fire station 30 city of lauderhill, florida rfp number
TRANSCRIPT
FIRE STATION 30
City of Lauderhill, Florida RFP NUMBER: 2020-012
March 13, 2020 BID Due: March 25, 2020 @ 3:45 PM
ADDENDUM NUMBER 9
The following items are issued to add to, modify, and/or clarify the Contract Documents and Specifications. These items shall have become a part of, and have full force and effect of the Contract Documents and all costs and time involved to comply with said addendum shall be included in the Bid Price.
Description of change:
I. Revisions to Bid Plans
II. Revisions to Bid Specifications
III. Responses to Bid RFI’s
Question 1: Bid bond percentage? Answer 1: 10% Question 2: Will the City provide a revised Bid Form with a line item for permit fees per response to Question 26 on Addendum 4? Please clarify. Answer 2: Would recommend an allowance for permit fees, suggest $50,000.00. Welcome City input on this.
Question 3: Addendum 7 dated 3/2/2020 on Questions number 2, 7 & 8 are related to fuel tank, the answer refers to attached document, but no attached document related to fuel tank it is part of the addendum. Please clarify Answer 3: Please find responses below. Addendum #7, Question #2 Question 2: What are the specifications for the above ground fuel tank? Answer 2: See site plan Dwg. AS-101 Rev. #1. 1,000 GALLON UL 2085, ABOVE GROUND CARBON STEEL FUEL TANK & PUMP ON 8" (24'-0" x12'-0" ) CONCRETE SLAB W/# 5 @ 18" O.C. EACH WAY. INSTALL PER MANUFACTURES SPECIFICATION. FINISH: EPOXY PRIMER, PAINT. COORDINATE COLOR WITH OWNER. Same response provided in Addendum #4 dated 02.06.20. Addendum #7, Question #7 Question 7: Regarding the requirement for bidders to furnish, install & fill the LP tank, what is the size (gallons) of the LP tank? Answer 7: See site plan Dwg. AS-101 Rev. #1. 1,000 GALLON UL 2085, ABOVE GROUND CARBON STEEL FUEL TANK & PUMP ON 8" (24'-0" x 12'-0" ) CONCRETE SLAB W/# 5 @ 18" O.C. EACH WAY. INSTALL PER MANUFACTURES SPECIFICATION. FINISH: EPOXY PRIMER, PAINT. COORDINATE COLOR WITH OWNER. Same response provided in Addendum #4 dated 02.06.20. Addendum #7, Question #8 Question 8: Will bidder be required to fill the above ground fuel tank? If so, what type of fuel is required? Answer 8: Yes, bidder required to fill the fuel tank. Diesel. Question 4: Addendum 4 / Answer to question no. 3 does not provide any clarification on the lightning protection system. Please clarify. Answer 4: Lighting protection system to be provided by the bidders. Specialty subcontractor to the GC to provide Engineered shop drawings for design team review and approval. Question 5: Did a LEED charrette take place? If so, please share these meeting notes with the design / construction team. Answer 5: LEED related topics were discussed amongst the Design Team during design process. There are no formal notes to share with the construction team. Question 6: Has a LEED scorecard been developed to show credits being pursued and project’s possible point total? Answer 6: Attached please find preliminary LEED Scorecard.
Question 7: Regarding addendum #7, we can find no attachments for the following items; 2, 3, 7, 8. Please provide this information so we can complete out bid. Answer 7: Please find responses below. Addendum #7, Question #2 Question 2: What are the specifications for the above ground fuel tank? Answer 2: See site plan Dwg. AS-101 Rev. #1. 1,000 GALLON UL 2085, ABOVE GROUND CARBON STEEL FUEL TANK & PUMP ON 8" (24'-0" x12'-0" ) CONCRETE SLAB W/# 5 @ 18" O.C. EACH WAY. INSTALL PER MANUFACTURES SPECIFICATION. FINISH: EPOXY PRIMER, PAINT. COORDINATE COLOR WITH OWNER. Same response provided in Addendum #4 dated 02.06.20. Addendum #7, Question #3 Question 3: Addendum 4, question 3 notes an E-107 plan page which is not in our plan set, is this a typo or will be page be issued? Please advise. Answer 3: Dwg. E-107 removed from set. Information can be found on Dwgs. E-100 and E-104. Addendum #7, Question #7 Question 7: Regarding the requirement for bidders to furnish, install & fill the LP tank, what is the size (gallons) of the LP tank? Answer 7: See site plan Dwg. AS-101 Rev. #1. 1,000 GALLON UL 2085, ABOVE GROUND CARBON STEEL FUEL TANK & PUMP ON 8" (24'-0" x 12'-0" ) CONCRETE SLAB W/# 5 @ 18" O.C. EACH WAY. INSTALL PER MANUFACTURES SPECIFICATION. FINISH: EPOXY PRIMER, PAINT. COORDINATE COLOR WITH OWNER. Same response provided in Addendum #4 dated 02.06.20. Addendum #7, Question #8 Question 8: Will bidder be required to fill the above ground fuel tank? If so, what type of fuel is required? Answer 8: Yes, bidder required to fill the fuel tank. Diesel. Question 8: Is the contractor required to provide the BDA Public Safety System? Answer 8: Yes, bidder to provide. Question 9: Is the contractor required to provide the cellular DAS system Answer 9: Yes, bidder to provide. Question 10: Is the contractor required to provide the Broward Fire Station Alerting System Answer 10: Yes, bidder to provide. The fire station alerting system is a single source vendor and is proprietary to the regional dispatch system.
I/we have read the addendum/ Signature Date
BBQ
APPARATUS BAY
119
GENERATOR
114
ELECT
116
MECH
115
BUNK #3
109
BUNK #1
107
BUNK #2
108
DAY ROOM
106
BUNK #6
112
BUNK #4
110
BUNK #5
111
PUBLIC
RESTROOM
127
IT
126
WALK-IN CARE/
TRIAGE
129
LAUNDRY
128
KITCHEN
104
LOBBY
101
WATCH
102
MEN
RESTROOM
117
WOMEN
RESTROOM
118
FITNESS ROOM
125
LIEUTENANT
OFFICE
103
DINING
105
CORRIDOR #1
113
2,455 SF
211 SF
117 SF104 SF
78 SF
367 SF
47 SF
127 SF
38 SF
358 SF
237 SF
154 SF
222 SF
480 SF
138 SF
230 SF
128 SF
78 SF 78 SF
78 SF78 SF78 SF
222 SF
180 SF
BUNKER
120
181 SF
LAUNDRY
ROOM
121
108 SF
EQUIPMENT
CLEANING
122
64 SF
EMS
SUPPLIES
123
64 SF
EQUIPMENT
STORAGE
124
375 SF
UP
CORRIDOR #2
113A
170 SF
CORRIDOR #4
113C
262 SF
CORRIDOR #3
113B
252 SF
CORRIDOR #5
113D
171 SF
CORRIDOR #6
113E
128 SF
17
1810
11
11
10
10
12
13
14
15
16
8
.8
8
8
P
P
1/2
1/2
UPUP
UP
UP
UP
25
'-0
"
S
ET
BA
CK
60'-5"
5'-1
"1
8'-0
"2
4'-0
"
14
'-8
"
10
'-4
"
5'-0"
SETBACK
84
'-8
"
122'-9"
12'-0"40'-2"21'-0"10'-0"
15
'-4
"5
'-8
"5
6'-1
0"
88
'-4
"
12'-0"40'-2"19'-8"31'-3"19'-8"
122'-9"
18'-4"9'-0"9'-0"9'-0"9'-0"9'-0"9'-0"9'-0"9'-0"
10
'-4
"
16'-1"6'-3"
3'-9
"
3'-1
"
61
'-9
"
S
ET
BA
CK
35
'-5
"
43
'-4
"
41
'-1
"
42
'-0
"
28
'-9
"
9'-0
"
26'-7" 18'-0" 5'-0" 2'-8"
29'-7"
70
'-3
"
9'-4" 32'-1" 9'-0" 9'-0"
31'-3"
10
'-6
"
6'-0"
13
'-0
"
2'-0
"
6'-0"
10
NEW CATCH BASIN REFER TO
CIVIL PLANS FOR MORE
INFORMATION
NEW CATCH BASIN REFER TO
CIVIL PLANS FOR MORE
INFORMATION
NEW CATCH BASIN REFER TO CIVIL
PLANS FOR MORE INFORMATION
NEW CATCH BASIN REFER TO
CIVIL PLANS FOR MORE
INFORMATION
NEW CATCH BASIN REFER TO
CIVIL PLANS FOR MORE
INFORMATION
25'-0" FLAG POLE REFER
TO 1/AS-102 FOR MORE
INFORMATION
CODE REQUIRED / PROVIDED
BIKE RACK REFER TO 2-AS-102
FOR MORE INFORMATION
DEMO EXISTING
ISLAND AND CURB
REFER TO CIVIL
PLANS FOR MORE
INFORMATION.
NEW LOCKABLE 24'-0" SLIDING GATE
REFER TO 5,6 /AS-102 FOR MORE
INFORMATION
NEW 8'-0" CONCRETE -PRE
CAST PRIVACY WALL REFER
TO DETAIL 5,6/AS-102 FOR
MORE INFORMATION
FIRE HYDRANT
TRASH
CARD READER
WITH INTERCOM
HANDICAP SIDEWALK
RAMP TYPICAL REFER
TO CIVIL PLANS FOR
MORE INFORMATION
EXISTING BUS SHELTER
TO REMAIN
FUEL
TANK
EXISTING BUS STOP SIGN TO BE
RELOCATED.
NEW CONCRETE SIDEWALK
EXTENSION FOR BUS STOP
EXISTING SIDEWALK
TO REMAIN
EXISTING SIDEWALK
TO REMAIN
+9.00
F.F.E.
+9.00
F.F.E
+9.00
F.F.E.
+9.00
+8.50
F.F.E
+9.00
7.00
+9.00
+9.00
+9.00
9.00
9.00
8.40
7.40
EXISTING
PEDESTRIAN
CROSSING SIGN TO
BE RELOCATED.
NEW CATCH BASIN REFER TO
CIVIL PLANS FOR MORE
INFORMATION
NEW MAN HOLE REFER TO
CIVIL PLANS FOR MORE
INFORMATION
CODE REQUIRED / PROVIDED
BIKE RACK REFER TO
2-AS102 FOR MORE
INFORMATION
NEW CONCRETE APRON REFER
TO STRUCTURAL DRAWINGS
FOR MORE INFORMATION
NEW CONCRETE APRON REFER
TO STRUCTURAL DRAWINGS
FOR MORE INFORMATION
9'-0
"1
2'-0
"5
'-0
"
NEW 8'-0" PRIVACY WALL
REFER TO DETAIL 5,6 /AS-101
FOR MORE INFORMATION
NEW RAMP REFER TO 3-AS102
FOR MORE INFORMATION
+9.00 +8.5
+8.5
RELOCATED BUS
STOP SIGN
RELOCATED
PEDESTRIAN
CROSSING SIGN.
17'-3"
89'-10"
10'-8"
14
'-7
"
5'-4
"
10'-1"
9'-0
"
5'-0
"3
'-1
"
4'-5"
8'-0" 4'-0"
4'-6
"
16'-8"
50
'-0
"
2'-0"
22'-3"
SETBACK
30'-2"
5'-0
"6
'-1
"
7'-8" 5'-10" 4'-0" 16'-9"
6'-4" 7'-2"
11
'-1
"
5'-9" 5'-0" 6'-5"
7'-6
"
3'-0
"
4
22'-3"
ACCESSIBLE PARKING
SIGNAGE REFER TO
4/AS-102 FOR INFO
AS-102
6
NEW 8'-0" PRIVACY WALL REFER TO
DETAIL 5/AS-102 AND STRUCTURAL
DRAWINGS FOR MORE INFORMATION
WITH ALUM. METAL CANOPY SYSTEM
ABOVE. TO DESIGNED BY LICENSED
FLORIDA ENGINEER. CONTRACTOR TO
PROVIDE SHOP DRAWING FOR REVIEW
AND APPROVAL .
SECURITY CAMERA
SECURITY
CAMERAS
SECURITY CAMERA
SECURITY CAMERA
SECURITY CAMERA
SECURITY CAMERA
SECURITY CAMERA
NEW BELOW GROUND
LP FUEL TANK
SECURITY CAMERA
SECURITY
CAMERAS
FREE STANDING COMMUNICATION
CONCRETE POLE TO BE DESIGNED
BY FLORIDA ENGINEER AND
INSTALLED BY THE CONTRACTOR
NEW CONCRETE DRIVE
T
PROPOSED
TRANSFORMER
3'-0
"
6'-0" 3'-0"
6'-0
"
1,000 GALLON UL 2085, ABOVE GROUND
CARBON STEEL FUEL TANK & PUMP ON
8" (24'-0" x12'-0" ) CONCRETE SLAB
W/# 5 @ 18" O.C. EACH WAY. INSTALL
PER MANUFACTURES SPECIFICATION.
FINISH: EPOXY PRIMER, PAINT
COORDINATE COLOR WITH OWNER.
4'-0
"4
'-2
"1
5'-1
0"
4'-8" 4'-2"4'-2"
4'-0
"
4'-2
"
ZONING CLASSIFICATION:
PROPOSED USE:
CO (COMMERCIAL, OFFICE)
RESIDENTIAL/ STORAGE
LAND USE DESIGNATION:
MAX. BUILDING HEIGHT PROVIDED:
FRONT YARD SETBACK =
REAR YARD SETBACK =
SIDE YARD SETBACK =
100
50'-0" A.F.F.
WATER & SEWER:
STORM WATER:
CITY OF LAUDERHILL
CITY OF LAUDERHILL
FLORIDA POWER & LIGHT CO.
ELECTRIC:
TOTAL SITE AREA:
BUILDING FOOTPRINT AREA
VEHICULAR USE AREA
PEDESTRIAN WALKS
IMPERVIOUS AREAS
TOTAL
18,874.45 S.F.
1,729.79 S.F.
5,907.17 S.F.
8,539.00 S.F.
26,250.00 S.F. (0.6026 ACRES)
32.52%
7.41%
.23%
68.37%
100.00%
SITE CALCULATIONS:
UTILITIES:
SITE INFORMATION:
VEHICLE PARKING CALCULATION:
LAND USE CLASSIFICATION: 100
26,250.00 S.F.
PARKING USE AREA
23.38%
STORAGE , DUMPSTER
2,257.19 S.F.
23.38%
PERVIOUS AREAS7,375.55 S.F.
31.63%
24'-8" A.F.F.
25'-0" FT 25'-0" FT
25'-0" FT 61'-8" FT
0'-0" FT
22'-3" FT (WEST)
ALLOWED PROVIDED
5'-0" FT (EAST)
441.30 S.F.
PARKING RATIO REQUIREMENT: 1 PLUS 1
PARKING REQUIRED: 14
PARKING PROVIDED: 14
(1 HC)
(1 HC)
FUEL TANK
(RE: PLAN)
T.O. SLAB
1
2
" DIA EXP. BOLT (MIN 4)
W/ 4" MIN EMBED (RE:
MFR FOR LOCATIONS)
CONCRETE SLAB
(RE: PLAN)
REV DATE DESCRIPTION
E:\1465-161216 Lauderhill F
ire S
tation N
o. 30\D
raw
ings\3-4-A
S-101-A
S-102.dw
g 11/5/2019 2:19:44 P
M
SHEET TITLE:
SHEET NUMBER:
DRAWN BY:
CHECKED BY:
SITE PLAN
SH
MR
AS-101
SHEET TITLE:
SHEET NUMBER:
DRAWN BY:
CHECKED BY:
Copyright (c) by SYNALOVSKI ROMANIK SAYE, LLC
All Rights Reserved.
REV DATE DESCRIPTION
LICENSE NO. AA26001863
CLIEN
T:
DESIGN
DELIVERABLE:
ISSUE DATE:
PROJECT NUMBER:
CIT
Y O
F LA
UD
ER
HILL
FIR
E ST
AT
IO
N N
O. 30
4051 N
.W
. 16TH
STREET
LAU
DERH
ILL, FLO
RID
A 33313
CIT
Y O
F LA
UD
ER
HILL
PERMIT
SUBMITTAL
07.03.19
1465-161216
1
SITE PLAN
SCALE: 3/32"= 1'-0"
2
SITE DATA INFORMATION
SCALE: 3/32"= 1'-0"
3
FUEL TANK DETAIL
SCALE: 3/4"=1'-0"
1
1
1
REV DATE DESCRIPTION
1 11/04/19 RE-BID/PER BLDG DEPT. COMMENT
LEED v4 for BD+C: New Construction and Major RenovationProject Checklist City of Lauderhill, Fire Station #30
6/7/2017
Y ? N1 Credit 1
11 2 3 16 5 3 3 13Credit 16 Y Prereq Required
1 Credit 1 Y Prereq Required
2 Credit 2 3 Credit 5
2 2 1 Credit 5 1 1 Credit 2
5 Credit 5 1 1 Credit 2
1 Credit 1 1 1 Credit Building Product Disclosure and Optimization - Material Ingredients 2
1 Credit 1 2 Credit 2
1 Credit Green Vehicles 1
8 1 0 Indoor Environmental Quality 168 0 2 10 Y Prereq Required
Y Prereq Required Y Prereq Required
1 Credit 1 2 Credit 2
2 Credit 2 1 Credit 3
1 Credit 1 1 Credit Construction Indoor Air Quality Management Plan 1
3 Credit 3 1 Credit 2
2 Credit 2 1 Credit 1
1 Credit 1 1 1 Credit 2
Credit 3
5 4 2 11 Credit 1
Y Prereq Required 1 Credit 1
Y Prereq Required
Y Prereq Building-Level Water Metering Required 6 0 0 Innovation 62 Credit 2 5 Credit 5
2 4 Credit 6 1 Credit 1
2 Credit 2
1 Credit Water Metering 1 4 0 0 Regional Priority 41 Credit Regional Priority: Specific CreditSensitive Land Protection 1
10 8 5 33 1 Credit Regional Priority: Specific CreditOpen Space 1
Y Prereq Required 1 Credit Regional Priority: Specific CreditRain water management 1
Y Prereq Required 1 Credit Regional Priority: Specific CreditLight Pollution or Outdoor use water reduction 1
Y Prereq Required
Y Prereq Required 58 18 15 TOTALS Possible Points: 1106 Credit 6
8 Credit 18
1 Credit 1
2 Credit 2
3 Credit 3
1 Credit 1
2 Credit 2
Site Development - Protect or Restore Habitat
Building Product Disclosure and Optimization - Sourcing of Raw Materials
Project Name:
Date:
Location and Transportation
Sensitive Land Protection
LEED for Neighborhood Development Location
Bicycle Facilities
Construction and Demolition Waste Management Planning
Materials and ResourcesStorage and Collection of Recyclables
Construction and Demolition Waste Management
Minimum Indoor Air Quality Performance
Building Product Disclosure and Optimization - Environmental Product
Declarations
Integrative Process
Construction Activity Pollution Prevention
High Priority Site
Surrounding Density and Diverse Uses
Sustainable Sites
Building Life-Cycle Impact Reduction
Green Power and Carbon Offsets
Heat Island Reduction
Outdoor Water Use Reduction
Indoor Water Use Reduction
Outdoor Water Use Reduction
Indoor Water Use Reduction
Enhanced Commissioning
Building-Level Energy Metering
Water Efficiency
Fundamental Commissioning and Verification
Demand Response
Renewable Energy Production
Enhanced Refrigerant Management
Optimize Energy Performance
Advanced Energy Metering
Certified: 40 to 49 points, Silver: 50 to 59 points, Gold: 60 to 79 points, Platinum: 80 to 110
Access to Quality Transit
Reduced Parking Footprint
Open Space
Site Assessment
Interior Lighting
Daylight
LEED Accredited Professional
Innovation
Rainwater Management
Light Pollution Reduction
Environmental Tobacco Smoke Control
Energy and Atmosphere
Minimum Energy Performance
Fundamental Refrigerant Management
Cooling Tower Water Use
Acoustic Performance
Quality Views
Enhanced Indoor Air Quality Strategies
Low-Emitting Materials
Indoor Air Quality Assessment
Thermal Comfort