final hoover power marketing, post-1987 (red...
TRANSCRIPT
FINAL
HOOVER POWER MARKETING
POST - 1987
June 7, 1985
ARIZONA POWER AUTHORITY
1810 WEST ADAMS STREET
PHOENIX, ARIZONA 85007
INTRODUCTION, SUMMARY AND SCHEDULE
Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Schedule . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7 Summary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
ALLOCATION PRINCIPLES & METHOD
Schedule A . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 Schedule B . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
ELIGIBILITY FOR ALLOCATION
Preference Qualifications &Requirements of A.R.S. Title 30 and Title 45 Eligibility for Allocation of Schedule A Power . . . . . . 13
Eligibility for Allocation of Schedule B Power . . . . . . . . . . . . 14 Non Tax-Exempt Entities . . . . . . . . . . . . . . . . . . . . . . . 15
DISCUSSICN OF PUBLIC COMMENTS. Possible Delay of Hoover Allocation and Contract Completion Dates . . . . . . . . . . . . . . . . . . . . . . 16 Hoover Schedule A and Renewal of Existing Hoover Allocations . . . . . 17 Hoover Schedule B and CAWCD. . . . . . . . . . . . . . . . . . . . . . 17
Consideration in Allocating Hoover Schedules A & B Power . . . . . . . 19 Allocation to City of Page . . . . . . . . . . . . . . . . . . . . . . 22 Term of Contracts . . . . . . . . . . . . . . . . . . . . . . . . . . 23
Considerations Under Recapture Conditions . . . . . . . . . . . . . . 18 Allocation of Schedules A & B Energy . . . . . . . . . . . . . . . . , 21
Customer's Contract Subject to Western Area Power ministration Contracts . . . . . . . . . . . . . . . . . . . . . . 24 Power Purchase Certificate . . . . . . . . . . . . . . . . . . . . . . 24 Opinion Letters of Legal Counsel; Resolution . . . . . . . . . . . . . 25 Financial Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25 Facilities of Others . . . . . . . . . . . . . . . . . . . . . . . . . . 26 Power Excess to Needs of Purchaser . . . . . . . . . . . . . . . . . . 26 Failure to Contract . . . . . . . . . . . . . . . . . . . . . . . . . 27 Allocation at Transmission Delivery Points . . . . . . . . . . . . . . 2 7 Hoover Uprating Program . . . . . . . . . . . . . . . . . . . . . . . 27
INTRODUCTION, SUMMARY AND SCHEDULE
Introduction
According to the Boulder Canyon Project Act, a portion of the power
output of the Federal Hoover Dam hydroelectric facility was allotted to Arizona
in its "sovereign capacity". The Arizona Power Authority ("Authority") is
the entity in Arizona established to receive and market Arizona's allotted
share of Hoover power. The Authority has been marketing Hoover power in
Arizona since 1952.
The present contract under which the Western Area Power Administration
sells Hoover power to the Authority expires on May 31, 1987.
The contracts under which the Authority sells Hoover power to its customers
also expire on May 31, 1987 .
The Authority has developed the final Hoover Power Marketing Plan
("Plan")contained herein, through a public process. The Authority began
that public process on September 1 4 , 1984, with
A Public Comment Forum was held on November 1 were solicited and received by the Authority.
a Public Information Forum.
1, 1984. Written comments
On January 11, 1985, 52
interested entities submitted Applications for amounts of either or both of
Hoover Schedule A and Schedule B power. These entities also submitted
Profile Data information requested by the Authority.
On March 2 9 , 1985, the Authority issued its Proposed Hoover Power
Marketing Plan. A second Public Comment Forum was held on April 26 , 1985,
and written comments were again solicited and received by the Authority to
A summary of the written comments received was included in the Authority's 1
Proposed Hoover Power Marketing Plan, dated March 29, 1985.
gather public input concerning the Authority's Proposed Hoover Power
Marketing Plan. 2
Summary
The Plan presented herein serves as the principles and guidelines for
the marketing of Hoover Schedule A and Schedule B power by the Authority.
This Plan provides:
1. Under the Plan, Districts with existing Hoover contracts with the
Authority will receive existing kilowatt (kW) contract amounts from
Schedule A .
2 . The remaining Schedule A contingent capacity (approximately 30,000
kW) wil l be allocated among those Districts which do not have existing
Hoover contracts with the Authority.
3 . The available Schedule A energy will be allocated among all Districts
based upon an equal division of kilowatt-hours (kWh) per kilowatt.
4. Schedule B contingent capacity and energy will be divided between
qualified tax-exempt and non tax-exempt entities on a 75/25 percent
basis as presently specified in I. R. S . (Treasury) Regulations.
5. A s suggested in its Public Information Forum of September 1 4 , 1984,
the Authority wil l include in its power purchase contracts for Schedule B
Hoover power and energy a "recapture" provision in the following form
which will not be subject to negotiation or modification (other than
technical corrections) :
"Notwithstanding any other provision in this contract (and in addition to any other recapture rights of the Authority), the Schedule B Hoover capacity and energy is sold under this contract on a withdrawable basis; that is , the capacity and energy are subject to an absolute right of recapture by the
Table One (attached) presents a summary of the written comments received. 2
-2-
Authority for the benefit of the Central Arizona Water Conservation District at any time or times during the term of this contract. The purchaser under this contract has no vested right or interest in the determination of the amount o r disposition of capacity and energy recaptured by the Authority.
In each event of recapture, the capacity and energy shall be withdrawn from all Schedule B Hoover contractors on a pro- rata basis. If the recapture provision in any contract for Schedule B power and energy shall be held invalid o r unenforceable by a final judicial decision from which no further appeal may be taken, then Schedule B power and energy shall be withdrawn on a pro-rata basis from those Schedule B power and energy contractors with which there remains a right of recapture which has not been determined by a final judicial decision to be invalid or unenforceable.
Each exercise by the Authority of its right to recapture Schedule B Hoover capacity and energy shall be accomplished as follows:
A. The Authority shall give the contractor written notice of recapture not less than twenty-four (24 ) months prior to the effective date of the recapture.
B. The Authority's notice shall identify the amount of capacity and energy which will be recaptured and the effective date of recapture.
The Authority's right to recapture shall not be affected by any claim of rights by the contractor from which the capacity and energy is recaptured, whether arising by reason of past, present or future claims."
The Authority wi l l recapture Schedule B Hoover capacity and
energy in accordance w i t h the foregoing contract provision in order to
implement a Plan adopted by the Secretary of the Interior for marketing
Navajo Surplus power and energy pursuant to Section 107(c) of the
Hoover Power Plant Act of 1984, if such adopted Plan includes:
a. Contracting for Schedule B Hoover capacity and energy by the
Central Arizona Water Conservation District (CAWCD) , and
b. Utilization and assignment of revenues from the sale and
exchange of Navajo Surplus power and energy as authorized by the
Hoover Power Plant Act of 1984, at least sufficient to make repayment
-3-
and establish reserves for repayment of $175,000,000 (or more) of funds
advanced by CAWCD for construction of authorized features of the
Central Arizona Project.
Recapture will be accomplished by giving written nctice of
recapture of all Schedule B capacity and energy included in the Navajo
Marketing Plan and doing all other acts necessary to effect the recapture
after adoption of the Plan by the Secretary of the Interior and not later
than 90 days after the receipt by the Authority of a written request by
CAWCD to recapture such capacity and energy.
The Authority will, at the time it offers power purchase contracts
for Schedule B Hoover power and energy, offer a power purchase
contract to CAWCD stating the terms under which Schedule B Hoover
power and energy recaptured by the Authority will be sold to CAWCD.
The Authority's contract offered to CAWCD shall, to the extent
practicable and consistent with the provisions of this marketing plan,
contain the same terms and conditions as the contracts with other
Schedule B Hoover power and energy contractors; provided, however,
that the recapture provision contained in other contracts will not be
included in the CAWCD contract.
. The Authority will not give notice of recapture of Schedule B
Hoover power and energy unless (and until) the following conditions
have been met by CAWCD, nor will a recapture of Schedule B Hoover
power and energy take effect unless, at the effective date of such
recapture, the following conditions continue to be met by CAWCD:
a. CAWCD has entered into a binding power purchase contract
w i t h the Authority for the purchase of Schedule B Hoover power and
energy and CAWCD has accepted, as a part of its contract, the
-4-
modifications, amendments and supplements required by the Authority in
its contracts wi th other Schedule B Hoover power contractors.
b. CAWCD shall have obtained (and the Authority shall cooperate
with CAWCD in seeking to obtain) written evidence from the rating
agency (or, if more than one rating agency shall have rated bonds o r
notes the Authority issued for the Hoover Uprating Project, rating
agencies) to the effect that such rating agency or agencies has reviewed
the power sales contract between the Authority and CAWCD and that, in
its or their opinion, the sale of the recaptured power and energy to
CAWCD pursuant to such power sales contract wil l result in a rating on
such bonds or notes of the Authority at least equal to the then existing
rating on such bonds or notes; provided, however, that nothing herein
contained shall prevent CAWCD from taking such actions including, but
not limited to, a letter of credit or other credit enhancement device as
may be necessary or advisable to support the CAWCD's payment obliga-
tions under the power sales contract; the Authority will cooperate wi th
CAWCD in its efforts to obtain written evidence of the opinion of such
rating agency or agencies that the sale of the recaptured power and
energy pursuant to such power sales contract will result in a rating on
such bonds or notes of the Authority at least equal to the then existing
rating on such bonds o r notes.
c . CAWCD has furnished to the Authority an opinion of a national
consulting engineering f i r m that the projected revenues of the Central
Arizona Water Conservation District can be reasonably expected to be
sufficient to fulfill its financial obligations under its power purchase
contract w i t h the Authority and such opinion is current and in place on
-5-
the date upon which recapture of Schedule B Hoover power and energy
takes effect.
The Authority does not intend that this Hoover power marketing
Plan by the Authority should constitute an interpretation of Section
107(b) of the Hoover Power Plant Act of 1984.
6 . If included as a part of the Navajo Marketing Plan adopted by the
Secretary of the Interior, the Authority intends to allocate and sell
Schedule C energy in a manner which is consistent with such adopted
Plan.
7. The available Schedule B energy will be allocated among all
qualified entities based upon an equal division of kilowatt-hours per
kilowatt.
8. The Authority will attempt to obtain additional supplies of energy
to supplement the annual f i rm energy to be made available with either
Schedule A or Schedule B (or both) if a customer so requests.
9. Each of the Authority's customers will be responsible for carrying
the required amount of generation reserves or making appropriate
arrangements with others for such reserves. The Authority, if
requested by any customer, wil l investigate and attempt to make
appropriate arrangements to obtain these generation reserves or will
assist, when possible, any customer in making such arrangements.
1 0 . The allocations of Schedule A and Schedule B have been made at
transmission delivery points located on Western's Parker-Davis
Transmission System. These Hoover A and B allocations are subject to
adjustment, f r o m 'time to time, for changes in transmission losses f r o m
Hoover to the transmission delivery points. Table Three includes
-6-
Schedule A and Schedule B allocations, both at Hoover generation and at
transmission delivery points.
The results of applying the Marketing Plan guidelines and principles are
summarized in attached Table Two and detailed in the attached Table Three,
In general, these results are:
Schedule A Schedule B 3
Existing Customers New Customers
Schedule
83% 17%
5 0% 50%
A schedule for developing and completing the final Marketing Plan, the
Hoover allocations and customer contracts was announced by the Authority at
the September 14, 1984 , Public Information Forum. Since that time, the
Authority, in response to requests from interested entities, delayed
publishing the Proposed Power Marketing Plan a total of 49 days to insure
that all applicants received equitable treatment and also to insure that
interested parties would not be penalized by a lack of reasonable opportunity
to comply with the Authority's marketing schedule.
The schedule for completing the remaining portions of the marketing and
contracting of Hoover Schedule A and Schedule B power and energy is:
* Filing of customer's application for purchase .of Hoover power and energy allocated herein. July 1, 1985
* Customer's financial data and opinion of legal counsel on ability to contract to be available.
* Customer contracts available for execution
October 1, 1985
October 1, 1985
3The Schedule B allocations are subject to recapture for CAWCD.
-7-
* All applications and Power Purchase Certificates to be filed and issued by Authority to customers October 1, 1986
* Customer contracts with others for wheeling and delivery of Authority power (if required) October 1, 1986
The Authority will cooperate with and furnish necessary information to
assist the customers in meeting the dates for the above activities in a timely
manner.
-8-
ALLOCATION PRINCIPLES & METHOD
1. Schedule A
The Authority was guided by comments received during the public
process and by its own Regulations in arriving at a fair allocation of the
Schedule A resource. The Authority believes that renewal of existing
contract kilowatt amounts and an allocation of the remaining Hoover Schedule
A power among those districts without existing Authority contracts will
provide a fair and equitable distribution of the Schedule A resource based
upon the following set of allocation principles and the allocation method
described below :
a. Allocation Principles - Schedule A
Allocation was made to the greatest number of eligible purchasers under
Arizona law taking into consideration the following items:
* First category preference under Title 30 to Districts. (A.R.S.
030-125)
* Distribution made on the widest possible use. (APA Reg.
R12-14-21A)
* Consideration given to the existing electric needs of applicants.
(APA Reg. R12-14-21B)
* The reliance of existing customers on a hydroelectric power
b. Allocation Method - Schedule A
1) The distribution of Schedule A power within each category was made
on the basis of the applicant's net load requirement. (Power was
allocated to the extent that the total hydroelectric resources (Hoover,
-9-
Colorado River Storage Project -"CRSP"- and Parker-Davis) did not
exceed 100 percent of the applicant's load requirements.]
2 ) Renewal of existing customers' kilowatt contract amounts because of
reliance upon hydroelectric power.
3 ) Remaining Schedule A capacity (approximately 30,000 kW) allocated to
new district applicants based on their total net existing electric load
requirements.
4 ) Schedule A energy allocated to existing customers, as well as new
eligible applicants, based upon an equal division of kilowatt-hour per
kilowatt of available Schedule A energy.
2 . Schedule B
The Authority was guided by comments received during the public
process and by its own Regulations in arriving at a fair allocation of the
Schedule B resource. This allocation is represented by a set of allocation
principles and an allocation method as described below:
Allocation Principles - Schedule B a.
Allocation was made to the greatest number of eligible purchasers under
Arizona law taking into consideration the following items:
* The greatest practical number of qualified potential users of
electric power based on the electric load requirements of
purchaser. (APA Reg. R12-14-21C)
An equitable distribution among all applicants of a class, w i t h due
consideration for priorities and preferences, as between different
classes. (APA Reg. R12-14-21C)
Limited concentration of power allocated to a particular customer or
service area. (APA Reg. R12-14-21E)
*
*
-10-
* An equitable distribution for water programs of districts,
municipalities and private utilities under Arizona law. ( A . R. S . 445-2501)
* Long-term contract use and future load trends.
* The State Water and Power Plan (Title 45 ) was originally enacted
for the purpose of constructing and financing the Central Arizona
Project (CAP); with the passage of federal legislation for the CAP,
the financial responsibility originally contemplated by the plan in
Title 45 , does not now exist. However, because of the need for
the State to assist the CAP under present conditions, Schedule B
power and energy has been distributed as outlined above, but will
be subject to recapture for the benefit of CAP.
b. Allocation Method - Schedule B
1) Schedule B power and energy was .divided among qualified
tax-exempt entities and qualified non tax-exempt public utilities on the
basis of a 75 /25 percent division under current I . R . S . Regulations.
(A.R.S. 045-2508)
2) The djstribution of Schedule B power, within each method and
category, was made on the basis of the applicant's net load requirement.
Power was allocated to the extent that the total hydroelectric resources
(Hoover, CRSP and Parker-Davis) did not exceed 100 percent of the
applicant's load requirements.
3 ) Schedule B energy was allocated to all eligible applicants based on
an equal division of kilowatt-hours per kilowatt of available Schedule B
energy.
4) Three main allocation distributions were made to each category
identified in Item 1 above:
-11-
a) One-third of available Schedule B was allocated equally among
all qualified applicants on the basis of widespread use
(approximately 45,000 kW for tax-exempt and approximately 15,000
kW for non tax-exenpi utilities).
b) One-third of Schedule B was allocated on the basis of
water-related programs of districts, municipalities and private
utilities. This distribution was limited to not greater than a 50
percent concentration to any one entity.
c) One-third of Schedule B was allocated to all qualified
applicants based upon peak load requirements which may occur
during the years 1984-1989 , including any possible conversions
from natural gas irrigation pumping. This distribution was limited
to not greater than a 50 percent concentration to any one entity.
-12-
ELIGIBILITY FOR ALLOCATION
The Authority, in accordance with the requirement to allocate Hoover
power pursuant to Arizona law and the Authority's Regulations (and
applicable federal statutes and regulations) , has made the following
determinations :
1. Preference Qualifications & Requirements of A.R.S. Title 30 & Title 45 Eligibility for Allocation of Schedule A Power
In its allocations of Schedule A power, the Authority Commission was
required to follow the provisions of Title 30, A.R.S., which, when read in
conjunction with the provisions of the State Water and Power Plan (A.R.S.
045-2501, et seq.) , direct that the power resources designated as "Schedule
A'' be marketed pursuant to A.R.S. 030-101, et seq, as amended.
To qualify for an allocation under Title 30, an entity must be a
"qualified purchaser1', "Qualified purchasers" include :
"Per sons "Operating Units"
1. Natural Persons 1. Districts 2. Mutual & Cooperative 2. State Agencies
3 . Corporations 4. Cities 4. Business Trusts 5. Towns 5. Partnerships
Concerns 3 . Federal Indian Agencies
"Districts" are further defined as power organizations comprehended in
the Arizona Power Authority (A.R.S. Title 30) or water organizations
comprehended in A.R.S. Title 4 5 , or both.
Eligibility for Schedule A power is also controlled by the order of
preference established in A.R.S . 030-125, which, in essence, states that if
available power supplies are insufficient to meet pending power applications,
preference must be given in the following order of priority:
-13-
First: Districts Second: Incorporated Cities, Towns & Cooperatives Third: Applicants other than Districts which use
power primarily for irrigation and drainage purposes, or both.
Fourth : Any Qualified Applicant
Because the supply of Schedule A power is insufficient to meet all
pending power applications (i. e . , available power, at transmission delivery ,
points, is 181,730 kW, and pending applications for Schedule A power exceed
649,000 kW) , the Authority Commission, by law, has been required to restrict
the allocations .of Schedule A power to Districts only. Therefore, no entities,
other than Districts, are entitled to an allocation of Schedule A power,
Eligibility for Allocation of Schedule B Power
Arizona law requires the Authority to market the Hoover Uprating power
(Schedule B) under the provisions of the State Water and Power Plan. (See
A . R . S . 545-2501, et seq., as amended.)
Under the 1982 amendments to the State Water and Power Plan, eligibility
for an allocation of Schedule B Power was restricted to public utilities
providing electrical service and Districts organized to provide electrical
service, except that non tax-exempt public utilities were allowed to purchase
the maximum amount of Schedule B power permitted by federal regulations
concerning the issuance of tax-free bonds.
Although the definition of a "public utility", as contained in the State
Water and Power Plan (A.R.S. §45-2502) is quite broad, the 1982
amendments, being specific in their terms, control over the general definitions
section in the statutes relating to this subject.
Similarly, the definition of a lldistrictff is also quite broad, but, again,
the 1982 amendments, being specific, control the general definitions.
-14-
Consequently, only those public utilities "providing electrical s e r v i c e " ,
and only those "districts" which are "organized to provide electrical service"
were deemed eligible for an allocation for Schedule B power. Cities and
towns , for example , which are not "providing electrical service" were deemed
by the Commission to have been excluded from eligibility as a result of the
1982 amendments to the State Water and Power Plan.
Non Tax-Exempt Entities
As noted above, the 1982 amendments to the State Water and Power Plan
reserved to non tax-exempt public utilities an option to purchase the maximum
amount of Schedule B power which is permitted by federal regulations
governing the issuance of tax-free bonds. In considering the allocations of
Schedule B power, the Authority Commission assumed that current tax
regulations would allow such utilities to purchase up to 25 percent of the
Schedule B resource. The identity of entities as being either tax-exempt o r
non tax-exempt was based upon the interpretation of federal tax regulations
by the Authority's bond counsel.
-15-
DISCUSSION O F PUBLIC COMMENTS
Throughout the public process, the Authority received numerous
constructive and hslpful comments from electrical and irrigation districts ,
public and private electric utilities, municipalities, customer organizations,
associations and private citizens. The comments centered around eight major
issues:
1. The impact of possible delay upon the Hoover allocations and
customer contract completion dates.
2 . Hoover Schedule A and renewal of existing Hoover allocations.
3 . Hoover Schedule B and the Central Arizona Project, including
recapture for (and pooling with) the CAWCD.
4 . Considerations under recapture conditions.
5. Considerations in allocating Hoover Schedules A and B power,
including : (a) total Colorado River resources not exceeding any entity's
load requirements; (b) irrigation and water-related load requirements;
and (c) natural gas and future load requirements.
6 . Allocation of Schedule A and Schedule B energy.
7. Allocation to City of Page.
8. Term of contracts.
1. Possible Delay of Hoover Allocation and Contract Completion Dates
The Authority appreciates the significance of the comments which have
been submitted by numerous entities regarding the importance of the timely
completion of the Authority's Marketing Plan and the completion of the
individual activities and contracts with each of the Authority's proposed
customers. The Authority has recognized, and continues to recognize, the
importance of timely completion of these activities so the Authority will be in
-16-
a position to make all the necessary arrangements to achieve the benefits
which will be available to entities in the State of Arizona through the
acquisition of both Hoover Schedule A and Schedule B power.
2 . Hoover Schedule A and Renewal of Existing Hoover Allocations
The Plan provides for a renewal of the existing kilowatt contract amounts
f r o m Schedule A . Through the public process, the Authority received
comments in favor of renewal and comments opposing such renewal. The
Authority has considered both sides of this question.
The predominance of comments received from Districts w i t h existing
Hoover contracts was for renewal. Other entities, including some Districts
without existing Hoover contracts, also urged renewal. Those opposed to
renewing the existing contract amounts indicated Schedule A power should be
allocated among all qualified entities based on each entity's individual load
requirements. The Authority considered both of these approaches. Study
results show that little, if any, difference would result in the amount of
Schedule A power (kilowatts) which would be allocated to those districts
without existing Authority Hoover contracts if the methodology of allocating
on the basis of individual load requirements was used. Thus, the question of
renewal versus non-renewal does not weigh upon the allocation of Hoover
Schedule A power.
3 . Hoover Schedule B and CAWCD
The Plan divides the Hoover Schedule B contingent capacity and energy
between qualified tax-exempt entities and non tax-exempt entities on a 75/25
percent basis. Many comments were received regarding making some or all of
the Schedule B resource available for pooling with CAWCD generation
resources for the purposes and benefit of the Central Arizona Project.
.
-17-
Many of the comments urged that pooling concepts should be explored
but that committing an allocation of the Hoover Schedule B resource for this
purpose at this time was premature. The Authority recognizes that potential
benefits may accrue through the future use of the Hoover Schedule B
resource in conjunction wi th the Central Arizona Project. However, the
Authority also recognizes the very same Hoover Schedule B resource can also
provide current and future benefits to the applicants for this power. The
Authority has recognized both of these sets of benefits in arriving at its
Marketing Plan by allocating the Hoover Schedule B resource in such a
manner that the Schedule B resource will be subject to recapture by the
Authority in accordance with the recapture provision included under
of this Marketing Plan, supra, pages 2-6.
4. Considerations Under Recapture Conditions
Several Districts commented that to recapture Schedule B power for the
benefit of CAWCD from entities not receiving water from the CAP is neither
justified nor equitable. These Districts argued that through taxation and
surcharges they are required to support the CAP but do not receive any of
its direct benefits.
The Authority understands these concerns and in its marketing process
considered a number of suggestions. To address this problem, the Authority
will , in the future, assist these Districts (and others if requested to do so)
in solving power procurement difficulties in the following manner:
a. A s stated in more detail under "Conditions of APA Power Purchase
Contract" in this Marketing Plan, the Authority will, under its
redistribution and reallocation procedures, give due consideration to the
electric needs of these customers.
b. Under the Navajo Marketing Plan addressed in the Hoover Power
Plant Act of 1984 and upon recapture of Schedule B power, it is
anticipated that upon implementation of that Plan, certain amounts of
Navajo power and energy will be made available for purchase at
appropriate savings to such purchasers. The Authority, if requested by
its customers, will attempt to replace such amounts of recaptured
Schedule B power with Navajo power; or explore the purchase of
additional amounts of Navajo power, as well as the purchase of other
lower cost power supplies.
c. The Authority believes that through pooling of electric power loads
and resources and through centralized wholesale power purchase
contracts with generation utilities, appropriate savings can also be
accomplished. The Authority will explore these alternatives with its
customers.
5. Consideration in Allocating Hoover Schedules A and B Power
Many of the comments received by the Authority during the public
process dealt with the mechanics of allocation. These comments centered
around (a) consideration of the amount of existing Colorado River resources
available to each applicant; (b) the types of loads to be served, including
irrigation and water-related electric load requirements ; and (c) consideration
of loads currently served by natural gas and future load requirements.
A s previously noted, the Authority has proposed that the Schedule A
capacity be allocated to Districts under a renewal approach combined with
providing the remaining amount of Hoover Schedule A capacity to those
districts without existing Hoover contracts ; the distribution of the remaining
Schedule A capacity (approximately 30,000 kW) among those districts was
made on the basis of the net load requirements. Net loads were determined
-19-
by taking the five-year average kilowatt peak demand loads (1979 through
1983) as submitted in each applicant's Profile Data and deducting that
applicant's share of the Colorado River electric resources (Parker-Davis plus
Colorado River Storage Project ). Schedule A contingent capacity allocations
were limited so that the applicant's total hydroelectric generation resources
did not exceed 100 percent of the applicant's load requirements.
A number of Districts commented that four-year average loads (obtained
by omitting 1983 data, perceived by some as a year with unusually low loads
because of the federal "Payment In Kind" program) should be used. The
comments suggested that because 1983 was a below-average year, its inclusion
produced inappropriate averages. This suggestion was tested by comparing
the proposed five-year average to the suggested four-year average loads.
The results showed that some entities' averages decreased and some
increased. Overall, the Districts' four-year average load decreased by only
one percent, rather than increasing, The five-year average provides a
broader base of data, and no equitable basis for eliminating 1983 appears to
exist.
Two Districts commented that existing natural gas loads should have
been included in the allocation bases for both Hoover Schedules A and B. A
variety of factors have been suggested for allocating Schedules A and B .
The Authority Commission has considered several alternative bases , including
natural gas loads. The use of many of these factors would have increased
the complexity of the allocation process beyond reasonable bounds. Examples
of these complexities (in the case of natural gas loads) are that the Authority
would have been required to obtain commitment schedules for converting the
natural gas facilities which, in turn, would require a mechanism for reviewing
the schedule of conversions. Further, the Authority would have been
-20-
required to assure that satisfactory electric transmission and distribution
facilities were either in place, or could be arranged, in time for these
potential customers to receive allocated power. The Authority Commission
has, however, given recognition to identifiable natural gas loads by including
those requirements as future loads in the allocation base for a portion of
Schedule B.
The proposed allocation issued on March 2 9 , 1985, used the existing
CRSP contract amounts. Many entities commented that future CRSP
allocations are to be reduced (effective 1989) in accordance with a September,
1984 , announcement by the Western Area Power Administration. I t was
suggested that the Authority should use the future CRSP amounts instead of
the existing amounts. Both levels of the CRSP resource were investigated.
The use of future CRSP amounts causes only small changes in the allocation
of Schedules A and B. The Authority Commission believes it is appropriate
to use the future CRSP amounts in the process of determining net loads for
the final allocation of Hoover Schedules A and B .
A few comments were received regarding the use of the highest five-year
peak demand for four Districts (which would have received a smaller allocation
than their existing contract amounts) in arriving at the proposed Schedule A
allocation. The Authority Commission, in order to be consistent in its
allocation method, used the same approach (five-year average peak demands)
for all Districts in the final allocation of Hoover Schedule A capacity.
6. Allocation of Schedules A and B Energy
The Plan provides for allocating Schedules A and B energy on an equal
kilowatt-hours per kilowatt basis. The Authority received several comments
during the public process favoring this approach; no comments in opposition
were received.
-21-
The equal kilowatt-hours per kilowatt approach is consistent w i t h past
practices of the Authority and others in the distribution of energy associated
with an electric capacity resource. The Authority also believes this approach
will provide the best and most fair distribution of this energy among all
entities receiving a share of either Hoover Schedule A or Hoover Schedule B
capacity.
7. Allocation to City of Page
The Authority has allocated 1 ,000 kW of Schedule B Hoover power and
energy to the City of Page, Arizona, contingent upon the Ci ty executing a
power sales contract when offered by the Authority and further conditioned
upon the completion by the City of arrangements necessary to qualify itself as
a public utility providing electric service not later than six months prior to
the effective date of the contract.
Comments from the Town of Gilbert, Arizona, and the Gila River Indian
Community Utility Authority ("CRICUA") suggest (among other points) that
they should be treated similarly to Page because they intend, at some future
time, to provide electrical service.
Based upon present circumstances, the position of the City of Page is
easily distinguishable from that of Gilbert and GRICUA. In the case of Page,
the Ci ty has already undertaken the steps necessary to qualify as an entity
"providing electrical service". Page has held an election in which the voters
approved acquisition of electric facilities of Arizona Public Service Company
(APA) which services the City.4 Based upon the approval of its voters, Page
4The Authority understands that a lawsuit contesting the election is on appeal.
-22-
has also commenced condemnation proceedings to acquire the APS facilities.
Neither Gilbert or GRICUA has undertaken similar qualifying steps.
Furthermore, Page arguably is already "providing electrical service" as a
result of the direct allocation to it, of Colorado River Storage Project (CRSP)
power, pursuant to the "Page, Arizona, Community Act of 1974" (P.L.
93-493, 93rd Congress; H.R. 15736, October 27, 1974), a part of the
"Reclamation Development Act of 1974".
8. Term of Contracts
The Authority received several comments during the public process
which urged a fixed thirty-year contract term. As previously noted, by the
Authority at page 19 of its Hoover Power Marketing booklet (initially
distributed at the Public Information Forum on September 14 , 1984), the
Authority's contract with its customers will have a term of thirty years. In
accordance with A . R . S . Title 30, the Authority reserves the right to
terminate that portion of the contract attributable to Schedule A power and
energy, upon reasonable notice by the Authority, at any time after the initial
twenty-year contract period.
-23-
CONDITIONS OF APA POWER PURCHASE CONTRACT
1. Customer's Contract Subject to Western Area Power Administration Contracts
The Authority's contract with the Western Area Power Administration
(Western) will contain terms and conditions which will be applicable to power
marketed by Western under the Conformed General Consolidated Power
Marketing Criteria or Regulations for the Boulder Canyon Area Projects and
in accordance .with the Hoover Power Plant Act of 1084. The Authority's
contracts with its customers, effective June 1 , 1987, will also contain terms
and conditions which are necessary to comply with the provisions of the
Authority's contract for purchase of Hoover power from Western, as well as
the terms and conditions for delivery under a transmission contract from
Western of such power to points of delivery on Western's Parker-Davis
Transmission System.
Terms and conditions of the Authority's contracts with its customers will
provide for (but wi l l not be limited to) the following: 1) Contract Term; 2 )
Conservation Programs ; 3 ) Reserve Requirements; 4) Transfer of Contract
Rights; 5) Conditions on Resale of Power and Energy; 6) Metering; 7 )
Performance Bonds; 8) Delivery Points and Conditions; 9) Losses; 10) Billing;
11) CAWCD Recapture Provision; and 1 2 ) Power Availability. The contracts
will also be subject to all applicable provisions of federal law, including the
Colorado River Compact; the Hoover Power Plant Act of 1984; the Boulder
Canyon Project Act; and the Boulder Canyon Project Adjustment Act and any
applicable federal regulations relating to the Hoover hydro-power resource.
2 . Power Purchase Certificate
No person or operating unit in the State shall become a purchaser of
-24-
electrical power from the Authority unless a power purchase certificate is
obtained as provided in Article 3 , Title 30 Arizona Revised Statutes
( A . R . S . ) , or as provided by the Authority's Regulations.
Following the date upon which power purchase contracts are offered for
execution (scheduled for October 1, 1985), and not later than October 1,
1986, a purchaser shall apply for and obtain a power purchase certificate
from the Authority, pursuant to procedures established by the Authority.
3 . Opinion Letters of Legal Counsel; Resolution
Upon execution of a power purchase contract; upon initial revenue bond
financing by the Authority and upon any subsequent financing, each
purchaser will be required to provide to the Authority (and its financial
representatives) an opinion letter of the purchaser's legal counsel indicating
that the purchaser is legally entitled to enter into the contract upon the
terms and conditions set forth in the contract. The opinion letter must also
be accompanied by a proper form of Resolution authorizing the execution of
the contract by the purchaser. The opinion letter and the Resolution must
be in a form acceptable to the Authority and its advisors and will be in
substantially the same form as the letter and Resolution previously circulated
among interested parties. (A sample form of opinion letter and Resolution will
be provided upon request.)
4. Financial Data
In connection with the Authority's power purchase contracts and its
financing program for the Hoover Uprating Project, each purchaser will be
required, upon the Authority's request, to provide financial data and
certification regarding such financial data.
-25-
5 . Facilities of Others
A purchaser not engaged in the management and operation of its own
electric transmission or distribution system will be required, on or before
October 1, 1986, to submit for approval by the Authority, its respective
contracts or agreements with others for the handling, wheeling, utilization,
administration and delivery of power and energy purchased from the
Authority.
6. Power Excess to Needs of Purchaser
a. Relinquishment with Right to Recapture: Authority Hoover power,
from time to time, may be in excess of the purchaser's immediate needs.
Power purchase contracts will provide that purchasers may tender or
relinquish to the Authority, for resale by the Authority, power and
energy not deemed immediately needed. Such power and energy will be
subject to recapture by the purchaser if needful and necessary within a
reasonable period of time. However, such tender or relinquishment for
resale shall not relieve the purchaser of any original contractual
obligations except under such conditions as may be provided in
supplemental contracts or agreements covering the resale of such power
or energy . b. Restoration to Authority Power Pool: Authority Hoover power, from
time to time, may be in excess of the purchaser's needs due (among
other things) to load change or delivery of Central Arizona Project
water. Authority contracts will provide that any Schedule A o r Schedule
B power which is found to be excessive or unnecessary for the electric
needs of the purchaser may be surrendered for restoration to the
Authority power pool, subject to approval of the Authority; provided,
however, that in the resale or reallocation of power and energy under
-26-
this paragraph and under paragraph 6a, above, due regard and
consideration shall be given to the electric needs of qualified districts
which do not receive, or are not eligible to receive, delivery of water
from CAP
7. Failure to Contract
If a purchaser (or
contract at the time such
potential purchaser) fails to place power under
contract is offered by the Authority (scheduled for
October 1, 1985), in accordance with the terms and conditions offered by the
Authority, or fails to obtain a power purchase certificate (or fails to meet
conditions precedent or to provide such other documentation or agreements
that may be required for the delivery of such power), the amount of power
and energy for which no effective contract has been made wil l be reallocated
for purchase by other qualified entities.
8. Allocation at Transmission Delivery Points
The amounts of Hoover contingent capacity (kW) and energy (kWh) listed
in the attached Tables Two and Three are at transmission delivery points on
Western's Parker-Davis Transmission System. To determine capacity and
energy amounts at generation, a four percent (4%) loss figure must be added.
This four percent (4%) transmission loss value is subject to modification from
time to time. Appropriate adjustments will be made in the amounts of Hoover
Schedules A and B capacity and energy when (and if) the four percent (4%)
value is modified. The Authority has also included in Table Three, the
allocation of Hoover Schedules A and B capacity and energy, at generation.
9. Hoover Uprating Program
The capacity amounts listed for Schedule B are equivalent to the
Authority's total allocated amount. The total Hoover Uprating Program wil l
provide an additional 503 MW of contingent capacity, of which the Authority
-27-
has been allocated 188 MW. The Hoover Uprating Program is now underway
by the United States Bureau of Reclamation (Bureau), and the Authority
estimates that approximately 90 MW will be available to the Authority on June
1, 1987 (the Bureau's determination of this amount is not known at this time).
The development and subsequent availability of the Hoover Uprating
capacity and associated energy is contingent upon the Authority finalizing
financing agreements w i t h the Bureau. The availability of such capacity and
energy is also contingent upon completion of the Uprating Program, which is
to be completed in stages and is currently scheduled for completion in 1992.
Power contracts effective on June 1, 1987, will contain an estimated schedule
for power deliveries from the Uprating Program as the Program progresses.
If any part of the Uprating Program is not completed, the total amount
of contingent capacity initially allocated to contractors will be reduced on a
proportional basis. Power proposed for Schedule A allocations wi l l not be
affected. If, subsequent to such a *capacity reduction, the Uprating Program
is reinstated, in whole or in part, the amounts initially allocated wil l be
restored to the contractors in proportionate amounts as the Upratings are
completed.
- 2 8 -
E N T I T Y C O M M E N T S S U M M A R Y
TABLE ONE PAGE 1-1
JUNE 7, 1985
ENTITY _____-c-----------------
Aguila Irrigation
Avra Valley Irrigation & Drainage District
Conservation District
District
Buckeye Water
Central Arizona Water Conservation District
Chandler Heights Citrus
Cortaro-Harana
Irrigation District
Irrigation District
Electrical District 1, Pinal
Electrical District 2 ,
Elect r i c a lDistrict 3,
Electrical District 4,
Electrical District 5,
Electrical District 5 ,
Electrical District 6,
Pinal
Pinal
Pinal
Maricopa
Pinal
Pinal
ARS ARS HIGHEST
30 45 SCBED RENEWAL DEMAND TITLE TITLE MAINT PEAK
__ __- ----- ----- ------- ------- - -
- -
* *
- -
- -
* *
A* ** * *
A* *
- -
A*
**
SCXED B FOR
CAWCD ------- D
- -
* *
D
- -
*
**
A* ** **
A* *
- -
**
**
LOADS 5-YEAR ALLOCATION CURRENT CRSP/NET TERM OF NATURAL AVG ---------------
GAS LOADS SCBED A SCRED B LOADS CONTRACTS SCHED C . .
D
- I -
* *
- -
- -
*
A*
* **
A* *
* *
- -
* *
**
D
- -
**
D
- -
*
A* *
* ** A* *
**
- -
A* *
* *
- -
*
- -
*
TABLE ONE PAGE 1-2
JUNE 7, 1985
€I I GH EST PEAK DEHAND -------
SCHED B FOR CAWCD -------
LOADS NATURAL GAS
* * A* *Electrical District 7, - - - - Maricopa
- - A - - - - Electrical District 8, Maricopa
A* *
D
Harquahala Power District
** D - - - - **
*f A** Maricopa Water District - - - - McMullen Valley Water ** D - - - - Conservation & Drainage District
Conservation District
Queen Creek Irrigation
- - - - ** * * Ocotillo Water
- - - - - - - - District
Roosevelt Irrigation - - - - * * A** District
Roosevelt Wa t e rConservation District
- - - - A** **
* A* A* Salt River Project - - San Tan Irrigation - - - - - - - - Silverbell Irrigation - - - - - - - - District
& Drainage District
District D * * Tonopah Irrigation D - -
We 1 1 t o n-Mo h a w k A A A * * ** Irrigation & Drainage District
A* *D
* * **
* * ** - - ** * * * *
D - - ** A* * ** - -
A* A* * A* *- - ** - -
A*
- -
** - - * * D **
D - - ** * * * *
TABLE ONE PAGE 1-3
JUNE 7, 1985
ENTITY ........................ City of
city of
City of
Town of
Town of
Mesa
Page
Saf fo rd
Thatcher
Wickenburg
ARS ARS
30 45 SCEED RENEWAL TITLE TITLE MAINT
----- ----- ----- ------- A* A A * A* * * * * - - - - ' - - c -
* - - *- - * *
* - - * *
SCHED B FOR
CAWCD ------- A*
D **
* * *
LOADS 5-YEAR
GAS LOADS NATURAL AVG
------- ------ *
* * **
* * *
* *
CUR RENT CRSP/NET LOADS --------- A* *
TERM OF CONTRACTS ---------
A*
- - * * *
Ak-Chin Indian - - Arizona Electric A*
Arizona Public - -
Citizens Utilities - -
Papago Tribal - -
Community
Power Cooperative
Service Company
Company
Utility Authority
San Carlos Project * Tucson Electric Power - - Company
TABLE ONE PAGE 1-4
JUNE 7, 1985
Agri-Business Council
Arizona Municipal Power Users' Association
Arizona Power Pooling Association
City of Phoenix
City of Tucson
Gila River Indian
of Arizona, Inc.
Community Utility Auth.
Districts Assoc. of Arizona
Irrigation & Electrical
Southern Arizona Water Resources Association
Town of Gilbert
ARS ARS HIGHEST SCRED B LOADS 5-YEAR ALLOCATION CURRENT
30 45 SCHED RENEWAL DEMAND CAWCD GAS LOADS SCHED A SCHED B LOADS CONTRACTS SCHED C CNSP/NET TERM OF FOR NATURAL AVG --------------- TITLE TITLE MAINT PEAK
. I
- - - - A - - A
D - - A - - A
A A 30 YR D
A A A A A
- -
- - - - A A D
* MEMBER OF AMPUA. SEE AMPUA'S COMMENTS.
A = AGREE D = DISAGREE
* * MEMBER OF IEDA. SEE IEDA'S COMMENTS.
S C H E D U L E A A N D S C H E D U L E B
A L L O C A T I O N S
I
* =5====== ====I======== =====c== ======a=======
* * * * * *
TOTALS 377,000 857,989, 000 25.98% 2,276 *
* HOOVER POWER AVAILABLE AT TRANSMISSION DELIVERY POINTS *
* * * SCHEDULE B ENTITIES:
* TAX-EXEMPT: (1)
* NON TAX-EXEMPT: ( 2 )
*
* * * (1) ASSUMED TO
* ( 2 ) ASSUMED TO * * * * * * * * * * * * * *
135,580 1 5 2 , 8 8 7 , 000 12.87% 1 , 1 2 8
45,190 50,959,000 12.87% 1,128
* BE 75%.
BE 25%. * . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
* *
JUNE 7, 1985
TABLE TWO PAGE 2-1
JUNE 7, 1985
Aguila Irrigation
Avra Valley Irrigation & Drainage District
Buckeye Water Conse rva t io n Di st r i c t
Central Arizona Water
District
Conservation District
Chandler Heights Citrus Irrigation District
Irrigation District
Electrical District 1, Pinal
Cortaro-Narana
Electrical District 2,
Electrical District 3,
Electrical District 4,
Electrical District 5,
Electrical District 5,
Electrical District 6,
Pinal
Pinal
Pinal
Maricopa
Pinal
Pi nal
6, 048
1, 5 7 5
2,871
23,732
1,282
6,188
12,793
53, 1 8 0
75,656
31,708
1,987
20,462
34,319
21,681,826
4, 466,000
6,285,729
143,000,000
5, 652,674
18,329,541
39,374,959
193,538,000
271,506,692
134,679,297
4,804, 448
87,623,861
104,940,356
6,048
1,575
2,871
0
894
6, 188
12,793
43,539
64,604
27,071
343
17,673
28,370
21,681,826
4,466,000
6,285,729
0
4,663,682
18,329,541
39,374,959
168,952,736
237,169,388
122, 855,457
611,024
80,512,421
89,770,100
AT TRANSMISSION DELIVERY POINTS ---^---------------------------
23,800
23,000
4, 400
141,000
1, 400
7,800
19,700
37,351
93,200
41,300
2,650
22,000
31,000
75,4501000
119,022, 240
18,586,000
159,000,000
6,700,000
32,848,000
71,960,000
96,584,000
424,120,000
200,800,000
8,700, 000
114,500,000
125,800,000
6,050
1, 580
2,870
0
890
6,190
10,240
28,070
27,820
24,900
340
17,180
1 5 , 8 0 0
12, 227,000
3,179,000
9,809,000
0
3, 042, 000
21,157,000
22, 976, 000
74,482,000
54, 962, 000
70,907,000
1,162,000
51,895, 0 0 0
35,452,000
TABLE TWO PAGE 2-2
Electrical District 7, Maricopa
Maricopa
District
Electrical District 8,
Harquahala Power
Maricopa Water District
McMullen Valley Water Conservation & Drainage District
Ocotillo Water Conservation District
Queen Creek Irrigation
Roosevelt Irrigation
Roosevelt Water
District
District
Conservation District
32,961
6,104
17,222
9,341
3,991
6,165
19,105
20,204
Salt River Project 2, 133,200
San Tan Irrigation 2,636 District
Silverbell Irrigation 1,738 & Drainage District
District Tonopah Irrigation 3,811
W el 1 t on-Mohawk 30,870 Irrigation & Drainage District
85, 506, 503
191576,048
53,870,261
19,633,641
17,770,524
65,052,792
75,638,529
91821,044,400
9,694,245
4,854,693
12,739,839
138,000,540
11,529
32,961
6,104
11,747
9,341
2,879
4,356
14,101
17,955
2, 003,385
1,786
1,738
3, 811
27,663
48,925,825
85, 506,503
19,576,048
39, 909,317
19,633,641
11,566,285
13,158,492
52,293,816
9,424,240,736
71527,765
4,854,693
12,739,839
122, 859, 444
AT TRANSMISSION DELIVERY POINTS
13,100
48,100
25,500
19,400
29,200
2,300
6,800
16,200
20,200
195,957
3,000
1,750
4,300
11,000
58,500,000
131,658,000
60,000,000
116,700,000
53,110,000
9,683,000
22,700,000
65,423,000
326,227,600
12,000,000
5,000,000
16,500,000
26,158,000
kW
11, 530 --------
23,260
6,090
11,370
8,740
2,300
4,350
7,850
12,790
61,870
1,790
680
3,810
7,800
55,705,000
12,340,000
71 861, 000
8,799,000
15,952,000
29,310,000
155,196,000
3,164,000
2,324,000
7,709,000
15,208,000
TABLE TWO PAGE 2-3
JUNE 7, 1985
TOTAL SCHEDULES A AND B ALLOCATIONS (1)
kW kWh ..................... -------- ------------
4,940 5,571,000
1,000 1,128,000
2,000 2,255,000
FIVE-Y EAR AVERAGE LOADS (3) ..........................
ENTITY kW kWh _I_________-_---------- ---------- --------------- City of Mesa 54,520 214,387,400
City of Page 10,233 46,023,948
City of Safford 9,432 37,885,343
Town of Thatcher 2,525 12,882, 893
Town of Wickenburg 3,392 13,653,500 -_-------- --------------- *Subtotal IRS Tax-Exempts 2,655,353 11,759,087,649 ---------- ---------------
Ak-Chin Indian Commu n i ty
power Cooperative
Company
Company
Papago Tribal Utility Authority
San Carlos Project
Tucson Electric Fower
Arizona Electric
Arizona Public Service
Citizens Utilities
Company
*Subtotal IRS Non Tax-Exempts
5,129 19,430,000 1,070 9,079,856 3,900 19,850,000 1,070
3,300
23,930
2,800
2,370
2,470
9,250
1,207,000
3,721,000
26,985,000
3,157,000
2,673,000
2,785,000
10,431,000
277,441 1,611,810,160 241,876 1,468,450,910 47,000 411,720,000
128,000 330,775,000 2,833,680 13,739,658,200 2,833,680 13,739,658,200
104,311 515,643,057 104,311 515,643,057 25,000 38,130,000
4,599 21,676,632 4,599 21,676,632 15,000 50,250,000
TOTAL :
(1) THE AMOUNTS OF SCHEDULE A ALLOCATIONS AND SCHEDULE B ALLOCATIONS ARE SHOWN ON THE ATTACHED TABLE THREE.
( 2 ) THE VALUES SHOWN FOR TOTAL APPLICATIONS ARE EITHER THE SUM OR MAXIMUM OF THE SCHEDULE A AND SCHEDULE B AMOUNTS SPECIFIED IN EACH APPLICATION AS APPROPRIATE.
(3) THE FIVE-YEAR AVERAGE LOADS ARE THE AVERAGE OF THE 1979 THROUGH 1983 KILOWATT (kw) AND KILOWATT-HOUR (kWh) AMOUNTS SPECIFIED IN THE PROFILE DATA ACCOMPANYING EACH APPLICATION.
( 4 ) THE NET LOADS ARE THE FIVE-YEAR AVERAGE LOADS LESS EACH ENTITY'S ENTITLEMENT FROM PARKER-DAVIS AND COLORADO RIVER STORAGE PROJECT (ADJUSTED FOR LOSSES TO TRANSMISSION DELIVERY POINTS).
PAGE 2-4
DETAILED INFORMATION
REGARDING
SCHEDULE A AND SCHEDULE B
ALLOCATIONS
TABLE THREE PAGE 3- 1
JUNE 7, 1985
Aguila Irrigation
Avra Valley Irrigation & Drainage District
Buckeye Water Conservation District
Central Arizona Water
District
Conservation District
Chandler Heights Citrus Irrigation District
Irrigation District
Electrical District 1, Pinal
Electrical District 2,
Electrical District 3,
Electrical District 4,
Electrical District 5,
Electrical District 5,
Electrical District 6,
Co r t a ro -Mar an a
Pinal
Pinal
Pinal
Maricopa
Pinal
Pinal
-- --
3,000
--
900
7,800
--
18,700
10 300
16,700
1,000
14,200
7,700
-- --
12,636,000
--
3,792,000
32, 848,000
--
78,746,000
43,378,000
78,746,000
4,212,000
59,799,000
32,429,000
EXISTING APA CONTRACTS AND
NEW SCHEDULES A AND B ALLOCATIONS AT TRANSMISSION DELIVERY POINTS ................................. ...............................
kW -------- 2,360
610
2,870
--
890
6,190
4,990
18,700
10,300
16,700
340
14,200
7,700
I .
kWh ------------- 8,066, 000
2,085,000
9,809,000
--
3,042,000
21,157,000
17,056,000
63,916, 000
35, 205,000
63,916,000
11162,000
48,535, 000
26,318,000
3,690
970
0
0
0
0
5, 250
9,370
17,520
6, 200
0
2,980
8,100
4, 161, 000
1,094,000
0
0
0
0
5,920,000
10,566,000
19,7571000
6, 991,000
0
3, 360,000
9,134,000
TOTAL kW --------
6, 050
1,580
2,870
0
890
6,190
10 , 240
28,070
27,820
24,900
340
17,180
15, 800
TOTAL kWh ---------_--
12, 227,000
3,179,000
9,809,000
0
31042,000
21,157,000
22,976,000
74,482,000
54, 962,000
70,907, 000
1, 162,000
51,895, 000
35, 452,000
TABLE THREE PAGE 3-2
JUNE 7, 1985
Electrical District 7, 10,100 Maricopa
Mar icopa
District
Electrical District 8, --
Harquahala Power --
Maricopa Water District 8,500
McMullen Valley Water -- Conservation & Drainage District
Ocotillo Water Cons e rva tion Di s t r ic t
Queen Creek Irrigation
Roosevelt Irrigation
District
District
Roosevelt Water Con se rva t ion D i st ric t
Salt River Project
San Tan Irrigation
Silverbell Irrigation & Drainage District
Tonopah Irrigation District
District
Wellton-Mohawk Irrigation & Drainage District
*Subtotal D i s t r i c t s:
2, 300
--
3,100
6,500
37,300
500
--
--
2, 800
42,532,000
--
35,794,000
--
9,683,000
--
13,049,000
27,371,000
157,079,000
2,106,000
EXISTING APA CONTRACTS AND
NEW SCHEDULES A AND B ALLOCATIONS AT TRANSMISSION DELIVERY POINTS ................................. ............................... NEW
SCHEDULE A ALLOCATIONS
10,100
12,870
2,390
8,500
3,650
2,300
1,700
3,100
6,500
37,300
500
680
1, 490
2, 800
34,521,000
43,989,000
8,168,000
29,053,000
12, 475,000
7,861, 000
5,811,000
10,596,000
22,217,000
127,489,000,
1, 709,000
2,324,000
5, 093, 000
9,570,000
1,430
10,390
3,700
2,870
5,090
0
2,650
4,750
6,290
24,570
1,290
--
2,320
5,000
-------- 124,430
. .
1,613,000
11,716,000
4,172,000
3,236,000
5,740,000
0
2,988,000
5,356,000
7,093,000
27,707,000
1,455,000
2,616,000
5,638,000
NEW TOTAL SCHEDULES A.and B
ALLOCATIONS ..................... TOTAL TOTAL
kW kWh -------- ------------ 11,530
23,260
6,090
11,370
81740
2,300
4,350
7,850
12,790
61,870
1,790
680
3,810
7,800
36,134,000
55,705,000
12,340,000
32,289,000
18,215, 000
7, 861,000
8, 799,000
15,952,000
29,310, 000
155,196,000
3,164,000
2,324,000
7,709,000
15,208,000
TABLE THREE PAGE 3-3
JUNE 7, 1985
-- -- City of Mesa
City of Page
City of Safford
Town of Thatcher
-- -- -- -- -- --
Town of Wickenburg -- -- -------- ------------ *Subtotal IRS Tax-Exempts 153,400 645,989,000 -------- ------------
Ak-Chin Indian
Arizona Electric
Community
Power Cooperative
Company
Company
Papago Tribal utility Authority
San ;Carlos Project
Tucson Electric Power
Arizona Public Service
Citizens Utilities
Company
*Subtotal IRS Non Tax-Exempts
TOTAL :
3,300 3,721,000
23,930 26,985, 000
2,800 3,157,000
2,370 21673,000
TABLE THREE PAGE 3-4
JUNE 7, 1985
EXISTING APA CONTRACT AMOUNTS
Aguila Irrigation
Avra Valley Irrigation & Drainage District
Conservation District
District
Buckeye Water
Central Arizona Water Conservation District
Chandler Heights Citrus Irrigation District
Irrigation District
Electrical District 1, Pinal
Cortaro-Marana
Electrical District 2, Pinal
Electrical District 3,
Electrical District 4,
Electrical District 5,
Electrical District 5,
Pinal
Pinal
Maricopa
Pinal
Electrical District 6, Pinal
--
--
3,000
--
900
7, 800
--
18,700
10,300
18,700
1,000
14,200
7,700
-- --
12,636,000
--
3,792,000
32,848,000
--
78,746,000
43,378,000
78,746,000
4,212,000
59,799,000
32,429,000
AT GENERATION -------------
2,450
630
2,980
0
930
6,440
5,190
19,450
10,710
19,450
350
14,770
8,010
8,389,000
2,168,000
10,201,000
0
3,164,000
22,003,000
17,738,000
66,473,000
36,613,000
66,473,000
1,208,000
50,476,000
27,371,000
3,840
1, 010
0
0
0
0
5,460
9,740
18,220
6,450
0
3,100
8,420
4,327,000
1,138,000
0
0
0
0
6,157,000
10,989,000
20,547,000
7,271,000
0
3,494,000
9,499,000
6,290
1,640
2,980
0
930
6, 440
10,650
29,190
28,930
25,900
350
17,870
16,430
12,716,000
3,306,000
10,201,000
0
3,164,000
22,003,000
23,895,000
77,462,000
57,160,000
73,744,000
1,208,000
53,970,000
36,870,000
TABLE THREE PAGE 3-5
JUNE 7, 1985
EXISTING APA CONTRACT AMOUNTS
Electrical District 7, 10,100 Mar i copa
Maricopa
District
Electrical District 8, --
Marquahala Power --
Maricopa Water District 8,500
McMullen Valley Water -- Conservation & Drainage District
Ocotillo Water Conservation District
Queen Creek Irrigation District
Roosevelt Irrigation District
Roo s eve lt Wa t e r Conservation District
Salt River Project
San Tan Irrigation District
Silverbell Irrigation & Drainage District
Tonopah Irrigation District
Wellton-Mohawk Irrigation & Drainage District
*Subtotal Districts:
2,300
--
3,100
6, 500
37,300
500
--
--
2,800
42,532,000
--
35,794,000
--
9,683,000
--
13 I 049 I 000
27,371,000
157,079,000
2,106,000
--
10,500
13,390
2, 490
8,840
3, 800
2, 390
1,770
3, 220
6,760
38 , 790
520
710
1, 550
2, 9 1 0
45,749,000
8, 495, 000
30, 215,000
12,974,000
8, 175,000
6 ,043,000
11,020,000
23,1O6,OOO
5,297, 000
9,953, 000
1,490
10, 810
3, 850
2, 980
5, 290
0
2,760
4,940
6,540
25,550
1,340
--
2,410
5, 200
1, 678,000
12,185,000
4,339,000
3,365,000
5, 970, 000
0
3,108,000
5,570,000
7,377,000
28,815, 000
1,513,000
--
2,721,000
5,864,000
AT GENERATION -------------
11, 990
24,200
6,340
11, 820
9,090
2,390
4,530
8,160
13,300
64,340
1,860
710
3,960
8,110
37,580,000
57,934,000
12, 834,000
33,580,000
18,944,000
16,590, 000
30,483,000
161,404,000
3,290,000
2, 417, 000
8,018,000
TABLE THREE PAGE 3-6
JUNE- 7, 1985
EXISTING APA CONTRACTS AND
NEW SCHEDULES A AND B ALLOCATIONS ................................. AT GENERATION -------------
5,140 5,794,000
1,040 1,173,000
-- -- City of Mesa
City of Page -- -- city of Safford -- --
-- -- Town of Thatcher Town of Wickenburg -- -- -------- *Subtotal IRS Tax-Exempts 153,400 645,989,000 -------- ------------
Ak-Chin Indian Community
Arizona Electric -- --
Arizona Public Service -- --
Citizens Utilities -- --
Power cooperative
Company
Company
Utility Authority -- -- Papago Tribal
Sari Carlos Project -- -- Tucson Electric Power -- -- Company
*Subtotal IRS -------- ------------
Non Tax-Exempts -- -- -------- ------------
-- -- 3,430 3,870,000 3,430 3,870,000
-- -- 24,890 28,064,000 24,890 28,064,000
-- -- 2,910 3,283,000 2,910 3,283,000
2,470 2,780,000
-- -- 2,570 2,896,000
L- -- 9,620 10,848,000
2, 570 2,896,000
9,620 10,848,000