final feasibility study work plan--soils · final feasibility study work plan - soils st. regis...
TRANSCRIPT
EPA Region 5 Records Ctr.
382170
Final Feasibility Study Work Plan - Soils
St. Regis Paper Company Site Cass Lake, Minnesota
Prepared for International Paper BNSF Railway Company
December 23, 2008
Final Feasibility Study Work Plan - Soils
St. Regis Paper Company Site Cass Lake, Minnesota
Prepared for International Paper BNSF Railway Company
December 23, 2008
4700 West 7?" Street Minneapolis. MN SS435-4S03 Phone: (952) H32-2600 Fax: (952) 832-2601
Final Feasibility Study Work Plan - Soils St. Regis Paper Company Site
Table of Contents
1.0 Introduction 1 1.1 Overview 1
1.2 Document Structure 1
2.0 Project and Task Organization 3
2 1 U.S. EPA Remedial Project Manager 3
2.2 International Paper Project Manager 3
2.3 Barr Engineering Company Project Manager 3
3 0 Scope of Work 5
3 1 Task 1: Prepare Feasibility Study Work Plan 5
3.2 Task 2: Prepare Alternatives Screening Technical Memorandum 5
3.2 1 Remedial Action Objectives 6
3.2.2 Identify Areas or Volumes of Media 6
3 2.3 Identify, Screen, and Document Remedial Technologies 6
3 2.4 Assemble and Document Alternatives 7
3 3 Task 3: Feasibility Study Report 8
3.3 1 Apply Nine Criteria and Document Analysis 8
3.3.2 Compare Alternatives Against Each Other and Document the Comparison of
Alternatives 9
3 3 3 Alternatives Analysis for Institutional Controls 9
3.4 Task 4 Progress Reports 10
3.4 1 Monthly Progress Reports ' 10
3.4.2 Semi-Annual Progress Reports 10 4 0 General Schedule 11
References 13
P\Mpls\23 MN\ll\2311005\WorkFiles\UAO-FS\FS Work Plan\l-inal FS-Work Plan\Final FS Work Plan 12_23_08doc
List of Tables
Table 1 Project Contact Information
List of Figures
Figure 1 Site Location
Figure 2 Site Layout
Figure 3 Project Organization
P \Mpls\23 MN\11\231 l005\WorkFiles\UAO-FS\FS Work Plan\Finjl FS-Work Plan\Final FS Work Plan 12_23_08 doc
1.0 Introduction
1.1 Overview This Feasibility Study (FS) Work Plan describes the proposed scope of work, general schedule and
technical approach for the Feasibility Study to be performed for soils of concern at the St Regis
Paper Company Site (the Site), which includes the former Cass Lake City Dump in Cass Lake,
Minnesota (Figure 1) The FS for Fox Creek sediment will be completed at a later date and is not a
part of this Work Plan, although the schedule for the sediment FS is presented herein. This FS Work
Plan was developed in accordance with the requirements in the Administrative Settlement Agreement
and Order on Consent for Feasibility Study (FS-AOC) with an effective date of September 11, 2008
(U.S. EPA Docket No. V-W-'08-C-912).
The Site, except for the Cass Lake City Dump is located within the Cass Lake city limits. The City
Dump is located south of the Cass Lake city limits. The Site is located in Cass County, Minnesota
and is bordered by the Chippewa National Forest, administered by the United States Department of
Agriculture (USDA). The Site and the surrounding areas, including the City of Cass Lake, are
located within the exterior boundaries of the Leech Lake Band of Ojibwe (LLBO) Reservation. The
Reservation encompasses 668,000 acres, including both Indian-owned and non-Indian-owned fee
land within Beltrami, Cass, Hubbard and Itasca counties
The Site includes a closed wood-treating facility that is listed on the National Priorities List (NPL) of
the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), which is
administered by the United States Environmental Protection Agency (U S EPA) The City Dump
area, in the southern portion of the Site, is located at a former city dump that is owned and was
operated by the City of Cass Lake. The Cass Lake City Dump is south of the former St. Regis Paper
Company wood treating property and adjacent to Fox Creek. The layout of the Site is shown in
Figure 2.
U S EPA Region 5 has required that various activities be undertaken at the Site under Remedial
Action and Removal Action authorities, as defined in CERCLA 121(c).
1.2 Document structure
This FS Work Plan consists of the following sections'
• Section 1 - Introduction
P\Mpls\23 MN\I1\23I 1005\WorkFiles\UAO-FS\FS Work Plan\Final FS-Work Plan\Final FS Work Plan 12_23_08 doc 1
• Section 2 - Scope of Work
• Section 3 - General Schedule
• References
The FS Work Plan describes the following two submittals that are specified in the FS-AOC' (1)
Alternatives Screening Technical Memorandum, and (2) Feasibility Study Report. The Feasibility
Study Report will consist of alternatives screening followed by a detailed analysis of alternatives.
Draft documents will be submitted to the U.S. EPA and support agency partners (i.e., LLBO and
Minnesota Pollution Control Agency (MPCA)).
P\Mpls\23 MN\1 l\2311005\WoikFiles\UAO-FS\FS Work Plan\Final PS-Work Plan\Finjl FS Work Plan 12_23_08 doc
2.0 Project and Task Organization
This section describes the organizational structure for conducting activities associated with the FS,
including project management and oversight and technical work associated with the FS. The
organizational structure for this project is shown in Figure 3. Contact information is provided in
Table 1. Project responsibilities are described below
The U.S. EPA Remedial Project Manager (RPM), International Paper Project Manager, and Barr
Engineering Company Project Manager will be responsible for project management Their roles are
described below.
2.1 U.S. EPA Remedial Project Manager The U S. EPA Remedial Project Manager (RPM), Mr. Timothy Drexler, has overall responsibility for
the oversight of all phases of the FS. The RPM will direct other U S. EPA technical staff, as required,
to provide technical support for this project. The RPM will also coordinate input to the process and
comments on the deliverables for the U.S. EPA and support agency partners and will resolve any
inconsistencies in the input and comments
2.2 International Paper Project Manager The International Paper Project Manager, Tom Richardson, will provide final approval on behalf of
International Paper of the submittals required by the FS-AOC. He oversees remediation and
management activities at the Site and will ensure compliance with the FS-AOC, provide technical
oversight and consultation, and provide final approval on behalf of International Paper for activities
to accomplish project objectives. Mr Richardson will serve as the primary point of contact on behalf
of IP for the U.S EPA and support agency partners on all non-legal matters related to the
performance of the FS Communications from the U.S EPA and support agency partners on these
matters should be directed to Mr. Richardson
2.3 Barr Engineering Company Project Manager The Barr Engineering Co. (Barr) Project Manager for the FS, Tom Mattison, will be responsible for
the management and overall coordination of all project activities to be completed by Barr. The Barr
Project Manager's primary function is to ensure that technical and scheduling objectives are achieved
successfully. The Barr Project Manager reports directly to the International Paper Project Manager
and will provide the major point of contact and control for matters concerning the project. The Barr
Project Manager's duties and responsibilities are as follows:
P\Mpls\23 MN\1 l\23ll005\WorkFiles\UAO-FS\FS Work Plan\Final FS-Work Plan\Final FS Work Plan 12_23_08 doc 3
• Define project objectives and develop a detailed work plan and schedule,
• Establish project policies and procedures to address specific needs of the project as a whole
for each project task;
• Acquire and apply technical and corporate resources as needed to ensure that project
performance is achieved within budget and schedule constraints,
• Orient the technical staff to the project's special considerations;
• Monitor and direct the collection of any needed information;
• Develop and meet ongoing project or task staffing requirements, including mechanisms to
review and evaluate each project work product;
• Review the work performed under each task to ensure quality, responsiveness, and timeliness;
• Review and analyze overall task perfonnance with respect to planned requirements and
authorizations;
• Approve external reports (deliverables) before submittal to U.S. EPA Region 5; and,
• Represent the project team at meetings and public hearings.
P \Mpls\23 MN\1 1\2311005\WorkFiles\UAO-FS\FS Work Plan\Final FS-Work Plan\Final FS Work Plan 12_23_08 doc
3.0 Scope of Work
The following tasks will be completed for the Feasibility Study.
3.1 Task 1: Prepare Feasibility Study Work Plan This document is the draft FS Work Plan and has been submitted to the U.S EPA with copies to the
LLBO and the MPCA for review and approval in accordance with Section X of the FS-AOC. Prior
to submittal of the document, IP has met or conferred with U.S. EPA, and support agency partners as
detennined appropriate by U S EPA. The FS Work Plan was prepared in a manner consistent with
applicable portions of the U.S. EPA RI/FS Guidance (U S EPA 1988) and other relevant guidance
documents, and sets forth general approaches and concepts with the intent of streamlining
preparation of the FS and minimizing review times for deliverables.
3.2 Task 2: Prepare Alternatives Screening Technical Memorandum
The Alternatives Screening Technical Memorandum will document the development and screening of
an appropriate range of remedial alternatives for detailed analysis in the Feasibility Study Report.
The Alternatives Screening Technical Memorandum will summarize the work performed and the
results of each of the subtasks, and will include an alternatives array summary. If required by U S
EPA, in consultation with the support agency partners, the alternatives array will be modified to
assure that the array identifies a complete and appropriate range of viable alternatives to be
considered in the detailed analysis. The alternatives array will build on the FS Work Plan, as
appropriate. The range of alternatives will include, as appropriate,
• Options in which treatment is used to reduce the toxicity, mobility, or volume of wastes, but
which vary in the types of treatment, the amount treated, and the manner in which long-term
residuals or untreated wastes are managed,
• Options involving removal;
• Options involving containment with little or no treatment,
• Options involving both treatment and containment, and,
• A no-action alternative.
P \Mpls\23 MN\1 1\2311005\WorkFiles\UAO-FS\FS Work Plan\Final FS-Work Plan\Final FS Work Plan 12_23_08 doc
The Alternatives Screening Technical Memorandum will document the methods, rationale and results
of the alternatives screening process, and will include:
• Remedial Action Objectives
• Identification of Areas and Volumes of Media
• Identification, Screening, and Documentation of Remedial Technologies and Processes
• Assembly and Documentation of Remedial Action Alternatives
3.2.1 Remedial Action Objectives
Remedial Action Objectives (RAOs) will be developed through consultation with the U.S. EPA and
support agency partners. The baseline human health and ecological risk assessment (Integral, 2007
and 2008, U.S. EPA, 2008, Integral 2009) will serve as the basis for establishing site-specific RAOs
for the soil in the nearby residential area, the former operations area, and the southwest area. The FS
for Fox Creek sediment will be completed at a later date and is not a part of this Work Plan The
RAOs will specify the contaminants of concern (COCs) and media of concern (i.e., soil), potential
exposure pathways and receptors, and contaminant level or a range of levels at particular locations
for each exposure route (i.e , preliminary remediation goals) that are protective of human health and
the environment. RAOs will be developed by considering the factors set forth in 40 C.F.R. §
300.430(e)(2)(i).
3.2.2 Identify Areas or Volumes of Media
The Alternatives Screening Technical Memorandum will identify general areas or volumes of soil to
which response actions may apply, taking into account requirements for protectiveness as identified
in the RAOs and the chemical and physical characterization of each area.
3.2.3 Identify, Screen, and Document Remedial Technologies
The Alternatives Screening Technical Memorandum will.
• Identify and evaluate applicable technologies and/or process options, and,
• Eliminate those technologies that cannot be implemented in a specific area of the Site
Technologies and/or process options will be evaluated based on effectiveness, implementability, and
cost factors The goal will be to select one or more representative processes for each technology
P\Mpls\23 MN\11\231 1005\WorkFiles\UAO-rS\FS Work Plan\Final FS-Work Plan\Final FS Work Plan 12_23_08 doc f.
type. Whenever practicable, the technologies/process options will also consider the CERCLA
preference for treatment over conventional containment or land disposal approaches
3.2.4 Assemble and Document Alternatives
The Alternatives Screening Technical Memorandum will identify potential Applicable or Relevant
and Appropriate Federal, State and Tribal requirements (ARARs) and non-promulgated criteria,
advisories, guidance, and policies issued by federal, state, or tribal governments to be considered
requirements (TBCs) and how the technologies/process options meet those potential ARARs and
TBCs. As described in the FS-AOC, U.S. EPA considers the following as potential ARARs or TBCs:
•
•
Approach for Addressing Dioxin in Soil at CERCLA and RCRA Sites, U.S. EPA, OSWER
Directive 9200 4-26, April 13, 1998;
Risk-Based Guidance for the Soil-Human Health Pathway, MPCA, Site Remediation Section,
Working Draft, September 1998 (i e., MPCA Soil Reference Values);
• Guidance on Incorporation of Planned Property Use into Site Decisions, MPCA, Site
Remediation Section, Working Draft, September 1998;
• Leech Lake Hazardous Substances Control Act, LLBO, Resolution No. 01-29, August 25,
2000;
• Leech Lake Land Acquisition Ordinance, LLBO, Resolution No 09-34, Ordinance 2009-01
The screening of technologies and process options will be conducted to assure that only the
technologies and process options with the most favorable composite evaluation of all factors are
retained for further analysis As appropriate, the screening will preserve the range of treatment and
containment technologies that was initially developed. The reasons for eliminating technologies
during the preliminary screening process will be presented.
The selected representative technologies and process options will be assembled into remedial action
alternatives for soils at each location of concern. Together, the alternatives will represent a range of
treatment and containment combinations that addresses the soil and locations of concern at the Site.
The memorandum will summarize the assembled alternatives and their related potential ARARs and
TBCs.
P\Mpls\23 MN\1 1\231 l005\WorkFiles\UAO-FS\FS Work Plan\Final FS-Work PlanNFinal FS Work Plan 12_23_08doc
3.3 Task 3: Feasibility Study Report The draft FS Report will be prepared and submitted to U.S. EPA, with copies to MPCA, and LLBO,
for review and approval pursuant to Section X of the FS-AOC. The FS Report will summarize the
development and screening of the remedial technologies and process options, assembly of remedial
alternatives and present the detailed analysis of the selected remedial alternatives. In addition, the
FS Report will include the information U.S EPA, in consultation with its support agency partners,
will need to prepare relevant sections of the Record of Decision (ROD) for the Site [see Chapters 6
and 9 of U S. EPA's Guide to Preparing Superfund Proposed Plans, Records of Decision, and Other
Remedy Selection Decision Documents (EPA/540/R-98/031, OSWER Publication 9200.1-23P, July
1999) for the information that is needed].
The FS Report will build on the Alternatives Screening Technical Memorandum and will present a
detailed analysis of the identified remedial alternatives to provide U.S. EPA, in consultation with its
support agency partners, with the information needed to select a remedy.
The FS Report will provide a detailed analysis of the remedial alternatives for each identified
location of concern at the Site. The detailed analysis will include an analysis of each remedial
alternative measured against evaluation criteria set forth in 40 C F.R. § 300.430(e)(9)(iii) and a
comparative analysis of alternatives using the same criteria as the basis for comparison.
3.3.1 Apply Nine Criteria and Document Analysis
The FS Report will apply the evaluation criteria to the assembled remedial alternatives to document
that the selected remedial alternative will protect human health and the environment and meet
remedial action objectives; will comply with or include a waiver of ARARs (will address compliance
with ARARs); will be cost-effective; will utilize permanent solutions and alternative treatment
technologies, or resource recovery technologies, to the maximum extent practicable, and will address
the statutory preference for treatment as a principal element. The U.S. EPA-established evaluation
criteria include: 1) overall protection of human health and the environment; 2) long-term
effectiveness and permanence; 3) short-term effectiveness; 4) compliance with ARARs, 5) reduction
of toxicity, mobility, or volume through treatment, 6) implementability, 7) cost, 8) state and tribal
acceptance; and 9) community acceptance. (Note- criteria 8 and 9 will be considered after the FS
Report has been released to the general public.)
For each alternative, the FS Report will contain' 1) a description of the alternative that outlines the
waste management strategy involved and identifies the key ARARs and TBCs associated with that
P \Mpls\23 MN\11\2311005\WorkFiles\UAO-FS\FS Work Plan\Final FS-Work Plan\Final FS Work Plan 1223^08 doc
alternative, and 2) a discussion of the individual criterion assessment. Since the Respondents do not
have direct input on criteria 8, state and tribal acceptance; and 9, community acceptance; the U.S.
EPA will address these criteria in consultation with its support agency partners after the FS Report is
released for public comment.
3.3.2 Compare Alternatives Against Each Other and Document the Comparison of Alternatives
The FS Report will provide a detailed comparative analysis among the remedial alternatives Each
alternative will be compared against the other alternatives using the evaluation criteria. The FS
Report will present a recommended alternative although it is recognized that U.S. EPA in
consultation with its support agency partners will ultimately identify and select the preferred
alternative.
3.3.3 Alternatives Analysis for Institutional Controls
Institutional controls are nonengineering measures designed to prevent or limit exposure to
hazardous substances left in place at a site, or assure effectiveness of the chosen remedy. Institutional
controls are usually, but not always, legal controls, such as easements, restrictive covenants, and
zoning ordinances (U.S. EPA, 2000)
For each alternative that relies on institutional controls, the FS Report will provide an evaluation of
the following: 1) overall protection of human health and the environment including what specific
institutional control components will ensure that the alternative will remain protective and how these
specific controls will meet the RAOs, 2) compliance with potential ARARs and TBCs, 3) long-term
effectiveness including the adequacy and reliability of institutional controls and how long the
institutional control must remain in place; 4) short-term effectiveness including the amount of time it
will take to impose the institutional control; 5) implementability including research and
documentation that the proper entities (e.g., potential responsible parties, state, and local government
entities, local landowners, conservation organizations) are willing to enter into any necessary
agreements or restrictive covenants with the proper entities and/or that laws governing the restriction
exist or allow implementation of the institutional control, and 6) cost, including the cost to
implement, maintain, monitor and enforce the institutional control. State, tribal and community
acceptance of the institutional control will be evaluated by U.S EPA after receiving public comments
on the FS Report.
P \Mpls\23 MN\1 1\231 1005\WorkFiles\UAO-FS\FS Work Plan\Final FS-Work Plan\Final FS Work Plan 12_23_08 doc
3.4 Task 4: Progress Reports International Paper and the BNSF Railway Company will provide U.S. EPA and support agency
partners with project progress reports as follows:
3.4.1 Monthly Progress Reports
International Paper and the BNSF Railway Company will submit written and electronic monthly
progress reports to U.S. EPA, LLBO and the MPCA concerning actions undertaken pursuant to the
FS-AOC in accordance with the schedule in Section 4.0 of this FS Work Plan, unless otherwise
directed in writing by the U.S. EPA RPM. These reports will include a description of significant
developments during the preceding period, including the specific work that was performed and any
problems that were encountered; a summary of any analytical data that was received during the
reporting period, and the developments anticipated during the next reporting period, including a
schedule of work to be performed, anticipated problems, and actual or planned resolutions of past or
anticipated problems. The monthly progress report will summarize any field activities conducted
during that month. In addition, International Paper and BNSF Railway Company will provide the
U.S. EPA RPM with any laboratory data with the monthly progress reports and in no event later than
ninety (90) days after samples are shipped for analysis. These monthly progress reports will continue
until the final FS Report is submitted or until other correspondence from U.S. EPA terminates this
obligation.
3.4.2 Semi-Annual Progress Reports
In accordance with the schedule in Section 4.0, International Paper and BNSF Railway Company will
submit Semi-Annual Progress Reports including underlying data, in hard copy and electronic
formats, to U.S. EPA, LLBO, and MPCA. These reports will address the areas of the Site where
International Paper and BNSF Railway Company perform FS activities and will summarize overall
progress in completing the work required by the FS-AOC. These reports will continue until
termination of the FS-AOC, unless otherwise directed in writing by U.S. EPA.
P\Mpls\23 MN\1 1\231 1005\WorkFiles\UAO-FS\FS Work Plan\Final FS-Work Plan\Fmal FS Work Plan 12_23_08doc \Q
4.0 General Schedule
The FS-AOC and related scope of work establish the general schedule for preparation of the
Alternatives Screening Technical Memorandum and the Feasibility Study Report. The project start
date as defined by the U.S. EPA is the effective date of the FS-AOC (September 11, 2008).
The following general schedule will apply to the FS activities. The general schedule may be modified
when- (1) a different schedule is approved by U S. EPA in a Work Plan or other U.S. EPA-approved
document; or (2) International Paper and BNSF Railway Company submit, in writing, a request for
an extension or schedule modification, and U.S EPA approves such request
DELIVERABLE DUE DATE
TASK 1 - Feasibility Study Work Plan - Soils
TASK 2 - Alternatives Screening Technical Memorandum - Soils
TASK 3 - Feasibility Study Report - Soils
Draft FS Work Plan is due 45 days after the effective date of the FS-AOC (i.e., October 27, 2008). Final FS Work Plan is due 30 days after U S. EPA direction to modify the draft FS Work Plan pursuant to Section X of the FS-AOC.
60 days after submittal of the Final FS Work Plan.
Draft FS Report due 90 days after receipt of U.S. EPA's comments on the Alternatives Screening Technical Memorandum Final FS Report is due 45 days after receipt of U.S. EPA's direction to modify the draft FS Report pursuant to Section X of the FS-AOC
Task 4 - Progress Reports
Monthly Progress Reports
Semi-Annual Progress Reports
Miscellaneous Documents
Due on the 15"" day of each month or the first business day after the 15"" of the month commencing 60 days after September 11, 2008 and continuing until the Final FS Report is submitted, covering the previous month (first report due November 15, 2008).
Due six months after the effective date of the FS-AOC (i.e , March 11, 2009), and every six months thereafter until the Final FS Report is submitted.
In accordance with the submittal date provided by the U S. EPA RPM.
For the Fox Creek Area of the Site, the following schedule will apply for the FS Work.
P \Mpls\23 MN\11\2311005\WorkFiles\UAO-FS\FS Work Plan\Final FS-Work Plan\Final FS Work Plan 12_23_08 doc 11
DELIVERABLE DUE DATE
TASK 1 - Feasibility Study Work Plan - Fox Creek Area
TASK 2 - Alternatives Screening Technical Memorandum - Fox Creek Area
TASK 3 - Feasibility Study Report - Fox Creek Area
Miscellaneous Documents
Draft FS Work Plan - Fox Creek Area is due 20 days after the U.S. EPA approval of the 28-day amphipod study to be conducted by the PRP International Paper under the Unilateral Administrative Order issued by the U S. EPA on August 11, 2004. Final FS Work Plan - Fox Creek Area is due 10-days after U.S. EPA direction to modify pursuant to Section X of the FS-AOC
50 days after submittal of the Final FS Work Plan - Fox Creek Area.
Draft FS Report - Fox Creek Area is due 70 days after receipt of U.S. EPA's comments on the Alternatives Screening Technical Memorandum - Fox Creek Area. Final FS Report - Fox Creek Area is due 25 days after receipt of U.S EPA's direction to modify the draft FS Report - Fox Creek Area pursuant to Section X of the FS-AOC.
In accordance with the submittal date provided by the U.S EPA RPM
P \Mpls\23 MN\1 1\231 1005\Workriles\UAO-FS\FS Work Plan\Final FS-Work Plan\Final FS Work Plan 12_23_08 doc 12
References
Integral 2007. Human Health and Ecological Risk Assessment, St. Regis Paper Company Site, Cass
Lake, MN Prepared for International Paper pursuant to Unilateral Administrative Order
Docket No. V-W-04-C-796 Prepared by Integral Consulting Inc September 28, 2007.
Integral 2008. Addendum Human Health and Ecological Risk Assessment, St. Regis Paper Company
Site, Cass Lake, MN. Prepared for International Paper pursuant to Unilateral Administrative
Order Docket No. V-W-04-C-796. Prepared by Integral Consulting Inc. May 30, 2008.
Integral 2009. TO BE DEVELOPED. Revisions Based on the Results of the 28-day Amphipod Study.
Prepared for International Paper pursuant to Unilateral Administrative Order Docket No. V-W-
04-C-796 Prepared by Integral Consulting Inc. 2009.
U.S. EPA, 1988 Guidance for Conducting Remedial Investigations and Feasibility Studies Under
CERCLA, Interim Final, Office of Emergency and Remedial Response U S. Environmental
Protection Agency Washington, D C. 20460. EPA/540/G-89/004. October 1988
U S EPA, 1999. Guide to Preparing Superfund Proposed Plans, Records of Decision, and Other
Remedy Selection Decision Documents (EPA/540/R-98/03 1, OSWER Publication 9200.1-23P,
July 1999).
U.S. EPA, 2000. Institutional Controls and Transfer of Real Property under CERCLA Section
J20(h)(3)(A), (B) or(C). U.S. Environmental Protection Agency.
http //www epa.iiov/fedfac/pdf/fi-icops_106 pdf. February 2000.
U S EPA, 2008. Approval of the HHERA with Modifications Letter from Tim Drexler, U S. EPA
RPM to Tom Richardson, International Paper Dated August 15, 2008.
P\Mpls\23 MN\1 l\231 1005\WorkFiles\UAO-FS\FS Work Plan\Final FS-Work Plan\Final FS Work Plan 12_23_08doc [ 3
Tables
Table 1
Project Contacts Feasibility Study Work Plan
St. Regis Paper Company Site
Tim Drexler Remedial Project Manager U S. EPA, Superfund Division 77 West Jackson Blvd SR-6J Chicago, IL 60604-3590
Phone: 312-353-4367 Email: drexler timothv(S)epa gov
John Persell St Regis Site Project Coordinator Leech Lake Band of Ojibwe 6530 U.S. 2 NW Cass Lake, MN 56633
Phone. 218-335-7412 Email. psersell(a)lldrm org
Susan Johnson Project Manager Minnesota Pollution Control Agency 525 S Lake Avenue Suite 400 Duluth, MN 55802
Phone 218-725-7762 Email- susan iohnson(a>pca state mn us
Tom Richardson Project Manager International Paper 6400 Poplar Avenue Memphis, TN 38197
Phone: 901-419-3878 Email tom richardson(S)ipaper com
Greg Jeffries Manager Environmental Remediation BNSF Railway Company General Office Building 80 44"" Avenue NE Minneapolis, MN 55421
Phone: 763-782-3490 Email. greqory geffnes(a)bnsf com
Tom Mattison Project Coordinator Barr Engineenng Company 4700 West 77th Street Minneapolis, MN 55437
Direct- 952-832-2876 General 952-832-2600 Email. tmattison(a)barr com
Figures
-• *•' 1 ® ' " ' - " ' ' •'- ' }
• . •• i - iAMK • .
•> - .
. . - > • •
• . • -
• • • ^ . - > * ' • " ' ' . • - 1 . - u a ; ••»i-'?-. > t V ; f ^ S ^ ^ . . : . -shf ' •••»«' ' ^ ^
* .̂* •1 - S i . i ' . '
. . . • V . . - I . . . . , . _ , . ^ _ . i ' r . - i '
' • ' • • ' • ^ . j ' - " . ••<• ' • • : • • - • V - ' / J - -.V "f" ' ' •
*A' ' i ' i ^ l i ' i fc. •' ..
.^-
' * * • » > • • • •
''f'fi. • . " • • •• t:V-' a ? ^ i h i t f ;••-
»!«•.•!.; / t . - - • .- • ' •<. , •»• . • ' ' • - I . ' TOW
>—I'-ii-'.''."'
Figure 1
LOCATION MAP
St. Regis Paper Company Site and City Dump Pit Site
Cass Lake, Minnesota
LEGEND [̂ ,̂ Si St. Regis Paper Company Site
Cass Lake City Dump Site
0 5 0 0125 0 25
I
Miles
Ban-Footer Date 12/12/2008 9 35 55 AM File I \Prqecls^3\11 \0q5\qis\Maps\Fiqure2 Site Uyoul SI Reais Paper Co 10172008 mxd U;
c n (—̂ 73 (D
(Q O cfl c/) 0) -p , — «> ^ - I (fl ^ rn
- o O ^ 3 c
I—^
DDD C —n (D N3
© -n o O
9 T>
-n o 3 (D - 1
() •:s:
o c =1
-T)
Q.
SL U
o T !
a. 0) cn
-n o
- 1
(1 ^ (i) o 3
^ 0)
Figure 3
Project Organization FS Work Plan - Soils
Leech Lake Band of Ojibwe St Regis Site Project Coordinator
John Persell
U.S. EPA Region 5 Remedial Project Manager
Tim Drexler
Minnesota Pollution Control Agency Project Manager
Susan Johnson
International Paper Company
Project Manager
Tom Richardson
Barr Engineering Company
Project Manager
Tom Mattison
BNSF Railway Company Manager Environmental Remediation
Greg Jeffnes