flexi hybrid commissioning manual

111
 FlexiHybrid Commissioning Manual  FlexiHybrid Commissioning SVR 1.3 911-448/02C0000 Issue 2, November 2008

Upload: saqib-naveed

Post on 10-Oct-2015

188 views

Category:

Documents


38 download

DESCRIPTION

Flexi Hybrid Commissioning Manual

TRANSCRIPT

  • FlexiHybrid

    Commissioning Manual

    FlexiHybrid Commissioning SVR 1.3

    911-448/02C0000Issue 2, November 2008

  • 2 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480dc

    The information in this document is subject to change without notice and describes only the product defined in the introduction of this documentation. This documentation is intended for the use of Nokia Siemens Networks customers only for the purposes of the agreement under which the document is submitted, and no part of it may be used, reproduced, modified or transmitted in any form or means without the prior written permission of Nokia Siemens Networks. The documentation has been prepared to be used by professional and properly trained personnel, and the customer assumes full responsibility when using it. Nokia Siemens Networks welcomes customer comments as part of the process of continuous development and improvement of the documentation.

    The information or statements given in this documentation concerning the suitability, capacity, or performance of the mentioned hardware or software products are given "as is" and all liability arising in connection with such hardware or software products shall be defined conclusively and finally in a separate agreement between Nokia Siemens Networks and the customer. However, Nokia Siemens Networks has made all reasonable efforts to ensure that the instructions contained in the document are adequate and free of material errors and omissions. Nokia Siemens Networks will, if deemed necessary by Nokia Siemens Networks, explain issues which may not be covered by the document.

    Nokia Siemens Networks will correct errors in this documentation as soon as possible. IN NO EVENT WILL Nokia Siemens Networks BE LIABLE FOR ERRORS IN THIS DOCUMENTA-TION OR FOR ANY DAMAGES, INCLUDING BUT NOT LIMITED TO SPECIAL, DIRECT, INDI-RECT, INCIDENTAL OR CONSEQUENTIAL OR ANY LOSSES, SUCH AS BUT NOT LIMITED TO LOSS OF PROFIT, REVENUE, BUSINESS INTERRUPTION, BUSINESS OPPORTUNITY OR DATA,THAT MAY ARISE FROM THE USE OF THIS DOCUMENT OR THE INFORMATION IN IT.

    This documentation and the product it describes are considered protected by copyrights and other intellectual property rights according to the applicable laws.

    The wave logo is a trademark of Nokia Siemens Networks Oy. Nokia is a registered trademark of Nokia Corporation. Siemens is a registered trademark of Siemens AG.

    Other product names mentioned in this document may be trademarks of their respective owners, and they are mentioned for identification purposes only.

    Copyright Nokia Siemens Networks 2008. All rights reserved

    f Important Notice on Product Safety Elevated voltages are inevitably present at specific points in this electrical equipment. Some of the parts may also have elevated operating temperatures.

    Non-observance of these conditions and the safety instructions can result in personal injury or in property damage.

    Therefore, only trained and qualified personnel may install and maintain the system.

    The system complies with the standard EN 60950 / IEC 60950. All equipment connected has to comply with the applicable safety standards.

    The same text in German:

    Wichtiger Hinweis zur Produktsicherheit

    In elektrischen Anlagen stehen zwangslufig bestimmte Teile der Gerte unter Span-nung. Einige Teile knnen auch eine hohe Betriebstemperatur aufweisen.

    Eine Nichtbeachtung dieser Situation und der Warnungshinweise kann zu Krperverlet-zungen und Sachschden fhren.

    Deshalb wird vorausgesetzt, dass nur geschultes und qualifiziertes Personal die Anlagen installiert und wartet.

    Das System entspricht den Anforderungen der EN 60950 / IEC 60950. Angeschlossene Gerte mssen die zutreffenden Sicherheitsbestimmungen erfllen.

  • 911-448/02C0000Issue 2, November 2008

    3

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480dc

    Table of ContentsThis document has 111 pages.

    1 Preliminary information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111.1 Foreword. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111.1.1 Object of the present manual . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111.1.2 Applicability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111.1.3 Manual status . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111.1.4 Introduction to this document . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111.2 Safety rules and precautionary measures . . . . . . . . . . . . . . . . . . . . . . . . . 121.2.1 RF Energy Health Hazard. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121.2.2 Protection against Lightning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121.2.3 Protection from RF Burns . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 131.2.4 Risk of Personal Injury from Fiber Optics . . . . . . . . . . . . . . . . . . . . . . . . . . 131.2.5 Warning This is a Class A product. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 131.2.6 Warning Turn off all power before servicing . . . . . . . . . . . . . . . . . . . . . . 131.2.7 Safety Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13

    2 Test instrument list and measurement accessories . . . . . . . . . . . . . . . . . . 142.1 Test Instruments . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 142.2 Typical test bench overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15

    3 System Operating Mode . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16

    4 ODU and Modem Module connection. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17

    5 System configuration and line-up phase. . . . . . . . . . . . . . . . . . . . . . . . . . . 185.1 Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 185.1.1 Installation Check . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 185.1.2 Terminal station configuration summary . . . . . . . . . . . . . . . . . . . . . . . . . . . 195.1.3 Antennas alignment (both terminal stations). . . . . . . . . . . . . . . . . . . . . . . . 205.1.4 Line-Up and commissioning (both terminal stations) . . . . . . . . . . . . . . . . . 205.2 Installation check . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 215.2.1 Indoor installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 215.2.1.1 Fuse/Breaker for Main DC power distribution . . . . . . . . . . . . . . . . . . . . . . . 215.2.1.2 DC power supply check . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 225.2.1.3 Assembling and positioning the IDU in the Rack . . . . . . . . . . . . . . . . . . . . 235.2.1.4 Installation check of the "Coaxial cable fixing bracket" . . . . . . . . . . . . . . . . 235.2.1.5 Service and tributary cabling. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 245.2.2 Outdoor installation check. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 245.2.2.1 Antenna. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 245.2.2.2 Flexible waveguide . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 285.2.2.3 Mounting kit. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 305.2.2.4 ODUs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 315.2.3 IDU-ODU cable installation check. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 315.2.3.1 Visual checking of installation quality . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 325.2.3.2 Cable continuity check using a multimeter . . . . . . . . . . . . . . . . . . . . . . . . . 34

    6 Equipment start-up and configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 366.1 System switch ON. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36

  • 4 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480dc

    6.2 PC connection on Serial Interface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 366.3 Web Access Management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 406.4 System Configuration (Link Wizard Configuration) . . . . . . . . . . . . . . . . . . . 446.4.1 Step 1: ODU Operational Mode. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 446.4.2 Step 2: IDU Operational Mode. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 456.4.3 Step 3: ODU Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 476.4.4 Step 4: ODU Channel Selection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 486.4.5 Step 5: Configuration Summary and Update. . . . . . . . . . . . . . . . . . . . . . . 496.5 Additional Radio Link Configuration Parameters . . . . . . . . . . . . . . . . . . . . . 516.5.1 APC Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 516.5.2 Protection Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 536.5.3 ODU Power and ODU Channel Configuration . . . . . . . . . . . . . . . . . . . . . . . 546.5.4 ODU Configuration. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 556.6 Traffic and Port Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 566.6.1 Ethernet Port Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 566.6.1.1 Example of Ethernet Port Configuration with Standard or Enhanced Master I/O

    Module . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 566.6.1.2 Example of Ethernet Port Configuration with 42xE1 Master I/O Module . . . 576.6.1.3 Example of Ethernet Port Configuration with Gigabit Ethernet Master I/O Mod-

    ule . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 586.6.2 E1 Ports and Payload Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 606.6.2.1 Example of E1 Ports Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 626.6.3 STM 1 Payload Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 676.6.3.1 Example of STM-1 Mux demux Configuration . . . . . . . . . . . . . . . . . . . . . . . 686.6.3.2 Example of STM Trace Message Configuration . . . . . . . . . . . . . . . . . . . . . 696.7 Antenna alignment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70

    7 System commissioning and testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 737.1 DC Voltage Power supply . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 737.2 Access Level Configuration and check of Management Ports Connection . 737.3 Port Connectivity Check. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 737.3.1 Port Check . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 737.3.2 E1 Loopback Check. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 747.3.3 E1 End to End Connectivity Check . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 767.3.4 STM-1 Local Loopback Check. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 787.3.5 STM-1 End to End Connectivity Check . . . . . . . . . . . . . . . . . . . . . . . . . . . . 797.3.6 Eth Port Connectivity Check . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 807.3.6.1 Local connectivity check using two laptops . . . . . . . . . . . . . . . . . . . . . . . . . 807.3.6.2 Workaround testing for Ethernet local connectivity check using one laptop 817.3.6.3 Workaround testing for Ethernet End to End connectivity check using two lap-

    tops . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 847.3.6.4 End to End connectivity check using one laptop . . . . . . . . . . . . . . . . . . . . . 857.4 Manual Switch Protection Check . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 877.5 Background BER Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 887.5.1 Background BER Test with Test Equipment . . . . . . . . . . . . . . . . . . . . . . . . 887.5.2 Background BER Test with SW Quality Performance Tool . . . . . . . . . . . . . 89

    8 Annexes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 928.1 IDU's References images . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 92

  • 911-448/02C0000Issue 2, November 2008

    5

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480dc

    8.2 Typical IDU's Composition . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 928.3 IDU's Single Modules Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 948.3.1 Main Common Modules . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 948.3.2 Master I/O Modules. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 958.3.3 E1 Expansion Modules . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 978.3.4 STM-1 Interfaces Modules . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 978.3.5 Additional Modules for Protected or East-West Mode . . . . . . . . . . . . . . . . 988.4 Tributary Ports front panel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 998.5 Tributary Port Pin Out . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1018.6 Test Equipments and Accessories . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 103

    9 Abbreviations and Acronyms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 110

  • 6 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480dc

    List of FiguresFigure 1 General layout for the link test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15Figure 2 ODU connection for Not Protected system type . . . . . . . . . . . . . . . . . . . 17Figure 3 Breaker Visual check . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21Figure 4 DC power supply check . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22Figure 5 Example of IDU Installed Front view. . . . . . . . . . . . . . . . . . . . . . . . . . . . 23Figure 6 Coaxial cable fixing bracket . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23Figure 7 Example of 0.3m (1ft) Faini / Comelit antenna (Dual Polar Horn Feeder) .

    25Figure 8 Example of 0.6m (2ft) Andrew antenna (Low profile version shown) . . . 25Figure 9 Example of Andrew Antenna 0,3 and 0,6 mt Polarization Identification on

    Horn Feeder . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 26Figure 10 Example of Andrew Dual Polar Horn Feeder . . . . . . . . . . . . . . . . . . . . . 26Figure 11 Example of Dual Polar Horn Feeder on Comelit / Faini (alternative supplier)

    Antennas. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27Figure 12 Dual Polar Horn Feeder with antenna on the left side of the mounting pole

    27Figure 13 Dual Polar Horn Feeder with antenna on the right side of the mounting sup-

    port . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28Figure 14 Outdoor overview for 1+1 HSTBY Integrated Mounting . . . . . . . . . . . . . 30Figure 15 Overview 1+1 HSTBY Not Integrated Mounting . . . . . . . . . . . . . . . . . . . 30Figure 16 Overview of ODU . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31Figure 17 Fixing of IDU-ODU cable . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32Figure 18 IDU-ODU cable, Grounding connection . . . . . . . . . . . . . . . . . . . . . . . . . 33Figure 19 Short circuit Check . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34Figure 20 Open Circuit Check. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35Figure 21 Power/Fault Alarm Led on DC Power Module . . . . . . . . . . . . . . . . . . . . 36Figure 22 PC Laptop Connection on Serial Interface . . . . . . . . . . . . . . . . . . . . . . . 37Figure 23 Starting Information Screen . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38Figure 24 Controller Module . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40Figure 25 Typical Ping Dos Command . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41Figure 26 URL address on web browser. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41Figure 27 Starting Information on WEB Interface . . . . . . . . . . . . . . . . . . . . . . . . . . 42Figure 28 Device Names Menu and Configuration of Device Name. . . . . . . . . . . . 43Figure 29 Step 1: ODU Operational Mode . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45Figure 30 Step 2: IDU Operational Mode . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45Figure 31 Step 3: ODU Configuration. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47Figure 32 Step 4: ODU Channel Selection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48Figure 33 Step 5: Configuration Summary and Update (1) . . . . . . . . . . . . . . . . . 49Figure 34 Step 5: Configuration Summary and Update (2) . . . . . . . . . . . . . . . . . 50Figure 35 Step 5: Configuration Summary and Update (3) . . . . . . . . . . . . . . . . . 50Figure 36 APC configuration menu . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51Figure 37 APC configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52Figure 38 Protection Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53Figure 39 ODU Power and ODU Channel Configuration . . . . . . . . . . . . . . . . . . . . 54Figure 40 ODU Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55Figure 41 Ethernet Port Configuration with Enhanced Master I/O Module . . . . . . . 56

  • 911-448/02C0000Issue 2, November 2008

    7

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480dc

    Figure 42 Ethernet Payload Configuration. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 57Figure 43 Ethernet Port Configuration with 42xE1 Master I/O Module . . . . . . . . . 57Figure 44 Ethernet Payload Configuration. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 58Figure 45 Ethernet Port Configuration with Gigabit Ethernet Master I/O Module . 58Figure 46 Ethernet Payload Configuration. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59Figure 47 Location of E1 Ports on Standard or Enhanced Module . . . . . . . . . . . . 60Figure 48 Location of E1 Ports on 42xE1 Module . . . . . . . . . . . . . . . . . . . . . . . . . 60Figure 49 Location of E1 Ports on Gigabit Ethernet Module . . . . . . . . . . . . . . . . . 61Figure 50 Location of E1 Ports on Expansion Module. . . . . . . . . . . . . . . . . . . . . . 61Figure 51 E1 Ports Configuration. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64Figure 52 E1 Ports Configurations. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 66Figure 53 STM Mux demux and STM Trace message menu . . . . . . . . . . . . . . . . 67Figure 54 STM-1 Mux demux Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68Figure 55 STM Trace Message Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . 69Figure 56 Example BNC Connection on ODU . . . . . . . . . . . . . . . . . . . . . . . . . . . . 71Figure 57 Standard antennas pointing for 1 antennas system. . . . . . . . . . . . . . . . 71Figure 58 Antennas pointing for 2 antennas system in Hot Stand By configuration 72Figure 59 Antennas pointing for 2 antennas system in Frequency Diversity configura-

    tion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 72Figure 60 Typical Test Bench . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74Figure 61 Loopback Command . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 75Figure 62 Loopback Duration Menu. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 75Figure 63 Typical Test Bench . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 76Figure 64 Typical Test Bench . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 78Figure 65 Typical Test Bench . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79Figure 66 Typical Test Bench . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 80Figure 67 Typical Ping Dos Command . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81Figure 68 Typical Test Bench . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82Figure 69 Eth and NMS Ports connections . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 82Figure 70 Typical Test Bench . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 84Figure 71 Typical Test Bench . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85Figure 72 Typical Test Bench on Terminal A. . . . . . . . . . . . . . . . . . . . . . . . . . . . . 85Figure 73 Eth and NMS Ports connections on Terminal B. . . . . . . . . . . . . . . . . . . 85Figure 74 Typical Test Bench . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 87Figure 75 Example of Test Bench applied on E1 Port . . . . . . . . . . . . . . . . . . . . . . 88Figure 76 BERT Mode menu selection and BERT Mode Screen . . . . . . . . . . . . . 90Figure 77 Errors Seconds menu selection and Errors Seconds Screen (no events re-

    corded). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91Figure 78 Typical Errors Seconds Screen with anomalous events recorded. . . . . 91Figure 79 IDU Overview. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 92Figure 80 System Not Protected with up to 16xE1 and Eth Channel. . . . . . . . . . . 92Figure 81 System Not Protected with up to 32xE1, Eth Channel and STM 1 Port 92Figure 82 System Protected with up to 16xE1 and Eth Channel . . . . . . . . . . . . . . 92Figure 83 System Not Protected with up to 32xE1, Eth Channel and STM 1 Port 93Figure 84 System Not Protected with up to 63xE1, Eth Channel. . . . . . . . . . . . . . 93Figure 85 System Not Protected with up to 62xE1, Eth Channel. . . . . . . . . . . . . . 93Figure 86 Power Supply Module . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 94

  • 8 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480dc

    Figure 87 Controller Module . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 94Figure 88 Modem and IF/Telemetry Module (Lower or East Side) . . . . . . . . . . . . . 94Figure 89 Standard I/O Module up to 16xE1. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 95Figure 90 Enhanced I/O Module up to 16xE1 and STM-1 Mux/Demux . . . . . . . . . 95Figure 91 42xE1 I/O Module up to 42xE1 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 96Figure 92 Gigabit Ethernet Master I/O Module and 2xE1 . . . . . . . . . . . . . . . . . . . . 96Figure 93 Expansion I/O Module (E1 Expansion Module) . . . . . . . . . . . . . . . . . . . 97Figure 94 21xE1 Expansion I/O Module (E1 Expansion Module) . . . . . . . . . . . . . . 97Figure 95 STM-1 Optical I/O Module (Mini I/O Module) . . . . . . . . . . . . . . . . . . . . . 97Figure 96 STM-1 Electrical I/O Module (Mini I/O Module) . . . . . . . . . . . . . . . . . . . 98Figure 97 Power Supply Module (Upper) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 98Figure 98 Modem and IF/Telemetry Module (Upper or West Side) . . . . . . . . . . . . 98Figure 99 E1 Port on Expansion Module . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 99Figure 100 E1 and Eth Port on Standard / Enhanced Master IO Module . . . . . . . . . 99Figure 101 E1 and Eth Port on GE Master IO Module . . . . . . . . . . . . . . . . . . . . . . . 99Figure 102 STM 1 Optical on Mini STM 1 Module . . . . . . . . . . . . . . . . . . . . . . . . . . 99Figure 103 STM 1 Electrical on Mini STM 1 Module. . . . . . . . . . . . . . . . . . . . . . . . 100Figure 104 Single Molex 60 Pin / RJ48C Cable Interface. . . . . . . . . . . . . . . . . . . . 100Figure 105 Eth RJ45 Payload Ports Connector Pin Out . . . . . . . . . . . . . . . . . . . . . 101Figure 106 Eth RJ45 for NMS Ports Connector Pin Out . . . . . . . . . . . . . . . . . . . . . 101Figure 107 E1 RJ48-C Payload Ports Connector Pin Out . . . . . . . . . . . . . . . . . . . 101Figure 108 E1 RJ48-C Payload Ports Connector Pin Out on Single Molex 60 Pin /

    RJ48C Cable Interface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 102Figure 109 RJ48C / RJ45 Connector Pin Out Overview . . . . . . . . . . . . . . . . . . . . . 102Figure 110 STM-1 Optical SC Duplex Ports . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 102Figure 111 STM-1 Electrical BNC Ports . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 102Figure 112 Personal Computer / Laptop (Suggested Qty 2 in case of test for ETH

    Ports) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 103Figure 113 Multimeters . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 104Figure 114 PDH signal Analyzer (Only for E1 PDH Ports) . . . . . . . . . . . . . . . . . . . 104Figure 115 Acterna/JDSU EDT 135 PDH Signal Analyzer . . . . . . . . . . . . . . . . . . . 104Figure 116 SDH signal Analyzer (Only for E1 / E3 / STM 1 Ports) . . . . . . . . . . . . . 105Figure 117 Acterna/JDSU ANT-5 or equivalent (if required with optical SDH Ports Op-

    tion) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 105Figure 118 RS232 PC serial cable (in case of Alarm/Serial Port Connector Kit cable)

    106Figure 119 ETH Cat 5 cable type RJ45 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 106Figure 120 ETH Cat 5 cable type RJ45 . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 106Figure 121 RJ45 Female Female Adaptors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 107Figure 122 Series of coax adapters (for 75 Ohm Interface) . . . . . . . . . . . . . . . . . . 107Figure 123 Series of Optical adapters (for Optical Interface) . . . . . . . . . . . . . . . . . 108Figure 124 Tests Cable for Electrical E1 or STM-1e Interface . . . . . . . . . . . . . . . . 108Figure 125 Optical Pig Tails for STM-1o Interface . . . . . . . . . . . . . . . . . . . . . . . . . 109

  • 911-448/02C0000Issue 2, November 2008

    9

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480dc

    List of TablesTable 1 Standard Documentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11Table 2 Flexible waveguide . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29Table 3 Connection parameters . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38Table 4 System login . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38Table 5 Web access FlexiHybrid default parameters . . . . . . . . . . . . . . . . . . . . 39Table 6 FlexiHybrid configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40Table 7 PC configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 40Table 8 IDU operational modes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46Table 9 Cross-connection group description of Default Channel Map . . . . . . . . 62Table 10 TP identification and Prefix Syntax . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64Table 11 E1 configuration parameters . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65Table 12 STM-1 Mux demux Configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68Table 13 Port interface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 73Table 14 E1 port configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74Table 15 E1 port configuration . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 76

  • 10 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480dc

  • 911-448/02C0000Issue 2, November 2008

    11

    FlexiHybrid Commissioning SVR 1.3 Preliminary information

    Id:0900d805802480c2

    1 Preliminary information

    1.1 Foreword

    1.1.1 Object of the present manualThis manual is meant to be a guideline for placing into service the FlexiHybrid system.

    1.1.2 ApplicabilityThis document is applicable for all field Lineup and commissioning activities and is a support to system control, configurations and commissioning.

    1.1.3 Manual status

    With respect to the previous issue, the current Issue 2, dated November 2008, has: inserted the SVR 1.3 features.

    1.1.4 Introduction to this documentThe procedure begins (after a brief introduction) with the local Installation control, switch on and settings of the Local parameter and radio link parameter, it continues with the line-up and the commissioning of both radio stations.Note that this procedure is meant to be a useful guide for all types of systems; for this reason some settings and figures must differ from those of the system in field, because the displayed windows depend on the system SVR, System Type and configuration applied in field.Refer to the relevant UMN and OMN manual of system and follow this procedure only as a guide line.g Note - Should the pictures used in this document differ from those of the equipment

    in field it is suggested to refer to the corresponding manual with the S.V.R. of your system.

    Suggested basic support documentation for Line-up and commissioning activities.

    - Current: Issue 2, November 2008- Previous: Issue 1, August 2008

    Standard Documentation NoteOMN Manual (Operator Manual) Related to the system SVRUMN Manual (User Manual) Related to the system SVRInstallation Manual Related to the system type, ODU and IDU typeField Test sheets Standard or customized form

    Table 1 Standard Documentation

  • 12 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480c2

    Preliminary information

    1.2 Safety rules and precautionary measuresIn this paragraph are indicated all the safety rules and the precautionary measures to follow while carrying out operations on the equipment in order to prevent injuries to per-sonnel and/or damages to the equipment components.g PLEASE READ THESE SAFETY PRECAUTIONS!

    1.2.1 RF Energy Health Hazard

    This symbol indicates a risk of personal injury due to radio frequency exposure.The radio equipment described in this guide uses radio frequency transmitters. No one shall be allowed to come in the close proximity of the antenna's front while the transmitter is operating. The antenna will be professionally installed on the outdoor per-manent fix-mounted structures in order to keep it separate from any other antenna and from everybody else.

    1.2.2 Protection against Lightning

    Article 810 of the US National Electric Department of Energy Handbook 1996 specifies that radio and television lead-in cables must have adequate surge protection at or near the point of entry to the building. The code specifies that any shielded cable from an external antenna must have the shield directly connected to a 10 AWG wire that connects to the building ground electrode. Do not turn on power before reading product documentation. This device has a -48 VDC direct current input.

    !WARNING:RF Energy Exposure Limits and Applicable Rules for 6-38 GHz. It is recommended that for each radio equipment deployment site the radio equipment operator refers to the RF exposure rules and precaution for each frequency band and to all other applicable rules and precautions with respect to transmitters, facilities, and operations that may affect the environment due to the RF emissions.Appropriate warning signs must be properly placed and affixed at the equipment site and access entries.

  • 911-448/02C0000Issue 2, November 2008

    13

    FlexiHybrid Commissioning SVR 1.3 Preliminary information

    Id:0900d805802480c2

    1.2.3 Protection from RF BurnsIt is dangerous to stare into or stand in front of an active antenna aperture. Do not stand in front of or look into an antenna without first ensuring that the associated transmitter or transmitters are switched off. Do not stare into the waveguide port of an ODU (if appli-cable) when the radio is active.

    1.2.4 Risk of Personal Injury from Fiber Optics

    1.2.5 Warning This is a Class A product

    1.2.6 Warning Turn off all power before servicing

    1.2.7 Safety RequirementsA switch must be placed between the FlexiHybrid external power supply and the Flex-iHybrid power supplies in order to meet safety requirements. The switch must discon-nect both of the power supply poles.A single-pole cut-off device can be used to disconnect the line conductor when the DC MAINS SUPPLY is configured with an earthed conductor.

    !DANGER:Invisible laser radiation. Avoid direct eye exposure to the tip-end of a fiber, fiber cord, or fiber pigtail. The infrared light used in fiber optics systems is invisible, but can cause serious injury to the eye.

    !WARNING:Never touch exposed fiber with any part of your body. Fiber fragments can enter the skin and are difficult to detect and remove.

    !WARNING:This is a Class A product. In a domestic environment this product may cause radio inter-ference in which case the user may be required to take adequate measures.

    !WARNING:Turn off all power before servicing.

  • 14 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480c5

    Test instrument list and measurement accessories

    2 Test instrument list and measurement acces-sories

    2.1 Test InstrumentsChoose the specific test instrument (and tests cabling) according to the following param-eters:

    IDU Type (E1 interface, STM# Interface for Standard Type) Physical Interface type (Electrical or Optical) IDUs Physical Interface connectors (i.e., on the IDU, the E1 ports are with RJ48C

    120 ohm impedance Interface, the Electrical STM-1 with BNC Connectors and the optical STM-1 with SC Interface.

    Type of Physical Interface connectors used on the Electrical Digital Distribution Frame (DDF)

    Type of Physical Interface connectors used on the Optical Distribution Frame (ODF)The test cabling and series of coax adaptor depend on the DDF type installed in field and on the physical Interface of the test Instruments used.For more details on the Test Equipment, Equipment Interface, Accessories and cables recommended, it is suggested to refer to the Annexes at the end of this document.However, the standard IDU access interfaces for the FlexiHybrid are: STM 1 electrical access type BNC (female) STM 1 optical access type SC Service E1 access type RJ48C (Male or Female related the Ports Numbers and use

    of Molded cable adaptor) Service V11 / 64 Kb/s user Data access type RJ45 ETH Access for management Network type RJ45 ETH Access for Service and ETH channel type RJ45 AGC Measurement point (on ODU) access type BNC (female)

  • 911-448/02C0000Issue 2, November 2008

    15

    FlexiHybrid Commissioning SVR 1.3 Test instrument list and measurement accessories

    Id:0900d805802480c5

    2.2 Typical test bench overview

    Figure 1 General layout for the link test

    The above figure is only an example of the typical layout for Field Tests using one PDH BER Test Instruments and portable PC.

    g Warning for Laptop Connection - If wanting to use an external power supply for the Laptop, it is recommended to connect first the serial cable and then the power supply cable.Doing this the other way round could be dangerous, because the power supply unit for the laptop normally contains an autotransformer, and the dif-ference of ground potential could damage the serial port of the PC and (or) the serial interface of the IDU.

  • 16 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480c8

    System Operating Mode

    3 System Operating ModeThe System Operating Mode configuration defines the types of the Link System. During the "Link Wizard Configuration" one of the following mode should be selected: "Standard" mode for 1+0 Not protected System "Protect non-diversity" mode for 1+1 Hot Stand-By System "Protect diversity" mode for 1+1 Frequency Diversity or Cross Polarization System "East-West" mode for 2+0 System / Ring Configuration System "East-East" mode for 2+0 configuration (available only with the Gigabit Ethernet

    unit)

    g Note - The "Protect non-diversity" mode configuration is independent from the number of antennas used by the terminal station.

  • 911-448/02C0000Issue 2, November 2008

    17

    FlexiHybrid Commissioning SVR 1.3 ODU and Modem Module connection

    Id:0900d805802480cb

    4 ODU and Modem Module connection For Standard mode, the default Modem Unit must be connected in the lower posi-

    tion, identified as East side. For Protection mode, the Modem Unit in the lower position is identified as East

    side (suggested to use for the main channel) and the modem unit on the upper position must be identified as West side (suggested to use for the protection chan-nel).

    For East-West mode, the Modem Unit in the lower position is identified as East side and the modem unit in the upper position must be identified as West side.

    Figure 2 ODU connection for Not Protected system type

  • 18 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480cd

    System configuration and line-up phase

    5 System configuration and line-up phase

    5.1 RequirementsThe technicians responsible for the installation and commissioning of the equipment must have the following basic requirements: PDH / SDH / ETH main concept system know-how Microwave Radio Link system know-how FlexiHybrid equipment radio basic know-how Basic PC know-how Skill to install and use FlexiHybrid software management (Terminal and Web Mode) Mechanical installation know-how (antennas, rack, waveguide, cabling, etc.)If the technician is not familiar with the FlexiHybrid system, it is suggested that he reads the system manuals (UMN and OMN).Before switching ON the equipment verify that all the installation items have been properly installed and that the system is equipped as stated in the Project specification.With regard to system composition refer to the "Equipment Composition" paragraph on the UMN manual and to the project specification.In order to operate and configure the FlexiHybrid system it is important to follow the phases step by step.Assuming that the link is made up of a Station A and of a Station B, the operations shall begin on Station A and the other station will be OFF.For each terminal station it is suggested to proceed in the manner stated below.

    5.1.1 Installation CheckIndoor installation Proper Breakers for DC power supply Primary supply voltage Assembling and positioning of IDU in the Rack Check the proper connection of the TNC/N coaxial tail supplied with the system Check the proper installation of the "Coaxial cable fixing bracket" and related

    grounding connection Tributary cable (PDH / SDH / ETH) Alarm cable (if request) Networking connection (if request) Auxiliary Channel (if request)Outdoor installation Antenna assembling and Positioning Antenna Fixing Antenna Polarization Flexible waveguide (or elliptical WG) fixing If applicable fix and assemble the Mounting Kit Properly assemble the ODU to the antenna or mounting Kit ODU Grounding Connections IDU - ODU cable properly assembled IDU - ODU cable Grounding connection

  • 911-448/02C0000Issue 2, November 2008

    19

    FlexiHybrid Commissioning SVR 1.3 System configuration and line-up phase

    Id:0900d805802480cd

    IDU - ODU cable installation IDU - ODU Cable length (refer to the system specification descripted in the UMN

    manual) IDU - ODU cable connections (in particular the correspondence between modem

    units and related ODUs) IDU - ODU cable properly assembled IDU - ODU cable short/open contact check IDU - ODU cable properly fixedAcceptance tests are performed to ensure that proper installation procedures detailed in the installation manual have been applied.During the installation start up phase it is fundamental for the shelf to be properly power-wired and that the equipment shelves are free from defects or damages.

    g Note - Report any problems to the installation group in order to solve the problem before System Switching On or Line-Up and Commissioning.

    5.1.2 Terminal station configuration summary Check the DC Power voltage and related Pin Out connection. Check that all Modules are connected (included the ODUs). Switch ON the DC Power Breakers. Connect the PC to the Serial port and connect the PC using the Hyperterminal appli-

    cation. Log-In into the system. Set the basic IP address. Logout from the Hyperterminal connection and Disconnect the PC from the Serial

    Port. Set the IP Address of the PC Network card according to the IP Address configured

    on the system. Connect the PC on the ETH Management Port. Log-In into the system. Check the IDU Status. Start with Link Configuration Wizard Steps. Configure the other Request Parameter. Configure the E1 / SDH and Eth Payload and request Mapping. Check and Configure all other additional Request Parameters. Check all available local Ports. Repeat all the above steps on the opposite terminal station.

  • 20 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480cd

    System configuration and line-up phase

    5.1.3 Antennas alignment (both terminal stations) Set the APC to disabled mode on both terminal stations. On the protection setting force the working path on the main ODU (suggest the East

    Modem / ODUs Units, recommended in particular for 1+1 Hot Stand By System. Start with the Alignment phase After alignment check the RF Rx Power value (using the PC) and verify that the

    value complies with that of project specification. On the protection setting configure the system to automatic mode. On both terminal stations set the Tx Power configuration as per project specification.

    5.1.4 Line-Up and commissioning (both terminal stations) Taking as reference the relevant commissioning test sheets, proceed to register the

    configuration data and all Local and Link Line-up tests.The above point is detailed in the chapters further on in this document.

  • 911-448/02C0000Issue 2, November 2008

    21

    FlexiHybrid Commissioning SVR 1.3 System configuration and line-up phase

    Id:0900d805802480cd

    5.2 Installation checkThis phase is fundamental for all the other technical activities.It is a statistical data, where most of the field problems or link troubles are caused by a wrong mechanical installation of all the parts making up the system.Installation check must be sub-divided into three fundamental groups: Indoor installation (section 5.2.1) Outdoor installation (section 5.2.2) IDU-ODU cable installation (section 5.2.3)

    5.2.1 Indoor installation

    5.2.1.1 Fuse/Breaker for Main DC power distributionIt is fundamental to verify that the Fuse/Breaker used on the PDB (Power Distribution Box), complies with the consumption of the FlexiHybrid. Note that the system consump-tion value depends on the type of system (refer to the installation manual (UMN) for the proper consumption value).In any case it is suggested to use one breaker for each Power Supply Module installed in the IDU. The suggested value for each breakers/fuse is 4 Ampere.Open the cover of the PDB and check if the Breaker specifications are compliant with the requirements.(The figure below is for reference only).

    Figure 3 Breaker Visual check

    g Bracker P/N depends on the Power distribution type. If needed the NSN power Distribution model (South Product and relevant Breacker P/N are on: https://share-net-ims.inside.nokiasiemensnetworks.com/Open/372201350

  • 22 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480cd

    System configuration and line-up phase

    5.2.1.2 DC power supply checkAfter the visual installation inspection check that the DC Power supplied to the FlexiHy-brid system is correct.The procedure below lists the steps followed to check the power supplied to the Flexi-Hybrid. Turn OFF the switch of the breaker. Disconnect the DC Power connectors from the equipment (Power Supply mod-

    ules). Turn ON the main power supply from the DC Main distribution Box. With a Digital Multi-Meter (DMM) or equivalent, confirm that the voltage supplied

    from the DC line is -48 V nominal and within the nominal tolerance accepted by the equipment ( 20 %).

    g Warning - The measure applied directly on the connectors' pins is subject to short circuit through multimeter contact (in any case caused by the operator).

    At the end of the measure, turn OFF the main power supply from the DC Main dis-tribution Box.

    Finally connect the power supply connectors on the Power Supply Modules of the IDUs.

    g Warning - Since the Power Supply positive is also the ground reference, pay atten-tion to the Multimeter connection when measuring the DC voltage.Normally, if the Common port of the multimeter (Black cable) is connected to ground or to Positive voltage, and the port measure to the Negative voltage (Red Cable), the value read will be negative: - 48 Volt.

    Figure 4 DC power supply check

  • 911-448/02C0000Issue 2, November 2008

    23

    FlexiHybrid Commissioning SVR 1.3 System configuration and line-up phase

    Id:0900d805802480cd

    5.2.1.3 Assembling and positioning the IDU in the RackCheck that the IDUs have been placed inside the rack as explained in the project spec-ifications.Verify that the mounting brackets on each side of the IDU (supplied with the installation material) are properly screw-fastened to the type of rack installed (ETSI or 19").Check the mechanical fixing of the output connectors and cabling from the IDU to the related termination fixing point (DDF, Coax Plate, etc...).It is not a mandatory requirement, but it is suggested a separate running path for Digital signal, DC Power supply and IDU-ODU connection cable.Check that the Grounding connection of the IDU Sub-rack is properly fixed to the rack and consequently to the main grounding ring (or other grounding distribution) present in the station (or shelter).When more than one unit is installed, it is recommended to leave a 1U space between the IDUs in the rack.This rule has two functions: assure proper air ventilation between all IDUs, have a facility path for all the cabling installed from the IDU to the external con-nections.

    Figure 5 Example of IDU Installed Front view

    5.2.1.4 Installation check of the "Coaxial cable fixing bracket"Refer to the UMN manual or Installation documentation. Verify that the "Coaxial cable fixing bracket" and the related grounding connection have been properly assembled and installed.In particular, check the fixing assembly of the coax tail incoming from the IDU and the straight N connector on the IDU-ODU cable.Check also the grounding connection of the fixing bracket to the Rack or to the station main grounding distribution.

    Figure 6 Coaxial cable fixing bracket

  • 24 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480cd

    System configuration and line-up phase

    5.2.1.5 Service and tributary cablingVerify that all applicable connectors and IDU cabling have been properly laid and fas-tened.Verify that all cables (divide according to the type of digital signal) are properly grouped and fixed to the support ladder or other running support.Check that the DDF or other distribution frame (indicated on the project specification) has been connected properly.

    5.2.2 Outdoor installation checkUse all the necessary safety devices for working at certain altitudes. Verify that all outdoor components making up the system have beem properly assembled, installed and cabled (re. the UMN manual, installation documentation and project specification).The following are the typical outdoor components making up the systems: Antenna Flexible waveguide Mounting Kit (if applicable) ODUs and related Grounding Connections ODUs interconnection (in case of CC configuration)

    5.2.2.1 AntennaFollowing the assembling instruction supplied by the antennas supplier, check that all mechanical assembling components have been properly assembled and fixed.Verify that the antennas positioning have already been oriented in the direction of the remote terminal station (refer to the project specification; to check the antenna Azimuth value pay attention if using the compass to verify the antenna positioning).

    g Warning - The compass reader placed near a metallic structure (in particular on the TLC structure) is subject to errors introduced by magnetic effects. It is suggested to direct the antenna towards an external reference point (mountain, building, tree etc.).Use the compass (not near the tower structure) to identify the reference point.Note that the value measure with the compass refers to the magnetic coordinates (Magnetic North), but most of the project refers to the geographic coordinates (True North).Slight differences are possible.

    Check that the output polarization agrees with the project specification.Normally horn feeder fixing or antennas, have a reference mark to identify polarization.In the case of dual polarization horn feeder a label or mark (also described in the antenna assembling instructions) identifies the H or V polarization.Polarisation can be easily identified on all those systems that are provided with flexible wave-guide or single integrated ODUs. Conversely, polarisation cannot be immediately identified if installation is carried out with an integrated mounting kit because the mark, in this case, would be covered up by it.

  • 911-448/02C0000Issue 2, November 2008

    25

    FlexiHybrid Commissioning SVR 1.3 System configuration and line-up phase

    Id:0900d805802480cd

    To this concern contact the installation personnel to confirm the installed polarization.Depending on the antenna diameter, type and supplier, verify (if necessary) the instal-lation of the wind bracket and check (if applicable) if this component has been properly installed. Note that the wind bracket needs to be fixed on a separate mount pole in order to maintain a proper angle between the antenna and the bracket fixing point.

    Figure 7 Example of 0.3m (1ft) Faini / Comelit antenna (Dual Polar Horn Feeder)

    Figure 8 Example of 0.6m (2ft) Andrew antenna (Low profile version shown)

  • 26 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480cd

    System configuration and line-up phase

    Figure 9 Example of Andrew Antenna 0,3 and 0,6 mt Polarization Identification on Horn Feeder

    Figure 10 Example of Andrew Dual Polar Horn Feeder

  • 911-448/02C0000Issue 2, November 2008

    27

    FlexiHybrid Commissioning SVR 1.3 System configuration and line-up phase

    Id:0900d805802480cd

    Figure 11 Example of Dual Polar Horn Feeder on Comelit / Faini (alternative supplier) Antennas

    Figure 12 Dual Polar Horn Feeder with antenna on the left side of the mounting pole

  • 28 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480cd

    System configuration and line-up phase

    Figure 13 Dual Polar Horn Feeder with antenna on the right side of the mounting support

    5.2.2.2 Flexible waveguideThis chapter is applicable if the connection of ODUs (fixed to the proper mounting kit support), is through a flexible waveguide supplied with the systemCheck that they have been properly installed, in particular: Appropriate length, based on antenna diameter and distance (typically 0.6 mt or 1

    mt). No close bending or anomalous torsion (note that normally the flexible waveguide

    supplied is also twistable). Check that the flange termination has been properly fixed to the antenna and

    Mounting support; in case of doubt disconnect them from the antenna and mounting support and

    check the installation of the O-ring between the flange. Check that the waveguide-fixing bracket (supplied with the flexible wave-guide) has

    been properly installed. The system needs 1 fixing bracket for WG of up to 0.6 mt, and 2 fixing brackets for WF of up to 1 mt.

  • 911-448/02C0000Issue 2, November 2008

    29

    FlexiHybrid Commissioning SVR 1.3 System configuration and line-up phase

    Id:0900d805802480cd

    Flexible Waveguide

    Supplied Fixing Kits

    Scheme Installation Hints

    60 cm One : Pole Fixing Set

    1.The Clamp must be installed as close as possible to the middle of the Flex. (30cm), this in accordance with structural boundaries.2.The Flexible Waveguide must be installed according to its mechanical specifications as: Maximum twist and minimum bend radius (E/H Plane)

    100 cm Two : Pole Fixing Sets

    1.The two Clamps must be installed with (33cm) spacings this in accor-dance with structural boundaries.2.The Flexible Waveguide must be installed according to its mechanical specifications as: Maximum twist and minimum bend radius (E/H Plane)

    Table 2 Flexible waveguide

  • 30 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480cd

    System configuration and line-up phase

    5.2.2.3 Mounting kitCheck if the ODUs mounting kit has ben properly assembled and fixed to the pole.Check that the position of this component does not introduce an anomalous torsion on the flexible waveguide.Refer to the UMN manual or installation manual to verify if the mounting kit model installed is like the model reported in project specification.It is also fundamental to verify the positioning of the ODU installed on the mounting support. This applies in particular to Hot stand-by or CC operating systems.For Hot stand-by system a label affixed on the mounting identifies the positioning of the Main channel and the Stand-By Channel.

    Figure 14 Outdoor overview for 1+1 HSTBY Integrated Mounting

    Figure 15 Overview 1+1 HSTBY Not Integrated Mounting

  • 911-448/02C0000Issue 2, November 2008

    31

    FlexiHybrid Commissioning SVR 1.3 System configuration and line-up phase

    Id:0900d805802480cd

    5.2.2.4 ODUsCheck that the ODUs installed are set to the proper frequency band as specified on the project (check the P/N and extension number on the ODU label and check the relevant P/N reported in the UMN manual).Verify the proper positioning of the mounting kit and related connection with the IDU ODU cable (and the appropriate Modem Module on IDU).Verify that the cover cup of the BNC connector (used for antenna aiming phase) is properly closed.Verify that a properly fixed 90 N type connector is used for the IDU - ODU cable con-nection.To check if the antenna (or mounting support) has been properly fixed refer to the description given in the UMN manual or in the Installation manual.

    Figure 16 Overview of ODU

    Check that the grounding connection tail, starting from the ODUs, is properly connected to a good grounding distribution point.

    5.2.3 IDU-ODU cable installation checkScope of this chapter is to illustrate a step by step procedure so as to check the IF cable and related connectors already installed in field.The assembly instruction for connectors is not part of this document. The assembling instructions are included in the Connectors Box supplied in field.Note that all figures inserted in this document are only indicative.Some differences may be present on field, but the basic steps described in this document apply.The IF cable check test consists of 2 basic testing groups: Visual checking of Installation quality

  • 32 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480cd

    System configuration and line-up phase

    Checking the cable using a multimeter

    5.2.3.1 Visual checking of installation qualityVerify if the cable is properly tied, if all connectors are properly assembled and installed in the right position (N 90 side ODUs and N straight side Indoor).On the outdoor 90 connector, verify that the shrink sleeve is properly assembled and fixed on the connector body.Other PVC and water proofing material is optional material; the connectors need no other particular protection.Verify that the cable is properly fixed and tied to the support ladder (indoor and outdoor). The distance suggested between each fixing point is defined in the UMN Manual and installation documents.In any case refer to the following table:

    If the cable is tie-fixed, it is suggested to fix the ties in a cross mode, in order to prevent the cable from sliding or falling off.

    Figure 17 Fixing of IDU-ODU cable

    Check that the cable path from the ODU is not under stress or subject to an anomalous torsion.Check that the grounding connection of the IDU-ODU cable is properly connected before the building/shelter entrance to an appropriate Grounding distribution plate.Note that with the system one grounding kit per cable is supplied. Not more than one grounding kit is required for standard installation. In any case refer to the customer and project specification.

    Braided cable type CNT 300 or INC48Recommended Maximum Clamp Spacing:0.5 mt

  • 911-448/02C0000Issue 2, November 2008

    33

    FlexiHybrid Commissioning SVR 1.3 System configuration and line-up phase

    Id:0900d805802480cd

    Figure 18 IDU-ODU cable, Grounding connection

  • 34 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480cd

    System configuration and line-up phase

    5.2.3.2 Cable continuity check using a multimeterExcept for some particular cases no Return loss or VSWR test instruments are used to test the cable.It is important to check the cable in order to assess the Short circuit or open cable status.For this test a sample multimeter with buzzer option is recommended.Proceed as follows:Switch OFF the ODUs (it is suggest to switch Off completely all IDUs).

    g Warning - It is mandatory to switch OFF the ODUs Power to prevent damage on the Equipment or injury to the operator when operating on the IF cable. Note that the DC Voltage is approx. 50 Volts DC.

    Disconnect the cable from the ODUs and the indoor distributor.

    g Warning - If the cable is connected with PVC, pay attention when removing the PVC tape on the N connectors Side ODU so as not to damage the cable.

    With the cable in open status (ODU side), connect a Multimeter with buzzer on the indoor connector side.Check that any short circuit is detected (Buzzer OFF).

    Figure 19 Short circuit Check

    g Warning - Pay attention to the hand contact on the multimeter. In this case a parallel resistance introduced by the Human Body will give a wrong test result.

    Near the Indoor connector, move the cable and check that any short circuit is detected by the Multimeter.Near the Outdoor connector, move the cable and check that any short circuit is detected by the Multimeter.

  • 911-448/02C0000Issue 2, November 2008

    35

    FlexiHybrid Commissioning SVR 1.3 System configuration and line-up phase

    Id:0900d805802480cd

    If a short circuit is detected, open the faulty connector, reassemble and then after re-check (also with a mutimeter) the cable/connector assembly.On the connector ODU side, place a shorted cable in order to simulate a short circuit.Connect a Multimeter with buzzer on the indoor connector side. Check that the short circuit is detected (Buzzer ON).

    Figure 20 Open Circuit Check

    Near the Indoor connector, move the cable and check that any open contact is detected by the Multimeter.Near the Outdoor connector, move the cable and check that any open contact is detected by the Multimeter.If an open contact is detected, open the faulty connector, reassemble and then re-check (also with a mutimeter and with the equipment alarms) the cable/connector assembly.

  • 36 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480d0

    Equipment start-up and configuration

    6 Equipment start-up and configurationThis section provides guiding information (which is applicable to all types of systems too) for the execution of the first system line-up procedure.Note that some settings and figures can differ from the system in field, because the windows displayed depend on the system SVR, System Type and configuration applied in-field.

    6.1 System switch ONSwitch ON the IDU, using the main switch from the Power Distribution Box.Check that after the system is switched ON the related Power/Fault LED on the DC Power module must be glowing green.With regard to the Protected system switch on both DC Breakers.Before the PC connection, wait for about 60 seconds for all IDUs processes to start up.

    Figure 21 Power/Fault Alarm Led on DC Power Module

    6.2 PC connection on Serial Interface

    g Warning - If wanting to use an external power supply for the Laptop, first connect the serial cable and then the power supply cable.Connecting the other way round could be dangerous, because the power supply unit for the laptop normally contains an autotransformer, and the difference of ground potential could damage the serial port of the PC and (or) the serial interface of the IDU

    Connect the serial cable between the Serial/Alarm interface (positioned on the Control-ler unit) and the Serial port of Computer.

    g Warning - The system is provided with a special Serial Cable adaptor in order to split the Alarms and Serial connections from the main Alarm/Serial Interface.Check that this cable is provided and supplied with the system.Connect the laptop to the DB 9-Pin connector by using a DB-9 pin-to-pin cable.

  • 911-448/02C0000Issue 2, November 2008

    37

    FlexiHybrid Commissioning SVR 1.3 Equipment start-up and configuration

    Id:0900d805802480d0

    Figure 22 PC Laptop Connection on Serial Interface

    g Warning - If the laptop is provided with a Serial 9-Pin Interface a standard Pin to Pin Serial cable (optional Item) can be used.If the Laptop has no serial interface, then use a USB/Serial Adaptor cable (supplied with the standard installation material).

    Access from the Serial Port is also synonymous with CLI access mode.CLI access is obtained by connecting the serial cable between the PC and the IDU, by launching and configuring a terminal program (e.g. Hyperterm) and then pressing the enter key.To locate the Hyperterm application from Windows XP begin from Start Program menu, then select Accessories > Communications Folder.When opening the Hyperterm application for the first time ask to save the configuration file for connection (i.e. save them with FlexiHybrid name).The communication port to associate to the Hyperterm application is the serial commu-nication port (Com1 or other Com port in case of USB/Serial cable adaptor) and shall be configured with the parameter indicated below:

  • 38 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480d0

    Equipment start-up and configuration

    After the configuration and connection phases press the enter key, you will be prompted for a username and password.The factory default configuration for the system login is:

    Select the Integrator Level LogIn data.The factory default configuration for the system login is:

    Figure 23 Starting Information Screen

    g Note: The configuration values on the figure may be not the default values.

    Parameter Value

    Speed 38400 Bits 8

    Stop-Bits 1 Parity NONEFlow-Control NONE

    Table 3 Connection parameters

    Default access value User Log-In Password Log-InMonitor monitor monitor

    Operator operator col1ma Administrator administrator d1scovery Integrator integrator p1nacate

    Table 4 System login

  • 911-448/02C0000Issue 2, November 2008

    39

    FlexiHybrid Commissioning SVR 1.3 Equipment start-up and configuration

    Id:0900d805802480d0

    The factory default parameters are:

    From main "Starting Information Window" press the M-key to navigate to the Main Menu

    Press the B-key to navigate to Administration. Press the A-key to navigate to Network Configuration. Press the A-key to navigate to General. Press the A-key to navigate to IP Address. Enter the new IP address and press the D-Key to update. If the IP address has been

    entered correctly enter Y when prompted. If necessary, use the same menus to set the IP Netmask and IP Gateway. Close the hyperterminal connection.More details are included in the OMN manualAt the end of Networking configuration Quit the Hyperterm access (using the Quit command from the main menu) and proceed to the next step using the Web access.

    g Warning - Although basic configuration of the Software Defined IDU needs no con-nection to the ODU, it is nonetheless recommended that the ODU and IDU be con-nected prior to configuring the IDU Parameter.A connection to the ODU must be established prior to running the Link Configuration process in order to configure ODU related parameters.It might occur to have to configure some parameters using the CLI access if the system is not completely installed and with ODUs disconnected. In this case on the CLI prompt an Alarm message incoming from the Modem Module must appear.In this case it will be suggested to access the equipment (only if the CLI access mode is used) with the Modem Module disconnected from the IDU shelf.

    g Note - Other parameters of the system can be configured through the CLI Interface. For further details refer to the FlexiHybrid OMN Manual. However, for simplicity, it is suggested to use the Web Interface.

    Parameter Value

    IP Address 192.168.0.1Netmask 255.255.255.0

    Gateway 192.168.0.1

    Table 5 Web access FlexiHybrid default parameters

  • 40 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480d0

    Equipment start-up and configuration

    6.3 Web Access ManagementUse a web browser to access the "FlexiHybrid" GUI.The Web GUI may be accessed via ETH port by connecting a CAT5 patch cable between the IDU front-panel NMS port and a PC. The PCs network interface must be configured with an IP address within the same subnet of the equipment IP address.For the default IDU configuration, the IP address of the PC needs to be 192.168.0.x, where x (between 2 and 253) provides an available IP address.If no DCN Planning configuration is available (or Stand alone Link) it is suggested to configure on the equipment the following IP addresses.

    Based to above configuration (only for example), the IP address of the PC needs to be 192.168.0.x (where "x" between 5 and 253) to provide an available IP address.Consequently the PC Laptop configuration for Web Access trough ETH Port must be:

    *Gateway value is not mandatory.After configuring the PCs network interface, using a Cat 5 ETH cable, connect the PC to the NMS Port 1 on the front panel of the Controller Module.

    Figure 24 Controller Module

    Before opening the web browser it is suggested to verify of the connectivity between the PC and the Equipment. To check them apply a ping command from the Windows DOS Prompt.A network 'ping' can be done to verify IDU connectivity.

    FlexiHybrid Configuration Description Station A Station BIP Address 192.168.0.1 192.168.0.3IP Netmask 255.255.255.0 255.255.255.0

    IP Gateway 192.168.0.254 192.168.0.254DHCP Client Disabled Disabled

    Table 6 FlexiHybrid configuration

    PC Configuration Description Connection from Station A

    Connection from-Station B

    IP Address 192.168.0.5 192.168.0.5IP Netmask 255.255.255.0 255.255.255.0

    IP Gateway 192.168.0.2* 192.168.0.4*

    Table 7 PC configuration

  • 911-448/02C0000Issue 2, November 2008

    41

    FlexiHybrid Commissioning SVR 1.3 Equipment start-up and configuration

    Id:0900d805802480d0

    On your desktop, click the Start button and select Programs. Then click on the MS-DOS Prompt icon.

    On the MS-DOS window, type ping 192.168.0.1 (or other configured IP Address) and press enter. Note that 192.168.0.1 is the default factory IP address.

    If the ping is successful, the following message will appear: Reply from 192.168.0.1: bytes=a. time=b ms, TTL=c." Refer to Figure 25 for an example of a ping (the shown IP address is only for refer-

    ence). A successful ping implies that the "FlexiHybrid" and the PC can interact across an

    Ethernet connection. If the ping is not successful, check network connections between the equipment and

    the PC. At the end close the MS-DOS prompt window

    g Attention - To access and manage the system through the Web Access it is sug-gested to disable the windows Firewall or other IP firewall installed on the PC.

    Figure 25 Typical Ping Dos Command

    After the connectivity check, start a web browser and use the "FlexiHybrid" configured IP address (i.e. 192.168.0.1).Insert on the URL link the following URL command http://192.168.0.1 (or other config-ured IP Address) to access the Web GUI:

    Figure 26 URL address on web browser

    On access the system requires the Log-In prompt. Insert the related User and Pass-word, already used for the CLI access, and Log in at the login prompt. The FlexiHybrid Graphical User Interface will appear.

  • 42 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480d0

    Equipment start-up and configuration

    Figure 27 Starting Information on WEB Interface

    The GUI interface is structured as follows:All system management menus include a navigation menu on the left of the frame.The right of the frame includes a Status Bar with a summary of Local and remote statuses and configuration.

    g Attention - If this navigation menu and Status Bar is not displayed, make sure the Java Environment is properly installed and active.

    The main screen (Starting Information) includes the Device and Host name, IP address, Application SW and IDU Chassis (IDUs type) used.By using the proper menu command some of this information will be customised.From the menu Bar select Administration > Device Configuration > Device NamesIf required, configure the Device Name / Host Name and Location Data and "Update" the Data.

  • 911-448/02C0000Issue 2, November 2008

    43

    FlexiHybrid Commissioning SVR 1.3 Equipment start-up and configuration

    Id:0900d805802480d0

    Figure 28 Device Names Menu and Configuration of Device Name

  • 44 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480d0

    Equipment start-up and configuration

    6.4 System Configuration (Link Wizard Configuration)The first Step carried out to configure the FlexiHybrid is Link Configuration. This config-uration mode (also called Link Wizard Configuration) guides the operator to execute link configuration through the step by step wizard mode. Start the GUI Expand the Menu tree and from the Radio Link menu select Radio Link > Link Con-

    figurationBasically, the system configuration requires 5 consecutive steps: Step 1: ODU Operational Mode Step 2: IDU Operational Mode Step 3: ODU Configuration Step 4: ODU Channel Selection Step 5: Summary of ConfigurationsDuring the configuration Wizard it is suggested to observe the following notes:g To configure the Framer and ODU related parameters, a standard IO card and

    modem should be configured and be present. Otherwise an error message will be displayed.

    g In the Link Configuration Wizard, use only back/ next button given in the web page to move to the previous/next page. Do not use the browser back button.

    g If the selected parameters on the current page are not supported by the terminal, an error message will be displayed on the next page. To correct the error, go back to the previous page and select a different value for the selected parameter.

    6.4.1 Step 1: ODU Operational ModeThe operator selects the main system type: Standard Mode = for not protected mode (1+0) Protected non-diversity = for protected link in Hot Stand By mode (1+1 HSTBY) Protected diversity = for protected link in Frequency diversity mode (1+1 FD) East-West Mode = for 2 + 0 different destination in Add/Drop Repeater or Ring con-

    figuration East-East Mode = for 2 + 0 same destination configuration (available only with the

    Gigabit Ethernet unit)

  • 911-448/02C0000Issue 2, November 2008

    45

    FlexiHybrid Commissioning SVR 1.3 Equipment start-up and configuration

    Id:0900d805802480d0

    Figure 29 Step 1: ODU Operational Mode

    6.4.2 Step 2: IDU Operational ModeThe operator selects the main usage of the IDU mode referred to the IDU HW configu-ration, Permitted License agreement and Project requirement configuration.Several Modes are available, select one of them and go to the next Step.g The IDU Operational Mode menu must differ from the system SVR and License

    available.

    Figure 30 Step 2: IDU Operational Mode

    For Standard or Protected Modes the IDU Operational mode screen has only one selec-tion.

  • 46 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480d0

    Equipment start-up and configuration

    In case of East-West Operational mode, the screen is split into two selections, one for the East direction and the other for the West Direction.Note that the IDU Operational mode settings depend on several factors, System License, Modules making up the IDUs and operational mode defined by Project specifi-cation.The acronym used in the IDU operational mode defines exactly the number of PDH, Ethernet or SDH capability.The IDU Operational Mode Acronymous can be structured with the following suffix rule:

    Where: BW is the Channel Bandwidth in MHz Mod is the Modulation Type (4=QPSK, 16=16QAM, 32=32QAM, 64=64QAM,

    128=128QAM) #e is the maximum number of E1 Ports Channel (i.e. 16e is up to 16 E1) #M is the Maximal Ethernet Data on the Eth Ports (i.e. 26M is up to 26 Mbps) #s is the maximum number of STM-1 Ports Channel In two types of IDUs there is also the suffix P# before the Eth capacity, this when the

    system is configured in Ethernet Plus Mode. See the examples given in the table below:

    BW.Mod-#e#M#s

    Mode Name Modulation Channel Bandwidth

    NxE1 (n= )

    Ethernet Data (Mbps)

    STM-1

    14.4-4e9M QPSK 14 4 9 028.32-95M 32QAM 28 0 95 028.128-63e26M 128QAM 28 63 26 028.128-P55-100M 128QAM 28 0 55+100 0

    Table 8 IDU operational modes

  • 911-448/02C0000Issue 2, November 2008

    47

    FlexiHybrid Commissioning SVR 1.3 Equipment start-up and configuration

    Id:0900d805802480d0

    6.4.3 Step 3: ODU ConfigurationThe operator selects the basic configuration of the ODUs.The operator must select the ODU Type (HT or LT selection identifies the ODU RF Band, for High Band it is HT and for Low band it is LT). These parameters must be detected automatically from the ODUs.The operator must check if it is compliant with the Project RF Planning.The required configuration is the Start Tx Power data.The SW detects from the ODUs the Tx RF Power Range and the operator selects the value referred to in the Project Planning Data.In this case too the displayed screen depends on the Link Configuration Mode.For Standard (1+0) and Protected Non Diversity (1+1 HSTBY) only one setting is dis-played.For Protected Diversity and East-West Mode both ODUs (East and West setting) are displayed.

    Figure 31 Step 3: ODU Configuration

  • 48 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480d0

    Equipment start-up and configuration

    6.4.4 Step 4: ODU Channel SelectionThe operator configures the Operative Working Frequency for the ODUs.Select the option Manual Frequency Entry and write directly the Tx frequency defined in the Project RF Planning. The frequency must be written in MHz.The system detects also (from the ODUs) the Max and Min frequency range and the Spacing.These data depend on the ODU Type and relevant P/N.In this case too the displayed screen depends on the Link Configuration Mode.For Standard (1+0) and Protected Non Diversity (1+1 HSTBY) only one setting is dis-played.For Protected Diversity and East-West Mode first is displayed the configuration for East ODU and then, in the next step, the configuration for West ODU.

    Figure 32 Step 4: ODU Channel Selection

  • 911-448/02C0000Issue 2, November 2008

    49

    FlexiHybrid Commissioning SVR 1.3 Equipment start-up and configuration

    Id:0900d805802480d0

    6.4.5 Step 5: Configuration Summary and UpdateThe operator verifies all the configuration data and, if all the data meet the Project spec-ification, applies the command to execute them on the system.The displayed screen depends on the Link Configuration Mode.For Standard (1+0) and Protected configuration only one command is displayed to apply the configuration.For East-West Mode the command can be applied with three options: Update East Link, the settings are applied on the East Local and Remote system

    (if connected); Update West Link, the settings are applied on the West Local and Remote system

    (if connected); Update All, the settings are applied on the East / West Local and on the relevant

    Remote systems (if connected).After the Update confirmation command the system reconfigures all the Local and remote IDUs.This task takes a few minutes.During this phase the Status Bar shows a Reconfiguring message.At the end, the Status Bar shows the Relevant data from the local and remote system.

    g During the reconfiguration phase do not apply any setting on the system.

    Figure 33 Step 5: Configuration Summary and Update (1)

  • 50 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480d0

    Equipment start-up and configuration

    Figure 34 Step 5: Configuration Summary and Update (2)Before continuing with the other configurations check on the Configuration Summary if all the system data has been configured according to the project specifications. From the main menu select Link Configuration then Configurations Summary.

    Figure 35 Step 5: Configuration Summary and Update (3)

  • 911-448/02C0000Issue 2, November 2008

    51

    FlexiHybrid Commissioning SVR 1.3 Equipment start-up and configuration

    Id:0900d805802480d0

    6.5 Additional Radio Link Configuration Parameters

    6.5.1 APC ConfigurationAs per project specification requirements (typically RF Network Planning Specifications) configure the APC (Adaptive Power Control).This configuration defines the Threshold and the Transmission Output range, if needed. To enable/disable APC, click on the radio button and click the update button. To change RSL Low Threshold, RSL High Threshold, RSL Maximum Threshold,

    CER Threshold, Tx Power Minimum, and Tx Power Maximum values or Step size, enter the required value in the text box (for Step Size scroll through the select box) and click update button.

    To Enable/Disable Update Far End Thresholds parameter, select the relevant radio button and press Update button.

    Figure 36 APC configuration menu

    g In the 1+1 HSTBY configuration, the settings related to the Coupler Configuration are also on the APC configuration menu.

    In case of Unbalanced Coupler configure the ODUs (East or West) installed on the Main Port or on the Decoupled Port.Normally it is suggested to install the East ODU on the main port (HW installation) and set the value of Coupler Nominal Power Side with East.If the Coupler is the Unbalanced type, configure the Coupler Loss with the proper value stated in the coupler specification (typically 10 dB).

  • 52 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480d0

    Equipment start-up and configuration

    Figure 37 APC configuration

  • 911-448/02C0000Issue 2, November 2008

    53

    FlexiHybrid Commissioning SVR 1.3 Equipment start-up and configuration

    Id:0900d805802480d0

    6.5.2 Protection ConfigurationFor Protected system check and configure the Protection as stated in the Project Spec-ification requirements.This configuration defines the rule for system switching. This setting is particularly for Hot Stand-By systems. The Power down ODU is a command to switch OFF completely the ODU in case of

    Switching (it will be suggested to keep this parameter Disabled). Preferred ODU defines the active ODU in the system Start Up (it will be suggested

    to set the main channel defined by the East ODU). Remote Transmitter Switching enables (or not) the remote switching operation in

    case of local switch (suggested to be kept disabled).A manual Transmission switch command is also present in case of switch testing.

    Figure 38 Protection Configuration

  • 54 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480d0

    Equipment start-up and configuration

    6.5.3 ODU Power and ODU Channel ConfigurationThe ODU power and ODU Channel configuration define the Power Transmission Power and Operating Frequency (Tx).This typical configuration is already configured during the Link Configuration Wizard Operation.In any case, the same configurable parameters are also available apart from the other configurable data defined in the Link Configuration Wizard.

    Figure 39 ODU Power and ODU Channel Configuration

  • 911-448/02C0000Issue 2, November 2008

    55

    FlexiHybrid Commissioning SVR 1.3 Equipment start-up and configuration

    Id:0900d805802480d0

    6.5.4 ODU ConfigurationThe ODU Configuration Screen allows the operator to squelch manually.This command allows to squelch the transmission of the TX RF signal.In this case too the screens differ according to the Link configuration parameters.These parameters must be applied only for testing or troubleshooting applications (for example to check interference or if the ODU mute operation is working properly).

    Figure 40 ODU Configuration

  • 56 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480d0

    Equipment start-up and configuration

    6.6 Traffic and Port ConfigurationThe different Traffic and Port configuration settings menus depend on the Link and IDU configuration.The indications given in this chapter are only as example.

    6.6.1 Ethernet Port ConfigurationBasically, Ethernet payload is supported when: The IDU is equipped with Standard Master IO Module, Enhanced Standard Master

    IO, 42xE1 Master IO Module or GE Master IO Module. IDU Operational Mode is configured with Eth Port Capabilities System License permits the IDU Operational Mode with Eth Port CapabilitiesNote that the Standard or Enhanced Module or 42xE1 Master IO Module support up to 2 Eth Ports.The GE Master Module supports up to 4 Eth ports and one SFP configurable module to the SFP type.

    6.6.1.1 Example of Ethernet Port Configuration with Standard or Enhanced Master I/O ModuleThe following examples refer to an IDU equipped with: Standard or Enhanced Master I/O Moduleg The main difference between a Standard or Enhanced Master I/O Module and

    Gigabit Ethernet Master I/O Module is the number of configurable Eth Port (from two to four) and on the Gigabit Module the configuration of an optional SFP module.

    With this configuration only two Eth Ports are available.The ports are located on the Enhanced Master I/O Module.

    Figure 41 Ethernet Port Configuration with Enhanced Master I/O Module

    Configuration of the Ethernet payload: from the Main menu select the Administration > Network Configuration > Ethernet Payload (refer to the OMN).

    Configuration of the QoS: from the Main menu select the Administration > QoS Con-figuration (refer to the OMN).

  • 911-448/02C0000Issue 2, November 2008

    57

    FlexiHybrid Commissioning SVR 1.3 Equipment start-up and configuration

    Id:0900d805802480d0

    Figure 42 Ethernet Payload Configuration

    All the Eth Port settings are shown.

    6.6.1.2 Example of Ethernet Port Configuration with 42xE1 Master I/O ModuleThe following examples refer to an IDU equipped with: 42xE1 Master I/O ModuleWith this configuration only two Eth Ports are available.

    Figure 43 Ethernet Port Configuration with 42xE1 Master I/O Module

    Configuration of the Ethernet payload: from the Main menu select the Administration > Network Configuration > Ethernet Payload (refer to the OMN).

    Configuration of the QoS: from the Main menu select the Administration > QoS Con-figuration (refer to the OMN).

  • 58 911-448/02C0000Issue 2, November 2008

    FlexiHybrid Commissioning SVR 1.3

    Id:0900d805802480d0

    Equipment start-up and configuration

    Figure 44 Ethernet Payload Configuration

    All the Eth Port settings are shown.

    6.6.1.3 Example of Ethernet Port Configuration with Gigabit Ethernet Master I/O ModuleThe following examples refer to an IDU equipped with: Gigabit Ethernet Master I/O Module with SFP type 1000 Base-T direct modeWith this configuration up to 4 Eth Ports can be configured plus the SFP operational mode.

    Figure 45 Ethernet Port Configuration with Gigabit Ethernet Master I/O Module

    Configuration of the Ethernet payload: from the Main menu select the Administration > Network Configuration > Ethernet Payload (refer to the OMN).

    Configuration of the QoS: from the Main menu select the Administration > QoS Con-figuration (refer to the OMN).

  • 911-448/02C0000Issue 2, November 2008

    59

    FlexiHybrid Commissioning SVR 1.3 Equipment start-up and configuration

    Id:0900d805802480d0

    Figure 46 Ethernet Payload Configuration

    All the Eth Port settings are shown.g The configurable parameters of the SFP module depend on the type of module

    inserted.