    CITY OF HOUSTON Annise D. Parker  

    Mayor  

    P.O. Box 1562Houston, Texas 77251-1562 

    Telephone – Dial 311 

    www.houstontx.gov November 2014 

    Over the past decade, the City of Houston (COH) has experienced numerous disasters each growing in

    strength and accumulated damage. The Finance Disaster Recovery Group (DRG) has focused on building

    stronger internal controls in managing disaster cost reimbursement. This manual serves to provide

    guidance for local government representaves to review applicable policies, procedures, templates and

    tools for managing when disasters strike. Addionally, it will provide guidance on the disaster recovery

    process with an emphasis on funding and reimbursement from key external sources. Each year, the

    COH conducts various disaster trainings for citywide representaves in preparaon of hurricane season.

    Key points to focus on are: 

    Role of DRG in accounng, State and Federal reporng, project worksheet closeouts and monitoring

    and compliance review process; 

    Preparaon pracces for long-term recovery eorts including best pracces for project worksheet

    documentaon; 

    Compliance with Federal and State guidance; 

    Role of key divisions including Insurance Management, Payroll and Strategic Procurement during a

    disaster; and 

    Departmental responsibilies regarding documentaon requirements to avoid de-obligaon of

    funds including mely reporng and meeng deadlines. 

    I want to acknowledge key sta from the Financial Reporng and Operaons Division— Michelle Simp-

    son and Fazal Syed, Disaster Recovery Group; and Nickea Bradley and Gloria Moreno, Grants Manage-

    ment, for their reless work in this recent edion of the Disaster Recovery Manual. When a disaster is

    impending, this tool should serve as the rst place to look for nancial preparaon guidance and more

    importantly aer the event for assistance in project cost documentaon. 

    Sincerely, 

    Kelly Dowe, Finance Director 

    Council Members: Brenda Stardig Jerry Davis Ellen R. Cohen Dwight A. Boykins Dave Martin Richard Nguyen Oliver Pennington EdwardGonzalez Robert Gallegos Mike Laster Larry V. Green Stephen C. Costello David W. Robinson Michael Kubosh C.O. “Brad” Bradford JackChristie

    Controller: Ronald C. Green 

  • 8/18/2019 Finance Disaster Handbook

    3/72 

    Table of Contents OVERVIEW: 

    Acronyms  4 

    Overview  5 

    Stakeholders  7 

    Finance 8 

    FOUR PHASES OF EMERGENCY MANAGEMENT: 

    Phase 1: Migaon 

    COH Hazard Migaon 9 

    Federal Migaon Grant Program  9 

    Phase 2: Preparedness 

    Emergency Operaons  10 

    Emergency Procurement  12 

    Emergency Cash 

    15 

    Internal Order  16 

    Emergency Payroll  17 

    Phase 3: Response 

    Damage Documentaon  19 

    Summary of Funding  21 

    Insurance  23 

    Duplicaon of Benets  26 

    Phase 4: Recovery 

    Public Assistance 

    27 

    Project Worksheet  31 

    Reporng  35 

    COMPLIANCE: 

    Funds Management  36 

    Project Closeout  37 

    Record Keeping  38 

    Audits  39 

    Audit Findings: Case Study  41 

    REFERENCES 

    42 

    APPENDICES 

    Appendix 1: Administrave Procedure 4-2  45 

    Appendix 2: PW Forms for Summary Records  61 

    Appendix 3: Eligibility Charts  69 

    Appendix 4: Claim Summary Form  71 

    DISCLAIMER: The informaon provided in this manual is intended as guidance ONLY and does not relieve the City of Houston and its departments of its re-

    sponsibility to comply with Federal regulaons and policies. Documentaon requirements may change over me. For addional informaon on documenta-

    on requirements for items listed in this manual, refer to the Appendix secon. 

  • 8/18/2019 Finance Disaster Handbook

    4/72 

    Acronyms ARA Administraon & Regulatory Aairs

    AP Administrave Procedure 

    CFR  Code of Federal Regulaons 

    CMOC  Catastrophic Medical Operaons Center 

    COH  City of Houston 

    DAC  Direct Administrave Cost 

    DARM  Disaster Assistance Recovery Manual 

    DDC Disaster District Commiee

    DDCT  Disaster Data Collecon Team 

    DON 

    Department of Neighborhoods 

    DPU  Departmental Purchasing Unit 

    DRG  Disaster Recovery Group 

    ECA  Emergency Cash Account 

    EDR  Expenditure Data Request

    EPO  Emergency Purchase Order 

    EOC Emergency Operaons or Operang Center

    EMC Emergency Management Coordinator

    EPA  Environmental Protecon Agency 

    ER  Emergency Relief  

    FEMA  Federal Emergency Management Agency 

    FHWA Federal Highway Administraon 

    FIN Finance Department 

    FMD  Fleet Management Department 

    GM Grants Management 

    GSA  US General Services Administraon 

    GSD  General Services Department 

    HAS  Houston Airport System 

    HFD  Houston Fire Department 

    HITS  Houston Informaon Technology Services 

    HLT  Health and Human Services 

    HMGP  Hazard Migaon Grant Program

    HPD  Houston Police Department

    HR Human Resources

    HUD  US Housing and Urban Development 

    I/O  Internal Order 

    OEM Houston Oce of Emergency Management

    OIG 

    FEMA Oce of Inspector General 

    P4  Project Compleon Report and Cercaon 

    PA  Public Assistance 

    PD  Planning Department 

    PO  Purchase Order 

    POP  Program of Projects Spreadsheet 

    PR  Parks and Recreaons

    PSHS  Public Safety and Homeland Security 

    PW  Project Worksheet 

    PWE  Public Works and Engineering 

    RFI  Request for Informaon 

    SAP  System, Applicaons and Products

    SMOC  Texas State Medical Operaons Center 

    SOC Texas State Operaons Center

    SOP Standard Operang Procedures

    SPD Strategic Procurement Division

    SWM  Solid Waste Management 

    TDEM  Texas Division of Emergency Management 

    TXDOT  Texas Department of Transportaon 

  • 8/18/2019 Finance Disaster Handbook

    5/72

    OVERVIEW

    Finance Disaster Recovery Manual—Revised November 20145

    Overview Emergency management has evolved to an all-hazards approach that includes potential

    threats to life and property through environmental, biological and technological hazards,

    and domestic and foreign attacks. However, preparedness is only one phase of emergency

    management. The Mayor is responsible for the overall coordinaon of the event from pre-

    paredness to post-disaster eorts ulizing the City of Houston (COH) Emergency Plan. To

    assist the Mayor, the Emergency Operaons Center (EOC) combines various stakeholders

    to assist in the execuon of the emergency plan. 

    These stakeholders include internal and external partners that play signicant roles in the

    four phases of emergency management: migaon, preparedness, response and recovery.

    The following diagram illustrates the four phases of emergency management and the larg-

    er coordinaon funcons of response and recovery. 

    Mayor, Emergency Management Director 

    ARA 

  • 8/18/2019 Finance Disaster Handbook

    6/72

    OVERVIEW 

    Finance Disaster Recovery Manual—Revised November 20146 

    The City is required to provide comprehensive documentaon of damages, materials, and

    personnel used during the course of the event. Managing and maintaining funding for dis-

    asters is a crucial aspect of disaster recovery. Accurately and quickly assessing the scale of

    damage following a disaster is dicult. The level of declaraon is based on the City’s ability

    to recover from the disaster with its own resources.

    Robert T. Staord Act authorizes Federal disaster assistance in the aermath of a major

    emergency or disaster and outlines available assis-

    tance through two types of declaraons: 

    An Emergency Declaraon is declared for any

    instance or occasion when the President deter-

    mines that Federal assistance is needed to sup-

    plement State and local eorts and capabilies

    to save lives and protect property, public

    health, and safety. 

    A Major Disaster Declaraon is declared when

    the President determines that a natural event,

    re, ood, or explosion causes damage beyond

    the combined capabilies of State, local gov-

    ernments, and disaster relief organizaons. 

    In addion to assisng in the disaster declaraon, event documentaon also begins with

    the project worksheet (PW). Project worksheets are completed for each category of work.

    Depending on the type of damage, each category may consist of several PWs. Furthermore,

    PWs are a growing, changing document serving as a coversheet to supporng documenta-

    on of costs incurred related to the work for necessary restoraon. The importance of

    keeping accurate records cannot be overemphasized. Supporng documentaon of the

    event prior, during, and post disasters is crical and essenal departmental responsibili-

    es.

    Compliance of expenditures to Federal and State guide-

    lines is crical to funding reimbursement. Periodic re-

    views, reports and audits are the basis for vericaon of

    the accuracy of project cost esmates. Negave ndings

    may result in de-obligaon (withdrawal) of funds or an

    adverse City scal year end report.

    Lessons learned from prior audit ndings serve as the cat-

    alyst for DRG process improvements through numerous

    citywide disaster trainings, disaster manual development

    and a customer service driven support for departments. 

    http://courageconcepts.com/blog/wp-content/uploads/2012/09/lessons-learned.jpg

  • 8/18/2019 Finance Disaster Handbook

    7/72

    OVERVIEW

    Finance Disaster Recovery Manual—Revised November 20147

    Internal and external stakeholders are essenal components to eecve coordinaon and

    collaboraon during and aer an event. The capability to recover swily and eciently

    Oce of Emergency Management/Houston Emergency Center

    Oversight of emergency operaons Enumerates responsibilies

    Emergency Plan and Funconal Annexes Disaster Data Collecon Team 

    Administraon and Regulatory Aairs  Liaison between City & insurance

    carriers 

    Emergency Payroll 

    Finance Department  Emergency procurement  Cost reimbursements  Submits quarterly reports  Liaison for disaster recovery audits 

    Key COH Departments in EmergencyCoordinaon  Public Works & Engineering 

    -Restores key services i.e. ulies

     

    -Repairs crical infrastructure  Solid Waste Management 

    -Conducts debris and waste collecon -Ensures proper documentaon ofcollecon acvies 

    General Services Department -Coordinates resource management -Oversees major reconstrucon 

    Texas Division of Emergency Management  Manages disasters statewide  Conducts damage assessment 

    Reviews quarterly reports  Audits projects 

    Federal Highway Administraon/ Texas Department of Transportaon  Coordinates emergency relief   Repairs or reconstructs Federal roads

    and highways 

    Federal Emergency Management Agency  Determines obligaon and de-

    obligaon of funding 

    Reviews project worksheet  Conducts audits 

    Other Key External Partners  Insurance carriers  Supplementary donaons  Consultants and contractors 

    increase with the commitment of stake-holders when an event strikes. Below is a

    summary of potenal dues stakeholders

    complete during and aer an event. 

  • 8/18/2019 Finance Disaster Handbook

    8/72

    OVERVIEW 

    Finance Disaster Recovery Manual—Revised November 20148 

    Disaster Recovery Group (DRG): The Disaster Recovery Group funcons include periodic re-

    porng to internal and external agencies such as the Federal Emergency Management Agen-

    cy (FEMA) and the Texas Division of Emergency Management (TDEM), and facilitates cost re-

    imbursement, project closeouts and agency audits.

    hp://www.houstontx.gov/nance/acct/general_accounng.html 

    Strategic Procurement Division (SPD): SPD is a division within the Finance department and

    is responsible for emergency purchases and procurement pertaining to disaster projects.

    SPD has developed guidance and policies for City employees to use for purchases made dur-

    ing a disaster.

    hp://purchasing.houstontx.gov/index.shtml 

    Grants Management (GM): Grants Management is responsible for the applicable grant ad-

    ministraon and the issuance of an internal order number and grant set up in SAP, the City’s

    nancial accounng system. 

    hp://www.houstontx.gov/nance/grants/ 

    Financial Planning and Analysis: The Financial Planning and Analysis division is responsible

    for the development and administraon of budgets pertaining to a disaster.

    hp://www.houstontx.gov/nance/fpa 

    FEMA & TDEM oer training in

    emergency management including

    self -studies and online courses.

    www.fema.gov 

    www.preparingtexas.org

  • 8/18/2019 Finance Disaster Handbook

    9/72

    PHASE 1: MITIGATION

    Finance Disaster Recovery Manual—Revised November 20149

    COH Hazard Migaon 

    Migaon is the eort to reduce loss of life and

    property by lessening the impact of disasters.

    The City created the hazard migaon plan to

    detail concepts for administrave and operaon-

    al acvies, which could lead to the reducon

    and/or possible removal of those condions that

    cause potenal hazards or are hazardous to the

    public. It balances the cost of implementaon

    against the potenal cost of connued damages,

    if such measures are not taken. Guidelines are given to manage migaon eorts in concert

    and coordinaon with State and Federal policies. Addionally, it provides opportunies forlong-term programs that could reduce the negave eects of disasters or emergencies.

    Federal Migaon Grant Program 

    The Hazard Migaon Grant Program (HMGP) is authorized under the

    Robert T. Staord Disaster Relief and Emergency Assistance Act to im-

    plement long-term hazard migaon measures aer a major disaster

    declaraon. Each level of government has an important, but dierent,

    role within HMGP. The City develops, coordinates, and manages the

    approved projects as a subgrantee of the State. Subsequently, the

    State monitors all program and administrave requirements. FEMA

    provides technical assistance to States in order to ensure eecve and

    ecient implementaon of the program. Addional subcategories of

    assistance have been created to provide increased funding for migaon. 

  • 8/18/2019 Finance Disaster Handbook

    10/72

    PHASE 2: PREPAREDNESS 

    Finance Disaster Recovery Manual—Revised November 201410 

    Revised: February 2014

    M – Resource Management

    N – Direcon & Control

    O – Human Services

    P – Hazard Migaon

    Q – Hazardous Materials

    R – Search & Rescue

    S – Transportaon

    T – Donaons Management

    U – Legal

    V – Terrorism

    W – Debris Management

    A – Warning

    B – Communicaons

    C – Shelter/Mass Care

    D – Radiological

    E – Evacuaon

    F – Fireghng

    G – Law Enforcement

    H – Health & Medical

    I – Public Informaon

    J – Recovery

    K– Public Works 

    Emergency Operations The Mayor is responsible for overall coordina-

    on and direcon of the City Emergency Man-

    agement Plan which includes post-disaster

    eorts. The Emergency Management, BasicPlan establishes the role of COH Oce of Emer-

    gency Management (OEM) and provides general

    procedural guidance for addressing emergency

    and disaster situaons. The plan is supported

    by a series of separate funconal annexes that

    address operaonal response, coordinaon,

    management, recovery and migaon to com-

    mon emergencies. Addionally, annexes pro-

    vide guidance of internal departmental opera-

    ons in support of emergency operaons. Fur-

    ther, this plan provides guidance on how COH

    coordinates operaons with regional, State and

    Federal agencies. The plan and annexes are re-

    viewed and revised for submission to TDEM for

    cercaon. The Emergency Management Coor-dinator, appointed  by the Mayor, takes the lead

    in compiling data and coordinang inputs for all

    departments.

    Like most major cies, OEM serves as the central collecon point for all preliminary dam-

    age documentaon related to City-owned facilies and infrastructure that is impacted by a

    disaster. Each year OEM provides departmental training on the Disaster Assistance Recov-

    ery Manual (DARM) and associated procedures. This ensures that all departments are ap-propriately trained on damage assessments and documentaon compleon. OEM also

    serves as a liaison and coordinator between State and Federal representaves and COH to

    ensure maximum recovery. Addionally, OEM’s daily responsibilies include severe

    weather monitoring, issuing emergency warnings and emergency resource coordinaon.

    During an event, OEM collaborates with interagency partners to coordinate a citywide re-

    sponse. 

  • 8/18/2019 Finance Disaster Handbook

    11/72

    PHASE 2: PREPAREDNESS

    Finance Disaster Recovery Manual—Revised November 201411

    DARM Outlines Recovery Process 

    Coordinate with City departments andagencies 

    Facilitate shelter operaons  Distribute public recovery Informaon Complete restoraon projects 

    Individual and Public Assistance Programs

    Coordinate damage assessments withdepartments and agencies 

    Collect damage informaon  Develop documentaon to request

    disaster declaraons 

    Training and Exercises 

    Incident Command System and FEMATraining 

    COH-Specic Response Plan Training

     

    DARM Training 

    OEM coordinates a citywide response by providing a framework for a mul-agency response

    and the ecient use of resources during all phases of a major emergency or disaster.

    INTER-AGENCY COORDINATION 

  • 8/18/2019 Finance Disaster Handbook

    12/72

    PHASE 2: PREPAREDNESS 

    Finance Disaster Recovery Manual—Revised November 201412 

    Emergency Procurement 

    In collaboraon with “rst responder”

    departments, “Pre-Posioned” contracts

    were established for acvaon subse-

    quent to the disaster or catastrophic event.

    Examples of pre-posioned contracts currently

    in place at COH are: 

    Disaster Debris Removal Services

    Disaster Management Consulng Services 

    Mobilizaon, Collecon, Characterizaonand Packaging of Household HazardousWaste 

    Emergency Medical Transportaon Services 

    Base Camp Services 

    An emergency procurement arises when a pur-

    chase is required to protect personal safety or

    property aer a serious and urgent event occurs

    demanding immediate acon. Such procure-

    ments should be made with compeon as to

    the extent feasible under the circumstances.

    Procurement rules applicable to compeon are

    relaxed but only for a short period aer the dis-

    aster, usually 72 hours. Aer 72 hours, normal

    compeve bidding rules apply. 

    Execuve Order 1-42 may authorize Pcardhold-

    ers to make purchases beyond there single/

    monthly transacon limits during emergencypreparedness or disaster. 

    The Conngency Contracng (Emergency Purchases) Guide was created to assist City em-ployees (buyers) during a disaster. The Guide lists, alphabecally and by category, pre-

    approved Emergency Response Contractors with their 24/7 contact informaon. 

    The guide assists with maximizing the use of City, inter-local, cooperave purchasing con-

    tracts and U.S. General Services Administraon (GSA) Federal Supply Schedules. For sup-

    plies and services not available from established contracts, the compeve bid procedures

    must be followed as promulgated by State and local procurement rules and regulaons. 

  • 8/18/2019 Finance Disaster Handbook

    13/72

    PHASE 2: PREPAREDNESS

    Finance Disaster Recovery Manual—Revised November 201413

    Contracng Work 

    Contracts must be of reasonable cost, generally must be compevely bid, and must com-

    ply with Federal, State and local procurement standards. Not all emergency work is me

    sensive to the point where compeve bidding is infeasible.

    Small Purchases  – An Informal method for services or

    supplies that do not cost more than $100,000 and are

    secured by obtaining several price quotes. 

    Sealed Bids  – A formal method in which bids are pub-

    licly adversed and solicited. Contracts are awarded to

    the responsive and responsible bidder who submits the

    lowest bid. This is the preferred method for construc-

    on contracts. 

    Compeve Proposals – A formal bidding method sim-

    ilar to sealed bid; but the contract is awarded based on contractor qualicaons, not solelyon price. This is used for procuring architectural and engineering professional services. 

    “Piggyback Contracng” is not eligible.  It consists of expanding on a previously awarded

    contract with a vendor. This does not meet procurement requirements because it is non-

    compeve and may have an inappropriate price structure. 

    There are four methods of acceptable procurement. Each is described below in general

    terms. 

    1. 

    Lump sum contracts for work within a prescribed boundary with a clearly dened scopeand a total price. 

    2.  Unit price contracts for work done on an item-by-item basis with cost determined per

    unit. 

    3.  Cost plus xed fee contracts, which are either lump sum or unit price contracts with a

    xed contractor fee added into the price. 

    4.  Time and materials contracts, while acceptable, should be avoided. These contracts

    when used are for a limited period (generally not more than 72 hours) for work that isnecessary immediately aer the disaster has occurred when a clear scope of work can-

    not be developed. However, be aware that FEMA has strict guidelines and require-

    ments to qualify for FEMA reimbursement when these contracts are used. Monitoring is

    crical and a compeve process sll should be used to include labor and equipment

    rates. 

    NOTE: Cost Plus + Percentage of Cost contracts are NOT allowed 

  • 8/18/2019 Finance Disaster Handbook

    14/72

  • 8/18/2019 Finance Disaster Handbook

    15/72

    PHASE 2: PREPAREDNESS

    Finance Disaster Recovery Manual—Revised November 201415

    Emergency Cash An emergency cash account (ECA) is created when a state

    of emergency is declared by the Mayor and used to assist

    departments with access to cash for use in disaster recov-

    ery. All funds allocated must be withdrawn in one lumpsum, thereby acvang the ECA. Each ECA shall have a pri-

    mary custodian and up to three alternate custodians. To

    document transacons the journal entries must be made with ECA receipts for all expendi-

    tures. ECA purchases are limited to goods or services that cannot reasonably be accommo-

    dated through exisng contracts and serve to directly assist in disaster recovery (see Appen-

    dix 1).

    Prohibited use of the ECA are: 

    Cashing personal checks. 

    Loans to employees or others. 

    Payroll advances to employees. 

    Entertainment of any kind. 

    Personal expenditures (i.e. oce decoraons). 

    An ECA may not be deacvated unl the Mayor rescinds the state of emergency. Once re-

    scinded, all ECAs must be deacvated within 30 days with Finance Department approval. If

    extenuang circumstances present a reason requiring connued ECA spending, extensions

    to the 30 day closeout may be granted by the Finance Director with wrien juscaon.

    Other inappropriate purposes established by the

    Approving Authority. 

    Making change for transacons involving cash sales

    or where cash is received. 

    Reimbursements of state sales tax for any purchase. 

  • 8/18/2019 Finance Disaster Handbook

    16/72

    PHASE 2: PREPAREDNESS 

    Finance Disaster Recovery Manual—Revised November 201416 

    In addion, ALL supporng documentaon related to the transacons such as work orders,receipts and invoices, should be maintained by departmental  contacts for future audits and

    inquiry. Copies should also be provided to the Finance department and OEM as requested.

    NOTE: Supporng documentaon for projects is to be maintained 

    at least 3 years aer the date that the FINAL STATUS REPORT   issued

    by TDEM and received by DRG for the disaster as a whole.

    WHEN IN DOUBT, DON’T THROW IT OUT! 

    Internal Order An internal order (I/O) number is established by Finance Grants Management prior to the

    onset of the disaster and distributed to all departments. The I/O number is specic for

    each disaster event and used to idenfy all SAP transacons (revenues and expenditures)

    resulng from this event. Disaster related expense transacons are entered into SAP andcoded to the applicable Internal Order number, fund, business area, grant and cost center,

    as assigned. NOTE: Expenses charged to disaster internal order number should be limited

    to approved reimbursable expenses or projects.

  • 8/18/2019 Finance Disaster Handbook

    17/72

    PHASE 2: PREPAREDNESS

    Finance Disaster Recovery Manual—Revised November 201417

    Emergency Payroll The Payroll Services Division has two central missions dur-

    ing a disaster event: (1) ensure that all City employees con-

    nue to receive their proper remuneraon during or aer

    a disaster event; and (2) ensure all employee me spent

    preparing for, responding to and recovering from a disaster

    event is properly recorded in Kronos mekeeping system

    and SAP in order to maximize any reimbursement to which

    the City may be entled to from the Federal and State gov-

    ernments. These missions are reinforced by procedures to

    ensure that employees are paid during and aer a disaster.

    In order for the City of Houston to maximize its cost recovery, all disaster-related me must

    be recorded in Kronos and supporng documentaon must be prepared and maintained by

    the individual department. Kronos is an automated and paperless me and aendance sys-

    tem. Kronos has the capability to annotate me that was worked in relaon to a disaster by

    use of special pay codes and internal order numbers. Special instrucons regarding the use

    of special pay codes and internal order numbers

    will be disseminated prior to, during or immedi-

    ately aer the disaster period. 

    In the event communicaons are lost between

    Kronos me clocks and the Kronos server, as

    long as they are powered, the me clocks will

    store all me stamps and will transmit the

    stored informaon once communicaons are

    reestablished. Employees and supervisors should take extra care in reviewing electronic

    me cards to ensure me stamp data was accurately recorded during the disaster event

    and make any needed correcons. 

    It is not enough for City employees to clock in and out of Kronos for me worked preparing

    for, responding to and recovering from a disaster. In order to fulll Federal and State re-

    quirements, departments must also maintain detailed log of hours worked for all employ-

    ees performing disaster-related duties. The hours logged submitted for reimbursement on

    timesheets must coincide with the hours reported on the Kronos electronic time card.

  • 8/18/2019 Finance Disaster Handbook

    18/72

    PHASE 2: PREPAREDNESS 

    Finance Disaster Recovery Manual—Revised November 201418 

    Payroll Scenarios 

    There are three scenarios that may aect the procedures for processing and capturing pay-

    roll costs. They are: 

    1.  City Network and Internet are functional. Kronos is available as normal and the SAP

    payroll module is available to Payroll Services Division sta: 

    a.  Payroll Services Division will coordinate with the HITS Department to expand the use

    of the TeleTime remote me card service and or Kronos Mobile App access as neces-

    sary. 

    b.  Payroll Services Division will disseminate any special payroll processing instrucons

    such as the use of special pay codes and/or internal order numbers or paper me-

    sheets. 

    c.  All supervisors are required to review and approve sta me cards as normal and ap-

    propriate. 

    2.  SAP is only available to payroll personnel. Kronos is unavailable to City employees to

    record me stamps, request/approve me-o requests and review/approve me cards,

    the Payroll Services Division will ensure; 

    a.  Exempt employees (salaried) and Non-exempt employees (hourly) will be paid ac-

    cording to their normal bi-weekly work schedule. 

    b.  Temporary employees will be paid an average number of hours from the previous

    three pay periods. All temporary employees working through a stang agency arerequired to submit their approved me cards to their stang agency and will not be

    issued a check from COH. 

    3.  No systems are available. 

    a.  With the Mayor’s approval, Pay-

    roll Services will authorize a re-

    peat of the previous payroll peri-

    od’s banking instrucons to the

    City’s banking services provider. 

    b.  Payroll Services Division will dis-

    seminate special instrucons

    such as paper mesheets to doc-

    ument for reconciliaons post

    event. 

  • 8/18/2019 Finance Disaster Handbook

    19/72

      PHASE 3: RESPONSE 

    Finance Disaster Recovery Manual—Revised November 201419

    Damage Documentaon When a disaster hits, the primary responsibilies for Departments are to: 1) maintain docu-

    mentaon on the preliminary damage for all property within 3 days of the disaster; 2) assign

    representaves to report damage; 3) provide updates on damage assessments; 4) monitor

    repairs; and 5) maintain ALL documentaon. Other departmental responsibilies includeassisng the Disaster Recovery Group (DRG), Federal and State adjusters by compleng and

    maintaining records to idenfy costs for eligible work, recording disaster expenses separate

    from day-to-day operaons and cerfying that all informaon submied in response to re-

    quests are true and correct. (See Appendix 1, AP 4-2, Secon 6.8 for a complete lisng of

    responsibilies).

    During the inial response, assessments play a vital role in determining the scope of the dis-

    aster and necessary resources for recovery. The three most common inial assessments

    are: 

    Rapid Assessment is normally limited to evaluang the following humanitarian and emer-

    gency needs and acvies:

    Preliminary Damage Assessment is conducted to determine the extent of damage to the

    community as soon as humanitarian and emergency needs have been idened and access

    into the area is safe.

    Detailed Site Assessment includes detailed analysis of the damages to all private sector and

    public infrastructures. It may take several days or even weeks to complete.

    Good documentaon facilitates the project formulaon,validaon, approval and funding processes 

    Life safety (e.g., search and rescue,medical assistance, mass care, hazard-ous materials) 

    Life lines (e.g., ulies and transporta-on systems)

    Essenal services (e.g., medical, emer-gency communicaon and logiscs) 

  • 8/18/2019 Finance Disaster Handbook

    20/72

  • 8/18/2019 Finance Disaster Handbook

    21/72

      PHASE 3: RESPONSE 

    Finance Disaster Recovery Manual—Revised November 201421

    Summary of Funding Individual  municipalies are to determine what damage may be covered by their insurance

    policies and what damage may qualify for assistance from FEMA or other government pro-

    grams. 

    Municipal Insurance 

    State Assistance 

    Federal Assistance 

    Naonal Voluntary Organizaons Acve in Disaster (www.NVOAD.org)

    Faith and community based organizaons.

    Private sector.  Educaonal instuons and organizaons (fraternies/sorories).  Regular service providers (meals-on-wheels, special needs transport, etc).

    Insurance 

    Municipal insurance providers cover losses experienced by public enes. Services include

    management of all insurance policies, consulng and recommendaons for contracts and

    post disaster recovery insurance claims.

    Budget Stabilizaon Fund (formerly Rainy Day Fund)

    The COH Budget Stabilizaon Fund establishes

    cash reserves available for any lawful use in the

    event of an emergency including major disasters.

    State Assistance 

    Disaster grant funds from the Governor are typi-

    cally available only aer appropriated funds to

    local agencies for disasters are depleted. The

    Governor has the authority to consider approval

    of disaster grants for agencies with insucientfunds to operate or meet unancipated situaons. 

    The Urgent Needs Fund is by invitaon only. Funds can only be ulized for acvies that will

    restore water or sewer infrastructure whose sudden failure has resulted in either death, ill-

    ness, injury or poses an imminent threat to life or health within the aected applicant’s juris-

    dicon and the problem being addressed must be of recent origin (no more than 30 days

    from the date of the event).

  • 8/18/2019 Finance Disaster Handbook

    22/72

    PHASE 3: RESPONSE 

    Finance Disaster Recovery Manual—Revised November 201422 

    Texas Division of Emergency Management 

    TDEM is accountable for the use of pass-through funds provided by FEMA and is responsi-

    ble for disbursing those funds to the City. TDEM is also responsible for providing: 1) tech-

    nical advice and assistance; 2) ensuring that the City is aware of the available assistance

    programs; 3) providing support for damage assessment operaons; 4) supporng project

    idencaon acvies including large and small project idencaon and validaon of

    small projects; and 5) subming the necessary paperwork for grant awards. 

    Texas Department of Transportaon 

    TXDOT is accountable for the use of pass-through funds provided by the Federal Highway

    Administraon and assuring compliance to project regulaons. TXDOT is also responsible

    for: 1) idenfying federal-aid highways; 2) requesng Emergency Relief (ER) funding; 3) par-

    cipang on detailed damage teams; 4) coordinang locally administered projects; and 5)

    providing technical advice and assistance. 

    FederalFederal disaster funding programs are available from the FEMA, FHWA, Environmental Pro-

    tecon Agency (EPA), and US Department of Housing and Urban Development (HUD).  

    Each federal funding program will cover dierent uses, including planning, construcon, op-

    eraons and maintenance. The following table highlights applicability under the govern-

    ment programs listed below. 

    Program 

    EmergencyRepairs (M, R)

    1  Planning andDesign (M) 

    Construcon/Capitalizaon (M, R) 

    TechnicalAssistance

    FHWA  x  x  x 

    FEMA Public Assistance  x  x  x 

    FEMA Hazard Migaon Grant Program  x  x 

    EPA Drinking Water State Revolving Fund  x  x  x  x 

    EPA Clean Water State Revolving Fund   x  x  x 

    HUD Community Develop Block Grant  x  x 

    HUD Secon 108 Loan Program  x 

    1M = Acvity is related to Migaon; R = Acvity is related to Response/Recovery 

    2 Technical Assistance = May include acvies undertaken to help ulies recover from disasters

  • 8/18/2019 Finance Disaster Handbook

    23/72

      PHASE 3: RESPONSE 

    Finance Disaster Recovery Manual—Revised November 201423

    The Insurance Management group is responsible for working with departments to idenfy

    and document damages that may be eligible for insurance recovery. The group also coordi-

    nates and negoates selements for all insurance claims related to the disaster. Addional-

    ly, the group serves as a liaison to the City insurance representaves. Departments must

    allocate and account for insurance proceeds at the level of individual project worksheets.  

    Insurance

    Total Insured Value - $10.9B for over 2600 Locaons 

    High Maximum Property Policy Deducble - $20M 

    Policy Loss Limit - $175M 

    *as of June 2014 

    Immediate Noce of

    Damages – Three Days 

    Disaster Data Collecon

    Team (DDCT) – ARA/OEM/FIN 

    Department Designated

    Representaves

    Damage Esmates of

    Owned Property(Buildings, Contents, etc.) 

    Insurance Claim Process Immediately following an event, rst responders (re, police, public works, etc.) are nor-

    mally required to provide an inial “snapshot” of the geographic area aected. As emer-

    gency calls come in and the response phase begins, the general locaon and the severity of

    damage becomes known.

  • 8/18/2019 Finance Disaster Handbook

    24/72

    PHASE 3: RESPONSE 

    Finance Disaster Recovery Manual—Revised November 201424 

    The schedule of insured property is used to idenfy insured properes to assist in com-

    pleng the City’s Preliminary Property Damage form (Appendix 1).

    Insurance Claim Timeline 

     S A M

      P  L  E 

  • 8/18/2019 Finance Disaster Handbook

    25/72

      PHASE 3: RESPONSE 

    Finance Disaster Recovery Manual—Revised November 201425

    City Preliminary Property Damage Form 

    What is REQUIRED? 

    1.  Idencaon of Damages –

    Schedule of Insured Property 

    2.  Include Locaon of Damages, Ad-

    dress and Insurance Key Number 

    3.  Damage Esmates 

    Buildings

    Permanently Installed Fix-

    tures & Machinery 

    Contents (All Departments) 

    Furniture, Fixtures, Supplies

    & Computers 

    4.  Damage Documentaon –

    Emergency Repairs & Permanent

    Repairs 

    Photograph Damages Upon Dis-

    covery 

    5.  Damage Inspecons 

    Mulple Inspecons for Mulple

    Purposes 

    6.  Descripon of Damaged Vehicles 

    Designate a Vehicle Contact Person 

    Why should it be a priority? 

    Time Sensive – Preliminary Re-port Due in Three Days 

    Inial Insurance Claim 

    Request for State and/or Federal

    Disaster Assistance – Filing Dead-

    lines 

    Mobilizaon of Resources 

    Claim Selement 

    How Much and Where Does it go?  

    Actual Expenses vs. Negoated Selement 

    Claim Payment Aer Applicaon of Deducble 

    Insurance Recovery Deposited into Disaster

    Recovery Fund and managed by Finance De-

    partment 

  • 8/18/2019 Finance Disaster Handbook

    26/72

  • 8/18/2019 Finance Disaster Handbook

    27/72

    PHASE 4: RECOVERY

    Finance Disaster Recovery Manual—Revised November 201427

    Public AssistancePublic Assistance is aid to State or local governments to pay part of the costs of rebuilding a

    community's damaged infrastructure. Public Assistance may include debris removal, emer-

    gency protecve measures and public services, repair of damaged public property, loans

    needed by communies for essenal government funcons and grants for public schools.The two most commonly used Federal public assistance program agencies are Federal High-

    way Administraon and Federal Emergency Management Agency. 

    Eligibility 

    Federal-aid highways are public roads that are classied as arterial, urban collectors and

    major rural collectors. To idenfy eligible Federal-aid roadways, the Guidance for the Func-

    onal Classicaon of Highways web link is listed on References page. There are two cate-

    gories of emergency relief. Emergency repairs are repairs undertaken during or immediately

    aer a disaster to restore essenal trac, to minimize the extent of damage or to protect

    the remaining facilies. Permanent repairs are those repairs undertaken aer the occur-

    rence of a disaster to restore the highway to its pre-disaster condion. Funds are primarily

    used for permanent work and are granted on the basis of inspecons performed by FHWA

    and State highway personnel.

    As a general rule, the esmated cost for repairs must require at least $700,000 for Federal

    road and bridge damage and $5,000 for each damage site (emergency and permanent re-

    pairs) in ER funding before the FHWA will consider approving the disaster or catastrophic

    failure as eligible for funding under the ER program.

    FHWA administers the Emergency Relief (ER) Pro-

    gram to assist State and local governments with the

    repair of Federal aid roads and bridges damaged

    during disasters. The applicability of the ER program

    to a natural disaster is based on the extent and in-tensity of the disaster. Damage to highways must be

    severe, occur over a wide area and result in unusu-

    ally high expenses to the highway agency. This pro-

    gram supplements the commitment of resources by

    States, their polical subdivisions, or other Federal

    agencies to help pay for unusually heavy expenses

    resulng from extraordinary condions.

  • 8/18/2019 Finance Disaster Handbook

    28/72

    PHASE 4: RECOVERY 

    Finance Disaster Recovery Manual—Revised November 201428 

    Project Management

    Approved ER funds are available at the pro-rata share that would normally apply to the

    damaged Federal-aid facility. For most projects, the recipient of ER assistance is TxDOT.

    Projects are iniated by the signing of a contract between TxDOT and COH dening roles

    and responsibilies of each party. Funding is issued as a reimbursement program. Localgovernments work with TxDOT district sta to idenfy and priorize funding for projects.

    Aer priorizing needs in the context of available funding, the district sta updates and

    coordinates these plans. Aer the project is complete, the TxDOT and DRG will coordinate

    to perform a close-out accounng for project funds.

    TxDOT requires the following project support documents to be completed by COH: 

    Through the public assistance (PA) program, FE-

    MA provides supplemental Federal disaster grant

    assistance for debris removal, emergency protec-

    ve measures, the repair, replacement, or resto-

    raon of disaster-damaged, publicly owned facili-

    es. Such assistance may take the form of equip-

    ment, supplies, personnel, or other available ca-

    pabilies. FEMA is responsible for managing the

    program, approving grants and providing tech-

    nical assistance to the State and the City of Hou-

    ston. The State, in most cases, acts as the Grantee for the PA program. The State educates

    potenal applicants, works with FEMA to manage the program, and is responsible for im-

    plemenng and monitoring the grants awarded under the program. PA reimbursements

    provide funding on a percentage basis to eligible applicants who have suered damages as

    a result of a Presidenally declared disaster and whose damages are within a county au-

    thorized for PA. Aer a declaraon, FEMA designates the area eligible for federal assis-

    tance, and the types of assistance available. Implementaon of the PA Program is man-

    aged by FEMA in partnership with the State.

    Detailed damage inspecon report 

    Damage survey summary report 

    ER program of projects 

    Maps of damaged areas 

    Before and aer photos 

  • 8/18/2019 Finance Disaster Handbook

    29/72

    PHASE 4: RECOVERY

    Finance Disaster Recovery Manual—Revised November 201429

    Eligibility Thresholds FEMA and the State require that the applicant, facility, work and costs are eligible and meet

    applicable criteria. The order in which eligibility is evaluated starts with applicant eligibility

    and ends with the eligibility of cost.

    All four basic components for the Public Assistance Pro-

    gram must meet eligibility: 

    1)  The applicant must be eligible to receive assistance. 

    2)  The applicant’s facility must be eligible. 

    3)  The work must be designated as eligible. 

    4)  The cost of performing the approved work must be

    eligible for reimbursement. 

    Categories of Work

    Eligible work is idened as Emergency Work and Perma-

    nent Work:

    Emergency Work is an acvity done immediately aer a disaster to save lives, protect

    and preserve property, public health and safety and to provide essenal public services.

    The two "Emergency" work categories are idened as categories "A" and "B" and re-

    quire a six month me limit to complete work. 

    Category A: Debris Removal 

    Category B: Emergency Protecve Measures 

    Permanent Work is work required to restore a damaged facility to its pre-disaster condi-

    on. The ve "Permanent" work categories are idened as categories "C" through "G".

    There is an 18 month me limit to complete permanent work. However, the State may

    grant extensions in 6 month intervals up to 30 addional months. If the project exceeds

    48 months addional me extension must be approved by FEMA through the State. 

    Category C: Roads and Bridges 

    Category D: Water Control Facilies 

    Category E: Buildings and Equipment 

    Category F: Ulies 

    Category G: Parks, Recreaonal, and Other Facilies 

    The State has limited authority to grant me extensions, if requested. 

  • 8/18/2019 Finance Disaster Handbook

    30/72

    PHASE 4: RECOVERY 

    Finance Disaster Recovery Manual—Revised November 201430 

    Type of Projects 

    FEMA reimbursement projects are categorized

    into large or small projects according to the

    amount threshold for that year.  If the esmated

    cost of a project is equal to or exceeds this

    threshold, the project is classied as a large pro- ject. During the recovery process on a specic

    disaster, the small/large dollar threshold remains

    the same amount as existed during the year the

    disaster rst occurred.

    As a result of the Sandy Recovery Improvement Act of 2013, FEMA raised the threshold to

    $120,000 from $68,500 for large projects. This threshold is eecve for new declaraons on

    or aer February 26, 2014. Addionally, in order for a FEMA Project Worksheet to be creat-

    ed, the esmated project cost must meet the minimum threshold of $3,000.

    Small Project (Under $120,000)— The Federal share for small projects, at any point-in-me,

    is the same as for large projects. However, all of the individual small project PW’s are han-

    dled by FEMA as a group and have several dierent requirements than large projects. Small

    projects are subject to Small Project validaon, in which a review of inial supporng docu-

    mentaon and esmates are performed.

    Large Project ($120,000 and above)— A large project is any project which has a cost es-

    mate greater than the threshold for small projects. Reimbursement occurs throughout the

    repair period or aer project compleon and is based on actual expenses or costs actually

    incurred. 

    Improved Project—  Projects in which the applicant makes addional improvements while

    sll restoring the facility to its pre-disaster funcon, such as replacing a re staon that origi-

    nally had two bays with three bays. The Applicant must request approval from FEMA and

    TDEM to make the improvements PRIOR  to construcon. Project reimbursement is usually

    capped at approved Federal Share.

    Alternate Project— Occurs when the service provided by a facility is no longer needed or

    useful, although the facility was in use at the me of the disaster. Examples of alternave

    projects include the repair or expansion of other facilies, demolion of original structure,

    or the construcon of a new facility. Only permanent work projects (category C– G  on page

    29) are eligible. Funding is limited to the Federal Share or the actual costs of performing the

    alternate project, whichever is less (see Reference page). The State is noed to approve

    the project PRIOR to commencement of work. 

  • 8/18/2019 Finance Disaster Handbook

    31/72

    PHASE 4: RECOVERY

    Finance Disaster Recovery Manual—Revised November 201431

    Project Worksheet (PW) is the primary form (see Appendix 2) usedto document and request FEMA reimbursement on each project. City departments are re-

    quired to maintain a COMPLETE and ACCURATE set of records for each eligible project in ac-

    cordance with the City’s Administrave Procedure AP 4-2 (see Appendix 1). Support provid-

    ed should clearly idenfy the project by PW number and include a summary schedule ofcosts idened for the project based on the following criteria: 

    1.  Reasonable and Necessary to accomplish the work. 

    2.  Compliant  with Federal, State and local requirements for compeveprocurement. 

    3.  Reduced by all applicable credits, such as insurance proceeds, salvagevalue, and other funding sources. 

    Supporng documents such as work orders, receipts, and invoices are provided by depart-

    ments to the Disaster Recovery Group (DRG) throughout the duraon of the project.

  • 8/18/2019 Finance Disaster Handbook

    32/72

    PHASE 4: RECOVERY 

    Finance Disaster Recovery Manual—Revised November 201432 

    PW Supporng Documentaon 

    Force Account Labor is a term used to idenfy labor provided by the City’s employees rather

    than by a contractor. Labor rates include actual wages plus fringe benets paid or credited to

    personnel. The descripon of the work performed on the FEMA – Disaster Related Work

    forms must be very specic. Eligibility payroll costs includes regular me, overme, com-

    pensatory me and fringe benets (see Appendix 3).

    Required labor supporng documents are: 

    FEMA Form 90-123 Force Account Labor Summary Record (see Appendix 2);  

    Signed employee me sheets (electronic and manual) from Kronos and SAP, when appli-

    cable, with specic hours dedicated to PWs; 

    Signed and approved overme approval forms; 

    Proof of payment payroll documents; and

    Record regular and overme hours separately. 

    Required benets supporng documents are: 

    FEMA Form 90-128 Applicant's Benet Calculaon Worksheet (see Appendix 2);  

    Record the benets separately for regular and overme hours; 

    HR employee vericaon list; 

    HR payroll list; and

    Overme, compensatory me, exempt me, payroll policy prior to disaster. 

    Direct Administrave Costs (DAC) are costs for me and materials (administrave acvies)

    used in support of a specic PW. See Eligibility Chart on page 69 for Public Assistance Pro-

    gram Indirect and Direct administrave acvity list for a detailed descripon and eligible

    DAC.

    *Accuracy of date as well as me start and me stop is crical. 

    Direct Administrave Cost (DAC) Summary 

    PW # or

    Temp # Name Title

    Date of

    Work* 

    Time

    Start* 

    Time

    Stop* Hours  Work Descripon 

    8776 

    John Doe 

    Financial

    Analyst  6/2/2014 02:15 PM  3:05 PM  0:50 

    Aendance in the audit nd-

    ings meeng with State audi-

    tors 

    12356 

    John Doe 

    Financial

    Analyst  6/4/2014 10:05 AM  11:05 AM  1:00 

    Emailing project managers re-

    garding data collecon for PW

    development

  • 8/18/2019 Finance Disaster Handbook

    33/72

    PHASE 4: RECOVERY

    Finance Disaster Recovery Manual—Revised November 201433

    Force Account Materials is a term used to idenfy equipment,

    materials and supplies owned by COH prior to the disaster or

    purchased as a result of the disaster. Eligible material costs in-

    clude materials and supplies taken from exisng stock or pur-

    chased for the disaster project.

    Required supporng documents are: 

    FEMA Form 90-124 (see Appendix 2);

     

    Procurement policy; 

    List of materials used; 

    Purchase orders, invoices, and proof of payment for purchases; and 

    Proof of cost on-hand/in warehouse materials used. 

    Force Account Equipment is equipment owned by the City used to perform eligible work

    related to the disaster. Equipment rates are applied only to the me equipment is actually

    working. However, If equipment is used intermiently for more than half the normalscheduled working day, the enre day may be claimed. For vehicles, both the hours of

    use and miles driven must be recorded. 

    Required equipment usage supporng documents are: 

    FEMA Form 90-127 Force Account Equipment Summary (see Appendix 2); 

    Proof of equipment ownership; 

    Copy of inventory at the me of disaster; 

    Equipment rate source documents; 

    Signed equipment use logs with operator name; and 

    Operator “force account labor” support documents. 

    Approved rental/lease equipment supporng documents are: 

    FEMA Form 90-125 Rented Equipment Summary Record (see

    Appendix 2); 

    Rental/Lease Procurement policy; 

    Juscaon of need; 

    Rental/Lease agreement; 

    Use logs as applicable; 

    Invoices and purchase orders; 

    Proof of payment; and 

    Detailed use logs that idenfy: 

    Date & mes used;  Name of user;  Miles driven (if applicable);  Descripon of work performed; and  Duplicaon of benets and compliance cercaon. 

  • 8/18/2019 Finance Disaster Handbook

    34/72

    PHASE 4: RECOVERY 

    Finance Disaster Recovery Manual—Revised November 201434 

    Contract Work is work specied for a short period of me

    under a wrien agreement to perform services. In gen-

    eral, contracng for emergency work requires compeve

    bidding. Whether ulizing compeve or non-

    compeve procurement procedures, all costs must be

    determined reasonable by FEMA to be eligible for reim-

    bursement. 

    Required supporng documents for contracts are: 

    FEMA Form 90-126 Contract Work Summary (see Ap-

    pendix 2); 

    Approved Contractor/Vendor Contract; 

    Contractor/Vendor Procurement Documentaon:

    Publically adversed requests for bids 

    Copies of all received proposals  Contractor selecon/rejecon criteria  Cost Price Analysis 

    Noce of Award; 

    Noce to Proceed/Work Orders: 

    Signed copies of mulple Work Orders, if more than one 

    Contractor Proof of Insurance; 

    Contractor Debarment Check on SAM.gov; 

    Subcontractors: 

    Contracts  Invoices  Proof of Applicant (City) and Contractor contract monitoring and other Federal

    requirements  Debarment Check with appropriate date checked at me of review on SAM.gov 

    Contractor Invoices, mesheets and other pernent details of work completed;

    Proof of Payment: 

    Check or Proof of Bank Transfer 

    Proof of applicant (City) contract monitoring of Contractor/Vendor; 

    In order to be reimbursed for work performed under a con-

    tract that was not compevely bid, the procurement of

    that work also must NOT have been feasible under small

    purchase procedures, sealed bids, or compeve proposals. 

  • 8/18/2019 Finance Disaster Handbook

    35/72

    PHASE 4: RECOVERY

    Finance Disaster Recovery Manual—Revised November 201435

    Other pernent supporng documentaon includes: 

    Providing copies of specic codes and standards, especially if proposed repairs orreplacements exceed the pre-disaster design. 

    Lisng evidence of pre-disaster damage, such as cracks on a steel bridge coveredby rust and corrosion. 

    Providing pre-disaster inspecon reports with noted deciencies.  Idenfying ineligible work or maintenance, inacve facilies, responsibilies of

    other federal agencies, etc.  Referencing a Hazard Migaon Proposal, if included in the project.  Indicang that the project is an Improved Project, if applicable. An Improved Pro-

     ject makes addional improvements while sll restoring the facility to its pre-disaster funcon and capacity. Descripon of the overall project is required. 

    Idenfying any special equipment or construcon approach, such as heavytrucks, access roads, staging areas, coer dams, etc.

    Describing the larger acon, if the project is part of a larger one, (e.g., one build-

    ing within a complex). 

    Reporng The City ulizes both internal and external reporng to communicate the project status.

    DRG coordinates project status reports to ensure projects are staying on schedule, within

    guidelines and decrease the opportunies for potenal issues. Progress reports are crical

    to ensuring that FEMA and the State have up-to-date informaon on PA program grants.

    Departments verify supporng documentaon to transacons entered in SAP. Costs by

    project are reported by each department to DRG. Reports should be in the Expenditure

    Data Request (EDR) format shown above including percentage of compleon and cumula-

    ve costs incurred per project. Total EDR costs reported should be reconciled to SAP with

    any discrepancies or cost overruns idened for further research and approval.

     S A M  P  L  E

     

  • 8/18/2019 Finance Disaster Handbook

    36/72

    COMPLIANCE 

    Finance Disaster Recovery Manual—Revised November 201436 

    Funds Management Eligible costs are typically reimbursed by FEMA based on percentages which determines

    the Federal share. The remaining poron or percentage is paid by the City of Houston.

    DRG facilitates funds management between external fundersand internal City departments. DRG serves as a liaison for

    audits, project closeouts and assists the departments with

    accounng entries and reporng. This ongoing process re-

    quires eecve coordinaon with departmental contacts for

    cost reporng, as well as communicang with external par-

    es like FEMA and FHWA for reimbursement related issues. 

    COH DEPARTMENTS FINANCE DEPARTMENT

    (Disaster Recovery Group) 

    Record Accounng

    Entries

    Periodic &

    Quarterly

    Reporng 

    Project

    Closeout 

    Coordinate 

    Audits 

    Auditors conductreviews and submit

    audit ndings 

    Costs areincurred to

    repair &recovery 

    Costs arecaptured

    in SAP andaccording

    toEmergency

    Procurementapproval

    procedures 

    EDR (ExpenditureData Request)

    Reports arePeriodically submiedto FIN by

    Departments 

    TDEMtransfers

    funding tothe City ofHouston 

    File Appeals

    TDEM adjusts projectfunding based onaudit results and

    FEMA determinaon 

    EXTERNAL FUNCTIONS(TDEM & FEMA) 

  • 8/18/2019 Finance Disaster Handbook

    37/72

    COMPLIANCE

    Finance Disaster Recovery Manual—Revised November 201437

    Project Closeout Quarterly reports are required to be submied to

    TDEM for all projects that have not received nal

    payment. The reports explain the progress that

    has been made on the various projects. The re-

    ports are due the rst full quarter aer the closure

    of the joint eld oce. The following dates are

    deadlines for subming reports to TDEM: 

    March 31st  June 30th September 30th  December 31st 

    Quarterly reports includes: 

    Status of the project, such as percentage of construcon completed; 

    Time extensions granted, if any; 

    Projected compleon date; 

    Amount of expenditures and payment for each project; and

    Problems or circumstances that could delay the project or result in noncompliancewith the condions of the FEMA approval. 

    Extensions 

    Extension requests are generated if addional me is required beyond the established

    meframes. In that event, the status of both large and small outstanding projects are re-

    ported to TDEM as an extension request each six months aer the disaster date.  

    Juscaon for an extension must be detailed and project specic explaining:  

    Cause of the delays and why the extension is needed;

    How similar delays will be avoided in the future; and  

    All projects involved with the request. 

    Both large and small eligible projects are to be completed within the meframes below:

    Compleon Deadlines 

    Type of Work  Months 

    Debris Clearance  6 

    Emergency Work  6 

    Permanent Work  18 

  • 8/18/2019 Finance Disaster Handbook

    38/72

    COMPLIANCE 

    Finance Disaster Recovery Manual—Revised November 201438 

    Project Compleon Report 

    When all work has been performed on a project, the project is reported as 100% complete

    on the EDR by the department. DRG coordinates with the department to complete a claim

    summary form. The claim summary form (see Appendix 4) categorizes and subtotals the

    actual cost in comparison to the esmates included on the PW. The claim summary along

    with a Project Compleon Report and Cercaon (P4) with an approval signature of the

    COH authorized representave is then submied to TDEM. The submission of the claim

    summary and P4 serve as nocaon to TDEM that the project is complete and ready for

    audit. 

    The P4 form is an internal document for TDEM placed in the COH le stang: 

    All work and costs claimed are eligible; 

    All work claimed has been completed; 

    All expenses for work claimed and deemed eligible have been paid in full; and 

    No further claims for damages. 

    Record Keeping Each department must maintain an accurate and

    secure record keeping system to provide a clear

    audit trail of all documentaon and expenditures

    to be provided to the inspecon team, reviewersand/or auditors. This documentaon is crical

    for the City to receive reimbursement for eligible

    disaster related costs.

    Specic documentaon and procedures are based on the requirements of the Federal

    Oce of Management and Budget and other Federal agencies. All of the documentaon

    pertaining to a project should be led with the corresponding PW and maintained by the

    responsible City department as the permanent record of the project. These records be-

    come the basis for vericaon of the accuracy of project cost esmates during validaon

    of small projects, reconciliaon of costs for large projects and audits. 

    Supporng documents should NOT be destroyed nor archived through Records Manage-

    ment division unl three years aer the date that the Final Status Report issued by

    TDEM and received by the Finance DRG. Even if a State audit has been completed on

    your projects, the project is sll subject to further audit requests, for example by FEMA

    Oce of Inspector General, and records should sll be retained within your department.  

  • 8/18/2019 Finance Disaster Handbook

    39/72

    COMPLIANCE

    Finance Disaster Recovery Manual—Revised November 201439

    Audits Audits and quarterly reviews are conducted on all projects that have not received nal pay-

    ment. However, all approved projects are subject to random audits. These audits may be

    performed in conjuncon with a nancial statement audit, internal audit or other forms of

    aestaon engagement. Currently, Single Audit Act requires an audit of grant recipients

    expending greater than $500,000. However, this threshold will be increased to $750,000

    eecve December 26, 2014. Even though a single audit must be performed, grant recipi-

    ents also are subject to addional audits by the FEMA, Oce of Inspector General and

    State auditors for items not covered by the Single Audit.

    The City may be audited by all or one of the following: 

    Texas Department of Emergency

    Management. 

    Oce of Inspector General. 

    Federal Highway Administraon. 

    Internal Auditors. 

    External Auditors. 

    Generally, audits are performed by TDEM to verify

    eligibility and compliance with the applicable FEMA

    regulaons. 

    Audit Process Flow 

    When projects are submied for closing, TDEM begins auding projects. A lisng of pro-

     jects that will be opened for audit is communicated by State auditors to the City’s Finance

    department. A Request for Informaon (RFI) is then provided to the DRG. The RFI lists all

    documents that the auditor will need to begin the audit including supporng documenta-

    on for the reported costs.

  • 8/18/2019 Finance Disaster Handbook

    40/72

    COMPLIANCE 

    Finance Disaster Recovery Manual—Revised November 201440 

    DRG idenes which requested items require input from City departments. Documentaon

    provided to DRG should clearly idenfy the PW and associated costs. The responses are

    then compiled for review and are submied to the auditors. Note: Throughout the audit

    period, the RFI is oen updated with addional items or follow-up quesons that are

    needed to complete the audit. Finding meengs are held between COH and auditors

    throughout the process. 

    Common audit ndings are: 

    State auditors reviews the claim and submit an audit report along with a nal funding rec-

    ommendaon to Federal agencies for review and approval. The Federal agencies review the

    claim and make any necessary funding adjustments. Final reimbursement is made, or in

    some cases, a refund of excess advances is required.

    Missing overme approval forms

    Pay rate discrepancies 

    Ineligible Invoices or Receipts 

    Duplicate Invoices or Billings 

    Overstated Invoice amounts 

    Timesheet Discrepancies 

    Missing Receipts/Documentaon 

    Costs Outside Scope of Work 

    Contract/Bid Approval Deviaons 

    Time & Materials Contracts 

    Negave audit ndings may result in:

    De-obligaon (return) of funds by FEMA or FHWAAdverse City scal year end report

    General fund absorbing return of funds 

  • 8/18/2019 Finance Disaster Handbook

    41/72

    COMPLIANCE

    Finance Disaster Recovery Manual—Revised November 201441

    Audit Findings: Case Study Due to ooding from Tropical Storm Allison in June of 2001, the City per-

     formed debris removal operaons, emergency protecve measures, and

    search and rescue operaons. Following an Oce of Inspector General’s

    (OIG) audit report, FEMA de-obligated $2,500,302 based on the OIG’s nd-

    ings and recommendaons related to documentaon, equipment rates, la-

    bor costs, and project management costs. COH did not dispute $2,992 of

    the inial OIG nding. 

    An inial decision leer from FEMA is not the ulmate decision. The City may appeal any

    decision made by FEMA, whether a project worksheet assessment or an issue such as eligi-

    bility or an extension request denial. However, an appeal has to be led with the State with-

    in 60 days of receiving noce of the acon. In turn, FEMA will have 90 days to review the

    appeal and render a decision or request addional informaon.

     An appeal was led by the City, requesng the re-obligaon of $2,497,310.

    However, this request was denied due to the City not providing sucient doc-

    umentaon to evaluate the appeal resulng in a $78,169 loss. 

     A second appeal was led by the City, requesng the re-obligaon of

    $2,419,141. Due to the denial of the rst appeal for insucient documenta-

    on, over 600 hard copies and over 1,000 scanned pages of documentaon

    were submied. The documentaon included contracts, me sheets, equip-

    ment logs, and other documents 

    to support reimbursement.

    In summary, $1,320,007 of the force account labor and equipment costs and

    contract costs submied for reimbursement was re-obligated. However, the

    remaining $1,099,134 for the project management costs was denied and re-

    mained de-obligated resulng in the general fund absorbing this loss. Second

    appeals are nal and should be unnecessary if complete support is submied.

    LESSONS LEARNED may seem obvious but numerous factors contributed to

    these oversights. With improvements in planning, communicaons, and data quality, audit

    readiness has become more accurate and ecient. The revision of AP 4-2 as collaborave

    eort with stakeholders established roles and responsibilies for future events. Lines of

    communicaons were improved during this process and familiarized all with expectaons.

    Addionally, detailed data collecon processes were instuted to create an audit trail. Fi-

    nally, the annual disaster training and disaster manual aid in connually updang and pro-

    mong best pracces.

    http://www.splicesoftware.com/wp-content/uploads/2013/10/Customer-Care-Case-Study-Servus.pdf

  • 8/18/2019 Finance Disaster Handbook

    42/72

    Finance Disaster Recovery Manual—Revised November 201442 

    References FEDERAL:  2 Code of Federal Regulaons (CFR): 

    www.ecfr.gov/cgi-bin/text-idx?SID=b88be42f570bbb3fa992d90e718ee545&tpl=/ecfrbrowse/Title02/2tab_02.tpl  

    44 CFR: www.gpo.gov/fdsys/pkg/CFR-2002-tle44-vol1/content-detail.html 

    9500 Series Policy Publicaons - FEMA (Disaster Assistance Policy [DAP] series): www.fema.gov/9500-series-policy-publicaons 

    Debris Management Guide - FEMA 325/July 2007: www.fema.gov/pdf/government/grant/pa/demagde.pdf  

    Guidance for the Funconal Classicaon of Highways: 

    www.wa.dot.gov/planning/processes/statewide/related/highway_funconal_classicaons/fcauab.pdf  

    Developing and Maintaining Emergency Operaons Plans: www.fema.gov/media-library-data/20130726-1828-25045-0014/cpg_101_comprehensive_preparedness_guide_developing_and_maintaining_emergency_operaons_plans_2010.pdf  

    Public Assistance Guide-

     FEMA 322/June 2007: 

    www.fema.gov/pdf/government/grant/pa/paguide07.pdf  

    Robert T. Staord Disaster Relief and Emergency Assistance: www.fema.gov/media-library-data/1383153669955-21f970b19e8eaa67087b7da9f4af706e/staord_act_booklet_042213_508e.pdf  

    System for Award Management (SAM) www.sam.gov/portal/SAM/#1 

    State: 

    Texas Department of Public Safety, TDEM forms and publications: www.txdps.state.tx.us/dem/downloadableforms.htm 

    Secon 252-022 of the Texas Local Government: www.statutes.legis.state.tx.us/SOTWDocs/LG/htm/LG.252.htm 

    TDEM-62 Disaster Recovery Manual: www.txdps.state.tx.us/InternetForms/Forms/TDEM-62.pdf  

  • 8/18/2019 Finance Disaster Handbook

    43/72

    Finance Disaster Recovery Manual—Revised November 201443

    STATE continued:  TDEM-93 Disaster Summary Outline: 

    www.txdps.state.tx.us/InternetForms/Forms/TDEM-93.pdf  

    LOCAL:  City of Houston Finance Department: 

    www.houstontx.gov/finance/acct/general_accounting.html  

    City of Houston Emergency Management Plan: www.houstonoem.org/external/content/document/4027/1124975/1/COH%  

    COH Disaster Assistance Recovery Manual (DARM)  COH Emergency Plan Annex J Recovery  COH Emergency Plan Annex M Resource Management  COH Hazard Migaon Plan 

    City of Houston Administrave Policies and Execuve Orders: www.houstontx.gov/Administrave-Policies-and-Procedures 

    COH AP 4-2 Internal Disaster Preparaon and Recovery

     

    COH AP 5-2 Procurement Procedures  COH AP 5-3 Pey Cash  COH EO 1-14 Procurement Payment and Policies  COH EO 1-42 Purchasing Card Policy and Procedures 

    City of Houston Procurement Department: //purchasing.houstontx.gov/index.shtml  

    COH Guide to Conngency Contracng (Emergency Purchases) 

    COH Procurement Manual 

    DISCLAIMER: The informaon provided in this manual is intended as guidance ONLY and does not re-

    lieve the City of Houston and its departments of its responsibility to comply with Federal regulaons

    and policies. Documentaon requirements may change over me. The most current documentaon

    requirements for items listed in this manual can be found in the above references. 

  • 8/18/2019 Finance Disaster Handbook

    44/72 

    APPENDIX 1:Administrave

    Procedure 4-2 

  • 8/18/2019 Finance Disaster Handbook

    45/72

    APPENDIX 1

    Finance Disaster Recovery Manual—Revised November 201445

    1. AUTHORITY 

    1.1   Article VI, Section 7a, of the City Charter of the City of Houston. 

    1.2  City of Houston Emergency Management Plan. 

    2. PURPOSE 

    2.1  To outline the process by which the City implements appropriate action for collecting, documenting, main-

    taining, and reporting timely and accurate information in connection with a disaster that financially affects the

    City directly or indirectly. 

    2.2  To establish a method by which departments have cash available for use in disaster recovery.  

    3. OBJECTIVE 

    3.1  To establish a clear delineation of responsibilities for administration of a Public Assistance Program (PAP)

    grant and insurance recovery. 

    3.2 

    To establish documentation procedures whereby eligible disaster recovery costs can be reimbursed under aPAP and any insurance policy or program that exists at the time of the disaster.  

    3.3  To identify roles and responsibilities of City departments have related to collecting, documenting, and report-

    ing information during and after a disaster.

    3.4  To provide guidance, instruction for identifying and documenting Eligible Work done by City personnel and

    authorize the Finance Department (Finance) to issue procedures governing financial matters in this process

    to be used by other departments. 

    3.5  To provide for the establishment and administration of special accounts such as disaster recovery funds,

    cost center(s) and internal order numbers where all disaster related costs are captured. 

    3.6  To establish policies and procedures designed  to govern an Emergency Cash Account (ECA).  

    4. SCOPE 

    4.1   All City departments are covered by this administrative procedure.  

    CITY OF HOUSTON 

    Administrative Procedure 

    Subject: 

    Internal Disaster Preparation & Recovery 

     A.P. No: 

    4-2 Revised 

    Effective Date: 

    May 16, 2014 

  • 8/18/2019 Finance Disaster Handbook

    46/72

    APPENDIX 1 

    Finance Disaster Recovery Manual—Revised November 201446 

    4.2  With the exception of §8, this policy applies to all disasters that financially affect the City directly or indirect-

    ly, regardless of declaratory status, and will follow guidelines set forth to enhance and maximize capture of

    information to achieve maximum recovery reimbursement in the form of insurance, state, or federal reim-

    bursement programs that exist at time of disaster (i.e. Public Assistance Program, Robert T. Stafford Disas-

    ter Relief, Emergency Assistance Act, insurance policy/program, etc.).

    5. DEFINITIONS 

    Council Approval Threshold (CAT)  – State law sets the dollar threshold (currently $50,000) at which purchases mustbe solicited using a competitive process, unless specifically exempted by state law. Purchases greater than $50,000

    must also be approved by City Council.

    Disaster Data Collection Team (DDCT)  – The central preliminary damage information gathering body coordinated by

    the Office of Emergency Management (OEM), and consisting of representatives from Finance and the Administration

    & Regulatory Affairs Departments (ARA). 

    Disaster Assistance/Recovery Manual (DARM)  – Maintained by OEM, the DARM provides guidance for City depart-

    ments, along with the private sector, volunteer organizations, and citizens, outlining concept of operations, organiza-

    tional plans, responsibilities, and methods for evaluating, documenting, and reporting damages as well as short and

    long-term recovery activities of mass care, individual assistance, and public assistance following a disaster. 

    Eligible Work – Work that is (i) a direct result of a presidentially declared major disaster or emergency, (ii) within the

    designated disaster area, unless associated with sheltering or evacuation activities, (iii) the scope of work is clearly

    defined on an approved Project Worksheet (PW) and (iv) the legal responsibility of the City. The purpose of such work

    is either for emergency protective measures, permanent restoration or debris removal.  

    Emergency Cash Account  (ECA) – A fund used to facilitate needs for cash during a disaster. These monies are desig-

    nated exclusively for payment of goods or services directly associated with disaster response and recovery.  

    Emergency Work –  An activity done before, during and after a disaster to save lives, protect and preserve property,

    public health, or safety, and to provide essential public services. The two “emergency” work categories are identified

    as Categories “A” and “B”. 

    (A)   –  Debris Removal – Work to clear debris from public rights of way and other public property. 

    (B)   –  Emergency Protective Measure – Work before, during and after a disaster to eliminate / reduce imme-

    diate threats to life, public health, or safety, or to eliminate / reduce an immediate threat of significant

    damage to public and private property through cost -effective measures. 

    Federal Emergency Management Agency (FEMA) – A component of the U.S. Department of Homeland Security that

    prepares the nation for hazards, manages federal response and recovery efforts following any national incident, and

    administers the National Flood Insurance Program. 

    FEMA Kick -off Meeting  – A meeting held by the FEMA Public Assistance Coordinator, establishing a partnership

    among FEMA, state and City, and is designed to focus on the specific needs of the City, while establishing eligibility

    and documentation requirements pertaining to the disaster. 

    Public Infrastructure – For the purposes of this policy, the roads, streets, bridges, storm water systems, traffic signs

    and signals, freeway and road lighting, water and wastewater systems needed for the basic facilities and services to

    sustain a community that are maintained by the Public Works & Engineering Department (PWE).  

    Permanent Work  – Work that is required to restore a damaged facility to pre -disaster design, function, and capacity in

    accordance with applicable codes and standards. The five “permanent” work categories are identified as Categories

  • 8/18/2019 Finance Disaster Handbook

    47/72

  • 8/18/2019 Finance Disaster Handbook

    48/72

    APPENDIX 1 

    Finance Disaster Recovery Manual—Revised November 201448 

    6.3.3   Assemble when deemed safe to do so. 

    6.4  OEM is responsible for coordination of documentation related to a disaster, including: 

    6.4.1  Providing a departmental brief annually, prior to June 1, concerning the DARM, and the associ-

    ated forms and procedures outlined therein; 

    6.4.2  Ensuring all departments are trained appropriately in damage assessments and documentation

    completion. This assurance may be accomplished through regular meetings as OEM deemsappropriate and should include, at a minimum, annual training, prior to June 1, for department

    representatives assigned to take part in preliminary damage assessment; 

    6.4.3  Collecting disaster related damage information and creating the Disaster Summary Outline sub-

    mitted to the state, along with copies of the Local Disaster Declaration and the Mayor’s letter

    requesting state/federal assistance; 

    6.4.4  Preparing and coordinating the execution of applicable interlocal agreements by ensuring prior

    approvals are in place, and they are current and accessible at all times;  

    6.4.5  Ensuring City-wide compliance with the National Incident Management System (NIMS) and the

    Homeland Security Presidential Directive 5 (HSPD-5).

    6.4.6  Coordinating among state/federal representatives and the City to ensure maximum recovery; 

    6.4.7  Identifying work performed by the City that may be eligible for reimbursement in accordance

    with current FEMA regulations in conjunction with Finance and other City departments; and 

    6.4.8  Establishing documentation procedures and standards to enable maximum recovery for eligible

    City costs. 

    6.5  Finance is responsible for: 

    6.5.1  Issuance of an internal order number and implementation instructions to departments.

    6.5.2  Development and administration of all budgets, fund transfers, and all other fiscal matters per-

    taining to the disaster, including establishing and communicating a system for tracking adminis-

    trative time when preparing PWs. 

    6.5.3  Depositing disaster relief funds to the established recovery funds and provide copies of docu-

    mentation to the OEM. 

    6.5.4  Through the authority of the Finance Director, transferring funds within general and enterprise

    fund budgets in accordance with the disaster recovery fund budget, subject to Council approval

    as required by the budget ordinance and the five (5) % transfer provisions. 

    6.5.5  Working with City departments to plan and coordinate the accounting process necessary to rec-

    ord the financial transactions resulting from the disaster, including the yearly instructions to de-

    partments on record keeping.

    6.5.6  Determining the proper amount of claims to submit to FEMA, other reimbursing agencies, and

    insurance companies, working in concert with ARA’s Insurance Management Division

    (Insurance Management).

    6.5.7   Approving P-card limit adjustment plans. Authorizing and adjusting P-card limits upon disaster

  • 8/18/2019 Finance Disaster Handbook

    49/72

    APPENDIX 1

    Finance Disaster Recovery Manual—Revised November 201449

    declaration. Approving exceptions and increases after initial adjustments. Ensuring limits are ad-

     justed back to normal at some period (TBD) after the disaster.  

    6.5.8  Preparing the City’s emergency procurement policies and procedures and educating departments

    on a yearly basis on these policies and procedures.  

    6.5.9  Obtaining the Mayor’s signature for all procurements that require an exception to the City’s emer-

    gency procurement policies (with reason for exceptions, for FEMA reimbursement facilitation).

    6.5.10  Maintaining separate records of all emergency purchases made by City departments above their

    purchasing authority in support of the disaster recovery effort, and requesting Council approval

    when required. 

    6.5.11  Preparing emergency specifications and bids in a manner consistent with relevant procurement

    laws. 

    6.6   ARA is responsible for handling insurance claims pertaining to the disaster. 

    6.6.1  Insurance Management is responsible for working with departments to identify and document dam-

    ages that may be eligible for insurance recovery and the coordination and negotiation of settlement

    for all insurance claims related to the disaster. 

    6.7  The Legal Department is responsible for: 

    6.7.1  Ensuring every contract for services implemented in connection with applicable federal grant fund-

    ing has complied with applicable procurement laws and includes sufficient assurances and lan-

    guage to meet all applicable federal, state, and local requirements as well as any insurance proce-

    dures. 

    6.7.2   Assisting OEM in the preparation of interlocal agreements by ensuring prior approvals are in place,

    and that the agreements are current and accessible at all times. 

    6.7.3   Assisting in determining the eligibility of costs under the Stafford Act and other relevant state and

    federal disaster laws. 

    6.7.4  Filing appeals to FEMA, if necessary. 

    6.8   All departments are responsible for: 

    6.8.1  Completing preliminary damage information for all property (e.g. buildings, vehicles, etc.) for which

    they are assigned responsibility. 

    6.8.2   Assigning representatives to work in conjunction with the DDCT, and with the state and federal

    government. These representatives will attend training coordinated through the OEM. Representa-tives will be responsible for reporting damage, providing updates on damage assessments, monitor

    repairs, and report completed repairs. These representatives shall include: 

    6.8.2.1  One or more employees who are knowledgeable of the damages and capable of re-

    porting such damages; and 

    6.8.2.2  One or more employees who will handle the financial documentation. 

    6.8.3  Completing the required City Preliminary Property Damage Form (Attachment A) and submitting

    those forms to the DDCT within three calendar (3) days of the disaster. 

  • 8/18/2019 Finance Disaster Handbook

    50/72

    APPENDIX 1 

    Finance Disaster Recovery Manual—Revised November 201450 

    6.8.4  Completing and maintaining separate records of all forms and providing such documentation as

    is necessary to identify costs related to federal, state, or insurance Eligible Work. 

    6.8.5  Providing all necessary information and assistance to federal officials performing damage esti-

    mates and the City’s insurance representatives. 

    6.8.6  Understanding that signatures on each form certify that all information summarized and/or at-

    tached is true and correct. 

    6.8.7  Completing, documenting and maintaining their own internal departmental costs for the purpose

    of keeping disaster expenses separate from day-to-day operations. These records shall be main-

    tained for audit purposes.

    6.8.8  Performing any emergency work required and for formulating and/or review of all bid specifica-

    tions developed for permanent work on facilities for all buildings for which, at the time of the dis-

    aster, they are assigned responsibility.