Agenda
• Go-Live Target Date• ITS Progress • Change Management Overview
– User Testing– Training Plan– Communications
• UL Action Items• ITS Next Steps
05/18/112
Target Go-Live DateAugust 2011
S M T W T F S
1 2 3 4 5 6
7 8 9 10 11 12 13
14 15 16 17 18 19 20
21 22 23 24 25 26 27
28 29 30 31 1 2 3
05/18/113
• July 2011: – Finalize go-live date based on:
• System testing of end-to-end processes• Business Process Owner input
– Announce transaction cutoff dates and process workarounds
M-Pathways unavailable:Aug. 4 @ 5 p.m. – Aug. 9 @ 7 a.m. Reporting environments available
ITS 9.1 Upgrade Progress
05/18/114
These three areas occur along overlapping timeframes.
University departments and business process owners contribute to each of these areas.
As of 05/13/11
Overall, the level of system and business process change for 9.1 is low.But there are some changes…
9.1 Changes by Module
• Procurement: – ePro Req profile– New look for the ePro Req
• Same data entry and business processes
– New ePro Req approval rule • Department manager approval
• Inventory:– Fewer steps for fulfillment process
• Asset Management:– Departmental security removed
05/18/115
05/18/116
Change Management Overview
You & your unit
TestingTesting
Training
Training
Email &
Other
Email &
Other
Participate in user testing•Pre-test survey•Hands-on activities•Validate & evaluate 9.1
Review My LINC material:•July: change information for existing users•August: new user training
Read and review:•Upgrade communications•Upgrade web sitehttp://www.mais.umich.edu/fin/9.1-upgrade.html
User Testing• Why: Solicit feedback
– Current M-Pathways use• How a task fits into your job• Successes/challenges
– 9.1 functionality• Impact of changes• Successes/challenges
• What: eProcurement Reqs• Where: WOTO training rms• When: June 14 – 16 & 20
– 2 hour sessions, AM or PM
05/18/117
• Who: Current ePro users– Experienced users– Infrequent users
• Selected by M-Pathways statistics & Help Desk calls
User Testing
How we will communicate?• Email FIN ULs (May 19)
– Proposed participant list– Request for participants’ time
• Email participants (June 1)– Registration instructions– Pre-testing survey
• Web site (post testing)– Testing information– Feedback summary– http://www.mais.umich.edu/
fin/9.1-upgrade.html
What will ITS use the info for?• Validate system test
conditions• Improve performance
support content• Identify best practices• Improve customer service
05/18/118
Training Plan
05/18/119
July/August 2011 S M T W T F S
1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30
31 1 2 3 4 5 6
7 8 9 10 11 12 13
• Use My LINC to deliver training materials – Simulations– Job aids (e.g., procedures, overviews of change)
9.1 procedures available
New user training available
Potential Interchanges & Webinars
Upgrade Communications
• Communication Archive available @http://www.mais.umich.edu/fin/9.1-upgrade-comm-
archive.html
05/18/1110
UL Action ItemsUser Testing• By 05/27/11:
– Review list of participants – Notify supervisors about
request for staff time in mid-June
– Identify alternate participant, if necessary
Unit Readiness• Advertise upgrade
deadlines in your unit:– RDA users – verify contacts – PS Query users – rename or
delete public FINPROD queries by 07/20/11
– FIN users – review updated training materials in July
• Stay informed – visit the upgrade web site– http://www.mais.umich.edu/
fin/9.1-upgrade.html
05/18/1111
ITS Next Steps• Continue system testing & performance
support activity• Conduct user testing
– Central Office (May – June)– Departmental (June)
• Release table change information in June to:– RDA users– PS Query users– UM Data Warehouse/BusinessObjects users
05/18/1112