final project
DESCRIPTION
Route Alignment and DesignTRANSCRIPT
-
1
Table of Contents Section 1 ........................................................................................................................................................ 3
Introduction .................................................................................................................................................. 3
Background ................................................................................................................................................... 4
Objectives ..................................................................................................................................................... 4
Methodology ................................................................................................................................................. 4
Broad Band Analysis ...................................................................................................................................... 5
Broadband Selection ................................................................................................................................. 7
Decision Matrix ......................................................................................................................................... 9
Risk Analysis ............................................................................................................................................ 10
Narrowband Analysis .................................................................................................................................. 13
Earthworks .............................................................................................................................................. 15
Existing Structures .................................................................................................................................. 15
Right of Way ............................................................................................................................................ 16
Drainage .................................................................................................................................................. 16
Maintenance Costs ................................................................................................................................. 17
Economic Analysis ................................................................................................................................... 17
Financial Analysis .................................................................................................................................... 18
Cost Analysis ........................................................................................................................................... 20
Decision Matrix ....................................................................................................................................... 22
Risk Analysis ............................................................................................................................................ 24
Environmental Impact Assessment ............................................................................................................. 41
Anticipated Impacts Due To Highway Construction Project ................................................................... 41
Encroachment on precious ecology .................................................................................................... 41
Adverse impact on historical/cultural monuments ............................................................................ 41
Water quality impacts due to construction sites: ............................................................................... 41
Air Quality Impacts during Construction ............................................................................................. 42
Effect on Natural resources ................................................................................................................ 42
Conclusion ................................................................................................................................................... 42
SECTION 2 ................................................................................................................................................... 44
Introduction. ............................................................................................................................................... 44
Design Criteria ............................................................................................................................................. 44
-
2
Design Traffic Volume ............................................................................................................................. 44
Design Speed ........................................................................................................................................... 44
Grade ................................................................................................................................................... 45
Methodology of Route Location ................................................................................................................. 45
Plotting of Horizontal Curves: ................................................................................................................. 45
Plotting of Vertical Curves ...................................................................................................................... 46
Horizontal Curvature ................................................................................................................................... 46
Horizontal Alignment .............................................................................................................................. 47
Results ..................................................................................................................................................... 48
Sample Calculation .............................................................................................................................. 48
Vertical Alignment ...................................................................................................................................... 49
Stopping Sight Distance .......................................................................................................................... 49
Results ..................................................................................................................................................... 50
Sample Calculation: ............................................................................................................................. 50
Cross Section ............................................................................................................................................... 51
Drainage .................................................................................................................................................. 52
Safety Features ........................................................................................................................................... 53
Soil Failure ............................................................................................................................................... 53
Driver Safety ........................................................................................................................................ 54
Conclusion ................................................................................................................................................... 55
References .................................................................................................................................................. 56
Appendix ..................................................................................................................................................... 56
-
3
Section 1
Introduction Travel to and from the East West Corridor to Maraval, Trinidad, is currently facilitated by two
routes out of Maraval, two routes out of Port-of-Spain, and the Lady Young Road. These routes
are often congested at peak hours during the week, and for most of the day during weekends and
public holidays. Special events have also resulted in massive jam density causing untold
inconvenience and distress to users. Thus, an alternative route that traverses from the Lady Young
Road to the Maraval Road is required to be designed in order to alleviate the current traffic
congestion.
A highway by definition is a thoroughfare, route, or way on land between two places which has
typically been paved or otherwise improved to allow travel by some conveyance. Highways are
one part of transportation infrastructure, and transportation is one aspect of meeting human
needs. In order to construct new highways, there is an entire design process in which a
considerable amount of planning is done. This process is comprised of two major portions: 1) the
route location and 2) the geometric alignment. Under the general heading of the route location
stage, there are two main processes that must be undertaken: 1) a broad band analysis and 2) a
narrow band analysis. This portion of the report deals with the extensive route location stage in
which a tentative general area for the final alignment is selected.
In the route location stage, the first thing that must be done is properly study the area in which
the required route must be designed. The given area subtended by the Maraval Road and Lady
Young Road, consists of Cascade and St. Anns: two very densely populated residential areas.
Directly north of this area is the St. Anns peak: a very steep and mountainous terrain that goes in
excess of 300 metres in height above sea level. It is also important to note that there are largely
forested areas around the residential areas, as well as existing rivers in the general area, namely
the St. Anns river and the Arapita river.
-
4
Once the observation and study of the general area has been accomplished, the broad band
stage can now begin; this stage consists mainly of dividing the broad study area into large
(broad) bands that can be studied and assessed individually in order to determine which area is
Background Travel to and from the East West Corridor to Maraval, Trinidad, is currently facilitated by two routes out
of Maraval, two routes out of Port-of-Spain, and the Lady Young Road. These routes are often congested
at peak hours during the week, and for most of the day during weekends and public holidays. Special
events have also resulted in massive jam density causing untold inconvenience and distress to users.
Objectives
The objective of this project is to plan and produce an alternative route between the Lady Young
Road and Maraval in order to reduce the congestion and travel time on the current route.
Establish a suitable broadbands with the aid of Google Earth satellite imagery with at least
three alternatives along with a risk analysis
Produce a route alignment within the established broadband utilizing the concepts of
horizontal and vertical curves in accordance to appropriate design guidelines.
Produce detailed drawings of the roadway with setting out data, profiles of the existing and
proposed roadway, location and type of water crossings, retaining structures and safety
features along with cross sections.
Methodology
1. Using Google Earth satellite imagery, three broad bands with the widths ranging from
500m to 500km were set out in the area of interest. Each broadband was then analyzed
and rated and the optimum broad band was selected.
2. After establishing the optimum broadband, two narrow bands were selected within it.
These narrow bands were then analyzed, rated and compared under more detailed criteria
which includes the Economic, Financial, Environmental, Physical, Social, Technological
factors and a Risk Analysis which was given a 40% weighting in any considerations done.
-
5
3. A route alignment was then designed using the ideal narrow band. The geometric
alignment was that designed in accordance to the criteria set out in the American
Association of State Highway and Transport Officials (AASHTO 2001) design handbook.
4. Engineering drawings including cut and fill, vertical and horizontal curves and profile views
were produced.
Broad Band Analysis
Fig. 1 showing the location of the broad band alternatives.
-
6
Fig. 2 showing the geographical map along with the broadband alternatives
Fig. 3 showing the Hydrological map along with the broadband alternatives
-
7
Broadband Selection
Physical suitability in addition to the Triple bottom line factors were used in order to analyze rate and
compare the broadband. The triple bottom line factor are:
1. Environmental
2. Social
3. Economical
4. Physical
Environmental Factors
During construction, sufficient care for the environment must be undertaken in order to ensure
the sustainability of the project. Special considerations must be made to meet the needs of the
design without heavily compromising the standards of the environment such as foliage, wild life
and also to prevent obstruction or contamination to any natural water ways and drainage that
may be present.
Social Factors
The Social factor deals with the impact of the construction to the community and those in close
proximity to it. Construction brings about a lot of noise, pollution and many undesirable factors
which negatively affect residents in the area. Also, it may be necessary for land to be acquired
from residents to facilitate possible widening or realignment of the road. Some social factors
include; travel time, background views along travels, noise levels, pollution during construction
and pollution of water supply
-
8
Economic Factors
The economic factors play a pivotal role for any construction project to determine the economic
feasibility of said project. In highway construction, it is important to minimize the total project
cost and duration, while providing a quality facility. Also, minimizing vehicle operating costs,
which means; the shorter and less steep the route, the less cost in fuel. This also results in less
pollution and increased leisure time as well as lower vehicle maintenance costs. It is also equally
important to minimize the cost of environmental mitigation.
Physical Factors
The physical considerations deal with the stability of the soil which if unstable would require the
use of stabilizing structures such as retaining walls. The geology of the construction area such as
fault lines, slope of the land and rock types present. The type of soil which contributes to the soil
stability and facilitation of drainage
The vegetation and land use of the area- the removal of which may affect the potential for soil
erosion and lead to land slips.
The amount of rainfall that the area receives as well as the level of the water table level in the area
both relate to the drainage as the soil in the area may not allow for quick infiltration of surface
water which may cause pooling problems on the roadway.
-
9
Decision Matrix
ObjectivesMeasure of
EffectivenessDescription
1 Economic Incurs the least amount of cost
2 SocialIncreases quality of life in surrounding
communities
3 Physical Incurs the least amount of physical risk
4 EnvironmentalIncurs the least negative environmental
impact
Table 1. Measures of Effectiveness
I II III
1 Economic 6 4.5 4
2 Social 8 7 5
3 Physical 7 7 6.25
4 Environmental 7 6.5 5
NumberMeasure of
Effectiveness
Broadband Alternatives
Objective RankingRelative
Weight
Weighting
Factor
1 3 3 20.0
2 3 3 20.0
3 1 5 33.3
4 2 4 26.7
TOTAL: 15
Table 3. Ranking and Weights
I II III
1 20.0 15.0 13.3
2 26.7 23.3 16.7
3 38.9 38.9 34.7
TOTAL 85.6 77.2 64.7
Measure of
Effectivene
ss
Alternatives
Table 4. Point Score for Alternatives
-
10
Risk Analysis
Broadband 1
Environmental
Risk Event Likelihood Impact Severity Risk Level
Suspension of works during heavy
rainfall.3 3 9
Traversing over the mountain will
increase work time and constuction
risks (higher elevations)
3 5 15
Landslides, Mudslides during
construction2 5 10
Social
Clearing of land for construction:
Visual Pollution; Construction
is unsightly and can affect
businesses in the nearby
region
3 4 12
Noise Pollution can disrupt
public productivity3 3 9
Construction of roadway:
Displacement of private
residents and worplaces4 5 20
Environmental
Displacment/Destruction of Flora in
construction path5 3 15
- Removal of wildlife habitats 2 2 4
Noise Pollution 4 3 12
Pollution of waterways 3 3 9
Air pollution:
- Incurrence of respiratory ailments
due to inhalation of dust particles3 3 9
Total Risk Level124
-
11
Broadband 2
Broadband 3
Environmental
Risk Event Likelihood Impact Severity Risk Level
Suspension of works during heavy
rainfall.3 3 9
Traversing over the mountain will
increase work time and constuction
risks (higher elevations)
3 5 15
Landslides, Mudslides during
construction3 5 15
Social
Clearing of land for construction:
Visual Pollution; Construction
is unsightly and can affect
businesses in the nearby
region
3 3 9
Noise Pollution can disrupt
public productivity2 3 6
Displacement of private
residents and worplaces4 5 20
Environmental
Displacment/Destruction of Flora in
construction path5 4 20
- Removal of wildlife habitats 3 2 6
Noise Pollution 4 3 12
Pollution of waterways 3 3 9
Air pollution:
- Incurrence of respiratory ailments
due to inhalation of dust particles3 3 9
Total Risk Level130
-
12
Broadband 1 was shown to have the lowest risk level and the highest score in the decision matrix. Hence
it was chosen for further analysis.
Environmental
Risk Event Likelihood Impact Severity Risk Level
Suspension of works during heavy
rainfall.3 3 9
Traversing over the mountain will
increase work time and constuction
risks (higher elevations)
5 5 25
Landslides, Mudslides during
construction5 5 25
Social
Clearing of land for construction:
Visual Pollution; Construction
is unsightly and can affect
businesses in the nearby
region
2 2 4
Noise Pollution can disrupt
public productivity2 2 4
Displacement of private
residents and worplaces3 2 6
Environmental
Displacment/Destruction of Flora in
construction path5 3 15
- Removal of wildlife habitats 4 4 16
Noise Pollution 3 3 9
Pollution of waterways 3 3 9
- Incurrence of respiratory ailments
due to inhalation of dust particles3 3 9
Total Risk Level131
-
13
Narrowband Analysis
Narrowband Alternative I: This corridor passes close to mountain and provides a more direct route from
Lady Young to Maraval
-
14
Narrowband Alternative II: This corridor passes close to the existing path to Maraval
This corridor passes close to mountain and provides a more direct route from Lady Young to Maraval.
The factors considered in the following matrix and risk analysis included:
Economic
Financial
Social
Environmental
Physical
Technological
After selecting an effective broadband that satisfied the requirements of the analysis, it was
necessary to undertake the narrow band stage of the route alignment. A narrow band is of the
order five to ten times the final alignment; hence it shows the specific area within the chosen
broad band that would be directly affected by the construction of the final alignment. In this
stage of the analysis, we were required to select alternative narrow bands from the optimum
corridor that would be most effective to construct within. In the area between the Lady Young
-
15
Road and Maraval Road, two suitable narrow bands were plotted out such that certain criteria
were considered; the criteria of selection of the narrow band are stated below:
1) Earthworks (amount of cut and fill)
2) Existing structures
3) Right of way
4) Drainage
5) Maintenance costs
These considerations were applied more in depth under the individual data considerations for
the weighted narrow band analysis; in this section, they would each be introduced.
Earthworks
One of the most costly aspects of any road works project is the amount of cut and fill that needs
to be done in order to accommodate the foundation and structure of the proposed road. Cutting
existing earth requires hiring the use of plant/equipment that would be able to remove the earth
in order to achieve the necessary grade; the grading process is not cheap as the rental cost of
equipment is high and the time required to grade existing earth may be extensive, depending on
the type of soil present at the site as well as the length of the proposed narrow band. On the
opposing side, filling existing earth also is costly because even though it is easy to quantify the
amount of fill required, more fill that the calculated volume is required as compaction of the
loose fill must be taken into consideration. Thus the volume of fill required as well as the
equipment necessary to compact the fill are contributing factors to the cost of filling. In order to
minimize costs of earthworks, narrow bands were chosen such that they traversed along a
relatively constant grade along the entire route. By doing this, longer narrow band lengths were
obtained; narrow band 1 was approximately 3.15 km in length while narrow band 2 was 3.26 km.
Existing Structures
Considerations of existing structures within the narrow bands were also made. It was almost
impossible to avoid existing structures due to the fact that the chosen broadband was mainly
consisting of built up areas. It would be a major project delay if the final alignment were to pass
-
16
through currently existing structures, thus requiring time to be put into acquiring rights to
demolish structures and acquire land. It is for this reason that both narrow bands were routed in
order to avoid existing structures in the presently built up areas.
Right of Way
Right of way takes into consideration the legal right for a road to be routed through parcels of
land belonging to residents in the area. For the chosen broadband, right of way is a major cause
of concern due to the fact that any alignment through the residential area would infringe the
right of ownership of parcels of land by residents, thus requiring land to be acquired. In major
construction projects, acquiring land is a very costly and time consuming process as the legal
procedure to acquire land is very drawn out. For major roadwork projects, land is almost always
able to be acquired; however the process would become longer if there is resistance from the
owners of the land to forfeit their parcels. Even if the final alignment is routed along existing
roadway, there still may be the necessity to acquire land in order to widen the roads to
accommodate heavier traffic. While there is still a risk of the necessity of land acquisition, it is
more feasible to route the alignments along existing roads, as was done by the proposed narrow
bands.
Drainage
One of the greater causes for concern would be the resulting drainage situation, should an
alignment be constructed within the chosen narrow band. Drainage has already been accounted
for in the design of the currently existing road, thus any cut, fill or change of gradient of the
current earth would have an impact on the volume of flow through culverts and drains. It is for
this reason, that in the final alignment, grades of road must be selected such that effective
drainage of the roadway can be obtained. Constructing roads results in removing existing soils
which may have allowed drainage through ground seepage and changing of the existing grade
would both have an impact on the volume of direct runoff that would flow through the drains. It
is for this reason that due care and consideration must be given to re-designing the existing
drainage routes; this would therefore result in an increase in the financial cost of the project, as
it is impossible to neglect drainage designs of the alignment.
-
17
Maintenance Costs
Lastly, we must consider the long term maintenance cost of the chosen route. The maintenance
cost of a project is one of the major deciding factors in determining the economic feasibility of
the proposed narrow band. Major factors that affect the maintenance costs along the design life
include repair costs due to natural occurrences such as slope failures and general wear and tear
of the road from daily usage over an extended period of time. For our proposed narrow bands, it
has been estimated that the maintenance cost of the route would be 5% of the original
construction cost, leading narrow band 1 to have a lower maintenance cost.
Economic Analysis
While the financial section of the narrow band analysis was concerned mainly with up front, initial
project costing, the economic analysis is concerned with the long term financial aspects of the
proposed roadway. The economic considerations deal mainly with aspects such as, design life and
maintenance cost of the roadway, cost/benefits and rate of return for the proposed roadway, long
term improvement to industrial and agricultural production, funding to reduce environmental
hazards in the long term and reducing vehicle maintenance costs over the roads design period.
Overall, the economic analysis of the narrow bands deals mainly with the long term financial
benefits of the proposed roadways to be built in the tentative narrow bands.
Under the economic examination of the narrow bands, we deal with maintenance cost over the
design life of the roadway and the estimated vehicle operation costs incurred by motorists. It has
been estimated that the maintenance cost for the proposed narrow bands in the given area would
be approximately 5% of construction costs of the roadway. On this basis, it can be clearly noted
that the narrow band that possessed a lower construction cost to build within it would have a
lower maintenance cost over its design period; this would lead narrow band 1 to be more
economically feasible in incurring an estimated lower maintenance cost over its design period. In
addition to maintenance costs, vehicle operating costs must also be considered, as it is an indicator
of how efficient the road is in transporting motorists from point A to point B with least effects on
their vehicles. Vehicle operating costs have various contributing factors, including the gradient of
-
18
the road, roughness of the road surface, curvature of the road and the amount of speed changes
done by the vehicle while traversing the route. Taking these factors into consideration, vehicle
maintenance costs for the area of the proposed roadway have been generalised as roughly $2 per
kilometre of road. Based on this estimated vehicle operating cost, it can be said that narrow band
1 would contribute to a lower cost as it has a generally shorter length of road. The unit cost of
construction, which has been derived by dividing the machine rates by the production rates, is
generally the same for both narrow band 1 and 2; hence it is not a major economic factor that
needs to be considered.
It is also necessary to pay attention to other economic factors, such as improvement to agricultural
and industrial productivity, while balancing the cost to mitigate environmental impacts after
constructing the road. It is noted that building a road through narrow band 1 would allow for an
increase in industrial productivity, as it would allow easy access to large businesses located nearby;
agricultural productivity would also be improved as a road built on the peak of the mountain would
allow easy access to agricultural lands there. Lastly, the economic analysis deals with the cost for
the mitigation of environmental hazards and disturbances. This encompasses all environmental
risks that can be encountered should a road be built in the proposed narrow band and the funding
that would need to be allocated in order to mitigate these risks.
After comparison of both narrow bands in terms of their economic benefit, it can be seen that
narrow band 1 has a better economic standing than its alternative under the aforementioned
headings. It must be noted that both financial and economic factors will be discussed further and
with more accuracy after the actual alignment of the proposed road way is set out.
Financial Analysis
In the scope of the project, it is quite necessary for us to consider the financial factors that could
impact the progress of the project, as without proper funding, major construction projects cannot
be undertaken. These factors come mainly in the form of construction costing, which includes the
costing of plant/equipment, cost of cut and fill, payment for labour and funding for property
acquisition. In conducting a feasibility study of a project, construction cost is of utmost importance
as it necessary to inform the client, who would be funding the project, of the amount of money
-
19
needed to be put in so they can decide whether or not the project is worth undertaking. While the
estimated construction cost is quite important, of equal importance is the funding source (the
client), the current financial ecosystem and the economic conversion rates. However, as pertains
to the current project being undertaken, it would be more necessary to consider construction cost,
due to the fact that the three aforementioned factors would be common for all alternative narrow
bands under analysis.
In the process of planning out road works, one of the most influential factors in construction is the
soil type that must be built on as it dictates how much soil preparation (in terms of compaction of
soil, backfill etcetera) must be done before construction can begin. However, in the present
situation, both alternative narrow bands are mapped out on relatively similar soil types, mainly
consisting of alluvium rock. As per the Department of Civil Engineering in the University of the
West Indies, St. Augustine, estimated costing per kilometre of road for building on alluvium rock
have been obtained and calculations are shown below it is noted that building on alluvium rock
has an estimated value of $1.4M per kilometre of road works. In examining narrow band 1 with
an average length of 3.15 km, the estimated construction cost of road works would be $4.4M. On
the other hand, building on narrow band 2 with an estimated length of 3.26 km, the estimated
construction cost of road works would be $4.56M. We must also examine the cost of undertaking
earthworks for the construction of the roadway. It is important to note that in doing this, the
method of selecting an equilibrium length was used, in which an attempt was made to reduce
earthworks by sacrificing short road lengths. In inspecting the cost of earthworks, it must be noted
that narrow band 1, while attempting to stay as close as possible to reducing property acquisition
and keeping the road shorter, there was a compromise in the amount of earthworks needed to be
done; this can be seen when cutting a section through the existing path of the narrow band. It can
be seen that the existing ground is quite undulating, thus more attention must be paid to cut and
fill with regards to this narrow band. Narrow band 2, however, sacrificed road length in order to
obtain less need for cut and fill.
-
20
Cost Analysis
Narrow Band 1 total distance = 3.14 km
Construction Cost
Construction cost for alluvium soil = $M1.4 TT/km
alluvium soil would cost = $M1.4 TT x 3.14km
= $M4.4TT
Total construction cost = $M4.4TT
Maintenance cost.
Maintenance cost = 5% of total construction cost
= 5% x $M4.4 TT
= $M0.22TT
Vehicle operating cost.
Vehicle operating cost = $2.30 per km
= $2.30 x 3.14km
= $7.22 per trip across the path
-
21
Narrow Band 2 total distance = 3.26 km
Construction Cost.
Construction cost for alluvium soil = $M1.4 TT/km
3.26 km of alluvium soil would cost = $M1.4 TT x 3.26km
= $M4.56 TT
Total construction cost = $M4.56 TT
Maintenance cost.
Maintenance cost = 5% of total construction cost
= 5% x $M4.56TT
= $M0.23 TT
Vehicle operating cost.
Vehicle operating cost = $2.30 per km
= $2.30 x 3.26km
= 7.50 per trip across the road
-
22
Decision Matrix
I II
1 Financial 4 3.5
2 Economic 3 3
3 Social 4 4
4 Physical 3 3
5 Technological 3 3
6 Environmental 3 2.5
7 Risk Analysis 5 5
NumberMeasure of
Effectiveness
Alternatives
Objectives RankingRelative
Weight
Weighting
Factor
1 1 7 22.6
2 2 6 19.4
3 5 3 9.7
4 2 6 19.4
5 7 1 3.2
6 4 4 12.9
7 4 4 12.9
TOTAL 31
I II
1 22.58 20
2 19.35 19
3 9.68 10
4 19.35 19
5 3.23 3
6 12.90 11
7 12.90 13
TOTAL 100.00 95
Alternatives
Point Scores for Alternatives
Measure of
Effectiveness
-
23
-
24
Risk Analysis
Narrowband 1
Economic
Risk Event Likelihood Impact
Severity
Risk Level Mitigation,
Prevention,
Control
Likelihood after
Mitigation
Impact Severity
after Mitigation
Risk Level
after
Mitigation
Demand for environmental
mitigation and compensation
3 4 12 Education of
public on
benefits of
roadway and
expected
effects
3 2 6
Change in alignment due to
unforeseen conditions:
- Delay in project
completion time
3 4 12 Perform
necessary site
investigations
in order to
address
problems
during design
stage
2 2 4
-
25
- Prolonged use of leased
equipment
2 3 6 Perform
necessary site
investigations
in order to
address
problems
during design
stage
2 2 4
Increased cost due to legal
action taken by (third party)
community members
2 4 8 Education of
public and
regular
progress
announceme
nts
2 3 6
Relocation of
homes/businesses
compensation
3 4 12 Placing of
persons in
areas more
convenient to
lifestyles or
business
1 2 2
Social
-
26
Clearing of land for
construction:
- Dislocation of persons
settled in nearby areas causing
emotional distress
3 4 12 Giving of
sufficient
notice and
available
options of
alternative
residents
2 3 6
- Loss of arable land that
may have been used as source
of income
3 4 12 Provision of
alternative
crop land
3 3 9
- Interference with
culturally, historically significant
sites
2 3 6 Monumentin
g of
significant
areas if
possible,
preservation
of discovered
artifacts
1 3 3
Construction of roadway:
-
27
- Noise from construction
activities causing distress to
surrounding communities
4 3 12 Use of sound
walls, work
schedule
implemented
at times
convenient
for
surrounding
community
2 2 4
- Respiratory issues arising
due to dust from construction
processes
2 4 8 Wetting of
site to reduce
spread of
dust
1 3 3
- Restricted access to
certain areas of land due to
enforce safe distance from
construction site
3 2 6 Education of
public on
necessity of
safety
measures
2 2 4
Steep Terrain:
- Risk of landslips resulting in
danger to site personnel
3 5 15 Carry out soil
stability
studies and
construct
2 3 6
-
28
effective
earth
retaining
structures.
- Risk of damaging equipment
due to mountainous terrain
4 5 20 Only operate
machinery
rated for the
specific
terrain
3 3 9
Risk of encountering
underground waterways,
aquifers during cutting process
2 3 6 Prior in-depth
hydrogeologic
al study
1 3 3
Environmental Impacts
Deforestation:
- Loss of agricultural lands for
food production
4 3 12 Provision of
alternative
crop land
3 3 9
- Removal of wildlife habitats 3 3 9 Creation of
protected
wildlife
3 3 9
-
29
reserve in
other location
Noise Pollution 4 3 12 Use of sound
walls, work
schedule
implemented
at times
convenient
for
surrounding
community
3 4 12
Pollution of waterways 3 3 9 Wetting of
site to reduce
spread of
dust and
effective
clean up of
site
2 3 6
Air pollution:
-
30
- Incurrence of respiratory
ailments due to inhalation of
dust particles
3 3 9 Wetting of
site to reduce
spread of
dust
2 2 4
- Damaging local flora due to
coating of tree leaves with dust
particles
4 3 12 Wetting of
site to reduce
spread of
dust
2 2 4
Project Delay
Delayed processes in property
acquisition, due to resistance
from residents and drawn-out
negotiations
3 4 12 Education of
the public of
the benefits
of the project
2 3 6
Equipment malfunctions 3 4 12 Prior
Inspection
and regular
maintainace
during project
duration
2 3 6
-
31
Delayed approval of project
from regulatory bodies, such
as Town and Country, EMA,
OSHA etc
4 4 16 Early
document
submition
and constant
follow up
3 3 9
Total Risk Level 250 Total Risk Level
After
Mitigation
134
Narrowband 2
Economic
Risk Event Likelihood Impact
Severity
Risk Level Mitigation,
Prevention,
Control
Likelihood after
Mitigation
Impact Severity
after
Mitigation
Risk Level after
Mitigation
Demand for environmental
mitigation and compensation
5 5 25 Education
of public on
benefits of
roadway
and
3 2 6
-
32
expected
effects
Change in alignment due to
unforeseen conditions:
Delay in project
completion time
3 4 12 Perform
necessary
site
investigatio
ns in order
to address
problems
during
design
stage
2 2 4
Prolonged use of leased
equipment
2 3 6 Perform
necessary
site
investigatio
ns in order
to address
problems
2 2 4
-
33
during
design
stage
Increased cost due to legal
action taken by (third party)
community members
4 4 16 Education
of public
and regular
progress
announcem
ents
3 3 9
Relocation of
homes/businesses
compensation
3 3 9 Placing of
persons in
areas more
convenient
to lifestyles
or business
2 2 4
Social
Clearing of land for
construction:
-
34
- Dislocation of persons
settled in nearby areas
causing emotional distress
3 4 12 Giving of
sufficient
notice and
available
options of
alternative
residents
2 3 6
- Loss of arable land that
may have been used as
source of income
3 3 9 Provision of
alternative
crop land
2 2 4
- Interference with
culturally, historically
significant sites
4 4 16 Monumenti
ng of
significant
areas if
possible,
preservatio
n of
discovered
artifacts
3 3 9
Construction of roadway:
-
35
- Noise from
construction activities causing
distress to surrounding
communities
4 3 12 Use of
sound
walls, work
schedule
implemente
d at times
convenient
for
surrounding
community
2 2 4
- Respiratory issues
arising due to dust from
construction processes
2 4 8 Wetting of
site to
reduce
spread of
dust
1 3 3
- Restricted access to
certain areas of land due to
enforce safe distance from
construction site
3 2 6 Education
of public on
necessity of
safety
measures
2 2 4
Steep Terrain:
-
36
- Risk of landslips resulting in
danger to site personnel
2 5 10 Carry out
soil stability
studies and
construct
effective
earth
retaining
structures.
2 3 6
- Risk of damaging equipment
due to mountainous terrain
4 5 20 Only
operate
machinery
rated for
the specific
terrain
3 3 9
Risk of encountering
underground waterways,
aquifers during cutting
process
2 3 6 Prior in-
depth
hydrogeolo
gical study
1 3 3
Environmental Impacts
Deforestation:
-
37
- Loss of agricultural lands for
food production
3 3 9 Provision of
alternative
crop land
2 2 4
- Removal of wildlife habitats 3 3 9 Creation of
protected
wildlife
reserve in
other
location
3 3 9
Noise Pollution 4 3 12 Use of
sound
walls, work
schedule
implemente
d at times
convenient
for
surrounding
community
3 4 12
-
38
Pollution of waterways 3 3 9 Wetting of
site to
reduce
spread of
dust and
effective
clean up of
site
2 3 6
Air pollution:
- Incurrence of respiratory
ailments due to inhalation of
dust particles
3 3 9 Wetting of
site to
reduce
spread of
dust
2 2 4
- Damaging local flora due to
coating of tree leaves with
dust particles
5 4 20 Wetting of
site to
reduce
spread of
dust
3 3 9
-
39
Project Delay
Delayed processes in
property acquisition, due to
resistance from residents
and drawn-out negotiations
4 4 16 Education
of the
public of
the benefits
of the
project
3 3 9
Equipment malfunctions 3 4 12 Prior
Inspection
and regular
maintainac
e during
project
duration
2 3 6
Delayed approval of project
from regulatory bodies, such
as Town and Country, EMA,
OSHA etc
4 4 16 Early
document
submition
and
constant
follow up
3 3 9
-
40
Total Risk
Level
279 Total Risk Level
After
Mitigation
143
Narrow Band 1 was chosen as it scored higher in the decision matrix and was shown to be of lower risk after mitigating steps have been taken.
-
41
Environmental Impact Assessment
Anticipated Impacts Due To Highway Construction Project
Encroachment on precious ecology:
The proposed routing of the highway encroaches upon precious ecological resources, including forests
and streams. This also disturbs the natural habitats of animals living on the encroach land. The
ecological disturbance is likely to occur.
The construction activities will drive some wildlife away from their habitats, particularly the birds that
live on the hill. Many birds within about 500 m of the proposed roadway will leave their currently
roosting and feeding places and move away.
During road construction, the vegetation on the acquired land will be destroyed, and the local
ecosystem is changed. In addition, the destruction and fragmentation effect of the road construction
may diminish the habitats for some of the animal species, so that there may not be enough roosting
places any more for them to survive. During operation, the traffic noise, traffic lights at night and vehicle
emissions may cause some adverse impacts on the wildlife around the road.
Adverse impact on historical/cultural monuments:
The nearby structures to highway projects are adversely affected due to the pollution and
environmental disturbances created by the project. During the construction phase, huge amount of CO2
(Carbon Dioxide) and CO (Carbon Monoxide) gases are released into the atmosphere. The gas poses a
threat to cultural landmarks as they are made up of lime which reacts with these gases in presence of
water/moisture.
Water quality impacts due to construction sites:
Wastewater and hazardous materials may drain into streams and drainage areas, causing pollution to
surface water and groundwater. This is particularly true for large construction sites, construction
campsites, and staging areas where workers, construction equipment, and building materials are most
concentrated.
-
42
Air Quality Impacts during Construction Construction activities particularly earthworks; increased traffic and the use of cement, asphalt, and
other building materials will produce excessive airborne dust and toxic asphalt fumes, causing a major
impact on air quality within the project area.
Effect on Natural resources The highway will disrupt some existing irrigation systems, particularly below the hilly areas where the
road will be constructed. This interception will also affect the existing flood relief channels and natural
drainage of the area.
Conclusion After comparing each broad band under the general headings of the triple bottom line: social,
economic and environmental factors in conjunction with physical characteristics of each, an
evaluation matrix based on these factors was constructed which was used to give scores to each
broadband. The economic aspect of the broadband was weighted as the most imported factor,
while physical characteristics were weighted second and social and environmental factors were
placed third. From this analysis, broad band 1 was calculated to have the highest point score,
thus becoming the chosen broad band in which to construct a narrowband. A risk assessment of
each broad band was subsequently done, in which all possible risks that could occur within each,
was identified and given a risk score. It was determined that broad band 1 also had the lowest
risk score, thus determined to be the least likely to pose serious risk.
Once broad band 1 was chosen, two alternative narrow bands within the chosen broad band
were constructed. These narrow bands were planned out such that they have minimal
earthworks, short lengths and suitable soil types such that they reduce maintenance costs, and
existing roadways were utilized where possible in order to reduce interference of right of way
and existing structures. The narrow bands were analyzed under the broad headings of financial,
economic, physical, environmental, social and technological characteristics. Additionally, a risk
assessment was done for each narrow band in which the initial and mitigated risk scores were
calculated for each. After scoring for each of the aforementioned considerations, a final point
-
43
score was obtained for each, which showed that narrow band 1 was the higher scored of the 2
alternative narrow bands, thus leading it to be the chosen narrow band in which to construct the
final alignment.
-
44
SECTION 2
Introduction. The geometric design of the highway alignment was done in accordance to AASHTO standards.
AASHTO is an American organisation responsible for setting design standards which all engineering
works must comply to. In roadway design, these include, design speeds, topography, safety and
earthworks. Some design guidelines were also taken from the recommended Manuals &
Guidelines on Road Engineering for Development published by TRL Ltd, specifically, from the Road
Safety Guidelines chapter (pg. 2848 3394).
Design Criteria
Design Traffic Volume
The proposed route is expected to have a projected average daily traffic flow of 400 2000
vehicles. This range was also used for the economic analysis of the narrow bands to access vehicle
operating costs.
Design Speed
Design should be consistent with a specific design speed selected as appropriate for
environmental and speed is a selected speed used to determine the various design features of the
roadway. Geometric design features terrain conditions.(ASSHTO 2001) The design speeds were
chosen with reference to Chapter 5, Local Roads and Streets
In the mapping of the horizontal and vertical alignments, the main objectives were:
The minimisation of cut and fills in order to reduce cost
The avoidance of possibly unstable areas
The safety and comfort of the driver along the entire route
-
45
Grade Different grades were selected throughout the entire route. The grades chosen were defined by AASHTO
guidelines. They are dependent on the terrain and the design speed involved. The maximum grade for the
road designed was 16
Methodology of Route Location The following steps were undertaken in order to plot the centreline of the proposed roadway.
A contour interval spacing of 30m was selected
Circle with radius CI/G was calculated and used to plot out alignment by moving from contour to
contour within the boundary of the radius extension in order to comply with the required maximum
grade of 14%=0.14.
R = CI/G = 25/0.14 215
Where necessary, alignment was plotted along the contours in order to get to a point where
movement from one contour to another is possible within the radius boundary.
Plotting of Horizontal Curves:
The radii of each curve was calculated using the following formula below (sample calculations are
shown in latter sections). The values of e and f were selected based on the design speed.
=2
127( + )
Using AutoCAD, the Fillet tool was used to trim each intersection point with the appropriate radius.
-
46
Plotting of Vertical Curves
Civil 3D was used to generate the profile view of the existing ground, EG. on a grid where the
vertical scale was in 30 m intervals and the horizontal scale at 100m intervals.
The length L of the chord on which the vertical curve is suspended was calculated from the
equation below and was drawn onto the vertical intersection points in AutoCAD.
=
||
The vertical curve was then generated using the ARC command in AutoCAD.
Horizontal Curvature.
A horizontal curve provides a transition between two tangent strips of roadway, allowing a vehicle to
negotiate a turn at a gradual rate rather than a sharp cut. The design of the curve is dependent on the
intended design speed for the roadway, as well as other factors including drainage and friction. These
curves are semicircles as to provide the driver with a constant turning rate with radii determined by the
laws of physics surrounding centripetal force. . There are three main factors to consider in horizontal
curvature:
Superelevation, e Which is the amount of rise seen on an angled cross-section of a road given a
certain run, otherwise known as slope. The presence of superelevation on a curve allows some of
the centripetal force to be countered by the ground, thus allowing the turn to be executed at a
faster rate than would be allowed on a flat surface.
Side Friction factor, f refers to the need for the vehicle to have friction with surface on which it is
travelling.
Velocity, v Depends on the type or terrain, purpose of the road and the location of the roadway.
-
47
Horizontal Alignment
According to the AASHTO design guidelines, the recommended maximum grade for an Urban Collector in
mountainous terrain is 14%
The velocity, side friction and superelevation values were selected based on the design speed which was
in turn selected by terrain type. The design values used in the geometric design of this highway are
summarized below.
Table Showing Selected Design Values
The radius for each curve, R, was calculated using the formula below:
=2
127( + )
The length of the curve, L was calculated using the formula below:
= 2 360
The Tangent length, T, was calculated using the formula below:
= 2
Velocity (km/h) 50
Superelevation, e 0.1
Side Friction, fs 0.16
Maximum Grade, G 14%
Contour Interval, CI 30
Design Values
-
48
Results
Sample Calculation:
Curve #1
Angle of directional change, = 32.88
Design Speed, V = 50 km h
Superelevation, e = 0.10
Friction factor, f = 0.16
Min. Radius =V2
127(e+f)=
202
127(0.10+0.16)= 75.7m rounded to 80 m
Radius used = 135 m
Tangent length, T = R tan (
2) = 135 tan (
32.88
2) = 39.84 m
Beginning of Curve, PC = PI T = [0 + 461.75] 39.84 = [0 + 421.91]
CURVE
POINT OF
INTERSECTIO
N
CENTRAL
ANGLE VELOCITY
SIDE
FRICTION
SUPER
ELEVATION
RADIUS
Min
RADIUS
USED
TANGEN
T
BEGINNING
OF CURVE
LENGTH
OF
CURVE
END OF
CURVE
# PI V f e Rmin R T PC L PT
1 0+461.75 32.88 50 0.16 0.1 80 135 39.84 0+421.91 77.47 0+499.39
2 0+659.16 30.23 50 0.16 0.1 80 135 36.46 0+622.70 71.23 0+693.92
3 0+883.71 7.4 50 0.16 0.1 80 135 8.73 0+874.98 17.44 0+892.42
4 1+104.34 39.86 50 0.16 0.1 80 135 48.95 1+055.39 93.92 1+149.31
5 1+320.67 29.54 50 0.16 0.1 80 135 35.59 1+285.08 69.60 1+354.68
6 1+582.00 15.19 50 0.16 0.1 80 135 18.00 1+564.00 35.79 1+579.79
7 1+765.34 45.19 50 0.16 0.1 80 135 56.18 1+709.16 106.48 1+815.64
8 1+992.33 12.65 50 0.16 0.1 80 135 14.96 1+977.37 29.81 2+007.17
9 2+201.41 23.47 50 0.16 0.1 80 135 28.04 2+173.37 55.30 2+228.67
10 2+410.73 36.47 50 0.16 0.1 80 135 44.48 2+366.25 85.93 2+452.18
11 2+644.30 12.96 50 0.16 0.1 80 135 15.33 2+628.87 30.54 2+659.40
12 2+867.87 60.55 50 0.16 0.1 80 135 78.81 2+789.06 142.67 2+931.73
13 3+150.76 16.62 50 0.16 0.1 80 135 19.72 3+131.04 39.16 3+170.20
14 3+426.93 50 0.16 0.1 80 135 0.00 3+426.96 0.00 3+426.93
HORIZONTAL CURVE DATA
-
49
Arc Length, L =2R
360=
2 135 32.88
360= 77.44 m
End of Curve, PT = PC + L = [0 + 421.91] + 74.44 = [0 + 499.39]
Vertical Alignment Two types of vertical curves exist: Sag Curves and Crest Curves. Sag curves are used where the change in
grade is positive, such as valleys, while crest curves are used when the change in grade is negative, such
as hills. Both types of curves have three defined points: PVC (Point of Vertical Curve), PVI (Point of Vertical
Intersection), and PVT (Point of Vertical Tangency). PVC is the start point of the curve while the PVT is the
end point.
Stopping Sight Distance
Sight distance is dependent on the type of curve used and the design speed. For crest curves, sight
distance is limited by the curve itself, as the curve is the obstruction. For sag curves, sight distance is
generally only limited by headlight range. AASHTO has several tables for sag and crest curves that
recommend rates of curvature, , given a design speed or stopping sight distance. These rates of
-
50
curvature can then be multiplied by the absolute slope change percentage, to find the recommended
curve length, .
Results
Sample Calculation: Curve #1
Design Speed = 50 km h
Type of curve: Crest
Design K value for sag curve = 44
Point of Intersection, PVI = 0 + 540.008
Absolute Difference of Gradients, |A| = |G1 G2| = |3.317 (11.995)| = 8.678
Length of Chord, L = K |A| = 44 8.678 = 555.376 ft = 182.210 m
Beginning of Vertical Curve, BVC = PVI L
2= [0 + 540.008] (
182.210
2) = [0 + 096.355]
CURVEPOINT OF
INTERSECTIONVELOCITY
GRADE OF
TANGENT
GRADE
OF
TANGEN
T
TYPE OF
CURVE
DESIGN
VALUES
DIFFERENCE
IN GRADES
CHORD
LENGTH
BEGINNING
OF CURVE
HALF
CHORD
END OF
CURVE
# PVI V(km) G1 (%) G2 (%) K |A| L BVC L/2 EVC
1 0+540.008 50 -3.317 -11.995 Crest 44 8.678 182.210 0+096.355 91.105 0+278.745
2 1+263.784 50 -11.995 1.292 Sag 44 13.287 278.986 0+698.827 139.493 0+997.113
3 1+624.357 50 1.292 5.223 Sag 64 3.932 82.555 1+215.633 41.277 1+298.187
4 1+986.663 50 5.223 13.841 Sag 64 8.617 180.941 1+414.490 90.470 1+594.430
5 2+714.852 50 13.841 5.066 Crest 64 8.775 184.248 1+659.376 92.124 1+843.624
6 2+950.026 50 5.066 -6.835 Crest 64 11.901 249.882 2+576.869 124.941 2+826.751
7 3+050.348 50 -6.835 -10.899 Crest 44 4.064 85.332 3+199.884 42.666 3+285.216
8 3+265.048 50 -10.899 0.000 Sag 44 10.899 228.846 3+402.507 114.423 3+631.353
VERTICAL CURVE DATA
-
51
End of Vertical Curve, EVC = PVI +L
2= [0 + 540.008] = (
182.210
2) = [1 + 278.745]
Cross Section According to the New Zealand State Highway Geometric Design Manual (2002), the cross section
of a road is a vertical plane at right angles to the road control line (centreline). It is standard
practice for the cross sections to be viewed in the direction of increasing stationing and shows
traverse details of the road way. The locations of the cross sections for the proposed carriageway
are detailed below:
Type of Cross
Section Stationing (km)
Elevation of
Ground Level (m)
Elevation of
Proposed Road (m)
Cut and Fill 0+600 84.12 84.34
Fill 0+700 68.34 75.19
Cut 1+200 65.94 62.98
Fill 1+400 63.34 68.97
Fill 3+000 131.47 133.96
Cut 3+300 118.93 113.67
-
52
Drainage
Provision for adequate drainage is of paramount importance in road design and cannot be
overemphasized. The presence of excess water or moisture within the roadway will adversely affect the
engineering properties of the materials with which it was constructed. Cut or fill failures, road surface
erosion, and weakened subgrades followed by a mass failure are all products of inadequate or poorly
designed drainage. Many drainage problems can be avoided in the location and design of the road. When
the location of a road way is being chosen hydrological factors such as water table level, natural steam and
drainage patterns must be considered. When it comes to road design the cross slope is critical to the design
a long with effect drains and channels to effectively and safely move away from the road protect the road
sublayer.
Pavement cross slope is an important cross-sectional design element. The cross slope drains
water from the roadway laterally and helps minimize ponding of water on the pavement. This prevents
maintenance problems. On roadways with curbed cross sections, the cross slope moves water to a
narrower channel adjacent to the curb, away from the travel lanes, where it can be removed. Cross
slopes that are too steep can cause vehicles to drift, skid laterally when braking, and become unstable
when crossing over the crown to change lanes. These conditions are exacerbated by windy conditions
which are common in Trinidad. Both maximum and minimum criteria exist for cross slope. The cross slope
for the proposed road was selected to be 2% in accordance to the AASHTO 2002 guidelines for
mountainous roadways.
-
53
Safety Features
Soil Failure
As shown on the cross section drawings, the mountainous terrain on which the proposed
alignment is defined resulted in large amounts of cut and fill in some areas which will increase the
risk of soil and slope failure. Therefore, safety features have to be implemented in these areas that
help to minimise soil instability. Below shows some of the problems associated with cutting and
filling on a slope as well as well as safety features to combat them.
Methods that can be used to reduce the risk slope and soil failure include the use of:
-
54
Stepped slopes- however, this greatly increases the amount of earthworks that need to be
performed
Retaining Walls
Crib walls these are much cheaper to construct than retaining walls.
Vegetation Inexpensive and sustainable. Those with deep roots can provide stability for
long periods of time.
Geotextiles Also sustainable Gabion walls cheaper and easier to construct than
retaining walls.
Driver Safety
Safety features implemented for driver safety:
Picture Above shows Guard Rails that should be installed as a safety feature to prevent Roadway
Departure hazards.
-
55
Sign should be clearly displayed along the route alerting drivers to potential hazardous conditions along
the route.
Conclusion
From the analysis performed on the area of study, it was concluded that narrow band 1 would be
used to design the highway for the alternative route form Lady Young Road to Maraval..
The geometric alignment was designed in accordance to the AASHTO highway manual. The
design was found optimum and sustainable design minimizing damage to the environment and
the negative effects to the community. The detailed drawings were produced.
-
56
References
1. Engineering Economic Analysis, Ninth Edition. Newnan Donald G; Eschenbach Ted G;
Lavelle Jerome P. Oxford University Press. 2004
2. Trinidad and Tobago Soils map and Topographical map
3. White, John A., Kenneth E. Case, David B. Pratt and Marvin H. Agee. 1939. Principles of
economic analysis. 4th ed. New York: John Wiley and Sons, Inc.
4. Highway engineering handouts and spreadsheets (V.O.C). Department of Civil
Engineering. University of the West Indies.
5. Civil Engineering Design 2 Handouts. Department of Civil Engineering. University of the
West Indies.
6. Slope Stabilization and Stability of Cuts and Fills.
http://ntl.bts.gov/lib/24000/24600/24650/Chapters/M_Ch11_Slope_Stabilization.pdf
British Columbia. How Vehicle Emissions Affect
Us.http://www.env.gov.bc.ca/epd/bcairquality/topics/vehicle-emissions-impacts.html
7. David Levinson.Superelevation.http://www.learncivilengineering.com/wp-
content/uploads/2012/11/superelevation.pdf
8. http://safety.fhwa.dot.gov/geometric/pubs/mitigationstrategies/chapter3/3_crossslope.c
fm
Appendix