final - oati · final . completed for . lgiq # q0377 . proposed interconnection . ... 2.0 scope...

25
Large Generator Interconnection Facilities Study Report Final Completed for LGIQ # Q0377 Proposed Interconnection To the Transmission Provider’s Dead-end Located adjacent to the Interconnection Customer’s substation at 138kV December 9, 2011

Upload: lythuy

Post on 06-Sep-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

Large Generator Interconnection

Facilities Study Report

Final

Completed for LGIQ # Q0377

Proposed Interconnection To the Transmission Provider’s Dead-end

Located adjacent to the Interconnection Customer’s substation at 138kV

December 9, 2011

DRAFT Facilities Study Report

Q0377 December 9, 2011 Page i CONFIDENTIAL / DRAFT

TABLE OF CONTENTS

1.0 Description of the Project .................................................................................................... 12.0 Scope & Objectives .............................................................................................................. 13.0 Study Assumptions .............................................................................................................. 24.0 Scope of Work ..................................................................................................................... 3

4.1 Facilities Analysis Results ............................................................................................... 34.1.1 Substation .................................................................................................................. 54.1.2 Radial Interconnection Line ...................................................................................... 74.1.3 Oquirrh substation ..................................................................................................... 74.1.4 Substation .................................................................................................................. 84.1.5 Protection and Control Specifications .................................................................... 124.1.6 Metering Specifications .......................................................................................... 134.1.7 Communications Specifications .............................................................................. 164.1.8 Other Substations / Remote Sites ............................................................................ 18

5.0 Cost Estimate ..................................................................................................................... 196.0 Schedule ............................................................................................................................. 217.0 Appendix 1: Property Requirements .................................................................................. 22

DRAFT Facilities Study Report

Q0377 December 9, 2011 Page 1 CONFIDENTIAL / DRAFT

1.0 Description of the Project Interconnection Customer is constructing a new generation resource on their system which will interconnect to PacifiCorp’s (Transmission Provider) system at the locations shown in Figure 1. The new Project consists of a 199 MW GE combustion (gas) turbine in the Interconnection Customer’s system. The exhaust heat from this combustion turbine will be directed into a heat recovery steam generator to generate steam to re-power the existing Power Plant Units 1, 2 and 3. The combined output of the combustion turbine and Units 1-3 will be 269.4 MW for summer and 275 MW for winter. The point of interconnection is defined as the point the Interconnection Customer’s conductor attaches to the Transmission Provider’s take off structure located in the protection and control, communication and interchange metering substations which are adjacent to the Interconnection Customer’s substations. The requested commercial operation date for the Project is January 1, 2014. Transmission Provider has assigned the Project Queue “Q0377”. Interconnection Customer has chosen to have the project interconnection as an Energy Resource.

2.0 Scope & Objectives The objective of the facilities study is to:

• Complete a facilities analysis which shall specify and estimate the cost of equipment, engineering, procurement, and construction required to address issues as outlined in the system impact study, and

• Provide a scope of work and an estimated cost and schedule for completing the scope of

work.

DRAFT Facilities Study Report

Q0377 December 9, 2011 Page 2 CONFIDENTIAL / DRAFT

3.0 Study Assumptions • All active higher priority transmission service and/or generator interconnection

requests will be considered in this study. If any of these requests are withdrawn, the Transmission Provider reserves the right to restudy this request, as the results and conclusions contained within this study could significantly change.

• For study purposes there are two separate queues: o Transmission Service Queue: to the extent practical, all network upgrades that are

required to accommodate active transmission service requests and are expected to be in-service on or after the Interconnection Customer’s requested in-service date for the Project will be modeled in this study.

o Generation Interconnection Queue: when relevant, interconnection facilities associated with higher queue interconnection requests will be modeled in this study. However, network upgrades required to provide delivery will only be modeled for projects which have requested network resource integration service only or qualified facility status. No generation will be simulated from any higher queued project unless a commitment has been made to obtain transmission service.

• The Interconnection Customer’s request for interconnection service in and of itself

does not convey transmission service.

• This study assumes the Project will be integrated into Transmission Provider’s system at the substations.

• The Interconnection Customer will construct and own the any facilities required

between the point of change of ownership and the Project.

• Generator tripping may be required for certain outages.

• All facilities will meet or exceed the minimum WECC, NERC, and Transmission Provider performance and design standards.

• It is assumed the Interconnection Customer’s proposed two new 138kV lines of

approximately 8.4 miles in length from the new 138kV substation to a new Interconnection Customer owned 138kV substation are in service. It is assumed that OPGW fiber optic cable was installed with the transmission lines. This is modeled in the study.

DRAFT Facilities Study Report

Q0377 December 9, 2011 Page 3 CONFIDENTIAL / DRAFT

• It is assumed the GIS substation will be constructed and in service as part of the Interconnection Customer’s scope of work for the Interconnection Customer’s load addition project. It is assumed that a medium D20 RTU with an interposition rack using DNP 3.0 protocol into the multiplex channel was installed with the load project.

• It is assumed any transmission line upgrades beyond the point of interconnection are in service as part of the scope of work for the Interconnection Customer’s load addition project.

• It is assumed the fiber upgrades are in service as part of the scope of work for the

Interconnection Customer’s load addition project.

• It is assumed that the existing 138kV line will be re-terminated making it the Terminal- New substation 138kV line.

• If the assumptions used in this study significantly change, the Transmission Provider

reserves the right to perform a re-study.

4.0 Scope of Work

4.1 Facilities Analysis Results The interconnection of the Q0377 project will require the construction of a small Transmission Provider owned protection and control, communication and interchange metering substation adjacent to the Interconnection Customer’s substations. The Transmission Provider’s scope of work will also include the installation of metering, protection and control and communication equipment at the Interconnection Customer’s existing Power Plant, new generation and new generation facilities. Three existing circuit breakers will need to be replaced at the Transmission Providers Oquirrh substation and communication upgrades will be needed at the Salt Lake City and Portland Communication centers. Approximately ¼ mile of the existing 138kV transmission line will need to be decommissioned at approximately 1800 feet of new 138kv transmission line will need to be constructed to create the new Terminal – new substation transmission line.

DRAFT Facilities Study Report

Q0377 December 9, 2011 Page 4 CONFIDENTIAL / DRAFT

Figure 1: System one line diagram

DRAFT Facilities Study Report

Q0377 December 9, 2011 Page 5 CONFIDENTIAL / DRAFT

4.1.1 Substation

Work to be completed by the Interconnection Customer

• Design, procure, install own and maintain a dead-end structure to industry design criteria to avoid failure located adjacent to the Transmission Provider’s protection and control, communication and interchange metering substation.

• Coil enough conductor on the Interconnection Customer’s dead end to reach the Transmission Provider’s dead-end structure located in the protection and control, communication and interchange metering substation.

• Provide land for the Transmission Provider’s protection and control, communication and

interchange metering substation outside the Interconnection Customer’s substation.

• Design, procure, install, own and maintain line protection relays in the substation. These relays will provide high speed line protection and function with the relays installed in the substation.

• Design, procure, install, own and maintain the necessary splice boxes, patch panels, 48

fiber cable and racks required for terminating the high speed communication system installed between the substations and between those substations and the Transmission Providers protection and control, communication and interchange metering substation control house.

• All high speed communication equipment between the substation and the substation will be owned by the Interconnection Customer.

• Design, procure, install, own and maintain the necessary splice boxes, patch panels, and fiber required for terminating the 48 fiber cable installed between the Transmission Providers control house and substation control house. All fiber and fiber patch panels between the substation and the Transmission provider’s substation will be owned by the Interconnection Customer.

• Design, procure, install, and own the communication raceway from the substation control

house to the fence line of the Transmission Provider’s protection and control, communication and interchange metering substation. The location of the raceway will be determined when detailed project engineering is performed.

• Terminate all field I/O connections required to provide data and control in accordance

with safe system operation and in compliance with the Interconnection Agreement.

DRAFT Facilities Study Report

Q0377 December 9, 2011 Page 6 CONFIDENTIAL / DRAFT

Work to be completed by the Transmission Provider

• Provide a list of data inputs and outputs required for protection, control, and data collection in accordance with the interconnection agreement.

• Design, procure, construct own and maintain a protection and control, communication and interchange metering substation outside the Interconnection Customer’s substation.

• Design, procure, construct, own and maintain a dead end at the Transmission Provider’s protection and control, communication and interchange metering substation located adjacent to the Interconnection Customer’s substation.

• The Transmission Provider’s protection and control, communication and interchange metering substation shall be a independently fenced area with unrestricted Transmission Provider access. The facility will require one access gate suitable for vehicular access. The ground grids of this facility and the substation are to be tied together.

• Design, procure, install, own and maintain the revenue metering system. This includes instrument transformers, junction boxes, and secondary lead conductors.

• The metering design package will include two revenue quality meters, a test switch, and all digital and analog data terminated at a metering interposition block. One meter will be designated a primary meter and be used for Ranger data that includes bidirectional KWH quantities, instantaneous MW, MVAr and per phase voltage data. The second or backup meter will be used for MW data sent to the alternate control center.

• Design, procure, install own and maintain a medium D20 RTU with interposition rack using DNP 3.0 protocol into a multiplex channel.

• Design, procure, install, own and maintain the communications to the primary interchange meter that will be directly polled by Ranger using DNP 3.0 protocol. The meter will be brought into a RS-232 bridge and into the RTU mux channel.

• Design, purchase, and install the communications to the Backup interchange meter that will be directly polled by Ranger using DNP 3.0 protocol. The meter will be brought into a mux channel.

DRAFT Facilities Study Report

Q0377 December 9, 2011 Page 7 CONFIDENTIAL / DRAFT

• The following equipment, installed in the Transmission Provider’s protection and control, communication and interchange metering substation will be designed, procured, installed, owned and maintained by the Transmission Provider: metering panels, line protection panel, RTU, fiber optic terminals, multiplex, and fiber optic termination panels for fiber between the substations.

• The Transmission Provider will own and maintain the fiber optic cable between the

Interconnection Customer’s substation control house and the Transmission Providers protection and control, communication and interchange metering substation control house.

• Perform final checkout and testing/commissioning of the Transmission Provider’s

equipment located in the Transmission Provider’s protection and control, communication and interchange metering substation.

• Supply a dial up or Ethernet communications path for retail sales metering and

generational accounting via the MV-90 translation system. This may be provided by utilizing the Transmission Providers digital communications system.

4.1.2 Radial Interconnection Line Work to be completed by the Interconnection Customer

• The two (2) Interconnection Customer owned 138kV lines (8.4 miles) from the substation to the substation, are assumed to be in service prior to this project.

• OPGW fiber optic cable is assumed to have been installed with these lines and terminated in splice boxes on the final dead end towers.

Work to be completed by the Transmission Provider • No work required.

4.1.3 Oquirrh substation Work to be completed by the Interconnection Customer

• No work required.

Work to be completed by the Transmission Provider • Design, procure, replace, own and maintain circuit breakers CB143, B145, and C152

with units that have higher fault interrupting rating of 63kA.

• Replace or modify the existing bus as required to allow for the reconnection of the switches to the new breakers.

DRAFT Facilities Study Report

Q0377 December 9, 2011 Page 8 CONFIDENTIAL / DRAFT

4.1.4 Substation Work to be completed by the Interconnection Customer

• The Interconnection Customers 138kV substation is assumed to be in service prior to this project.

• Design, purchase and install all equipment necessary to terminate the 138kv line at the substation bus.

• Design, procure, install own and maintain a dead-end structure to industry design criteria to avoid failure located adjacent to the Transmission Provider’s protection and control, communication and interchange metering substation.

• Coil enough conductor on the Interconnection Customer’s dead end to reach the Transmission Provider’s dead-end structure located in the protection and control, communication and interchange metering substation.

• Provide land for the Transmission Provider’s protection and control, communication and interchange metering substation outside the Interconnection Customer’s substation.

• Design, procure, install, own and maintain line protection relays in the substation. These

relays will provide high speed line protection and function with the relays installed in the substation.

• Design, procure, install, own and maintain the necessary splice boxes, patch panels, 48

fiber cable and racks required for terminating the high speed communication system installed between the substations and between those substations and the Transmission Providers protection and control, communication and interchange metering substation control house.

• All high speed communication equipment between the substation and the substation will be owned by the Interconnection Customer.

• Design, procure, install, own and maintain the necessary splice boxes, patch panels, and fiber required for terminating the 48 fiber cable installed between the Transmission Providers control house and substation control house. All fiber and fiber patch panels between the substation and the Transmission provider’s substation will be owned by the Interconnection Customer. The Transmission Provider will need at least 2 pairs of fiber.

DRAFT Facilities Study Report

Q0377 December 9, 2011 Page 9 CONFIDENTIAL / DRAFT

• Design, procure, install, and own the communication raceway from the substation control house to the fence line of the Transmission Provider’s protection and control, communication and interchange metering substation. The location of the raceway will be determined when detailed project engineering is performed.

• Terminate all field I/O connections required to provide data and control in accordance

with safe system operation and in compliance with the Interconnection Agreement.

• Terminate all field I/O connections required to provide data and control in accordance with safe system operation and in compliance with the Interconnection Agreement.

Work to be completed by the Transmission Provider

• Supply specifications required to terminate the new 138kV substation line.

• Provide a list of data points required for protection, control and data collection in accordance with the Interconnection Agreement.

• Construct a protection and control, communication and interchange metering substation

outside the Interconnection Customer’s substation.

• Design, procure, construct, own and maintain a dead end at the Transmission Provider’s protection and control, communication and interchange metering substation located adjacent to the Interconnection Customer’s substation.

• Design, procure, install, own and maintain a relay for under/over voltage and over/under

frequency protection of the system at the Transmission Provider’s protection and control, communication and interchange metering substation located adjacent to the Interconnection Customer’s substation. If an out of operating range condition occurs a signal will be sent to Interconnection Customer over the high speed communication system to trip the generation.

• Design, procure, install, own and maintain the revenue metering system. This includes

instrument transformers, junction boxes, and secondary lead conductors. A dial-up phone line or equivalent communications path is required for retail sales and generation accounting via the MV-90 translation system.

• The metering design package will include two revenue quality meters, a test switch, and all digital and analog data terminated at a metering interposition block. One meter will be designated a primary meter and be used for Ranger data that includes bidirectional KWH quantities, instantaneous MW, MVAr and per phase voltage data. The second or backup meter will be used for MW data sent to the alternate control center.

DRAFT Facilities Study Report

Q0377 December 9, 2011 Page 10 CONFIDENTIAL / DRAFT

• Design, procure, install own and maintain a medium D20 RTU with interposition rack using DNP 3.0 protocol into a multiplex channel.

• Design, procure, install, own and maintain the communications to the primary interchange meter that will be directly polled by Ranger using DNP 3.0 protocol. The meter will be brought into a RS-232 bridge and into the RTU mux channel.

• Design, purchase, and install the communications to the Backup interchange meter that will be directly polled by Ranger using DNP 3.0 protocol. The meter will be brought into a mux channel.

• The following equipment, installed in the Transmission Provider’s protection and control, communication and interchange metering substation will be designed, procured, installed, owned and maintained by the Transmission Provider: metering panels, line protection panel, RTU, fiber optic terminals, multiplex, and fiber optic termination panels for fiber between the Interconnection Customer’s and the Transmission Provider’s Terminal substations.

• The Transmission Provider will own and maintain the fiber optic cable between the Interconnection Customer’s substation control house and the Transmission Providers protection and control, communication and interchange metering substation control house.

• Provide a list of data inputs and outputs required for protection, control, and data

collection in accordance with the interconnection agreement.

• Perform final checkout and testing/commissioning of the Transmission Provider’s equipment located in the Transmission Provider’s protection and control, communication and interchange metering substation.

• Supply a dial up or Ethernet communications path for retail sales metering and

generational accounting via the MV-90 translation system. This may be provided by utilizing the Transmission Providers digital communications system.

DRAFT Facilities Study Report

Q0377 December 9, 2011 Page 11 CONFIDENTIAL / DRAFT

4.1.4.1 Transmission Specifications Work to be completed by the Interconnection Customer

• Substation transmission - Construct a new Interconnection Customer designed, procured, owned and maintained transmission line.

• Provide access to Transmission Provider to remove the abandoned portion of the old transmission line.

Work to be completed by the Transmission Provider • Remove approximately ¼ of a mile the abandoned transmission line from Transmission

Provider structure 11/8 to the substation.

4.1.4.2 Transmission Specifications Work to be completed by the Interconnection Customer

• Design, procure, install own and maintain a dead-end structure to industry design criteria to avoid failure located adjacent to the Transmission Provider’s protection and control, communication and interchange metering substation.

• Provide the required easements and rights of way for the Transmission Providers new substation transmission line.

Work to be completed by the Transmission Provider • Design, procure, construct, own and maintain approximately 1800 feet of 138kV

transmission line with fiber from the substation to an existing splice point on structure 11/8 on the 138kV transmission line. This will create a new transmission line.

• Design, procure, replace own and install the line relays at Terminal substation for the Terminal - Interconnection Customer substation line (circuit breaker CB101) for compatibility with the relays at the Transmission Provider’s protection and control, communication and interchange metering substation located adjacent to the Interconnection Customer’s substation.

• Design and install the necessary generator tripping/load reduction schemes that will be

required to insure system stability during system disturbances.

DRAFT Facilities Study Report

Q0377 December 9, 2011 Page 12 CONFIDENTIAL / DRAFT

• Design, procure, install own and maintain protection and control, and communications equipment. This includes but is not limited to the removal of panels A7, A16 and B2 and for the installation of two new panels. Once the designated panels are removed, the 12” panel (PC210) is to be installed in the B2 position and the 24” panel (PL345) to be installed next to it in the B1 position.

• Perform final checkout and testing/commissioning of the protection and control and

communication systems at the Terminal substation.

4.1.5 Protection and Control Specifications Work to be completed by the Interconnection Customer

• The two interconnection Customer transmission lines between the substations will be operated in parallel with the Transmission Provider’s network.

• The addition of the two new transmission lines along with the new generator creates the need for high speed fault clearing of all line faults on these lines and the other lines connected to this system to maintain the stability of the generation and power quality in the area.

• High speed clearing can be accomplished by installing pilot relaying on all of the 138kV line connected to this system. It will be the responsibility of the Interconnection Customer to implement high speed fault detection and clearing (5 cycle or less).

• High speed communication links will be needed between all of these substations to

support the pilot relaying.

DRAFT Facilities Study Report

Q0377 December 9, 2011 Page 13 CONFIDENTIAL / DRAFT

Work to be completed by the Transmission Provider • The Transmission Provider will be implementing line pilot relaying systems.

• In addition to the line protective relaying a relay used for under/over voltage protection of

the system will be installed at the substation. If the magnitude of the voltage is outside normal range the plant will be tripped

4.1.6 Metering Specifications

4.1.6.1 Interconnection Customer Power Plant Work to be completed by the Interconnection Customer

• Provide space in the substation control building for installation of the Transmission Provider owned and maintained panels and racks. Front and rear access will be required for this equipment.

Work to be completed by the Transmission Provider

• At the generation facility each of the four individual generators will have high accuracy extended range revenue class metering instrument transformers located on the high side of the transformer for per unit NET generation.

• Design, procure, install, own and maintain the revenue metering system. This includes instrument transformers, junction boxes, and secondary lead conductors. The metering design package will include revenue quality meters, a test switch, and all digital and analog data terminated at a metering interposition block. A dial-up phone line or equivalent communications path is required for retail sales and generation accounting via the MV-90 translation system.

• Design, procure, own, install and maintain ten (10) revenue quality meters and five (5) combination CT/VT wye connected metering instrument transformers. Five (5) meters will be designated a primary meter and be used for Ranger data that includes bidirectional KWH quantities, and instantaneous MW, MVAr and per phase voltage data. The primary meter will provide data to SCADA and the five (5) secondary meters will provide backup data. A dialup or dial up or Ethernet connection is required for retail sales and generation accounting via the MV-90 translation system.

DRAFT Facilities Study Report

Q0377 December 9, 2011 Page 14 CONFIDENTIAL / DRAFT

4.1.6.2 New generation Work to be completed by the Interconnection Customer

• Provide space in the substation control building for installation of the Transmission Provider owned and maintained panels and racks. Front and rear access will be required for this equipment.

• The Transmission Provider recommends the Interconnection Customer install meter by-pass switches to reduce operational disruption. If customer elects not to install metering bypass switches, the customer’s generator will need to be taken off line for metering testing, repair and service.

Work to be completed by the Transmission Provider

• Design, procure, install, own and maintain the revenue metering system. This includes instrument transformers, junction boxes, and secondary lead conductors. The metering design package will include revenue quality meters, a test switch, and all digital and analog data terminated at a metering interposition block. A dial-up phone line or equivalent communications path is required for retail sales and generation accounting via the MV-90 translation system.

• Design, procure, own, install and maintain two (2) revenue quality meters and one (1) combination CT/VT wye connected metering instrument transformers. One meter will be designated a primary meter and be used for Ranger data that includes bidirectional KWH quantities, and instantaneous MW, MVAr and per phase voltage data. The primary meter will provide data to SCADA and the one (1) secondary meter will provide backup data. A dialup or Ethernet connection is required for retail sales and generation accounting via the MV-90 translation system.

DRAFT Facilities Study Report

Q0377 December 9, 2011 Page 15 CONFIDENTIAL / DRAFT

4.1.6.3 New generation Work to be completed by the Interconnection Customer

• Provide space in the substation control building for installation of the Transmission Provider owned and maintained panels and racks. Front and rear access will be required for this equipment.

• The Transmission Provider recommends the Interconnection Customer install meter by-pass switches to reduce operational disruption. If customer elects not to install metering bypass switches, the customer’s generator will need to be taken off line for metering testing, repair and service.

Work to be completed by the Transmission Provider

• Design, procure, install, own and maintain the revenue metering system. This includes instrument transformers, junction boxes, and secondary lead conductors. The metering design package will include revenue quality meters, a test switch, and all digital and analog data terminated at a metering interposition block. A dial-up phone line or equivalent communications path is required for retail sales and generation accounting via the MV-90 translation system.

• Design, procure, own, install and maintain two (2) revenue quality meters and one (1) combination CT/VT wye connected metering instrument transformers. One meter will be designated a primary meter and be used for Ranger data that includes bidirectional KWH quantities, and instantaneous MW, MVAr and per phase voltage data. The primary meter will provide data to SCADA and the one (1) secondary meter will provide backup data. A dialup or Ethernet connection is required for retail sales and generation accounting via the MV-90 translation system.

DRAFT Facilities Study Report

Q0377 December 9, 2011 Page 16 CONFIDENTIAL / DRAFT

4.1.7 Communications Specifications Work to be completed by the Interconnection Customer

• It is assumed that OPGW fiber optic cable was installed with the two new 138kV lines.

• Install ADSS fiber optic cable from splice boxes on the final dead-end structures at the substations via underground raceways into the respective control buildings and terminate in fiber optic patch panels.

Work to be completed by the Transmission Provider • Install OPGW fiber optic cable from substation to an existing splice point on structure

11/8 on the line and install ADSS fiber into the Transmission Provider’s control house and terminate on a fiber termination panel.

4.1.7.1 Interconnection Customer Power Plant Substation: Work to be completed by the Interconnection Customer

• Provide space, cabling, and power for any equipment provided and installed by Transmission provider.

• A dialup or Ethernet connection will be required for retail sales and generation accounting via the MV-90 translation system.

Work to be completed by the Transmission Provider

• Design, procure, install, own and maintain a small D20 RTU using DNP 3.0 protocol into a mux channel connected back to the substation fiber node. Circuit breaker statuses will be hardwired to the RTU, or alternately brought in on a DNP 3.0 port on the RTU if a connection to Interconnection Customer’s control system can provide the required data. Hard wired is preferred.

• The Primary meters for generators 1-4 will be directly polled by Ranger using

DNP 3.0 protocol. The four meters can be tied together with RS-485 to combine them and an RS-485 to RS-232 converter will bring them into a mux channel.

• The Secondary meters for generators 1-4 will be directly polled by Ranger using

DNP 3.0 protocol. The meters can be tied together with RS-485 to combine them and an RS-485 to RS-232 converter will bring them into a mux channel to provide backup data to Ranger.

DRAFT Facilities Study Report

Q0377 December 9, 2011 Page 17 CONFIDENTIAL / DRAFT

4.1.7.2 New generation: Work to be completed by the Interconnection Customer

• Provide space, cabling, and power for any equipment provided and installed by Transmission provider.

• A dialup or Ethernet connection will be provided for retail sales and generation accounting via the MV-90 translation system.

Work to be completed by the Transmission Provider

• Design, procure, install, own and maintain the following: Since the meter panel for the plant will likely be located in the substation, the Gross MW and MV from the generator can be hard wired to the substation RTU. The 138KV breaker status can be hard wired over to the substation RTU. If this is not feasible, a small RTU could be installed at the Plant and fiber converters could connect it back to a mux channel at the substation, or the audio might be bridged back to the DNP 3.0 9600 baud leased line that the meters in the refinery substation are using.

4.1.7.3 New Generation Work to be completed by the Interconnection Customer

• Provide space, cabling, and power for any equipment provided and installed by Transmission provider.

• A dialup or Ethernet connection will be provided for retail sales and generation accounting via the MV-90 translation system.

Work to be completed by the Transmission Provider • Design, procure, install, own and maintain the following: The generator Primary

meter is already scanned as an RTU, providing the required analog signals. Bridge the audio of the primary meter so it can also be scanned on the same DNP 3.0 9600 baud leased line channel.

• The generator Backup meter is already scanned as an RTU. This leased line

channel could be eliminated because of the addition of interchange meters at the substations.

• The 13.8 KV breaker indications could be hardwired 1500 feet to the RTU in the

substation. If this is not feasible, a small RTU could be installed at the substation with the audio bridged onto the DNP 3.0 9600 baud leased line that the meters are using.

DRAFT Facilities Study Report

Q0377 December 9, 2011 Page 18 CONFIDENTIAL / DRAFT

4.1.7.4 Substation: Work to be completed by the Interconnection Customer

• Provide space, cabling, and power for any equipment provided and installed by Transmission provider.

• A dialup or Ethernet connection will be provided for retail sales and generation accounting via the MV-90 translation system.

Work to be completed by the Transmission Provider

• Design, procure, install, and maintain the following: Hardwire four breaker statuses 1890 feet over to RTU in substation. If this is not feasible, a small RTU could be installed at substation and fiber converters could connect it to a mux channel in the , or the audio might be bridged back to the DNP 3.0 9600 baud leased line that the meters in the substation are using.

4.1.8 Other Substations / Remote Sites Work to be completed by the Interconnection Customer

• No work required

Work to be completed by the Transmission Provider

• Salt Lake Control Center and the Portland Control Center – Engineering and installation of communication upgrades.

DRAFT Facilities Study Report

Q0377 December 9, 2011 Page 19 CONFIDENTIAL / DRAFT

5.0 Cost Estimate Interconnection – Direct Assignment Facilities Substation – Engineering, procurement and installation of metering equipment.

$215,000

Substation – Engineering, procurement and installation of metering, protection and control and communications equipment.

$215,000

Q0377 Power Plant - Engineering, procurement, and installation of metering and communication equipment.

$935,000

Q0377 218 MVA new generation – Engineering, procurement and labor to install metering, protection and control and communication equipment.

$385,000

Q0377 new generation - Engineering, procurement and labor to install metering and communication upgrades.

$185,000

NU Q0377 – Decommissioning and removal of approximately ¼ mile of transmission line from the existing Transmission Provider structure 11/8 to the substation.

$35,000

NU Terminal transmission line – Engineering, procurement and labor to construct approximately 1800 feet of transmission line from the existing line to convert it to the substation line.

$280,000

Sub-total Direct Assignment Costs $2,250,000

DRAFT Facilities Study Report

Q0377 December 9, 2011 Page 20 CONFIDENTIAL / DRAFT

Interconnection – Network Upgrade Costs Substation - Engineering, procurement and installation of the take off structure, control house, yard construction, protection and control and communications equipment.

$1,300,000

Oquirrh substation – Engineering, procurement and construction to replace three existing circuit breakers and upgrade communication and protection and control equipment.

$2,215,000

Substation – Engineering, procurement and installation of the take off structure, control house, yard construction, protection and control and communications equipment.

$1,300,000

Terminal substation – Engineering, procurement and installation of protection and control and communications equipment.

$360,000

Salt Lake Control Center and the Portland Control Center - Engineering and installation of communication upgrades.

$50,000

Sub-total Network Upgrade Costs $5,225,000 Total Cost – ER Interconnection Service – Interconnection Only $7,475,000

DRAFT Facilities Study Report

Q0377 December 9, 2011 Page 21 CONFIDENTIAL / DRAFT

6.0 Schedule This schedule is contingent upon Transmission Provider receiving the signed Interconnection Agreement by February 9, 2012. If the signed agreement is not received by that date there will be, at a minimum, a day for day slip in the entire schedule. Initiating task Date Execute interconnection agreement 2/9/2012 Engineering & procurement commences 4/9/2012 Engineering design completed 10/9/2012 Construction Begins 12/9/2012 Generator step-up transformer receives back feed power 12/1/2013 Generations testing 12/1/2013 Commercial operation 2/28/2014

DRAFT Facilities Study Report

Q0377 December 9, 2011 Page 22 CONFIDENTIAL / DRAFT

7.0 Appendix 1: Property Requirements Property Requirements for Point of Interconnection Substation The following applies to property acquired by an Interconnection Customer on which a point of interconnection substation will be built to accommodate the Interconnection Customer’s project. The property will ultimately be assigned to PacifiCorp, the Transmission Provider.

• Property must be environmentally, physically and operationally acceptable to the Transmission Provider without any material defects of title (or as deemed acceptable to the Transmission Provider) and without unacceptable encumbrances. The property shall be a permitted or permittable use in all zoning districts. Property lines shall be surveyed and show all encumbrances, roads (private or public); easements (prescriptive or express) etc.

Examples of potentially unacceptable environmental, physical, or operational conditions:

• Environmentally unacceptable conditions could include but are not limited to known contamination of site; evidence of environmental contamination by any dangerous, hazardous or toxic materials as defined by any governmental agency; property is in violation of building, health, safety, environmental, fire, land use, zoning or other such regulation, ordinances, or statues of any governmental entities having jurisdiction over the property; underground or above ground storage tanks; known remediation sites on property; ongoing mitigation activities or monitoring activities; asbestos; lead-based paint, etc. At a minimum, a phase I environmental study is required for company land being acquired in fee. Evidence will be required 60 days prior to the start of construction.

• Physically unacceptable conditions could include but are not limited to inadequate drainage; in flood zone; erosion issues; wetland overlays; threatened and endangered species; archeological or culturally sensitive areas; inadequate sub-surface elements, etc. Geotechnical studies are required by company.

• Operationally unacceptable conditions could include but are not limited to inadequate access for company equipment; existing structures on land that require removal prior to building of substation; ongoing maintenance for landscaping or extensive landscape requirements; ongoing homeowner's or CC&R's that are not acceptable to company.

• Property should be acquired by fee ownership. If fee acquisition is not possible, then the term shall be perpetual and the use exclusive and provide PacifiCorp with all property rights it deems necessary (perpetual easement). All contracts are subject to the Transmission Provider’s approval prior to execution.

DRAFT Facilities Study Report

Q0377 December 9, 2011 Page 23 CONFIDENTIAL / DRAFT

• The Interconnection customer is required to identify any and all land rights to the subject property, which are to be retained by the Interconnection customer prior to conveying property. All retained land rights are subject to the Transmission Provider’s approval.

• If the Interconnection Customer is building facilities to be owned by the Transmission

Provider, then the Interconnection Customer must obtain all permits required by all relevant jurisdictions for the use including but not limited to conditional use permits, Certificates of Public Convenience and Necessity, California Environmental Quality Act, etc., as well as all construction permits for the project

. • Interconnection Customer will not reimburse through network upgrades for more than the

market value of the property.

• Property must be assignable to company and without litigation, suit, liens, condemnation actions, foreclosures actions, etc.