Customer supplied structural design
basis
Conceptual design
In-place analysis & design
Loadout analysis &
design
Transportation analysis &
design
Jacket/ Tower / Template
installtion analysis & design
Pipe installation analysis & design
Deck / topside module
installation analysis &
design
Structural Drafting
Fabrication support engineering
Structural drafting
Installation support engineering
Structural drafting
Overveiw 1
Input from next 4 flow charts
Creat / update Micro SAS model
Perform analysis for operational / extreme environmental load cases
Perform dynamic analysis (if required)
Perform earthquake analysis (if required)
Perform fatigue analysis (if required)
Design appurtenances &
detail steel
Inplace 3
Design appurtenances &
detail steel Provide information to
structural drafting
Establish transportation configuration & structure hard points
Create/update SACS transportation model
Perform structural transportation analysis, including fatigue analysis (if required)
Create/update MOSES transportation model
Verify structural adequancy of barge
Perform marine transportation analysis. Generate accelerations
Verify barge stability (if known)
Go to Inplace
Analysis
Repeat in place analysis
Input from Installation Support
Engineering
Yes
5
yes
Transportation
Design detail steel & perform local member checks
Provide information to structural drafting
Advise offshore operating group
Verify structural adequancy of barge
Go to Inplace
Analysis
Repeat in place analysis
From page 1 of flowchart # 6
Perform structural on -
bottom analysis
Create / update Micro SAS on - bottom model
Input from flowchart # 10
Repeat in place analysis
Go to flow chart # 3
No
No
6 part 2
Flow through
Lift
Repeat in place analysis
Provide information to structure drafting
Go to flow chart # 3
Design installation appurtenances
Input from flowchart # 10
Perform structural float - through
analysis
Lift or float through
Create / update Micro SAS model
Create / update MOSES float- through model
Perform structural lift analysis
Perform marine float - through analysis
yes
No
8
Structural Engineering Naval Architecture
launch
Lift
Yes
Perform structural float - through
analysis
Provide information to structural drafting
Design installation appurtenances
Go to flow chart # 3
Perform structural lift analysis
Repeat in place analysis
Launch or lift structure
Go to flowchart # 6 or # 8
Select lift rigging
Establish lift arrangement
Verify lift weight & centre of gravity
Repeat lift analysis
Go to A page 2 of 2 of this
flowchart # 10
Go to flowchart # 5
Determine structure tow arrangement on material barges
Establish field arrangement & derrick
barge mooring requirements
Provide information to
structural drafting
Repeat transportation
analysis
Provide information to
structural drafting
No
10 part 1
Structural Drafting Structural Engineering / Naval Architect Other Disciplines
Go to flowchart # 6 or # 8
Provide information to structural drafting
Provide on site assistance during installation
Design rigging platform
Verify lift eye / trunnion adequacy
Perform derrick barge hook check
Repeat lift analysis
Provide onsite assistance during installation
Prepare tug hoursepower,tow ballast , & tow safety reports
Perform seafastening design
Provide information to
structural drafting
EPCI/ EPC /EP BID package
Review scope of work
Manhours estimate & scope for BID support
Review structural design basis philosophies & specifications
Prepare & / or Review :
EPCI/ EPC /EP BID package
Review scope of work
Manhours estimate & scope for BID support
Review structural design basis , philosophies & specifications
- Preliminary project specifications.- Feed reports.- Preliminary jacket main steel.- Preliminary deck main steel.-Miscellaneous steel.
BATAM Yard
Proposal group
Electrical
Input to electrical steel surface area calculation
Prepare & / or Review : Preliminary drawings : - Jacket main steel.- Deck main steel.- Miscellaneous steel.
Technical clarification
Input to proposal
- Deliverable test. - CTR / Manhours estimate.- Input to schedule.
- Preliminary project specifications.- Feed reports.- Preliminary jacket main steel.- Preliminary deck main steel.-Miscellaneous steel.
Technical clarification
Input to proposal
- Technical qualifications- Input for engineering execution- Response to questionaires.- Deliverable list.- CTR / Manhours estimate.- Input to schedule.
RFQ For building architectural items- Doors.
- Windows.- Ceiling.- Flooring. - Wall insulation.- Wall lining.- ETC.
Technical BID evaluation (Quick TBE)
Building architectural cost summary
BID project engineer
Document control
Planner
Procurement
Vendor's proposal
Through Document control
Identify customer requirements
Identify operations material handling
requirements
Identify pipeline riser / J-tube requirements
Identify platform access / egress requirements for operations observation & maintenance activities
Identify fabrication constrains
Identify hull constrains
(reference hull designer criteria / premise)
Identify layout of
major process
equipment & buildings
Identify space allocations for pipe & electrical raceways
Identify drilling / process
requirements (reference equipment
arrangements).
Generate preliminary
jacket concept
Develop supplementary
structural design premise
Generate preliminary deck concept
Develop cost estimate & schedule (if required).
Identify installatio
n constrain
s
Conceptual 2
yesNO
Input from Installation Support
Engineering
Establish loadout method & structure hard points
Create/update SACS loadout model
Verify stability of barge (if known)
Create / update MOSES loadout model
Perform structural loadout analysis
Perform base structural & deflection check
Verify adequacy of skidways
Perform marine loadout analysis
Repeat in place analysis
Go to flow chart # 3
loadout 4
Launch
Noyes
Lift
No
yes yesNO
No
Verfiy adequacy of barge skids
Advice offshore operations group
Repeat in place analysis
Provide information to structural drafting
Design detail steel & perform local member checks
Input from Flow chart # 10
Create / Update Micro SAS model (flow chart # 3)
Verify Ballast
flotation
Upend?
Go to flow chart # 3
Repeat in place analysis
Perform marine launch analysis . Generate loads
Create / update MOSES launch model
Launch or lift ?
Perform structural lift analysis
Create / update Micro SAS lowering model
Go to page 2 of this flowchart #
6
Perform structural launch analysis
Lower to mudline?
Noyes
6 part 1
Perform float / upend analysis
Upend? Perform structural lowering analysis
Create / Update Moses float / upend modelCreate/ update MOSES
lowering model
Perform marine lowering analysis
Repeat in place analysis
Input from Flowchart # 10
Perform Micro SAS pile lift analysis. Perform
MOSES upend analysis
Determine pile makeup
Perform pile stickup analysis
Perform pile driveability
analysis
7
Fabrication support Loadout support
yes
No
Provide information to structural drafting
Design pile installation appurtenences
Determine pile makeup
Establish engineering scope of work for structure assemly / erection in fabrication yard
Establish required support points;design
support pads and foundation,as required
Provide information to structural drafting
Provide information to structural drafting
Perform structural analysis , as required , for: jacket bent rollups , jacket bent floats , deck
truss rollups , deck pancake floats
Design appurtenances , as required for rollups & floats
Evaluate fabrication yard foundation adequacy for loadout, if
required
Provide information to structural
drafting
Design new skidways or evaluate existing skidways,as
applicable
Go to flowchart # 4
Develop structure loadout procedure
Repeat loadout analysis
9
Structural Engineering Naval Architecture
yesYes
NoNo
yes Yes
Installation Support Engineering
Provide information to structural drafting
Evaluate fabrication yard foundation adequacy for crawler crane operations, if
required
Provide lift point locations & crawler crane hook loads to fabrication yard
Design appurtenances , as required for rollups & floats
Provide onsite assistance during loadout
Design appurtenances as required for loadout
Evaluate fabrication yard foundation adequacy for loadout, if
required
Provide information to structural
drafting
Go to flow chart 7
Verify adequacy of mudmats
Go to flow chart 6
Perform overturning / sliding analysis
Establish pile installation sequence
Repeat on-bottom analysis
Repeat pile installation
analysis
A
Go to flow chart # 6
Verify launch cradle & launch lug adequacy
Go to flow charet # 6
Verify launch weight,buoyancy,center of gravity & center of buoyancy
Repeat launch analysis
Repeat float & upend analysis
No No
10 part 2
Provide onsite assistance during installation
Provide information to structural drafting
Review grout system design & details
Verify skirt pile guide adequacy
Design pile stops & lifting eyes
Go to flow chart 7 Repeat pile installation
analysis
Go to flow chart # 6
Verify upending eye adequacy
Provide on site assistance during installation
Provide launch / flotation / upending report
Select upending rigging
Review flooding system design & details
Repeat float & upend analysis