final pil masterplan

29
IN THE HIGH COURT OF KARNATAKA AT BANGALORE (ORIGINAL JURISDICTION) WRIT PETITION NO.__________ / 2008 (PIL) BETWEEN: 1. Citizens’ Action Forum #31/1, 1 st Floor M.K. Puttalingaiah Road Padmanabhanagara Bangalore 560 070 Represented by its Secretary Lt. Col Mathew Thomas (Retd.) 2. Lt. Col. Mathew Thomas (Retd) s/o Late Shri T P John Age: 70 years Secretary Citizens’ Action Forum #30/1, 1 st Floor M. K. Puttalingaiah Road Padmanabhanagara Bangalore 560 070 3. Sadashivanagar Residents Welfare Association No. 457, 11 th Main Road, R.M.V.Extension, Sadashivanagar, Bangalore 560 080. Represented by its Honorary Secretary Mr. B.K.Jagadishchandra, IFS (Retd.) 4. Mr. B.K.Jagadischandra Secretary, SRWA Age 69 years S/o Late Shri. B.N. Kappanna 438, 11 th Main Road, R.M.V.Extension Sadashivanagar, Bangalore 560 080 5. Maj. Gen. M.K. Paul (Retd.) AVSM, s/o Late Mr. Nripendra Kishore Paul. Aged 74 years, Past President, Defence Colony Residents Association, “Devalaya”, 3 rd Main Road, Defence Colony, Bangalore 560 038. 6. Mr. Xerxes Desai, s/o Mr. Sapue Desai, Aged 71 years, Retd. Chief Executive, Titan Group of Companies and President, Defence Colony Residents Association, 41, 4 th Main, 3 rd Cross, Defence Colony, Indiranagar, Bangalore 560 038 1

Upload: tarlesubba

Post on 11-Apr-2015

1.450 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Final PIL Masterplan

IN THE HIGH COURT OF KARNATAKA AT BANGALORE

(ORIGINAL JURISDICTION)

WRIT PETITION NO.__________ / 2008 (PIL)

BETWEEN: 1. Citizens’ Action Forum #31/1, 1st Floor M.K. Puttalingaiah Road

Padmanabhanagara Bangalore 560 070 Represented by its Secretary Lt. Col Mathew Thomas (Retd.)

2. Lt. Col. Mathew Thomas (Retd)

s/o Late Shri T P John Age: 70 years

Secretary Citizens’ Action Forum #30/1, 1st Floor

M. K. Puttalingaiah Road Padmanabhanagara Bangalore 560 070

3. Sadashivanagar Residents Welfare Association No. 457, 11th Main Road, R.M.V.Extension, Sadashivanagar, Bangalore 560 080. Represented by its Honorary Secretary Mr. B.K.Jagadishchandra, IFS (Retd.)

4. Mr. B.K.Jagadischandra Secretary, SRWA Age 69 years S/o Late Shri. B.N. Kappanna 438, 11th Main Road, R.M.V.Extension Sadashivanagar, Bangalore 560 080 5. Maj. Gen. M.K. Paul (Retd.) AVSM,

s/o Late Mr. Nripendra Kishore Paul. Aged 74 years, Past President, Defence Colony Residents Association, “Devalaya”, 3rd Main Road, Defence Colony, Bangalore 560 038.

6. Mr. Xerxes Desai,

s/o Mr. Sapue Desai, Aged 71 years, Retd. Chief Executive, Titan Group of Companies and President, Defence Colony Residents Association, 41, 4th Main, 3rd Cross, Defence Colony, Indiranagar, Bangalore 560 038

1

Page 2: Final PIL Masterplan

7. Air Vice-Marshal (Retd.) S. Krishnaswamy AVSM, s/o Late Mr. K.R. Srinivasan, Aged 77 years, Retired Senior IAF Officer, A1, “Vijayasrinivas”, 218, 3rd Main, Defence Colony, Indiranagar, Bangalore 560 038.

8. Mr. J.R. Kapur,

s/o Mr. N.D. Kapur, Aged 80 years, Former General Manager, HAL, 2973, 5th Cross, 13th Main, HAL 2nd Stage, Bangalore 560 008.

9. Gp. Capt. K. Bhaskaran,

S/o Late Mr. Kunhambu, Aged 76 years, Retired Senior Air Force Officer, Former President, HAL 2nd Stage Civic Amenities and Cultural Association, 3019, 12-B Main, HAL 2nd Stage, Bangalore 560 008.

10. Mr. S. Shyam Sundar, IFS (Retd.),

S/o Mr. S. Venkata Rao, Aged 76 years, Former Principal Chief Conservator of Forests, Govt. of Karnataka, and former President, HAL 2nd Stage Civic Amenities and Cultural Association, 2989/D, 12th Main, HAL 2nd Stage, Bangalore 560 008.

11. Mr. P.P.R. Nair,

S/o late Mr. K.K.R. Panicker, Aged 72 years, Former Special Secretary, Ministry of Home Affairs, Govt. of India, 3367/B, 13th Main Road, HAL 2nd Stage, Bangalore 560 008.

12. Mr. S.N.S. Murthy IPS (Retd.),

s/o Late Mr. S. Narayana Rao, Aged 72 years, Former DG & IGP, Karnataka State and Former President, HAL 2nd Stage Civic Amenities and Cultural Association, No. 3367/C, 13th Main Road, HAL 2nd Stage, Bangalore 560 008.

13. Dr. B.R. Pai,

s/o Late Mr. Rama Bhaskar Pai, Aged 63 years, Former Director, National Aerospace Laboratories, 1078, 12th Main Road, HAL 2nd Stage, Bangalore 560 008.

2

Page 3: Final PIL Masterplan

14. Dr. R. Balasubramaniam, s/o Late Dr. K. Ramakrishna Iyer, Aged 64 years, Director and Scientific Adviser, National Aerospace Laboratories (Retd.) 808, “Mayurapriya”, 7th Main, 1st Cross, HAL 2nd Stage, Bangalore 560 008.

15. Mr. Kumar Ranganathan,

s/o Cdr. T.V. Ranganathan, Aged 40 years, Senior Manager, Intel Corpn., 15, Defence Colony, Indiranagar, Bangalore 560 038.

16. Mr. S. Janardhan,

s/o Late Mr. Subramanian Seshadri, aged 75 Years, Formerly Scientist at National Aerospace Laboratories,Bangalore (1960 to 1991) and Chief Moderator for National Computing Centre,UK (1991 - 1999) 1196, 13th Main Road, HAL 2nd Stage, Bangalore 560 008.

17. Mr. Ravindranath Guru,

s/o late Mr. Maheshchander Guru, Age: 64 years, 593, DUNDUBHI. 24th Cross, BSK II Stage, Bangalore – 560 070 ………. PETITIONERS

AND: 1. State of Karnataka Department of Urban Development M.S. Building Bangalore – 560 001 Represented by its Secretary 2. Bangalore Development Authority T. Chowdaiah Road Kumara Park West Bangalore – 560 020 Represented by its Commissioner 3. Bangalore Metropolitan Regional Development Authority No.1, Ali Askar Road

Bangalore 560 052 Represented by its Commissioner ....… RESPONDENTS

MEMORANDUM OF WRIT PETITION UNDER ARTICLES 226 & 227 OF THE CONSTITUTION OF INDIA

3

Page 4: Final PIL Masterplan

The Petitioners above named beg to submit as follows –

1. The first Petitioner is a registered society having its office at #31/1, 1st Floor,

M.K. Puttalingaiah Road, Padmanabhanagara, Bangalore. All the members of

the Petitioner are public spirited citizens and the Petitioner’s main objectives,

inte ralia, include working towards participation of the Citizens’ in

Governance, proper disclosure norms for the Government and having absolute

transparency and accountability in Urban Governance with primary focus on

Civic issues. More than 20 resident welfare associations spread all over the

city, viz., Koramangala Initiative, Kumara Park West Resident’s Welfare

Association, Banashankari 1st Stage Resident’s Welfare Association etc. along

with several citizens’ federations are members of the Petitioner. A copy of the

Certificate of Registration of the Petitioner society, the Memorandum and

Articles of Association and Rules and regulations of the Petitioner and the

names of its members are produced herewith and collectively marked

ANNEXURE ‘A’. The second Petitioner is the Secretary of the first Petitioner

Society and a citizen of India.

2. The third Petitioner is a registered society having its office at # No. 457, 11th

Main Road, R.M.V.Extension, Sadashivanagar, Bangalore 560 080.. All the

members of the Petitioner are public spirited citizens. The third Petitioner has

been for last 18 years rendering yeoman services to the Sadashivanagar

community. It has been instrumental in developing and maintaining the Low

Level Park in Sadashivanagar which is an outstanding example of public

private partnership. Rupees 70.00(seventy) lakhs has been spent in the park for

providing a jogging and walking track, children play equipment and water

fountain and water cascade. It is the only “Pay and Use” Park in Bangalore.

The entire amount of Rs.70.00 lacs has been raised from the residents of

Sadashivanagar and donations from benefactors. Further, Sadashivanagar

4

Page 5: Final PIL Masterplan

Association has played a prominent role in motivating and influencing civic

agencies like BBMP, BWSSB, BESCOM, traffic police and other agencies to

yearly implement projects and programmes for improving the civic amenities

in the area and for ensuring efficient traffic regulations and management. A

copy of the Certificate of Registration of the Petitioner society, the

Memorandum and Articles of Association and Rules and regulations of the

Petitioner and the names of its members are produced herewith and

collectively marked ANNEXURE ‘B’. The fourth Petitioner is the Honorary

Secretary of the fourth Petitioner Society and a citizen of India.

3. Petitioners 5 to 17 are distinguished citizens from various walks of life, and are

public spirited individuals who have involved themselves in matters of local

welfare.

4. Section 25 of the Karnataka Town and Country Planning Act, 1961

(hereinafter referred to as “the Act”) stipulates revision of Comprehensive

Development Plan at least once in 10 years from the date on which the last

Comprehensive Development Plan has come into force. Accordingly, the

existing Master Plan for the Bangalore Metropolitan Area namely Revised

Comprehensive Development Plan 1995 approved vide Govt. Order dated

05.01.1995 was required to be revised since the currency of the Master Plan

was due to expire.

5. The second Respondent - BDA, purportedly acting as the designated Planning

Authority, formulated a Revised Master Plan 2015, which was approved and

confirmed by the first Respondent vide its order No. UDD 540 BEM AA SE

2004, Bangalore dated 25.06.2007. The Petitioners are filing this petition in

public interest to redress the approval granted by the first Respondent to the

Revised Master Plan 2015 (hereinafter referred to as “the RMP”) for the

5

Page 6: Final PIL Masterplan

Bangalore Metropolitan Region (hereinafter referred to as “the BMR”)

formulated by the second Respondent, particularly on account of the second

Respondent over-reaching its powers in formulating the RMP, the non-

exercise of powers by the third Respondent and non-consideration of citizens’

feedback and expert opinion reflected in the PSS Thomas Committee Report

that has directly affected the rights of the citizens and residents of Bangalore,

as shall be detailed hereinafter.

STATUTORY BACKGROUND

6. For the purposes of this petition, it is relevant to trace the circumstances under

which the third Respondent came to be constituted and also peruse the hitherto

statutory situation prior to the constitution of the third Respondent as the prime

Authority for the planning, co-ordinating and supervising the proper and

orderly development of the area within the Bangalore Metropolitan Region.

Urban planning in Bangalore is largely governed by the Act. The Act aims to

provide for the regulation of land use development and for the making and

execution of town planning schemes in the State of Karnataka. In order to

ensure that town-planning schemes are made in a proper manner and their

execution is made effective, the Act provides for declaration of “local planning

areas” and a “local authority” to prepare a development plan for the entire local

planning area falling within its jurisdiction. The preparation of the Master Plan

is vested with the Planning Authority constituted under Section 4 of the Act.

The Bangalore Development Authority (hereinafter referred to as “BDA”) is

the Planning Authority for the local planning area comprising the city of

Bangalore. However this has undergone a change with the enactment of the

Bangalore Metropolitan Region Development Authority Act, 1985 (hereinafter

“the BMRDA Act”).

6

Page 7: Final PIL Masterplan

7. Given that Bangalore is the capital city of Karnataka and over the past two

decades has emerged as the hub of information technology, biotechnology,

commerce and other areas, great concern and interest has been shown by the

State Government for its planned development. As the State Government felt

that there was no proper coordination among the local bodies like the BDA, the

Bangalore Water Supply and Sewerage Board (hereinafter referred to as

“BWSSB”), the Karnataka Electricity Board (hereinafter referred to as

“KEB”), and the Corporation etc. within the Bangalore Metropolitan Area, it

decided to set up the Bangalore Metropolitan Region Development Authority

under a separate legislation.

8. The BMRDA Act, 1985 was, inter alia, enacted in order to constitute an

Authority to co-ordinate the activities of the local bodies like BDA, BWSSB,

KEB, Karnataka State Road Transport Corporation (hereinafter referred to as

“KSRTC”), Karnataka Slum Clearance Board, Bangalore City Corporation

(hereinafter referred to as “BMP”), etc., in the Bangalore Metropolitan Area,

especially in view of the growing problems of unplanned development,

housing etc. The preamble to the Act itself is categorical in this regard and

reads as under –

“An act to provide for the establishment of an authority for the

purpose of planning, coordinating and supervising the proper and

orderly development of the area within the Bangalore

Metropolitan Region and to provide for matters connected

therewith.

Whereas, it is expedient to provide for the establishment of an

authority for the purposes of planning, co-ordinating and

supervising the proper and orderly development of the area within

the Bangalore Metropolitan Region and to provide for matters

connected therein;”

[Emphasis supplied]

7

Page 8: Final PIL Masterplan

9. Thus, the third Respondent BMRDA came to be constituted under the

BMRDA Act and is the Authority within the meaning of Section 2(a) thereof.

For the purposes of the BMRDA Act, the terms ‘Bangalore Metropolitan

Region’ and ‘Local authority’ are defined in section 2(c) and 2(j) and read as

under:

“2(c) “Bangalore Metropolitan Region” means the area

comprising the Bangalore District and Malur Taluk of Kolar

District and such other areas as the State Government may, from

time to time, by notification, specify;

“2(j) “local authority” means the City of Bangalore municipal

Corporation, the Bangalore Development Authority, the Bangalore

Water Supply and Sewerage Board, a Zilla Parishad, a Municipal

Council, a Sanitary Board, the Karnataka Electricity Board, the

Karnataka Road Transport Corporation, a Zilla Parishad, a

Municipal Council, a Sanitary Board, or a Mandal Panchayat

constituted or continued under any law for the time being in

force;”

[Emphasis Supplied]

10. The functions to be discharged by the third Respondent and the powers vested

in it are enumerated in Section 9 of the BMRDA which reads as under:

“9. Powers and functions of the Authority:- (1) Subject to the

provisions of this Act and the rules made thereunder the functions

of the Authority shall be-

(i) to carry out a survey of the Bangalore Metropolitan Region and

prepare reports on the surveys so carried out;

(ii) to prepare a structure plan for the development of the

Bangalore Metropolitan Region;

8

Page 9: Final PIL Masterplan

(iii) to cause to be carried out such works as are contemplated in

the structure plan

(iv) to formulate as many schemes as are necessary for

implementing the structure plan of the Bangalore Metropolitan

Region;

(v) to secure and co-ordinate execution of the town planning

scheme and the development of the Bangalore Metropolitan

Region in accordance with the said schemes;

(vi) to raise finance for any project or scheme for the development

of the Bangalore Metropolitan Region and to extend assistance to

the local authorities in the Region for the execution of such project

or scheme

(vii) to do such other acts and things as may be entrusted by the

Government or as may be necessary for, or incidental or

conducive to, and matters which are necessary for furtherance of

the objects for which the Authority is constituted;

(viii) to entrust to any local authority the work of execution of any

development plan or town planning scheme;

(ix) to Co-ordinate the activities of the Bangalore Development

Authority, the corporation of the city of Bangalore, the Bangalore

Water supply and Sewerage Board, the Karnataka Slum

Clearance Board, the Karnataka Electricity Board, the Karnataka

Industrial Areas Development Board, the Karnataka State Road

Transport Corporation and such other bodies as are connected

with development activities in the Bangalore Metropolitan

Region.”

[Emphasis supplied]

11. A perusal of the powers and functions conferred under Section 9 of the

BMRDA Act makes it clear that the range and sweep of the powers are such

that the BMRDA is vested with the power to formulate as many schemes as are

necessary for implementing the structure plan for the BMR and to do all such

9

Page 10: Final PIL Masterplan

acts that may be entrusted by the Government or which may be necessary or

incidental to further the object for which the authority is constituted. Section 9

(ii) empowers the third Respondent to prepare a structure plan for the

development of the Bangalore Metropolitan Region and (iii) to cause to be

carried out such works as are contemplated in the structure plan”. The Master

Plan is the next and consequential step after a structural plan is prepared and it

comes within the sweep of Section 9(iv) and 9(vii) which provides for

formulating schemes necessary for implementing the structure plan for the

region and which also authorizes the Authority to do such acts as are necessary

or incidental or conducive to matters necessary for furthering the objects for

which the Authorities are constituted. Section 9 (viii) empowers the Authority

to entrust the execution of any developmental plan or scheme to any local

authority.

12. Further, section 10 of the BMRDA Act lays down that no person or Authority

shall undertake any development in the Region which may be specified by

issuing a notification in the Gazette, without its prior permission. Section 18 of

the BMRDA Act enjoins the Authority with a power to issue directions. It

reads as under:

“18. Directions by the Authority. (1) The Authority may, in order

to carry out the development plans and schemes formulated under

Section 9 or any town planning scheme may issue direction to the

Bangalore Development Authority, Bangalore Water Supply and

Sewerage Board, Karnataka Electricity Board and such other

bodies as are connected with developmental activities in the

Bangalore Metropolitan Region. The directions issued by the

Authority shall prevail over any directions issued by the Bangalore

Development Authority under Section 53 of the Bangalore

Development Authority Act, 1976 (Karnataka Act 12 of 1976).

10

Page 11: Final PIL Masterplan

(2) Notwithstanding anything contained in any other law for the

time being in force, every such direction shall be complied with by

the body to whom it is issued On failure, it shall be competent for

the Authority to take necessary action to carry out the directions

issued under Sub-section (1) and recover expenses, if any, incurred

thereof from the body concerned.

(3) Any dispute which arises between the Authority and the Boards

or other bodies referred to in Sub-section (1) in respect of the

directions issued to them shall be determined by the State

Government whose decision shall be final.”

[emphasis supplied]

13. As per Section 28 of the BMRDA Act, the provisions of Act shall override

other laws and reads as under:

“28. Act to override other laws.- the provisions of this Act shall

have effect notwithstanding anything inconsistent therewith

contained in any other law for the time being in force.”

14. Thus, as per the provisions of the BMRDA Act, it is the primary responsibility

of the third Respondent to bring out a comprehensive development plan as also

to carry out these works, including the supervision and co-ordination of any

development activities carried out by the local authorities including those

undertaken by the second Respondent. It is the paramount task of the third

Respondent to not only bring out requisite schemes and plans of development

for the BMR, but also actively keep the local authorities, viz., the second

Respondent in check and ensure that any and all development activity taken in

respect of the BMR is in accordance with the provisions of the BMRDA Act,

and the rules framed therein and is in line with the object of planned

development. The powers and functions of the BMRDA, examined in the

background of the object for which the Authority was constituted have

11

Page 12: Final PIL Masterplan

overriding effect over the provisions of Section 9 of the Town and Country

Planning Act, wherein the local planning authorities established for the areas

falling within the metropolitan Region are conferred with the powers and

duties to prepare the Mater Plan. Since the enactment of the BMRDA Act, the

special powers for the formulation of a development plan/schemes, if any

granted to the local planning authority- the second Respondent in case of the

BMR, is subject to the powers and sanction of the third authority.

15. In this regard, the Act has been suitably amended with the introduction of

Section 81-C, which reads as under:

“81-C. outline development plan and comprehensive

development plan of Bangalore Metropolitan Region.—

Notwithstanding anything in this Act, the Planning Authorities

within the Bangalore Metropolitan Region as defined in the

Bangalore Metropolitan Region Development Authority Act, 1985

shall submit the outline development plans and comprehensive

development plans under sections 9 to the State Government

through the Bangalore Metropolitan Region Development

Authority for approval and the said Authority shall exercise the

powers and discharge the functions of the Director of Town

Planning in respect of such outline development plans or

comprehensive development plans. The provisions of sections 9

and 19 shall mutatis mutandis be applicable for the purpose of this

section.”

Thus, any development plan or scheme formulated by the second Respondent

has to be approved by the third Respondent and must be in consonance with

the directions issued by the third Respondent.

12

Page 13: Final PIL Masterplan

FACTS

16. The second Respondent purportedly in its capacity as the Designated Planning

Authority undertook the task of revising the Comprehensive Development Plan

1995 and submitted a draft Master Plan to the State Government under letter

dated 18.12.2004, which the Government then accorded approval to publish

the same under Government Order dated 10.06.2005. The said draft Master

Plan was prepared by the second Respondent enlisting the help of a French

consultancy firm, M/s. SCE. The Draft Master Plan was published vide

Notification No.BDA/TPM/RCDP/1137/2005-06 dated 22.06.2005, inviting

objections/suggestions from the general public. Despite the short response

period given to the citizens for their feedback, the second Respondent received

approximately around 7,200 objections. Subsequently, an officially constituted

Review Committee of experts, headed by Mr. P.S.S. Thomas, I.A.S (Retd.),

Advisor, Planning Commission was appointed vide Government order dated

21.06.2005, to interact with the public and also to give their own

recommendations. The Review Committee, interacted with several Residents’

Welfare Associations and NGOs, studied in great detail the implications of the

draft master plan and submitted its recommendations. A copy of the said

Committee Report is produced herewith marked ANNEXURE ‘C’

17. The Committee’s report had several reservations about the Draft Master Plan

and disagreed with proposals of the Draft Master Plan, inter alia, regarding the

proposed zonal regulations, introduction of mixed residential areas under the

guise of development of commercial space, designation of main corridors and

even main roads in residential areas as commercial axes, mutation corridors in

mainly residential areas, Zoning of Transformation Zones etc. leading to

automatic regularization of violations etc. Much to the surprise of the citizens

of Bangalore, most of these recommendations were not considered and

13

Page 14: Final PIL Masterplan

blatantly overlooked by the second Respondent. An extract of the Committee’s

recommendations compared with the implementation of these

recommendations in the Revised Master Plan 2015 is produced herewith

marked ANNEXURE ‘D’.

18. In an exercise that turned out to be a mere eye-wash, in that the said

recommendations are largely ignored. The third Respondent vide its letter

dated 07.02.2007 sent the Draft Master Plan back to the second Respondent

rejecting some proposals with its suggestions and recommendations. A copy of

the said letter is produced herewith marked ANNEXURE ‘E’. This in turn

resulted in the constitution of a Core Group, vide Government order dated

09.03.2007, under the chairmanship of Additional Chief Secretary and

Principal Secretary, Energy Department and Administrator, Bruhath Bangalore

Mahanagara Palike to furnish recommendations to the Government. A copy of

order is produced herewith marked ANNEXURE ‘F’. The Core Group made

some suggestions have been ignored, which is apparent from the Vision

Document and Zonal Regulations.

19. Vide letter dated 22.06.2007 issued by the Principal Secretary to the State

Government to the BDA appears to have sought changes to the Revised Master

Plan. Without even considering the contents of the letter issued, the second

Respondent replied to the said letter on 23.06.2007, the very next day with the

false assurance that the changes sought were incorporated. Subsequently, the

first Respondent approved the Revised Master Plan despite the fact that the

second Respondent had not taken into consideration the ground realities of the

city, the recommendations of the Committee, the recommendations of the third

Respondent, and the genuine grievances and reactions of the citizens of

14

Page 15: Final PIL Masterplan

Bangalore. The original order approving the Revised Master Plan, 2015 is

produced herewith marked ANNEXURE ‘G’.

20. The Petitioners submit that the first Respondent has failed its citizens by

illegally directing the third Respondent to approve the master plan when the

second Respondent has failed to incorporate the suggestions and

recommendations of the expert committee, the third Respondent, the Advisory

Committee and the citizens. Though the preparation of the Master Plan is

vested with the Planning Authority – the second Respondent in case of

Bangalore, constituted under section 4 of the Karnataka Town and Country

Planning Act, 1961, in so far as the developmental activities coming within the

jurisdiction of BMRDA, it is the third Respondent as the Authority which is

competent to exercise these powers. The third Respondent has abdicated its

functions and duties under the BMRDA Act, frustrating the very object of its

enactment. The second Respondent is outside its powers in formulating a

revised master plan for the BMR, when there is a specific authority constituted

for this purpose. In any case, the second Respondent can only carry out the

instructions handed to it by the third Respondent.

21. The Petitioner submits that the Revised Master Plan, 2015 has been formulated

in a mechanical manner with non application of mind, apart from the fact the

said plan violates the letter and spirit of the Act.

22. The Revised Master Plan, 2015 has been formulated by the second Respondent

without affording the citizens of Bangalore an opportunity to appraise the Plan

and is violative of Article 14 of the Constitution. The second Respondent has

not taken into consideration the needs of the citizens and is not in the best

interests of the citizens of Bangalore. It is the resident citizen whose interests

should always be at the centre of any development plan. The revised master

15

Page 16: Final PIL Masterplan

plan has ignored the interests of the resident citizen however is an

acknowledgement of all the violations that have taken place in the past several

years and merely attempts to legalise and further perpetuate the chaos created

by land use violations in residential areas, valley areas and green belt areas.

Worse, it has added complicated classifications like Mutation Corridors,

Transformation / Development Area, Commercial Axes running right through

predominantly residential areas, High tech. Zones, and so on. If this did not

create sufficient complication, the plan also envisages further Ancillary

activities in residential areas, which are nothing short of free for all

commercial activities, not necessarily adding to the quality of the resident’s

life.

23. The Expert Committee constituted by the Government of Karnataka to

appraise the Revised Mater Plan, 2015 has taken objection to several proposals

in the development plan. The third Respondent has also raised several concerns

and has even rejected certain proposals about the Plan. The first Petitioner has

filed objections in response to the second Respondent inviting objections in

respect of the Revised Master Plan, 2015. A copy of the objections filed by the

Petitioner is produced herewith marked ANNEXURE ‘H’. The Petitioner

society had even organized a panel discussion on the ‘Revised Master plan-

2015 for Bangalore & Building Bye-Law & Land Use Zoning Violations

Regularization Act’ on 19.09.2007 at the Institute of Agricultural

Technologists, Bangalore providing a common platform for the Government,

the representatives of the Expert Committee, the BDA and other municipal

bodies and other leaders to interact with the citizens of Bangalore and arrive at

practical solutions in this regard. A copy of the invitation to this panel

discussion and other such representations / programmes etc. are

compendiously produced herewith marked ANNEXURE ‘J’. Sadly, though

there was an overwhelming participation of citizens and eminent panelists,

16

Page 17: Final PIL Masterplan

representatives of the Respondents failed to utilize this opportunity and did not

attend the discussion despite having tentatively agreed to attend the same. The

first Petitioner has made a detailed representation dated 5.12.2007 to the

Governor of Karnataka supported by over 2,000 signatures of residents of

Bangalore and public-spirited associations, and copy thereof is produced

herewith marked ANNEXURE ‘K’. The Petitioners, in order avoid burdening

the record of this Hon’ble Court are not filing the said documents and

undertakes to produce copies of the said documents as and when directed by

this Hon’ble Court. The Petitioner has also been constrained to make

applications under the Right to Information Act to obtain relevant information /

documents before approaching this Hon’ble Court and a copy thereof is

produced herewith marked ANNEXURE ‘L’.

24. Further, a perusal of the Minutes of the Cabinet Meeting approving the Plan,

produced herewith marked ANNEXURE ‘M’ would disclose that the second

Respondent has paid no heed to the objections raised by the Expert Committee,

the third Respondent, Petitioner or any other aggrieved citizens and has

mechanically forwarded the Revised Master Plan to the first Respondent for

approval. As such, the second Respondent has hopelessly failed in its role as a

planning authority and has acted in violation of the principles of natural justice

as well as in violation of the law. The State Government has also mechanically

granted approval to the Plan without considering interests of the citizens.

25. A comparative table between the BMRDA / Thomas Committee

recommendations and the actual Plan, disclosing the glaring and inherent

deficiencies and illegalities in the Revised Master Plan, is produced herewith

marked ANNEXURE N. The Petitioner craves leave to rely upon the contents

of the Annexures at the time of hearing.

17

Page 18: Final PIL Masterplan

26. There are glaring differences between the Draft Master Plan which was

published by the second Respondent inviting public opinion and expert

opinion and the Revised Master Plan which it has finally approved. Drastic

changes have been brought about in the zoning regulations without assigning

any rationale and which were not originally contemplated in the Draft Master

Plan, and the same reeks of arbitrariness. Further, the very exercise of

publicizing the draft plan and inviting expert and public opinion was redundant

and mere eyewash, if the third Respondent did not intend to heed any of the

suggestions. A table enumerating the changes introduced by the BDA to the

Revised Master Plan, which were not proposed in the Draft Master Plan and

are otherwise squarely opposed to the objections of the citizens as well the

recommendations of the Committee is produced herein as ANNEXURE ‘P’.

27. Vide its order dated 11.02.1988, the Government of Karnataka had accepted

the recommendations of the Lakshman Rau Committee constituted for the

preservation, restoration or otherwise of existing tanks in the Metropolitan area

of Bangalore City, clearly stipulating that any tank bed- used or unused,

drainage areas and natural valleys must not be diverted for use as housing

layouts. Thus, valleys, natural drains, tank bed areas and disused tank beds

have been declared protected areas in light of environmental concerns in line

with the said expert committee report. A copy of the Gazette Notification of

the order along with the Expert committee report is produced herewith marked

ANNEXURE ‘Q’. The Draft Master Plan had in fact demarcated such areas as

‘Protected Land’. However, in the Final Revised Master Plan, these spaces

have been depicted as ‘built up’ and demarcated for ‘residential’ use in total

disregard to the above said order. Instances of these violations are produced

herewith marked ANNEXURE ‘R’.

28. The original Master Plan is produced herewith marked ANNEXURE ‘S’.

18

Page 19: Final PIL Masterplan

29. The Petitioners submit that the Hon’ble Supreme Court of India has repeatedly

held that planned development, protection of the environment and safe and

healthy atmosphere for comfortable living cannot be achieved unless the

Authorities invested with the powers act with vision for the future and take

preventive actions curbing unplanned and indiscriminate growth of the region

which has the potential danger of causing great health hazards to the citizens in

the region.

30. Further, large scale conversions and illegal usage of land use violate the Right

to Life enshrined in Article 21 of the Constitution of India, inter alia, by

causing pollution, threat to ecology and environment, stress and public

inconvenience and lack of peace and comfort. The Revised Master Plan 2015,

seeks to give credence to these very illegal actions through its proposal of

Mixed Zones, commercial axes, mutation corridors etc. Further, the readiness

with which the third respondent has sought to introduce mixed land use in pure

residential areas, is merely an attempt to disguise its inability to check the

illegal change in land use, rampant in the city.

31. The Petitioners submit that this Hon’ble Court could take judicial notice of the

violation of the rights of the citizens of Bangalore including the right to live in

a healthy and well planned environment, resulting from gross omissions and

commissions of the BDA, the BMRDA and the State Government.

32. In the circumstances, the Petitioners submit that they have no other alternative

and efficacious remedy except to approach this Hon’ble Court in exercise of its

extraordinary jurisdiction under Articles 226 and 227 of Constitution of India.

The Petitioners have not preferred any other writ petition on the said cause of

action and there are no legal proceedings pending in connection therewith.

19

Page 20: Final PIL Masterplan

Therefore, the Petitioners beg to prefer this Memorandum of Writ Petition on

the following amongst other grounds –

G R O U N D S

33. The Revised Master Plan, 2015 formulated by the second Respondent

(hereinafter referred to as “the said Plan”) and the approval granted by the first

Respondent - State Govt. (hereinafter referred to as “the said approval”) are

illegal, without jurisdiction, arbitrary, mala fide, unconstitutional and ultra

vires.

34. Despite the express language of Sections 9, 10, 18 of the BMRDA Act and

Section 81-C of the Town & Country Planning Act that the ultimate authority

in respect of development plans and schemes for the Bangalore Metropolitan

Region shall be the third Respondent, the second Respondent has usurped the

power and has exercised unbridled power in formulating the Revised Master

Plan, 2015. As such, the said Plan is without jurisdiction and ultra vires.

35. The approval of BMRDA has not been obtained for the said Plan and as such

the said Plan is illegal and unsustainable.

36. The said Plan is formulated and the said approval granted is in gross violation

of Section 81C of the Act, particularly as the approval is not sought through

the BMRDA, which is mandatory. The very purpose of the BMRDA Act

stands frustrated, with the second respondent overreaching its powers by

failing to take into consideration the suggestions of the third respondent.

37. The third Respondent is guilty of dereliction of its duty under the BMRDA Act

and has abdicated its powers and functions.

20

Page 21: Final PIL Masterplan

38. The said Plan bears no nexus with the objects sought to be achieved by the

Town & Country Planning Act and BMRDA Act, and is hence illegal and

violative of Article 14 of the Constitution. In this regard, the particular

objectives of the Act providing full civic amenities and prevention of

speculation and profiteering in land are undermined by the said Plan.

39. The second Respondent has failed to consider and incorporate the

recommendations of the PSS Thomas Committee and general citizen input

received in response to the Draft Master Plan. Hence, the entire exercise is

unscientific and haphazard.

40. The second Respondent has rejected the recommendations of the third

Respondent with regard to the said Plan without assigning any reasons and has

over-reached its powers.

41. The first Petitioner has made several representations to the authorities that have

not been heeded despite the legal obligation on the authorities to consider and

respond to the same and the right of the petitioner on behalf of the citizens of

Bangalore to seek appropriate intervention in matters of public concern.

42. The second Respondent is guilty of non-consideration of relevant materials and

thus the Plan suffers form lack of application of mind.

43. The said Plan has introduced a new category “T” denoting transportation

facility that can be principal usage in a residential area. However, the same was

not present in the Draft Master Plan and thus no input from the Expert

committee, the BMRDA or the general public is available in this aspect and

thus the said Plan suffers from arbitrariness.

21

Page 22: Final PIL Masterplan

44. Even otherwise, the second Respondent has failed to comply with the

requirements of Section 81-C of the Town & Country Planning Act and no

valid approval of the BMRDA is forthcoming.

45. The second Respondent has failed to consider the public interest element

involved and the process mandated by Law.

46. With the deletion of section 19 of the Act, the first and second Respondents

have no right to undertake the formulation of the Plan without the approval of

the third Respondent BMRDA. The said Plan hence defeats the very purpose

of the constitution of the BMRDA and the amendment to the Act by the

deletion of section 19.

47. BMRDA has not acted as the Director, Town Planning as required by section

9, 81C of the Act, inter alia, and hence, the entire exercise is illegal and

opposed to statute.

48. The said Plan and approval are formulated / granted without considering the

various objections filed to the proposed plan, and hence violative of the

Principles of Natural Justice.

49. The Petitioners have reason to suspect that the said Plan and approval are a

result of pressure brought by various real estate ‘lobbies’ to circumvent the

checks and balances provided by zoning and to facilitate rampant

commercialization and are hence vitiated by mala fides.

22

Page 23: Final PIL Masterplan

50. The second Respondent has acted in a mechanical and arbitrary fashion and in

total violation of all the mandates prescribed under the BMRDA Act and the

Town & Country Planning Act.

51. The second Respondent has failed to apply its mind to the requirements of the

city and its residents and has acted in a high-handed fashion.

52. The action of the second Respondent, the complicity of the first and third

Respondents in granting approval to the Revised master plan, despite the

Master Plan being illegal, for the above said reasons, tantamount to fraud on

the statute and is vitiated with mala fides, both legal and factual.

53. The high-handedness of the second Respondent, the inaction of the first and

third Respondents to refuse approval to the Master Plan have affected the

fundamental rights of the citizens of Bangalore enshrined in Articles 14 and 21

of the Constitution of India.

54. Article 21 grants all citizens the right to live in a clean, orderly and healthy

environment, which stands affected by the impugned Plan and approval.

55. The second Respondent has failed to invite national or global tenders for the

formulation of the Revised Master Plan, 2015 and suffers from lack of

transparency.

56. The second Respondent has failed to take into account local participation at

ward levels, or from the local elected representatives while formulating the

Revised Master plan, 2015.

23

Page 24: Final PIL Masterplan

57. The Master Plan was prepared by the second Respondent enlisting the help of a

French consultancy firm, M/s. SCE, a foreign entity with little or no idea of the

ground realities of the city and its needs while ignoring the detailed analysis

proffered by the expert committee and the BMRDA, the primary authority

responsible for the development of the BMR. As such, the entire exercise is

arbitrary, unreasonable and vitiated.

58. The said Plan seeks to treat unequals as equals and is hence discriminatory and

violative of Article 14.

59. The action of the second Respondent in formulating the Plan violates the

Wendsbury principles of reasonableness and the second Respondent has acted

outside the scope of its delegated administrative powers.

60. The said Plan is passed without taking into account the recommendations of

the BMRDA and on this short ground the said Plan to be quashed.

61. The said Plan is passed without complying with the mandatory requirements of

the Karnataka Planning Authority Rules, 1977, particularly Rules 41 & 42 that

provide for ingredients and surveys to be conducted.

62. The Plan is a violation of the very parent statute and is hence a colourable

exercise of powers vested in the Government.

63. The Plan is violative of the provisions of the Act as well as the BMRDA Act.

64. The said Plan does not take into account the various recommendations of the

BMRDA as well as the expert committee / core group. Further, the said Plan

24

Page 25: Final PIL Masterplan

reflects disparity between the Vision Document and the final Plan itself, and is

ultra vires.

65. The absence of public participation in the formulation of the plan as well as in

the constitution of the BMRDA, core group and expert committee violates the

very purpose of the 73rd and 74th Amendment to the Constitution. The said

amendment is further violated by the failure to take into account the role and

suggestions of the BMRDA in the approval of the said Plan.

66. The Plan has introduced several new categories of zones, such as "mixed

zones" Mutation Corridors", Transformation zones all of which are ultra vires

the Act its objectives.

67. The said Plan militates against the Right to Life as the civic authorities would

not be able to provide these due to the errors in the Plan. For example the Plan

permits increase in FAR that would lead to higher density of population and

the consequent impossibility of providing water supply and sanitation to the

affected areas. The opinion of BWSSB the authority responsible to provide the

same were not considered in approving the Plan and the Petitioner believes that

the expert opinion of BWSSB was deliberately ignored by both first and

second Respondents. Similarly, the views of the Fire Force and Police Force

have also not been taken into account.

68. With the introduction of the new Zonal Regulations under the Revised Master

Plan 2015 granting mixed use in all areas, Section 14-A of the Town &

Country Planning has been rendered otiose. Section 14-A was inserted with a

laudable object of restricting change of land use in matter of public interest in

cases of cartographical errors. The said provision (though bereft of guidelines

and abused indiscriminately in practice) has been made redundant by virtue of

25

Page 26: Final PIL Masterplan

the said Plan, sans any cogent reason or justification, hence offending Article

14 of the Constitution of India.

69. The Revised Master Plan, 2015 suffers from various infirmities, viz.,

permitting topographical changes in valley and tank bed areas, reduction of

green belt area from 56% in the year 1995 to a mere 35% currently, permission

for ancillary activity in residential areas etc.

70. The said Plan violates the very objects of the Act and the purpose of planning,

zoning and provisions of change of land use.

71. The said Plan causes a disastrous effect upon the ecology, planning and

identity of the City of Bangalore and violates the fundamental Right to Life of

its residents.

72. The inaction and apathy of the Respondents violates the Constitutional and

Fundamental rights of the Petitioners and the citizens of Bangalore on whose

behalf the present proceedings are brought.

73. The Zonal Regulations framed under the said Plan as well as all consequential

permissions granted thereunder also suffer from the illegalities referred to

above and are liable to be quashed.

74. There is a pressing need for judicial intervention in connection with the failure

in functioning of constitutional and statutory authorities that affect the public

rights of citizens.

75. The impugned Revised Master Plan and the actions of the Respondents suffer

from various other infirmities that shall be pointed out at the time of hearing.

26

Page 27: Final PIL Masterplan

76. The various grounds raised herein are in the alternative and without prejudice

to one another.

GROUNDS FOR INTERIM PRAYER

77. The second Respondent has since obtaining approval from the State

Government has started implementing the zonal regulations formulated under

the Revised Master Plan 2015. Third parties such as IT and BPO companies

and other commercial concerns are being granted permission to start

operations in residential areas. Further, implementation of commercial axes

and mutation corridors are also to begin shortly. These changes once granted

will change the landscape of the city absolutely and there will be no recourse

to remedy this and the Petitioners along with other citizens will be put to

undue and irreversible hardship.

78. Therefore, it is just and necessary to restrain the second Respondent from

taking any action under the Revised Master Plan 2015, and stay the operation

of the Revised Master Plan 2015 pending disposal of this petition, in the

interests of justice. More over, there is a need to constitute a Committee to

enquire into the damage already caused by the implementation of the Plan

and undo the same by filing an appropriate report before this Hon’ble Court.

Unless such orders are passed, the Petitioners and the residents of Bangalore

shall suffer irreparable harm and the petition itself will be rendered

infructuous. Per contra, no hardship shall be caused to the Respondents.

27

Page 28: Final PIL Masterplan

P R A Y E R

WHEREFORE the Petitioners respectfully pray that this Hon’ble Court

may be pleased to –

(i) Issue a writ of Certiorari or any other appropriate writ, order or direction

quashing the Revised Master Plan 2015 formulated by the second

Respondent including the Zoning Regulations framed thereunder and all

illegal permissions granted subsequent to the said Plan (at Annexure S);

(ii) Issue a writ of Certiorari or any other appropriate writ, order or direction

quashing the approval granted by the first Respondent vide its order No.

UDD 540 BEM AA SE 2004, Bangalore dated 25.06.2007 (at Annexure

G);

(iii) Issue a writ of Mandamus or any other appropriate writ, order or

direction, directing the Respondents no. 1 & 2 to reconsider the

formulation of the Revised Master Plan 2015 in view of the

Recommendations of the P. S. S. Thomas Expert Committee and the

representations of the Petitioners (at Annexures C, H & K);

(iv) Grant such other and further reliefs, including the costs of this writ

petition, in the interests of justice.

28

Page 29: Final PIL Masterplan

INTERIM PRAYER

Pending the disposal of this Writ Petition, the Petitioners respectfully pray

that this Hon’ble Court may be pleased to (a) stay the operation of the Revised

Master Plan 2015 (at Annexure S), and (b) constitute a Technical Committee to

enquire into the implementation of the said Plan and the illegal permissions and

sanctions granted pursuant thereto, and to file a report before this Hon’ble Court,

and grant such other and further orders as may be expedient in the interests of

justice

BANGALORE DATED: ADVOCATE FOR PETITIONERS

Address for service: Mr. Aditya Sondhi Advocate Law Chambers 101, Landmark 5/2, Cunningham Crescent Road Bangalore 560 052 +91 80 2225 0428

29