel) and thor (Opnuntia stricta). Other abnoxious
weeds and those which appear in crops are pohli or thistle (Carthamus oxyacantha), shial
kanta (Argemone mexicana), kandyari (Solanum xanthocarpum) and bhang (Cannabis
sativa).
Flora of the Core zone: The core zone comprises of Satluj river bed, where mining
operation is proposed. This area consists of riparian vegetation in which aquatic and
marshland plants are the main component. No ecologically sensitive plant species has been
![Page 54: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/54.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP-Section- III Description of Environment
Page 21/III
reported from this area. Riparian vegetation is found along the river side. The river Satluj is
full of water throughout the year with great flow. Popular ciliate and Dalbergia sisso grows
along the river bank (Fig-3.6 & 3.7)
Fig-3.6: Trees grown along the river bank Fig-3.7: Scattered annual grasses near the mine
area
Flora of the Buffer zone: Buffer zone of the proposed project is mainly agricultural land.
The flora of buffer zone comprises of plants growing on the edges of agricultural land, village
woodlots and trees planted along the roads. Many tree species are planted in the area
because of their usefulness, economic and aesthetic values. Some tree species observed in
the area are, Aam (Mangifera indica), Jamun (Syzygium cumini), Bail (Aegle marmelos),
Bakain (Melia azedarach), Bargad (Ficus bengalensis), Neem (Azadirachta indica), Peepal
(Ficus religiosa), Popular (Populas dealtoides), Safeda (Eucalyptus umbelatus), Sisam
(Dalbergia sissoo), etc.
In agricultural waste land and along the road side, growth of weeds like Argemone
mexicana, Cannabis sativa, Cenchrus cilitaris, Heteropogon contortus, Lantana camara,
Parthenium hysterosporus, etc. are very common. These weeds are affecting the agricultural
productivity of the region due to fast growth, short life cycle and enormous production of
seeds.
Agricultural crops: The study area is surrounded by agricultural field in which many plants of
agricultural importance are cultivated. Wheat (Triticum aestivum), Rice (Oryza sativa), Maize
(Zea mays), Sugarcane (Saccharum officinarum), Bajra (Pennisetum glaucum), Sunflower
(Helianthus annuus) are commonly grown crops of this area.
![Page 55: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/55.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP-Section- III Description of Environment
Page 22/III
Fauna reported in Core zone:
During the faunal survey in the area no wildlife corridor or movement of animals was
recorded from proposed project area. A list of animals of the study area has been prepared
on the basis of local inquiry from the village people and from the available published
literatures. The animals thus recorded were cross checked with Wildlife Protection Act, 1972
for their schedule. No established habitats of any mammals or birds are noticed in river bed
and along the banks. Among mammals Rat & squirrels and among birds common mayna,
house crow, koel and sparrow were reported to be found the core zone.
Fauna reported in Buffer zone:
Mammal: Many domesticated mammal species are reported from buffer zone during the
field survey. Common grazing animals like Buffalo, cow, goat etc. can be noticed in open
grass fields. Small mammals like Indian palm squirrel (Funambulus palmarum) and field
mouse (Apodemus sylvaticus) are noticed in vicinity of village. Inquiry from village people
regarding wild animals reveals that monkey (Macaca silenus), Indian hare (Lepus nigricollis),
fruits bat (Pteropus conspicillatus), Nilgai (Boselaphus tragocamelus), mongoose (Herpestes
edwardsii), jackal (Canis aureus), etc. are often seen in the area.
Avifauna: Water birds like Gadwall (Anas strepera), Common teal (Anas crecca), White
throated kingfisher (Halcyon smyrnensis), Pied kingfisher (Ceryle rudis), Red wattled lapwing
etc are noticed. House crow (Corvus splendens), House sparrow (Passer domesticus),
Common hill Myna (Gracula religiosa), Red-rumped Swallow (Cecropis daurica), Hoopoe
(Upupa epops ceylonensis) are of common occurrence.
Reptile: The reptilians species commonly reported are Agama (Laudakia tuberculata) in
settlement area, Garden lizard (Calotes versicolor) and Eutropis macularia along shady
places in agricultural field or where growth of bushes is noticed.
Table 3.6 (i) Flora of the Core zone
S. No. Species Family Habit
1. Ageratum conyzoides L. Asteraceae Herb
2. Amaranthus spinosus L. Amaranthaceae Herb
3. Calotropis procera (Aiton) R.Br. Asclepiadaceae Shrub
4. Cannabis sativa L. Canabaceae Herb
5. Cassia tora L. Caesalpinaceae Herb
6. Cenchrus ciliaris L. Poaceae Herb
7. Chenopodium album L. Chenopodiaceae Herb
8. Datura innoxia Mill. Solanaceae Shrub
![Page 56: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/56.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP-Section- III Description of Environment
Page 23/III
Table 3.6(ii) Flora of the Buffer zone
9. Hydrolea zeylanica (L.) Vahl Hydrophylaceae Herb
10. Ipomoea carnea Jacq. Convolvulaceae Shrub
1. Alternanthera paronychioides A.St.-Hil. Amaranthaceae Herb
2. Alternanthera pungens Kunth Amaranthaceae Herb
3. Amaranthus spinosus L. Amaranthaceae Herb
4. Colocasia esculenta (L.) Schott Araceae Herb
5. Ageratum conyzoides L. Asteraceae Herb
6. Grangea maderaspatana (L.) Poir. Asteraceae Herb
7. Parthenium hysterophorus L. Asteraceae Herb
8. Cassia tora L. Caesalpinaceae Herb
9. Cannabis sativa L. Canabaceae Herb
10. Chenopodium album L. Chenopodiaceae Herb
11. Commelina benghalensis L. Commelinaceae Herb
12. Cyperus alopecuroides Rottb. Cyperaceae Herb
13. Cyperus rotundus L. Cyperaceae Herb
14. Fimbristylis aestivalis (Retz.) Vahl. Cyperaceae Herb
15. Scirpus brachyceras Hochst. ex A.
Rich.
Cyperaceae Herb
16. Argemone mexicana L. Papaveraceae Herb
17. Brachiaria ramosa (L.) Stapf. Poaceae Herb
18. Cynodon dactylon (L.) Pers. Poaceae Herb
19. Dactyloctenium aegyptium (L.) Willd. Poaceae Herb
20. Echinochloa colona (L.) Link Poaceae Herb
21. Eleusine indica (L.) Gaertn. Poaceae Herb
22. Eragrostis tenella (L.) Roem. & Schult. Poaceae Herb
23. Imperata cylindrica (L.) P. Beauv. Poaceae Herb
24. Panicum brevifolium L Poaceae Herb
![Page 57: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/57.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP-Section- III Description of Environment
Page 24/III
25. Saccharum spontaneum L. Poaceae Herb
26. Physalis minima L. Solanaceae Herb
27. Calotropis procera (Aiton) R.Br. Asclepiadaceae Shrub
28. Cassia occidentalis L. Caesalpinaceae Shrub
29. Croton bonplandianum Baill. Euphorbiaceae Shrub
30. Abutilon indicum (L.) Sweet Malvaceae Shrub
31. Bougainvillea spectabilis Willd. Nyctaginaceae Shrub
32. Ziziphus mauritiana Lam. Rhamnaceae Shrub
33. Datura innoxia Mill. Solanaceae Shrub
34. Solanum virginianum L. Solanaceae Shrub
35. Lantana camara L. Verbenaceae Shrub
36. Mangifera indica L. Anacardiaceae Tree
37. Polyalthia longifolia (Sonn.) Thw. Annonaceae Tree
38. Alstonia scholaris (L.) R. Br. Apocynaceae Tree
39. Cassia fistula L. Caesalpinaceae Tree
40. Ricinus communis L. Euphorbiaceae Tree
41. Albizia lebbeck (L.) Benth. Fabaceae Tree
42. Bauhinia acuminata L. Fabaceae Tree
43. Butea monosperma (Lam.) Taub. Fabaceae Tree
44. Dalbergia sissoo Roxb. Fabaceae Tree
45. Bombax ceiba L. Malvaceae Tree
46. Azadirachta indica A.Juss. Meliaceae Tree
47. Melia azedarach L. Meliaceae Tree
48. Acacia nilotica (L.) Willd. ex Delile Mimosaceae Tree
49. Ficus benghalensis L. Moraceae Tree
50. Ficus religiosa L. Moraceae Tree
51. Ficus virens Dryand. Moraceae Tree
52. Morus alba L. Moraceae Tree
53. Morus australis Poir. Moraceae Tree
![Page 58: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/58.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP-Section- III Description of Environment
Page 25/III
Table 3.6 (iii) Fauna of the Core zone:
S. No. Common Name Scientific Name Wildlife
schedule
Avian fauna (Bird):
1. Common Myna Acridotheres tristis IV
2. House Crow Corvus splendens IV
3. Drongo Dicrurous adsimilis IV
4. Koel Eudynamys scolopacea IV
5. Sparrow Passer domesticus IV
Mammals
1 Squirrel Funambulus pennant IV
2 Rat Ratthus ratthus V
Amphibians
1 Common Indian tod Bufo melanostictus IV
2 Indian skipper frog Euphlyctis cyanophlyctis IV
3 Indian bull frog Hoplobatrachus tigerinus IV
Fishes
1 Bhangan or Bata Labio bata --
2 Chappera or Palla Gudusia chapara --
3 Dumra or Dhambra Labio rohita --
4 Pari or Battu Notopterus notopterus --
5 Theila Catla catla --
Mollusca:
1 -- Bellamya benghalensis --
2 -- Pila globosa --
3 -- Brotia costula --
54. Eucalyptus umbellata Dum.Cours. Myrtaceae Tree
55. Syzygium cumini (L.) Skeels Myrtaceae Tree
56. Aegle marmelos (L.) Corrêa Rutaceae Tree
57. Citrus jambhiri Lush. Rutaceae Tree
58. Populus deltoids Bartram ex Marshall Salicaceae Tree
59. Ailanthus excelsa Roxb. Simaroubiaceae Tree
![Page 59: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/59.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP-Section- III Description of Environment
Page 26/III
4 -- Angulyara oxytropis --
5 -- Lemellidens marginalis --
Table 3.6 (iv) Fauna of the Buffer zone:
S.No Common Name Scientific name Wildlife
Wild Animals (mammals)
1 Squirrel Funambulus pennant Schedule –IV
2 Rat Ratthus ratthus Schedule –V
3 Blue bull Boselaphus tragocamelus Schedule –III
Avians (Birds)
1 Common Myna Acridotheres tristis Schedule -IV
2 King fisher Halcyon smyrnensis Schedule –IV
3 Pond Heron Ardeola grayii Schedule –IV
4 Blue Rock Pigeon Columba livia Schedule -IV
5 House Crow Corvus splendens Schedule -V
6 Cuckoo Cuculus canorus Schedule -IV
7 House Sparrow Passer domesticus Schedule -IV
8 Roseringed Parakeet Psittacula krameri Schedule -IV
9 Pond Heron Ardeola grayii Schedule -IV
10 Grey Horn Bill Ocyceros birostris Schedule -IV
11 Common Babbler Turdoides caudatus Schedule –IV
12 Peacock Pavo cristatus Schedule –I
Reptiles & Amphibians
1 Common Toad Buyo melanostictus Schedule -IV
2 India bull frog Rana tigerina Schedule -IV
3 India tree frog Polypedates maculates Schedule IV
4 Skipping frog Buyo stomaticus Schedule –IV
5 Garden lizard Calotes versicolor Schedule -IV
6 House lizard Hemidactylus sp Schedule -IV
7 Rat snakes Ptyas mucosa Schedule –II
******************
![Page 60: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/60.jpg)
![Page 61: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/61.jpg)
![Page 62: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/62.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP-Section – IV Anticipated Environmental Impact
and Mitigation Measures
Page 1/IV
SECTION-IV
ANTICIPATED ENVIRONMENTAL IMPACT AND MITIGATION MEASURES
INDEX
S. No. CONTENTS Page No.
4.0 GENERAL 2/IV
4.1 LAND ENVIRONMENT 2/IV
4.2 WATER ENVIRONMENT 7/IV
4.3 AIR ENVIRONMENT 8/IV
4.4 NOISE ENVIRONMENT 11/IV
4.5 BIOLOGICAL ENVIRONMENT 12/IV
4.6 TRAFFIC ANALYSIS 16/IV
4.7 STATUATORY REQUIREMENTS 17/IV
4.8 MATRIX FOR EIA 18/IV
![Page 63: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/63.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP-Section – IV Anticipated Environmental Impact
and Mitigation Measures
Page 2/IV
4.0 GENERAL
All development projects are likely to have an impact on the natural set up of the
environment. This impact may be beneficial or adverse, depending on the improvement or
the deterioration it brings about change in the status of air, water, land, ecology, natural
systems, socio-cultural life styles and economics of the population. Depending on the nature
of activities and baseline environment status, the impacts are assessed for their importance.
On the basis of the impact analysis, the mitigating action and future monitoring requirement
are focused in the Environmental Management plan for countering or minimizing the
impacts.
Keeping in mind, the environmental baseline scenario as detailed in Section III and the
proposed mining activity described in Section II, it is attempted to assess the likely impact
and its extent on various environmental parameters and likely mitigation measures to be
adopted.
4.1 LAND ENVIRONMENT
The mining and allied activities involved in river bed mining are creation of temporary haul
roads / transportation track and formation of mined pits inside river, etc. The systematic
removal of sand will not cause bed degradation and will not affect aquatic environment.
This RBM project does not involve any waste generation. Thus no waste dump sites are
needed for the project.
IMPACT OF SAND MINING
The proposed extraction of streambed materials, mining below the existing streambed, and
alteration of channel-bed form and shape leads to several impacts such as erosion of
channel bed and banks, increase in channel slope, and change in channel morphology.
These impacts may cause:
• Undercutting and collapse of river banks.
• Loss of adjacent land and/or structures.
• Upstream erosion as a result of an increase in channel slope and changes in flow
velocity.
• Downstream erosion due to increased carrying capacity of the stream
• Downstream changes in patterns of deposition.
• Changes in channel bed and habitat type.
![Page 64: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/64.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP-Section – IV Anticipated Environmental Impact
and Mitigation Measures
Page 3/IV
Mitigation measures
• Since the project is mainly for sand excavation (soil deficient), no loss of top soil is
involved /anticipated.
• The RBM activity will be semi-mechanized, most of the work is proposed to be done
manually which will avoid adverse effects associated with heavy machinery /
equipments / their functioning.
• Sand mining will be restricted down to 3 m below river bed or the water table whichever
less.
• The RBM will be done in unsaturated zone, thus minimising loss to habitat.
• Dredging will not be allowed.
Sand Budget
Determining the sand budget for a particular stream reach requires site-specific topographic,
hydrologic, and hydraulic information. This information is used to determine the amount of
sand that can be removed from the area without causing undue erosion or degradation,
either at the site or at a nearby location, upstream or downstream.
In-channel or near-channel sand-and-gravel mining changes the sediment budget, and may
result in substantial changes in the channel hydraulics. These interventions can have
variable effects on aquatic habitat, depending on the magnitude and frequency of the
disturbance, mining methods, particle-size characteristics of the sediment, the
characteristics of riparian vegetation, and the magnitude and frequency of hydrologic events
following the disturbance.
Temporal and spatial responses of alluvial river systems are a function of geomorphic
thresholds, feedbacks, lags, upstream or downstream transmission of disturbances, and
geologic/physiographic controls. Minimization of the negative effects of sand-and-gravel
mining requires a detailed understanding of the response of the channel to mining
disturbances.
Decisions on where to mine, how much and how often require the definition of a reference
state, i.e., a minimally acceptable or agreed-upon physical and biological condition of the
channel. Present understanding of alluvial systems is generally not sufficient to enable the
prediction of channel responses quantitatively and with confidence; therefore, reference
states are difficult to determine. Still, a general knowledge of fluvial processes can provide
guidelines to minimize the detrimental effects of mining. Well-documented cases and related
field data are required to properly assess physical, biological, and economic tradeoffs.
![Page 65: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/65.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP-Section – IV Anticipated Environmental Impact
and Mitigation Measures
Page 4/IV
Mitigation measures
Quantities will be strictly limited so that sand accumulation rates are sufficient to avoid
extended impacts on channel morphology and instream habitat. Although conceptually
simple, annual sand recruitment to a particular site is highly variable and not well
understood.
• Flow and sediment transport for most rivers and streams is highly variable from year-to-
year, thus an annual average rate may be meaningless.
• An "annual average deposition rate" could bear little relation to the sediment transport
regimes in a river in any given year.
� Mining will be done as per the approved mine plan from the respective State Mining
Department.
� The site selection was done keeping the following points; minor mineral reserves, site
specific problems like flooding, submergence crop lands / fields, need of excavation, rate
of sediment deposition etc.
� RBM will be done in responsible manner.
The sand budget calculation and replenishment capacity are given in Table 4.1
a. In whole Satluj basin
Table 4.1
Sand budget calculation and replenishment capacity of river
S. No. Factors Probable Replenishment
1. Total sand budget of mine 4,85,460 Tonnes
2. River Satluj River
3. Runoff 156.63 mm or 6.17 in
4. Catchment area 23,815.09km2 or
9195.06 mi2
5. Drainage density 0.069 km-1
6. Average slope 2.51 %
7. Average rainfall 681 (mm)
8. Vegetation cover factor 0.4
9. *Sediment yield
Formula
For Q < 2 in:
S = 1280 Q 0.46 [1.43-0.26 log (A)]
11,07,812.51 TPA
sediment will be
regenerated every year
increasing the mineable
![Page 66: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/66.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP-Section – IV Anticipated Environmental Impact
and Mitigation Measures
Page 5/IV
For Q > 2 in:
S = 1965 e -0.055Q [1.43-0.26 log (A)]
Here:
Q (in) = Mean Annual run off =156.63 mm
= 6.17 in
A (mi2) = Catchment area= 23,815.09 km2
= 9195.06 mi2
Sediment yield S= (tons/yr)
S= 1965 e-0.055x6.17[1.43 - 0.26 log (9195.06)] S = 11,07,812.51 tons/year
*source:- Calculation of sediment yield by the Dendy-
Bolton formula
reserves.
Stability of Structures
Excessive and unscientific Sand mining of instream channels may damage public and
private property. Channel incision caused by mining may undermine bridge piers and expose
buried pipelines and other infrastructure.
The bed degradation caused by Riverbed mining:
(1) Pit excavation
(2) Bar skimming
Bed degradation (channel incision), occurs through two primary processes:
(1) Head cutting
(2)"hungry" water.
Head cutting mobilizes substantial quantities of streambed sediments which are then
transported downstream to deposit in the excavated area and locations further downstream.
In gravel-rich streams, effects on downstream of mining sites may be short-lived when
mining ends, because the balance between sediment input and transport at a site can
reestablish itself relatively quickly. Effects in gravel-poor streams may develop rapidly and
persist for many years after mining has finished. Regardless of downstream effects, head
cutting in both gravel-rich and gravel-poor streams remains a major concern. Head cuts
often move long distances upstream and into tributaries, in some watersheds moving as far
as the headwaters or until halted by geologic controls or man-made structures.
A second form of bed degradation occurs when mineral extraction increases the flow
capacity of the channel. A pit excavation locally increases flow depth and a bar skimming
![Page 67: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/67.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP-Section – IV Anticipated Environmental Impact
and Mitigation Measures
Page 6/IV
operation increases flow width. Both conditions produce slower stream flow velocities and
lower flow energies, causing sediments arriving from upstream to deposit at the mining site.
As stream flow moves beyond the site and flow energies increase in response to the
"normal" channel form downstream, the amount of transported sediment leaving the site is
now less than the sediment carrying capacity of the flow. This sediment-deficient flow or
"hungry" water picks up more sediment from the stream reach below the mining site,
furthering the bed degradation process. This condition continues until the equilibrium
between input and output of sediments at the site is reestablished.
A similar effect occurs below dams, which trap sediment and release "hungry" water
downstream, where channel incision usually ensues. Riverbed mineral excavation
downstream of dams compounds this problem. Although other factors such as levees, bank
protection, and altered flow regimes also promote channel incision, mineral extraction rates
in many streams are often orders-of-magnitude in excess of sediment supply from the
watershed, suggesting that extraction is largely responsible for observed channel changes.
Susceptibility to hungry-water effects would depend on the rate of extraction relative to the
rate of replenishment. Gravel-poor streams would be most susceptible to disturbance.
Channel incision not only causes vertical instability in the channel bed, but also causes
lateral instability in the form of accelerated stream bank erosion and channel widening.
Incision increases stream bank heights, resulting in bank failure when the mechanical
properties of the bank material cannot sustain the material weight. Channel widening causes
shallowing of the streambed as deep pools fill with gravel and other sediments. Shallowing
and widening of the channel also increases stream temperature extremes, and channel
instability increases transport of sediments downstream. Mining-induced bed degradation
and other channel changes may not develop for several years until major channel-
adjustment flows occur, and adjustments may continue long after extraction has ended.
Mitigation measures
� Head cutting will not be allowed.
� Sand mining will be restricted up to 3 m below bed / water table whichever is lesser.
� The RBM will be done in unsaturated zone.
� No mining will be done near to important structure like bridges, dam and others to
prevent bar skimming.
� No mining will be done nearby the dam and important structure to prevent hungry water
problems.
� Mining will not exceed beyond the magnitude.
![Page 68: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/68.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP-Section – IV Anticipated Environmental Impact
and Mitigation Measures
Page 7/IV
4.2 WATER ENVIRONMENT
Damage in the water body, depends on its assimilative capacity. To find out assimilative
capacity of receiving water body, water samples were collected from different groundwater
and surface water sources.
Mining of sand from within or near a streambed has a direct impact on the stream’s physical
habitat characteristics. These characteristics include geometry, bed evaluation, substrate
composition and stability, in stream roughness elements, depth, velocity, turbidity, sediment
transport, stream discharge and temperature. Altering these habitat characteristics can have
deleterious impacts on both in stream biota and associated riparian habitat.
The detrimental effects, if any, to biota resulting from bed material mining are caused by
three main processes:
i. alteration of flow patterns resulting from modification of the river bed
ii. an excess of suspended sediment
iii. damage to riparian vegetation and in stream habitat
The disturbance activities can also disrupt the ecological diversity in many ways.
As the project activity is carried out in the meandering part of the river bed, none of the
project activities affect the water environment or riparian habitats. In the projects, it is not
proposed to divert or truncate any stream. No proposal is envisaged for pumping of water
either from the river or tapping the ground water. In the lean months, the proposed sand
mining will not expose the base flow of the river and hence, there will not be any adverse
impact on surface hydrology and ground water regime due to this project. DIC, GoP will
adhere all guidelines and rules for proper and scientific method of mining during the period
of extracting the sand.
Mitigation measures
The deposits occur in the middle/bottom of the river. During the lease period, the deposit will
be worked from the top surface to 3 m bgl. The ultimate depth of the open cast pits will be 3
m below ground level or the ground water table whichever is less.
4.3 AIR ENVIRONMENT
Anticipated impacts and evaluation
Information on air quality was studied and various modeling techniques predicted that the
mining activity is not likely to affect the air quality in a significant manner. However, loading
![Page 69: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/69.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP-Section – IV Anticipated Environmental Impact
and Mitigation Measures
Page 8/IV
of sand, its transportation and unloading operations may cause some deterioration in air
quality due to handling dry materials. In the present case, only wet materials will be handled,
thus eliminating problems of fugitive dust. Also, the collection and lifting of minerals will be
done manually without any blasting. Therefore the dust generated is likely to be insignificant
as compared to mining processes involving drilling, blasting, mechanized loading etc.
Air Modeling
In general, mining operations generate substantial quantities of airborne respirable dust,
which may lead to the development of respirable diseases in mine workers. The increasing
trend of mining leads to release of huge amount of dust. These air borne dust particles,
generally below 100 micron in size, are nuisance particulates and cause health hazards as
an ill effect of mining activities. Extraction activities like drilling, blasting, material handling
and transport are a potential source of air pollution. Therefore, a detailed study on emission
sources and quantification of pollutant concentration by means of dispersion modeling is
required to access the environmental impact of a mine. On the basis of the predicted
increments to air pollutant concentrations, an effective mitigation and environmental plan can
be devised for sensitive areas. In case of river bed sand mining, as there is no blasting and
drilling activities, the impacts may only be caused by material handling and transportation
activities of mostly wet sand and the same are minimal.
FUGITIVE DUST- MODELING
Air quality modeling was done using line source model as published by USEPA “Workbook
of Dispersion Modeling” by Turner, for transportation though roads and the empirical
emission factor equations from USEPA. Emission factors to be used in Line source
Dispersion equation is adopted from formula as given below:
E= k * (1.7) * (s/12)*(S/48) * (W/2.7)0.7 * (w/4)0.5 * (365-p/365) kg/VKT
Where
E = Emission Rate (kg/VKT)
k= Particle size multiplier = (0.36)
s = Silt Content of the Road surface material (%) = 10%
S = Mean Vehicle Speed (km/hr) = 20 km/hr
W=Mean Vehicle Weight (tonnes) = 20 tonnes
w= Mean number of wheels = 8
![Page 70: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/70.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP-Section – IV Anticipated Environmental Impact
and Mitigation Measures
Page 9/IV
p= Number of days with at least 0.254 mm of precipitation per year = 60
f = frequency of Vehicle movement in no per hour =4 vehicles / hour
Thus using equation (1)
E = 1.00339 kg/VKT
E = 0.0011 g/sec/m
Concentration of the fugitive dust was calculated using the empirical equations for unpaved
roads published by USEPA- AP42. The Concentration of the fugitive Dust is given below:
C = (2/π) 1/2 (E / σz υ) Exp- [(h2) / (2 σz2)] x 106 ---------------------------- (2)
Where
C = Hourly Concentration in microgram/ m3
E = Emission Rate = 0.0011 g/sec/m
υ = Wind Speed =4 m/s
h = 0 m
Modeling was done for an infinite line source assuming unpaved road. For conservative
calculation wind was assumed to blow at a velocity of 4 m/s perpendicular to the road. The
results for 24 hourly concentration values are given in the Fig. 4.1:
![Page 71: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/71.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP-Section – IV Anticipated Environmental Impact
and Mitigation Measures
Page 10/IV
Fig.4.1 Graph showing Concentration of Fugitive dust vs Distance
It is observed that the ground level concentration (GLC) decreases from 8.19 µg/m3 at 100 m
from the centre line of the road to 1.73 µg/m3 at 500 m from the centre line of the road.
These values have been predicted for a dry unpaved road.
Mitigation measures
The only air pollution sources are the road transport network of the trucks/dumpers. The dust
suppression measures like the following will be resorted:
• Water sprinkling will be done on the roads regularly. This will reduce dust emission further
by 75%.
• Care will be taken to prevent spillage by covering the carrying vehicles with tarpaulin and
sprinkling of water, if dry.
• Fortnightly scraping of road in order to keep the roads almost leveled. This will ensure
smooth flow of vehicles and also prevent spillage.
• Overloading will be kept under check by giving prior awareness.
• Proper Tuning of vehicles to keep the gas emissions under check.
• Plantation of trees along the roads to help reduce the impact of dust in the nearby
villages.
![Page 72: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/72.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP-Section – IV Anticipated Environmental Impact
and Mitigation Measures
Page 11/IV
4.4 NOISE ENVIRONMENT
The RBM projects are mainly not noisy as these are mainly semi-mechanized in nature.
Impact on environment
At mines, noise is created by movement of machinery & transportation vehicles, etc. The
noise level in the working environment are compared with the standards prescribed by
Occupational Safety and Health Administration (OSHA-USA) which has been adopted and
enforced by the Govt. of India through model rules framed under Factories Act, 1980 and
CPCB 2000 norms. The summary of the permissible exposures in cases of continuous noise
as per above rules is given below:
Table 4.2
Noise impact
Total time of exposure
per day in hour
Sound pressure
dB(A)
Remarks
1 2 3
8.0 90 No exposure in excess of 115
dB(A) is permissible
6.0 92 --
4.0 95 For any period of exposure
falling in between any figure
and lower figure as indicated in
column (1), the permissible
sound is to be determined by
extrapolation or proportionate
scale.
3.0 97
2.0 100
1 ½ 102
1 105
¾ 107
½ 110
¼ 115
Noise at lower levels (sound pressure) is quite acceptable and does not have any bad effect
on human beings, but when it is abnormally high- it incurs some maleficent effects.
a. Mitigation measures
i. On-site
a) Maintenance of Machinery: Regular maintenance of machinery will keep the
generated noise level below the minimum prescribed limit i.e. not exceeding 90 dB (A)
at a distance of 2 m from the machine. All machines will be as per stipulated standards
and will be used at their optimum capacity.
b) Trained Operators: Only trained operators will be allowed to operate machines
during mining to reduce any chance of safety failures.
![Page 73: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/73.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP-Section – IV Anticipated Environmental Impact
and Mitigation Measures
Page 12/IV
c) Vegetation: Plantation of trees along the bank will be done to dampen the noise, if
possible.
d) Hearing Protection: No hearing protection is generally needed for RBM projects.
e) Phasing out the old and worn out trucks.
ii. Off-site
The off-site receptors are not significantly affected as noise generated by RBM is
insignificant but some disturbances due to vehicle movement may not be avoidable.
However the following measures have been envisaged:
a) The vehicles will be maintained in good running condition so that noise will be
reduced to minimum possible level.
b) Awareness will be imparted prior to mining operations that smoke silencers remain
in a good conditions not to generate noise.
c) In addition, trucks drivers will be instructed to make minimum use of horns at the
village area.
4.5 BIOLOGICAL ENVIRONMENT
Table 4.3
Anticipated impact and mitigation measures for biological environment:
Impact Predicted Suggestive measure
Disturbance to free
movement / living of
wild fauna viz. Birds,
Reptiles etc.
• If birds are noticed crossing the core zone, they will
not be disturbed at all;
• Labors will not be allowed to discard food, polythene
waste etc., which can attract animals/birds near the
core site;
• Only low polluting vehicles having PUC will be
allowed for carrying mining materials.
• Noise level will be maintained within permissible limit
(silent zone-50dB (A) during day time or residential
zone 55dB (A)) as per Noise Pollution (Regulation
and Control) Rules 2000, CPCB norms
Disturbance of riparian
ecosystem/ wetlands
• The riparian ecosystem or the wetlands will not be
destroyed by the mine owners/workers.
Monitoring of upstream
and downstream water
• Water quality will be monitored from upstream and
![Page 74: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/74.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP-Section – IV Anticipated Environmental Impact
and Mitigation Measures
Page 13/IV
quality downstream area to assess the impact on water
quality and mining activity will be controlled to
maintain the clean water conditions.
Ecological Impacts
Mining which leads to the removal of channel substrate, re-suspension of streambed
sediment and stockpiling on the streambed, will have ecological impacts. These impacts
may have an effect on the direct loss of stream reserve habitat, disturbances of species
attached to streambed deposits, reduced light penetration, reduced primary production, and
reduced feeding opportunities.
For thousands of years, sand and gravel have been used in the construction of roads and
buildings. Today, demand for sand and gravel continues to increase. Mining operators, in
conjunction with cognizant resource agencies, must work to ensure that sand mining is
conducted in a responsible manner.
Excessive and unscientific Riverbed sand mining causes the degradation of rivers. Riverbed
mining lowers the stream bottom, which may lead to bank erosion. Depletion of sand in the
streambed causes the deepening of rivers, and the enlargement of river mouths. Any volume
of sand exported from streambeds is a loss to the system.
Excessive and unscientific Riverbed sand mining is a threat to bridges, river banks and
nearby structures. Sand mining may also affects the groundwater system and the uses that
local people make of the river.
Excessive and unscientific riverbed sand mining results in the destruction of aquatic and
riparian habitat through large changes in the channel morphology. Impacts include bed
degradation, bed coarsening, lowered water tables near the streambed, and channel
instability. These physical impacts cause degradation of riparian and aquatic biota and may
lead to the undermining of bridges and other structures. Continued extraction may also
cause the entire streambed to degrade to the depth of excavation.
Sand mining generates extra vehicle traffic, which negatively impairs the environment.
Where access roads cross riparian areas, the local environment may be impacted.
![Page 75: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/75.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP-Section – IV Anticipated Environmental Impact
and Mitigation Measures
Page 14/IV
Mitigation measures
As the proposed mining will be carried out in a scientific manner as mentioned before, not
much significant impact is anticipated, however, the following mitigation measure will be
taken to further minimize it:
1. The activity will mainly be carried out manually to minimize associate loss, as stated
earlier.
2. No mining will be carried out in the vicinity of important structure like bridges, dam and
other structures if any.
3. No mining will be carried out during the rainy season to minimize impact on aquatic life.
4. As the mining site has no vegetation, no clearance of vegetation is required.
5. The mining activity will deploy a few dumpers/trucks for transportation of sand from the
mine to desired destination that may cause some loss to riparian habitat. Safe site / site
having least impact will be selected for transportation, all the vehicles employed for
transportation purpose will be PUC certified. On closure of mining operations / during the
rainy season the eroded bank will be restored / reclaimed to minimize negative impacts.
6. No lighting will be allowed in the lease area.
7. No piling of sand will be allowed in the area.
Flora and Fauna of Riparian Habitat
If sand mining is done in an unscientific way, i.e. beyond the replenishment capacity,
riverbed mining can have adverse effects at the mine sites. The fertile streamside land
will be lost gradually and the wildlife in the riparian areas may start vanishing. Degraded
stream habitats will result in loss of fisheries productivity, biodiversity, and recreational
potential. Thus the severely degraded channels may lower the aesthetic value too.
All species require specific habitat conditions to ensure long-term survival. Native species
in streams are uniquely adapted to the habitat conditions that existed before humans
began alterations. These have caused major habitat disruptions that favored some
species over others and caused overall declines in biological diversity and productivity. In
most streams and rivers, habitat quality is strongly linked to the stability of channel bed
and banks. Unstable stream channels are inhospitable to most aquatic species.
Factors that increase or decrease sediment supplies often destabilize bed and banks and
result in dramatic channel readjustments. For example, human activities that accelerate
stream bank erosion, such as riparian forest clearing / Riverbed mining cause stream
banks to become net sources of sediment that often have severe consequences for
aquatic species. Anthropogenic activities that artificially lower stream bed elevation cause
![Page 76: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/76.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP-Section – IV Anticipated Environmental Impact
and Mitigation Measures
Page 15/IV
bed instabilities that result in a net release of sediment in the local vicinity. Unstable
sediments simplify and, therefore, degrade stream habitats for many aquatic species.
The most important effects of excessive and unscientific Riverbed sand mining on aquatic
habitats are bed degradation and sedimentation, which can have substantial negative
effects on aquatic life. The stability of sand-bed streams depends on a delicate balance
between stream flow, sediment supplied from the watershed, and channel form. Mining-
induced changes in sediment supply and channel form disrupt channel and habitat
development processes. Furthermore, movement of unstable substrates results in
downstream sedimentation of habitats. The affected distance depends on the intensity of
mining, particles sizes, stream flows, and channel morphology.
Channel widening causes swallowing of the streambed, producing braided flow or
subsurface intersand flow in riffle areas, hindering movement of fishes between pools.
Channel reaches become more uniformly shallow as deep pools fill with sand and other
sediments, reducing habitat complexity, riffle-pool structure, and numbers of large
predatory fishes.
All such impacts can be reduced by following scientific mining practices and mitigation
measures as restricted.
Mitigation measures
Sand extraction operations will be managed to avoid or minimize damage to stream/river
banks and riparian habitats
• Sand extraction in vegetated riparian areas will be avoided.
• Undercut and incised vegetated banks will not be altered.
• Large woody debris in the riparian zone will be left undisturbed or replaced when
moved and not be burnt.
• Sand stockpiles, overburden and/or vegetative debris will not be stored within the
riparian zone.
• It is essential that overburden is evenly redistributed over exposed areas as soon as
possible after the operation has been completed for faster revegetation.
• Operation and storage of heavy equipment within riparian habitat will be restricted.
• Access roads will not encroach into the riparian zones
No exotic species will be introduced by the RBM project activity & associated persons at
all.
As the mining will not be done beyond the stipulated limit, so the chances of river mouth
widening, bank widening will be negligible.
![Page 77: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/77.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP-Section – IV Anticipated Environmental Impact
and Mitigation Measures
Page 16/IV
The river channel will get shallowed due to sediment deposition which will lead to
widening of the river channel and inturn cause submergence of the nearby areas. Thus,
mining in a scientific and systematic way will reduce such impending effects.
Thus there is a requirement to establish a stable ecosystem with both ecological and
economic returns. Minimization of soil erosion and dust pollution enhances the aesthetic
value of the core and the buffer zone. To achieve this, it is advised to have planned
increase in the area of green cover of plantation and green belts activities, wherever
possible. The basic objectives of plantations are as follows:
• Improvement of Soil quality,
• Quick vegetative cover to check soil erosion,
• Improvement in mining site stability,
• Conservation of biological diversity of plants, birds and animals,
• As dust receptor and dust filter, this is likely to be produced during mining.
4.6 TRAFFIC ANALYSIS
Traffic analysis is carried out by understanding the existing carrying capacity of the roads
near to the project site and the connecting main roads in the area. Then depending on the
capacity of the mine, the number of trucks that will be added to the present scenario will be
compared to the carrying capacity.
Table 4.4(i) : Existing Traffic Scenario & LOS
Road V C Existing V/C Ratio LOS
Near Village Raipur Araian 75 300 0.25 B
NH-1 intersection 126 700 0.18 A
V= Volume in PCU’s/hr & C= Capacity in PCU’s/ hr
The existing Level of Service “B” and “A”i.e.very good and excellent
V/C LOS Performance
0.0 - 0.2 A Excellent
0.2 - 0.4 B Very Good
0.4 - 0.6 C Good / Average / Fair
0.6 - 0.8 D Poor
0.8 - 1.0 E Very Poor
Note: Capacity as per IRC: 106-1990 page no 11 table-2 for arterial road/ Highways
![Page 78: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/78.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP-Section – IV Anticipated Environmental Impact
and Mitigation Measures
Page 17/IV
During Mine operation
Total Capacity of mine : 1, 61,820 tonnes per annum
No. of working days : 250 days
Truck Capacity : 20 tonnes
No. of trucks deployed : 33 trucks
Working Hours per day : 8 hours
No. of trucks deployed/hr : 4 trucks
Increase in PCU/hr : 24
Table 4.4(ii): Modified Traffic Scenario & LOS
Road V C Modified
V/C Ratio LOS
Near Village Raipur Araian 99 300 0.33 B
NH-1 intersection 150 700 0.21 B
Results
From the above analysis it can be seen that the V/C ratio is likely to change to 0.33 and 0.21
with LOS both being “B” which is ‘very good’, as per classification. So the additional load on
the carrying capacity of the concerned roads is not likely to have any significant adverse
affect.
4.7 STATUTORY REQUIREMENTS
It is accepted that effective resource management cannot be done in isolation. The
Department therefore vigorously pursues approaches towards coordination and integration
where possible, so as to lead to coordinated regulatory systems.
A regulatory system consists of both statutory and non-statutory components. In the
Sectoral-specific strategy for prospecting and mining, the Department participates within an
integrated environmental management system which is administered in terms of the Acts
and Rules. Other Acts dealing with matters relating to the conservation and protection of the
environment and which a holder of a mining authorization must also take cognizance of,
include inter alia, the following:
• The Mines Act, 1952
• The Mines and Mineral (Development and Regulation) Act, 1957
• Mines Rules, 1955
• Mineral Concession Rules, 1960
![Page 79: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/79.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP-Section – IV Anticipated Environmental Impact
and Mitigation Measures
Page 18/IV
• Mineral Conservation and Development Rules, 1988
• State Minor Mineral Concession Rules, Punjab 1964
• Metalliferrous Mines Regulations 1961
• Granite Conservation and Development Rule, 1999
• The Water (Prevention and Control of Pollution) Act, 1974
• The Air (Prevention and Control of Pollution) Act, 1981
• The Environment (Protection) Act, 1986
• The Forest (Conservation) Act, 1980
• The Wildlife (Protection) Act, 1972
4.8 Matrix for EIA
Table 4.5 (i): Qualitative Matrix
Items Nature of Likely Impacts
Adverse Beneficial
ST LT R IR L ST LT SI N
Air Quality √ √
Surface Water Quality √ √ √
Ground Water * * * * * * * * *
Land Environment √ √ √
Noise √ √
Soil
Forests √
Flora & Fauna √ √ √
Agriculture √
Socio Economic √ √
ST: Short Term LT: Long Term R: Reversible IR: Irreversible
L: Local SI: Significant N: Neutral *: Negligible
Table 4.5 (ii): Quantitative Matrix
![Page 80: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/80.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP-Section – IV Anticipated Environmental Impact
and Mitigation Measures
Page 19/IV
Items With Project
Without Project With EMP Without EMP
Air Quality -2 -6 -10
Surface Water
Quality
-2 -4 -6
Ground Water 0 0 -2
Land Environment +8 -2 -10
Noise -2 -6 -6
Flora +8 -2 -10
Fauna -2 -6 -6
Agriculture 0 0 0
Socio Economic +8 +4 0
Total +16 -22 -50
***************
![Page 81: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/81.jpg)
Project Name:Raipur Araian Sand Mine, Punjab. Final EIA/EMP Section-V: Environmental Monitoring Programme
Page 1/V
SECTION-V
ENVIRONMENTAL MONITORING PROGRAMME
INDEX
S. No. CONTENTS Page No.
5.0 INTRODUCTION 2/V
5.1 PROPOSED SET UP 2/V
5.2 MONITORING SCHEDULE AND PARAMETERS 3/V
![Page 82: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/82.jpg)
Project Name:Raipur Araian Sand Mine, Punjab. Final EIA/EMP Section-V: Environmental Monitoring Programme
Page 2/V
5.0 INTRODUCTION
Success of any post-project environmental monitoring programme depends upon the
efficiency of the organizational set up responsible for the implementation of the programme.
Regular monitoring of the various environmental parameters is also necessary to evaluate
the effectiveness of the management programme so that the necessary corrective
measures can be taken in case there are some drawbacks in the proposed programme.
Since environmental quality parameters at work zone and surrounding areas are important
for maintaining sound operating practices of the project in line with conformity with
environmental regulations, the post project monitoring work, therefore, forms a part of EMP.
5.1 PROPOSED SET UP
Keeping the utility of monitoring results in the implementation of the environmental
management program in view, an organizational chart has been proposed, headed by
General Manager as shown in Fig. 5.1.
The said team will be responsible for:
a. Collecting water and air samples from surrounding area and work zone
monitoring for pollutants.
b. Analyzing the water and air samples.
c. Implementing the control and protective measures.
d. Co-coordinating the environment related activities within the project as well as
with outside agencies.
e. Collecting statistics of health of workers and population of surrounding villages.
f. Monitoring the progress of implementation of environmental management
program. Greenbelt development, etc.
The laboratory will be suitably equipped for sampling/testing for various environmental
pollutants.
![Page 83: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/83.jpg)
Project Name:Raipur Araian Sand Mine, Punjab. Final EIA/EMP Section-V: Environmental Monitoring Programme
Page 3/V
Fig. 5.1 Organisation for implementation of Control Measures
5.2 MONITORING SCHEDULE AND PARAMETERS
Air Quality Monitoring
Air Quality monitoring is essential for evaluation of the effectiveness of abatement
programmes and to develop appropriate control measures. The project proponent will
monitor ambient air quality in and around the proposed sand mining project at a frequency
mentioned in the monitoring schedule for various parameters and take appropriate air
pollution control measures in order to ensure that the concentration of PM10, SO2 and NOX
are within limits
ENVIRONMENT MANAGEMENT
CELL
Implementation of Control Measures
Review with General Manager
Report submission and correspondence
with concerned State/ Central Government
Environmental Monitoring
Environmental Officer
Head Environment
• Liaison with MOEF/SPCB
• Implementation of EMP
• Allotment of Daily jobs
• Field visits
• Analysis of samples-Air,
water, soils etc
• Environment Budgets &
sanctions
• Review Implementation
Lab assistant
Senior Chemist
![Page 84: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/84.jpg)
Project Name:Raipur Araian Sand Mine, Punjab. Final EIA/EMP Section-V: Environmental Monitoring Programme
Page 4/V
Water Quality monitoring
Water quality monitoring involves periodical assessment of quality of surface water and the
ground water near the mining project. Surface water samples will be analyzed for all the
parameters as per EPA, 1986 and ground water samples will be analyzed for all the
parameters as per IS-10500.
Noise Level Monitoring
Noise level monitoring will be done for achieving the following objectives:
a) To compare sound levels with the values specified in noise regulations
b) To determine the need and extent of noise control measures of various noise generating
sources
Noise level monitoring will be done at the work zone to assess the occupational noise
exposure levels. Noise levels will also be monitored at the noise generating sources like
mineral handling arrangements, vehicle movements and also nearby villages for studying
the impact due to higher noise levels for taking necessary control measures at the source.
MONITORING SCHEDULE AND PARAMETERS:
Table 5.1 Monitoring Schedule and Parameters
S. No Description of Parameters Schedule and Duration of Monitoring
1 Air Quality: a) In the vicinity of the mine b) In the vicinity of the transportation network
24 hourly samples twice a week for one month in each season except monsoon season
2 Water Quality near or at the site: a) Surface water quality b) Ground water quality
Once a season for 4 seasons in a year
3 Ambient Noise Level Twice a year for two years & then once a year
4 Soil Quality Once in two years on project monitoring area
5 Inventory of Flora(tree plantation, survival etc) & Fauna
Once in two years on project monitoring area
6 Socio-economic condition of local, population, physical survey
Once in 3 years
*********
![Page 85: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/85.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section –VI Additional Studies
Page 1/VI
SECTION-VI
ADDITIONAL STUDIES
INDEX
S. No CONTENTS Page No.
6.0 PUBLIC CONSULTATION 2/VI
6.1 HAZARD IDENTIFICATION AND RISK ASSESSMENT
METHOLODOGY
4/VI
6.2 POTENTIAL HAZARD & ‘ALARP’ CONDITION 9/VI
6.3 RISK PRIORITISATION BASED ON HAZARDS 9/VI
6.4 ADDITIONAL MITIGATION MAJORS TO BRING HAZARDS
UNDER “ALARP” ZONE
12/VI
6.5 NATURAL RESOURCE CONSERVATION 13/VI
6.6 SOCIAL IMPACT ASSESMENT, REHABILITATION &
RESETTLEMENT (R&R) ACTION PLAN
14/VI
6.7 SUGGESTIONS 27/VI
6.8 CONCLUSIONS 28/VI
![Page 86: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/86.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section –VI Additional Studies
Page 2/VI
6.0 PUBLIC CONSULTATION
The public consultation for this project was held on 6th August, 2014. The records of the
proceedings are attached at Annexure III. The questions which were raised, the reply of
the project proponent/panel member and the action plan is given below:
S.
No
Name of the
Person
Questions/query/statement of the
person
Reply/clarification given by
the company/panel member
1. Sh. Narinder Singh,
Vill, Rasipur Araian,
Distt Jalandhar.
• How much amount should be
paid in case of personal/village
property to the villagers?
• Mining is being carried out
illegally and during
transportation the means of
transport are not covered
properly from the tops.
• The speed of vehicles used
during transportation of sand
mining is very high and do
some needful measures to
control it.
• Sh. Surjit Singh, G.M DIC
answered that according to
mining rule the 1/3 amount of
royalty should be paid in
case of personal/villages
property to the village
property to the villagers as
well as employment to the
villagers were also given.
• Sh. K.N Sharma answered
that mining should be carried
out scientifically and during
transport are covered
properly from the tops.
• Sh. Pritam Singh, PCS,
A.D.M, Jalandhar answered
that your suggestion has
been noted and send to
concerned department for
action.
2. Sh. Kulwinder
Ram, Vill Raipur
Araian, Distt.
Jalandhar.
• Whar are rules made for earth
mining in case of personal
property of villagers.
• Sh. Surjit Singh, G.M DIC
answered that no royalty has
been charged for earth
mining in case of personal
property.
3. Sh. Daljit Singh Vill
Raipur Araian,
Distt. Jalandhar.
• The means of transport used is
sand mining are passed
through
• Sh. K.N Sharma answered
that after introducing this
project the means of
transport used in sans
mining only in systematically
way which is approved by
revenue department.
4. Sh. Satpal
headmaster village
Raipur Araian,
Distt. Jalandhar
• The amount preserved in this
project for the up-gradation of
social economic life of the
villagers is being given to them.
• Sh. K.N Sharma answered
that the amount preserved in
this project for the up
gradation of social economic
life of the villagers will be
given as per provision.
![Page 87: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/87.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section –VI Additional Studies
Page 3/VI
As would be seen, the points raised by the public mainly pertain to any or many of the
following:
1. Existing haphazard state of mining.
2. Their annoyance to the state of the existing environment.
3. Problem of drinking water level having gone very deep due to the unchecked depth of
mining, resulting in drying up of their hand pumps in the homes.
4. The dilapidated condition/state of the roads on which the Dumpers/Trolleys pass
through.
5. The dust pollution created by the falling dry sand from the dumpers/trucks/trolleys
moving on uneven roads, which gets crushed further with the movement of the loaded
vehicles and easily become airborne.
6. The public is dissatisfied with the prevailing dust pollution being created when the
process of dry crushing instead of wet crushing of stones/gravel into bajri is resorted.
They attribute this heavy dust pollution to mining, because presently the mining and
the crushing is done by the same party, difficult to differentiate.
7. The nuisance created by the noise of DJ during night transportation of sand.
8. Heavy dust pollution in the air, which enters their houses.
9. Their children not able to pass the roads because of the narrowness of the roads and
movement of large 6 to 18 tyres dumpers/trucks.
10. The problem being faced by them from the sand/gravel mafia operating which
charges them when any one is mining sand.
11. Non availability or petty compensation to owners of land.
12. Extent of prevailing unauthorized/unregulated mining, not following any of the
imposed restrictions on mining under approved mine plan.
13. A number of people said the mining activity and the crushing activity going in their
area has in fact provided them with jobs thereby they have been able to sustain their
living and rearing up of their families, though under a difficult environment
14. The general opinion of the public was that if it is ensured that the mining will be done
in a scientific way as described, they will support the project.
The initial public concern was particularly about the existing state of environment. As
regards the new project all the persons who made queries did not express dissatisfaction
and wherever they raised points about the proposed project they were convincingly
replied with the provisions of suitable measures in the proposed project in respect of all
environmental aspects and mitigative measures to reduce the environment impact. The
moment they believed that the same will happen in due course their opinion changed
and when they have become known about the scope of employment potential for the
public and adequate compensation available to all the owners whose land will be used
![Page 88: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/88.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section –VI Additional Studies
Page 4/VI
for mining many agreed and wanted the project to come in their area which felt would
ultimately help in uplifting the standard of their living and life.
6.1 HAZARD IDENTIFICATION AND RISK ASSESSMENT METHODOLOGY
A) RISK
Risk concerns the deviation of one or more results of one or more future events from
their expected value.
Tolerable risk: Risk which is accepted in a given context based on the current values
of society
Protective measure: The combination of risk reduction strategies taken to achieve at
least the tolerable risk. Protective measures include risk reduction by inherent safety,
protective devices, and personal protective equipment, information for use and
installation and training.
Severity: Severity is used for the degree of something undesirable.
Risk Analysis: A systematic use of available information to determine how often
specified events may occur and the magnitude of their likely consequences.
Risk related to the
considered hazard
is a “function” of
Severity of the
possible harm that
can result from the
considered hazard
PROBABILITY OF OCCURRENCE OF THE
Frequency and
duration of
exposure
Probability of
occurrence of
hazardous event
Possibility of
avoiding or
limiting the harm
![Page 89: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/89.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section –VI Additional Studies
Page 5/VI
The different steps of risk assessment procedure are as given below:
Step I: Hazard Identification
The purpose of hazard identification is to identify and develop a list of hazards for each job
in the organization that are reasonably likely to expose people to injury, illness or disease
if not effectively controlled. Workers can then be informed of these hazards and
controls put in place to protect workers prior to them being exposed to the actual hazard.
Step II: Risk Assessment
Risk assessment is the process used to determine the likelihood that people exposed to
injury, illness or disease in the workplace arising from any situation identified during
the hazard identification process prior to consideration or implementation of control
measures.
Risk occurs when a person is exposed to a hazard. Risk is the likelihood that exposure
to a hazard will lead to injury or health issues. It is a measure of probability and potential
severity of harm or loss.
Step III: Risk Control
Risk control is the process used to identify, develop, implement and continually review
all practicable measures for eliminating or reducing the likelihood of an injury,
illness or diseases in the workplace.
Step IV: Implementation of risk controls
All hazards that have been assessed should be dealt in order of priority in one or more
of the following hierarchy of controls
The most effective methods of control are:
i. Elimination of hazards
ii. Substitute something safer
iii. Use engineering/design controls
iv. Use administrative controls such as safe work procedures
v. Protect the workers i.e. By ensuring competence through supervision and training, etc.
Each measure must have a designated person and date assigned for the
implementation of controls. This ensures that all required safety measures will be
completed.
Step V: Monitor and Review
Hazard identification, risk assessment and control are an on-going process.
Therefore regularly review the effectiveness of your hazard assessment and control
measures. Make sure that you undertake a hazard and risk assessment when there is
![Page 90: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/90.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section –VI Additional Studies
Page 6/VI
change to the workplace including when work systems, tools, machinery or equipment
changes. Provide additional supervision when the new employees with reduced skill
levels or knowledge are introduced to the workplace.
B) RISK ANALYSIS
The risk assessment portion of the process involves three levels of site evaluation:
a) Initial Site Evaluation,
b) Detailed Site Evaluation,
c) Priority Site Investigations and Recommendations.
The risk assessment criteria used for all levels of site evaluation take into account two
basic factors:
• The existing site conditions
• The level of the travelling public's exposure to those conditions.
The Initial Site Evaluation and Detailed Site Evaluation both apply weighted criteria to
the existing information and information obtained from one site visit. The Initial Site
Evaluation subdivides the initial inventory listing of sites into 5 risk assessment site groups.
The Detailed Site Evaluation risk assessment is then performed on each of the three
highest risk site groups in order of the group priority level of risk. The result of the
Detailed Site Evaluation process is a prioritized listing of the sites within each of the
three highest risk site groups.
Risk analysis is done for:
� Forecasting any unwanted situation
� Estimating damage potential of such situation
� Decision making to control such situation
� Evaluating effectiveness of control measures
C) ACCEPTABLE RISK
Risk that is acceptable to regulatory agency and also to the public is called acceptable
risk. There are no formally recognized regulatory criteria for risk to personnel in the
mining industry. Individual organizations have developed criteria for employee risk and
the concepts originally arising from chemical process industries and oil and gas
industries. Because of the uncertainties linked with probabilistic risk analysis used for
quantification of the risk levels the general guiding principle is that the risk be reduced
to a level considered As Low as Reasonably Practicable (ALARP). The risk
![Page 91: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/91.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section –VI Additional Studies
Page 7/VI
acceptability criteria are given in following Table. It can be seen that there are three
tiers:
a. A tolerable region where risk has been shown to be negligible and comparable with
everyday risks such as travel to work.
b. A middle level where it is shown the risk has been reduced to As Low As Reasonably
Practicable level and that further risk reduction is either impracticable or the cost is
grossly disproportionate to the improvement gained. This is referred as the ALARP
region.
c. An intolerable region where risk cannot be justified on any grounds. The ALARP region
is kept sufficiently extensive to allow for flexibility in decision making and allow for the
positive management initiatives which may not be quantifiable in terms of risk
reduction.
The risk acceptability criteria are given in following table:
1 Risk unacceptance and must be reduced. The actions
may include equipments and people or procedural
measures. If risk cannot be reduced to ALARP level,
operating philosophy must be fundamentally reviewed
by the management.
Intolerable Region
2 Efforts must be made to reduce risk further and to as
low as reasonably practicable, without expenditure that
is grossly disproportionate to the benefit gained
ALARP Region
(As Low as Reasonably
Practicable)
3 Risk level is so low as to not require actions to reduce
its magnitude further. Tolerable Region
Risk Likelihood Table for Guidance (TABLE -1)
Step 1: Assess the Likelihood Step 2: Assess the Consequences
L1 Happens every
time we operate
Almost
Certain
Common or
repeating
occurrence
C1 Fatality Catastrophic
L2 Happens regularly
(often)
Likely Known to have
occurred "has
happened"
C2 Permanent
disability
Major
![Page 92: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/92.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section –VI Additional Studies
Page 8/VI
A logical systematic process is usually followed during a qualitative risk assessment to identify
the key risk events and to assess the consequences of the events occurring and the likelihood
of their occurrence (TABLE-2)
RISK RATING:
• HIGH RISK 1-6
• MEDIUM RISK 7-15
• LOW RISK 16-25
6.2 POTENTIAL HAZARDS & ‘ALARP’ CONDITION
Mining and allied activities are associated with several potential hazards and risk to
both the employees and the public at large. A worker in a mine should be able to work
under “ALARP” conditions (as stated above), which are adequately safe and healthy.
At the same time the environmental conditions should be such as not to be impair his
working efficiency. This is possible only when there is adequate safety in mines.
L3 Has happened
(occasionally)
Possible Could occur or
"heard of it
happening"
C3 Medical/hospi
tal or lost time
Moderate
L4 Happens
irregularly (almost
never)
Unlikely Not likely to
occur
C4 First aid or no
lost time
Minor
L5 Improbable
(never)
Rare Practically
impossible
C5 No injury Insignificant
Risk Rank
Likelihood x Consequence
L1
Almost certain
L2
Likely
L3
Possible
L4
Unlikely
L5
Rare
C1
Catastrophic 1 2 4 7 11
C2
Major 3 5 8 12 16
C3
Moderate 6 9 13 17 20
C4
Minor 10 14 18 21 23
C5
Insignificant 15 19 22 24 25
![Page 93: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/93.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section –VI Additional Studies
Page 9/VI
6.3 RISK PRIORITISATION BASED ON HAZARDS
There are various factors, which can create unsafe working conditions/hazards in
mining of minor minerals from river bed.
The key risk (hazard x probability) event rating associated with sand bed mining and to
assess its consequences of such events occurring and the likelihood based on above
Table-2 are as:-
The Risk rating of such hazards is as follows:
a) Inundation / Flooding (C1 xL3=4)
b) Quick Sand Condition (C2 x L3=8)
c) Drowning.(C5 xL5=25)
d) Accident due to vehicular movement.(C3 xL3=13)
e) Accident during sand loading, transporting and dumping=14.
(i.e., C4 xL2=14)
6.3.1 Accident during sand/mineral loading, transportation and dumping
The risk rating assigned to this activity is assigned as “14 i.e. it is likely event with
minor consequences”, as frequency of this operation is more but the
predicted/assumed intensity(Based on experience) is less like minor cuts, abbration,
fall due to river bank collapse & falling of cattles, if not under proper supervision to
bring under ALARP ZONE.
a. The minerals are loaded in the trucks using hand shovels. There is possibility of injury
in the hands during loading with shovels.
b. There is possibility that the workers standing on the other side of loading may get injury
due to over thrown sand with pebbles.
c. There is possibility of workers getting injured during opening of side covers to facilitate
loading.
d. There is possibility of riverbank collapse.
e. There are chances of falling of cattle/children into pits in river bed by overlooking of
fenced area near worksite or improper supervision.
6.3.2 Accident due to vehicular movement
The risk rating assigned to this activity is assigned as 13 i.e., it is possible event with
moderate consequences as frequency of this operation is more but the
predicted/assumed intensity(Based on experience) is less like minor cuts, bodily injury
due to reckless or untrained driver. However, a strict control to be exercised to deploy
trained drivers with valid driving license with a helper. A strict supervision/control to be
![Page 94: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/94.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section –VI Additional Studies
Page 10/VI
exercised to avoid drunken driving or driving by unauthorized person to bring under
ALARP ZONE.
The minerals loaded in trucks are being sent to through public roads.
a. All possibilities of road accidents are possible due to rash driving.
b. Accident may also occur during movement in the mine, in case pathway is not
compacted suitably or movement is at the embankment.
c. There are possibilities that due to overloading. Some pebbles or big boulder may injure
the passerby public. In case Traffic & vehicle load bearing licensed capacity is
neglected.
6.3.3 Inundation/Flooding
The risk rating assigned to this activity is assigned as 4(C1 xL3=4) i.e., it is only
possible, if warnings are neglected and work started without assessment of the river
bed condition specially during monsoon season ,the event will be catastrophic with
major consequences as frequency of this operation is possible. However the event has
to be brought under ‘ALARP’ Zone by strict supervision based on river water and other
metrological data.
a. The possibility of inundation/flooding of the mines are very high during monsoon
or during heavy rains as the mine area lies in the riverbed.
b. There is danger to the trucks and other machineries due to flooding.
c. There is danger to the workers working in the mines.
Inundation or flooding is expected and beneficial for these mines as during this time
only the mineral reserve gets replenished.
6.3.4 Quick Sand Condition
The risk rating assigned to this activity is assigned as 8 (C2 x L3 =5) i.e., it is likely
event with major consequences as frequency of this operation is likely but the
predicted/assumed intensity (Based on experience) is major.
Hence data of water table must be collected and the mining work must be above the
water table (about 1.5 m above to bring under ALARP ZONE.) to avoid dangerous
condition to vehicles playing over sand dunes.
This condition occurs when the working crosses the water table at a certain depth and
the permeability of the strata is very high. This condition occurs when the effective
stress in the sand becomes zero due to influx of water i.e.
![Page 95: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/95.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section –VI Additional Studies
Page 11/VI
i = icr = y’/yw-;
Where, i = Hydraulic gradient,
icr = Critical Hydraulic gradient,
y’ = submerged unit weight,
yw = unit weight of water.
This creates danger condition to the trucks and other machineries plying over the sand
dunes on the river banks.
6.3.5 Drowning
The risk rating assigned to this activity is assigned as 25 i.e., it is insignificant due to
dry season mining.
There are no possibilities of drowning in the river, since mining operations are carried
out only in the dry seasons. All mining activities will be stopped during the monsoon
season.
6.4 ADDITIONAL MITIGATION MEASURES TO BRING HAZARDS UNDER “ALARP”
ZONE
6.4.1 Measures to Prevent Accidents during Loading
1. The truck should be brought to a lower level so that the loading operation suits to the
ergonomic condition of the workers.
2. The loading should be done from one side of the truck only.
3. The workers should be provided with gloves and safety shoes during loading.
4. Opening of the side covers (pattas) should be done carefully and with warning to
prevent injury to the loaders.
5. Operations during daylight only.
6. No foreign material should be allowed to remain/spill in river bed and catchment area,
or no pits/pockets are allowed to be filled with such material.
7. Stockpiling of harvested material on the river bank should be avoided.
6.4.2 Measures to Prevent Accidents during Transportation
1. All transportation within the main working should be carried out directly under the
supervision and control of the management.
2. The Vehicles must be maintained in good repairs and checked thoroughly at least once
a week by the competent person authorized for the purpose by the Management.
![Page 96: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/96.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section –VI Additional Studies
Page 12/VI
3. To avoid danger while reversing the trackless vehicles especially at the embankment
and tipping points, all areas for reversing of lorries should be made man free as far as
possible .
4. A statutory provision of the fences, constant education, training etc. will go a long way
in reducing the incidents of such accidents.
5. Generally, overloading should not be permitted.
6. The truck should be covered and maintained to prevent any spillage.
7. The maximum permissible speed limit should be ensured.
8. The truck drivers should have proper driving license.
6.4.3 Measures to prevent Dangerous Incidents during Inundation/Flooding
Inundation of flooding is expected and beneficial for these mines as during this time
only the mineral reserve gets replenished.
1. During monsoon months and heavy rains the mining operations are ceased.
2. There should be mechanism/warning system of heavy rains and discharges from the
upstream dams.
6.4.4 Measures to Prevent Quick Sand Condition
1. The only way to avoid quick sand condition is by avoiding mineral lifting below water
table.
2. The critical hydraulic gradient (icr) should be maintained at less than 1 to prevent high
artesian pressure in a coarse sand area.
3. At least 0.5 m sand bed should be left in-situ while harvesting sand from riverbed.
6.4.5 Measure to Prevent Drowning
1. The mining should be done under strict supervision and only during the dry season.
2. Deep water areas must be identified.
3. No go zones should be clearly marked and made aware to the mine workers.
6.5 NATURAL RESOURCE CONSERVATION
Mining at the concave side of the river channel should be avoided to prevent bank
erosion. Similarly meandering segment of a river should be selected for mining in such
a way as to avoid natural eroding banks and to promote mining on naturally building
(aggrading) meander components.
![Page 97: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/97.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section –VI Additional Studies
Page 13/VI
6.6 SOCIAL IMPACT ASSESSMENT, REHABILITATION & RESETTLEMENT (R&R)
ACTION PLAN
There is no resettlement or rehabilitation involved in the project being on meandering
course of river. However a detail Socio Economic Assessment has been performed,
which is given below
Introduction
In this section of the report an attempt has been made to assess the impact of
the proposed river bed mining project at village Raipur Araian, Jalandhar, on
Socio-economic aspect of the study area. The various attributes that have been
taken into account are population composition, employment generation,
occupational shift, household income, consumption pattern, ethnic issue and law
& order problem.
The objectives of the socio-economic impact assessment are as follows:
a) To study the socio-economic status of the people living in the study area of the
proposed mining project.
b) To assess the impact of the project on socio-economic environment in the study
area.
c) To assess the impact of the project on Quality of life of the people in the study
area.
d) To evaluate the community development measures proposed to be taken up by
the project proponent, if any.
e) To recommend Community Development measures needs to be taken up in the
study area
Approach & Methodology
a) A mixture of both quantitative and qualitative approach has been adopted in the
current socio-economic study.
b) The study has been conducted based on primary and secondary data. While
primary data has been collected through a sample survey of selected
households, the secondary data has been collected from the administrative
records of the Government of Punjab, Census 2001, district hand books and from
the Punjab government portal.
c) The details regarding population composition, number of literates, workers etc
have been collected from secondary sources and analyzed. Also village/city/town
wise details regarding amenities available in the study area have been collected
from secondary sources and analyzed.
![Page 98: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/98.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section –VI Additional Studies
Page 14/VI
d) Two stage sampling design has been adopted to select the sampling units. The
first stage units are census villages in the rural areas and towns/cities in urban
areas. The ultimate stage units are households in the selected villages and
towns/cities. Simple Random Sampling without Replacement (SRSWOR) has
been adopted to select the sampling units.
e) Estimation of various parameters has been made based on sample data and
bottom top approach has been adopted.
f) On the basis of a preliminary reconnaissance survey, two questionnaires were
developed to make it suitable to fulfill the objectives of the study. The
questionnaires contained both open ended and close ended questions
g) The data collected during the above survey was analyzed to evaluate the
prevailing socio-economic profile of the area.
h) Based on the above data, impacts due to mining operation on the community
have been assessed and recommendations for improvement have been made.
Concept & Definition of terms used
a) Study Area: The study area, also known as impact area has been defined as
the sum total of core area and buffer area with a radius of 10 Kilometers from the
periphery of the core area. The study area includes all the land marks both
natural and manmade, falling therein.
b) QoL: The Quality of Life (QoL) refers to degree to which a person enjoys the
important possibilities of his/her life. The ‘Possibilities’ result from the
opportunities and limitations, each person has in his/her life and reflect the
interaction of personal and environmental factors. Enjoyment has two
components: the experience of satisfaction and the possession or achievement
of some characteristic.
c) Household: A group of persons who normally live together and take their
meals from a common kitchen are called a household. Persons living in a
household may be related or unrelated or a mix of both. However, if a group of
related or unrelated persons live in a house but do not take their meals from the
common kitchen, then they are not part of a common household. Each such
person is treated as a separate household. There may be one member
households, two member households or multi-member households.
d) Sex Ratio: Sex ratio is the ratio of females to males in a given population. It is
expressed as 'number of females per 1000 males'.
e) Literates: All persons aged 7 years and above who can both read and write with
understanding in any language are taken as literate. It is not necessary for a
![Page 99: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/99.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section –VI Additional Studies
Page 15/VI
person to have received any formal education or passed any minimum
educational standard for being treated as literate. People who are blind but can
read in Braille are also treated as literates.
f) Literacy Rate: Literacy rate of population is defined as the percentage of
literates to the total population aged 7 years and above.
g) Labour Force: The labour force is the number of people employed and
unemployed in a geographical entity. The size of the labour force is the sum total
of persons employed and unemployed. An unemployed person is defined as a
person not employed but actively seeking work. Normally, the labour force of a
country consists of everyone of working age (commencing from 14 to 16 years)
and below retirement (around 65 years) that are participating workers, that is
people actively employed or seeking employment. People not counted under
labour force are students, retired persons, stay-at home people, people in
prisons, permanently disabled persons and discouraged workers.
h) Work: Work is defined as participation in any economically productive activity
with or without compensation, wages or profit. Such participation may be physical
and/or mental in nature. Work involves not only actual work but also includes
effective supervision and direction of work. The work may be part time or full time
or unpaid work in a farm, family enterprise or in any other economic activity.
i) Worker: All persons engaged in 'work' are defined as workers. Persons who are
engaged in cultivation or milk production even solely for domestic consumption
are also treated as workers.
j) Main Workers: Those workers who had worked for the major part of the
reference period (i.e. 6 months or more in the case of a year) are termed as Main
Workers.
k) Marginal Workers: Those workers who did not work for the major part of the
reference period (i.e. less than 6 months) are termed as Marginal Workers
l) Work participation rate: The work participation rate is the ratio between the
labour force and the overall size of their cohort (national population of the same
age range). In the present study the work participation rate is defined as the
percentage of total workers (main and marginal) to total population.
![Page 100: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/100.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section –VI Additional Studies
Page 16/VI
Figure 6.1: Socio Economic survey of study area
Findings of the study:
Study Area:
The field investigation has revealed that the study area of the proposed river bed mining
project is spread over in Phillor sub-district of district Jalandhar, Punjab. The entire study
area is rural as no city or town is located within its periphery. The total number of villages
located in the study area is 45 and all of them are inhabitant villages. The proposed
mining project is located at village Raipur Araian.
The Table and Figure presented below provides Broad Land use pattern in Study Area:
![Page 101: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/101.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section –VI Additional Studies
Page 17/VI
Table 6.1
Broad Land use pattern in Study Area
S. No. Description Estimated Area (in
Hectares)
Percentage share in total
area
(1) (2) (3) (4)
1 Forest 5.3 0.02
2
Agriculture
a) Irrigated Area 27731 88.3
b) Un irrigated Area 21 0.1
c) Culturable waste 187 0.59
Total for Agriculture 27939 89.0
3
Area not available for
cultivation 3456 11.0
a) Mining leased area 17.98* 0.057
b) Other Area 3438.2 10.95
Total 31400 100
*Actual mine area proposed for lease
Figure 6.2
Broad Land use Pattern in Study Area (%)
0.02
88.32
0.07
0.59
11.01
Broad Land Use Pattern In Study Area
Forest
Irrigated Area
Un-irrigated Area
Cultivable waste
Area not in used for agriculture including mine leased area
![Page 102: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/102.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section –VI Additional Studies
Page 18/VI
Demographic composition:
Population
According to Census 2001, the total population of the identified villages in the study area
is 40638. As there is no urban area, the entire population of the study area consists of
rural folks. The area is comparatively thinly populated as the density of population is only
340 persons per square kilometer. Of the total population 12.8 percent belongs to 0-6
age group. Further, of the total population 52.5 percent are male and the remaining 47.5
percent are female. The overall sex ratio has been worked out to 904 females per 1000
males, which is less than the national average of 933 females per 1000 males. The sex
ratio is lowest (500) at village Giddarpindi and highest (1090) at village Sadarpur.
Furthermore, 34.9 percent of the total population belongs to Schedule Caste community.
There is no Schedule Tribe population in the study area, as per Census 2001.
Number of households and household size
The entire population of the study area has been grouped into 7349 households and the
average household size is 5.5. The household size is highest (6.8) at village Hardo
Sangha and lowest (4.5) at village Giddarpindi.
Number of Literates and Literacy rate
The total number of literates in the study area has been worked out to 24770, which is
around 61 percent of the total population. However, the overall literacy rate increases to
69.9 percent when the population under 6 years of age is taken off from the total
population. The literacy rate of male population has been worked out to 75.7 percent as
against 63.5 percent for female, creating a gender gap of 12.2 percent. The gender gap
in literacy rates varies from a minimum of 4.3 percent in village Gadara to a maximum of
39.8 percent in village Bhundri.
Number of Workers and work participation rate
The total number of workers in the study area is 14390, which is 35 percent of the total
population. Among the total workers 86.4 percent are main workers and the remaining
13.6 percent are marginal workers. The percentage of male in the main workers is 86.5
percent, while it is 48.8 percent in the case of marginal workers. On the other hand, the
percentage share of female in the main workers is only 13.5 percent; it is 51.2 percent in
the case of marginal workers. This indicates that the main workers are dominated by
male population. However, female has a fair share in the marginal workers.
The classification of workers based on occupation reveals that around 56.2 percent of
the total workers are Agricultural workers. However, its share in the total population is
only 19.9 percent. This indicates that people in the study are not solely depended upon
![Page 103: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/103.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section –VI Additional Studies
Page 19/VI
agriculture. There has been an occupational shift of population from agriculture to other
sectors of the economy, without making a negative impact on agricultural production and
its yield rate. Further, among the agricultural workers 60.9 percent are cultivators and the
remaining 39.1 percent are agricultural labours who do not possess land but cultivate the
land of big farmers as wage earners. The field investigation has revealed that these
agricultural labours are migrants from distant states like Bihar and U.P.
The percentage share of household industrial workers in the total workers is 2.4 percent.
Though over the years industrial development in the state has been spectacular, there
exists a declining trend in the number of household industrial workers in the total work
force. Deep probe made during field survey has revealed that low percentage of
household workers in the total workers is due to the fact that industries in the study area
are not confined to household cottage industries but have swell into micro, small,
medium and large industries due to greater government intervention and high doses of
public and private investment in industrial sector. It may be added here that the workers
engaged in above four categories of industrial undertakings are not covered under
‘household industrial workers’ but form part of ‘Other Workers’.
The percentage share of ‘Other workers’ constitute 41.4 percent of the total workers in
the study area. This includes white color workers, professional workers, shopkeepers,
traders, business persons and people working in industrial undertakings other than
‘household industrial workers’.
Village wise data on number of households, population, sex ratio, literacy rate, main and
marginal workers is presented in Annexure IV.
Amenities
Various facilities presently available in the study area are described below:
House Structure
The field survey has revealed that 88 percent of the households living in the study area
have Semi-Pucca or Pucca structure to live in. Only 12 percent households live in kutcha
houses.
Education facilities Secondary sources have revealed that 91 percent of the villages in the study area are
provided with educational facilities. These include schools of various categories and
adult literacy centre. The project village is provided with one primary school. The Table
below indicates number and types of educational institutions located in the study area.
![Page 104: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/104.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section –VI Additional Studies
Page 20/VI
Table 6.2
Type and number of Educational Institutions located in the study area
S. No. Educational Institution Number Percentage
to total
(1) (2) (3) (4)
1 Primary Schools 39 53.42
2 Middle Schools 19 26.03
3 Secondary Schools 9 12.33
4 Senior Secondary Schools 3 4.11
5 Adult literacy centre 3 4.11
Total 73 100
There is no provision for higher education in the study area. Hence, students are
compelled to travel to nearby towns/cities, which are generally located beyond 10
kilometres from their residence villages.
Medical Facilities Secondary data has revealed that the study area is lacking in medical facilities as 36
percent of the villages do not have institutional health facilities of any type even after the
introduction of Centrally Sponsored NRHM Programme in the state. In the study area
there is no hospital or nursing home but there are few dispensaries, PHC, RMP, and
PHSC. To add further, that there is no medical facility at the project village Raipur
Araian. Various health facilities available in the study area are presented in the Table
below:
Table 6.3
Availability of Health Facilities in the study area and average number people served
S. No. Health Institution/Health
facilities Number
Average number of
people served by the
health institution
(1) (2) (3) (4)
1 Allopathic Dispensary 8 5080
2 Ayurvedic Dispensary 1 40638
3 PHC 1 40638
4 RMP 27 1505
5 PHSC 1 40638
![Page 105: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/105.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section –VI Additional Studies
Page 21/VI
As the study area is lacking in medical facilities, people living in the villages visit district
or sub-district hospitals or hospitals/dispensaries located in the nearby towns/cities
during emergency and for long treatments. Deep probe made during the field survey has
revealed that the health institutions located in the villages are not fully equipped with
man power, medicines, equipment and vehicles for carrying patients.
The Accredited Social Health Activist (ASHA) duly trained and provided with kits is being
increasingly deployed in the villages in the study area. She is responsible for creating
awareness on health and mobilizes the community towards local health planning and
increased utilization of the existing health services. She is a promoter of good health
practices and provides a minimum package of curative care as appropriate and feasible
for that level and makes timely referrals.
There is an urgent need for greater attention towards occupational health. Due to
prolong exposure to sand and dust the workers may face several health hazards. It is
therefore essential that health hazards due to dust and need to be identified on priority
basis and preventive measures be taken.
Drinking water
Drinking water facility is available in all the habitations located in the study area. Hand
Pump is the principal source of drinking water. Next to Hand pump comes tube well,
which is available in 27 villages. At the Project village Raipur Araian tube well and hand
pump are the sources of drinking water. The Table below presents various sources of
drinking water facility in the study area.
Table 6.4
Availability of drinking water facilities in the Study area
Sr. No. Source of Drinking water Number villages
(1) (2) (3)
1 Tap 13
2 Well 1
3 Tank 1
4 Tube well 27
5 Hand Pump 45
![Page 106: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/106.jpg)
Project Name: Raipur Araian Sand Mine, Punjab
Sources of Drin
Electricity
According to secondary sources
Electricity is available for domes
electricity for industrial uses i
neighborhoods. The demand fo
mining activities will start.
Roads
All the villages in the study area
roads are available along with pa
with paved roads and no mud
Araian village by mud roads.
Communication Facilities
The study area is provided with
project village Raipur Araian the
connections.
Bus and Railway services
In the study area bus services a
one village named Khurampur.
services but not by railways as ye
Bank and institutional finance
The study area is served by Com
village Raipur Araian there is no
Ax
is T
itle
Sourc
ab Final EIA/EMP Section –VI Addit
Pa
Figure 6.3
inking Water in the villages in Study Area
s electricity has reached all the villages in the stu
estic lighting and agricultural operations. The de
is fast growing due to rapid industrializatio
for electricity r will increase further when the p
ea are provided with paved roads. In eight villa
paved roads. The project village Raipur Araian is
d roads. However, the quarry is connected wit
th three Post offices and 1200 phone connection
there is no post office but there are 25 land lin
are available in 34 villages and railway service
r. The project village Raipur Araian is connecte
yet.
e
ommercial and Co-operative banks (one each). A
o banking facility.
0
50 13 1 127 45
Axis Title
ources of drinking water in
study area
itional Studies
Page 22/VI
study area.
emand for
ion in the
proposed
llages mud
is provided
ith Raipur
ons. At the
line phone
ces in only
ted by bus
. At project
![Page 107: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/107.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section –VI Additional Studies
Page 23/VI
Social Condition
With the advancement of education and under the stresses and strains of the modern
economic and social set up, the joint family system in the study area is breaking up very
fast. The field survey has revealed that 89 percent of the households are nuclear families
or conjugal families consisting of a father, mother and their children. The remaining 11
percent are extended families, also known as consanguineous families or joint families.
Due to increase in population and adoption the new ways of life, there is a general
tendency among the younger generation to move out to urban areas in search of job and
business opportunities. However, it cannot be concluded that the institution of joint family
system has disappeared totally. During the field survey it was observed that in many
cases, the younger people keep their families with their parents or extend financial help
to them at the time of marriages, hospitalization, repaying of outstanding debts,
purchase of land and construction of houses etc. Besides the above, they often send
their families to their parents or keep the parents with them for a period convenient to
both sides. Thus joint family system has not yet completely broken. Though many men
and women have left their villages for higher education, jobs and business but they still
have close link with their parents and make regular visits to them, who have preferred to
stay back in the villages.
The condition of women in the study area has considerably improved and they are
competing with men in all walks of life. They receive higher education and do jobs in
schools, colleges and offices. All avenues of life are now open to them. Further, they are
fast becoming economically independent.
It has also been observed that in the study area the caste feeling in the society is in the
wane and the people of different castes and creed mix together quite freely in their day-
to -day life. Lastly, the study area is somewhat free from poverty as number of BPL
Card holders is only 6.5 percent.
Income
The sample survey in randomly selected villages in the study area covering 34
households in each village have revealed that average monthly income of a households
from all sources is Rs. 8927.18, which is more than two times the national average of
Rs. 3874.33 per month during 2009-10.
Consumption Pattern
In the study area wheat is the staple food. Other food articles consumed in the area are
rice, pulses & grams, edible oils, milk & milk products, fruits & vegetables, eggs, meat &
![Page 108: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/108.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section –VI Additional Studies
Page 24/VI
meat products. The Table below presents average weekly consumption of cereals and
non-cereal items in the study area.
Table 6.5
Weekly Household Consumption Cereal and Non-cereal items
S. No. Items Unit of
measurement Consumption
(1) (2) (3) (4)
1 Wheat Kg. 9.29
2 Rice Kg. 5.26
3 Pulses & Grams Kg. 0.81
4 Edible oils & other
cooking media Liters 3.02
5 Spices Kg. 0.59
6 Milk Liters 9.37
7 Fruits & Vegetables Kg. 3.19
8 Eggs pieces 12
9 Meat & Meat Products Kg. 1.67
Impact on population composition
The impact of the proposed mining project on population composition will be marginal as
only few skilled and managerial staff will be recruited from outside and the rest will be
recruited locally. The impact will be significant if a large number of people from outside
get employed in the project. In that case not only the population of the study area will go
up but also the skewed sex ratio may make permanent social effects like rise in
exploitation of women, higher crime rate, an increase in sexual diseases and depression
among youth.
Impact on Family income
During the field survey an attempt was made to gather information on household income
in the study area. As many as 34 sample households spread over in each sample village
were approached for collection of information. Based on the above data the average
monthly income of a household in the study area has been worked out to Rs 8927.18,
which is high in comparison to national average of Rs. 3874.33 per month during 2009-
10. The impact of the proposed mining activity on household income in the study area
will be positive since it will provide employment to local people. It is expected that
![Page 109: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/109.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section –VI Additional Studies
Page 25/VI
monthly income of those households recruited for mining operation will increase further
but for 250 days in a year.
Impact on consumption pattern
The field survey has revealed that people in the study are not poverty ridden. Increased
household income may change the consumption pattern substantially. There may be a
marginal or no increase in the consumption of food articles but consumption of non-food
items may go up due to increased income.
Impact on road development
Movement of trucks and other vehicles to and fro the quarry site is expected to increase
substantially, when the construction and operation of the mine will commence. The
existing roads connecting the quarry with the national and state highways are narrow
mud roads. There will be mud slide and traffic bottle neck if these roads are not widened
and their conditions are not improved by making them paved roads. Hence, there is
scope for road development in the area.
Impact on law & Order
If local people are employed to run the quarry, there will be no law & order problem. The
mine workers will attend to their duties from their residence and return to their homes
after the day’s work is over. However, there may cause law & order problem due to
ethnic issues if the workers are migrants and live nearby. Hence, to meet any untoward
incident one police post may be set up to tackle law & order problem in the project
village..
6.7 Suggestions
Provision of First Aid at mining site
Extraction of sand, boulder and bajri from the river bed poses serious health risks due to
dust, quarrying. The effects vary depending on the nature of the dust particles, silica
content in it and the size of the particle. To meet any emergency during extraction of the
minerals from the river bed and subsequent loading in the transport vehicles, provision
for First Aid should be made by the project proponent. Before the affected person is
removed to a doctor or health institution for necessary medical aid, the miner should be
provided with First Aid.
Tie up with the nearest PHC for medical help
To meet the medical needs of the mine workers it is suggested that tie-ups with nearest
hospital or Primary Health Center (PHC) may be made. Few beds may be exclusively
![Page 110: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/110.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section –VI Additional Studies
Page 26/VI
reserved for the mine workers in the above health institutions. This will ensure timely
medical aid to the affected persons.
Supply of Mask, Gloves
The mine workers are subject to respiratory diseases, muscular-skeletal and gastro-
intestinal disorders and skin diseases. For protection from dust it may be made
compulsory for all mine workers to wear masks and gloves while working in the mines.
Regular health checkups
The miners may be encouraged to undergo health checkups at regular intervals in order
to protect themselves from various diseases. The health Department of Punjab
Government must Organize Health Camps at regular intervals preferably in every
quarter. Further, free medical facilities may be made available to the workers and their
family members.
Administration of Anti-venom injections
Provision of Anti-venom therapy must be made available at the near health institution.
Anti-venom injections may be administrated to the mine workers in case of snake, spider
and insect bites, while working in the mines.
Special telephone number
A special telephone number may be made available to the mine workers. In case of
emergency the miners can dial the above number for medical assistance. Vehicle may
be provided to the patients in short duration for shifting to the health institution.
Special Group Insurance Scheme
All the mine workers may be covered under a Group Insurance Scheme of LIC or any
other Insurance company.
6.8 Conclusion
The implementation of the Raipur Araian sand mining project will generate both direct
and indirect employment. Besides, it will provide a check on existing system of mining
operation. Since the quarries will be allotted on lease basis, mining operation will be
legally valid and it will bring income to the state exchequer. It will also reduce flooding of
river banks, destruction of standing crops, land and property to a great extent. The
project will also provide impetus to industrialization of the area. Where transfer of
boulders into bajri is necessary crushing units will come up. It is expected that intending
![Page 111: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/111.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section –VI Additional Studies
Page 27/VI
entrepreneurs will venture to set up micro and small scale units in the near future making
the area a mixed society, dependent on industry, trade and business. At present
agriculture is the main occupation of the people as more than half of the population
depends on it. With the implementation of the proposed mining project the occupational
pattern of the people in the area will change making more people engaged in industrial
and business activities rather in agriculture. Thus there will be a gradual shifting of
population from agriculture to mining and industry. Further, the mining and industrial
activities in the area may lead to rapid increase in population and thereby urbanization.
Due to urbanization of the area, employment opportunities will further increase.
The study area is still lacking in education, health, housing, water, electricity etc. It is
expected that same will improve to a great extent due to proposed mining project and
associated industrial and business activities. It is therefore suggested that extraction of
minerals should be taken up on regular basis during the post monsoon period. This will
dredge the river bed on regular basis, regulate the course of the river and check flooding
of the catchment area.
Proposed activities and expenses on Corporate Social Responsibility will be as per CSR
Mandate of the Government.
***************
![Page 112: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/112.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - VII Project benefits
Page 1/VII
SECTION-VII
PROJECT BENEFITS
INDEX
S. No. CONTENTS Page No.
7.0 GENERAL 2/VII
7.1 BENEFITS OF MINING 2/VII
7.2 EMPLOYMENT 2/VII
7.3 IMPROVEMENTS IN PHYSICAL AND SOCIAL INFRASTRUCTURE 2/VII
7.4 HEALTH 3/VII
![Page 113: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/113.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - VII Project benefits
Page 2/VII
7.0 GENERAL
The execution of the project i.e removal of sediments will protect against widening of the
river channel and flooding of adjoining areas, bring overall improvement in the locality,
neighbourhood and the State by bringing industry, roads, water supply, electricity,
employment, living standard and economic growth.
7.1 BENEFITS OF MINING
i. Controlling river channel
ii. Protecting river banks
iii. Reducing submergence of adjoining agricultural lands due to flooding.
iv. Reducing aggradation of river level.
v. Generating useful economic resource for construction.
vi. Generating employment
vii. Improvement of socio economic conditions of nearby habitats.
7.2 EMPLOYMENT
The socio-economic conditions of the surrounding villages indicate that employment
generation is seasonal. The occupational activities are agriculture, cattle rearing and
employment in mines but on daily wages. The mining activity will provide employment to
local people which will increase socio- economic status of the area.
7.3 IMPROVEMENTS IN PHYSICAL AND SOCIAL INFRASTRUCTURE
The opening of the proposed project will enhance the socio-economic activities in the
adjoining areas. This will result in following benefits:-
a. Improvements in physical infrastructure.
b. Improvements in Social Infrastructure.
c. Increase in Employment Potential
d. Contribution to the Exchequer.
e. Prevention of illegal mining.
f. During and Post-mining enhancement of green cover.
7.3(a) IMPROVEMENTS IN PHYSICAL INFRASTRUCTURE
The opening of the proposed project will improve the physical infrastructure of the adjoining
areas. This will include the following:-
• Improved road communication due to opening of the proposed project.
• Strengthening of existing community facilities through the Community Development
Programme.
![Page 114: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/114.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - VII Project benefits
Page 3/VII
• Creation of community assets (infrastructure) like provision for drinking water,
construction of school buildings, village roads/ linked roads, dispensary & health centre,
community centre, market place etc.
• Awareness program and community activities, like health camps, medical aids, family
welfare programs, immunization camp sports & cultural activities, plantation etc.
7.3(b) IMPROVEMENTS IN SOCIAL INFRASTRUCTURE
There will be some obvious changes in various environmental parameters due to mining
activity. There will be positive impact in socio-economic area due to increased economic
activities, creation of new employment opportunities, infrastructural development and better
educational and health facilities. Lessee will also undertake awareness program and
community activities like health, camps, medical aids, family welfare camps, AIDS
awareness program etc.
7.3(c) INCREASE IN EMPLOYMENT POTENTIAL: - There is a possibility of creation of
direct and indirect employment opportunities due to working of this mine.
7.3(d) PREVENTION OF ILLEGAL MINING & CONTRIBUTION TO THE EXCHEQUER: -
Since the quarries will be leased out to successful allottees, mining operation in the state will
get legalized and it will fetch income to the state exchequer.
7.3(e) ENHANCEMENT OF GREEN COVER
Plantation/afforestation will be done as per program i.e. along the road sides and near civic
amenities, which will be allotted by Government bodies as it is not feasible to plant trees
near the mine lease area. Post plantation, the area will be regularly monitored in every
season for evaluation of success rate. For selection of plant species local people will also be
involved. The management will provide free saplings of fruit and other trees, etc. to local
during rain for plantation.
7.4 HEALTH
Periodic medical checkups as per Mines Act/ Rules and other social development and
promotional activities will be undertaken. All this will lift the general health status of the
residents of the area around mines.
*********
![Page 115: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/115.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - VIII Environment Management Plan
Page 1/VIII
SECTION-VIII
ENVIRONMENTAL MANAGEMENT PLAN
INDEX
S. No. CONTENTS Page No.
8.0 INTRODUCTION 2/VIII
8.1 ENVIRONMENTAL MANAGEMENT PLAN (EMP) 2/VIII
8.2 ENVIRONMENTAL MANAGEMENT PLAN IMPLEMENTATION 3/VIII
8.3 PROPOSED SET UP 4/VIII
8.4 BUDGET ALLOCATION FOR EMP IMPLEMENTATION 4/VIII
8.5 MONITORING SCHEDULE AND ACTIVITIES 5/VIII
8.6 DIVISION OF RESPOSIBILITY OF VARIOUS ACTIVITIES FOR A
SAND MINE PROJECT
6/VIII
![Page 116: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/116.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - VIII Environment Management Plan
Page 2/VIII
8.0 INTRODUCTION
To mitigate the adverse impacts which are likely to be caused due to the mining operation and
overall scientific development of local habitat, environmental management plan (EMP) has been
formulated and integrated with the mine planning. The details of the anticipated impacts and
mitigative measures have been discussed in Section IV of this report, based on the results of
present environmental conditions and environmental impact assessment. The EMP has
therefore been made considering implementation and monitoring of environmental protection
measures during and after mining operations.
The mitigation measures which reduce the impact have already been identified earlier in this
report. To minimize the adverse impact, certain additional EMP are enumerated below for
implementation.
8.1 ENVIRONMENTAL MANAGEMENT PLAN (EMP)
Proper environmental management plan are proposed for “Sand” mining project to mitigate the
impact during the mining operation.
a. Care will be taken that no labour camps will be allowed on river bed.
b. Care will be taken that no cooking, or burning of woods will be allowed in the adjoining
area.
c. Prior to mining, short awareness program will be conducted for labours to make them
aware to way of working.
d. If some causality or injury to animal occurs, it will be informed to forest department and
proper treatment will be given.
e. No tree cutting, chopping, lumbering, uprooting of shrubs and herbs will be allowed.
f. Corridor movement of wild mammals (If exists) will be avoided.
g. Care will be taken that noise produced during vehicles movement for carrying sand are
within the permissible noise level.
h. No pilling of RBM material will be in adjoining area.
i. If wild animals are noticed crossing the river bed, it will not be disturbed or chased away,
instead the labours will move away from their path.
j. The persons whose standing crops get destroyed/damaged by the wild animals can
approach the DFO, who on investigation can allow a suitable compensation to be paid.
![Page 117: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/117.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - VIII Environment Management Plan
Page 3/VIII
8.2 ENVIRONMENTAL MANAGEMENT PLAN IMPLEMENTATION
Environmental Management Plan serves no purpose if it is not implemented with true spirit.
Some loopholes in the EMP can also be detected afterwards when it is implemented and
monitored. Thus, an implementation and monitoring programme has to be prepared.
The major attributes of environment are not confined to the mining site alone. Implementation of
proposed control measures and monitoring programme has an implication on the surrounding
area as well as for the region. Therefore, mine management should strengthen the existing
control measures as elaborated earlier in this report and monitor the efficacy of the control
measures implemented within the mining area relating to the following specific areas for eco-
friendly mining plan:
a. Collection of air and water samples at strategic locations with frequency suggested and by
analyzing thereof. If the parameters exceed the permissible tolerance limits, corrective
regulation measure will be taken.
b. Collection of soil samples at strategic locations once in every year and analysis thereof with
regard to deleterious constituents, if any.
c. Measurement of water level fluctuations in the nearby ponds, dug wells and bore wells.
d. Regular visual examination will be carried out to look for erosion of river banks. Any abnormal
condition, if observed will be taken care of.
e. Measurement of noise levels at mine site, stationary and mobile sources, and adjacent villages
will be done twice a year for the first two years and thereafter once a year.
f. Plantation/afforestation as should be done as per program i.e along the road sides and near
civic amenities, which will be allotted by Government bodies as it is not feasible to plant trees
near the mine lease area. Post plantation, the area will be regularly monitored in every season
for evaluation of success rate. For selection of plant species local people should also be
involved.
Mine management will be in regular touch with local surrounding villages to update the various
developmental schemes made by them. They will also consider any immediate requirement,
which could be taken care of in near future.
An Environmental Management Cell (EMC) is envisaged which will be responsible for
monitoring EMP and its implementation. EMC members should meet once in a month to assess
the progress and analyze the data collected during the month. The EMC will function as per Fig.
5.1(Section V).
![Page 118: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/118.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - VIII Environment Management Plan
Page 4/VIII
EMC will be in regular touch with State Pollution Control Board and Indian Bureau of Mines and
send them annual progress report. Any new regulations considered by State/Central Pollution
Control Board for the industry will be taken care of.
8.3 PROPOSED SET UP
Keeping the utility of monitoring results in the implementation of the environmental management
program in view, an organizational chart has been proposed, headed by General Manager as
shown in Fig. 5.1(Section V).
The said team will be responsible for:
a. Collecting water and air samples from surrounding area and work zone monitoring for
pollutants.
b. Analyzing the water and air samples.
c. Implementing the control and protective measures.
d. Co-coordinating the environment related activities within the project as well as with outside
agencies.
e. Collecting statistics of health of workers and population of surrounding villages.
f. Monitoring the progress of implementation of environmental management program. Greenbelt
development, etc.
The laboratory will be suitably equipped for sampling/testing for various environmental
pollutants.
8.4 BUDGET ALLOCATION FOR EMP IMPLEMENTATION
Annual budget for EMP is very essential for successful implementation of EMP. As there are no
pollution control systems, no capital cost of Pollution Control systems are envisaged. Costs will
be annual operating costs as given below. The fund allocated will not be diverted for any other
purposes and the top management will be responsible for this. The budget will take into
consideration the following capital and operating expenses:
a. Field cost for monitoring of parameters.
b. Cost of any defined outsourcing
c. Cost of chemicals, consumables and transport for data generation
d. Man power cost for environmental cell
e. Any other cost as per EC condition.
![Page 119: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/119.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - VIII Environment Management Plan
Page 5/VIII
Table 8.1
Cost of EMP
Sl. No Description Cost to be incurred
(in lakhs/annum)
1
Air Quality
a)Monitoring in the vicinity of the mine
b) Monitoring in the vicinity of the transportation network
c) Cost of dust suppression
2.0
2 Water Quality Water quality of surface and groundwater around the site
1.0
3 Ambient Noise Level
0.5
4 Soil Quality 0.5
5 Socio-economic condition of local, population, physical
survey 0.12
6 Inventory of Flora(tree plantation, survival etc) & Fauna 0.5
7 Man power cost for environmental cell 0.5
TOTAL 5.12
8.5 MONITORING SCHEDULE AND ACTIVITIES
To evaluate the effectiveness of environmental management program regular monitoring of the
important environmental activities to be monitored are shown in Table. 6.1. (Section VI).
![Page 120: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/120.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - VIII Environment Management Plan
Page 6/VIII
8.6 Division of Responsibility of various Activities for a Sand Mine Project
S.No Activity Responsibility
of the Project
Proponent
(Regulator)
Responsibility
of the
Contractor
(Operator)
1 Demarcation of mine area (Outermost boundary)
as per Khasra Numbers of the mine
Regulator
through
revenue dept.
2 Demarcation of Buffer zone on either side of
River/Choe bank
Operator-
Based on the
regulations
passed from
time to time
3 Restriction on Mining : The mining is prohibited to a distance of 500 m both
on upstream and downstream from the high level
bridge and 250 m form the other bridges.
If width of the river is less than 120 m the mining will
be restricted within the bed of river. If higher than
120 m the mining will be restricted after leaving the
area within 30 m from the edge of embankment on
either side of the river bed.
The contractor will not do any quarry operations
within the distance of:
75m from railway line
60m from national highway
50m from reservoir tank, canal roads, public works
or buildings and in-habitat sites etc.
The mining will not be allowed below the water
table.
No mining operation will be allowed in forest area.
Compliance to various provisions laid down under
Mines Act, 1952, Mines & Minerals (Regulation and
Operator Operator Operator Operator Operator
![Page 121: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/121.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - VIII Environment Management Plan
Page 7/VIII
Development) Act, 1957, Forest (Conservation) Act,
1980, MMR, 1961.
Assuring for the provisions of Mines Act, 1952,
Interstate Migrant Workman Act and Central and
State Govt. labor laws in respect of following:
drinking water
rest shelter
first aid box
welfare facilities
Abiding by the Punjab Minor Mineral Concession
Rules, 1964 and 2008.
Adherence to the Eco-friendly mine plan for mining
of minor minerals.
Compliance to the measures kept in the EMP
Operator Operator Operator Operator Operator
4 Making amenities available :
Water for Drinking purposes
Water for Sprinkling on roads
Water for wetting of dry sands
Provisions of Portable/Community toilets and
making water available for them.
Operator
5a Mitigation Measures for Land environment:
Assuring sand mining to a depth of 3m or maximum
upto ground water table whichever is minimum
The RBM will be done in unsaturated zone.
No mining will be done nearby the dam and
important structure to prevent hungry water
problem.
Mining will not exceed beyond the magnitude.
The RBM activity will be semi-mechanized, most of
Operator Operator Operator Operator
![Page 122: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/122.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - VIII Environment Management Plan
Page 8/VIII
the work is proposed to be done manually.
Dredging will not be allowed.
Prohibiting ponding on river bed.
While disposing incidental solid wastes generated
care taken that it is not disposed of in meandering
course of the river.
Operator- Tyred excavator with bucket capacity of 0.3 cum will only be permitted. Operator
Operator
Operator
5b Top Soil
In a case, where agricultural land is involved and
after mining the land is to be returned for
agricultural purposes:
Earmarking space for piling/keeping top soil
Removal of top soil
Transporting and piling of top soil at the designated
space
Redevelopment of agricultural land: Spreading,
mixing, compacting and leveling of top soil after
mining
Operator
Operator
Operator Operator
5c Making minimum number of access roads with least
steepness to river bed.
Avoiding mining during the monsoon season and at
the time of floods.
Synchronizing mining schedule with the river flow
direction and the gradient of the land.
Making haulage roads parallel to the river bank.
Taking care to ensure that ponds are not formed in
the river bed
Operator Operator- as per the directions of the Regulator Operator Operator Operator
6 Mitigation Measures for Air environment:
![Page 123: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/123.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - VIII Environment Management Plan
Page 9/VIII
No overloading of dumpers/trucks/trolleys.
Covering the carrying vehicles with tarpaulin to
prevent spillage.
Wetting of sand in case it is dry.
Regular sprinkling of water on roads in the morning
and also at a moment if observed that the dust on
road is easily getting airborne.
Fortnightly scraping/bulldozing of road to prevent
accumulation of lose dust on road, to shift it to sides
and to keep roads almost leveled to ensure smooth
movement of vehicles and also prevent spillage,
thereby, minimizing fugitive dust emissions from the
roads towards the villages.
Prior awareness to explain the Eco-friendly mine
plan.
ii. Proper tuning of vehicles to keep the CO gas
emissions and noise under check.
iii. Plantation of trees at the places, if allowed by the
authorities, to help reduce the impact of dust in the
nearby villages.
Regulator
Operator
Operator Operator Operator Operator Operator Operator
7 Mitigation Measures for Noise environment:
On site:
Regular maintenance of machinery to keep a check
on source of noise generation.
Only trained operators to operate machines during
mining to reduce any chance of safety failures.
Making available gadgets, in places where more
excavators and dumpers/trucks are involved, for
hearing protection like ear muffs/plugs and gas/dust
mask.
Off-site:
Phasing out the old and worn out vehicles.
Operator
Operator
Operator
Operator
![Page 124: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/124.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - VIII Environment Management Plan
Page 10/VIII
Maintaining vehicles in good running condition
Awareness will be imparted prior to mining
operations that smoke silencers are kept in good
conditions.
In addition, trucks drivers will be instructed to make
minimum use of pressure horns at the village area
and not to use DJ sound systems.
Operator
Operator
8 Provisions/Maintenance of Access road from
the nearby main road to the mine:
Maintenance of path
Widening of road
Leveling of road
Planting of trees at places decided and marked for
this purpose.
Operator
Operator
Operator
Operator- With
consent from
the respective
department
9 Health & Safety:
Safety of people and property against flooding or
any calamity and unforeseen circumstances.
Occasional health check
Provisions of safety appliances
Operator Operator
Operator
10a Flora & Fauna:
Ecological impacts
Carrying the mining activity mostly manually.
No mining activity in the vicinity of important
structure like bridges, dam and other structures if
any.
No mining during the rainy season to minimize
impact on aquatic life.
Deploying Pollution Under Check (PUC) certified
vehicles for transportation purpose.
Restoring/reclaiming the eroded banks on closure of
Operator
Operator
Operator
Operator Operator
![Page 125: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/125.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - VIII Environment Management Plan
Page 11/VIII
mining operations just before the rainy season.
No lighting allowed in the leased area.
ii. No piling of sand allowed in the area except for the
top soil.
Operator Operator
10b Flora & Fauna:
Riparian habitat:
Avoiding Sand extraction in vegetated riparian
areas.
No alteration of undercut and incised vegetated
banks.
Large woody debris in the riparian zone leaving
undisturbed or replaced when moved and not burnt.
Sand stockpiles, overburden and/or vegetative
debris will not be stored within the riparian zone.
Restriction on operation and storage of heavy
equipment within riparian habitat.
Access roads not to encroach into the riparian
zones
Operator
Operator
Operator
Operator
Operator
Operator
11 Local labour:
Giving employment
Imparting skills
Safety awareness
To maintain hygienic environment conducive for
working
Discouraging using horns as far as possible
Operator
Operator
Operator
Operator
Operator
12 General :
Erecting a hoarding indicating in English, Hindi and
preferably the local language:
Operator
![Page 126: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/126.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - VIII Environment Management Plan
Page 12/VIII
The name of the mine
The name of the Lessee
An indicative map of the mine
Production capacity
Time of lease period
Erecting at all the turns:
Safety sign boards
Direction indicators
Reflectors
Preparing and preserving the year round data on
the following to study the pattern of sedimentation,
replenishment and extraction:
Production records of mine
Area mined
Depth of mining related to defined axes.
Reporting accidents
Restriction on entering or working in any reserved
or protected area
Regulator
Operator Operator Operator
13 Meeting Corporate’s Social responsibility
Creating a corpus fund for reclamation and rehabilitation.
Regulator in coordination with village authority
Operator
14 Compliance to Environment Monitoring & Management Plan: Allocation of Funds
Carrying out environment monitoring following
provisions kept in EMP.
Maintenance of Monitoring Schedule
Meeting administrative & statutory requirements
Regulator
Operator Operator Operator
![Page 127: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/127.jpg)
Project Name: Raipur Araian Sand Mine, Punjab Final EIA/EMP Section - VIII Environment Management Plan
Page 13/VIII
Management of entire Environment Programme.
Regulator- through operator
15 Compensation to be paid as per Government rules: Paying compensation to the owners whose land is
acquired for mining purposes whether;
Government
Panchayat Land
Private
Regulator
16 Compliance to Statutory requirements:
The Mines Act, 1952
The Mines and Mineral (Development and
Regulation) Act, 1957
Mines Rules, 1955
Mineral Concession Rules, 1960 framed by the
Central govt.
Mineral Conservation and Development Rules,
1988
Punjab State Minor Mineral Concession Rules,
1964
ii. Metalliferrous Mines Regulations 1961
iii. Granite Conservation and Development Rule, 1999
The Water (Prevention and Control of Pollution) Act,
1974
The Air (Prevention and Control of Pollution) Act,
1981
The Environment (Protection) Act, 1986
ii. The Forest (Conservation) Act, 1980
iii. The Wildlife (Protection) Act, 1972
Operator
********
![Page 128: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/128.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP Section – IX: Executive Summary
Page 1/IX
SECTION-IX
EXECUTIVE SUMMARY
9.1 INTRODUCTION OF PROJECT & PROPONENT
It is a proposed project to mine sand and the estimated project cost is Rs 1.5 lacs. GM-
cum-Mining Officer, District Industries Center, Jalandhar has applied for mining lease in the
name of Raipur Araian sand Mine over an area of 17.98 ha at Village: Raipur Araian,
Tehsil: Phillor, District: Jalandhar, Punjab. The proposed mine site on Satluj River bed with
approx. 4, 85,460 tonnes of Sand deposit in it, which is replenishable due to sediment
inflow. The approved mining plan of sand Mine is approved by State Geologist, Punjab.
The proposed project is to mine sand from the river bed of Satluj. The proponent has
applied for Environmental Clearance for mining Sand from the leased area of 17.98 ha at
an estimated project cost is Rs 1.5 lacs.
The leased area has approx. 4, 85,460 tonnes of Sand deposit in it, which is replenishable
due to the sediment inflow. It is proposed to collect approximately 1, 61,820 tonnes of river
bed materials annually. As per the MoEF, New Delhi Gazette dated 14th September 2006
amended in December 2009 and April 2011, the proposed mining project is categorized as
category ‘B’ and the EC shall be given by the SEIAA of the state of Punjab
9.2 LOCATION
The mining area is located in Village: Raipur Araian, Taluka:Phillor, District: Jalandhar
Punjab. The mining lease / proposed project area falls in Survey of India Toposheet No.
44M/16. The mine lease area is located between:
Latitude 31° 0'56.09"N to 31° 1'7.46"N
Longitude 75°53'38.43"E to 75°54'8.92"E
Nearest Railway Station Phillor R.S (about 11 km in North-West direction)
Nearest Airport Ludhiana Airport (about 19 km in SSE direction)
Nearest Highway NH-1 (about 11 km in West direction)
![Page 129: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/129.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP Section – IX: Executive Summary
Page 2/IX
9.3 RESERVES
As much of the lease area is covered with water catchment area, only the middle area is
considered for reserve estimation. The sand which is exposed in all the three dimensions
(3.0m on an average) is considered as proved. From the field trials conducted in the
sector and information gathered from the applicant, the bulk density is found to be 1.8
t/cum.
Category wise updated reserves with grade are as follows:
Category Total (in Tonnes) UNFC Code
Proved 4,85,460 Tonnes 111
9.4 MINING
Sand Mining
The salient features of sand mining method are:
Mining of sand is proposed to be carried out by the excavators. The mining involve
following steps-
I. River Bed Mining activities do not involve top soil.
II. Excavation of sand is done by excavators.
III. Drilling and blasting is not required.
Working Depth (below ground level)
The deposits occur in the middle/bottom of the river. During the entire lease period, the
deposit will be worked from the top surface to 3 m bgl. The ultimate depth of the open cast
pits will be 3 m below ground level or ground water table whichever is less. Under no
circumstances it will intersect with ground water table.
9.5 WATER SUPPLY
In the river bed mining projects there is, as such, no need of water to carry out operations,
except for dust suppression. The number of working people is 12 so the water
requirement for workers will be around 1 KLD for drinking purpose & 0.7 KLD for dust
suppression the total water requirement will be around 1.7 KLD. This water will be
supplied from the nearby area.
![Page 130: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/130.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP Section – IX: Executive Summary
Page 3/IX
9.6 BASE LINE DATA
This section contains the description of baseline studies of the 10 km radius of the area
surrounding “Raipur Araian Sand Mine, Jalandhar, Punjab. The data collected has been
used to understand the existing environment scenario around the proposed mining project
against which the potential impacts of the project can be assessed.
Environmental data has been collected in relation to proposed mining for:-
(a) Air
(b) Noise
(c) Water
(d) Soil
(e) Ecology and Biodiversity
(f) Socio-economy
Table 9.1: BASELINE ENVIRONMENTAL STATUS
Attribute Baseline status
Ambient Air
Quality
Ambient Air Quality Monitoring reveals that the minimum &
maximum concentrations of PM10 for all the 5 AQ monitoring
stations were found to be 73.7 µg/m3 at AQ3 and 100/m3 at
AQ5, respectively.
As far as the gaseous pollutants SO2 and NO2 are concerned,
the prescribed CPCB limit of 80 µg/m3 for residential and rural
areas has never been surpassed at any station.
Noise Levels
Noise monitoring was carried out at four locations. The results
of the monitoring program indicated that both the daytime and
night time levels of noise were well within the prescribed limits
of NAAQS, at all the four locations monitored.
Water Quality
3 Groundwater samples and 3 surface water samples were
analyzed and concluded that:
The ground water from all sources remains suitable for drinking
purposes as all the constituents are within the limits prescribed
by drinking water standards by Indian Standards IS: 10500.
From the Surface water analysis it is evident that most of the
parameters of the samples comply with ‘Category ‘C’ standards
of CPCB indicating their suitability for Drinking water source
after conventional treatment and disinfection.
Soil Quality
Samples collected from identified locations indicate the soil is
sandy type and the pH value ranging from 7.58 to 8.36, which
![Page 131: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/131.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP Section – IX: Executive Summary
Page 4/IX
shows that the soil is alkaline in nature.
Ecology and Bio-diversity
There are no Ecologically Sensitive Areas present in the study
area, but many reserved forests regions do surround the project
area
Socio-economy
The implementation of the Raipur Araian sand mining project on
river Satluj in district Jalandhar will throw opportunities to local
people for both direct and indirect employment.
The study area is still lacking in education, health, housing,
water, electricity etc. It is expected that same will improve to a
great extent due to proposed mining project and associated
industrial and business activities.
9.6 BIOLOGICAL ENVIRONMENT
Flora
Core Zone:-
The core zone comprises of Satluj river bed, where mining operation is proposed. This area
consists of riparian vegetation in which aquatic and marshland plants are the main component.
Buffer Zone:-
Buffer zone of the proposed project is mainly agricultural land. The flora of buffer zone
comprises of plants growing on the edges of agricultural land, village woodlots and trees planted
along the roads. Many tree species are planted in the area because of their usefulness,
economic and aesthetic values.
Agricultural crops: The study area is surrounded by agricultural field in which many plants of
agricultural importance are cultivated. Wheat (Triticum aestivum), Rice (Oryza sativa), Maize
(Zea mays), Sugarcane (Saccharum officinarum), Bajra (Pennisetum glaucum), Sunflower
(Helianthus annuus) are commonly grown crops of this area.
Vegetation in and around human settlement
The study area comprise of tropical dry deciduous vegetation. Several tropical elements can be
seen scattered in the area. Species of Achyranthes, Calotropis, Lantana, Ricinus, Ziziphus, etc.
are of common occurrence.
Fauna
Core zone:
During the faunal survey in the area no wildlife corridor or movement of animals was recorded
from proposed project area. A list of animals of the study area has been prepared on the basis
of local inquiry from the village people and from the available published literatures
Buffer zone:
Many domesticated mammal species are reported from buffer zone during the field survey.
![Page 132: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/132.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP Section – IX: Executive Summary
Page 5/IX
Common grazing animals like Buffalo, cow, goat etc. can be noticed in open grass fields. Small
mammals like Indian palm squirrel (Funambulus palmarum) and field mouse (Apodemus
sylvaticus) are noticed in vicinity of village.
Table 9.2
Anticipated impact and mitigation measures for biological environment
Impact predicted Suggestive measures
Disturbance to free
movement / living of wild
fauna viz. Birds,
Reptiles etc.
If birds are noticed crossing the core zone, they will not be
disturbed at all;
Labourers will not be allowed to discards food, plastic etc.,
which can attract animals/birds near the core site;
Only low polluting vehicles having PUC will be allowed for
carrying mining materials.
Noise level will be maintained within permissible limit (silent
zone 50 dB(A) during day time or residential zone 55 dB(A))
as per noise pollution (regulation and control), rules, 2000,
of CPCB
Disturbance of riparian
ecosystem/ wetlands
The riparian ecosystem or the wetlands will not be destroyed
by the mine owners
Monitoring of upstream
and downstream water
quality
Water quality will be monitored from upstream and
downstream area to assess the impact on water quality and
plankton. The mining activity will be controlled to maintain
the clean water conditions.
9.7 LAND ENVIRONMENT
Mining Activity: Harvesting of river bed minerals and other associated activities are the
main sources of environmental degradations and most serious ones are detailed
hereunder:
a. Damage of river bank due to access ramps to river bed, causing damage to vegetation,
soil erosion, micro disturbance to ground water, possible inducement of charged river
course.
b. Loss of riparian vegetation standing along the bank due to making roads connecting
successive access to river bed.
![Page 133: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/133.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP Section – IX: Executive Summary
Page 6/IX
c. Contamination of sand aquifer water due to ponding: Due to uneven rocky bed of river,
sand bed thickness vary considerably and digging more sand from a pocket where
thickness of sand is more may cause ponding. In this stagnant water, bio-degradable
materials especially flora waste gets accumulated causing contamination and inducing an
unhealthy environment.
d. Surface degradation due to stockpiling and road network.
Mitigation measures
i. Minimum number of access roads to river bed for which cutting of river banks will be
avoided and ramps are to be maintained.
ii. Access points to the river bed will be decided basing on least steepness of river
bank and least human activity.
iii. Mining is avoided during the monsoon season and at the time of floods.
iv. Mining schedule is synchronized with the river flow direction and the gradient of the
land.
v. Haulage roads parallel to the river bank and roads connecting access to river bed
will be made away from the bank
vi. Care will be taken to ensure that ponds are not formed in the river bed
vii. Access roads from public roads and up to river bank will be aligned in such a way
that it would cause least environmental damage.
viii. Vegetation development is proposed along the road sides of the approach roads, to
arrest soil erosion. While selecting the plant species, preference will be given for
planting native species of the area.
9.8 AIR ENVIRONMENT
Anticipated impacts and evaluation
Information on air quality was studied and various modelling techniques predicted
that the mining activity will not affect the air quality in a significant manner. In mining
operations, loading, transportation and unloading operations may cause
deterioration in air quality due to handling dry materials. In the present case, only
wet materials will be handled, thus eliminating problems of fugitive dust. Also, the
collection and lifting of minerals will be done manually without any blasting.
Therefore the dust generated is insignificant as compared to mining process of
other hard minerals like the process of drilling, blasting, mechanized loading etc.
![Page 134: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/134.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP Section – IX: Executive Summary
Page 7/IX
Mitigation measures
The only air pollution sources are the road transport network of the trucks.
i. Water sprinkling will be done on the roads regularly.
ii. Care will be taken to prevent spillage by covering the carrying vehicles with
tarpaulin and sprinkling of water, if dry.
iii. Fortnightly scraping of road in order to keep the roads almost leveled. This will
ensure smooth flow of vehicles and also prevent spillage.
iv. Overloading will be kept under check by giving prior awareness.
v. Proper tuning of vehicles to keep the gas emissions under check.
vi. Plantation of trees along the roads to help reduce the impact of dust in the nearby
villages.
9.9 WATER ENVIRONMENT
Mining of sand from within or near a streambed has a direct impact on the stream’s
physical habitat characteristics. These characteristics include geometry, bed evaluation,
substrate composition and stability, in stream roughness elements, depth, velocity,
turbidity, sediment transport, stream discharge and temperature. Altering these habitat
characteristics can have deleterious impacts on both in stream biota and associated
riparian habitat.
The detrimental effects to biota resulting from bed material mining are caused by three
main processes:
i. Alteration of flow patterns resulting from modification of the river bed
ii. An excess of suspended sediment
iii. Damage to riparian vegetation and in stream habitat.
Mitigation measures
The deposits occur in the middle/bottom of the river. During the lease period, the deposit
will be worked from the top surface to 3 m bgl. The ultimate depth will be 3 m below
ground level or the ground water table whichever is less.
9.10 NOISE ENVIRONMENT
Anticipated impacts and evaluation
As there will be no heavy earth moving machinery there will not be any major impact on
noise level due to the mining and other association activities a detailed noise survey has
been carried out and results are discussed in Section III. Blasting technique is not used for
sand lifting, hence no possibility of land vibration. It was found that the mining activity will
![Page 135: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/135.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP Section – IX: Executive Summary
Page 8/IX
not have any significant impact on the noise environment of the region. The only impact
will be due to transportation of materials by trucks. trucks and movement of small
machinery.
a. Mitigation measures
i. On-site
a) Maintenance of Machinery: Regular maintenance of machinery will keep the
generated noise level below the minimum prescribed limit i.e. not exceeding 90 dB (A)
at a distance of 2 m from the machine. All machines will be as per stipulated standards
and will be used at their optimum capacity.
b) Trained Operators: Only trained operators will be allowed to operate machines during
mining to reduce any chance of safety failures.
c) Vegetation: Plantation of trees along the bank will be done to dampen the noise, if
possible.
d) Hearing Protection: No hearing protection is generally needed for RBM projects.
e) Phasing out the old and worn out trucks.
ii. Off-site
The off-site receptors are not significantly affected as noise generated by RBM is
insignificant but some disturbances due to vehicle movement may not be avoidable.
However the following measures have been envisaged:
a) The vehicles will be maintained in good running condition so that noise will be reduced
to minimum possible level.
b) Awareness will be imparted prior to mining operations that smoke silencers remain in
a good conditions not to generate noise.
c) In addition, trucks drivers will be instructed to make minimum use of horns at the
village area.
9.11 TRAFFIC ANALYSIS
From the analysis it has been seen that the V/C ratio will be modified to 0.33 and 0.21
with LOS both being “B” which is “very good”. So the additional load on the carrying
capacity will not be affected to any significant level.
9.12 SOCIO-ECONOMIC ENVIRONMENT
The implementation of the Raipur Araian sand mining project will generate both direct and
indirect employment. Besides, it will provide a check on existing system of mining operation.
Since the quarries will be allotted on lease basis, mining operation will be legally valid and it
will bring income to the state exchequer. It will also reduce flooding of river banks,
![Page 136: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/136.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP Section – IX: Executive Summary
Page 9/IX
destruction of standing crops, land and property to a great extent. The project will also
provide impetus to industrialization of the area. Where transfer of boulders into bajri is
necessary crushing units will come up. It is expected that intending entrepreneurs will
venture to set up micro and small scale units in the near future making the area a mixed
society, dependent on industry, trade and business. At present agriculture is the main
occupation of the people as more than half of the population depends on it. With the
implementation of the proposed mining project the occupational pattern of the people in the
area will change making more people engaged in industrial and business activities rather in
agriculture. Thus there will be a gradual shifting of population from agriculture to mining and
industry. Further, the mining and industrial activities in the area may lead to rapid increase in
population and thereby urbanization. Due to urbanization of the area, employment
opportunities will further increase.
9.13 ENVIRONMENTAL MANAGEMENT PLAN (EMP)
Proper environmental management plan are proposed for “Sand” mining project to
mitigate the impact during the mining operation.
• Care will be taken that no labour camps are allowed on river bed.
• Care will be taken that no cooking, or burning of woods will be allowed in the
adjoining area.
• No lighting will be allowed in the area.
• Prior to mining, short awareness program will be conducted for labours to make
them aware to way of working.
• If some causality or injury to animal occurs, it will be informed to forest department
and proper treatment will be given.
• No tree cutting, chopping, lumbering, uprooting of shrubs and herbs will be
allowed.
• Corridor movement of wild mammals (If exists) will not be disturbed.
• Care will be taken that noise produced during vehicles movement for carrying sand
is within the permissible noise level.
• No pilling of RBM material will be allowed in adjoining area.
• If wild animals are noticed crossing the river bed, they will not be disturbed or
chased away, instead the labours will move away from their path.
![Page 137: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/137.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP Section – IX: Executive Summary
Page 10/IX
9.14 ENVIRONMENTAL MANAGEMENT PLAN IMPLEMENTATION
Environmental Management Plan serves no purpose if it is not implemented with true
spirit. Some loopholes in the EMP can also be detected afterwards when it is implanted
and monitored. Thus, an implementation and monitoring programme has to be prepared.
The major attributes of environment are not confined to the mining site alone.
Implementation of proposed control measures and monitoring programme has an
implication on the surrounding area as well as for the region. Therefore, mine
management will strengthen the existing control measures as elaborated earlier in this
report and monitor the efficacy of the control measures implemented within the mining
area relating to the following specific areas for eco-friendly mining:
a. Collection of air and water samples at strategic locations with frequency suggested and by
analyzing thereof. If the parameters exceed the permissible tolerance limits, corrective
regulation measure will be taken.
b. Collection of soil samples at strategic locations once in every year and analysis thereof with
regard to deleterious constituents, if any.
c. The effectiveness of drainage system depends upon proper cleaning of all drains provided
in the surrounding of mine area. Any blockage due to siltation or loose material will be
checked at least once in a month.
d. Measurement of water level fluctuations in the nearby ponds, dug wells and bore wells.
e. Regular visual examination will be carried out to look for erosion of river banks. Any
abnormal condition, if observed will be taken care of.
f. Measurement of noise levels at mine site, stationary and mobile sources, and adjacent
villages will be done in every quarter of the year.
g. Plantation/afforestation as will be done as per program i.e. along the road sides and near
civic amenities, which will be allotted by Government bodies as it is not feasible to plant
trees near the mine lease area. Post plantation, the area will be regularly monitored in
every season for evaluation of success rate. For selection of plant species local people will
also be involved.
![Page 138: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/138.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP Section – IX: Executive Summary
Page 11/IX
9.15 BUDGET ALLOCATION FOR EMP IMPLEMENTATION
Table 9.3 COST OF EMP
Sl. No Description Cost to be incurred
(in lakhs/annum)
1
Air Quality
a)Monitoring in the vicinity of the mine
b) Monitoring in the vicinity of the transportation network
c) Cost of dust suppression
2.0
2 Water Quality Water quality of surface and groundwater around the site
1.0
3 Ambient Noise Level
0.5
4 Soil Quality 0.5
5 Socio-economic condition of local, population, physical
survey 0.12
6 Inventory of Flora(tree plantation, survival etc) & Fauna 0.5
7 Man power cost for environmental cell 0.5
TOTAL 5.12
![Page 139: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/139.jpg)
Project Name: Raipur Araian Sand Mine, Punjab. Final EIA/EMP Section – IX: Executive Summary
Page 12/IX
9.16 MONITORING SCHEDULE AND PARAMETERS:
Table 9.4 Monitoring Schedule and Parameters
Sl No
Description of Parameters Schedule and Duration of Monitoring
1 Air Quality: a) In the vicinity of the mine b) In the vicinity of the transportation network
24 hourly samples twice a week for one month in each season except monsoon season
2 Water Quality near or around the site: a) Surface water quality b) Ground water quality
Once in a season for 4 seasons in a year
3 Ambient Noise Level Twice a year for two years & then once a year
4 Soil Quality Once in two years on project monitoring area
5 Inventory of Flora(tree plantation, survival etc) & Fauna
Once in two years on project monitoring area
6 Socio-economic condition of local, population, physical survey
Once in 3 years
BENEFITS OF MINING
i. Controlling river channel.
ii. Protecting river banks.
iii. Reducing submergence of adjoining agricultural lands.
iv. Reducing aggradations of river level.
v. Generating useful economic resource for construction.
vi. Generating employment.
vii. Improvement in socio economic conditions of the people of the study area.
***********
![Page 140: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/140.jpg)
1/X
CHAPTER-X
DISCLOSURE OF CONSULTANT ENGAGED
The EIA/EMP Report for Raipur Arain Mining Project has been prepared by
Grass Roots Research & Creation India (P) Ltd.
Name of the
Consultant
Address
Grass Roots Research &
Creation India (P) Ltd.
F:374- 375, Sector: 63,
Noida, India
ISO 9001: 2008 (QMS),
14001:2004 (EMS) &
OHSAS 18001: 2007
Certified Co.
Accredited by QCI/NABET.
Name of the
Laboratory
Address
GRC India Training and
Analytical Laboratory
F- 375, Sector: 63, Noida,
India
NABL Accredited
Laboratory,
Recognized by MoEF under
Environment (Protection)
Act, 1986.
A unit of GRC India (P) Ltd.
![Page 141: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/141.jpg)
2/X
The EIA/EMP report has been prepared under the guidance of the following
Coordinator & Functional Area Experts:
EIA Coordinator Mr. K D Choudhury
FAE- AP Mr. K D Choudhury
FAE- NV Mr. K D Choudhury
FAE- EB Dr. P R Chaudhari
FAE- WP Dr. P R Chaudhari
FAE- SE Mr. K N Dutta
FAE- Soil Dr. S. R. Maley
FAE- Geology Dr. Tapan Mazumder
FAE- Hydrology Dr. Tapan Mazumder
FAE- RH Dr. Ravindra Kode
FAE- Land Use Mr. P Radhakrishnamoorthy
FAE- SHW Ms. Anasua Nag
FAE- AQM Prof. B Padmanabha Murty
The following team was involved under the guidance of experts for preparation of the report:
Personnel involved in
Preparation of EIA/EMP
report as Team Member
Mr. Sourav Seal (Project Associate)
Mr. Varghese Mathew
Mr. Ashish Verma (FAE)
![Page 142: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/142.jpg)
3/X
Accreditation from Quality Council of India, QCI NABET
Grass Roots Research & Creation India (P) Ltd. has got the Initial accreditation
from QCI NABET and has undergone Surveillance Assessment as well. The result
of continued accreditation is published on the QCI website as SAAC 69th and
subsequent Minutes of Meeting in the year 2013-14.
As per the recently published QCI NABET ‘List of Accredited Consultant
Organizations/Rev. 25/December 05, 2014’, listed in as accredited consultant,
Category ‘A’ Sl. No. 72. The list of accredited consultants is published on QCI
NABET and MoEF websites as well.
For reference, a snapshots of the list where GRC India’s name is listed is pasted
below:
![Page 143: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/143.jpg)
4/X
*********
![Page 144: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/144.jpg)
ANNEXURES
![Page 145: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/145.jpg)
SURFACE PLAN
1 2 3 4 5
10 9 8 7 6
151474/131211
20 19 18 17 16
21 22 23 24 25
1 2 3 4 5
10 9 8 76
5
80/15 11 12
16 20 19
25 21 22/1 23/2 24
1 2 3 4
10 9 81/8 7
11 12 13 14
15141312 1512 141311
19 18 17 19 18 172016 16
22 23 24 25 22 23 24 2521
21 22 23/1 24 25
20/2
11/1
10
1
21
20/2
11 12 18/13 1415/2 15/3
16171819
24/2 23 24/1 24/2 25
2 3 4
9 7 68/1
8/2
11/2 12 25/13 14/2
20/1 19 18
17/1
17/2
15/1
15/2
16/2
5/2
5/2
N
Scale (1:2000)1cm=2000
LEGEND
S.no Particulars Symbol
1
2
3
4
5
6
Boundary
Contour line
Agri land
Govt. waste land
Khasra no
River sand
Road
Village :-
Tehsil :-
Dist :-
State :-
SAND MINE
Area :-
105.2106.6
63/14
A1 A2
A3A4
A5A6
A7A8
B1 B2
B3B4
C1C2
C3C4
C5 C6
C7C8
C9C10
C11C12
Raipur Araian
Nakodar
Jalandharpunjab
11.79 ha
![Page 146: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/146.jpg)
![Page 147: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/147.jpg)
![Page 148: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/148.jpg)
![Page 149: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/149.jpg)
![Page 150: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/150.jpg)
![Page 151: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/151.jpg)
![Page 152: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/152.jpg)
![Page 153: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/153.jpg)
![Page 154: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/154.jpg)
![Page 155: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/155.jpg)
![Page 156: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/156.jpg)
![Page 157: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/157.jpg)
![Page 158: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/158.jpg)
![Page 159: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/159.jpg)
![Page 160: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/160.jpg)
![Page 161: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/161.jpg)
![Page 162: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/162.jpg)
![Page 163: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/163.jpg)
![Page 164: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/164.jpg)
![Page 165: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/165.jpg)
Annexure II
Name of project RAIPUR ARAIAN SAND MINING
Location name ASHOUR
Location code AQ-1
S.No Date
PM10
(µg/m3) SO2 (µg/m3)
Nox (as NO2)
(µg/m3)
IS:5182:Pt-23 IS:5182:Pt-2 IS:5182:Pt-6
1 01.03.11 75.7 7.3 18.2
2 05.03.11 77.2 9.5 19.4
3 08.03.11 78.7 6.9 20.4
4 12.03.11 80.1 10.1 21.4
5 16.03.11 81.6 8.3 22.7
6 20.03.11 83.0 9.1 23.4
7 24.03.11 84.5 7.6 25.4
8 28.03.11 83.3 10.6 19.2
9 01.04.11 79.3 8.5 21.2
10 05.04.11 80.5 10.8 22.0
11 08.04.11 82.0 9.0 22.4
12 12.04.11 83.5 8.7 21.7
13 16.04.11 94.6 11.0 24.0
14 20.04.11 92.1 13.4 19.7
15 23.04.11 90.5 10.2 17.7
16 27.04.11 92.1 7.5 18.7
17 01.05.11 92.6 9.8 20.8
18 05.05.11 79.9 10.8 23.1
19 09.05.11 84.2 11.4 18.4
20 13.05.11 79.6 8.5 20.3
21 17.05.11 83.8 11.2 23.4
22 20.05.11 85.3 9.4 14.3
23 24.05.11 75.5 11.6 16.2
24 28.05.11 77.0 7.2 14.0
Minimum 75.5 6.9 14.0
Maximum 94.6 13.4 25.4
Average 83.2 9.5 20.3
98 Percentile 93.7 12.6 24.8
NAAQS (For 24 hrs.
except CO) 100 80 80
![Page 166: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/166.jpg)
Name of project RAIPUR ARAIAN SAND MINING
Location name RAUR
Location code AQ-2
S.No Date
PM10
(µg/m3) SO2 (µg/m3)
Nox (as NO2)
(µg/m3)
IS:5182:Pt-23 IS:5182:Pt-2 IS:5182:Pt-6
1 03.03.11 77.7 9.2 19.4
2 07.03.11 79.1 8.9 17.4
3 10.03.11 80.6 8.8 18.0
4 14.03.11 82.0 11.7 17.9
5 18.03.11 83.5 10.2 21.0
6 22.03.11 84.9 11.0 25.3
7 26.03.11 86.4 9.5 18.1
8 30.03.11 85.1 10.8 22.4
9 03.04.11 81.3 11.3 25.9
10 07.04.11 82.5 10.6 26.4
11 10.04.11 84.0 11.8 27.1
12 14.04.11 85.5 10.6 29.4
13 18.04.11 94.0 12.7 26.1
14 21.04.11 91.4 15.2 24.4
15 25.04.11 96.0 14.3 23.7
16 29.04.11 97.7 9.4 23.4
17 03.05.11 99.4 13.0 23.4
18 07.05.11 94.6 9.0 22.4
19 11.05.11 86.2 9.6 22.9
20 15.05.11 81.6 10.4 24.9
21 19.05.11 85.8 13.1 27.4
22 22.05.11 87.3 11.3 14.6
23 26.05.11 77.5 10.9 22.0
24 30.05.11 79.0 9.1 18.0
Minimum 77.5 8.8 14.6
Maximum 99.4 15.2 29.4
Average 86.0 10.9 22.6
98 Percentile 98.6 14.8 28.5
NAAQS (For 24 hrs.
except CO) 100 80 80
![Page 167: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/167.jpg)
Name of project RAIPUR ARAIAN SAND MINING
Location name NEAR SITE
Location code AQ-3
S.No Date
PM2.5
(µg/m3)
PM10
(µg/m3) SO2 (µg/m3)
Nox (as NO2)
(µg/m3)
Gravimetric
IS:5182:Pt-
23 IS:5182:Pt-2 IS:5182:Pt-6
1 04.03.11 32.7 75.0 7.2 19.2
2 07.03.11 31.8 77.1 6.9 17.2
3 11.03.11 34.0 76.1 10.0 14.3
4 14.03.11 33.0 77.6 7.4 13.7
5 18.03.11 35.2 79.0 8.2 15.2
6 21.03.11 33.7 78.2 9.0 16.7
7 25.03.11 34.3 80.6 7.5 13.9
8 28.03.11 35.6 83.7 10.6 18.0
9 02.04.11 31.6 74.3 8.4 16.4
10 05.04.11 36.0 75.4 11.0 19.4
11 09.04.11 32.7 76.8 8.9 16.5
12 12.04.11 39.0 78.3 11.7 15.9
13 16.04.11 37.8 89.3 14.8 24.7
14 19.04.11 35.0 85.7 7.8 17.2
15 23.04.11 37.4 84.0 12.0 18.7
16 26.04.11 36.4 85.0 7.4 20.0
17 02.05.11 34.6 86.5 12.4 18.0
18 05.05.11 33.7 82.3 7.0 21.4
19 09.05.11 34.7 85.0 7.6 18.2
20 12.05.11 32.8 80.4 12.9 23.0
21 16.05.11 33.4 81.8 11.1 21.0
22 19.05.11 34.0 83.3 9.3 20.4
23 23.05.11 31.0 73.7 7.0 18.3
24 26.05.11 30.7 75.2 7.1 15.5
Minimum 30.7 73.7 6.9 13.7
Maximum 39.0 89.3 14.8 24.7
Average 34.2 80.2 9.3 18.0
98 Percentile 38.4 88.0 13.9 23.9
NAAQS (For 24 hrs.
except CO) 60 100 80 80
![Page 168: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/168.jpg)
Name of project RAIPUR ARAIAN SAND MINING
Location name RAIPUR
Location code AQ-4
S.No Date
PM10
(µg/m3) SO2 (µg/m3)
Nox (as NO2)
(µg/m3)
IS:5182:Pt-23 IS:5182:Pt-2 IS:5182:Pt-6
1 02.03.11 77.0 8.8 19.1
2 06.03.11 78.4 10.7 19.2
3 09.03.11 79.9 8.4 16.4
4 13.03.11 81.3 11.4 17.1
5 17.03.11 82.8 9.8 18.6
6 21.03.11 84.2 10.6 24.4
7 25.03.11 85.7 9.1 17.3
8 29.03.11 84.4 8.6 21.4
9 02.04.11 80.5 10.0 24.9
10 06.04.11 82.0 11.3 25.4
11 09.04.11 84.1 10.5 26.1
12 13.04.11 84.8 11.9 25.4
13 17.04.11 93.2 10.1 28.5
14 21.04.11 90.7 14.2 23.4
15 24.04.11 91.8 8.6 22.0
16 28.04.11 93.4 9.0 24.1
17 02.05.11 94.0 8.7 21.7
18 06.05.11 81.1 12.0 22.7
19 10.05.11 85.4 9.2 22.0
20 14.05.11 80.8 10.0 23.9
21 18.05.11 85.0 12.7 26.5
22 21.05.11 86.5 10.9 16.8
23 25.05.11 76.8 11.7 17.0
24 29.05.11 78.3 8.7 15.2
Minimum 76.8 8.4 15.2
Maximum 94.0 14.2 28.5
Average 84.2 10.3 21.6
98 Percentile 93.7 13.5 27.6
NAAQS (For 24 hrs.
except CO) 100 80 80
![Page 169: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/169.jpg)
Name of project RAIPUR ARAIAN SAND MINING
Location name CHUHARWALA
Location code AQ-5
S.No Date
PM10
(µg/m3) SO2 (µg/m3)
Nox (as NO2)
(µg/m3)
IS:5182:Pt-23 IS:5182:Pt-2 IS:5182:Pt-6
1 04.03.11 78.2 9.5 19.0
2 07.03.11 79.6 9.2 23.1
3 11.03.11 81.1 10.5 20.0
4 15.03.11 82.5 9.7 18.4
5 19.03.11 84.0 10.5 20.0
6 23.03.11 85.4 11.3 26.0
7 27.03.11 86.9 9.8 18.6
8 31.03.11 85.6 11.9 23.2
9 04.04.11 82.0 10.7 26.6
10 07.04.11 83.0 10.9 27.1
11 11.04.11 84.5 11.2 28.7
12 15.04.11 96.3 15.0 30.2
13 19.04.11 98.0 13.2 26.9
14 22.04.11 99.4 12.0 25.1
15 26.04.11 96.6 11.0 23.2
16 30.04.11 98.3 9.7 24.2
17 04.05.11 100.0 12.0 24.1
18 08.05.11 85.0 10.6 23.2
19 12.05.11 86.6 9.9 25.8
20 16.05.11 82.0 10.7 25.6
21 20.05.11 86.3 13.4 28.0
22 23.05.11 87.8 11.6 15.0
23 27.05.11 78.0 12.2 19.8
24 31.05.11 79.5 9.4 16.5
Minimum 78.0 9.2 15.0
Maximum 100.0 15.0 30.2
Average 86.9 11.1 23.3
98 Percentile 99.7 14.3 29.5
NAAQS (For 24 hrs.
except CO) 100 80 80
![Page 170: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/170.jpg)
Annexure-V
Data on Population, Literacy rate, Main & Marginal Workers in respect of identified
villages/towns in the Study Area
S.No
Village /
town /
city
name
No. of
Househol
ds
Population
Sex
Ratio SC
Over all
Literacy
rate
Gender
Gap in
Literacy
Rate
Total Male Female
1 2 3 4 5 6 7 8 9 10
1 Adrama
n 399 2407 1256 1151 916 681 68.4 13.6
2 Awan
Khalsa 120 744 386 358 927 117 76.9 10.7
3 Baghela 300 1686 882 804 912 495 67.8 20.3
4 Bansian 4 18 11 7 636 7 80.0 22.2
5 Bulanda 215 1160 597 563 943 405 70.4 5.4
6 Baloki 217 1148 603 545 904 331 72.6 18.4
7 Behar 120 663 346 317 916 8 52.7 17.4
8 Bhaini 148 788 421 367 872 494 72.0 5.7
9 Bhoda 126 647 344 303 881 56 56.4 17.2
10 Bhundri 7 41 22 19 864 41 53.3 39.8
11 Bitlan 104 570 289 281 972 15 59.6 27.3
12 Gadra 57 368 198 170 859 311 72.6 4.3
13 Gursian
Nihal 120 708 366 342 934 318 67.4 14.2
14 Ghuduw
al 187 1095 561 534 952 134 73.3 13.0
15 Hardo
Sangha 64 432 227 205 903 121 72.2 6.5
16 Hazara 250 1317 681 636 934 474 74.0 10.7
17 Jandir 201 1069 536 533 994 255 82.0 12.0
18
Jhungia
n
Mahansi
ngh
33 210 116 94 810 117 79.9 6.9
19 Jhungia
n 180 992 511 481 941 266 66.7 11.2
20 Khiala 23 130 66 64 970 54 78.9 15.5
21 Khuram
pur 129 819 434 385 887 123 77.1 13.7
22 Killi 121 740 357 383 1073 402 69.2 19.9
23 Littran 344 1849 946 903 955 819 74.0 7.8
24 Madar 332 1861 955 906 949 1108 74.4 14.5
25 Mansurp
ur 229 1182 652 530 813 610 73.8 10.8
26 Mand 257 1336 701 635 906 501 81.4 14.8
27 Naurang
pur 97 553 296 257 868 162 83.3 12.1
![Page 171: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/171.jpg)
28 Udhowal 242 1365 706 659 933 538 73.3 11.3
29 Pasarian 77 480 247 233 943 114 81.2 5.4
30 Rajowal 171 964 492 472 959 458 69.4 11.5
31 Ramunw
al 150 793 433 360 831 551 64.1 12.5
32 Raowali 331 1706 1033 673 652 666 72.4 7.6
33 Rasulpu
r 102 539 287 252 878 165 87.9 13.2
34 Sangow
al 387 1877 1017 860 846 1002 46.8 7.4
35
Salempu
r
Masand
an
276 1488 806 682 846 398 76.1 9.8
36 Shekhe
wal 60 315 163 152 933 129 77.2 14.8
37 Singhpu
r 88 480 255 225 882 365 51.8 14.3
38 Talwara 18 89 51 38 745 0 68.7 24.9
39 Tandaur
a 177 1016 521 495 950 335 72.9 9.6
40 Umrewal 62 337 180 157 872 4 58.5 26.9
41 Ummar
wal Billa 400 2289 1167 1122 961 819 69.7 10.5
42 Raipur
Araian 235 1320 685 635 927 84 58.9 15.5
43 Samailp
ur 161 898 464 434 935 7 55.3 11.9
44 Sadarpu
r 26 140 67 73 1090 126 65.8 9.7
45 Giddarpi
ndi 2 9 6 3 500 0 77.8 16.7
Continued………….
S.No Village/town/city Name
Workers Agricultural Workers HH Ind. Workers
Other workers
![Page 172: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/172.jpg)
Total Main Marginal Total Cultivators Agri.
Labours
11 12 13 14 15 16 17 18
1 Adraman 812 716 96 517 222 295 4 291
2 Awan Khalsa 287 270 17 132 112 20 15 140
3 Baghela 553 462 91 409 195 214 10 134
4 Bansian 5 5 0 3 1 2 0 2
5 Bulanda 389 370 19 172 131 41 16 201
6 Baloki 495 416 79 227 157 70 4 264
7 Behar 287 199 88 269 180 89 0 18
8 Bhaini 247 230 17 52 51 1 5 190
9 Bhoda 193 191 2 169 138 31 1 23
10 Bhundri 14 14 0 10 9 1 0 4
11 Bitlan 183 143 40 134 80 54 2 47
12 Gadra 124 108 16 80 54 26 3 41
13 Gursian Nihal 266 260 6 186 156 30 40 40
14 Ghuduwal 573 381 192 200 169 31 6 367
15 Hardo Sangha 147 141 6 105 82 23 1 41
16 Hazara 352 348 4 112 80 32 9 231
17 Jandir 258 250 8 94 62 32 2 162
18
Jhungian
Mahansingh 84 49 35 43 35 8 0 41
19 Jhungian 333 236 97 174 133 41 3 156
20 Khiala 70 36 34 21 15 6 0 49
21 Khurampur 278 266 12 108 86 22 18 152
22 Killi 283 199 84 191 88 103 1 91
23 Littran 744 708 36 243 166 77 55 446
24 Madar 515 396 119 233 55 178 6 276
25 Mansurpur 365 359 6 177 122 55 15 173
![Page 173: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/173.jpg)
*************************
26 Mand 446 430 16 121 102 19 16 309
27 Naurangpur 208 186 22 175 138 37 4 29
28 Udhowal 460 293 167 341 144 197 4 115
29 Pasarian 156 156 0 80 66 14 11 65
30 Rajowal 283 264 19 204 110 94 12 67
31 Ramunwal 288 266 22 177 83 94 7 104
32 Raowali 689 523 166 101 68 33 28 560
33 Rasulpur 171 169 2 27 14 13 0 144
34 Sangowal 614 581 33 491 144 347 7 116
35
Salempur
Masandan 659 537 122 382 248 134 10 267
36 Shekhewal 80 80 0 32 17 15 0 48
37 Singhpur 161 158 3 15 15 0 4 142
38 Talwara 37 37 0 36 36 0 0 1
39 Tandaura 501 360 141 420 296 124 0 81
40 Umrewal 95 91 4 83 55 28 1 11
41 Ummarwal Billa 835 812 23 649 327 322 6 180
42 Raipur Araian 485 454 31 355 266 89 11 119
43 Samailpur 321 244 77 293 212 81 4 24
44 Sadarpur 40 30 10 36 2 34 0 4
45 Giddarpindi 4 4 0 3 3 0 0 1
![Page 174: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/174.jpg)
![Page 175: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/175.jpg)
APPENDIX
![Page 176: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/176.jpg)
Q-1
PROFORMA FOR ENVIRONMENTAL APPRAISAL OF MINING PROJECTS
(MINING SECTOR PROJECTS)
1. General Information
1. General information
a Name of the project Raipur Araian Sand Mining Project
I Name of the proponent GM-cum-Mining Officer, Jalandhar Punjab
ii Mailing Address General Manager-cum-Mining Officer, District
Industries Centre,
District Jalandhar
E-mail [email protected]
Telephone +91-9876363311
Fax No.
b Objective of the project River bed mining for sand
c Location of mine
Village Raipur Araian, H.B. No 88
Tehsil Phillor
District Jalandhar
State Punjab
Note 1: All information to be given in the form of Annex/s should be properly
numbered and form part of reply to this proforma.
Note 2: Please enter √ in appropriate box where answer is Yes / No
Note 3: No abbreviation to be used - Not available or Not applicable should be
clearly mentioned.
Note 4: Core zone is the mining lease area.
Buffer zone in case of ML area up to 25 ha is to be considered as 5 km all
around the periphery of the core zone and for ML area above 25 ha an area
10 km all around the periphery of the core zone.
Note 5: Adopt Scoping process in carrying out EIA study.
![Page 177: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/177.jpg)
Q-2
d Does the proposal relate to Yes No
i New mine √ -
ii Expansion - √
iii Increase in ML area - √
iv Increase in annual production - √
v Renewal of ML - √
vi Modernization - √
e Site Information
i Geographical Location
Latitude 31° 0'56.09"N to 31° 1'7.46"N
Longitude 75°53'38.43"E to 75°54'8.92"E
Survey of India Topo sheet number 44M/16 Elevation above Mean Sea Level Highest- 240m AMSL
Lowest – 238 m AMSL Total mining lease area (in ha.) 17.98 ii Dominant nature of terrain Yes No
Flat √ -
Undulated - √
Hilly - √
2. Land usage of the mining lease area (in ha.)
a Agricultural -
b Forest -
c Waste land -
d Grazing -
e Surface water bodies -
f Others (River Bed ) 17.98
Total 17.98
3. Indicate the seismic zone in which ML area falls. In case of zone IV & V, details of earth quakes in last 10 years.
Seismic Zone – III
a Severity (Richter Scale)
b Impact i.e. Damage to Yes No
Life - √
Property - √
Existing mine - √
![Page 178: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/178.jpg)
Q-3
4. Break-up of mining lease area (in ha.) as per approved conceptual plan:
Purpose
Mining Lease Area
Total
Area acquired Area to be acquired
Government Private Government Private Government Private
Forest Others Agri. Others Forest Others Agri. Others Forest Others Agri. Others
1. Area to be excavated - 14.348 - - 8.99 8.99
2. Storage for top soil - - - - - -
3. Overburden / Dumps - - - - - -
4. Mineral storage - - - - - -
5. Infrastructure
(Workshop,
Administrative Building)
- - - - - -
6. Roads - - - - - -
7. Railways - - - - - -
8. Green Belt - - - - - -
9.Tailings pond - - - - - -
10.Effluent treatment plant - - - - - -
11.Coal handling plant /
mineral separation plant
- - - - - -
12. Township area - - - - - -
13.Other (Safety zone
including road)
- 3.596 - - 3.596 3.596
TOTAL - 17.98 - - 17.98 17.98
![Page 179: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/179.jpg)
Q-4
5 Township (outside mining lease) Not Applicable
a Total area (in ha) -
b No. of dwelling units -
c Distance from mine site -
6 Distance of water bodies (in km)
Distance from
River Bank * Other Water bodies * Sea / creek / lake / nalla etc.
(specify) Mining lease boundary
It is a river bed mining -
Ancillary facilities
- -
[* From highest flood line / high tide line]
7 For projects falling within the Coastal Regulation Zone (CRZ) Whether the mineral to be mined is of rare
nature and not available outside CRZ? Yes - No √
if yes, annex a scaled location map showing low tide line (LTL), high tide line (HTL) duly demarcated by one of the authorized agencies* [ *Director, Space Application Centre, Ahmedabad: Centre for Earth Sciences Studies, Thiruvananthapuram: Institute of Remote Sensing, Anna University, Chennai: Institute of Wetland Management & Ecological Designs, KolKata: Naval Hydrographers’s Office, Dehradun: National Institute of Oceanography, Panjim, Goa: and National Institute of Ocean Technology, Chennai], boundary of mining lease area, distance of ML area from LTL and HTL CRZ boundary and CRZ classification of the project area as per the approved Coastal Zone Management Plan, and settlements, sand dunes, mangroves, forest land/patches, turtles breeding and nesting sites etc., if any, in the project area.
8 Indicate aerial distance from the periphery of core zone / area from the periphery of the buffer zone to the boundary of following (up to 10 km):
S. No.
Area Name
Aerial distance from (in km.)
Core Zone Buffer Zone 1. National Park / Sanctuary
Nil - -
2. Biosphere Reserve / Tiger Reserve / Elephant Reserve / any other Reserve
Nil - -
3. Forest (RF / PF / unclassified)
Nil
-
4. Habitat for migratory birds Nil - 5. Corridor for animals of
schedule I & II of the Wildlife (Protection) Act, 1972
Nil - -
6. Archaeological sites * Notified
* Others Nil - -
![Page 180: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/180.jpg)
Q-5
7.
Defence Installation Nil - -
8. Industries / Thermal Power Plants
Nil - -
9. Other Mines Chaulle Sand Mine - About 3.5 Km in East Direction
10. Airport Nil - -
11. Railway Lines Nil - -
12. National / State Highways Nil - - [* Buffer zone in case of ML area up to 25 ha. is to be considered as 5 km all around the periphery of the core zone and for ML area above 25 ha. an area 10 km all around the periphery of the core zone]. 9. Description of flora & fauna separately in the core and buffer zones.* [* Consult the Wildlife (Protection) Act, 1972 as amended subsequently and list species with (1) Common name (2) Scientific name and (3) under which schedule of the Wildlife (Protection) Act the identified species fall. Get the list authenticated by an Expert in the field / credible scientific institute / University / Chief Wildlife Warden Office. Information to be based on field survey List of Flora & Fauna is given in Section III of Final EIA report.
10 Details of mineral reserves (as per approved Mining Plan)
Quantity (in tonnes)
a Proved 4,85,460 b Indicated - c Inferred - d Mineable reserves 4,85,460
11 Major geological formation / disturbances in the mining lease area
Yes No
a Geological maps submitted √ - b Geological sections submitted - √
c Contour map submitted - √
d Whether the presence, if any, noted of I Faults - √
Ii Dykes - √
Iii Shear Zone - √
Iv Folds - √
V Other weak zones - √
e Source of data (Indicate) - 12 Production of mineral(s) and life of mine a Rated capacity of mine mineral wise (Tonnes /
annum) 1,61,820 TPA
b Life of mine at proposed capacity (Years) - c Lease period (Years) - d Date of expiry of lease (D /M /Y) - e
Indicate in case of existing mines -
i Date of opening of mine After environmental clearance
![Page 181: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/181.jpg)
Q-6
ii Production in the last 5 years 1st year 5th year from year……… to year ……… in million tonnes.
-
iii Projected production for the next 6th to 10th year 5 years from year ……… to year ………..in million tonnes.
-
iv Whether mining was suspended after opening of the mine?
-
v If yes, details thereof including last production figure and reason for the same.
-
f Whether plans & sections provided? - 13 Type and method of mining operations
TYPE METHOD Opencast √ Manual - Underground - Semi-Mechanized √ Both - - -
14 Details of ancillary operations for mineral processing a Existing Not applicable b Additional Not applicable
15 Mine details a Opencast mine i Stripping ratio (mineral in tonnes to over burden in
m3) -
ii Ultimate working depth (in m bgl) 3 m iii Indicate present working depth in case of existing
mine (in m bgl) -
iv Thickness of top soil (in m.) -
a Minimum - b Maximum -
c Average - v Thickness of overburden (in m.) - a Minimum - b Maximum -
c Average - vi Mining Plan a Height and width of the bench in overburden /
waste. -
b Height & width of the bench in ore body / coal seam.
-
c Proposed inclination / slope of the sides of the opencast mine (separately for overburden, coal / ore and overall slope of the pit sides) both while operating the mine as well as at the time of closure of the mine.
-
d Whether transverse sections across the open cast mine at the end of fifth year and at the end of the life of the mine have been submitted?
-
vii Type of blasting, if any, to be adopted - b Underground mine- Not Applicable
i Seam / Ore body
![Page 182: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/182.jpg)
Q-7
Min. Depth (m) -
Max. Depth (m) -
Avg. thickness (m) -
Rate of dip -
Direction of dip in degree -
ii Mode of entry into the mine
Shaft -
Adit -
Incline -
iii Details of machinery
On surface -
At Face -
For transportation -
Others -
iv Method of stopping (metalliferrous mines) Open -
Filled -
Shrinkage -
Caving -
Combination of above -
Others (Specify) -
v Extraction method
Caving -
Stowing -
Partial extraction -
vi Subsidence
Predicted max. subsidence (in m) -
Max. value of tensile strain (in mm/m) -
Max. slope change (in mm/m) -
Whether identified possible subsidence area(s) superimposed on Surface Plan has been submitted?
-
Major impacts on surface features like natural drainage pattern, houses, buildings, water bodies, roads, forest, etc.
-
Salient features of subsidence management (monitoring and control).
-
16 Surface drainage pattern at mine site Yes No
a Whether the pre-mining surface drainage plan submitted?
- √
b Do you propose any modification / diversion in the existing natural drainage pattern at any stage? If yes, when. Provide location map indicating contours, dimensions of water body to be diverted, direction of flow of water and proposed route / changes, if any i.e. realignment of river / nallah / any other water body falling within core zone and its impact
- √
![Page 183: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/183.jpg)
Q-8
17 Embankment and / or weir construction
a Do you propose, at any stage, construction of
i Embankment for protection against flood? No
ii Weir for water storage for the mine? No
b If so, provide details thereof. -
c Impact of embankment on HFL and settlement around.
-
d Impact of weir on downstream users of water -
18 Vehicular traffic density (outside the ML area) Type of vehicles
No. of PCU per hour
a Existing Car, Jeep, Truck
75
b After the proposed activity Car, Jeep, Truck
99
c Whether the existing road network is adequate? Yes
If no, provide details of alternative proposal? -
19 Loading, transportation and unloading of mineral and waste rocks on surface
Yes No
a Manual √ -
b Tubs, mine cars, etc. - √
c Scraper, shovels, dumpers / trucks √ -
d Conveyors (belt, chain, etc.) - √
e Others (specify) - √
20 Mineral(s) transportation outside the ML area
Qty. (in TPD) Percentage
(%)
Length (in
km)
a Road 668 100 -
b Rail - - -
c Conveyors - - -
d Rope way - - -
e Water ways - - -
f Pipeline - - -
g Others (Specify) - - -
Total 668 100 -
![Page 184: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/184.jpg)
Q-9
21. Baseline Meteorological and Air Quality data (a) Micro-meteorological data
[Continuous monitoring through autographic instrument for one full season other than monsoon] (i) Wind rose pattern for one full season (16 points of compass i.e. N, NNE, NE, ---) based on 24-hourly data. For coastal area also
furnish day-time and night time data. • Day time • Night time • 24 – hours period
(ii) Site specific monitored data
Month
Wind Speed (kmph) Temperature (oC) Relative Humidity (%) Rain Fall * (mm)
Cloud Cover**
(Octas of sky)
Mean Max. % of
calm Mean
(Dry Bulb) Highest Lowest Mean Highe
st Lowest Total 24-hours
Highest No. of rainy days
Mean
March,11 3 14 1.9 - 31.1 8.6 - - - 11 4 2 - April,11 3.4 15 1.0 - 39.7 10.8 - - - 21 12 2 - May,11 4.2 20 0.84 - 42.2 20.8 - - - 25 19 1 -
* 24-hours rainfall should be reported from 08:30 hrs. IST of previous day to 08:30 hrs. IST of the day. * Rainy day is considered when 24 hrs. rainfall is ≥ 2.5 mm. ** Visual observations of cloud cover should be recorded four times a day at regular intervals.
(iii) Indicate name and distance of the nearest IMD meteorological station from which climatological data have been obtained for reporting in the EIA report, if any. Ludhiana 35 km SE Direction
(b) Ambient air quality data* (RPM, SPM, SO2, and NOx) [*Monitoring should be carried out covering one full season except monsoon – same season as in 21 (a) (i)] [*Frequency of sampling: Sampling to be done twice a week for the entire season 24 hourly for SPM & RPM. For gaseous pollutants
24- hourly data be given irrespective of the sampling period. ]
(i) Season and period for which monitoring has been carried out. Pre Monsoon (March-May, 2011)
(ii) No. of samples collected at each monitoring station: 24
![Page 185: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/185.jpg)
Q-10
Name of monitoring equipment
used
PM2.5 (µg/m3) PM10 (µg/m3) SO2 (µg/m3) Nox (µg/m3) Pb**
Envirotech FPS – APM 5.50
RDS 460 BL APM 411 attachment with RDS 460 BL
APM 411 attachment with RDS 460 BL
-
Equipment sensitivity
< 0.5 µg/m3 from 0.000 mg to 0.100
mg/ m3
< 0.5 µg/m3 from 0.000 mg to 0.100 mg/ m3
< 0.5 µg/m3 from 0.000 mg to 0.100
mg/ m3
< 0.5 µg/m3 from 0.000 mg to 0.100
mg/ m3
-
Permissible AAQ standard (CPCB) R
I
S
60 µg/m3 100 µg/m3 80 µg/m3 80 µg/m3 -
60 µg/m3 100 µg/m3 80 µg/m3 80 µg/m3 -
60 µg/m3 100 µg/m3 80 µg/m3 80 µg/m3 -
Monitoring Location
No. of Sample
s Drawn
Category*
(R, I, S)
Min. Max. 98% tile
Min. Max. 98% tile
Min. Max. 98% tile
Min. Max. 98% tile
Min.
Max.
98% tile
Core zone
CA1 24 I 30.7 39.0 38.4 73.7 89.3 88.0 6.9 14.8 13.9 13.7 24.7 23.9 - - -
Buffer zone BA1
24 R - - - 75.5 94.6 93.7 6.9 13.4 12.6 14.0 25.4 24.8 - - -
BA2 24 R - - - 77.5 99.4 98.6 8.8 15.2 14.8 14.6 29.4 28.5 - - -
BA3 24 R - - - 76.8 94.0 93.7 8.4 14.2 13.5 15.2 28.5 27.6 - - -
BA4 24 R - - - 78.0 100.0 99.7 9.2 15.0 14.3 15.0 30.2 29.5 - - -
*R = Residential; I = Industrial; S = Sensitive **Pb for mineral specific sites only. # Annex a location map indicating location of AAQ stations, their direction and distance with respect to project site. (AAQ station location map is attached in Section III)
![Page 186: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/186.jpg)
Q-11
22. Stack and emission details, if any* Not Applicable
S. No.
Process / unit of operation (e.g. DG Set, Boiler)
Height of stack (m)
Internal top dia. (m)
Flue gas exit velocity (m/sec)
Emission rate (kg/hr) Heat emission rate from top of stack (K.cal/hr)
Exhaust / Flue gas
SPM SO2 NO2 CO Temp
OC Density Specific
Heat Volumetric flow rate (m3/hr.)
23. Details of fugitive emissions during mining operations*
Not Applicable
24. Air Quality Impact Prediction (AQIP)* Not Applicable
(a) Details of model(s) used for AQIP including grid size, terrain features, and input meteorological data
(b) Maximum incremental GLC values of pollutants based on prediction exercise
(in µg/m3) S. No. Pollutants
Incremental Value Ambient Air Quality Resultant Air Quality
1. SPM
2**. SO2
3**. NOX
[* Question Number 22, 23 & 24 need not be filled-in for mines having ML area of 25 ha. or less.] [**Information on item no. 2 & 3 to be provided in cases with captive power generation of 500 KVA and above]
![Page 187: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/187.jpg)
Q-12
25. Water requirement (m3/day) Purpose Avg. Demand Peak Demand A. Mine site 1. Mine operation - -
2. Land reclamation - -
3. Dust suppression 0.7 0.7
4. Drinking 1.00 1.00
5. Green Belt - -
6. Beneficiation - -
7. Washeries - -
8. Fire Service - -
9. Others (specify) - -
B. Township
1. Green Belt - -
2. Domestic - -
C. Other (specify) - -
Total 1.7 1.7
26. Source of water supply*
S. No. Source m3/day
1 River (name) -
2 Ground water 1.7 KLD from nearby village
3 Mine water (sump / pit) -
4 Other surface water bodies (specify) -
[*Annex a copy of sanction letter / permission from the concerned authority (Central Ground Water Authority in case of ground water abstraction is from notified area / State Ground Water Board in case of non-notified area / State Irrigation Department for surface water pumping) for drawing water.]
![Page 188: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/188.jpg)
Q-13
27 Lean season flow in case of pumping from river / nalla (cumecs)
Not applicable
28 Ground water potential of the study area 28.1 Ground water availability
a Range of water table (m bgl) - i Pre-monsoon (April/May) -
Core Zone 8-9 Buffer zone 8-15 ii Post-monsoon (November) - Core Zone 5-7 Buffer zone 5-10 b Total annual replenishable recharge (million m3/
year) -
c By ground water table fluctuation method - d By rainfall infiltration factor method - e Annual draft excluding estimated draft through
mine discharge (million m3/ year) -
f Estimated draft through mine discharge (million m3/ year)
-
g Net annual ground water availability (million m3/ year)
-
h Stage of ground water development (%) -
28.2. Water demand - Competing users of the water source
S. No.
Usage Present
Consumption (m3/day)
Additional proposed as per local plan
(m3/day)
Total (m3/day)
Surface Ground Surface Ground Surface Ground 1 Drinking - 1.0 - 1.0 2 Irrigation - - - - 3 Industry - - - -
4 Mining - - - -
5 Others (Dust suppression)
- 0.7 - 0.7
Total - 1.7 - 1.7
29. Water quality*
(a) Annex physico -chemical analysis of water at intake point **
Details are given in Section III
(b) In case of existing mine, annex report on quality of water discharge
i.e. complete physico - chemical analysis** [*For non-discharging mines at least four ground water samples to be taken preferably from downstream direction of the mine in pre-monsoon and post-monsoon periods and analysed. For discharging mines six samples are to be analysed]
![Page 189: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/189.jpg)
Q-14
**All parameters as per BIS 10500. Indicate name of Methodology, Equipment used for analysis, and Detection Level (DL) for each parameter.
*** Wherever any analytical parameter is below detection level, “BDL” (Below Detection Level) should be written instead of ‘NIL’.
30. Impact on ground water regime / stream / lake / springs due to mine dewatering *
a Radius of influence (in m) [To be estimated based on analysis of pumping test data and application of empirical formula]
-
b Whether saline water ingress will take place? (applicable to coastal areas)
-
c Impact on stream / lake / springs - [* Provide a comprehensive hydro-geological assessment report if the average mine dewatering is more than 100 m3/day and or going below water table in non-monsoon period. The report should be based on preferably latest one year pre-monsoon and post-monsoon baseline data covering information on ground water situation, aquifer characteristics, water level conditions (April – May and November), estimate of ground water resources, predicted impact of the project on ground water regime and detailed remedial / conservation measures such as artificial recharge of ground water etc. The report should be based on actual field inventory out of existing wells, at least 30 observation wells in the buffer zone with supplementary information from secondary sources (mention name). For estimation** of ground water resource (refer question no. 28 above) be designated study area of the buffer zone may be sub-divided into command and non-command areas, watershed-wise (in case of hard rock / consolidated formations) / block-wise / mandal-wise in case of alluvial / unconsolidated formations)]
[**For estimating ground water resources in the area follow the Ground Water
Estimation Committee recommendations of 1997]
31. Waste Water Management Not Applicable a Daily average discharge (m3/day) from
different sources
i Mine water discharge during Lean period Monsoon period ii Workshop iii Domestic (mine site) iv Beneficiation / Washeries v Coal Handling Plant vi Tailings pond vii Others (Specify) Total b Waste water treatment plant; flow sheet for
treatment process attached.
c Quantity of water recycled / reused / to be recycled in
i Percentage ii m3 /day d Point of final discharge
![Page 190: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/190.jpg)
Q-15
Final Point Quantity discharged (in m3/day)
1 Surface i Agricultural land ii Waste land iii Forest land iv Green belt 2 River / nallah 3 Lake 4 Sea 5 Others (specify) Total e Users of discharge water Yes No i Human ii Livestock iii Irrigation iv Industry v Others (specify) F Details of the river / nalla, if final effluent is /
will be discharged (cumecs)
i Average flow rate ii Lean season flow rate iii Aquatic life iv Analysis of river water 100 meters upstream
and 100 meters downstream of discharge point submitted.
g Township a Waste water generation from township
(m3/day)
b Are you planning to provide sewage treatment plant?
c Usage of treated water 32. Attach water balance statement in the form of a flow diagram
indicating source (s), consumption (Section-wise) and output.
Purpose Demand(KLD) Drinking 1.00 Dust suppression 0.7
Total 1.7
33 Ambient noise level leq dB(A)
Details given in Section III
34 Solid Waste Not Applicable a Top soil and Solid waste quantity and quality
Name (Lump/fines/slurry/
Sludge/others)
Composition Quantity (m3/month)
Method of disposal
Mining activity*
a. Top Soil b. Over burden c. Others (specify)
![Page 191: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/191.jpg)
Q-16
Effluent Treatment Plant (sludge)
Total [* Annex layout plan indicating the dump sites.]
b (i) Does waste (s) contain any hazardous/toxic substance/radioactive materials or heavy metals?
(ii) If yes, whether details and precautionary measures provided?
c Recovery and recycling possibilities. d Possible user(s) of the solid waste.
e (i) Is the solid waste suitable for backfilling? (ii) If yes, when do you propose to start
backfilling?
Solid waste (s)
Already accumulated
(A)
To be generated
(B)
% of A & B to be backfilled
A B Over burden
Others (specify)
Land reclamation Plan Not Applicable f In case waste is to be dumped on the
ground, indicate
i Associated environmental problems ii Number & type of waste dumps No. of external dumps Max. projected height of dumps (in m) No. of terraces and height of each stage Overall slope of the dump (degree) Proposed reclamation measures
iii Section of the waste dump in relation to the adjacent ground profile attached
35 Fuel / Energy requirements* [*To be furnished for mines having ML area mothan 25 ha. or captive power generation of 500KVA and above]
Not Applicable
a Total power requirement (in MW) S. No. Mine Site Township Others (specify) Total
1 Present 2 Proposed
/ additional
Total b Source of power (in MW)
S. No. SEB/Grid* Captive power plant DG Sets 1 Present 2 Proposed /
additional
Total
![Page 192: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/192.jpg)
Q-17
[* Annex a copy of the sanction letter from the concerned authority] c Details of fuels
S.No. Fuel Daily Consumption (TPD)
Calorific value
(Kcals/kg)
% Ash % Sulphur
Existing Proposed 1 HSD 2 LSHS 3 Other
(specify)
36 Storage of inflammable / explosive materia Not Applicable S.
No. Name Number of
Storages Consumption
(in TPD) Maximum Quantity at
any point of time 1 Fuels
2 Explosives
37 Human Settlement Core Zone Buffer Zone
Population*
-
Details given in Chapter VI
No. of villages
-
Number of households village-wise
-
[* As per 2001 census record or actual survey] 38. Rehabilitation & Resettlement (R&R) Plan*
[*Provide a comprehensive rehabilitation plan, if more than 1000 people are likely to be displaced, other-wise a summary plan]
Not Applicable
a Villages falling within the study area Villages Number Name Core zone 500 m from the blasting site (s)
Buffer zone Township site
b Details of village(s) in the core zone S.
No. Village name
Population* Average Annual
Income Tribal Others 1
[*As per 2001 census / actual survey] c Population to be displaced and / or Land
Oustees
Name of village(s) falling within Number of oustees
![Page 193: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/193.jpg)
Q-18
Land (only)
Homestead (only)
Land and Homestead (both)
Mining Lease 1.
Township Site 1.
d Whether R&R package has been finalised? If yes, salient features of R&R plan for oustees.
Not Applicable
i Site details where the people are proposed to be resettled & facilities existing / to be created.
ii Funds earmarked for compensation package iii Agency /Authority responsible for their
resettlement.
iv Time of commencement of resettlement of Project Affected People (PAP).
v Period by which resettlement of PAP will be over.
39 Lease -wise plantation details Not Applicable a Lease area (in ha.) Existing Proposed i. Area broken up - - ii. To be broken up - - iii. Area not to be broken-up - - b Township area (in ha.) - c Area afforested and proposed (in ha.) -
Peripheral Dumps Roads Township Others i Existing ii Proposed
d No. and type of trees planted and proposed i Existing When plantation was started? Month / Year
No.of plant species planted Number saplings (per ha.)
- - Survival rate % Avg. height
ii Proposed No. of plant species to be planted Number of saplings (per
ha.) - -
40 Environmental health and safety a What major health and safety hazards are
anticipated? None
What provisions have been made/proposed to be made to conform to health and safety requirements?
As per Mines Act/ Rules
b In case of an existing mine i Comprehensive report on health status
of the workers as under the Mines Act annexed
As per Mines Act/ Rules
![Page 194: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/194.jpg)
Q-19
ii Mineralogical composition of RPM (dust) • Free silica Not applicable • Chromium* (Total as well as
Hexavalent) Not applicable
• Lead** [* Only for Chromite mines] [**Only for Base Metal mines]
Not applicable
Information on radiation protection measures, if applicable
Not applicable
41. Environmental Management Plan Salient features of environmental protection measures
S. No.
Environmental issues* Already practiced, if applicable
Proposed
1 Air pollution
- � Regular water sprinkling � Plantation activities along the roads to reduce the impact of dust in the nearby villages
2 Water pollution - � Mining will be done not beyond the ground water depth, to avoid Ground water pollution.
3. Water conservation
- Not Applicable
4. Noise pollution - � Well maintained vehicles will be used for transportation in order to reduce noise during movement of vehicles � Proper maintenance of machines will be done to reduce the noise levels.
5. Solid waste / Tailings - Not Applicable
6. Land degradation - Not Applicable
7. Erosion & Sediment - Not Applicable
8. Top soil - Not Applicable
9. Ground vibration - Not Applicable
10. Wildlife conservation - Not Applicable
11. Forest protection - Not Applicable
12. Others (specify)
- Not Applicable
[* As applicable]
![Page 195: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/195.jpg)
Q-20
42 Compliance with environmental safeguards (For existing units)
Yes No
Status of the compliance of conditions of Environmental clearance issued by MoEF, if any, enclosed.
- √
Status of the compliance of ‘Consent to Operate’ issued by SPCB, if any, enclosed.
- √
Latest 'environmental statement' enclosed. - √
43 Scoping of EIA Whether environmental impact assessment
of the project has been carried out by following scoping process?
Yes
If yes, a copy of scoping of EIA annexed. Details given in Section I 44 Mine closure a Have you planned mine closure? No b Submitted a conceptual mine closure plan. No c If yes, indicate estimated amount for
implementing the same (in Rs. lakhs) No
45 Capital cost of the project (in Rs.) (Based on latest estimate)
Rs. 1.5 lacs
46. Cost of environmental protection measures
(in Rs. Lakh) S.
No. Capital cost Annual recurring cost
Existing Proposed Existing Proposed
1 Pollution Control (Separately provide break-up)
- - - 0.6
2 Pollution Monitoring (Separately provide break-up)
- - - 3.4
3 Occupational Health - - - 0.12
4 Green Belt • Mine • Township
- - - 0.5
5 Reclamation / Rehabilitation of mined out area
- - - -
6 Others (Man power cost for environmental cell)
- - - 0.5
Total -
-
-
5.12
![Page 196: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/196.jpg)
Q-21
47 Amount earmarked for socio-economic welfare measures for the nearby villages other
than R&R plans.
48 Public Hearing a Date of Advertisement 07/07/2014 b Newspapers in which the advertisement appeared Daily Post, Hindustan times
& Daily Ajit c Date of public hearing (DD/MM/YYYY) 06/08/2014 d Public Hearing Panel chaired by & members
present S. Pritam Singh, PCS, Additional District Magistrate, Jalandhar Er. Manohar Lal Chauhan, Environmental Engineer, PPCB, Regional Office, Jalandhar Er. Sandeep Kaur, Asstt. Environmental Engineer, PPCB, Regional Office, Jalandhar Sh. Surjit Singh GM cum Mining Officer, Jalandhar
e No. of people attended the public hearing meeting and number of people from the lease area.
Around 100
f Summary/details of public hearing in tabular form. 49 Whether the following approvals* (wherever
applicable) have been obtained? YES NO
a Site clearance from MoEF - √
b Consent for Establishment’ from the State Pollution Control Board
- √
c NOC from Atomic Mineral Division - √
d Mining plan approval from IBM / Ministry of Coal - √
e In case of existing mines, mining scheme approval from IBM
- √
f Forestry clearance under FCA, 1980 - √
g NOC from Chief Controller of Explosives - √
h Commitment regarding availability / pumping of water from the concerned Authorities
- √
i In case of ML area falling in notified areas of the Central Ground Water Authority, NOC from them.
- √
[* Annex copies of approvals and number them]
50 Was / is there any court case relating to the project or related activities? If so, provide details present status.
NO
![Page 197: FINAL ENVIRONMENTAL IMPACT ASSESSMENT AND ...environmentclearance.nic.in/writereaddata/EIA/2702201579...A Environmental Impact Assessment report was prepared to comply with the Terms](https://reader034.vdocument.in/reader034/viewer/2022050518/5fa20669d12f95635a1247c7/html5/thumbnails/197.jpg)
Q-22
Verification: The data and information given in this proforma are true to the best of my knowledge and belief.
Date: Signature of the applicant* with full name & address Place: [* Owner or his authorized signatory]
Given under the seal of organisation on behalf of whom the applicant is signing