final - section c operating · 9. tc01-9 10. tc01-8 11. tc01-7 12. tc01-6 13. tc01-5 14. tc01-4 15....

84
SCENARIO TITLE: SCENARIO NUMBER: EFFECTIVE DATE: EXPECTED DURATION: REVISION NUMBER: PROGRAM: ESG-NRC-01 5/30/00 1.5 Hours 02 L.O. REQUAL ZXZ |INITIAL LICENSE OTHER REVISION SUMMARY: PREPARED BY: REVIEWED BY: APPROVED BY: APPROVED BY: N/A INSTRUCTOR N/A EP REPRESENTATIVE N/Al TRAINING SUPERVISOR N/A OPS MANAGER OR DESIGNEE N/A DATE N/A DATE N/A DATE N/A DATE

Upload: others

Post on 30-Sep-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

SCENARIO TITLE:

SCENARIO NUMBER:

EFFECTIVE DATE:

EXPECTED DURATION:

REVISION NUMBER:

PROGRAM:

ESG-NRC-01

5/30/00

1.5 Hours

02

L.O. REQUAL

ZXZ |INITIAL LICENSE

OTHER

REVISION SUMMARY:

PREPARED BY:

REVIEWED BY:

APPROVED BY:

APPROVED BY:

N/AINSTRUCTOR

N/AEP REPRESENTATIVE

N/AlTRAINING SUPERVISOR

N/AOPS MANAGER OR DESIGNEE

N/ADATE

N/ADATE

N/ADATE

N/ADATE

Page 2: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-01

A. The Candidates must demonstrate the ability to operate effectively as a team whilecompleting a series of CRITICAL TASKS, which measure the Candidate's ability to safelyoperate the plant during normal, abnormal, and emergency plant conditions.

(Critical tasks within this examination scenario guide are identified with an

A. Raise reactor power with rodsB. Stuck Control Rod, recoverableC. Place RFP in serviceD. APRM FailureE. Loss of A Control Room Ventilation Supply FanF. Turbine TripiATWS/Failure of Turbine Bypass Valves to OpenG. RCIC steam line break on initiation, manual isolation required

The scenario begins with the plant at 35% power. Reactor power is raised to approximately 40%. Duringthe power ascension, a control rod will become stuck. Actions are taken in accordance with theAbnormal Procedures, and the rod is unstuck. The standby Reactor Feed Pump is placed in service. AnAPRM failure occurs requiring bypassing the affected APRM and resetting RPS. The A Control RoomSupply Fan tripson over current, causing a loss of the A Control Area Ventilation System (CAVS). Thestandby CAVS auto starts. After Technical Specifications are addressed, a Main Turbine trip/ReactorScram/ATWS occurs. Due to an EHC logic malfunction, most of the BPVs will fail to open. Theoperators will be required to control pressure using Safety Relief Valves. When RCIC starts, a steamleak develops in the RCIC room. The RCIC system isolation will fail to occur automatically, requiring theoperator to isolate RCIC to stop the steam leak to the secondary containment.

The scenario may be terminated when all rods are "Full In", secondary containment parameters areimproving, and RPV water level is stable between +12.5" and +54".

ESGNRC01 .doc Page 2 of 16 Rev.: 02

Page 3: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-01

Initialize the simulator to IC-05; 35% power, pull sequence step #485.Complete Attachment 1 "Simulator Ready-for-Training/Examination Checklist" of NC.TQ-WB.ZZ-0004(Z)

I Description

1. NONE

I Description

_ 1. Markup IOP-0003 through step 5.4.18.E._ 2. Start the 3r PCP and SCP._ 3. Place E Condensate Filter Demineralizer_ 4. Raise MSL radiation monitor setpoints.

_ 5.

Malfunction # Severity RT#/ET# Delay Ramp Description

1. CD18 202. CD0318353. RC104. RP06

5. RP076. NM11C7. HV02A8. TC03

9. TC01-910. TC01-8

11. TC01-712. TC01-613. TC01-514. TC01-415. RC09 50

Pre-insertPre-insertPre-insertNone/3None/3I/None2/None3/None3/None

3/None

3/None3/None

3/None3/NoneNone/2

22

HIGH ROD WORTHSTUCK CONTROL RODRCIC STM ISOLATION VLVS FAILURE TO AUTO CLOSEHALF CORE ATWS (LEFT SIDE)HALF CORE ATWS (RIGHT SIDE)APRM CHANNELC INOPERABLECONTROL ROOM SUPPLY FAN A TRIPMAIN TURBINE TRIPTURBINE BYPASS VALVE - 9 FAILS CLOSEDTURBINE BYPASS VALVE - 8 FAILS CLOSEDTURBINE BYPASS VALVE - 7 FAILS CLOSEDTURBINE BYPASS VALVE -6 FAILS CLOSEDTURBINE BYPASS VALVE - 5 FAILS CLOSEDTURBINE BYPASS VALVE - 4 FAILS CLOSEDRCIC STEAM LINE BREAK INSIDE RCIC RM 4110

ESGNRC01 .doc Page 3 of 16 Rev.: 02

Page 4: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-01

Singer ID# Value RTET Delay Ramp Description

NONE

Remote# Value RT#/ET# Delay Ramp Description_ 1 NONE

_ 1. LCPNEPOI >= 290 11 CRD DiieWater pressure at 290 psid.Command: DMF CD031835 I/ Removes stuck rod when drve pressure is 290 psid.

2. RCNP > 0.511 RCIC speed3. RP:K14A <1 && RP:KI4B <1 11 RPS scrammed4.

ESGNRC01 .doc Page 4 of 16 Rev.: 02

Page 5: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-01

State shift job assignments.

Hold a shift briefing, detailing instruction to the shift.(Provide crewmembers a copy of the shift turnover sheet)

Unfreeze the simulator and inform the crew;"The simulator is running. You may commence panel walk downs at this time. CRS pleaseinform me when your crew is ready to assume the shift."

Allow sufficient time for panel walk-downs. When informed by the CRS that the crew is ready toassume the shift, make the following announcement:

'The Hope Creek simulator examination is in progress. All personnel not directly associatedwith the examination process please exit the simulator. This exam scenario hascommenced."

Incorporate/evaluate the following activities during the scenario exam:

ESGNRCO1.doc Pang A; of I .. sy- W WI I V Mev.: UZ

Page 6: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-01

Note: It asked if the reactivityworth for the rods beingwithdrawn is expected,respond yes as the RE, asmentioned on the TurnoverSheet.

Note: If asked, respond as theRE that a 1 notch insertattempt may be made and therod recovered if it does movein.

* CRS orders power ascension withcontrol rods in accordance withRE's guidance.

* RO withdraws control rods inaccordance with RE's guidanceand Section 5.3 of HC.OP-SO.SF-0001.

* RO notices rod stuck and informsCRS.

* CRS orders the RO to attempt tofree the stuck control rod inaccordance with HC.OP-AB.ZZ-0104.

* RO:- attempts to operate the drive in

both directions,- ensures drive water flow

fluctuates normally,- ensures proper operation of the

SETTLE, INSERT, andWITHDRAW lights,

- and reports failure of rod tomove.

* RO raises drive water pressure in50 psig increments, and attemptsto move the control rod. ROreports that the rod has moved.

* RO returns drive water pressure tonormal operating range (260-270psid).

* CRS orders PO to place B RFP inservice.

Ensure CDO31835 is removedwhen drive pressure exceeds290 psid.

Note: If the RE is asked forrod history, inform the crewthat this rod has a history ofsticking.

ESGNRC01 .doc Page 6 of 16 Rev.: 02

Page 7: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-01

PO places B RFP in service inaccordance with Section 5.6 ofHC.OP-SO.AE-0001.- Verify the pump's discharge

valve open- Close Low Pressure Supply Stop

Valve Below Seat Drain- Select DEMAND indicated on the

In-service and the standby RFP- INC the standby RFP demand

until it is matched with theoperating RFP demand

- Select Auto

Crew notices APRM failure, Rodout motion blocks, and RPS halfscram signal.

CRS orders actions to be taken inaccordance with HC.OP-AB.ZZ-0108 and HC.OP-AR.ZZ-0009.- Enters HC.OP-AB.ZZ-0300 and

executes it concurrently. Orderscrew to monitor for coreinstabilities.

- Ensures all appropriateImmediate Operator Actions arecomplete.

CRS orders the RO to bypass theC APRM and reset RPS.RO bypasses APRM inaccordance with Section 5.3.4 ofHC.OP-SO.SE-0001.RO resets RPS in accordance withSection 5.3 of HC.OP-SO.SB-0001CRS evaluated TechnicalSpecifications 3.3.1 and 3.3.6 forapplicability.

Tracking LCO.

ESGNRC01 .doc Page 7 of 16 Rev.: 02

Page 8: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-01

Note: As ABEO report, theonly alarm is "Evaporator LowWater Flow" on 1AK400. Ifasked, as the Shift Electricianreport, thermal overload trip ofthe A CRS fan breaker 52-471062.

NOTE:Seven day LCO.

* RO/PO recognizes trip of "A"Control Room Ventilation viaannunciators E5-D2, E6-B1, and1 OC651 E bezel indications andinforms CRS.

* CRS enters and implementsHC.OP-AB.ZZ-01 54.

* RO/PO dispatches ABEO toinvestigate trip of "A" train ofcontrol room ventilation.

* CRS directs maintenance toinvestigate trip of "A" train ofcontrol room ventilation.

* RO/PO places/verifies "B" train ofcontrol room ventilation inservice IAW HC.OP-SO.GK-0001 and CRS direction.

* OS/CRS evaluates Tech Spec3.7.2 and determines applicabilityof action 3.7.2.a.

* Crew recognizes Main Turbine Tripand informs CRS.

* CRS directs actions in accordancewith HC.OP-EO.ZZ-0101.

* RO places and locks the Rx modeswitch to shutdown.

ESGNRCOI .doc Page 8 of 16 Rev.: 02

Page 9: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-01

* RO performs scram actions inaccordance with Section 5.2 ofHC.OP-SO.SB-0001.- Ensure all rods are in- Ensure RPS Mode Switch in

Shutdown- Ensure SDV Vent and Drain

Valves close- Ensure RPS Logic Channels

are tripped- Ensure IRMs and SRMs are

inserted(ing) into the Reactor- Select IRM on Recorder Input- Inform CRS of APRM power

> or < 4%• CREW determines all control rods

are NOT inserted to or beyondposition 02 via CRIDS, SPDSand/or NSSS computer, andinforms CRS.

• CRS directs actions in accordancewith HC.OP-EO.ZZ-0101A.

* RO/PO verifies RRCS has initiatedif an initiation signal is reached andinforms CRS.

* RO/PO manually initiates RRCS(ARI) if not already initiated.

* RO/PO notices failure of mostBPVs to open and informs CRS.

* CRS orders PO to control pressureusing SRVs.

* PO inhibits ADS lAW CRSdirection.

* CRS orders SLC initiated.

* RO/PO initiates SLC lAW CRSdirection.* Crew manually starts "A" and"B" SLC pump before suppressionpool temperature reaches 11 OF.

(K/A 295037 EA1.04 4.5/4.5)

ESGNRCOI .doc Page 9 of 16 Rev.: 02

Page 10: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-01

NOTE:CRS may direct a morerestrictive level control band.

SCPs and RFPs may trip dueto low suction pressures. Thecrew make take actions torestore a RFP to service.

NOTE:Support EO-322 bypass.

* CRS implements HC.OP-EO.ZZ-0101A, ATWS-RPV Control, tocontrol Rx power and directs:- control of RPV water level

between -50" and -190"- scram actions

* CRS orders HC.OP-EO.ZZ-0322implemented and HPCI injectionsecured until HC.OP-EO.ZZ-0322is implemented or -129" isreached.

* PO operates HPCI in accordancewith CRS direction.

* If Suppression Pool Temperaturereaches 110F., and reactorpower is > 4%, the crewintentionally lowers RPV waterlevel until:- Rx power drops below 4%

OR- RPV water level reaches

-129 inchesOR

- All SRVs remain closed andDRWL press remains below1.68#.

* RO/PO terminate injection asdirected by the CRS.

* RO/PO commence feeding theRPV and maintains RPV level asdirected by the CRS.

* CRS determines that water levelcannot be maintained above -190inches and directs:- Terminating injection except

from SLC, CRD, and RCIC.- Emergency Depressurization in

accordance with HC.OP-EO.ZZ-0202. (Open 5 ADS valves.)

* RO/PO terminate injection asdirected.

* PO opens 5 ADS valves.

Note: These actions are onlyif water level cannot bemaintained above -190inches, then RPV EmergencyDepressurization is required inaccordance with HC.OP-EO.ZZ-0202.

ESGNRC01.doc Page 10 of 16 Rev.: 02

Page 11: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-01

* CRS directs raising injection toraise RPV level when RPVpressure drops to 200 psig.

• RO/PO commence injecting intothe RPV as directed.

* Crew restores level to above -190inches, and maintains level above-190 inches but less than -129inches until the Reactor isshutdown.

* Crew notices RCIC steamleak/isolation signal following RCICsystem initiation, and informs theCRS.

* CRS orders RCIC system isolatedmanually.

* PO isolates RCIC system manuallyin accordance with section 5.2.1 ofHC.OP-SO.SM-0001.* Crew initiates actions toterminate source of leakage andshuts HV-F008 and/or F007 beforeRCIC room 4110 temperatureexceeds 250°F

(K/A 217000 A2.15 3.8/3.8)* CRS directs actions in accordance

with HC.OP-EO.ZZ-0103 tomonitor Secondary Containmentparameters to ensure RCIC isisolated.

* RO/PO trips "A" and "B" RR pumpsIAW CRS direction.

• Crew directs bypassing the RWMto enable the insertion of controlrods using RMCS.

• RO/PO restores I E breakers ifdirected.

* CRS directs restoration of CRD iflost on 1 E breaker trip.

• RO restores CRD as directed.

* Crew directs implementation ofHC.OP-EO.ZZ-0322, Core SprayInjection Valve Override.

ESGNRC01 .doc Page I 1 of 16 Rev.: 02

Page 12: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-01 -

Support crew requests forimplementation of HC.OP-EO.ZZ-0322, and HC.OP-EO.ZZ-320.

Inform crew that HC.OP-EO.ZZ-0320 is completed.When SDV is drained, clearMalfunction RP06 and RP07to allow full Rx scram.

* Crew directs implementation ofHC.OP-EO.ZZ-0320 and resetsRPS.

* CRS directs RO/PO to place RHR'A' 'B' in suppression pool coolinglAW HC.OP-EO.ZZ-0102, whenavailable.

* CRS directs RO to arm anddepress RPS scram pushbuttonswhen overhead alarm C6-E4, CRDScram Discharge Volume NotDrained, is extinguished.

* RO initiates a manual scram byarming and depressing RPS scrampushbuttons.

* CREW observes control rodmovement via full core display,CRIDS, 4-rod display, and/orNSSS computer.

* * CRS directs implementation ofHC.OP-EO.ZZ-0320, resets RPS,and initiates manual Rx scramsuntil all control rods are fullyinserted.

(K/A 295037EA1.01 4.6/4.6)* CRS directs SLC be secured, exits

HC.OP-EO.ZZ-0101A, ATWS-RPVControl, enters HC.OP-EO.ZZ-0101 and directs R01/PO tomaintain RPV level between +12.5"to +54".

* RO removes "A" and "B" SLCpumps from service.

* CRS directs RO/PO to commencean RPV depressurization and cooldown and to maintain cool downrate below 900 F/hr.

ESGNRCO1.doc Page 12 of 16 Rev.: 02

Page 13: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-01

V

ESGNRCOI .doc Page 13 of 16 Rev.: 02

Page 14: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-01 -

A. ES-301 Preparation of Operating TestsB. ES-604 Dynamic Simulator Requalification Examination StandardC. K/A CatalogD. JTA ListingE. Hope Creek Generating Station Probabilistic Risk AssessmentF. Technical SpecificationsG. Emergency Plan (ECG)H. Alarm Response Procedures (Various)1.

J.K.

L.

M.N.0.

P.

Q.R.S.

T.U.

V.

W.

X.

Y.

Z.

NC.TQ-TC.ZZ-0028HC.OP-SO.SF-0001HC.OP-SO.AE-0001HC.OP-SO.SE-0001HC.OP-SO.SB-0001HC.OP-AB.ZZ-0104HC.OP-AB.ZZ-0108HC.OP-AB.ZZ-0154HC.OP-AB.ZZ-0300HC.OP-EO.ZZ-0101HC.OP-EO.ZZ-0101AHC.OP-EO.ZZ-0102HC.OP-EO.ZZ-0103/4HC.OP-EO.ZZ-0202HC.OP-EO.ZZ-0320HC.OP-EO.ZZ-0322HC.OP-AZ.ZZ-0002SH.OP-DD.ZZ-0004

Conduct of Simulator TrainingReactor Manual Control System OperationFeedwater System OperationNuclear Instrumentation System OperationReactor Protection System OperationStuck Control RodLPRM/APRM MalfunctionLoss of HVACReactor Power OscillationsRPV ControlATWS-RPV ControlPrimary Containment ControlReactor Building and Rad Release ControlEmergency RPV DepressurizationPerforming ARI and RPS InterlocksHPCI Core Spray Injection Valve OverrideHope Creek Operations StandardsOperations Standards

ESGNRC01.doc Page 14 of 16 Rev.: 02

Page 15: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-01

rr

ESG-NRC-01 I 00

1.* * Crew manually starts "A" and "B" SLC pump before suppression pool temperature reaches IIOF.(KIA 295037 EA1.04 4.5/4.5)

If the SLC pumps are not started, reactor power will not be reduced sufficiently to prevent significant heataddition to the suppression pool. Once suppression pool temperature reaches 110 F with the reactor notshutdown and SLC not injecting, the capability to inject the hot shutdown boron weight before reaching theheat capacity temperature limit is jeopardized. If suppression pool temperature cannot be maintainedbelow the heat capacity temperature limit, emergency depressurization will be required. Given the ATWSconditions, executing emergency depressurization is a degraded control strategy.

2.* * Crew directs implementation of HC.OP-EO.ZZ-0320, resets RPS, and initiates manual Rx scrams untilall control rods are fully inserted.(K/A 295037EA1.01 4.6/4.6)

Implementation of HC.OP-EO.ZZ-0320 provides the only method for control rod insertion and substantialnegative reactivity addition. It is critical for the crew to implement this procedure and to initiate actions toallow the scram discharge volume to drain. Failure to initiate this action would result in significant heataddition to the suppression pool and possible complications with the heat capacity temperature limit.Insertion of additional manual scrams will fully insert control rods and terminate the ATWS event.

3.* * Crew initiates actions to terminate source of leakage and shuts HV-F008 and/or F007 before RCICroom 4110 temperature exceeds 250°F(K/A 217000 A2.15 3.8/3.8)

The crew will have indication of a valid isolation signal to the RCIC system with a failure to isolate condition.Initiating actions to isolate the system before exceeding the 250-degree limit allows adequate time for thecrew to respond to the failure and manually isolate RCIC. 250F was chosen to ensure that adequate corecooling, containment integrity, safety of personnel, and continued operability of equipment required toperform EOP actions were available.

ESGNRC01 .doc Page 15 of 16 Rev.: 02

Page 16: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

Hope Creek Generating Station Turnover SheetToday's Date

Oncoming Shift: Days [X] Nights [OPERATIONAL CONDITION: 1, 35% RTP, MAIN GEN. OUTPUT: 334 MWe

RISK MATRIX COLOR: Green RIVER TEMPERATURE: 650F'D' CHANNEL WORK WEEK - BLUE Folders

Major activities accomplished last shift:* Commenced Reactor startup lAW HC.OP-IO.ZZ-0003, complete through step 5.4.18.E. The startup follows Hot

Standby operation in accordance with HC.OP-lO.ZZ-0007.* Currently at step 485 of the Rod Pull List. RE guidance is to expect slightly higher than normal rod worth for these

rods.* I&C is investigating problems with a C RFP Vibration Probe. Do not start up C RFP until troubleshooting is

complete.Major activities scheduled for this shift:* Continue with Reactor startup. Withdraw control rods to end of RWM Group 49(step 500). Place B RFP in service.

Problems .

Protected .Equipment .

U

Update StatusA

Action Plans I

Active LCO's

Follow-up Operability Assessments (CRFA) Assigned

Compensatory Actions in effect (Required by CROD/CRFA for Operability)

Reactivity Controls:.

Standby Safety Systems:.

Balance of Plant:.

Electrical:* CRIDS 'Excess MVARS" point is INOP; contact Load Dispatch for info regarding this point.Cooling Water Systems:0

Ventilation:

Administrative:

Page 16 of 16 Rev.: 01

Page 17: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

SCENARIO TITLE:

SCENARIO NUMBER:

EFFECTIVE DATE:

EXPECTED DURATION:

REVISION NUMBER:

PROGRAM:

ESG-NRC-02

5/30/00

1.5 Hours

02

| | L.O. REQUAL

| X | INITIAL LICENSE

LIIII OTHER

REVISION SUMMARY:

PREPARED BY:

REVIEWED BY:

APPROVED BY:

APPROVED BY:

N/AINSTRUCTOR

N/AEP REPRESENTATIVE

N/ATRAINING SUPERVISOR

N/AOPS MANAGER OR DESIGNEE

N/ADATE

N/ADATE

N/ADATE

N/ADATE

Page 18: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG-NRC-02

A. The Candidates must demonstrate the ability to operate effectively as a team whilecompleting a series of CRITICAL TASKS, which measure the Candidate's ability to safelyoperate the plant during normal, abnormal, and emergency plant conditions.

(Critical tasks within this examination scenario guide are identified with an

A. Raise Reactor power with Recirculation flowB. Perform Core Spray Surveillance/Trip of Core Spray PumpC. Recirculation Pump RunawayD. Condenser level transmitter failureE. Recirculation Pump TripF. Recirculation loop leak/Loss of power to A and B vital bussesG. C RHR Pump suction strainer clogging/Failure of D RHR pump to auto start

= EAI SIIV= .

The scenario begins with the plant at 93% power. The operators will raise Reactor power to 100% withRecirculation Pumps. Core Spray surveillance is required for the shift. The Core Spray Pump will tripduring the test. B Recirculation Pump Speed control fails and the B Recirculation Pump speed rises to itsmaximum setting. The Reactor Operator will have to take control of the A Recirculation Pump speed tolower power below 100%. The selected Main Condenser level transmitter fails high. The operator mustrecognize the failure and select a good level transmitter or Main Condenser Hotwell level will lower and aloss of all feedwater will eventually occur. A Recirculation Pump trip requires action to be taken for singleloop operations. A leak will develop from the Recirculation System requiring plant shutdown. When theMain Generator trips, off-site power is lost, and the A and B EDG fail resulting in a loss of the 1 0A401and 1 OA402 buses. The D EDG output breaker fails to automatically close in on the 1 OA403 bus. CRHR pump suction strainer becomes clogged reducing the C RHR Pump's output. This requires that theoperator close the D EDG output breaker and inject with D RHR Pump in order to maintain RPV waterlevel.

The scenario may be terminated when RPV water level is being controlled above 12.5 inches, andprimary containment parameters are improving.

Page 2 of 14 Rev.: 02

Page 19: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

FSG-NRC-O2

Initialize the simulator to IC-01; 100% power, MOL, Xe equilibrium, pull sequence step #727.Complete Attachment 1 'Simulator Ready-for-Training/Examination Checklist" of NC.TQ-WB.ZZ-0004(Z)

I Description

1. NONE

Description

1. Reduce Reactor power to 93% with Recirc.

2. Complete HC.OP-IS.BE-0001 through step 5. 1.10 for a regular surveillance.3. Ensure Condenser Level Transmitter B is selected.

pM i I166, .,6 V Im ~6

Malfunction # Severity RT#/ET# Delay Ramp Description1. DG01A

2. DG02B

K> __ 3. RH05C4. DG08D

5. RH08D

6. CS01A7. RRO8B

8. MC13B 100

9. RR11B

10. RR31B2 0-75

11. EG12

12. RR31A2 50

Pre-insertPre-insert

Pre-insert

Pre-insertPre-insert

1/None2/None3/None

4/None5/None

None/1None/2

DIESEL GENERATOR A FAILURE TO STARTDIESEL GENERATOR B FAILURERHR LOOP C LOW FLOWDIESEL GENERATOR D BREAKER FAILURE TO AUTO CLOSERHR SYSTEM D AUTO INJECTION FAILED TO ENERGIZECORE SPRAY PUMP A TRIPREACTOR RECIRC PUMP SPEED CONTROLLER B FAILS HIGHCONDENSER LVL TRANSMITTER LT-1657B FAILURERECIRC PUMP B TRIP

600 VARIABLE LOCALOSS OF ALL OFF-SITE POWERVARIABLE LOCA

Page 3 of 14 Rev.: 02

Page 20: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG-NRC-02

Singer ID# Value RTIET Delay Ramp Description

1. NONE

2.

_ 3.

Remt A#, V ..ET# wt Mely R DRemote# Value RT#IET# Delay Ramp Description

1. NONE

1. TC:TRIP //Main Turbine Trip

2. RRLWR <= -129 11 RPV water level -129 inches

Page 4 of 14 Rev.: 02

Page 21: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG-NRC-02

State shiftjob assignments.

Hold a shift briefing, detailing instruction to the shift.(Provide crewmembers a copy of the shift turnover sheet)

Unfreeze the simulator and inform the crew;"The simulator is running. You may commence panel walk downs at this time. CRS pleaseinform me when your crew is ready to assume the shift."

Allow sufficient time for panel walk-downs. When informed by the CRS that the crew is ready toassume the shift, make the following announcement:

"The Hope Creek simulator examination is in progress. All personnel not directly associatedwith the examination process please exit the simulator. This exam scenario hascommenced."

Incorporate/evaluate the following activities during the scenario exam:

Page 5 of 14 Rev.: 02

Page 22: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG-NRC-02

N'4ote: repor Trom Tield that allpersonnel are ready for pumpstart.

* CRS orders the RO to raiseReactor power using Recirc flowin accordance with Section 5.2 ofHC.OP-SO.BB-0002.

* RO raises Reactor power withRecirc by using the Master SpeedController

* RO contacts Turbine Bldg EO tomonitor Recirc MG Lube Oiltemperatures.

* CRS directs PO to complete theCore Spray surveillance HC.OP-IS.BE-0001.

* PO performs 'A" Core SprayPump surveillance IAW HC.OP-IS.BE-0001:- Starts A Core Spray pump- Throttles F015A to establish

3200 gpm* PO recognizes trip of A Core

Spray pump on motor overcurrentand informs the CRS.

* CRS directs PO to secure fromthe test.

* PO secures from the test inaccordance with HC.OP-IS.BE-0001.

* CRS refers to T/S 3.5.1.a.1 forfailed Core Spray surveillance.

* Crew recognizes B RR Pumprunaway by flow and powerindications, and informs the CRS.

Use CRIDS page 95 for CSflow.

Note: Support crew requestsfor placing the breaker in PTLand restoring keep-fill.7 day LCO (Loop consideredinop until keep-fill restored.)Support crew efforts to fill andvent the A CS loop.

-

Page 6 of 14 Rev.: 02

Page 23: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

Note: Respond as l&C totroubleshoot RR Pumpproblem.

When requested toinvestigate, as l&C reportafter a short time delay that itappears the speed controlsignal has failed upscale.

Support shift requests for RRpump speed adjustment.Increaseldecrease "A" RRspeed using Remote RRO9.

* CRS implements HC.OP-AB.ZZ-0204 and directs actions tostabilize Rx power by runningback the non-effectedRecirculation pump.

* RO reduces the speed of the non-effected Recirculation pump tostabilize power below 100%.

* CRS directs action to ensure RRloop flow mismatch is within 5% ofrated core flow lAW tech spec3.4.1.3.

* RO/PO notifies TBEO and l&C ofscoop tube problem and directsinvestigation.

* IF local adjustment of the scooptube is desired, CRS directsactions IAW HC.OP-SO.BB-0002

* RO/PO maintains constantcommunication with field at alltimes during scoop tube localadjustment.

24 Hour Report

* CRS evaluates Licensing Basisfor exceeding 102% power.

* CRS may review or request theOS to review ECG Section11.1.3.a.

* Crew recognizes failure ofcondenser level transmitter fromCRIDS alarm point, 10C651Aindications, and informs CRS.

* CRS directs the PO to selectanother condenser leveltransmitter.

Per r-I.P.Ur-AIR.Z./-uuu4,actions for alarms A6-F1 (2,3)is to ensure proper controlleroperation.

Page 7 of 14 Rev.: 02

Page 24: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

Note: If the level transmitter isnot noticed, eventuallyCONDENSATE TRAINTROULBLE alarms will bereceived. If no action is taken,a low level trip of the PCPs,SCPs, RFPs, and a reactorscram will eventually occur.

* PO selects the directedcondenser level transmitter.

* Crew recognizes trip of the BRecirculation Pump and informsCRS.

* CRS orders the immediateoperator actions in accordancewith HC.OP-AB.ZZ-0112.- Enter HC.OP-AB.ZZ-0300,

monitor for thermal hydraulicinstabilities

* CRS orders the subsequentoperator actions in accordancewith HC.OP-AB.ZZ-01 12.- Close the discharge valve on

the tripped pump for 5minutes then reopen.

- Send operator to MG SetPanel

- Notify RE and l&C.- Insert control rods if

necessary* RO closes the discharge valve for

the B Recirculation Pump for 5minutes, and then reopens thevalve.

* RO/PO contacts Bldg. EO tocheck the MG Set Panel.

* RO/PO contacts RE and l&C.* RO inserts control rods as

necessary in accordance with theInterim Core Operating Instructionto suppress APRM Upscalealarms.

* CRS evaluates TechnicalSpecifications 3.4.1.

Page 8 of 14

Single loop requirements.

Rev.: 02

Page 25: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

l *

Note: The operators may nothave time to take theseactions due to the rapidlyrising Drywell pressure.

* Crew recognizes LOCA viaannunciator C6-B11, rising drywellpressure, and informs CRS.

* CRS orders actions to be taken inaccordance with HC.OP-AB.ZZ-0201.- Increase Drywell cooling- Monitor RR pump seals, SRV

position, Drywell sumps,Drywell conditions

* PO increases Drywell cooling bystarting all available cooling fans.

* CRS orders RR to minimum andReactor scram.

Page 9 of 14 Rev.: 02

Page 26: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG-N rC.-n

* RO performs scram actions inaccordance with Section 5.2 ofHC.OP-SO.SB-0001.- Ensure all rods are in- Ensure RPS Mode Switch in

Shutdown- Ensure SDV Vent and Drain

Valves close- Ensure RPS Logic Channels

are tripped- Ensure IRMs and SRMs are

inserted(ing) into the Reactor- Select IRM on Recorder Input- Inform CRS of APRM power

> or < 4%* RO reduces RR pump speed to

minimum and scrams theReactor.

* CRS enters and directs HC.OP-EO.ZZ-0101, RPV Control, anddirects actions to:- Verify scram actions- Control RPV water level

above +12.5"- Stabilize Rx pressure below

1037#* Crew determines RPV level,

pressure, and containmentparameters and informs CRS.

* Crew recognizes LOP, failure of Aand B EDGs, and the failure of DEDG to load, and notifies theCRS.

* RO/PO verifies start of ECCS andEDGs.

* CRS enters and directs HC.OP-EO.ZZ-0102, PrimaryContainment Control, to controlprimary containment parameters.

* CRS orders restoration of A, BEDGs, and closure of D EDGoutput breaker in accordance withHC.OP-AB.ZZ-01 35.

* PO attempts to restore A and BEDGs and closes D EDG outputbreaker.

Verify ET-2 active(LOP, failure ofA EDG to start, B EDGs starts andtrips, and D EDG to fail to load)when Main Turbine trips.

NOTE:Primary Containmentparameters cannot becontrolled because the "A"and/or "B" EDGs areinoperable.

Ensure ET-2 active when levelreaches -129 inches.

Page 10 of 14 Rev.: 02

Page 27: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

* * RO/PO closes "D" EDG outputbreaker 52-40407 andreenergizes 10A404 vital bus.

(K/A 262001 A2.03 3.9/4.3)

. PO observes indications ofsuction strainer clogging for the DRHR pump and informs CRS.

* PO recognizes failure of the DRHR pump to auto start andrecommends the starting of DRHR pump to maintain RPV level.

• CRS orders D RHR pump startedto maintain RPV level.

. * CREW starts the "D" RHRpump and opens HV-FO17D tomaintain RPV water level above-190".

(K/A 295031 EA1.01 4.4/4.4)PO starts D RHR pump andopens FO17D to inject into theRPV.

Page 11 of 14 Rev.: 02

Page 28: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG-NRC-02

A. ES-301 Preparation of Operating TestsB. ES-604 Dynamic Simulator Requalification Examination StandardC. K/A CatalogD. JTA ListingE. Hope Creek Generating Station Probabilistic Risk AssessmentF. Technical SpecificationsG. Emergency Plan (ECG)H. Alarm Response Procedures (Various)I. NC.TQ-TC.ZZ-0028

J. HC.OP-AB.ZZ-01 12K. HC.OP-AB.ZZ-0135L. HC.OP-AB.ZZ-0201M. HC.OP-AB.ZZ-0204N. HC.OP-AB.ZZ-03000. HC.OP-EO.ZZ-0101P. HC.OP-EO.ZZ-01 02Q. HC.OP-IS.BE-0001R. HC.OP-SO.BB-0002S. HC.OP-AZ.ZZ-0002T. SH.OP-DD.ZZ-0004

Conduct of Simulator TrainingRecirculation Pump TripLoss of Offsite PowerDrywell High Pressure/Loss of Drywell CoolingPositive Reactivity AdditionReactor Power OscillationsRPV ControlPrimary Containment ControlA&C Core Spray Pumps-AP206&CP206-lnservice TestReactor Recirculation System OperationHope Creek Operations StandardsOperations Standards

Page 12 of 14 Rev.: 02

Page 29: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG-NRC-02

ESG-NRC-02 / 00

1.* * Crew closes "D" EDG output breaker 52-40407 and reenergizesI 0A404 vital bus.(K/A 262001 A2.03 3.9/4.3)

The "D" EDG output breaker fails to auto-close following the LOP. With the failure of the "A" and"B" EDGs, the Crew must establish injection to the RPV to maintain adequate core cooling. Thiswill require injection with the "D" RHR Pump. To use the 'D" RHR Pump, power must be restoreto the 10A403 vital bus.

2.* * CREW starts the "D" RHR pump and opens HV-FO17D to maintain RPV water level above

-190".(K/A 295031 EAI.01 4.4/4.4)

The Crew must manually start and align injection to restore adequate core cooling by coresubmergence.

Page 13 of 14 Rev.: 02

Page 30: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG-NRC-02Hope Creek Generating Station Turnover Sheet

Today's DateOncoming Shift: Days [X] Nights [

OPERATIONAL CONDITION: 1, 93% RTP, MAIN GEN. OUTPUT: 1090 MWeRISK MATRIX COLOR: Green RIVER TEMPERATURE: 650F

A' CHANNEL WORK WEEK - BLUE FoldersMajor activities accomplished last shift:* Reduced Reactor power due to a Minimum Generation Alert* Completed preparations for HC.OP-IS.BE-0001 through step 5.1.10.Major activities scheduled for this shift:* Raise reactor power to 100% with recirc.* Complete HC.OP-IS.BE-0001.

SyslEquip .Problems .Protected .Equipment .

Update Status a

Action Plans

Active LCO's

q FRI M n W

Follow-up Operability Assessments (CRFA) Assigned

Compensatory Actions in effect (Required by CROD1CRFA for Operability)

Reactivity Controls:

Standby Safetv Svstems:

Balance of Plant:

Electrical:

* CRIDS 'Excess MVARS' point is INOP; contact Load Dispatch for info regarding this point.Cooling Water Systems:S

Ventilation:

Administrative:0

Page 14 of 14 Rev.: 02

Page 31: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

SCENARIO TITLE:

SCENARIO NUMBER:

EFFECTIVE DATE:

EXPECTED DURATION:

REVISION NUMBER:

PROGRAM:

ESG-NRC-03

5/30/00

1.5 Hours

02

| |1 L.O. REQUAL

| X | INITIAL LICENSE

I | OTHER

REVISION SUMMARY:

PREPARED BY: N/AINSTRUCTOR

N/ADATE

REVIEWED BY: N/AEP REPRESENTATIVE

N/ADATE

APPROVED BY:

APPROVED BY:

N/ATRAINING SUPERVISOR

N/AOPS MANAGER OR DESIGNEE

-

N/ADATE

N/ADATE

Page 32: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-03

The Candidates must demonstrate the ability to operate effectively as a team whilecompleting a series of CRITICAL TASKS, which measure the Candidate's ability to safelyoperate the plant during normal, abnormal, and emergency plant conditions.

(Critical tasks within this examination scenario guide are identified with an U*".)

A. HPCI In-service TestB. HPCI oil leakC. CRD pump tripD. Recirculation Flow unit failureE. Recirculation System Speed Control Fails LowF. Loss of 1CD482/TACS recoveryG. MSIV Closure/Reactor scram/stuck control rodsH. RCIC flow controller failure in Auto

The scenario begins with the plant at 100% power. HPCI In-service test in progress. HPCI develops anoil leak during operation, requiring the system shutdown and declared inoperable. The CRD Pump tripson overcurrent. The standby CRD Pump is placed in service and the system returned to normal. Then aRecirculation Flow Unit fails. After actions to bypass the Flow Unit and resetting RPS are complete, the ARecirculation Pump speed control signal fails. When power is stabilized, the crew will be directed toreduce the speed of the operating pump to meet Technical Specification requirements. An inverterfailure occurs that requires the operators to transfer TACS to the standby SACS loop. The operator willhave to re-open the TACS common supply valves in order to continue plant operation.

An inadvertent MSIV closure causes the Reactor to scram. 4 control rods do not insert on the scram.ATWS control strategies are used to insert these control rods. The MSIV closure and inoperable HPCImake RCIC operation required to maintain RPV water level above -190 inches. A RCIC flow controllerfailure requires the operator to take manual control of RCIC to control level.

The scenario may be terminated when all control rods are fully inserted, RPV water level is beingcontrolled above 12.5 inches, and primary containment parameters are under control.

ESGNRCO3.doc Page 2 of 18 Rev.: 01

Page 33: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-03

_ Initialize the simulator to IC-01; 100% power, MOL, Xe equilibrium, pull sequence step #727.Complete Attachment 1 'Simulator Ready-for-Training/Examination Checklist" of NC.TQ-WB.ZZ-0004(Z)

I Description

__ 1. NONE

_ 2.

_ 3.

Description

1. Set up HPCI surveillance test HC.OP-IS.BJ-0001 through step 5.1.16. Lower power by 10 Mwe._ 2. Place B RHR in Suppression Pool cooling.

3. Lower Suppression Pool level to 75 inches._ 4. Obtain DL-26 Attachment 3m.

Malfunction # Severity RT#/ET# Delay Ramp Description_ 1.

2.

3.4.5.6.7.

8.

9.

10.__ _ II.

12.13.

CD032203CD034259CD031835CD031823HP06MCD10ARR19B1 0RR01A

ED09C2

MS15RC03

Pre-insertPre-insert

Pre-insertPre-insert

1/None2/None3/None

4/None

5/None

None/2None/1

STUCK CONTROL ROD 22-03STUCK CONTROL ROD 42-59STUCK CONTROL ROD 18-35STUCK CONTROL ROD 18-23HPCI AUX OIL PUMP OIL LINE BREAKCRD PUMP A FAILURERECIRC FLOW TRANSMITTER B FAILURERECIRC SYSTEM A SPEED CONTROL FAILS LOWLOSS OF 120 VAC CLASS 1 E INVERTER CD482SPURIOUS GROUP I ISOLATION (MSIV CLOSURE)RCIC TURBINE SPEED CONTROL FAILURE

ESGNRCO3.doc Page 3 of 18 Rev.: 01

Page 34: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-03

Singer ID# Value RT/ET Delay Ramp Description

1. NONE

2.

Remote# Value RT#/ET# Delay Ramp Description

_ 1 RR07A OFF None/4 POSITIONER A POWER SWITCH2.3.4.

5.

1. RCNP >= 0.5 I/RCIC pump speed

_ 2. ISTRIGGER-ACT(7) > 0 11 ETARRAY(3) > 0 1 RT-6 activated or RPS scram_ 3. RP:K14A <1 && RP:K14B <1 11 RPS scrammed

4. ZARRS621(5) <= 0.65 11 RECIRC PUMP SPEED APPROXIMATELY 65%5.

ESGNRCO3.doc Page 4 of 18 Rev.: 01

Page 35: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-03

State shiftjob assignments.

Hold a shift briefing, detailing instruction to the shift.(Provide crewmembers a copy of the shift turnover sheet)

Unfreeze the simulator and inform the crew;"The simulator is running. You may commence panel walk downs at this time. CRS pleaseinform me when your crew is ready to assume the shift."

Allow sufficient time for panel walk-downs. When informedby the CRS that the crew is ready toassume the shift, make the following announcement:

"The Hope Creek simulator examination is in progress. All personnel not directly associatedwith the examination process please exit the simulator. This exam scenario hascommenced."

Incorporate/evaluate the following activities during the scenario exam:

ESGNRCO3.doc Page 5 of 18 Rev.: 01

Page 36: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-03

Note: It needed, supportstopwatch operation.

* PO continues HPCI surveillancetest in accordance with HC.OP-IS.BJ-0001.

* PO Starts the HPCI turbine andestablishes proper system flow.- Opens Vacuum Pump

discharge to Main Condenservalve

- Starts Vacuum Pump- Throttles Test Bypass Valve

(F008) for approximately 18-20 seconds

- Opens cooling water isolationvalve (F059)

- Simultaneously opens F001and starts the Auxiliary OilPump while timing theopening of the F001

- Observe proper operation ofHPCI

- Adjust flow controller and/orF008 to achieve desired testoperation

* PO notices indications of an HPCIoil leak and informs the CRS.

* CRS orders the PO to securefrom the HPCI surveillance.

* PO secures HPCI and restoresthe system to normal operationswith the exception(s) given by theCRS.

Respond as EO to HPCI whendirected and report an oil leak.Oil is still spraying into theroom(if the oil pump is still inoperation).

Support opening of oil pumpbreaker if requested.14 day LCO * CRS declares HPCI inoperable

and evaluates TechnicalSpecifications 3.5.1.c todetermine required actions.

ESGNRCO3.doc Page6 of 18 Rev.: 01

Page 37: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-03

• Crew recognizes the trip of the ACRD pump and informs the CRS.

* CRS directs action in accordancewith HC.OP-AB.ZZ-0105.- Start the standby CRD pump

* RO starts the B CRD pump andrestores the CRD system inaccordance with Section 5.2.7HC.OP-SO.BF-0001.- Dispatches an operator to

close the B CRD pumpdischarge valve, or takesmanual control of the CRDFCV (FIC-600) and closesthe FCV, prior to starting theB CRD Pump

- When the pump is operating,the equipment operatorslowly opens the B CRDpump discharge valve or theoperator restores the CRDFCV to normal (Auto)operation

ESGNRCO3.doc Page 7 of 18 Rev.: 01

Page 38: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-03

Note: When crew requestsl&C to adjust B RR Flow Unitoutput, raise severity ofRR19BI to 100%, and reportas I&C that the signal hasbeen adjusted.

Tracking LCO

* Crew recognizes failure of the BRR Flow Unit and reports this tothe CRS.

* CRS directs actions inaccordance with HC.OP-AB.ZZ-0108, and C6-Dl of HC.OP-AR.ZZ-001 1.- Monitor for thermal hydraulic

instabilities in accordance withHC.OP-AB.ZZ-0300.

- Bypass the B RR flow unit- When I&C has adjusted Flow

Unit output, reset RPS* RO resets RPS in accordance

with HC.OP-SO.SB-0001 byplacing the Al, A2, Bi, and B2Trip Logic key switchesmomentarily to RESET.

* CRS refers to TechnicalSpecification 3.3.6.

* Crew recognizes failure of the ARR Pump Runback Circuit andinforms the CRS.

* CRS directs monitoring ofReactor power, level andpressure

* RO reports status of Reactorpower, level, and pressure.

* CRS refers to TechnicalSpecification 3.4.1.3.

* CRS contacts l&C for assistance.

2 hour LCO to restore speeddifferential to less than 5%.Note: Respond as I&C; takeapproximately 6 hours totroubleshoot the problem.

ESGNRCO3.doc Page 8 of 18 Rev.: 01

Page 39: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-03

Note: May be required toprompt the power reduction.Call as Operations Managerand direct power reduction.

Respond, if required, thatbrake cannot be disengaged.Note: Respond as RE,reduction of B RR Pumpspeed to approximately 65%.No control rod motion shouldbe required and 15% powerchange should not beexceeded.TS 4.4.5

Note: May be required toprompt the power reduction.Call as Operations Managerand direct power reduction.

S ,

CRS may direct actions to locallyoperate the A RR Pump ScoopTube.

CRS contacts RE for guidance.

CRS may direct Chemistry andRad Pro to take Tech Specsamples due to the rapid powerchange. (Conservative)CRS directs power reduction inaccordance with RE's guidanceand Section 5.2 of HC.OP-IO.ZZ-0006.RO reduces B RR Pump speed inaccordance with RE's guidanceand Section 5.2 of HC.OP-SO.1BB-0002.

<-V

ESGNRCO3.doc Page 9 of 18 Rev.: 01

Page 40: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-03

* Crew recognizes loss of aninverter and the loss of TACS,and reports this to the CRS.

* Indications of the loss of theinverter include:- Loss of "C" ECCS status

indications- Loss of C EDG indications- Loss of C Channel electrical

system status indicators on1 OC651 D

* CRS directs actions to be taken inaccordance with HC.OP-AB.ZZ-0136.- Monitor Reactor power, level,

pressure, and Main Generatoroutput.

- Determine which inverter isfailed.

* RO reports power, level,pressure, and Main Generatoroutput steady.

* CRS directs actions to be taken inaccordance with HC.OP-AB.ZZ-0148.- Verifies no break in the TACS- Complete TACS transfer to the

B STACS loop- Open TACS isolation valves

HV-2522E AND F.- Open HV-2512B and close HV-

2512A.* PO opens HV-2522E, HV-2522F

and HV-2512B, and closes HV-2512A and HV-2522A/2496A.

* Verifies transfer IAW Section 5.7of HC.OP-SO.EG-0001.

* Crew recognizes loss of RBVS byobserving Reactor Bldg dp at 0',RBVS & Wing Area HVAC paneltrouble alarm(E6-C5), andinforms the CRS

ESGNRCO3.doc Page 10 of 18 Rev.: 01

Page 41: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-03

Note: If excessive sluicingoccurs between the SACSloops, a total loss of TACSmay occur. The crew will thenbe required to scram thereactor in accordance withAB-148. If the plant isscrammed, ensure ET-2 isactive.

8 hour LCO for 1CD482restoration,EDG inoperable requiresST.ZZ-0001 and evaluation ofother Tech Specs. CRSreviews HC.OP-AP.ZZ-0108for applicability of supportingsystems and declares thosepumps supplied from the EDGas inoperable. CS and RHR.3.0.3 entry is required due toHPCI inop, a CS, and a RHRsystem inoperable.Note:Support SACS and SSWpump realignments asrequired. B SSW pump startrequired to maintain TACSTemperatures.

* CRS directs actions to restoreReactor Bldg dp in accordancewith HC.OP-AB.ZZ-01 15:- Place FRVS in service

* PO places FRVS in service inaccordance with CRS directionsand Section 5.3 of HC.OP-SO.GU-0001.- Starts 4 FRVS Recirculation

Fans (indication for C fan islost)

- Starts 1 FRVS vent fan* CRS declares 1 CD482, and C

EDG, C RHR, C CS inoperableand refers to TechnicalSpecification 3.8.3.1, 3.8.1.1, and3.5.1.

'K

ESGNRCO3.doc Page I11 of 18 Rev.: 01

Page 42: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-03

l lW z m i l i * Crew determines the closure ofthe MSIVs and the Reactorscram, and reports this to the

* CRS directs scram actions betaken.

* RO places and locks the ModeSwitch in Shutdown and performsscram actions.

* RO performs scram actions inaccordance with Section 5.2 ofHC.OP-SO.SB-0001.- Ensure all rods are in- Ensure RPS Mode Switch in

Shutdown- Ensure SDV Vent and Drain

Valves close- Ensure RPS Logic Channels

are tripped- Ensure IRMs and SRMs are

inserted(ing) into the Reactor- Select IRM on Recorder

Input- Inform CRS of APRM power

> or < 4%

* CREW determines all control rodsare NOT inserted to or beyondposition 02 via CRIDS, SPDSand/or NSSS computer, andinforms CRS.

NOTE: * CRS implements HC.OP-EO.ZZ-CRS may direct a more 0101A, ATWS-RPV Control, torestrictive level control band. control Rx power and directs:

- control of RPV water levelbetween +54" and -190"

- scram actions

ESGNRCO3.doc Page 12 of 18 Rev.: 01

Page 43: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

EG- NR-C-nl

* PO recognizes failure of RCICflow controller in Automatic andinforms the CRS.

CRS directs PO to take manualcontrol of RCIC to maintain RPVlevel and SRVs to control Reactorpressure.

* * CREW takes manual controlof RCIC flow controller to controlRPV water level IAW HC.OP-EO.ZZ-0101A, and maintainRPV water level greater than -190" when the Rx is not shutdown.

(K/A 295037 EA2.02 4.1/4.2)* PO takes manual control of RCIC

and maintains RPV water levelas directed.

* PO takes control of the SRVsand maintains RPV pressure asdirected.

* RO/PO verifies RRCS hasinitiated if an initiation signal isreached and informs CRS.

* CRS enters HC.OP-EO.ZZ-0102if Suppression Pool temperatureexceeds 95F, and directs PO toplace RHR in Suppression PoolCooling

* PO places RHR in SuppressionPool Cooling as directed inaccordance with Section 5.5 ofHC.OP-SO.BC-0001.

* CREW manually initiates RRCS(ARI) if not already initiated.

* PO inhibits ADS IAW CRSdirection.

* CRS directs SLC initiation beforesuppression pool temperaturereaches 150OF

ESGNRCO3.doc Page 13 of 18 Rev.: 01

Page 44: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-03

Clear CD032203, CD034259,CD031835, and CD031823 whenthe SDV is full. (Use SDV monitorto determine when the SDV isfull.) This will allow rod movementby RMCS or EOP-320.

Note: Support completion ofHC.OP-EO.ZZ-0320 and informthe crew when completed in thefield.

* RO/PO initiates SLC pumpswhen directed.

* CRS directs bypassing the RWMto enable the insertion of controlrods using RMCS.

* RO bypasses RWM using thebypass key switch, takes manualcontrol of the CRD FCV toestablish near-normal systemflow, and inserts control rods.

* CRS may direct implementationof HC.OP-EO.ZZ-0320 andresets RPS.

* CRS directs RO to arm anddepress RPS scram pushbuttonswhen overhead alarm C6-E4,CRD Scram Discharge VolumeNot Drained, is extinguished.

* RO initiates a manual scram byarming and depressing RPSscram pushbuttons. (If ControlRods are were not insertedpreviously.)

* CREW observes control rodmovement via full core display,CRIDS, 4-rod display, and/orNSSS computer.

* * Crew inserts control rods viaRMCS and/or, when the SDV isdrained (annunciator C6-E4clear), Crew implements amanual scram IAW HC.OP-EO.ZZ-0320 to initiate rodinsertion.

(K/A 295037 EA1.01 4.6/4.6)(K/A 295037 EA1.07 3.9/4.0)* CRS directs RO to remove "A"

and "B" SLC pumps fromservice(if in operation).

ESGNRC03.doc Page 14 of 18 Rev.: 01

Page 45: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-03

* CRS secures SLC (if initiated)and exits HC.OP-EO.ZZ-OIOIA,ATWS-RPV Control, entersHC.OP-EO.ZZ-0101 and directsRO/PO to maintain RPV levelbetween +12.5" to +54".

* CRS directs RO/PO tocommence an RPVdepressurization and cooldownand to maintain cooldown ratebelow 900 F/hr.

ESGNRCO3.doc Page 15 of 18 Rev.: 01

Page 46: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-03

A. ES-301 Preparation of Operating TestsB. ES-604 Dynamic Simulator Requalification Examination StandardC. K/A CatalogD. JTA ListingE. Hope Creek Generating Station Probabilistic Risk AssessmentF. Technical SpecificationsG. Emergency Plan (ECG)H. Alarm Response Procedures (Various)1.J.

L.M.N.0.

P.

Q.R.S.

T.

U.

V.

W.

X.

NC.TQ-TC.ZZ-0028HC.OP-AB.ZZ-0105HC.OP-AB.ZZ-0108HC.OP-AB.ZZ-01 15HC.OP-AB.ZZ-0136HC.OP-AB.ZZ-0148HC.OP-AP.ZZ-0108HC.OP-EO.ZZ-0101HC.OP-EO.ZZ-0101AHC.OP-EO.ZZ-0102HC.OP-EO.ZZ-0320HC.OP-EO.ZZ-0322HC.OP-IS.BJ-0001

HC.OP-SO.GU-0001HC.OP-AZ.ZZ-0002SH.OP-DD.ZZ-0004

Conduct of Simulator TrainingLoss of CRD Regulating FunctionLPRM/APRM MalfunctionLoss of Reactor Building IntegrityLoss of 120 VAC InverterTurbine Auxiliaries Cooling System MalfunctionOperability Assessment and Equipment Control ProgramRPV ControlATWS-RPV ControlPrimary Containment ControlPerforming ARI and RPS InterlocksHPCI Core Spray Injection Valve OverrideHPCI Main and Booster Pump Set-OP204&0P217-ln-ServiceTestFiltration, Recirculation and Ventilation System OperationHope Creek Operations StandardsOperations Standards

ESGNRCO3.doc Page 16 of 18 Rev.: 01

Page 47: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-03

ESG-NRC-03 I 00

1.* CREW takes manual control of RCIC flow controller to control RPV water level IAW HC.OP-EO.ZZ-0101A, and maintain RPV water level greater than -190" when the Rx is not shut down.

(K/A 295037 EA2,02 4.1/4.2)

Sufficient injection capability remains to maintain reactor water level above -190 IN. If the crewcannot maintain reactor water level above this level, emergency depressurization is required.Under ATWS conditions, this is a degraded control strategy.

2.* Crew inserts control rods via RMCS and/or, when the SDV is drained (annunciator C6-E4clear), Crew implements a manual scram lAW HC.OP-EO.ZZ-0320 to initiate rod insertion.(K/A 295037 EA1.01 4.6/4.6)

(KIA 295037 EA1.07 3.9/4.0)

Implementation of HC.OP-EO.ZZ-0320 and/or manual insertion of control rods via the reactormanual control system will insert control rods (at least partial insertion for manual scram) toterminate the ATWS event and prevent fuel damage caused by a local criticality.

ESGNRCO3.doc Page 17 of 18 Rev.: 01

Page 48: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

Hope Creek Generating Station Turnover SheetToday's Date

Oncoming Shift: Days [X] Nights [ ]OPERATIONAL CONDITION: 1,100% RTP, MAIN GEN. OUTPUT: 1092 MWe

RISK MATRIX COLOR: Green RIVER TEMPERATURE: 650F'B' CHANNEL WORK WEEK - BLUE Folders

Major activities accomplished last shift:* Complete HPCI [ST HC.OP-IS.BJ-0001; procedure is complete through step 5.1.16, with system fill and vent

complete. All support personnel/test equipment are ready for test completion. Suppression pool level is at 75" tosupport the test.

.

Major activities scheduled for this shift:* Complete IST HC.OP-IS.BJ-0001. Local observation of HD-FV-0001Operation is not required.

OysimquipProblems .

Protected -

Equipment .U

Update Status

Action Plans

Follow-up Operability Assessments (CRFA) Assigned

Compensatory Actions in effect (Required by CRODICRFA for Operability)

4DFirWI N

Reactivity Controls:.

Standby Safety Systems:* B RHR in suppression pool cooling to support HPCI test.Balance of Plant:

Electrical:

* CRIDS "Excess MVARS" point is INOP; contact Load Dispatch for info regarding this point.Cooling Water Systems:0

Ventilation:.

Administrative:

Page 18 of 18 Rev.: 01

Page 49: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

SCENARIO TITLE:

SCENARIO NUMBER:

EFFECTIVE DATE:

EXPECTED DURATION:

REVISION NUMBER:

PROGRAM:

ESG-NRC-04

5/30/00

1.5 Hours

02

| | L.O. REQUAL

I X |Z INITIAL LICENSE

I I| OTHER

REVISION SUMMARY:

PREPARED BY:

REVIEWED BY:

APPROVED BY:

APPROVED BY:

N/AINSTRUCTOR

N/AEP REPRESENTATIVE

N/ATRAINING SUPERVISOR

N/AOPS MANAGER OR DESIGNEE

. .N/A

DATE

N/ADATE

N/ADATE

N/ADATE

Page 50: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-04

A. The Candidates must demonstrate the ability to operate effectively as a team whilecompleting a series of CRITICAL TASKS, which measure the Candidate's ability to safelyoperate the plant during normal, abnormal, and emergency plant conditions.

(Critical tasks within this examination scenario guide are identified with an

JI~~AO EVENS

A. Synchronize Main GeneratorB. Raise Reactor power with control rodsC. RWM FailureD. Control Rod DriftE. False Main Generator Core Monitor alarmF. Loss of Reactor Building VentilationG. RWCU System leak/Failure to isolateH. Steam leak inside the drywell/Downcomer failure/ Emergency DepressurizationI. 2 ADS SRVs fail to open

The scenario begins with the plant at 22% power. A Reactor Startup is in progress in accordance withHC.OP-lO.ZZ-0003. The crew will synchronize the Main Generator to the grid and raise power withcontrol rods. During control rod withdrawal, the Rod Worth Minimizer will fail. The crew will bypass theRWM and take actions to allow the startup to continue in accordance with Technical Specifications. Afteractions for the control rod drift are complete, a Main Generator Core Monitor alarm is received. The crewwill have to determine that the alarm is false. A damper in the Reactor Building Ventilation System(RBVS) fails closed causing a loss of RBVS. FRVS will be required to be placed in service. A leakdevelops from the RWCU system. The isolation valves will fail to automatically close. The crew will takeactions to isolate the leak. A major steam leak occurs inside the drywell. Due to a Downcomer failurethe Drywell pressure will raise to the action required region of the Pressure Suppression Pressure curve.This requires an Emergency Depressurization of the RPV in accordance with the Emergency OperatingProcedures. 2 ADS valves will fail to open. The crew will open two additional SRVs.

The scenario may be terminated when all control rods are fully inserted, RPV water level is beingcontrolled above 12.5 inches, and primary containment parameters are under control.

ESGNRCO4.doc Page 2 of 15 Rev.: 02

Page 51: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-04

Initialize the simulator to IC-07; 22% power, MOL, Xe equilibrium, pull sequence step #377.Complete Attachment 1 uSimulator Ready-for-Training/Examination Checklist" of NC.TQ-WB.ZZ-0004(Z)

I Description

_ 1. NONE

2.

Description

_ 1. Make the Main Generator ready IAW HC.OP-SO.MA-0001, step 5.2.1.2. Pull rods through step 388

_ 3. Close HV-1459A, B, AND C, HTRS 1&2/DC, S/U AND OPR VENTS

Malfunction # Severity RT#/ET# Delay Ramp Description

1. CU 1A

2. CU11B

3. AD02DC

4. AD02BC

5. CD19A

6. CD187. CD025027

8. RS019. EGO2

10. CU03

11. MS01

12. PCO4

13.

Pre-insertPre-insertPre-insert

Pre-insertPre-insert

10 Pre-insertPre-insert

1/None2/None

100 4/None

30 5/None5/None

RWCU VLV F001 FAILURE TO AUTO CLOSERWCU VLV F004 FAILURE TO AUTO CLOSESAFETY RELIEF VALVE D FAILURESAFETY RELIEF VALVE B FAILURECONTROL RODS BOUNCING ON SCRAM (2-4)HIGH ROD WORTHCONTROL ROD DRIFTS OUTRWM WITHDRAW BLOCKMAIN GENERATOR CORE MONITOR ALARM

120 RWCU SYSTEM LEAK720 STEAM LINE BREAK IN THE DRYWELL

PRIMARY CONTAINMENT DOWNCOMER FAILURE

ESGNRCO4.doc Page 3of 15 Rev.: 02

Page 52: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-04

Singer ID# Value RT/ET Delay Ramp

_ 1. 1A159 E OFF 3/None

2. 1A159 F ON 3/None

-

Description

DI HD-9414A OPEN-INBD EXH-REACTOR BUILDING -

DI HD-9414A CLOSE-INBD EXH-REACTOR BUILDING

Remote#

1. NONE

2.

Value RT#IET# Delay Ramp Description

1. ZCLCINSE > 0 && ZLLCWHIT(083) > 0 II Insert push button depressed and rod 50-27 selectedCommand: DMF CD025027

2. ZCLCCINS > 0 && ZLLCWHIT(083) > 0 11 Cont. Insert push button depressed and rod 50-27 selectedCommand: DMF CD025027

ESGNRCO4.doc Page 4 of 15 Rev.: 02

Page 53: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-04

v State shiftjob assignments.

Hold a shift briefing, detailing instruction to the shift.(Provide crewmembers a copy of the shift turnover sheet)

Unfreeze the simulator and inform the crew;"The simulator is running. You may commence panel walk downs at this time. CRS pleaseinform me when your crew is ready to assume the shift."

Allow sufficient time for panel walk-downs. When informed by the CRS that the crew is ready toassume the shift, make the following announcement:

"The Hope Creek simulator examination is in progress. All personnel not directly associatedwith the examination process please exit the simulator. This exam scenario hascommenced."

Incorporate/evaluate the following activities during the scenario exam:

ESGNRCO4.doc j Page 5 of 15 Rev.: 02

Page 54: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-04

CMAiNAl * CRS directs synchronizing themain generator in accordancewith HC.OP-SO.MA-0001.

* PO synchronizes the maingenerator in accordance withHC.OP-SO.MA-0001.

o * CRS directs continuation ofpower ascension in accordancewith HC.OP-IO.ZZ-0003 and RE

__ guidance.* RO withdraws control rods in

accordance with Section 5.2, or5.3, of HC.OP-SO.SF-0001 andRE guidance.

gFiu i|5 1 * RO observes failure of the RWM; and informs the CRS.

* CRS directs actions inaccordance with Section 4.3 ofHC.OP-AB.77-01 06:

- Check operation of RWM(Attempt to reinitialize/diagnostic test)

- Notify l&C- Bypass RWM

Note: Respond as Reactor * CRS reviews TechnicalEngineer or additional Specification 3.1.4.1 and directsqualified member of the plant bypassing the RWM instaff if required. accordance with Section 5.2 of

HC.OP-SO.SF-0003.* RO places the bypass switch for

the RWM in BYPASS.* CRS directs continuation of

startup.

ESGNRCO4.doc Page 6 of 15 Rev.: 02

Page 55: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

Fqr - NRC-04

* RO notices rod continuing tomove outward by observing RPIand overhead alarmC6-E3, and informs the CRS.

* RO informs CRS of actions to betaken in accordance withHC.OP-AR.ZZ-001 1.

* CRS directs actions inaccordance with HC.OP-AB.ZZ-0102, and HC.OP-AB.ZZ-0204:

- Insert control rods, insequence, as necessary toreduce Reactor power

* CRS directs actions inaccordance with HC.OP-AR.ZZ-0011:

- Apply a continuous insertsignal

* RO applies an insert signal; rodinserts; and informs the CRS.

* CRS directs removal of insertsignal.

* RO removes the insert signal,notices rod remains at its currentposition, and notifies the CRS.

* CRS confers with the RE todetermine actions for continuingReactor startup.

* CRS refers to TechnicalSpecification 3.1.3.1.b forapplicability

Ensure CD025027 clearswhen the insert push button isdepressed.

Note:As the RE inform the CRS thatyou are evaluating rodrecovery and that you willprovide guidance soon.

ESGNRCO4.doc Page 7 of 15 Rev.: 02

Page 56: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESr - NRC-04

Respond as TB to requests ofCore Monitor Status. Flow isnormal.

* RO/PO reports Gen CoreParticulate High alarm E1-D2and indications on the Coremonitor to the CRS.

* PO depresses the Core MonitorFilter push button for 15-20seconds and observes CoreMonitor indication and reports tothe CRS indications of a falseCore Monitor alarm.

* RO/PO reports alarm E6-C5,closure of HD-9414A, andindications of the loss of theRBVS to the CRS.

* CRS directs placing FRVS inservice in accordance withHC.OP-AB.ZZ-01 15 and HC.OP-AR.ZZ-001 9.

* PO places FRVS in service inaccordance with section 5.3 ofHC.OP-SO.GU-0001.

- Closes remaining isolationdampers

- Places an FRVS Vent Fan inMANUAL and starts theFRVS Vent Fan puts back inAuto Lead

- Starts 4 FRVS Recirc Fans

Note:Support removal of RBVS.

ESGNRCO4.doc Page 8 of 15 Rev.: 02

Page 57: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-04

* RO/PO reports RWCU alarmsD3-B3, Cl-A2, D3-B3, Cl-C2,and indications of the RWCUsystem to the CRS.

* RO reports failure of F001 andF004 to automatically isolate tothe CRS.

Note:The RWCU system may bemanually isolated before theleak detection system timerstime out.

* CRS directs manual isolation ofthe RWCU system in accordancewith HC.OP-AB.ZZ-01 16, andHC.OP-AB.ZZ-01 14:

- Close F001 and F004- Close SV-4310 and 4311

* RO closes F001, F004, SV-4310and 4311.

* * CREW isolates the RWCUsystem by shutting HV-F001and/or HV-F004 within two

- "minutes of confirming theautomatic isolation failure.

(K/A 223002 A4.06 3.6/3.7)(K/A 223002 A4.01 3.6/3.5)* CRS directs actions for RWCU

system isolation in accordancewith HC.OP-AR.ZZ-0008.

Conductivity samplingrequirements. Containmentisolation valves (if failure toauto isolate is noticed).Isolation instrumentation.

* CRS refers to TechnicalSpecification 3.4.4, 3.6.3, and3.3.2

ESGNRCO4.doc Page 9 of 15 Rev.: 02

Page 58: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-04

* Crew recognizes DRWLpressure at 1.68# viaannunciators A7-D4, C5-B5, &LOCA initiation signals andinforms CRS.

* CREW determines RPV waterlevel, pressure, and containmentparameters and informs CRS.

* CRS enters HC.OP-EO.ZZ-0101,RPV Control and directs actionsto:- Control RPV water level

above 12.5".- Verify ECCS actuates- Verify PCIS/NSSSS

isolations* RO places and locks the Rx

mode switch in SHUTDOWN.* RO inserts SRMs and IRMs and

informs CRS.* RO performs scram actions in

accordance with Section 5.2 ofHC.OP-SO.SB-0001.- Ensure all rods are in- Ensure RPS Mode Switch in

Shutdown- Ensure SDV Vent and Drain

Valves close- Ensure RPS Logic Channels

are tripped- Ensure IRMs and SRMs are

inserted(ing) into the Reactor- Select IRM on Recorder

Input- Inform CRS of APRM power

> or < 4%* RO/PO verifies initiation of HPCI

and RCIC and informs CRS.

ESGNRCO4.doc Page 10 of 15 Rev.: 02

Page 59: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-04

* Crew determines that all controlrods are not fully inserted viaSPDS, CRIDS, and/or NSSScomputer, and reports thepositions of those rods to theCRS.

* Crew determines that theReactor is shutdown under allconditions without boron.

* CRS directs closure of MSIVs tominimize the cool down rate.

* RO closes MSIVs as directed.

* RO/PO controls ReactorPressure and level as directed

* CRS enters and directs HC.OP-EO.ZZ-0102, PrimaryContainment Control, to controlprimary containment parameters.

* CREW monitors RPV waterlevel, pressure, and containmentparameters and informs CRS.

* CRS directs securing ReactorRecirculation Pumps if inoperation.

* RO secures ReactorRecirculation Pumps.

NOTE: . If reactor water level reaches-129", CRS directs action to

Level may not reach -129". inhibit ADS.

* PO inhibits ADS IAW CRSdirection.

* RO/PO verifies start of ECCSand EDGs and informs CRS.

* CRS directs actions to spray theDrywell in accordance withHC.OP-EO.ZZ-01 02.

* PO places the RHR system inDrywell Sprays as directed inaccordance with Section 5.6 ofHC.OP-SO.BC-0001.

ESGNRCO4.doc Page 1 1 of 15 Rev.: 02

Page 60: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-04

NOTE:

Crew should consider anticipatingEmergency Depressurizationusing BPVs if the Main Condenseris available

* CRS recognizes suppressionchamber pressure is in, orcannot be maintained below, therequired action zone on thePressure Suppression PressureCurve.

* CRS implements HC.OP-EO.ZZ-0202, EmergencyDepressurization, and directsaction to open five ADS valves.

* PO reports to the CRS that 2ADS valves failed to open.

* CRS directs the opening of 2additional SRVs.

* PO opens the SRVs directed.

* * CREW opens at least fourSRVs to emergencydepressurize the Rx beforesuppression chamber pressurereaches 55 psig, or within 2minutes of exceeding the PSPcurve.

(K/A 295030 EK3.01 3.8/4.1)* RO/PO restores level to 12.5-54

inches.

ESGNRCO4.doc Page 12 of 15 Rev.: 02

Page 61: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-04

A.B.C.D.E.F.G.H.1.J.K.L.M.N.0.P.Q.R.S.T.U.V.

W.X.

ES-301 Preparation of Operating TestsES-604 Dynamic Simulator Requalification Examination StandardK/A CatalogJTA ListingHope Creek Generating Station Probabilistic Risk AssessmentTechnical Specifications IEmergency Plan (ECG)Alarm Response Procedures (Various)NC.TQ-TC.ZZ-0028HC.OP-AB.ZZ-0106HC.OP-AB.ZZ-01 14HC.OP-AB.ZZ-0204HC.OP-AB.ZZ-01 16HC.OP-AB.ZZ-0126HC.OP-SO.BC-0001HC.OP-SO.GU-0001HC.OP-SO.MA-0001HC.OP-SO.SF-0001HC.OP-SO.SF-0003HC.OP-EO.ZZ-0101HC.OP-EO.ZZ-0102HC.OP-EO.ZZ-0202SH.OP-DD.ZZ-0004HC.OP-AZ.ZZ-0002

Conduct of Simulator TrainingRod Control System MalfunctionLoss of Primary Containment IntegrityPositive Reactivity AdditionContainment Isolations and Recovery for an IsolationAbnormal Releases of Gaseous RadioactivityResidual Heat Removal System OperationFiltration, Recirculation and Ventilation System OperationMain Generator & Exciter Operation & SwitchingReactor Manual Control System OperationRod Worth Minimizer OperationRPV ControlPrimary Containment ControlEmergency RPV DepressurizationOperations StandardsHope Creek Operations Standards

ESGNRCO4.doc Page 13 of 15 Rev.: 02

Page 62: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-04

ESG-NRC-04 1 00

1.* * CREW isolates the RWCU system by shutting HV-FOO1 and/or HV-F004 within two minutes

of confirming the automatic isolation failure.(K/A 223002 A4.06 3.6/3.7)(KIA 223002 A4.01 3.6/3.5)

The RWCU System has failed to isolate automatically. Failure of the Crew to manually isolate thesystem will result in a bypass of the Primary Containment boundary and release of radioactivematerials to the Reactor Building. Two minutes is deemed adequate time to affect isolation fromthe time confirmation of failure of the automatic isolation function is received.

2.* CREW opens at least four SRVs to emergency depressurize the Rx before suppression chamberpressure reaches 55 psig, or within 2 minutes of exceeding the PSP curve.

(K/A 295030 EK3.01 3.8/4.1)

With suppression chamber pressure approaching the maximum EOP-102 limit of 65 psig, thereactor must be emergency depressurized to reduce the RPV stored energy with the ultimate goalof preserving primary containment integrity. 55 psig, and within 2 minutes of exceeding the PSPcurve, was chosen as a reasonable performance value for a Crew. This value is reached underthe conditions of this scenario approximately 10 min. after the LOCA, which is the time assumedfor no operator action in the FSAR.

ESGNRCO4.doc Page 14 of 15 Rev.: 02

Page 63: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

Hope Creek Generating Station Turnover SheetToday's Date

Oncoming Shift: Days [ X ] Nights ]OPERATIONAL CONDITION: 22% RTP, MAIN GEN. OUTPUT: 0 MWe

RISK MATRIX COLOR: GREEN RIVER TEMPERATURE: 650F'D' CHANNEL WORK WEEK - YELLOW

'> Major activities accomplished last shift:* HC.OP-IO.ZZ-0003 complete up to step 5.4.7.* HC.OP-SO.MA-0001 complete through step 5.2.12* Unit synch in progress with turbine at 1800 rpm.Major activities scheduled for this shift:* Synch to grid and raise MVARs to 175 (per LD) IAW HC.OP-IO.ZZ-0003 (Salem units I & II are on-line).* RE guidance is to W/D rods IAW the pull sheet from step #389 to 30% power; then contact RE for further guidance.

Continuous rod withdrawal has been authorized.

SysiEquipProblems

:

Protected .Equipment

Update Status

Action Plans

Follow-up Operability Assessments (CRFA) Assigned

I . , _ _ I I I

I --Reactivity Controls:.

Standby Safety Systems:0

Balance of Plant:

Electrical:

* CRIDS "Excess MVARS" point is INOP; contact Load Dispatch for info regarding this point.Cooling Water Systems:.

Ventilation:0

Administrative:.

Page 15 of 15 Rev.: 02

Page 64: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None
Page 65: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

SCENARIO TITLE:

SCENARIO NUMBER:

EFFECTIVE DATE:

EXPECTED DURATION:

REVISION NUMBER:

PROGRAM:

ESG-NRC-05

5/30/00

1.5 Hours

02

I L.O. REQUAL

| X | INITIAL LICENSE

I I OTHER

REVISION SUMMARY:

PREPARED BY:

REVIEWED BY:

N/AINSTRUCTOR

N/AEP REPRESENTATIVE

N/ADATE

N/ADATE

APPROVED BY:

APPROVED BY:

N/ATRAINING SUPERVISOR

N/AOPS MANAGER OR DESIGNEE

N/ADATE

.

N/ADATE

Page 66: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-05

A. The Candidates must demonstrate the ability to operate effectively as a team whilecompleting a series of CRITICAL TASKS, which measure the Candidate's ability to safelyoperate the plant during normal, abnormal, and emergency plant conditions.

(Critical tasks within this examination scenario guide are identified with an *fl)

311 W, =A. Reduce Reactor power with Recirculation SystemB. Remove Reactor Feed Pump from serviceC. Failure of RPS EPA Breaker Undervoltage DeviceD. Recirculation Pump Dual Seal FailureE. Failure of 3 RD stage Air Ejector Flow, SJAE isolation.F. Seismic event, RHR rooms flood, unisolable Torus leak, Emergency DepressurizationG. Mode Switch failure (RPS contacts) on Scram

SCbENqARIO SUMAY e~. ~.~.

The scenario begins with the plant at 100% power. The B RFP will be removed from service formaintenance. The A RPS MG set EPA Breaker undervoltage device fails causing a loss of the A RPSbus. This requires a transfer to the alternate power supply and an RPS reset. Once RPS is reset, aRecirculation Pump dual seal failure occurs requiring isolation of the affected pump and preparations forSingle Loop operations. The 3 RD stage Air Ejector Flow transmitter fails requiring the Standby Steam JetAir Ejector to be placed in service. A Seismic Event causes a leak in the C RHR suction piping. The leakis unisolable. Due to a floor drain check valve problem, water will also fill up the A RHR pump room.This requires a plant shutdown. Due to the lowering Suppression Pool level, a scram and subsequentEmergency Depressurization is needed. The Mode Switch contacts fail on the scram.

The scenario may be terminated when all control rods are fully inserted, and RPV water level is beingcontrolled above 12.5 inches.

ESGNRCO5.doc Page 2 of 19 Rev.: 02

Page 67: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-05

_ Initialize the simulator to IC-01; 100% power, MOL, Xe equilibrium, pull sequence step #727.Complete Attachment 1 "Simulator Ready-for-Training/Examination Checklist" of NC.TQ-WB.ZZ-

__ 0004(Z)

| Description

_ 1 NONE

2.

1. NONE

2.

Malfunction # Severity RT#/ET# Delay Ramp Description_ 1. RP08A

2. RR05B

3. RR06B

4. MC06B

5. PC07A

6. PCO67. RH09C

8. RH09A

9.

1/None100 2/None100 2/None

3/None4/None

5-20 4/None4/None4/None

255

300420600

RPS EPA BREAKER A TRIPRECIRC PUMP B INBOARD SEAL FAILURERECIRC PUMP B OUTBOARD SEAL FAILURESJAE B StEAM SUPPLY FAILURESEISMIC EVENTSUPPRESSION POOL BREAKRHR PUMP ROOM C FLOODEDRHR PUMP ROOM A FLOODED

ESGNRCO5. doc Page 3 of 19 Rev.: 02

Page 68: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-05

Singer ID# Value RT/ET Delay Ramp Description

_ 1. 3S22 A OFF Pre-insert OVDI RPS MODE SWITCH-SHUTDOWN

2. 3S22 B OFF Pre-insert OVDI RPS MODE SWITCH-REFUEL

3. 3S22 C OFF Pre-Insert OVDI RPS MODE SWITCH-STARTUP&HOT STDY4. 3S22 D ON Pre-insert OVDI RPS MODE SWITCH-RUN

5.

E AUV Th 4dUA

Remote# Value RT#/ET# Delay Ramp Description

1. NONE

2.

EN]MMW', , , - I :

1 NONE

2.

ESGNRCO5.doc Page 4 of 19 Rev.: 02

Page 69: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-05

State shiftjob assignments.

Hold a shift briefing, detailing instruction to the shift.(Provide crewmembers a copy of the shift turnover sheet)

Unfreeze the simulator and inform the crew;"The simulator is running. You may commence panel walk downs at this time. CRS pleaseinform me when your crew is ready to assume the shift."

Allow sufficient fime for panel walk-downs. When informed by the OS/CRS that the crew is ready toassume the shift, make the following announcement:

"The Hope Creek simulator examination is in progress. All personnel not directly associatedwith the examination process please exit the simulator. This exam scenario hascommenced."

Incorporate/evaluate the following activities during the scenario exam:

ESGNRCO5.doc Page 5 of 19 Rev.: 02

Page 70: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-05

* CRS directs actions to reduceReactor power lAW HC.OP-1O.ZZ-0006.

* RO reduces Recirculation Pumpspeed lAW HC.OP-SO.BB-0002and CRS's direction.

* CRS directs actions to remove theB RFP from service lAW HC.OP-SO.AE-0001.

* PO removes the B RFP fromservice lAW Section 5.9 ofHC.OP-SO.AE-0001.- Take MANUAL control of the

RFP and reduce speed- Ensure other RFPs respond

properly- At 0 gpm, reduce speed to

<1000 rpm- Close RFP discharge valve- Lower flow to <1000 gpm and

TRIP the RFPT- Place on Turning Gear

* CREW recognizes failure of the"A" RPS channel via alarms C3-A2, C3-A3, C8-A1, C8-A2, C5(window) and indication at theRPS power source display on theH11 -P610 panel.

* RO monitors Rx power, pressure,water level and main generatoroutput for any changes.

* CRS implements and executesHC.OP-AB.ZZ-0110 and HC.OP-AB.ZZ-01 16 directs actions torecover from loss of "A" RPSpower and isolations

ESGNRCO5.doc Page 6 of 19 Rev.: 02

Page 71: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-05

As ABEO, report that theAN410 and BN410 EPAbreakers RPS "A" MG sethave tripped open on undervoltage.

* RO/PO notifies ABEO toinvestigate cause of "A" RPSchannel failure.

* CRS directs actions for RWCUsystem isolation in accordancewith HC.OP-AR.ZZ-0008.

Conductivity sampling * CRS refers to Technicalrequirements. Specification 3.4.4 for

applicability.Respond as Shift * CRS directs the following whenElectrician, that it appears conditions permit in accordanceto be an AN410 EPA with HC.OP-AB.ZZ-01 10 andbreaker under voltage HC.OP-AB.ZZ-01 16:device fault. - Re-energization of the tripped

RPS bus- Resetting the half scram- Resetting NSSSS and

restoration of RWCU systemRPS EPA breakers. * CRS refers to Technical

Specification 3.8.4.4 forapplicability.

* PO re-energizes the "A" RPS busby repositioning the RPS MGSET TRANSFER SWITCH onpanel HI 1-P610 to ALT "A" asdirected by the CRS.

* RO/PO reset NSSSS and PCISIAW CRS direction and Section5.3 of HC.OP-SO.SB-0001 andSection 5.3 of HC.OP-SO.SM-0001.

- Turn TRIP SYSTEMAl(A2,B1,B2) keysmomentarily to RESET toreset RPS

- Reset PCIS by depressingthe Channel A, B, C, and DRESET push buttons

- Reset NSSSS by depressingthe Channel A, B, C, and DRESET push buttons

ESGNRCQ5.doc Page 7 of 19 Rev.: 02

Page 72: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-05

The inboard seal fails whenRT-2 is inserted. Theoutboard seal fails 4.25minutes later.

NOTE:If CREW calls Rad Pro andrequests DWFDS andDWFDS readings on RM11,report actual readings fromthe RM 1 1.

* CREW recognizes "B" RR pumpinboard seal has failed via CRIDSand informs CRS.

* ROIPO monitors CRIDS pg. 85and heightens awareness forpotential second seal failure.

* CREW recognizes increasedleakage into DRWL and takesappropriate actions for followingalarms:1) CRIDS indication2) DRYWELL SUMP LEVEL

HI/LO - D31C33) DRYWELL PRESSURE

HI/LO - A71E44) RADIATION MONITORING

ALARM/TRBL - C6/A25) DLD SYSTEM ALARMITRBL

- C6/B1* CREW recognizes "B" RR pump

multiple seal failure and informsCRS.

* CRS implements HC.OP-AB.ZZ-0112 and directs actions to tripand isolate the "B" RR pump.

* * CREW trips and isolates the"B" RR pump before DRWLpressure reaches 1.68 psig by:- shutting pump suction valve

HV-F023B- shutting pump seal purge

valve HV-F3800B- shutting RWCU suction valve

BG-F1 06- shutting pump discharge

valve HV-FO31B(K/A 202001 A2.10 3.5/3.9)

ESGNRC05.doc Page 8 of 19 Rev.: 02

Page 73: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-05

v- NOTE:If plant is scrammed due toDRWL pressure increase,the following expectedactions for single loopoperation are notapplicable.

If guidance from RE isrequested, as the RE directcrew to monitor for power toflow oscillations and insertthe stuff sheet as necessaryto clear APRM Upscalealarms.

* OS/CRS ensures compliancewith the operability requirementsof Tech Spec 3.4.1.1 for singleloop operations.

* CRS implement HC.OP-AB.ZZ-0300, and directs actions tomonitor for power oscillations.

* CRS ensures that the CREWdoes not intentionally enterinstability (exit) region.

* RO inserts control rods lAW thestuff sheet and CRS direction toclear APRM upscale alarms.

* If Exit region is entered, theCREW exits the area of instabilityIAW HC.OP-AB.ZZ-0300 bymanually inserting rods orincreasing RR flow.

* CRS implements HC.OP-IO.ZZ-0006 for single loop operations.

* CREW references HC.OP-SO.BB-0002 sections 5.3 andimplements attachment 3V ofHC.OP-DL.ZZ-0026 for singleloop operations.

* RO/PO monitors APRMs andLPRMs for abnormal fluxoscillations.

* CRS notifies RE / I&C of RRpump trip and requirements ofTech Spec 3.4.1.1.

* RO/PO dispatches TBEO tomonitor MG Set lube oiltemperatures and adjust TACSflow as necessary.

ESGNRCQ5.doc Page 9 of 19 Rev.: 02

Page 74: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-05

Tech Spec 4.4.5 * CRS notifies Chemistry/Rad Proof Rx power decrease of >15% inone hour.

* PO notices failure of the SJAEvia overhead annunciator A4-D1,CRIDS alarm, and informs theCRS.

* CRS directs actions inaccordance with HC.OP-AB.ZZ-0128- Place the A SJAE in service.

ESGNRCO5.doc Page 10 of 19 Rev.: 02

Page 75: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

4'

ESG - NRC-05

Note: 15 minute warm-up is *not required for rapidresponse.

PO places the A SJAE in servicein accordance with Section 5.4 ofHC.OP-SO.CG-0001.- Open Air Ejector Exhaust

Valve- Open 3d Stage Jet Steam

Inlet- Open Main Steam Dist

Ejector- Place Air Ejector Exhaust

Pressure controller in AUTOand set at 11 psig

- Open Air Ejector Jet Suction3r Stage

- Open Air Ejector SecondStage Jet Inlet

- Open Air Ejector SecondStage Jet Suction

- Open Air Ejector Inter-Condenser Drain

- Open Air Ejector First StagJet Steam Inlet

- Open Air Ejector First StageJet Suction

- Close out of service SJAEvalves

PO monitors and reports MainCondenser Vacuum.

* CRS directs actions to lowerReactor Power to maintainCondenser vacuum less than 5.0"Hg ABS in accordance withHC.OP-AB.ZZ-0208.

* CRS directs a Reactor scram ifMain Condenser vacuum cannotbe maintained.

* RO places and locks the ModeSwitch in Shutdown. Notices thefailure to scram and informs theCRS.

* CRS enters and directs HC.OP-EO.ZZ-o101A, ATWS-RPVControl, and directs actions to:- Scram using RPS or ARI

ESGNRC05.doc Page 11 of 19 Rev.: 02

Page 76: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

FIqI- NRC-05)

* RO initiates an RPS scram usingthe Arm and Depress pushbuttons or by initiating ARI.Verifies rod movement andinforms the CRS.

* CRS exits HC.OP-EO.ZZ-0101A,ATWS-RPV Control, enters anddirects HC.OP-EO.ZZ-0101, RPVControl, and directs actions to:- Verify scram actions- Control RPV water level

above +12.5"- Stabilize Rx pressure below

1037#* Crew determines RPV level,

pressure, and containmentparameters and informs CRS.

* PO controls Feedwater System tomaintain water level as directed.

* RO performs scram actions inaccordance with Section 5.2 ofHC.OP-SO.SB-0001

* CRS directs pressure control withSRVs when the MSiVs close at756 psig due to Mode Switchfailure.

ESGNRCO5.doc Page 12 of 19 Rev.: 02

Page 77: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-05

* CREW recognizes Seismic Eventvia annunciator and ResponseSpectrum Analyzer panel displayand informs CRS.

* CRS implements HC.OP-AB.ZZ-0139 and directs actions to:- Monitor power, level, and

pressure- Inspect the plant for damage- Verify the security system

intact

* CRS determines from reports thatan immediate plant shutdown isrequired.

Report as the ABEO ifdispatched to the UpperRelay Room, that theseismic switch has tripped(Amber light on powersupply drawer is on) andthat the tape recorders areadvanced but not running.The Event indicator is white.If requested to reset theSeismic Monitor, clearMalfunction PCO7.Note: Only if the plant wasnot previously shutdown.

* Crew recognizes loweringSuppression Pool water level,flooding in the C RHR PumpRoom and flooding in the A RHRPump Room.

ESGNRCO5.doc Page 13 of 19 Rev.: 02

Page 78: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-05

nt! Instructor

Respond as EO to entervarious areas to report leak.Report Torus has a leakapproximately two feet fromthe bottom and appears tobe unisolable.

Note: If directed, respondas EO on attempts tomakeup to the SuppressionPool. Report makeup inprogress, but do notsimulate.

Note: Only if the plant wasnot previously shutdown.

Note: Raise severity ofPC06 to 40% over 10minute ramp when theReactor is scrammed.

* CRS implements HC.OP-AB.ZZ-01,14, HC.OP-EO.ZZ-0102, andHC.OP-EO.ZZ-0103, and directsactions to:- Restore Suppression Pool

level- Attempt to isolate the leaks by

closing the suction valves forthe C and A RHR Pumps.

* PO closes the suction valves forthe C and A RHR Pumps.

* Crew observes Suppression Poollevel continues to lower andreports this to the CRS.

* CRS directs that Recirculation berunback and a manual scraminserted if Suppression Pool waterlevel cannot be maintained above55".

* RO runs back RecirculationPumps to minimum, places theMode Switch in shutdown, noticesthe failure to scram, and informsthe CRS.

* CRS enters and directs HC.OP-EO.ZZ-0101A, ATWS-RPVControl, and directs actions to:- Scram using RPS or ARI

* RO initiates an RPS/ARI asdirected, or on own iniative, toscram the Reactor. Verifies rodmovement and informs the CRS.

* CRS exits HC.OP-EO.ZZ-0101A,enters and directs HC.OP-EO.ZZ-01 01, RPV Control, and directsactions to:- Verify scram actions- Control RPV water level

above +12.5"- Stabilize Rx pressure below

1037#

ESGNRC05.doc Page 14 of 19 Rev.: 02

Page 79: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

.

ESG - NRC-05

* Crew determines RPV level,pressure, and containmentparameters and informs CRS.

* RO initiates an RPS scram usingthe Arm and Depress pushbuttons. Verifies rod movementand informs the CRS.

* PO controls pressure as directed,SRVs or BPVs.

* PO controls Feedwater System tomaintain water level as directed.

* RO performs scram actions inaccordance with Section 5.2 ofHC.OP-SO.SB-0001.- Ensure all rods are in- Ensure RPS Mode Switch in

Shutdown- Ensure SDV Vent and Drain

Valves close- Ensure RPS Logic Channels

are tripped- Ensure IRMs and SRMs are

inserted(ing) into the Reactor- Select IRM on Recorder Input- Inform CRS of APRM power

> or < 4%* CREW monitors RPV water level,

pressure, and containmentparameters and informs CRS.

* CRS recognizes SuppressionPool level is, or cannot bemaintained above 38.5".

* CRS directs opening the BPVs inanticipation of emergencydepressurizing the Reactor.

NOTE:Crew should consideranticipating EmergencyDepressurization by usingBPVs if the Main Condenser isavailable. The Main Condenserwill not be available when theMSIVs close at 756 psig due tothe Mode Switch failure.NOTE:CRS may not direct opening ofthe BPVs for the reason statedabove.

* RO/PO opens all BPVs asdirected.

ESGNRCO5.doc Page 15 of 19 Rev.: 02

Page 80: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-05

* CRS implements HC.OP-EO.ZZ-0202, Emergency RPVDepressurization, and directsaction to open five ADS valves.

* PO opens the ADS valves, andreports this to the CRS.

* * CREW opens at least fourSRVs to emergency depressurizethe Rx within 1 minute ofsuppression pool level reaching38.5".

(K/A 223001 A2.11 3.6/3.8)

Note: Crew mayemergency depressurizebefore reaching 38.5 inches,satisfying this critical task.

ESGNRCO5.doc Page 16 of 19 Rev.: 02

Page 81: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-05

A.B.C.

D.E.F.G.H.1.

J.

K.

L.

M.N.0.

P.

Q.R.S.

T.U.

V.

W.

X.

Y.

Z.

AA.

BB.Cc.

ES-301 Preparation of Operating TestsES-604 Dynamic Simulator Requalification ExaminationlStandardK/A CatalogJTA ListingHope Creek Generating Station Probabilistic Risk AssessmentTechnical SpecificationsEmergency Plan (ECG)Alarm Response Procedures (Various)HC. OP-lO.ZZ-0006HC.OP-SO.AE-0001HC.OP-SO.BB-0002HC.OP-SO.CG-0001HC. OP-SO.SB-0001HC.OP-SO.SM-0001HC.OP-AB.ZZ-0110HC.OP-AB.ZZ-01 12HC.OP-AB.ZZ-0110HC. OP-AB.ZZ-0300HC.OP-AB.ZZ-01 16HC.OP-AB.ZZ-0139HC.OP-AB.ZZ-0208HC.OP-DL.ZZ-0026HC. OP-EO.ZZ-0101HC. OP-EO.ZZ-0101AHC.OP-EO.ZZ-0102HC.OP-EO.ZZ-0103HC.OP-EO.ZZ-0202HC. OP-AZ.ZZ-0002SH.OP-DD.ZZ-0004

Power Changes During OperationFeedwater System OperationReactor Recirculation System OperationCondenser Air Removal System OperationReactor Protection SystemIsolation Systems OperationLoss of an RPS ChannelRecirculation Pump TripLoss of an RPS ChannelReactor Power OscillationsContainment Isolations and Recovery From an IsolationActs of NatureMain Condenser Low VacuumSurveillance LogRPV ControlATWS-RPV ControlPrimary Containment ControlReactor Building & Rad Release ControlEmergency RPV DepressurizationHope Creek Operations StandardsOperations Standards

ESGNRCO5.doc Page 17 of 19 Rev.: 02

Page 82: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

ESG - NRC-05

ESG-NRC-05 /00

* * CREW trips and isolates the "B" RR pump before DRWL pressure reaches 1.68 psig by:- shutting pump suction valve HV-F023B- shutting pump seal purge valve HV-F3800B- shutting RWCU suction valve BG-F106

shutting pump discharge valve HV-FO31B(KIA 202001 A2.10 3.5/3.9)

Based upon the severity of the leak in the drywell, the operators will be able to identify and isolate thesource of leakage before drywell pressure reaches 1.68 psig. Reaching 1.68 psig in the drywell initiates areactor scram and starts ECCS and emergency systems. The scram and subsequent plant transient canbe eliminated by proper operator actions.

2.* * CREW opens at least four SRVs to emergency depressurize the Rx within 1 minute of

suppression pool level reaching 38.5".(KIA 223001 A2.11 3.6/3.8)

EOPs direct action to emergency depressurize the Reactor if Suppression Pool level cannot bemaintained above 38.5". This level represents the Suppression Pool level that results inuncovering the Downcomer pipes and a loss of pressure suppression function of the PrimaryContainment.

ESGNRCO5.doc Page 18 of 19 Rev.: 02

Page 83: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None

Hope Creek Generating Station Turnover SheetToday's Date

Oncoming Shift: Days [XI Nights [ ]OPERATIONAL CONDITION: 1,100% RTP, MAIN GEN. OUTPUT: 1104 MWe

RISK MATRIX COLOR: Green RIVER TEMPERATURE: 650F'D' CHANNEL WORK WEEK - BLUE Folders

k-' Major activities accomplished last shift:* Maintained 100% power..

Major activities scheduled for this shift:* Reduce Reactor power to 95%.* Remove B RFP from service for maintenance. Turbine inspection.

Sys/EquipProblems .

Protected IEquipment I -

Update Status .U

Action PlansX

Follow-up Operability Assessments (CRFA) AssignedAR = OEF_4JENa

Compensatory Actions in effect (Required by CROD/CRFA for Operability)

mbe Cnr

Reactivity Controls:

0

Standby Safety Systems:0

Balance of Plant:.

Electrical:

* CRIDS "Excess MVARS" point is INOP; contact Load Dispatch for info regarding this point.Cooling Water Systems:0

Ventilation:

Administrative:0

Page 19 of 19 Rev.: 02

Page 84: Final - Section C Operating · 9. TC01-9 10. TC01-8 11. TC01-7 12. TC01-6 13. TC01-5 14. TC01-4 15. RC09 50 Pre-insert Pre-insert Pre-insert None/3 None/3 I/None 2/None 3/None 3/None