An Analysis of Increase in Volumeof Payroll Queries and Streamlining
the Payroll ProcessINTERNSHIP REPORT
Compiled by: Dennis Joseph Koshy (50)
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
2/49
1
ACKNOWLEDGEMENT
First and foremost we offer our sincere gratitude to our project manager, Suresh SR,
(Associate Vice President & Lead HR Operations (Global Payroll)) who gave us the
opportunity to work with his team on this project. He supported us throughout our
project with his patience and knowledge whilst giving us the liberty to work in our own
way.
We are grateful to Saraswathy MS (Senior Manager - Global Payroll and International
Transfers), for her constant encouragement, guidance and support throughout our
project. We would also like to acknowledge the valuable inputs that she provided which
helped us to develop a better understanding of the entire payroll process.
We wish to express our deep sense of gratitude to Fanny Florence (Senior Officer - HR
Global Payroll), for her timely guidance and useful suggestions, which helped us in
carrying out the project work.
Sincere thanks to Shalom Thomas (HR Business PartnerCorporate Support) and
Julie John (Assistant Manager-PMO) for their timely guidance and valuable assistance
in the conduct of our project work.
I would like to thank Prof. J. Philip, President, XIME for instituting the Summer
Internship Programme (SIP) which has helped us prepare better for corporate life. I also
thank Prof. Reji Mathew, Dean, XIME for his support. I extend my warm gratitude to
Prof. Binu Modoor, Associate Dean, XIME and my Project guide for his time,
encouragement and able guidance.
Finally, yet importantly, we would like to express our heartfelt thanks to our beloved
parents, friends and the entire payroll team for their help and wishes for the successful
completion of this project.
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
3/49
2
Contents
List of Tables.3
List of Figures..4
Abbreviations5
Executive Summary6
Introduction to the Industry....7
Introduction to the Company....10
Introduction to Payroll & Project........................................14
Research Methodology...19
Findings & Analysis.25
Limitations of the Study.38
Recommendations..39
Conclusion43
Bibliography.45
Annexure............................................................................46
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
4/49
3
List of Tables
Table 1.1 Category of Queries 27
Table 2.1 Types of SalaryQueries
32
Table 3.1Volume of queries
from each businesstower
35
Table 4.1 Volume of queriesfrom each level
36
Table 5.1 Volume of queriesfrom each location 38
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
5/49
4
List of Figures
Figure 1.1 IPM StakeholdersInputs
17
Figure 2.1 Data Flow in PayrollSystem
18
Figure 3.1 L1 & L2 Queries v/sMonth
25
Figure 4.1 Types of Queries v/sMonth
26
Figure 5.1 Clarifications v/sMonth
29
Figure 6.1 Updates v/s Month 30
Figure 7.1 Errors v/s Month 31
Figure 8.1 Salary Issues fordifferent months
32
Figure 9.1 Category v/s Month 33
Figure 10.1 Business Tower v/sMonth
35
Figure 11.1 Level v/s Month 36
Figure 12.1 Location v/s Month 37
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
6/49
5
Abbreviations
AWOI Absent Without Information
C & B Compensation & Benefits
ESI Employee State Insurance ETW- Employee tagged Wrongly
FFS - Full & Final Settlement
FLM Front line Manager
HRA House Rent Advance
HRHD Human Resource Help Desk
HRMS Human Resource Management System
IPM Integrated Pay Master LAAS Leave and Attendance Automation System
LOP Loss of Pay
MDS Master Data System
MTP Medically terminated pregnancy
ML Maternity Leave
MSI Merit Salary Increment
OMS Offer Management System PIP - Performance Incentive Plan
PS PeopleSoft
RMG Resource Management Group
R & R Rewards & Recognition
SABL Sabbatical Leave
SAL Shift Allowance
TAT Turn Around Time
VPF Voluntary Provident Fund
VP/VD Variable pay/ Variable deduction
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
7/49
6
Executive Summary
The HR-Payroll and HR-Helpdesk teams handle any kind of salary discrepancies or
queries that are brought forward by the employees regarding their payroll variables and
components. This project attempts to identify the reasons for the large number of payroll
queries and aims at finding ways and means to reduce them.
In order to conduct the study we extracted the data i.e. the payroll queries from
November, 2011 to April, 2012 from PeopleSoft (PS) which constituted the primary
data. Apart from analyzing queries I also spoke to a few members of the payroll team
and the HR Helpdesk.
The study gave fresh insights about the functioning of HR-Payroll and HR-Helpdesk inanswering payroll queries. I observed that the steps taken to raise a query on
PeopleSoft were a cumbersome process and some of the queries raised did not require
the need for a team member to address it. I became aware of the facts that some
managers overlooked uploading important details on IPM, employees failed to
regularize their attendance, and the level of employees awareness on critical issues
like company policies, how to navigate through PeopleSoft, etc.
To overcome these problems we came up with a few suggestions. Some of the majorones were:
Customized tabs on PeopleSoft to raise queries effectively and efficiently.
Auto triggered emails for certain queries to route queries to concerned teams.
Constant communication regarding company polices to all employees.
Action against managers who fail to upload essential details on IPM.
Reminders to employees to ensure that they regularize their attendance.
Mandatory training hours on PeopleSoft (PS).
My main intention was to assist HRHD and the payroll team to function effectively and
efficiently, keeping in mind the need for payroll team to concentrate on core payroll
issues and HRHDs long term goal of going off calls in the future.
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
8/49
7
Introduction to the Industry
The Information Technology industry in India has gained a brand identity as a
knowledge economy due to its IT and ITES sector. The ITITES industry has two major
components: IT Services and Business Process Outsourcing (BPO). The growth in the
service sectorin India has been led by the ITITES sector, contributing substantially to
increase in GDP, employment, and exports. The sector has increased its contribution to
India's GDP from 1.2% in FY1998 to 7.1% in FY2011.
According to NASSCOM, the ITBPO sector in India aggregated revenues of US$88.1
billion in FY2011, where export and domestic revenue stood at US$59 billion and
US$29 billion respectively. The major cities that account for about nearly 90% of thissectors exports are Bangalore, Delhi, Mumbai, Chennai, Hyderabad, Pune, Kolkata and
Coimbatore. Export dominate the ITITES industry, and constitute about 77% of the
total industry revenue. Though the ITITES sector is export driven, the domestic market
is also significant with a robust revenue growth. The industrys share of total Indian
exports (merchandise plus services) increased from less than 4% in FY1998 to about
25% in FY2012. According to Gartner, the "Top Five Indian IT Services Providers" are
Tata Consultancy Services, Infosys, Cognizant, Wipro and HCL Technologies
This sector has also led to employment generation. Direct employment in the IT
services and BPO/ITES segment was 2.3 million in 2009-10 indirect employment of
over 8.3 million job opportunities is also expected to be generated due to the growth of
this sector in 2010-11. Generally considered a dominant player in the global outsourcing
sector, however, the sector continues to face challenges of competitiveness in the
globalized world, particularly from countries like China and Philippines.
India's growing stature in the Information Age enabled it to form close ties with both the
United States of America and the European Union. However, the recent global financial
crisis has deeply impacted the Indian IT companies as well as global companies. As a
result, hiring has dropped sharply, and employees are looking at different sectors like
the financial service, telecommunications, and manufacturing industries, which have
http://en.wikipedia.org/wiki/Information_technologyhttp://en.wikipedia.org/wiki/Indiahttp://en.wikipedia.org/wiki/Indiahttp://en.wikipedia.org/wiki/Brand_identityhttp://en.wikipedia.org/wiki/Knowledge_economyhttp://en.wikipedia.org/wiki/IT_Serviceshttp://en.wikipedia.org/wiki/Business_process_outsourcinghttp://en.wikipedia.org/wiki/Service_sectorhttp://en.wikipedia.org/wiki/GDPhttp://en.wikipedia.org/wiki/NASSCOMhttp://en.wikipedia.org/wiki/Bangalorehttp://en.wikipedia.org/wiki/Delhihttp://en.wikipedia.org/wiki/Mumbaihttp://en.wikipedia.org/wiki/Chennaihttp://en.wikipedia.org/wiki/Hyderabad,_Indiahttp://en.wikipedia.org/wiki/Punehttp://en.wikipedia.org/wiki/Kolkatahttp://en.wikipedia.org/wiki/Coimbatorehttp://en.wikipedia.org/wiki/Gartnerhttp://en.wikipedia.org/wiki/Tata_Consultancy_Serviceshttp://en.wikipedia.org/wiki/Infosyshttp://en.wikipedia.org/wiki/Cognizanthttp://en.wikipedia.org/wiki/Wiprohttp://en.wikipedia.org/wiki/HCL_Technologieshttp://en.wikipedia.org/wiki/Outsourcinghttp://en.wikipedia.org/wiki/Chinahttp://en.wikipedia.org/wiki/Philippineshttp://en.wikipedia.org/wiki/Information_Agehttp://en.wikipedia.org/wiki/United_States_of_Americahttp://en.wikipedia.org/wiki/European_Unionhttp://en.wikipedia.org/wiki/Financial_crisis_of_2007%E2%80%932010http://en.wikipedia.org/wiki/Financial_crisis_of_2007%E2%80%932010http://en.wikipedia.org/wiki/Financial_crisis_of_2007%E2%80%932010http://en.wikipedia.org/wiki/Financial_crisis_of_2007%E2%80%932010http://en.wikipedia.org/wiki/European_Unionhttp://en.wikipedia.org/wiki/United_States_of_Americahttp://en.wikipedia.org/wiki/Information_Agehttp://en.wikipedia.org/wiki/Philippineshttp://en.wikipedia.org/wiki/Chinahttp://en.wikipedia.org/wiki/Outsourcinghttp://en.wikipedia.org/wiki/HCL_Technologieshttp://en.wikipedia.org/wiki/Wiprohttp://en.wikipedia.org/wiki/Cognizanthttp://en.wikipedia.org/wiki/Infosyshttp://en.wikipedia.org/wiki/Tata_Consultancy_Serviceshttp://en.wikipedia.org/wiki/Gartnerhttp://en.wikipedia.org/wiki/Coimbatorehttp://en.wikipedia.org/wiki/Kolkatahttp://en.wikipedia.org/wiki/Punehttp://en.wikipedia.org/wiki/Hyderabad,_Indiahttp://en.wikipedia.org/wiki/Chennaihttp://en.wikipedia.org/wiki/Mumbaihttp://en.wikipedia.org/wiki/Delhihttp://en.wikipedia.org/wiki/Bangalorehttp://en.wikipedia.org/wiki/NASSCOMhttp://en.wikipedia.org/wiki/GDPhttp://en.wikipedia.org/wiki/Service_sectorhttp://en.wikipedia.org/wiki/Business_process_outsourcinghttp://en.wikipedia.org/wiki/IT_Serviceshttp://en.wikipedia.org/wiki/Knowledge_economyhttp://en.wikipedia.org/wiki/Brand_identityhttp://en.wikipedia.org/wiki/Indiahttp://en.wikipedia.org/wiki/Information_technology -
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
9/49
8
been growing phenomenally over the last few years. India's IT Services industry was
born in Mumbai in 1967 with the establishment of Tata Group in partnership with
Burroughs. The first software export zone SEEPZ was set up in Mumbai way back in
1973, the old avatar of the modern day IT Park. More than 80 percent of the country's
software exports happened out ofSEEPZ, Mumbai in the 80s.
The economic effect of the technologically inclined services sector in Indiaaccounting
for 40% of the country's GDP and 30% of export earnings as of 2006, while employing
only 25% of its workforce
Today, Bangalore is known as the Silicon Valley of India and contributes 33% of Indian
IT Exports. Two of Indias largest IT companies, Infosys and Wipro are head-quartered
in Bangalore, as are many of the global SEI-CMM Level 5 Companies.
Mumbai too has its share of IT companies that are India's first and largest, like TCS and
well established companies like Reliance, Patni, LnT Infotech, i-Flex, WNS, Shine,
Naukri, Jobspert etc. And these IT and dot com companies are ruling the roost of
Mumbai's relatively high octane industry ofInformation Technology.
Such is the growth in Information Technology; it was revealed that Cap Gemini will soon
have more staff in India than it does in its home market of France with 21,000
personnel+ in India.
A joint EU-India group of scholars was formed on 23 November 2001 to further
promote joint research and development. On 25 June 2002 India and the European
Union agreed to bilateral cooperation in the field of science and technology. India holds
observer status at CERN while a joint India-EU Software Education and Development
Center is due at Bangalore.
http://en.wikipedia.org/wiki/Mumbaihttp://en.wikipedia.org/wiki/SEEPZhttp://en.wikipedia.org/wiki/SEEPZhttp://en.wikipedia.org/wiki/Mumbaihttp://en.wikipedia.org/wiki/Silicon_Valley_of_Indiahttp://en.wikipedia.org/wiki/Mumbaihttp://en.wikipedia.org/wiki/Tata_Consultancy_Serviceshttp://en.wikipedia.org/wiki/Reliancehttp://en.wikipedia.org/wiki/Patni_Computer_Systemshttp://en.wikipedia.org/wiki/Larsen_%26_Toubro_Infotechhttp://en.wikipedia.org/wiki/Oracle_Financial_Services_Softwarehttp://en.wikipedia.org/wiki/WNS_Global_Serviceshttp://en.wikipedia.org/wiki/Information_Technologyhttp://en.wikipedia.org/wiki/European_Unionhttp://en.wikipedia.org/wiki/European_Unionhttp://en.wikipedia.org/wiki/CERNhttp://en.wikipedia.org/wiki/Bangalorehttp://en.wikipedia.org/wiki/Bangalorehttp://en.wikipedia.org/wiki/CERNhttp://en.wikipedia.org/wiki/European_Unionhttp://en.wikipedia.org/wiki/European_Unionhttp://en.wikipedia.org/wiki/Information_Technologyhttp://en.wikipedia.org/wiki/WNS_Global_Serviceshttp://en.wikipedia.org/wiki/Oracle_Financial_Services_Softwarehttp://en.wikipedia.org/wiki/Larsen_%26_Toubro_Infotechhttp://en.wikipedia.org/wiki/Patni_Computer_Systemshttp://en.wikipedia.org/wiki/Reliancehttp://en.wikipedia.org/wiki/Tata_Consultancy_Serviceshttp://en.wikipedia.org/wiki/Mumbaihttp://en.wikipedia.org/wiki/Silicon_Valley_of_Indiahttp://en.wikipedia.org/wiki/Mumbaihttp://en.wikipedia.org/wiki/SEEPZhttp://en.wikipedia.org/wiki/SEEPZhttp://en.wikipedia.org/wiki/Mumbai -
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
10/49
9
India's IT industry (in USD bn)
Particulars
FY
2004
FY
2005
FY
2006
FY
2007
FY
2008
IT Services 10.4 13.5 17.8 23.5 31.0
- Exports 7.3 10.0 13.13 18.0 23.1
- Domestic 3.1 3.5 4.5 5.5 7.9
ITES-BPO 3.4 5.2 7.2 9.5 12.5
- Exports 3.1 4.6 6.3 8.4 10.9
- Domestic 0.3 0.6 0.9 1.1 1.6
Engineering services, R&D and Software
products2.9 3.9 5.3 6.5 8.6
- Exports 2.5 3.1 4.0 4.9 6.4
- Domestic 0.4 0.7 1.3 1.6 2.4
Hardware 5.0 5.9 7.0 8.5 12.0
- Exports 0.5 0.5 0.6 0.5 0.5
- Domestic 4.4 5.1 6.5 8.0 11.5
Total IT industry (including hardware) 21.6 28.4 37.4 48.0 64.
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
11/49
10
Introduction to the Company
MphasiS a unit of Hewlett-Packard Co., is an Information Technology services
company based in Bangalore, India. MphasiS is certified with ISO 9001:2008, ISO/IEC
27001:2005 and is assessed at CMMI v 1.2 Level 5. MphasiS is ranked #7 in India IT
companies and overall #165 by Fortune India 500 in 2011 with more than 38,000
employees as of 2011. The company has 29 offices in 14 countries with delivery centers
in India, Sri Lanka, China, North America and Europe.
History
MphasiS (then, MphasiS BFL Limited) was formed in June 2000 after the merger of the
US-based IT consulting company MphasiS Corporation (founded in 1998) and the
Indian IT services company BFL Software Limited (founded in 1992). MphasiS
Corporation was founded in 1998 in Santa Monica, California by Jerry Rao and Jeroen
Tas.
In June 2006 Electronic Data Systems (EDS) purchased a controlling stake in the
company (52%) for $380 million and operated as an independent EDS unit. On May 13,
2008, Hewlett-Packard confirmed that it had reached a deal with Electronic Data
Systems to acquire the company for $13.9 billion. The deal was completed on August
26, 2008.
In September 2009 MphasiS changed its brand identity by dropping EDS association to
become "MphasiS, an HP Company" after HP retired EDS Brand to become "HP
Enterprise Services". MphasiS operates as an independent HP subsidiary with its own
board and continues to be listed on Indian markets as "MphasiS Limited". Currently HP
owns close to 62% in MphasiS.
MphasiS marked $1 billion in revenues and registered a consolidated revenue of Rs
5,037 crore ($1,099.3 million) for the year ended October 31, 2010 becoming the sixth
Indian IT company to do that. MphasiS headquarters at Bagmane Tech Park,
Bangalore.
http://en.wikipedia.org/wiki/Hewlett-Packard_Co.http://en.wikipedia.org/wiki/Bangalorehttp://en.wikipedia.org/wiki/Indiahttp://en.wikipedia.org/wiki/Fortune_India_500http://en.wikipedia.org/wiki/Santa_Monicahttp://en.wikipedia.org/wiki/Californiahttp://en.wikipedia.org/wiki/Jerry_Raohttp://en.wikipedia.org/wiki/Electronic_Data_Systemshttp://en.wikipedia.org/wiki/Hewlett-Packardhttp://en.wikipedia.org/wiki/HP_Enterprise_Serviceshttp://en.wikipedia.org/wiki/HP_Enterprise_Serviceshttp://en.wikipedia.org/wiki/Bagmane_Tech_Parkhttp://en.wikipedia.org/wiki/Bangalorehttp://en.wikipedia.org/wiki/Bangalorehttp://en.wikipedia.org/wiki/Bagmane_Tech_Parkhttp://en.wikipedia.org/wiki/HP_Enterprise_Serviceshttp://en.wikipedia.org/wiki/HP_Enterprise_Serviceshttp://en.wikipedia.org/wiki/Hewlett-Packardhttp://en.wikipedia.org/wiki/Electronic_Data_Systemshttp://en.wikipedia.org/wiki/Jerry_Raohttp://en.wikipedia.org/wiki/Californiahttp://en.wikipedia.org/wiki/Santa_Monicahttp://en.wikipedia.org/wiki/Fortune_India_500http://en.wikipedia.org/wiki/Indiahttp://en.wikipedia.org/wiki/Bangalorehttp://en.wikipedia.org/wiki/Hewlett-Packard_Co. -
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
12/49
11
Services
MphasiS is engaged in providing information technology services to its customers
around the world. MphasiS provides integrated solutions that include business process
outsourcing, infrastructure technology, and application services. The application
services offered by the company include application development as well as
applications maintenance and support services. The markets served by the company
are financial services & insurance, healthcare, manufacturing, government,
transportation, communications, and consumer & retail industries.
MphasiS- BPO
Fortune 500 companies globally are served through voice and contact center by the
MphasiS BPO. Personalizing near shore, offshore and onshore solutions are part of the
field of expertise of the company. Value added and efficient customer service care is
provided by the business process outsourcing unit. The various processes include
finance and accounting, tax and compliance, research and content management and
customer relationship management
The company has BPO operating in Mangalore, Pune, Noida, Mumbai, Bangalore,
Pondicherry and Ahmadabad. All these centers offers English language customer care
services. The Latin American clients are routed normally to the Tijuana and Mexico
units.
The support service in various sectors as provided by MphasiS business process
outsourcing includes comprehensible solutions. For instance in research and content
management processes the customer service helps you to clean, and manage through
integrated and aggregative mediums. This enhances access to information and data.
Similarly in financial processes effective management and awareness is provided byconforming to company rules and policies. Customer relationship management helps in
enhancing interactivity with customers. This includes leveraging in a seamless way
through phone, web and effective communicating devices. Human resource outsourcing
includes effective utilization of Human Resource policies and practices.
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
13/49
12
The MphasiS BPO operates through an efficient management system. This
management is dedicated to allotting processes and structuring them. A team of
management information systems, quality assurance and business analysts handles the
operations of each individual processes. Customer service improvement is handled by
the Six Sigma team. The business process outsourcing unit works on a three step
process principle: Transition, stabilization and finally optimization.
Offices
With more than 38,000 employees, MphasiS has presence across India with centers in
Bangalore, Raipur, Chennai, Pune, Mumbai, Noida-NCR, Indore, Pondicherry,
Ahmedabad, Bhubaneswarand Mangalore.
http://en.wikipedia.org/wiki/Indiahttp://en.wikipedia.org/wiki/Bangalorehttp://en.wikipedia.org/wiki/Raipurhttp://en.wikipedia.org/wiki/Chennaihttp://en.wikipedia.org/wiki/Punehttp://en.wikipedia.org/wiki/Ahmedabadhttp://en.wikipedia.org/wiki/Bhubaneswarhttp://en.wikipedia.org/wiki/Bhubaneswarhttp://en.wikipedia.org/wiki/Bhubaneswarhttp://en.wikipedia.org/wiki/Ahmedabadhttp://en.wikipedia.org/wiki/Punehttp://en.wikipedia.org/wiki/Chennaihttp://en.wikipedia.org/wiki/Raipurhttp://en.wikipedia.org/wiki/Bangalorehttp://en.wikipedia.org/wiki/India -
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
14/49
13
HR Organization Chart
Chief Human
Resource Officer
SVP & Head -
Global HR
Operations
SVP & Business HR
Head BPO
Domestic
SVP & Head -
Global Staffing &
Learning
SVP & Head -
Technical Learning
SVP & Head -
Global
Compensation &
Benefits
SVP & Apps Bus HR
Head-Matured
Mkts Benefits.
SVP and Business
HR Head ITO
core &Talent
Management
SVP and Head HR
BPO International,
Service desk &
Corporate Support
Executive Assistant
to CHRO
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
15/49
14
Introduction to Payroll and the Project
In a company, payroll is the sum of all financial records of salaries, wages, bonuses,
allowances, incentives and deductionsfor an employee. In accounting, payroll refers to
the amount paid to employees for services they provided during a certain period of time.In the case of most Indian companies that being on a monthly basis. Payroll plays a
major role in a company for several reasons. From an accounting perspective, payroll is
crucial because payroll and payroll taxes considerably affect the net income of most
companies and they are subject to laws and regulations. From an ethics in business
viewpoint payroll is a critical department as employees are responsive to payroll errors
and irregularities: good employee morale requires payroll to be paid timely and
accurately. The primary mission of the payroll department is to ensure that all
employees are paid accurately and timely with the correct withholdings and deductions,
and to ensure the withholdings and deductions are remitted in a timely manner. This
includes salary payments, tax withholdings, and deductions from a paycheck.
It consists of details regarding the employee ID, employee name, date of joining, daily
attendance record, basic salary, allowances, overtime pay, different types of bonuses,
commissions, incentives, pay for holidays, vacations and sickness, and accommodation
etc. Various deductions such as PF, taxes, loan installments or salary advances taken
by employee are deducted before releasing the salary to the employee.
Calculation of gross salaries and deductible amounts is a tedious task which involves
risk. Some of the organizations use the traditional manual method of payroll processing
and some go for the advanced payroll processing software.
In todays computerized environment, payroll system has developed into automated
software that performs every action needed by the payroll process. It helps in
calculating the payable amounts and deductions very easily. It also helps in generating
the pay slips in lesser time. MphasiS however, belongs to the first category, and still use
the traditional manual method.
http://en.wikipedia.org/wiki/Companyhttp://en.wikipedia.org/wiki/Financialhttp://en.wikipedia.org/wiki/Salaryhttp://en.wikipedia.org/wiki/Wagehttp://en.wikipedia.org/wiki/Tax_deductionhttp://en.wikipedia.org/wiki/Tax_deductionhttp://en.wikipedia.org/wiki/Paycheckhttp://en.wikipedia.org/wiki/Paycheckhttp://en.wikipedia.org/wiki/Paycheckhttp://en.wikipedia.org/wiki/Tax_deductionhttp://en.wikipedia.org/wiki/Wagehttp://en.wikipedia.org/wiki/Salaryhttp://en.wikipedia.org/wiki/Financialhttp://en.wikipedia.org/wiki/Company -
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
16/49
15
Automated calculations minimize errors. Data is validated automatically by the software.
It needs professionals to make use of the software for its efficient working.
IPM InputsIntegrated Pay Master (IPM) is an internal tool developed with the help of Chief
Information Office (CIO) team for collating all the payroll inputs. The various payroll
inputs for all India & Overseas employees or their respective managers are provided
through IPM. All the inputs given by the stakeholders on this tool are considered as
approved. All the inputs have to be provided before 15th of every month after which the
data uploaded on IPM, will be processed by the payroll team.
Features of IPM
Ensures data security and confidentiality
Removes person & email dependency (multiple handovers)
Audit Trail
Reduction in effort & time taken by the payroll team
IPM Stakeholders
IPM gets the inputs from various stakeholders for the Payroll Processing. The majorstakeholders are:
Recruitment
Offer Management System (OMS)
Delivery
Compensation & Benefits (C & B)
Finance
Human Resource (HR)- Talent Management Group
Resource Management Group (RMG)
Admin
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
17/49
16
Figure 1: IPM Stakeholders Inputs
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
18/49
17
Validation of Payroll System
Payroll system proves to be an integral part of any companys efficient and successful
running. At MphasiS, the payroll system comprises of 4 elements:
IPM
PS
MDS
Delphi
IPM Integrated Pay Master is an internal tool developed with the help of CIO team for
collating all the payroll inputs
PS - PeopleSoft is being used by MphasiS as the Human Resource Management
System (HRMS).
MDS - Master Data System is where all these details get accumulated and is sent to
other downstream applications. It is currently used only for VP/VD inputs.
Delphi It is the system used by the Finance team to integrate the payout details of
each employee.
Figure 2: Data Flow in Payroll System
IPM PS MDS DELPHI
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
19/49
18
Validation Process
In order to reduce the number of payroll related queries coming to the payroll team, a
study was conducted to identify the major issues or errors in the existing process.
Sample: A sample of 7989 payroll queries was pulled out from PeopleSoft, for doing the
study. The dump was from 1st November 2011 to 30th April 2012.
Validation: Each query was manually looked up on PeopleSoft and then categorized.
Validation was done in Excel with the help of vlookup formula to extract essential
details.
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
20/49
19
Research Methodology
Research in common parlance refers to a search for knowledge. Once can also define research
as a scientific and systematic search for pertinent information on a specific topic. The Advanced
Learners Dictionary of Current English lays down the meaning of research as a careful
investigation or inquiry especially through search for new facts in any branch of knowledge.
According to Clifford Woody research comprises defining and redefining problems,
formulating hypothesis or suggested solutions; collecting, organizing and evaluating
data; making deductions and reaching conclusions; and at last carefully testing the
conclusions to determine whether they fit the formulating hypothesis. Research is, thus,
an original contribution to the existing stock of knowledge making for its advancement. It
is the pursuit of truth with the help of study, observation, comparison and experiment. In
short, the search for knowledge through objective and systematic method of finding
solution to a problem is research.
The purpose of research is to discover answers to questions through the application of
scientific procedures. The main aim of research is to find out the truth which is hidden
and which has not been discovered as yet. Though each research study has its own
specific purpose, we may think of research objectives as falling into a number of
following broad groupings:
To gain familiarity with a phenomenon or to achieve new insights into it (studies
with this object in view are termed as exploratoryorformulate research studies)
To portray accurately the characteristics of a particular individual, situation or a
group (studies with this object in view are known as descriptive research
studies); To determine the frequency with which something occurs or with which it is
associated with something else (studies with this object in view are known as
diagnosticresearch studies);
To test a hypothesis of a causal relationship between variables (such studies are
known as hypothesis-testingresearch studies).
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
21/49
20
Statement of the Problem: The large amount of payroll queries that was coming to the
payroll team was considered more than what it should be getting each month. Some of
the issues caused by this were;
Increasing number of payroll queries lead to: low employee satisfaction and
increased man-hours.
Apart from that, this caused the payroll team to divert their focus from hard core
payroll issues.
Increasing the workload of the HR Helpdesk
Assumptions: Few assumptions regarding the study were that;
Since BPO employees were not used to the corporate setup, the initial
assumption was that maximum queries would come from the BPO Tower.
The main location from where the queries were coming in was considered to be
Bangalore and Pune, since they had the highest number of employees.
The assumption was that the new employees would be asking more queries than
the older employees.
Hypothesis: Since the study conducted was descriptive in nature, I did not have a
hypothesis for the same.
Sample: A sample of 7989 payroll queries was pulled out from PeopleSoft, for doing the
study. The dump was from 1st November 2011 to 30th April 2012.
Universe: All queries that were coming to the HR Helpdesk, from 1st November 2011 to
30th April 2012 would be the universe for the study.
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
22/49
21
Limitations of the Study: This study had its share of limitations. Some of the major
ones were:
Data was not accurate that was pulled out from PS - The L1 queries that were
pulled out for the November, December and January were all Salary queries,
unlike for the other months, which was purely data from payroll category.
Difficult to categorize since they were very similar- Some of the queries were
so similar in nature that it was difficult to put it into a category sometimes. The
categorization was done on the basis of our understanding of the query or
solution provided.
No proper Summary - Some of the L1 queries did not have a proper summary.
Because of this, there was no clarity on the issue. Therefore we were not able
categorize them.
Time Limitation Since the report has to be submitted before the results of the
implemented recommendations are still unknown, estimations cant be based it.
Due to the time limit, this study cant be compared to any other organizations that
have implemented similar recommendations.
The target population for the purpose of our analysis were all the permanent, contractbasis, pre-separated and separated employees of MphasiS Ltd, both onsite and
offshore employees, who have raised payroll related queries on PeopleSoft via calls
and e-mails, from November, 2011 to April; 2012.The duration of study was from May
7th June 29th, 2012.
The data was collected by, extracting reports from PeopleSoft by using the following
steps:
Main MenuReporting Tools Helpdesk Reporting Tools 9.1 Helpdesk Query
Manager 9.1
The command for each category being:
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
23/49
22
RC_CASE_SUMMARY L1 Queries
RC_CASE_SUMMARY_1_PAYROLL L2 Queries
The entire payroll dump was analyzed by using their respective case IDs on PeopleSoft
(PS). Based on our observation we were able to classify them on the following basis:
updates, clarification and errors.
Those queries which were grouped underclarifications were raised because:
The employees were seeking general information
Employees needed clarity on certain issues
Those queries marked as updates were done for the following reasons:
Employees faced difficulties in updating their bank account and PAN card details
so they required the assistance of the payroll team for the same.
Employees made requests with respect to application of leaves, salary advance
and VPF requests.
The Errors were classified taking into consideration the following:
Technical errors
Human errors
After going through the queries, on the basis of our understanding we were able to
classify them into the following categories:
Advances:Queries were based on employees requests to apply for salary advances
for medical reasons, house rent etc. as they required the payroll team to apply for it ontheir behalf and forward the same to the finance team.
Allowances: Queries based on shift/on-call special, deputation, onsite, leave travel
allowances.
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
24/49
23
Bank Accounts & Pan Card Issues: Requests to update the bank account numbers or
deletion of the previous accounts and updating the employee PAN details on People
Soft.
Bonus Issues: Issues relating to joining, longevity, referral, skill and retention bonus
were placed under this category.
Deductions: This consisted of issues involving deductions with respect to taxes
(Professional & Income), transport and insurance premium deductions.
Employee tagged wrongly: These were queries regarding incorrect Band, Level,
Designation and location of employees on their pay slips or on PS.
Gratuity and Superannuation: Employees want to know the status and breakup of the
gratuity amount for the tenure of the employees. The status of the gratuity cheque sent
is also clarified at times.
Incentives: Employees raise their concerns of the amounts due to them with respect torewards and recognition (R&R) amounts, PIP, and training incentives.
Leave Related:Requests relating to employees extending their LOP for the following
months, LOP reversal issues, leave balance and leave encashment for the year.
PF issues: Employees raise the cases for reasons of discontinuing the VPF or
information regarding PF transfer, withdrawal, contribution, balance enquiry etc.
Reimbursements: Joining /discontinuing transport and Car and fuel reimbursements
policies.
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
25/49
24
Salary Issues: Discrepancies in the Salary credited for the month and clarifications as
to why the salary hasnt been released. These queries were sub categories on the
solutions provided to the queries stated below:
HRMS Stoppay
LAAS Stoppay
Bank Stoppay
Released Through Cheque
Interim Payout
Raise case on PS
Salary deductions
Others
Miscellaneous Issues: Employees raised cases requesting for information purposes
on various issues like car enrollment policy, Change of LAN ID, payment of summit
award etc.
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
26/49
25
Findings & Analysis
The total amount of queries analyzed over a period of 6 months from November, 2011
to April, 2012 was 7989. Out of which 4502 (56.4%) were L1 Queries and 3487 (43.6%)
were L2 queries, handled by the HR- Helpdesk and HR- Payroll team respectively.
Figure 3.1
As shown in figure 3.1 the month of November 2011 had a sum total of 1536 queries.
This was because for the month of November, December and January the data
received was not purely Payroll data, but queries were extracted from the salary
category as well.
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
27/49
26
Figure 4.1
7989 queries were then classified into 6393 Clarifications (80%), 1283 (16.1%) request
for system updates and 313 (3.9%) technical or human errors.
As shown in figure 4.1 the queries that have hit payroll every month have been relativelyof the same type over the last six months. The clarifications seem to have reduced over
the months, but the updates have seen an upward trend till the month of March. The
errors have been relatively low on a month on month basis.
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
28/49
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
29/49
28
Gratuity and superannuation constituted around 2.3% of total queries where
employees inquired about their gratuity status.
PF issues were 2.2% of the total queries where employees raised queries about
their PF calculations, statement, and information on transfer or withdrawal of PF.
Queries were also raised with respect to alterations in VPF contribution.
Issues relating to incorrect information shown in PS or on Pay-slip of employees
with regard to Band, Designation, Level and Location represented 2% of total
queries.
Advances and Miscellaneous issues were 1.3% of total queries.
Reimbursements amounted to 0.9% of total queries.
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
30/49
29
Figure 5.1
As seen in figure 5.1 Clarifications were primarily because of salary issues 57%,
deductions 8%, leave related 7% and bank account and pan card issues 4.5% of total
clarifications. The rise in allowances and deductions were mainly because of the
change in shift allowance policy and transport policy for the month of April and March
respectively.
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
31/49
30
Figure 6.1
As seen in the above figure 6.1, Updates were largely because of requests for bank
account and pan card updates (61.6%) and leave related issues (21.2%) as a
percentage of total updates.
The reason for the increasing trend in bank account updates from the month of
February was because the data received for the month of November- January wasnt
purely Payroll data, majority of the queries were extracted from the salary category.
The leave related issues were considerably high for November and December because
of LOP reversals as employees would have gone on leave and on resuming work they
would have been on LOP.
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
32/49
31
Figure 7.1
As depicted in figure 7.1, Errors were mainly because of salary issues (30%).
Employees raised queries on salary deductions as they would have been on LOP after
resuming from December vacations.
Allowances were 28% of total errors, due to managers carelessness as they failed to
upload the shift allowance and incentive inputs on IPM. 15% were leave related LOP
reversal cases, which has been stopped as of June, 2012.
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
33/49
32
Figure 8.1
As seen in the above figure 8.1, Majority of the queries raised were because of salary
issues, 47.4 % of total queries. The number of queries raised for the months of
November to January is relatively higher because the data received for those months
wasnt purely Payroll data, majority of the queries were extracted from the salary
category.
Salary Issues cases raised were largely due to LAAS Stoppay that constituted 26% of
total salary issues and 12% of the total queries. Whereas for the months of February till
April the queries related to salary issues have been relatively stable.
Table 2.1
1005
638710
465 508 457
Nov Dec Jan Feb March April
Salary Issues
Salary Issues
Queries Cases Grand
Total
Percentage
HRMS Stoppay 159 7989 2.0
Bank Stoppay 314 7989 3.9LAAS Stoppay 993 7989 12.4
Interim Payout 411 7989 5.1
Raise Case 143 7989 1.8
LOP 222 7989 2.8
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
34/49
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
35/49
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
36/49
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
37/49
36
Figure 11.1
As seen in figure 11.1, a majority of the queries were raised by levels 4, 3 and 2.
But when compared as a proportion of the total number of employees active in the
system as on May 2012, vast majority of the queries were raised by employees fromlevels 4 (30.5%), 5 (29.6%) and 6 (25.9%).
Table 4.1
Levels No. of Cases No. of Employees Percentage
1 1343 6731 20.0
2 1418 9116 15.6
3 1477 7412 19.9
4 1534 5024 30.5
5 1086 3673 29.6
6 628 2422 25.9
7 288 1361 21.2
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
38/49
37
Figure 12.1
As observed in figure 12.1 a vast majority of the queries were raised by employees from
locations like Bangalore, Pune and Indore in descending order.
But when compared as a proportion of the total number of employees active in the
system as on May 2012, the location which had the most queries in proportion to the
number of employees was Indore (39.8%), Mumbai (26.1%) and Vadodara (25.9%).
Table 5.1
Location No. of Cases No. of Employees Percentage
Bangalore 2236 10872 20.6
Chennai 1008 5082 19.8
Indore 1378 3458 39.8Mangalore 295 1510 19.5
Mumbai 372 1428 26.1
Pune 1664 8435 19.7
Vadodara 417 1612 25.9
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
39/49
38
Limitations of the Study
This study had its share of limitations. Some of the major ones were:
Data was not accurate that was pulled out from PS - The L1 queries that were
pulled out for the November, December and January were all Salary queries,
unlike for the other months, which was purely data from payroll category.
Difficult to categorize since they were very similar- Some of the queries were
so similar in nature that it was difficult to put it into a category sometimes. The
categorization was done on the basis of our understanding of the query or
solution provided.
No proper Summary - Some of the L1 queries did not have a proper summary.
Because of this, there was no clarity on the issue. Therefore we were not able
categorize them.
Time Limitation Since the report has to be submitted before the results of the
implemented recommendations are still unknown, estimations cant be based it.
Due to the time limit, this study cant be compared to any other organizations that
have implemented similar recommendations.
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
40/49
39
Recommendations
Sr.
No
Problem Impact Solution
1. Responses to queries
are wavered and lack
clarity at times.
Employees are notcommunicatedefficiently.
Increased no. ofre-opened cases.
Standardization of
responses to certain
issues.
2. Employees are not
regularizing their
attendance in time.
Increased LAASstoppay cases
Alerts of LAAS systems
and Computer Systems
(wallpapers).
3. Lack of awareness -
Bank Account and Pan
card details.
Increased Bankand Pan cardRelated Queries.
On-boarding SPOCs
must ensure that
employees are well
informed.
4. Employees are
unaware of how to
navigate through PS.
Increased Updates for
Payroll.
Refresher /training
courses on PS.
5. Managers fail to:
Upload the
details on IPM.
Regularize
attendance
Inform policychanges
Employees are :
Unable to claim
their allowances
and incentives.
LAAS Stoppay
More cases raised
Managers should
without fail
Upload details
Regularize
attendance
Inform policychanges
(Action taken if found
lacking)
6. L2 Queries specific to
payroll are not being
routed to payroll.
Increased TAT HD has to make sure
that they clearly assign
queries to the respective
departments.
7. Employees have too
many options in
categories.
Wrong category chosen
thus increasing workload.
One category for payroll.
8.. Employees do not read
email alerts for policy
change.
Unaware of the change in
policy.
Change in structure of
email alerts conveying
policy changes.
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
41/49
40
9. Employees are
unaware how to check
their salary status.
Increase in salary status
queries.
Running scrolls on E-
payroll requesting
employees to check their
status
10. Employees sending tax
related queries to
payroll, instead of
raising a ticket on e-
payroll.
Unwanted increased
number of L1 payroll
queries.
Auto triggered mails to
ensure employees raise
a ticket on e-payroll.
11. Employees are
confused about when
they will receive their
bonus amounts.
Increase in L2 payroll
queries with reference to
bonus.
Clearly state the exact
date the employee can
expect to receive their
bonus amounts.
Recommendations in detail:
1. Reminders for regularization of attendance
Reminders should be sent in the form ofwallpapers on monitor screens
for those employees who have access to computers just before payroll
dates.
For those who do not have accessibility to computer systems, reminders
will be showcased on the LAAS system in the form of running scrolls.
2. Handbooks
On-boarding Handbook- A handbook containing details like: Bank/ PAN Card Updates on PS
Medi-claim ( w.r.t. now or never )
Allowances
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
42/49
41
Exit Handout at the start of the notice period - A handout containing
information on :
PF withdrawal/ PF Transfer(especially sharing of personal E-mail
ID)
Gratuity/ Superannuation
Pre-separation process
Full & Final settlement procedure
3. There should be only Single Category for employees to raise their queries
regarding payroll. ( Check Annexure II for further categories)
4. Auto-triggered mails for:
Queries specific to Transport,
Tax ( e-payroll)
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
43/49
42
Suggestions that have been initiated:
1. Running Scrolls on e-Payroll
Though the salary is being processed for the current month, please do login to
Self Service Po rtal (SSP)to know exactly what is yourSalary payout status
for the current month. Use this link, which navigates you to SSP:
URL:
https://appgate.mphasis.com/uniquesig6b474584fc2fa80679cd75f32eedf6b6253
cb4311c336d04850c4093eec403e1/uniquesig1/pfcab/aspx/PayStatusDetails.as
px?ParentId=1&Id=58&Type=1
Expectations
Strengthen HDs processes in order to go off calls in the near future.
Help employees who are unable to elucidate their queries.
Increase the speed and efficiency of the HRHD Team
Clearly stated problems, avoids confusion among HD team members.
Number of re-opened cases will reduce as HD team will have a clearer
understanding of Employees queries.
This will help streamline all queries to the correct stakeholders and there will be
less room for error.
https://appgate.mphasis.com/uniquesig6b474584fc2fa80679cd75f32eedf6b6253cb4311c336d04850c4093eec403e1/uniquesig1/pfcab/aspx/PayStatusDetails.aspx?ParentId=1&Id=58&Type=1https://appgate.mphasis.com/uniquesig6b474584fc2fa80679cd75f32eedf6b6253cb4311c336d04850c4093eec403e1/uniquesig1/pfcab/aspx/PayStatusDetails.aspx?ParentId=1&Id=58&Type=1https://appgate.mphasis.com/uniquesig6b474584fc2fa80679cd75f32eedf6b6253cb4311c336d04850c4093eec403e1/uniquesig1/pfcab/aspx/PayStatusDetails.aspx?ParentId=1&Id=58&Type=1https://appgate.mphasis.com/uniquesig6b474584fc2fa80679cd75f32eedf6b6253cb4311c336d04850c4093eec403e1/uniquesig1/pfcab/aspx/PayStatusDetails.aspx?ParentId=1&Id=58&Type=1https://appgate.mphasis.com/uniquesig6b474584fc2fa80679cd75f32eedf6b6253cb4311c336d04850c4093eec403e1/uniquesig1/pfcab/aspx/PayStatusDetails.aspx?ParentId=1&Id=58&Type=1https://appgate.mphasis.com/uniquesig6b474584fc2fa80679cd75f32eedf6b6253cb4311c336d04850c4093eec403e1/uniquesig1/pfcab/aspx/PayStatusDetails.aspx?ParentId=1&Id=58&Type=1https://appgate.mphasis.com/uniquesig6b474584fc2fa80679cd75f32eedf6b6253cb4311c336d04850c4093eec403e1/uniquesig1/pfcab/aspx/PayStatusDetails.aspx?ParentId=1&Id=58&Type=1 -
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
44/49
43
Conclusion
Every month the HRHD is hit by more than 10,000 queries, of which approximately
1,500 are payroll related queries. The project was conducted in order to reduce such
queries by finding means to streamline processes and create awareness thereby
utilizing companys resources in the best possible way.
Primarily, the trend analysis conducted lead to the following conclusions:
Majority of the queries were raised by the CS business tower and not APPS and
BPO which was the supposition.
Locations which had the most queries in proportion to the number of employees
were Indore, Mumbai and Vadodara. A good number of the queries were raised by employees from levels 4, 5 and 6.
Queries raised by employees who joined in 2005, 2006 and 2008 were the
highest in proportion to the total number of employees who joined that year.
Essentially, our recommendations for streamlining the entire process and thereby
reducing the number of queries were to:
Clear identification of L1 and L2 queries
Simplify the PS CRM navigations/ drop down list to help employee to select the
right option to raise the issue
Assign queries to the right stakeholder at the first place
Structure of responses can be more clear and understandable to employee
Conclusive closure to queries at first place rather than partial response or
incomplete responses
Identify area of concerns which are of repetitive nature and highlight back to the
stakeholders
Commitments made to employees should be tracked in system itself( PS-CRM)
While the overall communication can be improved by:
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
45/49
44
Make it effective to the end customer (employees)
Any policy or process changes which are impacting the employees , should
have multiple mode communication (email, FLM connects , running scrolls,
wallpapers, etc)
Reviewing Manager tool kit and updating it on regular basis
Strengthening the on-boarding effectiveness in terms of mandatory dos &
don'ts
Mandatory training for employees/Front Line Managers (FLMs) on PS system
Our main intention was to assist HRHD and the payroll team to function effectively andefficiently, keeping in mind the need for payroll team to concentrate on core payroll
issues and HRHDs long term goal of going off calls in the future.
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
46/49
45
Bibliography
Websites
www.mphasis.com
www.mymphasis.com
www.humanresource.net.in
www.hrdc.in
www.humancapitalonline.com
www.shrmindia.org
www.wikipedia.org
http://www.mphasis.com/http://www.humanresource.net.in/http://www.hrdc.in/http://www.humancapitalonline.com/http://www.shrmindia.org/http://www.shrmindia.org/http://www.humancapitalonline.com/http://www.hrdc.in/http://www.humanresource.net.in/http://www.mphasis.com/ -
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
47/49
46
Annexure
This will have further categories that an employee can select from:o Leave
o Allowances
o Advances
o Bonus
o Salary
o Payslip
o Bank account details
o Pan Card details
o Incentives
o Gratuity and
Superannuation
o Reimbursements
o Deductions
o PF
o Data upload in PS
o Others
Each Category thereafter will have a Specific Summary.
o Leave
LOP
LAAS
SABL / ML/MTP
Leave balance
Others
o Allowances
Dispute in Shift/On- Call allowance
Dispute in OT allowance
Dispute in Deputation allowance
Dispute in Leave travel allowance Special Allowance
Others
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
48/49
47
o Deductions
Professional Tax
Income Tax
Transport
ESI
Medi-claim
Others
o Payslip
Attestation
Changes in Details on Payslip
Designation
Others
o Bonus Issues
Joining
Referral
Retention
Longevity
Skill
Others
o Gratuity and Superannuation
Gratuity
Superannuation
o Incentives
Training
PIP
R&R
MSI
Others
o Advances Salary Advance
HRA / HDA
Medical Advance
Others
-
7/28/2019 Final PrAn Analysis of Increase in Volume of Payroll Queries and Streamlining the Payroll Processoject Doc
49/49
o Salary
Salary Not credited
Discrepancies in Salary Amount
Salary Status
Salary Deductions
Cheque not received
Wrong cheque
Others