fmc corp - evaluation of remedial action …1 i) the western boundary of the site, ii) the eastern...
TRANSCRIPT
c
-FMC NORTHERN ORDNANCE DIVISIONMINNEAPOLIS
EVALUATION ofREMEDIAL ACTION ALTERNATIVI
FMC and BNR LandsGroundwater Regime
May 1985Ref. No. 1518 CONESTOGA-ROVERS & ASSOCIATES LIMITED
L
TABLE OF CONTENTS
Page1.0 INTRODUCTION 1
2.0 PRELIMINARY ASSESSMENT OF POTENTIAL REMEDIAL TECHNOLOGY 42.1 GENERAL 42.2 ASSESSMENT CRITERIA 52.3 PRELIMINARY ASSESSMENT RATING SYSTEM 72.4 PRELIMINARY ASSESSMENT OF POTENTIAL
REMEDIAL TECHNOLOGIES 92.4.1 Excavation and Disposal 92.4.1.1 Disposal at an Off-Site RCRA Facility 112.4.1.2 Disposal On Site 122.4.2 Capping 132.4.2.1 Normal Portland Concrete Pavement 152.4.2.2 Asphaltic Concrete Pavement 162.4.2.3 In-situ Soil Admixtures 172.4.2.4 Sprayed on Covers 192.4.2.5 Low Permeability Soil Cover 202.4.2.6 Synthetic Membranes 212.4.2.7 Composite Construction 232.4.3 Physical Containment 252.4.3.1 Slurry Walls 262.4.3.1.1 Soil-bentonite mixtures 282.4.3.1.2 Cement-bentonite mixtures 292.4.3.2 Sheet Piles 312.4.3.3 Injected Screens 322.4.3.4 Grout Curtain 332.4.4. Hydraulic Containment 342.4.5 Groundwater Treatment 372.4.5.1 Biological Treatment 402.4.5.2 Carbon Adsorption 412.4.5.3 Stripping 432.4.6 Groundwater Disposal 442.4.6.1 Discharge to a Surface Fresh Water Body 45
TABLE OF CONTENTS (continued)
Page2.4.6.2 Discharge to a Publicly Owned Treatment Work 452.4.6.3 Disposal at a RCRA Permitted Facility 472.4.6.4 Reinjection 482.4.6.5 Deep Well Injection 482.4.7 Alternate Water Source Supply 492.4.7.1 Providing a Well Outside of the
Contaminated Plume 502.4.7.2 Providing a Potable Water Delivery Service 512.4.7.3 Providing a Water Service from a Municipal
Source 512.5 SELECTED REMEDIAL TECHNOLOGIES 522.5.1 Excavation and Disposal 532.5.2 Capping 542.5.3 Physical Containment 552.5.4 Hydraulic Containment 572.5.5 Groundwater Treatment 582.5.6 Groundwater Disposal 582.5.7 Alternate Water Source Supply 602.6 IN-SITU BIOLOGICAL TREATMENT 60
3.0 PRELIMINARY ASSESSMENT OF POTENTIAL REMEDIAL ALTERNATIVE 623.1 GENERAL 623.2 ASSESSMENT CRITERIA 623.3 ASSEMBLED POTENTIAL REMEDIAL ALTERNATIVES 63
3.4 PRELIMINARY ASSESSMENT OF POTENTIAL REMEDIAL
ALTERNATIVES 65
3.4.1 Preliminary Assessment of General Categories 663.4.1.1 Excavation of Contaminated Soils and
Disposal in a Containment Facility 663.4.1.2 Physical Containment 683.4.1.3 Hydraulic Containment 693.4.1.4 Groundwater Treatment and Groundwater Disposal 703.4.1.5 Alternate Water Source Supply 73
TABLE OF CONTENTS (continued)
3.4.2 Preliminary Cost Assessment of PotentialRemedial Alternatives 73
3.4.2.1 BNR Lands Assembled Potential RemedialAlternatives 75
3.4.2.3 FMC Lands Assembled Potential RemedialAlternatives 82
3.5 SELECTED REMEDIAL ALTERNATIVES 85
4.0 DISCUSSION OF HYDRAULIC CONTAINMENT ALTERNATIVE ATEVALUATION LOCATIONS 884.1 SCOPE 884.2 DESCRIPTION OF HYDRAULIC CONTAINMENT TECHNOLOGY 894.3 EVALUATION LOCATIONS 954.3.1 Site Property Boundary 954.3.2 Anoka County Lands 984.3.3 Mississippi River Shoreline 1004.3.4 Minneapolis Water Works Intake 1014.3.5 Residuals Following System Shutdown 1024.4 PERMITTING REQUIREMENTS 1034.4.1 General 1034.4.2 Fresh Water Body Discharge 1044.4.3 Sanitary Sewer Discharge 1054.4.4 Air Stripping Tower Discharge 106
5.0 CONCLUSIONS 108
APPENDIX A DETAILED RELATIVE COST
ESTIMATES OF REMEDIAL ACTION TECHNOLOGIES
APPENDIX B DETAILED RELATIVE COSTESTIMATE OF SELECTED REMEDIAL ACTION ALTERNATIVES
LIST OF FIGURES
FIGURE 1 ALTERNATIVE CAPPING TECHNOLOGIES
FIGURE 2 PRELIMINARY COST ASSESSMENT FOR TREATMENTAND DISPOSAL OF CONTAMINATED GROUNDWATER
Page
15a
74a
FIGURE 3 EXCAVATION AND DISPOSAL IN A CONTAINMENTTREATMENT FACILITY (ALTERNATIVE BNR 1)
FIGURE 4 PHYSICAL CONTAINMENT(ALTERNATIVES BNR 2 AND FMC 1)
FIGURE 5 HYDRAULIC CONTAINMENT(ALTERNATIVE BNR 3 AND FMC 2)
FIGURE 6 PROPOSED LOCATIONS FOR EXTRACTION WELLS- HYDRAULIC CONTAINMENT
75b
76b
79a
89a
FIGURE 7 ASSUMED RELATIONSHIP BETWEEN TCE REMOVALAND MASS VS PORE VOLUMES
92a
LIST OF TABLES
TABLE 1 EVALUATION OF REMEDIAL TECHNOLOGIES
TABLE 2 SUMMARY OF SELECTED REMEDIAL TECHNOLOGIES
TABLE 3 PREFERRED TREATMENT AND DISPOSAL METHODFOR CONTAMINATED GROUNDWATER
9a
63a
74b
TABLE 4 ESTIMATED COST SUMMARY FOR REMEDIAL ACTIONALTERNATIVES
75a
TABLE 5 SUMMARY OF ESTIMATED COST FOR HYDRAULICCONTAINMENT REMEDIAL ACTION ALTERNATIVESTO ACHIEVE 10-6 AND 1CT5 RISK LEVELSAT STIPULATED EVALUATION LOCATIONS
88a
LIST OF TABLES (continued)
Page
TABLE 6 AVERAGE AQUIFER PROPERTIES 89b
TABLE 7 SUMMARY OF REQUIRED PUMPING RATES FOR 95aEXTRACTION WELLS FOR HYDRAULIC CONTAINMENTPREFERRED REMEDIAL ACTION ALTERNATIVE
1
1
I
L
1.0 INTRODUCTION
I In response to the June 8, 1983
j Administrative Order and Interim Response Order by Consent
(Consent Order) between FMC Corporation (FMC), the Minnesota
I Pollution Control Agency (MPCA) and the United States
Environmental Protection Agency (USEPA), FMC has submitted
\ under separate cover, the report entitled "Feasibility Study
• - FMC and BNR Lands Groundwater Regime", Conestoga-Rovers and
^ Associates Limited, January 1985. The Feasibility Study
I evaluated the impact of volatile organic compound (VOC)
contamination identified in the groundwater beneath the Site,
1 on present and future potential human receptors and concluded
I that a long term groundwater monitoring program was the
appropriate response action for the Site. In the context of
} this report, reference to the Site as discussed herein shall
collectively mean the lands owned by FMC and the lands owned
I ^ by Burlington Northern Railroad (BNR).
In addition to carrying out the evaluation
1 contained in the Feasibility Study, the MPCA and USEPA
(hereafter referred to collectively as the Agencies) further
1 requested that FMC evaluate remedial action alternatives
, which would attain 10~6 and 10~5 excess cancer risk
criteria at defined evaluation locations between the Site and
1 the Mississippi River (MPCA letter dated December 6, 1984;
USEPA letter dated December 7, 1984). The Agencies
l_ identified the evaluation locations to be as follows:
i 1
1 i) the western boundary of the Site,
ii) the eastern boundary of the Anoka County lands,
| iii) the Mississippi River shoreline, and
i iv) the Minneapolis Water Works intake.
In submitting this further evaluation of
remedial action alternatives in accordance with the Agencies'
} request, FMC does not acknowledge or agree that such an
/ evaluation is warranted where the risk assessment contained
— in the Feasibility Study indicates no further response
I actions other than long term monitoring need be considered.
This further report is not required by the provisions or
1 intent of the June 8, 1983 Consent Order or applicable law,
i including the National Contingency Plan, 40 C.F.R. 300.
Remedial action alternatives are considered herein on the
I basis of data and information which are presently available.
Additional data and information collection would be
1 _ necessary, including information on the total cost of any
j particular remedial action, to determine whether a remedial
action would be cost-effective.
iThis remedial action alternative evaluation
I is organized in the following manner:
Section 2 provides a qualitative assessment of potential
{ remedial technologies within each remedial category
previously identified with the Agencies.
Section 3 provides a quantitative evaluation of the
technology chosen under each remedial category and identifies
the selected remedial action alternative which would achieve
a contaminant level equivalent to the 10 excess cancer
risk criterion at the Site property boundary.
Section 4 evaluates the performance standards of the selected
technology identified in Section 3 at each of the evaluation
locations stipulated by the Agencies.
Section 5 provides conclusions generated by the remediation
alternative evaluation.
This report is being submitted as an
accomodation to the Agencies. In light of the Feasibility
Study conclusions and the provisions of the Consent Order,
FMC does not believe the evaluation is warranted or required.
Furthermore, the 10-5 an(j io~6 excess cancer risk
criteria imposed by the Agencies have insufficient scientific
and medical support for their use. Even if FMC accepted such
criteria as valid for use at human receptors, which it does
not, the risk criteria at non-receptors should be
significantly lower.
I
2.0 PRELIMINARY ASSESSMENT OF POTENTIAL REMEDIAL TECHNOLOGIES
I 2.1 GENERAL
This chapter provides a preliminary
J assessment of potential remedial technologies which may be
feasible in achieving 10-6 an(j io~5 excess cancer
1 criteria at the specified evaluation locations.
_ The Feasibility Study concluded that
| contaminant levels in groundwater between the western
property boundary of the Site and the River did not pose a
I significant risk to current or future receptors. Therefore,
j candidate remedial technologies will be those that may be
feasible as source control measures, i.e., those that will
I control or contain the contaminants remaining on or beneath
the Site.
II Potential remedial technology categories
assessed in this chapter include excavation and disposal of
1 contaminated soils below the groundwater table, capping,
physical containment, hydraulic containment, groundwater
{ treatment, groundwater disposal, and alternate water source
i supply. The purpose of this preliminary assessment is to
identify a selected technology within each of the technology
I categories assessed.
II
At this level of assessment, no attempt has
been made to combine technologies within or between
j categories. Technologies have been assessed individually
. with respect to their effectiveness at performing the
' intended purpose for the category and without consideration
I of positive or negative effects when applied in combination
with other technology categories. The preliminary assessment
| process considers only major positive and negative features
. of the technology based on available data. The selected
^ technology for each category has been then identified based
[ on quantifiable and comparative features.
| The preliminary assessment of potential
. remedial technologies therefore allows an evaluation and
methodical reduction of the number of technologies in each of
I the identified categories. This is required in preparation
for assembling and screening remedial action alternatives as
] discussed in Section 3. The discussion presented under
I Section 3 will combine, assess and screen in more detail the
selected remedial technologies identified in this section.
1\ 2.2 ASSESSMENT CRITERIA
The preliminary selection or rejection of
I applicable remedial technologies was based on the following
general factors:
1. the chemical and physical characteristics of the
contaminant(s) that affect the effectiveness of a
I remedial technology,
2. physical site conditions that would preclude, restrict
I or promote a specific technology, and
1 3. the track record of a technology, including
i performance, reliability and operation
— characteristics.
iBased on the above three factors, potential remedial
I technologies were generated under various categories as
presented in Section 2.4. These potential remedial
technologies were then further assessed based on the
| following criteria:
I — 1. Technical Feasibility: Technical feasibility included
j a general assessment of reliability, implementation,
and safety. Effectiveness, durability and track record
| were considered under reliability. Implementation was
concerned with ease of installation, applicability to
1 Site conditions, time to implement and monitoring
j requirements. Safety addressed the relative safety of
a technology during operation and in the event of
I failure of the technology.
2. Environmental, Public Health and Institutional Impacts:
The environmental perspective addressed short- and
J long- term impacts on the natural and man-made
/ environments. These impacts include odor, noise, air
pollution, surface water and/or groundwater pollution,
\ use of natural resources, habitat alterations,
relocation of man-made structures and/or services, and
1 aesthetic changes. Public health addressed short- and
, long-term exposure from Site contaminants.
_ Institutional impacts considered environmental quality
I standards, land use, and federal, state or local laws
and/or policies.
II 3. Cost: The cost comparison involved development of
relative costs for each technology. Elements common
f among each technology assessed within a specific
category were not included in the relative cost
assessment. Costs presented are not, therefore,
, intended to represent actual construction cost
' estimates.
I| 2.3 PRELIMINARY ASSESSMENT RATING SYSTEM
*• Based on the assessment criteria developed in
| the previous section, each technology was individually rated
in accordance with the following scale:
II
L1
Rating Description
-2 Extremely negative effects, even with mitigating
measures. Technology not worth further
consideration in this category.
-1 Negative effects but not strong enough or certain
enough to be sole justification for eliminating
technology in this category.
0 Does not affect existing conditions or of very
little positive or negative affect.
1 A positive benefit.
+2 Extremely positive benefit.
* Inappropriate to draw conclusions at this point in
evaluation process.
8
2.4 PRELIMINARY ASSESSMENT OF POTENTIALREMEDIAL TECHNOLOGIES
This section provides the preliminary
I assessment of potential remedial technologies based on the
criteria stated in Section 2.2 and the preliminary assessment
I rating system identified in Section 2.3.
In order to establish consistent ratings,
I each potential remedial technology was rated according to its
effectiveness at performing its intended purpose within its
I specific category. Each individual remedial technology,
j therefore, does not address all hazards or problems
identified on the Site by itself. It was assumed that
I concern regarding other Site hazards could be potentially
mitigated by implementing or combining technologies from
I other categories. This is discussed in Section 3.
ITable 1 summarizes the preliminary assessment
1 of all potential remedial technologies discussed in the
following sections.
I
2.4.1 Excavation and Disposal
IThe excavation and disposal technology, in
L general, involves the excavation of saturated contaminated
materials from an identified area ("hot spot") with disposal
TABLE I
EVALUATION Of REMEDIAL TECHNOLOGIES
FMC CORPORATIONMINNEAPOLIS, MINNESOTA
SCREENING RATING COMMENTSTECHNOLOGY
Technical EnvironmentalP u b l i cHealth Institutional
CapitalCost Advantages
CATEGORY Excavation and Disposal (Section 4.4.1) (Costs based on a one acre area, contaminated from the 20 foot depth to the 35 foot depth)
Transportation andDisposal ofContaminated Soilsat a Hazardous WasteLandf111 Approvedby USEPA
Disposal ofContaminated SoilsIn a ContainmentFacili t y (CF)ConstructedOn-slte.
preferred technology for remedial category
N/A S 8,335,000
» 15,000 t 1,288,000
- physica l ly removes contaminatedmaterial off site, therebyminimizing future potential ofgroundwater contamination
- minimal site disturbance- restores future usage of entire
site- minimal future maintenance and
mon I tor I ng
- physically removes contaminatedmaterial and secures In CF,thereby reducing futurepotential of groundwatercontamination
- below grade on-sl te CF reducesrequirement for Imported f i l lfor site regradtng
- capital costs are low
Disadvantages
excavated material transportedoff site w i l l requirereplacement wi th Imported f i l lfor gradingdepending on depth and extentof contamination, capital costscan be prohibitivewaters collected throughdewaterlng w i l l requiretreatment and disposal.
extensive site disturbanceduring constructionarea of CF restricts futuresite usagecontinual monitoring andmaintenance of CF requiredwater collected throughdewaterlng w i l l requiretreatment and disposal.
continued....
TABLE 1
EVALUATION OF REMEDIAL TECHNOLOGIES
FMC CORPORATIONMINNEAPOLIS, MINNESOTA
SCREENING RATINGTECHNOLOGY
Public Summation MM Cost CapitalTechnical Environmental Heal th Institutional ol Rating per Year Cost
II. CATEGORY Capping (Section 4.4.2) (Costs based on a one acre area)
I . Normal Portland + t + 1 0 0Concrete Pavement
I 2,000 $ 100,000
COMMENTS
Advantages
minimal slope required,therefore minimal sitepregradlng requiredexcellent water repellencyexcel lent weatheringcharacteristicsdurable, long ternhard surface permits futuresurflclal usage of sitemoderately low maintenance costs
Disadvantages
Increased stormwater managementconcernstypical cap thickness Is 12Inches, may require removal ofexisting material from sitereinforcing and granular baserec 01 mendedmaintenance Involves repair offractureshigh capital cost
2. Asphaltlc ConcretePavement
$ 4,000 t 84,000 minimal slope required,therefore minimal sitepregradlng requiredexcellent water repellencygood weathering characteristicsdurable, long termsemi-rigid structure, thereforemore responsive to minordeflections and movement thannormal port)and concretepavement with minimal crackinghard surface permits futuresurflclal site use
Increased stormwater managementconcernstypical cap thickness Is 16Inches, may require removalof existing material frcm siteweathers more rapidly thanPortland cement concretepavement and Is susceptible toattack by v o l a t l l I zedcon tan I nan tsgranular base recommendedmaintenance Involves occasionalover I ays
• moderately high capital andmaintenance costs
con 11nued....
TABLE t
EVALUATION OF REMEDIAL TECHNOLOGIES
FMC CORPORATIONMINNEAPOLIS, MINNESOTA
TECHNOLOGYSCREENING RATING
Public Summation O&M Cost CapitalTechnical Environmental Health Institutional of Rating per Year Cost
COMMENTS
II. CATEGORY Capping (continued)
3. In-sltu soil 0Admixtures
-1 -2 $ 8.000 $ 41.000
Advantages
does not Increase voluveon-slte, therefore no materialto be removed fro* sitemoderate water repellencyIon capital cost
Disadvantages
moderate slopa required,therefore moderate sitepregradlng requiredmay require off-site materialfor pregradlng
• low durability restricts futuresite usage
• veathers more rapidly thanPortland cement concretepavement and Is susceptible toattack by volatilizedcontonlnants
• hard surfacing sealantrecommended
• Increases stormnater managementconcerns
• maintenance requires frequentsurface reseating
• high maintenance costs
continued*...
TECHNOLOGY
TABLE I
EVALUATION OF REMEDIAL TECHNOLOGIES
FMC CORPORATIONMINNEAPOLIS, MINNESOTA
SCREENING RATING
Public Summation 04M Cost CapitalTechnical Environmental Health Institutional of Rating per Year Cost
COMMENTS
II. CATEGORY Capping (continued)
4. Sprayed an Covers -1 -1 -1 -3 f 8,000 $ 25,000
Advantages
minimal slope required,therefore Minimal siteregradlng requiredtypical thickness Is 1/4Inch, therefore no materialto be removed froi siteexcel lent water repellencyeasy to apply
• low capital costs
Disadvantages
Increases stormwater managementconcernsmay require off-site materialfor pregradlngpoor durabll Ityrestricts future usage of sitemaintenance Involves extensiverecoatlnghigh maintenance costs
5. Low PermeabilitySoil Cover
46" $ 3,000 t 91,000 - minimal effect on existingfirst 2 yrs, stormwater runoff
1,000 - good water repellencythereafter - flexibility allows significant
movement with minimal effectson cap Integrity
- moderate to low maintenancecosts
" - preferred technology for remedial category
surface drainage Important,thereafore significant siteregradlng requiredtopsoll over loon over clayrecommended with vegetativecover for erosion controloverall thickness exceeds 5ft., may require removal ofexisting material from sitecontinual surface maintenancerequiredlimited future site use optionsloam over clay required tomaintain moisture In clay andprevent desslcatlonmoderate capital cost
continued....
TABLE I
EVALUATION OF REMEDIAL TECHNOLOGIES
FMC CORPORATIONMINNEAPOLIS, MINNESOTA
SCREENING RATINGTECHNOLOGY
PublicTechnical Environmental Health Institutional of Rat I
II. CATEGORY Capping Ccontlnued)
6. Synthetic Membranes +1 -H +1 +1 *4
Summation MM Cost Capitalper Year Cost
$ 3,000 $ 74,000first 2 yrs,
1,000thereafteruntilsyntheticlinerreplacementrequired
COMMENTS
Advantages
minimal effect on existingstormwater runoff whenprotective cover usedgood water repellencyflexibility alIons moremovement with minimal effectson leakagemoderately low capital costs
1 moderate maintenance costs
Disadvantages
membrane protection requiredtopsoll over loan protectivecover recommendedvegetative cover recommendedsurface drainage Important,therefore significant sitepregradlng requiredtypical overall membrane andcover thickness Is 2 1/2 ft.,may require removal of existingmaterial from site
7. CompositeConstruction
+2 +8 t 3,000 t 132,000first 2 yrs,
1,000thereafteruntilsyntheticlinerreplacementrequired
minimal effect on existingstormwater runoffgood water repellency,provides double form ofInfiltration protection
• flexibility allowssignificant movement withminimal effects on leakagemoderate maintenance costs
surface drainage Important,therefore significant sitepregradlng required
1 protective cover and vegetationrecommended
> cover thickness exceeds 5 ft.,may require removal of mistingmaterial frcm siterestricts future site useoptionscontinual surface maintenancerequired
• high capital costscontinued....
TABU 1
EVALUATION OF REMEDIAL TECHNOLOGIES
FMC CORPORATIONMINNEAPOLIS, MINNESOTA
SCREENING RATINGTECHNOLOGY
Public Summation MH CostTechnical Environmental Health Institutional of Rating per Year
CapitalCost
COMMENTS
III.
I. Slurry Halls(common to all types)
Advantages
Physical Containment (Section 4.4.3) (Costs based on containing a one acre area to I) 135 foot depth, and II) n foot depth)
See Subparts a, b & c for Rating - provides a continuous barrieragainst groundvater migration
- low maintenance requirements
Disadvantages
- excavated soils may requiretreatment as contaminatedmaterial
- economic feasibility dependanton required depth of slurry•all
- conventional backhoe can reach10 ft. - good production rate
- specially modified backhoe canreach 75 ft. - moderateproduction rate
- clamshelI buckets required over75 ft. depth - slew productionrate
- monitoring required todetermine Integrity of slurrynail
- restricots future site usage- high capital cost
continued....
TABLE I
EVALUATION OF REMEDIAL TECHNOLOGIES
FMC CORPORATIONMINNEAPOLIS, MINNESOTA
SCREENING RATINGTECHNOLOGY
EnvironmentalRib lieHsalth Institutional
Summation 0AM Costof Rating car Year
CapitalCost
COMMENTS
Advantages
III. CATEGORY Physical Containment (continued) (costs based on containing a one acre site to I) 133 ft. depth and II) 3? ft. depth)
I.a Soll-bentonltemixtures
II)
Kb Ceiient-bentonlte I)mixtures
II)
0
+1
+2
+2
+1
+2
+2
+1
+1
+7"
*4
$1.026.000 - provides low permeabilitybarrier for medium to fine
129,000 grained soils- extremely durable- resistant to minor deformations- utilizes excavated material for
backfill, thereby minimizingmaterial to be disposed of
$1,657,000 - suitable for all soilclassifications
229,000 - provides some structuralstability to the containment wall
- requires less site area- durable
Disadvantages
- not suitable for medium coarsegrained soils
- requires significant site areafor mixing of so 11-ben ton I temixture
- containment wall w i l l dry,shrink and crack If notprotected from moisture loss
- disposal required for excavatedmaterial
- Imported material required forbackfi l l
- susceptible to cracking andloss of some Impermeability dueto curing and minordeformations
l.c Syntheticmembranetnstallotion
I)
II)
-2
-1
+2
+2
*• - preferred technology for remedial category.
-I
-I
0
-1
SI,443,000 - leakage detection systemensures effective monitoring
229,000 regarding effectiveness ofbarrier
- applicable for medium to finegrained soils
- permeable material required torbackfill , may require Importedmaterial and disposal ofexcavated material
- Integrity highly dependant onInstallation expertise
- technology In experimentalstage
- Implementation very d i f f i c u l tcontinued....
TABLE I
EVALUATION OF REMEDIAL TECHNOLOGIES
FMC CORPORATIONMINNEAPOLIS, MINNESOTA
SCREENING RATING COMMENTS
PublicHealth
Summation MM CoatRat Ins per Year
CapitalCost
TECHNOLOGY
Technical Environmental Health Institutional o( Rating per Year Cost Advantages
III. CATEGORY Physical Containment (continued) (costs based on containing a one acre site to I) l» ft. depth and II) 35 ft. depth)
2. Sheet Piles I)
0 * 1 * 1 0 t 789,000 - n o excavation o r handling o fIn-sltu material* required
II) -2
- minimal disturbance to site
Disadvantages
- provides a segmented barrieragainst groundxater migration
- Integrity questionable as mayhave window between adjacentpilings, therefore questionableeffectiveness
- depth limited to approximately35 ft. due to plumbness control
- applicable for medium to finegrained soils only
- restricted future site usage- monitoring required to
determine Integrity- extremely high capital cost- limited life span due to
material deterioration
continued....
TABU I
EVALUATION OF REMEDIAL TECHNOLOGIES
FMC CORPORATIONMINNEAPOLIS, MINNESOTA
SCREENING RATING COMMENTSTECHNOLOGY
EnvironmentalPublicHealth Institutional
CapitalCost Advantages
III. CATEGORY Physical Containment (continued) (costs based on containing a one acre site to I) 139 ft. depth and II) 3? foot depth)
I) not technically feasible at this depth range
II) -1 0 0 0 -I t 438,000
3. InjectionScreens
- Minimal disturbance to sitearea
- no excavation or handling ofIn-sltu materials required
- provides a more continuousbarrier than sheet piletechnology
- durable
Disadvantages
- not ensured of continuousbarrier due to potentialwindowing of sheet piling
- depth limited to approximately39 ft* due to piunbness control
- applicable for fine to mediumgrained soils only
- restricted future site usage- monitoring required to
determine Integrity- moderate capital cost
4. Grout Curtain I)
II)
+2
+1
+2
+2
+2
+2
+7"
+6
" - preferred technology for remedial category
$ 676,000 - minimal disturbance to sitearea
S 179,000 -handling of In-sltu materialslimited to drill spoils
- continuity of barrier can beImproved by decreasing spacingof grout holes
- applicable to all material types- durable- no depth limitation- easily modified by Installation
of additional holes.
not ensured of continuousbarrier due to uncontrollabledeflection of d r i l l i n grestricted future site usagemonitoring required todetermine Integritymoderate capital cost
continued...
TABLE 1
EVALUATION OF REMEDIAL TECHNOLOGIES
FMC CORPORATIONMINNEAPOLIS, MINNESOTA
SCREENING RATING COMMENTSTECHNOLOGY
Technical EnvironmentalPublicHealth Institutional
Summationof Rat In
MM CostYear Advantages
IV. CATEGORY Hydraulic Containment (Section 4.4.4) {Costs based on containing a one acre area to I) 13? foot depth and II) 35 foot depth)
Extraction Me)I I) +2System
II) +2
+2
+2
+1
+1
+7"* $ 2,200 * 35,000
+7" $ 2,000 $ 32,000
- removes contmlnants fromsaturated zone, therebyMinimizing potential futuregroundwater contamination
- easily adjusted to compensatefor heterogeneous geologicconditions or groundvaterquality and quantity
- durable- required only for limited
period- ultimately restores full
usage of site- moderately low capital costs
Disadvantages
- additional remedial technologyrequired for disposal ofextracted water
- depletes groundvater resourceduring period of operation
- moderately high operation andmaintenance costs associatedMlth subsequent handlingrequirement of extractedgroundvater
"* - preferred technology for remedial category
continued....
TABLE 1
EVALUATION OF REMEDIAL TECHNOLOGIES
FMC CORPORATIONMINNEAPOLIS, MINNESOTA
SCREENING RATING COMMENTSTECHNOLOGY
Public Simulation O&M Cost CapitalTechnical Environmental Health Institutional of Rating per Year Cost Advantages
IV. CATEGORY Hydraulic Containment (continued) (costs based on containing a one acre area to I) 135 ft. depth and II) 33 foot depth!
2. I)Extraction andInjection Hal ISystem II)
*2
+1
+1
+1
+4 $ 10,900 S 197,000
+4 t 11,200 $ 151,000
reduces contaminants fromsaturated zone, therebyminimizing potential futuregroundwater contamination
> easily adjusted to compensatefor heterogeneous geologicconditions or groundxaterquality and quantitydurable
• required for shorter periodthan extraction only veilsystemIf treated extractedgroundvat«r used for Injection,minimize depletion ofgroundwater resource
• ultimately restores full usageof site
Disadvantages
- additional remedial technologyrequired for treatment ofextracted water prior toInjection, or additionalremedial technology requiredfor disposal of treated waterand supply other water forInjection
- high operation and maintenancecosts associated primarily withsubsequent disposal ofextracted groundwater andsupply of water for Injection
- moderately low capital costs
continued....
TECHNOLOGY
TABLE I
EVALUATION OF REMEDIAL TECHNOLOGIES
FKC CORPORATIONMINNEAPOLIS, MINNESOTA
SCREENING RATING
Public Subnotion MM Cost CapitalTechnical Environmental Health Institutional of Rating per Year Cost
V. CATEGORY GroundNater Treatment (Section 4.4.5)
1. Biological -1 +1Treatment
2. Carbon Adorptlon
3. Air Stripping
* Costs depend on volume and quality of Influent. ** Preferred technology for remedial category
COMMENTS
Advantages
Moderately ION capital costoperation and Maintenancedependent on results of pilottesting, can be Moderately ION
Disadvantages
- May be Insufficient organicMatter In groundNater to sustainbiological activity
- potential for uncontrolledrelease of volatile organiccompounds to atmosphere
- require substantial amount ofpilot testing
- require disposal of biologicalsludge
- operation and Maintenance costscan be extremely highdependent on characteristics ofcontaminated groundNater to betreated and volume
proven technology appl(cablefor both air and water phasesachieves a high level ofcontaminant removallittle potential for emissionof volatile organic compoundsto atmospheremoderately ION capital cost
proven technology for removal of - does not remove contaminants tovolatile organic contaminants same degree as carbon adsorptionfrom groundNater - May require polishing of treatedmoderately ION capital, operation *ater and air emissions fro* theand maintenance costs stripping process
continued....
TABLE I
EVALUATION OF REMEDIAL TECHNOLOGIES
FMC CORPORATIONMINNEAPOLIS, MINNESOTA
SCREENING RATINGTECHNOLOGY
Public Summation CAM Cost CapitalTechnical Environmental Health Institutional of Rating per Year Cost
VI. CATEGORY Groundwater Disposal (Section 4.4.6)
I. Discharge to a +1 -I -1Surface Fresh MaterBody
-1 -2
2. Discharge to aPublicly OwnedTreatment WorksIPOTW)
+1 -I
3. Disposal at a RCRADisposal Facility
-I -I
COMMENTS
Advantages
applicable to both treatedand untreated waterlow capital cost providedallovable receiving waterbody Is nearbyloo operation andmaintenance costs
applicable to both treatedand untreated waterlow capital cost provided a
POTW Is nearby
applicable to both treatedand untreated waterlow capital cost
* Costs depend on quantity and quality of effluent. *• Preferred technology for remedial category
Disadvantages
quality and quantity of waterto be discharged must meetallowable dischargerequirements for fresh waterrequire monitoring to ensuredischarge complies withrequirements
• quality and quantity of waterto be discharged must meetrequirements of MetropolitanWaste Control Commission (MWCC)require monitoring to ensuredischarge compiles withrequirementsoperation and maintenancecosts can be extremely high,depending on MWCC charges
requires transport via publictransportation systems fromsite to disposal facility
• operation and maintenance costsdependent on transport chargesand gate fees per volume ofgroundwater to be disposed of
continued....
TECHNOLOGY
TABU 1
EVALUATION OF REMEDIAL TECHNOLOGIES
FMC CORPORATIONMINNEAPOLIS. MINNESOTA
SCREENING RATING
Public SuMutlon MM Cost CapitalTechnical Environmental Health Institutional of Rating per Year Cost
VI. CATEGORY Oroundnatw Disposal (continued)
4. Relnjectlon +1 -1 -1
Advantages
Ion capital costIon Maintenance cost
COMMENTS
Disadvantages
applicable to treated wateronlyrequire a peralt
5. Deep HellInjection
»1 -2 -2 appl (cable to botti treatedand untreated waterloo capital costs afterIdentification of suitablereceiving aquiferION operation and maintenancecosts
require peewitpotential future exposure Ifreceiving aquifer Is tapped orleaksrequire extensive Investigationto Identify suitable receivingaquiferhigh Initial capital cost,usually only appropriate forlarge Haste vo I IOTAS
• Costs depend on quantity and quality of •fluent. continued...
TECHNOLOGY
TABLE I
EVALUATION OF REMEDIAL TECHNOLOGIES
FMC CORPORATIONMINNEAPOLIS. MINNESOTA
SCREENING RATING
Public Summation 0AM Cost CapitalTechnical Environmental Health Institutional of Rating per Year Cost
COMMENTS
V I I . CATEGORY Alternate Mater Source Supply (Section 4.4.7)
1. Mall Outside +1 +2 +2ContaminatedPlume
2. Portable PotableWater Del(veryService
3. Use ExistingMunicipalService
-2 +2
Advantages
all three alternativessatisfy objective tominimize potential risk tooff-site receptors ofeffects of contaminatedgrounditater
Disadvantages
- all three alternatives requireIdentification of all futurepotential receptors withineffective zone of contaminantplume
- costs depend on water qualityand quantity requirements ofusers and on distance users arefrom supply source point.
* Costs depend on volume and quality of Influent** Preferred technology for remedial technology
of the excavated contaminated material in an approved manner.
Disposal may be at either on-site or off-site facilities.
The purpose of excavation and disposal is to
physically remove the source of contaminants available for
future migration. This technology is, therefore, reliable
and effective in minimizing future groundwater
contamination.
Once the source of contamination has been
removed, imported fill would be required to backfill the site
to the approximate existing site elevations, and surficial
vegetation would be restored. The site would then be
returned to normal usage.
The feasibility of the excavation and
disposal technology is limited by the extent of contamination
and in-situ conditions. Excavation to significant depths and
disposal of extremely large quantities of contaminated
material generally is not feasible since extensive amounts of
earthwork are required. Also the depth of excavation is
usually limited to the unsaturated zone to avoid excessive
dewatering costs. Additional excavation may be limited to a
practical physical depth because of the volume of material to
be moved. If the contaminated zone is not in the upper soil
stratum, excavation and replacement of the uncontaminated
overburden usually renders this technology unacceptable.
Alternatives for disposal of the contaminated
excavated material include:
10
1. transporting off site to a hazardous waste landfill
approved by USEPA, and
2. securing in a newly constructed on-site containment
facility (CF).
A brief discussion of each of these disposal
technologies follows:
2.4.1.1 Disposal at an Off-Site HazardousWaste Landfill
Excavation of contaminated material would be
performed by a backhoe or other mechanical means. Excavated
material would be loaded directly into hazardous waste
licensed haulers and transported to an off-site hazardous
waste landfill approved by USEPA. Imported fill material
would be required to backfill the excavated areas.
The excavation and disposal method results in
minimal long-term disturbance to the site and permits full
future usage of the site. Long-term management of the
contaminated material would become the responsibility of a
third party.
Capital costs for off-site disposal are
extremely high compared to securement of contaminated
materials in an on-site CF due to transport costs and tipping
fees at the disposal facility. The magnitude of this
11
cost differential between off-site disposal and on-site
containment would be dependent on the distance between the
off-site disposal facility and the site. A major constraint
to off-site disposal is that it is doubtful that landfill
capacity exists at current USEPA approved sites within a
reasonable distance of the Site for the volume of material
that would be excavated. Additionally, transport of
hazardous waste by road inherently has a potential for
spillage of contaminants by haulage unit upset, accident or
equipment malfunction.
2.4.1.2 Disposal On Site
A CF for the on-site disposal of contaminated
soil would consist of a base, cap and sidewalls constructed
of low-permeability clay with a second internal synthetic
liner installed to further insure containment of
contaminants. A CF would be constructed either above ground
or below ground and either off-site or on-site.
Construction activities include constructing
the clay and synthetic liner base and sidewalls (above or
below ground), excavating the contaminated material and
placing it in the CF, constructing the synthetic overliner
and clay cover, and site restoration.
12
A below-ground CF is generally more feasible
than above-ground construction since the excavated material
from the CF construction may be used to backfill the
contaminated area excavation. The amount of imported
material required to fill this area of excavation is,
therefore, minimized. On-site construction of a CF would
generally be preferred to off-site construction since items
such as off-site transport, fill material and additional land
aquisition are all minimized.
Construction of an on-site CF would restrict
future site usage in the vicinity of the facility. Long-term
monitoring and maintenance of the CF final cover, and of
groundwater quality adjacent to the CF would also be
required.
Capital costs for the CF are moderately low
compared to off-site disposal when significant volumes of
contaminated material are considered.
2.4.2 Capping
I The capping technology, in general, involves
the construction of a low- to very low-permeability cover
I over an identified area of contamination. The purpose of
this cover is to minimize infiltration of surface waters
I through the contaminated unsaturated soils, thus reducing the
i 13
long-term mass loading rate of contaminants into the
groundwater from the unsaturated zone. The capping
[ technology does not address removal of the contaminants in
r" the soils below the cover and, therefore, does not remove the
potential source of future groundwater contamination. The
I capping technology also does not address containment or
removal of contaminants presently in the groundwater.
1 Capping does provide long-term protection against contact by
humans or wildlife with the contaminated soils, uncontrolled
^ volatilization of contaminants to the atmosphere, migration
of contaminated sediments by surface water runoff, and
migration of contaminants dissolved in surface water runoff
contacting contaminated soils.
Alternatives for provision of a low-
permeability cover over identified areas of contamination
include:
i _i 1. normal portland concrete pavement,
2. asphaltic concrete pavement,
J 3. in-situ soil admixtures,
4. sprayed on covers,
[ 5. low-permeability soil cover,
i 6. synthetic membranes, and
7. composite construction.
LTypical cross-sectional views of each of the
I above low-permeability capping options are presented in
i 14
If
Figure 1. A brief discussion of each of these capping
technologies follows.
2.4.2.1 Normal Portland Concrete Pavement
rThis technology involves removal and disposal
I of the existing organic topsoil, pre-grading the site to
provide contouring for effective surface water runoff,
"~ placement of a 6-inch thick granular base course and
placement of a 6-inch thick concrete slab.
1 The concrete slab would provide a durable
surface which would permit selective future surface use of
the site for storage or parking. The concrete slab has
excellent weathering characteristics and excellent water
repellency.
• ""-—-
j Due to the reduced infiltration rate,
increased precipitation runoff can be anticipated which may
cause stormwater management concerns. Large areas of
concrete pavement may, therefore, require some form of
1 stormwater retention to control peak runoff rates.
Although normal portland concrete is
I susceptable to cracking from settlement, shrinkage and frost
heave, proper design of expansion and contraction joints and
15
mm.
<: 6 CONCRETE%6. GRANULAR BASE
NORMAL PORTLAND CONCRETE PAVEMENT
_____________ 2% mm.
6" TO 12" LIQUID ASPHALT OR PORTLANDCEMENT MIXED WITH INSITU MATERIAL
V'̂ K'̂ -̂ ^V'^blfl-NATIVE^MATERIAL.^rO^x,1
- -•!.">" -.'"I VrV^O r-'ilrV'.Y-.•"-*
IN SITU SOIL ADMIXTURES
-'6" SANii \' H YLENE LINER :
SYNTHETIC MEMBRANE
::::.-:6"SAiy yM& HIGH DENSITY Si:;:;:::;:
' ' ' ' ' ' ' ' ' ' ' ' ' ' '
;^^^vr';''v<:>'^:':-l;v>iV7'^^^:V''c/-,r': NATIVE MATERIAL '''̂ 'x'̂ -'/''x.-.--''.OVooNS^"./!-.''•>-'*--.'f'.A'.."
CRA COMPOSITE MEMBRANE
.-;•• 4'.-ASPHALT •?••:,•:..
• 12 GRANULAR BASE •••-.o : • : • . • : • . • - . .-••:.•: • - - . . . . -p .
o
ASPHALTIC CONCRETE PAVEMENT
'A" THICK SPRAY COATING |O/°min-
•"r,\»j,-NATIVE MATERIAL :!&£;£-
SPRAYED ON COVERS
SEEDED
TOPSOIL
3% mio min.
LOW PERMEABILITY SOIL COVER
figure IALTERNATIVE
CAPPING TECHNOLOGIESFMC Northern Ordnance Plant
ISIS-29/04/89
proper construction methods will ensure control of the
cracking and minimize future maintenance.
The moderately low maintenance costs of the
normal portland concrete pavement technology help to offset
the high initial capital construction cost.
, 2.4.2.2 Asphaltic Concrete Pavement
j This technology involves removal and disposal
of the existing organic topsoil, provision of surface
contouring for effective surface water runoff, placement of a
• 12-inch thick granular base course and placement of a 4-inch
' thick asphaltic concrete surface course.
IAsphaltic concrete specifically designed to
( ^ reduce infiltration is similar to highway paving asphaltic
• concrete except that the percentages of mineral filler and
• asphalt cement are increased. The increased percentage of
j mineral filler and asphalt cement serve to provide an
excellent water repellent surface as well as to decrease thef[ photosensitive weathering characteristics of this asphaltic
concrete pavement when compared with normal asphaltic
'• pavements.
L
16
The asphaltic concrete surface retains enough
flexibility to mould to slight deformations of the subgrade
and is more resistant to surface cracking than normal
Portland concrete pavement. The asphaltic surface, however,
is durable enough to permit selective future surface use of
the site such as a storage or parking area.
The increased precipitation runoff resulting
from reduced infiltration by the asphaltic concrete pavement
may cause stormwater management concerns and may require some
form of stormwater retention to control peak runoff rates.
The asphaltic concrete pavement technology
has lower initial capital cost than normal portland concrete
pavement but generally requires increased maintenance over
the long term, since asphaltic concrete has a shorter
service life than does normal portland concrete.
2.4.2.3 In-situ Soil Admixtures
1This technology involves removal and disposal of
1 the existing organic topsoil, provision of surficial
• contouring for effective surface runoff, and addition and
mixing into the soil of either a liquid asphalt to create
I soil asphalt, or portland cement and water to create soil
cement. In either case, the mixing depth, approximately six
17
LI
to 12 inches, results in soil physical properties greater
than the natural soil. It may be necessary to import
material for contouring to create a minimum one percent
surface grade. Neither admixture will provide a surface as
durable as the normal portland concrete pavement or the
asphaltic concrete pavement technologies.
Soil cement has a tendency to crack and
shrink on drying, and soil asphalt generally retains a high
void content. Therefore, both soil cement and soil asphalt
do not contribute significantly to reducing permeability, and
both require a surface sealent such as epoxy asphalt or epoxy
coal-tar for the soil cement, or a bituminous seal for the
soil asphalt.
As with the normal portland concrete pavement
and the asphaltic concrete pavement, surface precipitation
runoff will be increased over the area where the in-situ
admixture has been placed. This may require further controls
for stormwater runoff management.
The initial low capital cost of the in-situ
soil admixture technology would be offset by high maintenance
costs for periodic surface resealing.
18
I
2.4.2.4 Sprayed on Covers
This technology involves removal and disposal
of the existing organic topsoil, provision of surficial
contouring for effective surface water runoff, compaction and
rolling of the base to obtain a smooth surface and
application of a sprayed surface membrane. The membrane
material generally used is an asphalt; however, more recent
advancements using rubber and plastic latexes are presently
in the experimental stages. The finished sprayed membrane
has a thickness of approximately 1/4 inch. Since minimal
material is imported onto the site to construct the sprayed
on cover, material may have to be imported for surficial
contouring to achieve the required grades to promote surface
water runoff.
Sprayed on membranes generally are not
durable. Without a protective cover future usage of the site
would be severly restricted.
The sprayed on cover has excellent water
repellency. As with the normal portland concrete and
asphaltic concrete pavements this may cause increased
stormwater management concerns.
j The low initial capital cost of the sprayed
on cover technology is offset by high maintenance costs for
( recoating.
1 19
2.4.2.5 Low-Permeability Soil Cover
r This technology involves excavation and
f" stockpiling of the existing topsoil, excavation of the area
to be covered to a depth of six feet below design finished
I grade and stockpiling of excavated native material on site,
placement and compaction of clay to a hydraulic conductivity
1 less than 1 x 10-7 cm/sec to a depth of two feet,
| placement of a 6-inch thick sand blanket over the clay layer,
••—- placement of a 3-foot thick layer of common fill material
| . from the on-site stockpile over the sand blanket,
replacement of the topsoil over the area, and revegetation.
fj The clay layer provides a low-permeability
barrier which minimizes infiltration of surface waters. The
j sand blanket provides a drainage layer above the clay to
intercept and provide a drainage channel for infiltrated
( _. surface water. The layer of common fill serves to protect
f the clay layer from frost penetration and surface erosion.
This layer also retains moisture, thereby preventing
J dessication and fracturing of the clay layer. Replacing the
topsoil promotes revegetation which serves to reduce surface
1 erosion.
This technology has been proven to be
j effective and has longevity assuming proper design,
installation and maintenance. The effectiveness of the
< system is derived from the clay which is least susceptible to
I 20
cracking from settlement or aging, and tends to be
"self-healing". Long-term maintenance of the vegetative
cover and surface erosion is required. The vegetative cover
will reduce surface runoff, and thereby reduce stormwater
management concerns.
The moderate capital cost of the low
permeability soil cover technology is associated with a
moderate to low maintenance cost.
2.4.2.6 Synthetic Membranes
Ii This technology involves excavating and
• stockpiling the existing topsoil, excavating and regrading
j the site area to two feet below design finished grade with
stockpiling of this native material on site, placing the
^ ^ synthetic liner, placing a 6-inch thick sand blanket below
• and above the synthetic membrane, placing a 1-foot thick
layer of common fill from the on-site stockpile over the sand
| layer, replacing the topsoil over the site area, and
revegetation.
I, The initial 6-inch thick sand blanket
provides a cushion for the synthetic membrane which is a
J flexible polymeric material. The 6-inch thick sand blanket
above the synthetic membrane provides a drainage layer for
121
infiltrated surface water. The 12-inch depth of material
above this sand layer provides protection to the synthetic
membrane from surficial activities, and the replacement of
the topsoil permits revegetation for erosion control. Due to
the limited cover over the synthetic membrane, future site
usage would be restricted compared to a low permeability soil
membrane.
The synthetic membrane provides excellent
water repellency provided a good quality control program is
implemented and maintained during construction. Flexibility
makes this technology relatively less susceptible to cracking
from settlement or frost heave than others. Long-term
maintenance of the vegetative cover and prevention of surface
erosion would be required. Long-term replacement of the
synthetic membrane must be anticipated due to the potential
for degradation from biological or chemical agents. The
vegetative cover would reduce surface runoff, and thereby
reduce stormwater management concerns. The long-term
durability of synthetic liners has not been conclusively
demonstrated in the field.
The moderate capital cost of the synthetic
membrane technology is associated with a moderate maintenance
cost.
22
2.4.2.7 Composite Construction
This technology involves excavating and
stockpiling existing topsoil, excavating and regrading the
site area to six feet below design finished grade with
stockpiling of excavated material on-site, placing and
compacting clay to a hydraulic conductivity of less than
1 x 10-7 cm/sec to a depth of two feet, placing a 6-inch
thick sand drainage blanket over the clay liner installing a
synthetic membrane liner and a second 6-inch thick sand
blanket over the liner, placing to a depth of 2-1/2 feet over
the sand blanket common fill material from the on-site
stockpile, replacing the topsoil over the site, and
revegetation.
This technology provides two low-permeability
liners for the minimization of infiltration. The synthetic
membrane would serve to retain moisture in the clay layer,
thus minimizing dessication fracturing of the clay layer.
The 6-inch thick sand blanket below the synthetic membrane
would serve as a cushion while the sand blanket over the
synthetic membrane serves as a drainage layer. The fill
material would provide a protective cover for both the
synthetic membrane and clay layer. Replacing the topsoil
would permit revegetation for runoff and erosion control.
23
J Since the composite cap is constructed of two
materials of significantly different physical properties
' (clay and a synthetic plastic liner), the response of each
( liner to various conditions and stresses will also differ.
This response difference is important to the long- term
| integrity of the cap in that conditions or stresses which may
deteriorate the effectiveness of one of the cap members, may
' not impact the other. As a result, a failure of one of the
| cap members does not necessarily result in a failure of the
"— cap, as the second member acts as a safety net to protect
I against failure of the entire cap.
I This technology is effective in minimizing
I surface water infiltration due to the low permeability of the
synthetic membrane combined with the "self-healing"
I properties of the low-permeability clay. Long-term
maintenance of the vegetative cover and surface erosion would
' -_- be required. It must be anticipated that the synthetic
f membrane liner would require replacement periodically due to
the potential degradation from biological or chemical agents.
I The vegetative cover serves to minimize surface runoff and
stormwater management concerns.
j The high capital cost of the composite
construction technology is associated with a moderate
| maintenance cost.
24
I 2.4.3 Physical Containment
( The physical containment technology, in
f general, involves the securement of contaminated material
either by excavation and placement of the material in a CF or
| by construction of a perimeter barrier wall around the areai
of contamination, effectively securing the contaminated
I material in place. Section 2.4.2 has addressed securement of
I contaminated material in a CF. This section will address
^ securement of the contaminated material in place.
(The purpose of a perimeter containment system
1 would be to provide a relatively impervious barrier
i surrounding an area of known contamination to minimize and
control the migration of contaminants to the groundwater. In
order to effectively control contaminant migration within the
groundwater regime, a perimeter barrier wall must be keyed
into a confining layer of low permeability at its base,
* extend upward to an elevation above the groundwater level,
and completely encompass the contaminated area. A dewatering
( system consisting of either a gravity drainage tile system
connected to a pumped sump or an extraction well system would
j be constructed within the perimeter barrier wall. A minimal
. amount of water would be extracted to lower the natural
groundwater level within the perimeter barrier wall system,
I thereby ensuring an inward hydraulic gradient within the
contaminated area. This extracted groundwater would require
| further collection, treatment and disposal.
I25
The physical containment technology strictly
{ contains the source of groundwater contamination within the
/ perimeter barrier wall and does not address the actual
removal of contaminants except for those removed incidentally
I while maintaining hydraulic control of the system. This
technology, therefore, does not to any extent remove the
\ potential source of future groundwater contamination.
Alternatives for provision of a perimeter
barrier wall to contain a specified defined area of
contamination include:
i) slurry walls,
ii) sheet piles,
iii) injected screens, and
iv) grout curtains
A brief discussion of each of these physical
containment technologies follows:
2.4.3.1 Slurry Walls
This technology involves excavating a trench
to the depth of a confining base layer while adding
bentonite/water slurry to maintain a stable trench face.
26
fI Following excavation, the bentonite/water slurry is displaced
with selective low-permeability backfill materials to produce
{ a low-permeability barrier wall.
The effectiveness of slurry walls is
j dependent on the control of proper excavation procedures and
proper proportioning and placement of the select backfill
1 material. The construction procedure to form a slurry wall
/ provides a continuous rather than a segmented barrier.
| The trench excavation is most commonly and
economically performed with conventional hydraulic backhoes.
1 Specially adapted backhoes for slurry wall construction can
• reach depths in excess of 75 feet. When excavations exceed
this depth range, clamshells which are much less productive
J are usually required and, significantly increase the cost of
the slurry wall. Alternatively, where groundwater conditions
j ^ permit, the alignment of the slurry wall can be benched by
r earth moving equipment to a depth compatible with the reach
of the trenching equipment.
1The addition of bentonite/water slurry during
1 trench excavation, provides trench stability during the
. slurry wall construction. The bentonite has favourable
^ swelling characteristics when combined with water. The
1 slurry forms a filter cake on the trench walls and the
hydrostatic head of the slurry, acting against the
I
low-permeability filter cake, resists inward movement of the
trench walls. The surface of the slurry is maintained at a
higher elevation than the adjacent groundwater. Excavation
of the trench proceeds through the bentonite/water slurry,
with excavated material being replaced by the slurry. The
trench is then backfilled with selected low-permeability
backfill materials. Backfill materials displace the
bentonite slurry during the trench backfilling. The backfill
materials are specially selected or manufactured to create a
low permeability barrier. Various backfill materials used
and their characteristics are described in Sub-Sections
2.4.3.1.1 through 2.4.3.1.3.
2.4.3.1.1 Soil-bentonite mixtures
IBentonite would be added to the excavated
I _^ native soil usually in slurry form, although dry bentonite
/ may be added where larger volumes of bentonite are called for
in the design. The bentonite and soil are mixed by
t windrowing, dozing or blading. The bentonite serves to
increase the fraction of fines in the native material,
\ thereby reducing the permeability. It also serves to provide
. a mix which is viscous so that the soil-bentonite mixture
* will slide slowly into the trench excavation, without
| entrapping pockets of slurry.
ii
Medium to coarse grained soils are not
suitable for soil-bentonite mixtures since low permeabilities
cannot be achieved consistently without massive additions of
bentonite.
The construction procedure requires
significant land area since a bentonite slurry mixing area
and a soil-bentonite mixing area are required. The completed
soil-bentonite barrier is durable and resistant to minor
deformations. The soil-bentonite barrier must retain its
moisture to remain effective since loss of moisture will
cause the bentonite to shrink and crack. The soil-bentonite
backfill material is relatively economical since it utilizes
native material.
2.4.3.1.2 Cement-bentonite mixtures
I „ ——————————. Bentonite is added in small amounts to
water-cement suspensions to extend the range over which the
| system is free from segregation by settlement. This mixture
generally is used in open granular soils and rock fissures,
1 or where some structural stability is required over and above
I that provided by a soil-bentonite wall barrier.
I The construction procedure requires less land
use area than for the soil-bentonite mixture since only
It 29
j imported materials are used for the backfill material. The
completed cement-bentonite barrier is durable but also
j susceptable to cracking due to minor deformations. This
i- cracking would cause the barrier wall to be more permeable
than the soil-bentonite backfill mixture.
rThe cement-bentonite mixture is less
1 economical than the soil-bentonite mixture since imported
/ materials are required and the native materials that are
•— excavated must be disposed.
2.4.3.1.3 Synthetic membrane installation
A synthetic membrane is placed over the
trench and caused to settle into the trench in a U
configuration by filling it with a highly permeable sand
material. Observation wells are then placed within the
permeable sand material to detect infiltration and ensure the
integrity of the synthetic membrane.
This method is still in the experimental
1 stages. Available information indicates that extreme
. difficulty has been experienced to date during construction
and installation of synthetic membranes in the field.
I1I
The use of imported materials as well as the
difficulty in construction lead to a high capital cost for
this form of containment wall.
2.4.3.2 Sheet Piles
1 This technology involves driving H piles,
i with the flanges back to back, around the perimeter of the
^ area to be contained. The piles are driven until the tips
f reach and penetrate an underlying low-permeability layer.
1 Since specifications generally call for a
. vertical variation of one percent or less, the maximum depth
' of installation is restricted to approximately 35 feet. For
I depths greater than 35 feet, deflection can create
unacceptable openings between adjacent piles.
I _, The installation of sheet piles results in
minimal disturbance to the existing site. However, a
I continuous barrier is not created due to the segmental nature
of the construction using H piles. The actual decrease in
I permeability obtained across a sheet pile is generally not
very large. The permeability has actually been found to
* decrease with time due to rusting and possible movement of
I fines. Long-term reliability would be suspect due to
deterioration by corrosion.
1I
Sheet piling is not feasible when the site
soils contain cobbles or larger fragments because of the
potential pile deflections that result during installation.
Sheet piling has a high installed construction capital cost,
and potentially has high maintenance costs.
2.4.3.3 Injected Screens
This technology requires similar construction
procedures as the sheet pile technology except that the piles
are subsequently extracted one at a time and the resultant
void filled with a clay-cement grout injected under pressure.
The extracted piles are redriven in the direction of travel
approximately ten feet from the point of extraction, thereby
minimizing the equipment and material required.
The injected grout produces a low
permeability barrier consisting of a "continuous" core of
relatively impermeable material which occupies the space left
by the extracted piles and is overlapped by a cemented zone
of soil penetrated by the injected grout. The thin fillet of
earth usually trapped between the flanges of adjacent piles
as they are driven, is removed by the pressure of the
injected grout during pile extraction.
This technology is limited to a maximum depth
of approximately 35 feet for reasons similar to the sheet
32
I pile technology. Windowing may cause unanticipated high
permeabilities across the barrier and thus defeat the purpose
J of this technology. As with sheet piles, this method is not
appropriate for use in soils containing cobbles or larger
rock fragments.
rCapital costs are moderate to high for the
| injected screen technology.
I 2.4.3.4 Grout Curtain
} This technology involves drilling holes along
, the perimeter of the area to be contained until an
' underlying low-permeability layer is reached. The drill is
I then extracted and a cement-bentonite grout is injected under
pressure through the drill holes. The grout creates a
/ ^_ cemented zone of soil around each drill hole, the diameter of
which depends on the penetrability of the grout into the
soils. The drill holes are spaced along a line at distances
f such that the cemented zone of each grout hole overlaps the
proceeding zone. Two or three staggered drill lines may be
| constructed such that the zone of each line overlaps the
previous line. This serves to increase the width of the
I grout curtain and effectively lowers its permeability.
J However, the injected grout will tend to flow in the
direction of least resistance and may not form a continuous
{ barrier.
I 33
This technology provides minimal disturbance
to the site during construction and requires disposal of the
drilling spoils only. Although some deflection of the grout
holes will be experienced, the horizontal spacing may be
adjusted to minimize the consequences of this deflection.
The permeability of the existing site soils
and the penetrating characteristics of the grout will
determine the required sequencing and spacing of grout holes,
and thereby significantly affect the initial capital cost
proportionally. Because of variability in soils on-site,
penetration of grout may not be completed in all areas, and
"windows" may exist after installation.
2.4.4 Hydraulic Containment
' v_- The hydraulic containment technology involves
I the use of extraction wells to manipulate the flow pattern of
groundwater. The extraction well system controls the flow
I pattern of groundwater by inducing a flow towards the
installed extraction wells. During the period of operation,
• the system captures contaminated groundwater and the
| contaminants released from both the saturated and unsaturated
soils. The hydraulic containment technology also removes the
source of contaminants in the groundwater and thereby reduces
the long-term impact of the site contamination to the
groundwater.
34
The extracted contaminated groundwater is
replaced at an accelerated rate by water from the surrounding
areas. The flushing of contaminants adsorbed in the aquifer
materials is also accelerated. The extracted contaminated
groundwater will require some form of treatment and disposal.
These are discussed in Section 2.4.6 of this report. Since
groundwater is being extracted and disposed, the technology
does deplete the groundwater resource.
The hydraulic containment technology offers
the flexibility of adjusting extraction rates to compensate
for heterogeneous geologic conditions or changes in
groundwater quality or quantity. The technology also offers
the ability of expansion to address potential problems that
may be identified after the system has been installed.
The extraction well system controls the
contaminant plume and, therefore, allows the continued use of
the aquifer by other users immediately outside of the zone of
contamination. These users may, however, incur some
additional pumping costs, depending on the area of drawdown
created by the remedial extraction wells.
Short-term site usage will be restricted
because of site utilities that will be required to transport
the extracted groundwater from the extraction wells to the
treatment system and subsequently to an approved discharge
outlet. However, long-term site usage will return to normal
35
I after the contaminants have been removed to an acceptable
level from the contaminated area.
f.- Off-site easements may be required during the
' period of operation of the extraction well system. Easements
may be necessary if it is deemed that off-site wells are
required to control the groundwater fl<effluent discharge outlet is off site.
r
required to control the groundwater flow pattern, or if the
j When properly designed, constructed and
maintained, the hydraulic containment technology is extremely
1 reliable, effective and durable as compared to the other
i technologies discussed herein. It is likewise relatively
easy to install and applicable to removal of dissolved
I contaminants especially where contaminants are identified at
a significant depth below the surface.
ICapital costs for this technology are
I ^ comparatively low. The majority of the cost is associated
. with operation and maintenance of the system. The treatment
cost of the extracted groundwater comprises a large| percentage of the operation and maintenance cost.
J The extraction well system discussed above
may be supplemented with an injection well system.
| Simultaneous injection of cleaner water during the extraction
process would further increase the rate of flow through the
I contaminated zone between the injection and extraction wells,
i thereby further accelerating the flushing of contaminants
( 36
adsorbed onto the alluvial materials. The injection wells
would be located such that the entire system creates a
controllable, stable flow pattern between the injection and
extraction wells.
The effect of the injection well system would
be to reduce the total pumping time required to remove the
contaminant source to a stipulated level. If permitted,
reinjection of the treated extracted groundwater could
provide a source of injection water.
The additional capital cost of the injection
well system and associated piping must be compared to present
worth costs of pumping and treating a smaller amount of
groundwater for a longer period of time relative to pumping
and treating larger amounts of water for a shorter period of
time. The reduction in pumping time achieved as a result of
installing an injection well system depends on the in-situ
soil permeability and specific contaminant characteristics
such as water solubility and coefficient of retardation.
12.4.5 Groundwater Treatment
I1
All potential remedial technologies discussed
in the previous sections, with the exception of capping,
. require extraction of groundwater to be effective. This
*" extracted groundwater would be contaminated and would require
I some form of treatment. This section discusses potential
I 37
I remedial technologies for the treatment of extracted
contaminated groundwater and is limited to treatment of
j groundwater contaminated by volatile organic compounds
(VOC's) only.1J Depending on the volume and quality of water
extracted, it may be feasible to dispose of the untreated
j groundwater by one of the technologies discussed in Section
2.4.6. If disposal costs for untreated effluent become
^. unacceptably high, or institutional restrictions are imposed,
j then some form of on-site treatment may be required.
( Treatment processes available for treatment
i of specific hazardous waste contaminant compounds, as listed
' by Shuckrow et al, ("Hazardous Waste Leachate Management
I Manual", Shuckrow; Pajak; and Touhill, 1982) include:
] ^ Biological Treatment Evaporation
( Carbon Adsorption Filtration
Catalysis Flocculation
J Chemical Oxidation Ion Exchange
Chemical Reduction Resin Adsorption
[ Chemical Precipitation Reverse Osmosis
Crystallization Solvent Extraction
' Density Separation Stripping
[ Dialysis/Electrodialysis Ultrafiltration
Distillation Wet Oxidation
138
1
I Of the above unit treatment processes, only
five would potentially have the capability of removing
I and/or degrading the majority of VOC contaminants in
i extracted groundwater. These five are:
( Biological Treatment
Carbon Adsorption
| Resin Adsorption
/ Stripping
— Wet Oxidation
I -Resin adsorption is somewhat similar to
( carbon adsorption. However, it is generally not as effective
, as carbon for treatment of waters which contain VOC
contaminants. For this reason, it appears that resin
J adsorption is probably not a suitable alternative for the
treatment of the groundwaters in question, although should
/ ^_. the need arise, actual testing may be required to confirm
• such a conclusion.
J The wet oxidation process is most applicable
for contaminants which are too refractory for chemical or
[ biological oxidation. Moreover, it is a technology which
i requires close operational control and is much more
' applicable for treating concentrated waste streams rather
[ than dilute concentrations such as those found in
groundwater. Furthermore, there is little to no evidence of
{ experience in the use of wet oxidation for treatment of
39I
groundwater. Therefore, wet oxidation will not be considered
further at this time. The list of treatment alternatives to
be further evaluated will therefore be limited to biological
treatment, carbon adsorption, and stripping.
2.4.5.1 Biological Treatment
j This technology has been applied in numerous
^ processes, including activated sludge, trickling filters,
I . rotating biological contactors and anaerobic treatment, and
has proven to be effective for a wide variety of organic
I compounds. However, this technology also has a number of
f limitations, of which the most significant is that sufficient
organic matter must be present to sustain biological
I activity. Most groundwater has a small amount of organic
material naturally present. Although microorganisms will be
i ^- found in the groundwater they will be insufficient in-situ to
j provide timely degradation of the organic materials.
Classic biological treatment systems require
a substantial organic load, measured in the 100 ppm or
*• greater range for BOD or TOG. Systems usually are designed
j to reduce this organic load to a range of 10 to 30 mg/L.
These systems require supplemental nutrients, oxygen, and pH
J control to sustain the biological activity.
II 40
j A side benefit from biological treatment is
the reduction in specific VOC's. However, to date biological
systems have not been designed to reduce only the
concentration of one or more specific VOC's.I
Some preliminary tests by USEPA have
indicated that reduction of VOC's in a biological system may
be totally or at least partially a result of volatilization
and not biological reduction. This would indicate that a
biological treatment system that was open to the atmosphere
would promote VOC volatilization to the air around it.
Application of this technology would have to
be site specific. Bench- or pilot-scale studies would be
required to demonstrate its applicability and to develop
design factors.
. 2.4.5.2 Carbon Adsorption
j This technology involves pumping extracted
groundwater through an activated carbon bed in which close
[ contact with the surface of the carbon grains promotes the
. adsorption of contaminants. This technology has been
*• extensively developed and proven suitable for the removal of
j a wide range of contaminants from both air and water phases.
Carbon adsorption achieves a high level of contaminant
II
removal and is capable of producing water that is of drinking
water quality.
Carbon adsorption systems are closed systems
and, therefore, unlike biological treatment systems, have a
low potential for emission of VOC's to the atmosphere.
Carbon adsorption systems have moderately low
capital costs and are commercially available. However,
operation costs vary significantly, being dependant upon the
total mass of contaminants and the adsorption characteristics
of the contaminants to be removed. If one contaminant has a
poor adsorption characteristic, breakthrough of this
contaminant would occur through the carbon system long before
the carbon has reached saturation for the other contaminants.
The carbon would, therefore, require replacement or
regeneration based on this one indicator compound. A common
method for improving the effectiveness of carbon adsorption
and lowering the cost for this process is to remove some of
the less easily removed compounds (ie. contaminants with poor
adsorption characteristics) prior to the carbon adsorption
system. This is accomplished by applying a process such as
stripping.
42
2.4.5.3 Stripping
This technology uses a system to mix large
volumes of air and/or steam with the contaminated water
to promote the transfer of VOC's into the air and/or steam.
The system may consist of a packed column, in which water is
pumped into the top of the column and cascades down over the
loosely packed media while air and/or steam is pumped upward
through the column. The steam generally is required only for
the removal of less volatile compounds and requires a
significant amount of energy input to maintain.
The efficiency of the air stripping process
is mainly dependant on the air/steam to water ratio and the
contact time in the tower. Both the ratio and tower length
can be adjusted to optimize the groundwater treatment with
minimal differences in overall capital cost.
If air stripping does not fully satisfy the
treatment objectives, a carbon adsorption system may be used
to further reduce the contaminant levels in the groundwater.
However, the air stripping process will significantly reduce
the carbon required in the carbon adsorption polishing
system.
A major concern of the stripping process is
the potential release of unacceptable concentrations of VOC's
43
to the atmosphere. If discharge from an air stripping tower
exceeds the allowable mass discharge, a vapor-phase carbon
adsorption system may have to be added to the tower
discharge.
2.4.6 Groundwater Disposal
IAlternative methods considered for the
•~— disposal of extracted groundwater include:
\1. discharge to a surface fresh water body,
[ 2. discharge to a Publicly Owned Treatment Works (POTW),
. 3. disposal at an RCRA permitted disposal facility,
' 4. reinjection, and
I 5. deep well injection.
I _ The appropriateness of the listed methods of
. disposal are dependent on whether or not the groundwater to
be disposed of has been treated, and if it has been treated,
I the degree of treatment received.
I A brief discussion of the alternative
• groundwater disposal methods for both treated and untreated
' groundwater and their applicability are as follows:
44
2.4.6.1 Discharge to a Surface Fresh Water Body
This alternative is applicable to both
treated and untreated groundwater provided that both the
quality and quantity of the groundwater being directly
discharged to the surface fresh water body meets the
allowable discharge requirements for fresh water as regulated
under Federal or State standards. The quantity of
groundwater that would be allowed to be discharged would
depend on the capacity of the discharge system and the
receiving water bodies. Groundwater quality sampling of the
waste groundwater to be discharged would be required to
identify its quality and to ensure that it meets the
allowable discharge requirements for fresh water.
The capital cost would depend on the
proximity of the nearest receiving fresh water body and the
available alternatives of conveying the waste groundwater to
this water body. Operation and maintenance costs would be
low, requiring only sampling and maintenance of the discharge
system.
2.4.6.2 Discharge to a Publicly Owned Treatment Works
This alternative is applicable to both
treated and untreated water provided that the quality and
45
quantity of the groundwater being discharged to the
publically owned treatment works (POTW) meets the allowable
discharge requirements of the local regulatory agency. The
quantity of groundwater that would be allowed to be
discharged would depend on the capacity of the discharge
system and the POTW. Sampling and analysis of the waste
groundwater to be discharged would be required to identify
its quality and to ensure that it meets the allowable
discharge requirements of the local POTW.
The capital cost would depend on the
proximity of the nearest conveyance system capable of
receiving the anticipated and allowable quantity of
groundwater to be discharged. A flow measuring device would
be required by the POTW at the point of discharge of waste
groundwater from the site. Operation and maintenance costs
for sampling and maintenance of the discharge system would be
similar to the discharge to a surface fresh water body
alternative. In addition, treatment costs would be charged
by the POTW based on the volume and/or quality of the waste
groundwater being discharged. These treatment charges could
potentially be quite significant and must be compared to the
cost of treatment by one of the technologies discussed in
Section 2.4.5, prior to ultimate disposal.
46
I 2.4.6.3 Disposal at a RCRA Permitted Facility
j This alternative is applicable to both
. treated and untreated groundwater and is limited only by
' cost. Waste groundwater would be transported to a RCRA
j permitted disposal facility that is approved to accept the
quality and quantity of the waste groundwater to be disposed
( of.
' -— Generally, transport costs and gate fees at a
| RCRA permitted disposal facility would limit the economic
feasibility of this alternative to relatively small
[ quantities of waste groundwater. This alternative would,
. therefore, only be considered when the requirements for
' discharge to a surface fresh water body or discharge to a
I POTW cannot be achieved, or when the quantity of waste
groundwater to be discharged is so minimal that on-site
J _. temporary storage and ultimate disposal to a RCRA permitted
I disposal facility would be more economical than an
alternative form of disposal (and treatment).
ICapital costs may be low depending on the
I size of temporary storage required on site. Operation and
• maintenance associated with the storage and transport filling
system would be minimal. The majority of costs would be
J associated with the actual transportation costs and receiving
facility gate fees.
II 47
2.4.6.4 Reinjaction
This alternative is only applicable to treated groundwater as
reinjection of untreated groundwater would not be a means of
disposal but rather a recirculation system. This alternative
would also only be applicable if a variance of the State of
Minnesota regulations could be obtained for subsurface
disposal of the waste groundwater. Reinjection of treated
groundwater would only be considered if all of the above
three alternatives prove not to be feasible.
Capital, operation and maintenance costs
would depend on the volume of waste groundwater to be
disposed of by injection.
2.4.6.5 Deep Well Injection
This alternative may be applicable to both
treated and untreated groundwater, but would require
a permit for subsurface disposal. This technology would
involve the construction of a well into an isolated,
nonpotable deep aquifer, thereby protecting potential
receptors using other aquifers. Future exposure could be
possible however, if the deep aquifer were used.
48
Capital costs for this alternative could be
low to moderately high, depending on the extent of
investigation required to identify an acceptable deep aquifer
disposal unit. Operation and maintenance costs are
relatively low.
2.4.7 Alternate Water Source Supply
The alternate water source supply technology
addresses the provision of alternate water sources to
potential receptors of contaminated groundwater. This
technology does not address containment or removal of
contaminated groundwater and, therefore, has no effect on the
future migration of groundwater contaminants. However, this
technology does satisfy the primary objective which is to
minimize the potential risk to off-site receptors from the
effects of contaminated groundwater.
In order to implement this alternative, all
present and potential future receptors must be identified and
quantified as to water consumption rates/water quality
requirements. Potential future receptors would include all
consumers of the groundwater within an area that may
eventually be impacted by the migration of contaminants from
the present zone of contamination.
49
Alternative methods of providing an alternate
water source supply include the following:
i) providing a well outside of the contaminated plume,
ii) providing a portable water delivery service, and
iiijproviding a water service from a municipal supply.
A brief discussion on each of these technologies follows:
2.4.7.1 Providing a Well Outside of theContaminated Plume
This technology would require the
installation and operation of a well outside of the present
and potential future contaminant plume, with provision and
operation of a distribution piping system from this well to
identified users.
Costs for this technology depend on both the
quality and quantity of water required for the identified
users. Land aquistion costs may also be substantial for the
distribution system, depending on the zone of contamination
which determines the location of the water supply well.
50
2.4.7.2 Providing a Potable Water Delivery Service
This technology would require provision of
all potential future receptors with water storage facilities
and potable water delivery on a regular basis. Water would
be obtained from either a municipal source or a well located
outside of the contaminated groundwater plume.
This technology would only be acceptable to
minor water consumers. Large water consumers could not
depend on a potable water delivery service.
Costs for this technology would depend on
both the quality and quantity of water required for the
potential receptors. Capital costs would be less than the
previous technology since no water distribution system is
required. However, operation costs for transportation would
be greater than operation costs for pumping.
2.4.7.3 Providing a Water Service from a Municipal Source
This technology would require provision of a
water distribution system from an existing municipal system
to potential future receptors. All potential future
receptors and required water consumptions would have to be
identified in order to size the water distribution system.
51
I!
This technology would then provide a reliable source of water
at a reliable quality.
Initial capital costs depend on the proximity
of a municipal source the size of the water distribution
system required and the aquistion of land easements for the
water distribution system. Some compensation may also be
required to the receptors to offset the difference in costs
of pumping water from a private well compared to purchasing
water from a municipal system. Once the water distribution
system is installed, the municipality may assume maintenance
and operation of the system.
2.5 SELECTED REMEDIAL TECHNOLOGIES
Section 2.4 presented potential remedial
alternative technologies in various categories applicable to
reducing the impacts to groundwater users by migrating
groundwater contaminants. Based on the technical,
environmental, public health, institutional and cost issues
presented in Section 2.4 and summarized in Table 1, the most
applicable remedial technology was identified for each
category in specific response to the Site.
52
L
The most applicable remedial technology in
each category may not be the same for the FMC lands as for
the BNR lands, since the vertical and areal distribution of
contamination is different in each of the two areas.
Therefore, the selected remedial technologies identified in
the following sections are based on data collected during the
remedial investigation and outlined in the Feasibility Study.
These concluded that contamination within the lower alluvium
has been identified beneath the FMC lands, and that
contamination within the upper alluvium has been identified
beneath the BNR lands.
2.5.1 Excavation and Disposal
Two technologies were discussed under the
excavation and disposal category, namely disposal in an
off-site hazardous waste landfill approved by USEPA, and
disposal in a newly constructed containment facility located
either on site or off site.
Both technologies become cost prohibitive for
the FMC lands due to the volume of overburden above the
contaminated lower alluvium (approximately 300,000 cubic
yards). No further consideration is therefore given to this
category for the FMC lands.
II 53
Disposal at a hazardous waste landfill
approved by USEPA is very costly (two orders of magnitude
greater) compared to disposal in an on-site CF for the BNR
lands and offers few benefits not shared by the CF option.
The CF option has, therefore, been selected as the excavation
and disposal option for the BNR lands.
2.5.2 Capping
Seven alternative technologies were discussed
under the capping category, namely normal portland
concrete pavement, asphaltic concrete pavement, in-situ soil
admixtures, sprayed on covers, low permeability soil cover,
synthetic membranes, and composite construction.
As previously stated, contamination has been
identified in the lower aquifer beneath the FMC lands. This
aquifer is isolated from the upper alluvium by a clay stratum
approximately 20 feet in depth which provides a natural low
permeability cap over the lower contaminated aquifer.
Providing an additional surface cap over the FMC lands would
therefore provide no benefit in terms of mitigation of
off-site contaminant migration. This category, therefore,
requires no further consideration for the FMC lands.
54
Furthermore, it was concluded in the
Feasibility Study, that no significant contaminant loading
from the unsaturated overburden soil to the saturated
alluvium occurs at the Site. On this basis, placement of a
low-permeability cap over the Site would only be appropriate
in the context of reducing the volume of groundwater required
to be pumped for the physical containment or hydraulic
containment alternatives. This reduction of pumping rates
would therefore affect the evaluation of treatment
alternatives discussed in Section 3.4.2.
2.5.3 Physical Containment
Four technologies were discussed under the
physical containment category, namely slurry walls, sheet
piles, injected screens, and grout curtains. The slurry wall
technology was further divided into three alternatives,
namely soil-bentonite mixtures, cement-bentonite mixtures,
and synthetic membrane installation.
Technical issues such as the depth to the
underlying low-permeability strata preclude the use of the
sheet pile and injected screen technologies for providing
physical containment of the lower aquifer in the FMC lands.
Based on environmental, public health, and cost issues, the
grout curtain is the selected technology for the FMC lands.
55
Based on environmental, public health, and cost issues, the
grout curtain is the selected technology for the FMC lands.
Technically, the slurry wall may be argued to provide a more
consistent continuous barrier than the grout curtain;
however, the grout curtain can easily be expanded to seal off
identified areas of leakage. Areas of leakage would be
identified by a long-term monitoring program which is common
to all forms of physical containment. The savings in capital
costs for the grout curtain as compared to the slurry wall
would allow significant additional expansion of the grout
curtain if it were deemed necessary by monitoring. For these
reasons, the grout curtain is the selected technology in the
physical containment category for providing a barrier to
contaminant migration from the lower aquifer of the FMC
lands.
Based on technical, institutional and cost
considerations, the slurry wall is the most applicable
technology to physically contain the upper aquifer of the
BNR Lands. Public health and environmental disadvantages of
this technology during construction may be alleviated through
the implementation of a safety and health program during
construction and proper post-construction site restoration.
Evaluations indicate the soil-bentonite wall to be the
applicable technology for containment barriers. Therefore,
the soil-bentonite containment wall is identified as the
selected technology in the physical containment category for
56
LI
provision of a barrier to contaminant migration from the
upper aquifer of the BNR lands.
2.5.4 Hydraulic Containment
Hydraulic containment through the use of a
series of groundwater extraction wells provides an
appropriate form of containment based on all issues addressed
for both the FMC lands and the BNR lands. Supplementing the
extraction well system with an injection well system
primarily affects only the cost issue of this technology,
since it provides a partial means of disposal of the
extracted groundwater/ and reduces the overall pumping time
required.
The extraction well system is identified as
the selected technology for the hydraulic containment
category for both the FMC lands and the BNR lands, with
additional consideration to be given to the
extraction/injection well system on a cost effectiveness
basis only.
57
Ifr
2.5.5 Groundwater Treatment
Three primary technologies were discussed
under the groundwater treatment category, namely biological
treatment, carbon adsorption, and air stripping.
Technical factors identified to date cannot
conclude that biological treatment is an effective and
reliable technology for treating VOC contaminated groundwater
and this technology, therefore, warrants no further
consideration. Cost issues identify air stripping as the
selected technology for groundwater treatment, with further
consideration required on carbon adsorption as a polishing
stage for both the treated groundwater effluent and air
emissions for environmental, public health and institutional
issues.
• 2.5.6 Groundwater Disposal
j Five technologies were discussed under the1
groundwater disposal category, namely discharge to a surface
I fresh water body, discharge to a POTW, disposal at a RCRA
j permitted disposal facility, reinjection, and deep well
injection.
L1t 58
1 Institutional issues in the State of
Minnesota preclude groundwater disposal by deep well
j injection. This technology, therefore, warrants no further
I consideration. Disposal at a RCRA permitted disposal
' facility becomes cost prohibitive for any significant volume
j of water requiring disposal. Therefore, this technology
warrants no further consideration unless the volume of water
I to be disposed of is minimal. Reinjection warrants further
, consideration based on cost issues and for treated water
^-- only, as a supplemental technology to hydraulic containment
I which is discussed in Section 2.5.3.
J On-site storm sewers and sanitary sewers
• are cost effective for disposal to a fresh water body and a
POTW, respectively. Proper assessment of these two disposal
i technologies cannot be performed until the quality and
quantity of groundwater requiring disposal is identified,
j x_ Therefore, further consideration of the discharge to a fresh
j water body and the discharge to a POTW technologies is
required under the groundwater disposal category. This will
J be performed in conjunction with the analysis of the
alternatives generated in Section 3.
Ii
59
2.5.7 Alternate Water Source Supply
Three alternative technologies were discussed
under the alternative water source supply category, namely
providing a well outside of the contaminated plume,
providing a potable water delivery service, and providing a
water service from a municipal system.
Environmental, public health and
institutional issues preclude the implementation of this
category in general as a sole means of remedial action.
Further consideration is therefore only warranted as an
interim measure, should it be identified that there is an
immediate risk to a potential receptor.
2.6 IN-SITU BIOLOGICAL TREATMENT
I In-situ biological treatment has been found
effective in some instances involving the remediation of
I hydrocarbon groundwater contamination (for example, oil or
gasoline spills). Evidence also exists which suggests that
I degradation of chlorinated organics by native soil microbes
j occurs naturally, albeit at very slow rates. Theoretical
considerations suggest that the rate of degradation of
I chlorinated organics in groundwater may be enhanced by
providing naturally occuring microbes with both nutrients and
I 60
oxygen (both normally rate limiting). Because apropriate
data were not readily available/ the technology of in-situ
biological treatment could not be evaluated in the context of
the Site.
61
3.0 PRELIMINARY ASSESSMENT OF POTENTIAL REMEDIAL ALTERNATIVES
3.1 GENERAL
This section assembles and combines into
potential remedial alternatives, the selected technologies
identified in Section 2 under each remedial category which
remediate or mitigate the impacts of the off-site migration
of VOC contaminants in the groundwater. On the basis of the
assessment criteria discussed under Section 3.2, an
appropriate remedial alternative will be identified which
will be utilized in evaluating each compliance location at
the 10"̂ an<3 10~6 excess cancer risk criteria.
This final evaluation step is presented in Section 4.
3.2 ASSESSMENT CRITERIA
j1
The initial primary assessment criterion
« which all potential remedial alternatives will address is the
j reduction of trichloroethylene (TCE) contamination in the
groundwater at the Site boundary to concentrations less than
j the 10~6 excess cancer risk criterion (2.8 ppb). The
generation of potential remedial alternatives will therefore
'. be limited to only those alternatives which provide a
J complete remedial action plan to achieve an average
groundwater concentration of TCE less than 2.8 part per
I billion (ppb).
62
I Remedial alternatives satisfying the above
primary criterion are then further assessed and screened
{ using criteria identical to those presented in Section 2.2,
f namely; i) technical feasibility, ii) environmental, public
health and institutional impacts, and iii) cost. The
appropriate remedial alternative selected in this section for
the worst case assumption of the 10~6 excess cancer risk
1 criterion at the Site boundary will be evaluated at each
/ receptor location in Section 4.
3.3 ASSEMBLED POTENTIAL REMEDIAL ALTERNATIVES
i The selected remedial technology for each
remedial category as summarized in Table 2 is identified
I separately for both the BNR lands and the FMC lands. This is
necessary since groundwater contamination in each of these
I ^ two areas has been identified to be in separate alluviums.
| Contamination beneath the BNR lands was identified in the
upper alluvium, which is isolated from the lower alluvium by
| a clay aquitard. Contamination beneath the FMC lands was
identified primarily in the deep alluvium below the clay
L aquitard.
IOn the basis of the assessment of the
I selected remedial technologies and the characteristics of the
actual contaminant source, potential remedial alternatives
I 63
TABLE 2
SUMMARY OF SELECTED REMEDIAL TECHNOLOGIES
FMC CORPORATIONMINNEAPOLIS, MINNESOTA
R E M E D I A L C A T E G O R Y
Area
BNR Lands
Excavationand Disposal
on- sitecontainmentfacility
PhysicalCapping Containment
low soil-bentonitepermeability containmentsoil cover wall
HydraulicContainment
extraction wellsystem withconsideration ofreinjection oncost effective-ness basis only
GroundwaterTreatment
air strippingwith additionaltreatment bycarbonadsorption ifrequired
GroundwaterDisposal
surface freshwater body orpublicly ownedtreatment works.reinjection oncost effective-ness basis only
Alternate WaterSource Supply
interim response onlywhen required forimmediate concernfor a receptor
FMC Lands notapplicable
notapplicable
grout curtaincontainmentwall
same as above same as above same as above same as above
will be assembled separately for the BNR lands and the FMC
lands. The selected remedial alternative for each area may
then be combined to provide an overall selected remedial
alternative for the entire Site.
Using the selected remedial technologies from
the categories summarized in Table 2, the following potential
remedial alternatives are assembled and assessed in respect
to the performance criterion (TCE concentration less than 2.8
— PPt>) at the Site boundary:
Assembled Alternatives - BNR Lands
IBNR-1 excavation of contaminated soils from the saturated
' zone with disposal in a newly constructed on-site
f containment facility,
BNR-2a physical containment utilizing a soil-bentonite
J _, containment wall,
BNR-2b physical containment utilizing a soil-bentonite
' containment wall with a low-permeability soil cap,
j BNR-3a hydraulic containment utilizing extraction wells,
and
| BNR-3b hydraulic containment utilizing extraction wells,
with a low-permeability soil cap.I
64
Assembled Alternatives - FMC Lands
FMC-1 physical containment utilizing a grout curtain wall,
and
FMC-2 hydraulic containment utilizing extraction wells.
The hydraulic containment alternatives will
be further evaluated in combination with reinjection in
Section 3.4.
3.4 PRELIMINARY ASSESSMENT OF POTENTIAL REMEDIALALTERNATIVES
j The potential remedial alternatives assembled
in the proceeding section can be classified into three
I general categories, namely,
( „ i) excavation of soils with disposal in a containment
I facility,
ii) physical containment, and
I iii) hydraulic containment.
IOn the basis of technical feasibility, the
I first category is applicable only to the BNR lands, whereas
the latter two categories are applicable to both the BNR
1-7- and the FMC lands. All three categories may in general be
assessed with respect to technical feasibility, and
65
I environmental, public health and institutional impact
criteria identified in Section 3.2. Only the cost criterion
( is site specific and cost therefore will be assessed
individually for each potential remedial alternative.f
3.4.1 Preliminary Assessment of General Categories
All assembled potential remedial alternatives
satisfy the primary criterion of reducing the concentration
of TCE in the groundwater to less than 2.8 ppb. at the Site
boundary. Therefore, the following discussions are limited
to major differences among the general categories.
3.4.1.1 Excavation of Contaminated Soils andDisposal in a Containment Facility
This alternative involves the dewatering and
I excavation of contaminated materials from a predefined area
of contamination ("hot spot"), with disposal of the excavated
• contaminated material in an on-site CF constructed to RCRA
| standards.
I This alternative does not remove the source
. of contaminants from the Site, but rather relocates the
L contaminated material into a secure facility which may be
I66
I
I monitored to ensure its effectiveness at containing the
contaminated materials. Therefore, the potential for future
groundwater impact is minimized.
' The excavated area would be backfilled with
[ uncontaminated material excavated and stockpiled during the
CF construction, and would be restored to normal site usage.
} The area occupied by the CF would restrict the future use of
that portion of the Site.
{ The large volumes and depth of excavation,
and the extensive dewatering required during the excavation
I would result in a significant time of implementation, during
which adjacent lands and facilities both underground and
' aboveground would be impacted. All water collected during
f dewatering operations potentially would be contaminated and
may require treatment prior to disposal. A stringent health
| and safety program would be instituted due to the potential
of worker exposure and contaminant migration from the Site
' during construction. Impacts to adjacent lands and
j facilities could not be significantly reduced during the
contaminated soil excavation process.
IPotential long-term environmental, public
* health and institutional impacts are mitigated through proper
f monitoring and operation of the CF.
I67
I
I 3.4.1.2 Physical Containment
I Physical containment of contaminated areas
involves securing in place "hot spots" by constructing a
« perimeter barrier wall having low permeability around the
f area of contamination. The barrier wall would be founded in
an underlying low permeability formation. This perimeter
| barrier wall would, therefore, restrict further migration of
contaminants off site.
j This alternative does not address the removal
of the source of contaminants but rather, effectively
1 contains the source of groundwater contamination within the
perimeter barrier wall, and thereby minimizes the potential
< for future migration of contaminated groundwater off site.
f The area within the perimeter barrier wall will be restricted
from future site usage. Monitoring of the barrier wall will
[ be required to ensure maintenance of its low permeability and
its effectiveness at containing the contaminated groundwater.
' Removal of contaminated contained groundwater to the degree
/ necessary to maintain an inward hydraulic gradient would be
accomplished by pumping. Collected waters may require
1 treatment prior to discharge.
* Potential risk of contaminant exposure to
f on-site workers, the general public and the environment would
not be as great as for the soil excavation alternative, sinceii
J the volume of soil excavated during the perimeter barrier
wall construction is substantially reduced. A less stringent
I health, safety and air monitoring program would be required
r in comparison to the excavation alternative.
f Long-term environmental, public health and
institutional impacts would be mitigated through proper
\ monitoring and maintenance of the perimeter barrier wall.
( ̂j 3.4.1.3 Hydraulic Containment
I Hydraulic containment involves the
• installation of a series of extraction wells to manipulate
the flow pattern of the groundwater regime. By extracting
I groundwater from the extraction wells, the groundwater flow
pattern is controlled, and the potential for migration of
1 contaminated groundwater beyond the extraction well system is
I minimized.
f The extracted contaminated groundwater is
replaced by better quality water from the surrounding
I aquifer, and over a period of time the contaminants adsorbed
j to the soils in the aquifer will be flushed out. This
alternative, therefore, physically removes the source of
j contaminants from all areas within the hydraulic influence of
the extraction wells and in turn provides a hydraulic control
1 to prevent off-site migration of contaminants.
69I
This alternative requires the shortest
construction period and results in the least amount of Site
disturbance, thereby mitigating the potential of contaminant
exposure to on-site workers/ the general public and the
environment.
The hydraulic containment alternative
requires implementation for a specific time period only,
after which the entire Site area will be returned to normal
use. Therefore, potential long-term environmental, public
health and institutional impacts are eliminated.
Combining a low-permeability soil cover with
hydraulic containment has the same effect as described for
physical containment in Section 3.4.1.2.
3.4.1.4 Groundwater Treatment and Groundwater Disposal
The following discussions on groundwater
treatment and groundwater disposal are combined since the
degree of treatment determines the alternate methods of
disposal. Considering the technical feasibility and the
environmental, public health and institutional impact
criteria, the potential alternatives for ultimate disposal of
extracted contaminated groundwater include the following:
70
I 1. no treatment with direct discharge to a surface water
body,
j 2. no treatment with direct discharge to a POTW,
. 3. treatment and subsequent discharge to a surface water
' body, and
| 4. treatment and subsequent discharge to a POTW.
1 It is understood that institutional
, guidelines will permit direct discharge to a surface water
^ body if the concentration of TCE in the discharge is less
1 than the 10~5 excess cancer risk criterion (28 ppb).
Therefore, this criterion has been used to determine the
j degree of treatment required prior to discharge to a surface
, water body. Implementation of this alternative would require
a National Pollutant Discharge Elimination System (NPDES)
( permit for the point of discharge of the treated effluent.
1 The Metropolitan Waste Control Commission
/ (MWCC) has permitted direct discharge of VOC contaminated
groundwater into the POTW system during the remedial work
( performed at the Site in 1983. Recent discussions with MWCC
staff indicate, within certain concentration (20 parts per
[ million) and volume limits, that this practice is currently
I acceptable. A formal proposal of the discharge program would
be required to be submitted to the MWCC for approval.
L71
Both discharge to a surface fresh water body
and to a POTW are technically feasible for the Site as both a
storm sewer system and a sanitary sewer system transverses
the Site. Provided the regulated concentration and volume
parameters established by the controlling authority are
adhered to, the environmental, public health and
institutional impacts will be minimal.
Air stripping can effectively reduce
concentrations of TCE contaminantion to less than 28 ppb,
and, therefore, treatment by air stripping alone can satisfy
the treatment and subsequent discharge requirements for a
fresh water body. Discussions with MPCA staff indicate that
the State of Minnesota may not require treatment of the air
emitted from the air stripping treatment system, provided
that the total VOC mass discharged into the atmosphere from
the stripping tower is below one ton per year. If this limit
is exceeded, treatment of the discharged gases by carbon
adsorption may be required. Section 4.4 discusses further
the permitting requirements for the treatment facility.
Treatment prior to direct discharge to a POTW
would be required if the contaminated groundwater exceeds the
direct discharge quality criteria of the POTW. This
condition is not anticipated for the extracted contaminated
groundwater from the Site.
72
3.4.1.5 Alternate Water Source Supply
This alternative is identified for
consideration only as an interim response action if there is
an immediate concern for a potential receptor. No immediate
receptor concern has been identified, and, therefore, this
alternative requires no further consideration at this time.
3.4.2 Preliminary Cost Assessment of PotentialRemedial Alternatives
I This section provides a relative cost
comparison of the assembled potential remedial alternatives.
j Elements common among all alternatives are not included in
this cost assessment. The costs presented in this section,
' therefore, are not intended to represent actual detailed
j construction cost estimates.
| Since all of the assembled potential remedial
alternatives extract contaminated groundwater to some degree,
<- a preliminary relative cost assessment of groundwater
j treatment and disposal alternatives is required to select a
treatment and disposal method which may be applied to each of
I the assembled potential remedial alternatives. Preliminary
relative groundwater treatment and disposal costs have been
*- determined for various flow rates and various time periods,
73
I and are presented in Figure 2. These costs are based on the
following assumptions:
I. i) on-site treatment is provided by air stripping designed
' to achieve an effluent TCE concentration of less than 28
Treated waters are discharged to the Mississippi
River via the existing storm sewer system. An initial
I capital cost has been assigned to the air stripping
treatment facility with subsequent treatment costs
' ^ assessed conservatively at $0.10/1,000 gallons,
Iii) direct discharge is permitted to the on-site sanitary
j sewer system with no pretreatment . Discharge costs are
assessed at $1.00/1,000 gallons as charged by the MWCC,
' and
Iiii) future costs are returned to a 1985 present worth costs
j using a six percent net discount factor.
' Table 3 summarizes the selected method of
j effluent discharge following treatment by air stripping based
on effluent flow rate. The cost assessments of the potential
] remedial alternatives as discussed in Sections 3.4.2.1 and
3.4.2.3 will apply the relative treatment and disposal
* alternatives selected on the basis of analysis of the
| information summarized in Table 3. A summary of all relative
costs estimated for the potential remedial alternatives
iI
PRESENT WORTH RELATIVE COSTS ($ X 10s) 6 % DISCOUNT FACTOR
Cl
o:oo zom
Im
1355Ilia>)I>02:g-\u>rr}§ m>z^ 3)r H
TABLE 3
SELECTED TREATMENT AND DISPOSAL METHOD_____FOR CONTAMINATED GROUNDWATER
FMC CORPORATIONMINNEAPOLIS, MINNESOTA
Pumping Rate BelowWhich Discharge to
POTW With NoTreatment is
Selected, and AboveInitial Design Total Pumping Which Treatment by
Flow Rate for Air Period Required Air Stripping andStripping Treatment for 20 Pore Discharge to Storm
Facility Volume Changes Sewer is Selected_______(GPM)_______ (YEARS) _______(GPM)________
30 2 50
30 4 24
30 11 12
30 20 9
100 2 68
100 4 37
100 11 17
100 20 13
LII
generated is presented in Table 4. Appendix A presents a
detailed cost summary for each of the alternatives summarized
in Table 4.
3.4.2.1 BNR Lands Assembled Potential RemedialAlternatives
i) Alternative BNR 1 - Excavation and Disposalin a Containment Facility_______________
This alternative involves constructing a
below grade, double lined, containment facility (CF) within
the FMC lands with a capacity for approximately 50,300 cubic
yards of contaminated soil; excavating and stockpiling
approximately 66,100 cubic yards of uncontaminated overburden
from the BNR lands; dewatering and excavating the
contaminated saturated soils from the BNR lands and placing
of these soils in the CF; backfilling the excavation in the
BNR lands with uncontaminated material from the BNR lands
overburden excavation and CF excavation stockpiles; obtaining
the balance of required backfill material from off-site
borrow pits; surface restoration of approximately ten acres;
and disposal by discharge to the POTW of approximately 3.1
million gallons of water generated by dewatering. Figure 3
illustrates the identified area of contamination to be
excavated and the proposed location of the CF.
75
TABLE 4
ESTIMATED COST SUMMARY OF REMEDIAL ACTION ALTERNATIVES
FMC CORPORATIONMINNEAPOLIS, MINNESOTA
Total CapitalRemedial Action Alternative Construction Cost
1. Excavation of contaminated soilsfrom BNR lands with disposal inconstructed CF on FMC lands $4,644,880
2. a) Hiyaleal containment of BNRlands with soil-bentonitecontainment wall and no cap 1,003,550
b) Ihysical containment of BNRlands with soil-bentonitecontainment wall and clay cap 1,125,645
3. Hydraulic containment of BNR lands 216,180
4. Ihysical containment of FMC landswith grout curtain wall 5,197,945
491,755
Operation, Maintenance and Monitoring Cost______Total Present
Worth CostCapital Cost
$15,000
18,000
18,000
18,000
48,000
48,000
Annual Cost
$71,840
54,340first 5 years
43,340remaining 15 years
57,818first 5 years
45,818remaining 15 years
72,900
62,144first 5 years
42,144remaining 15 years
77,500
$988,880 for30 yearperiod
536,185 for20 yearperiod
576,075 for20 yearperiod
133,625 for2 yearperiod
567,630 for20 yearperiod
5. Hydraulic containment of FMC lands
worth value for annual operation, maintenance and monitoring costs calculated at a six percent discount rate.
611,245 for11 yearperiod
Total RemedialAlternative Cost
$5,648,760
1,557,735
1,719,720
367,805
5,813,575
1,151,000
The relative capital cost of Alternative
BNR 1 is estimated to be $4,644,880. Table A.I presented in
Appendix A provides a summary of work required to implement
this alternative with associated relative costs.
Operation, maintenance and monitoring costs
of Alternative BNR 1 are estimated at $15,000 for initial
capital costs and $71,840 per year as shown in Table A.I.
These operation, maintenance and monitoring costs will be
incurred for an indefinite period of time. The present worth
value over a 30 year period at a six percent net discount
rate is $988,880, giving a total relative present worth cost
of $5,648,760 for Alternative BNR 1.
ii) Alternative BNR 2a - Physical Containment Utilizinga Soil-Bentonite Contained Wall
This alternative involves construction of a
soil-bentonite containment wall approximately 1,200 feet long
and 36 feet deep and installation of one extraction well to a
depth of 35 feet, as shown on Figure 4.
The estimated pumping rate for the extraction
well would be 0.57 GPM and the estimated concentration of
TCE in the extracted groundwater would be 13,500 ppb during
the first year of pumping. Based on this concentration and
flow rate, the selected treatment and disposal alternative
76
for the extracted groundwater is direct discharge to a POTW.
Since the pumping rates are relatively low, a holding tank
with a 14 day capacity and a connection to the existing
on-site sanitary sewer are provided in the relative cost
estimate.
The relative capital cost of Alternative BNR
2a is estimated at $1,003,550. Table A.2a, Appendix A
provides a summary of work required to implement this
alternative with respective costs.
Operation, maintenance and monitoring costs
of Alternative BNR 2a are estimated at $18,000 for initial
capital cost and $54,340 to $42,340 per year as shown in
Table A.2a. These costs provide for monitoring and
maintenance of the containment wall and extraction well, and
charges from the POTW for discharging contaminated
groundwater to the sanitary sewer system. These operation
and maintenance costs will be incurred for an indefinite
period of time. The present worth value over a 20 year
period at a six percent net discount rate is $536,185, giving
a total estimated relative present worth cost of $1,557,735
for Alternative BNR 2a. Table 4 summarizes the total*
remedial alternative cost.
77
iii) Alternative BNR 2b - Physical Containment Utilizinga Soil-Bentonite Containment Wall with a LowPermeability Soil Cap_________________________
This alternative involves construction of a
soil-bentonite containment wall and one extraction well
similar to that for Alternative BNR 2a with the addition of a
low-permeability soil cap covering the 59,000 square foot
affected area of the BNR lands. The low permeability soil
cap involves pregrading the affected area of the Site to a
minimum grade of three percent, placing a 2-foot thick layer
of clay, placing a 6-inch deep sand layer over the clay,
placing a 3-foot thick layer of common fill over the sand,
placing six inches of topsoil over the entire surface, and
revegetating the area.
Due to the low-permeability soil cover, the
estimated average pumping rate for the extraction well is
reduced from 0.57 GPM for Alternative BNR 2a to 0.01 GPM at
an average estimated concentration of 13,500 ppb TCE during
the first year. Based on this concentration and flow rate,
direct discharge to a POTW is the selected treatment and
disposal alternative for the extracted groundwater. Since
the pumping rates are extremely low, a holding tank with a
90-day capacity, and a connection to the existing on-site
sanitary sewer is provided in the relative cost estimate.
78
The relative capital cost of Alternative BNR
2b is estimated at $1,125,645. Table A.2b, Appendix A,
provides a summary of work required to implement this
alternative with respective costs.
Operation, maintenance and monitoring costs
of Alternative BNR 2b are estimated at $18,000 initial
capital cost and $57,818 to $45,818 per year as shown in
Table A.2b. These provide for maintenance of the low
permeability soil cover in addition to the operation and
maintenance items identified for Alternative BNR 2a. These
operation, maintenance and monitoring costs will be incurred
for an indefinite period of time. The present worth value
over a 20 year period at a six percent net discount rate is
$576,075, giving a total relative present worth cost of
$1,719,720 for Alternative BNR 2b. Table 4 summarizes the
total remedial alternative cost.
iv) Alternative BNR 3a - Hydraulic Containment UtilizingExtraction Wells
This alternatve consists of installing two
extraction wells to an average depth of 35 feet, and
installing 360 lineal feet of collection piping, as shown on
Figure 5.
79
The estimated combined pumping rate for the
two extraction wells is 30 GPM and the estimated average
concentration of TCE is 4,000 ppb during the first pore
volume extracted. The total time of pumping required to
achieve a 20 pore volume change over is estimated at two
years. Based on the pumping rate, TCE concentration and
pumping period, direct discharge to a POTW is the selected
treatment and disposal alternative for the extracted
groundwater. The relative cost estimate, therefore, provides
for direct discharge to the on-site sanitary sewer system.
The relative capital cost of Alternative BNR
3a) is estimated at $216,180. Table A.3, Appendix A,
provides a summary of work required to implement this
alternative with relative costs.
Operation, maintenance and monitoring costs
for Alternative BNR 3a) are estimated at $18,000 for initial
capital costs and $72,900 annual costs as shown in Table A.3.
These provide for monitoring and maintenance of the
extraction wells, and charges from the POTW for effluent
discharge to the sanitary sewer system. These operation,
maintenance and monitoring costs will be incurred for an
estimated two year period only, after which time the system
is no longer required. The present worth value over a two
year period at a six percent net discount rate is $133,625,
giving a total present worth cost of $367,805 for Alternative
80
BNR 3a). Table 4 summarizes the total remedial alternative
cost.
The potential alternative of combining
reinjection with the extraction well system for the BNR lands
is not economically justified since the installation costs
alone of the injection well system far exceed the total
present worth operation, maintenance and monitoring costs for
the extraction well system. Therefore, the reinjection
alternative does not require further consideration.
v) Alternative BNR 3b - Hydraulic Containment UtilizingExtraction Wells with a Low Permeability Soil Cap
The addition of a cap would effectively
reduce the pumping rate of the extraction well system by 0.46
GPM over the estimated two-year period of operation. The
present worth cost for disposal of the volume of water not
pumped due to the installation of a clay cap is less than
?1,000. Therefore, it is apparent that the low-permeability
soil cap would not be economically justifiable when combined
with a hydraulic containment system. This alternative,
therefore, warrants no further consideration.
81
3.4.2.3 FMC Lands Assembled Potential RemedialAlternatives
i) Alternative FMC 1 - Physical Containment UtilizingA Grout Curtain
This alternative involves construction of a
grout curtain wall approximately 3,000 feet in length and 135
feet in depth and installation of one extraction well to a
depth of approximately 135 feet, as shown on Figure 4.
The estimated pumping rate for the extraction
well would be 0.15 GPM with an estimated concentration of
TCE within the extracted groundwater of 95 ppb. The
selected treatment and disposal method for this volume and
concentration is direct discharge to the POTW. Since the
volume of water extracted is low, a 90-day capacity holding
tank and a discharge outlet to the on-site sanitary sewer
system is provided in the relative cost estimate.
The relative capital cost of Alternative FMC
1 is estimated at $5,197,945. Table A.4, Appendix A,
provides a summary of work required to implement this
alternative and relative costs.
Operation, maintenance and monitoring costs
of Alternative FMC 1 are estimated at $48,000 initial capital
82
costs and $62,144 to $42,144 per year as shown in Appendix A
on Table A.4. These annual costs provide for monitoring and
maintenance of the grout curtain wall and extraction well,
and charges from the POTW for effluent discharge to the
sanitary sewer system. These operation, maintenance and
monitoring costs will be incurred for an indefinite period of
time. The present worth value over a 20-year period at six
percent net discount rate is $567,630, giving a total
relative present worth cost of $5,813,575 for Alternative FMC
1.
ii) Alternative FMC 2 - Hydraulic Containment UtilizingExtraction Wells
This alternative consists of installing six
extraction wells to an average depth of 135 feet and
installing 950 lineal feet of collection piping, as shown on
Figure 6.
The estimated combined pumping rate for the
six extraction wells would be 95 GPM with an estimated
average concentration of TCE within the extracted groundwater
of 500 ppb during the first pore volume extracted. The total
time of pumping required to achieve a 20 pore volume
extraction is estimated at 11 years. Based on this pumping
rate, estimated TCE concentration and pumping period, the
appropriate treatment and disposal method is on-site
83
treatment by air stripping designed to a 95 percent VOC
removal efficiency, with subsequent disposal of treated
waters to the on-site storm sewer system. The relative cost
estimate, therefore, provides for an air stripping treatment
system with subsequent effluent discharge to the storm
sewer.
The relative capital cost of Alternative FMC
2 is estimated at §455,025. Table A.5, Apendix A, provides a
summary of work and associated costs required to implement
this alternative.
Operation, maintenance and monitoring costs
for Alternative FMC 2 are estimated at $48,000 for initial
capital costs and $77,500 per year as shown in Table A.5.
These provide for monitoring and maintenance of the
extraction wells, and operation and maintenance of the air
stripping treatment system. These operation and maintenance
costs will be incurred for an 11 year period only, after
which the system is no longer required. The present worth
value over an 11 year period at a six percent net discount
rate is $611,245, giving a total present worth of $1,151,000
for Alternative FMC 2. Table 4 summarizes the total remedial
alternative cost.
Combining reinjection with the extraction
well system can effectively reduce the required time of
84
pumping to produce a 20 pore volume extraction by
approximately 50 percent. This would realize a net present
worth savings in the operation, maintenance and monitoring
costs of the extraction well system of $94,460. This saving
is well below the estimated cost to install, operate and
maintain an injection well system. Therefore, the reinjection
alternative does not require further consideration with
respect to cost for the FMC lands.
3.5 SELECTED REMEDIAL ALTERNATIVES
Section 3.3 assembled potential remedial
alternatives based on achieving the primary criterion of
reducing the concentration of TCE in groundwater to less 2.8
ppb at the Site boundary. Potential remedial alternatives
were generated separately for the BNR lands and the FMC
lands.
On the basis of the discussion presented in
Section 3.4.1, technical feasibility, and environmental,
public health, institutional impacts criteria and cost, the
extraction well hydraulic containment alternative is the
appropriate remedial alternative applicable to both the BNR
and FMC lands. The extraction well hydraulic containment
alternative for the combined Site is primarily selected for
the following reasons:
85
1. minimal time and Site disturbance is required to
construct the extraction well system, thereby minimizing
short-term health and environmental impacts,
2. the source of contamination is removed from the
groundwater regime, thereby eliminating future potential
impacts on public health or environment,
3. contaminants are removed within the hydraulic influence
of the extraction wells, and
4. since contaminants are removed from the groundwater
regime, the system only requires implementation for a
specific period of time, after which the Site may be
fully restored and returned to normal unrestricted
usage.
On the basis of the discussion presented in
Section 3.4.2, the extraction well hydraulic containment
alternative would again be the selected remedial alternative
for both the BNR lands and the FMC lands. The selected
treatment and disposal alternative of contaminated
groundwater from the BNR lands was identified as direct
disposal to the on-site sanitary sewer system without
pretreatment, and for the FMC lands, treatment by air
stripping and subsequent disposal to the on-site storm sewer
system. However, should remediation of the BNR and FMC lands
86
occur concurrently, it is realized that an air stripping
treatment system will be provided for treatment of extracted
contaminated groundwater on the FMC lands, and, therefore,
the initial capital cost for hydraulic containment of the BNR
lands may be reduced by utilizing a common air stripping
system. In addition, treatment/disposal costs for the BNR
extracted groundwater would be reduced by an estimated
$14,000 per year.
Based on the above discussion, the
discussion presented in Sections 3.4.1 and 3.4.2, and
considering simultaneous implementation of the remedial
alternatives for the BNR lands and the FMC lands, the
selected remedial atlernative to reduce the concentration of
TCE in the groundwater to less than the 10~6 excess
cancer risk criterion at the Site boundary is the extraction
well hydraulic containment alternative with air stripping of
extracted groundwater and subsequent treated effluent
discharge to the Mississippi River via the on-site storm
sewer.
87
4.0 DISCUSSION OF HYDRAULIC CONTAINMENT ALTERNATIVE ATEVALUATION LOCATIONS
4.1 SCOPE
A qualitative review of remedial
technologies and a further quantitative review of appropriate
remedial alternatives combining preferred technologies have
identified that hydraulic containment with some form of
treatment and/or disposal is the most appropriate alternative
to reduce the off-site migration of VOCs in Site groundwater,
specifically TCE, to the 10~6 excess cancer risk
criterion at the Site boundary. This section discusses in
detail the technology of hydraulic containment and how,
through adjustments to extraction well pumping rates,
10~6 and 10 excess risk criteria can be attained
at each of the evaluation locations stipulated by the
Agencies. These Agency stipulated evaluation locations are:
- the Site boundary,
the Anoka County property,
the Mississippi River shoreline, and
the Minneapolis Water Works.
A present worth summary for the hydraulic
containment alternative at each evaluation location, for both
the 10~" and 10 excess cancer risk criteria, is
presented in Table 5. A detailed cost breakdown for each of
these alternatives is presented in Appendix B.
88
TABLE 5
SUMMARY OP ESTIMATED COST FOR HYDRAULIC CONTAINMENT REMEDIAL ACTION ALTERNATIVESTO ACHIEVE 10~6 and 10~5 RISK LEVELS AT STIPULATED EVALUATION LOCATIONS
Risk Level Achieved at Total CapitalEvaluation Point Construction Cost
1.
2.
3.
4.
5.
6.
7.
10~6 at Site boundary $576,745
10~5 at Site boundary 576,745
10~ at County lands 576,745
10" at County lands 576,745
10~6 at river shoreline 576,745
10~5 at river shoreline 184,520
10 at Water Works intake
FMC CORPORATIONMINNEAPOLIS, MINNESOTA
Operation, Maintenance and Monitoring Cost
Annual Cost Annual Cost Total Present Total RemedialCapital Cost FMC Lands BNR Lands Worth Cost Alternative Cost
$66,000 $79,900 $24,850 $675,720 $1,318,465
66,000 79,400 24,850 671,780 1,314,525
66,000 79,400 24,850 671,780 1,314,525
66,000 73,000 24,850 621,300 1,264,045
66,000 73,000 24,850 621,300 1,264,045
66,000 34,000 41,120 465,355 715,875
66,000 53.000 607,910 673,910
8. 10~5 at Water Works intake same as 10 risk level Water Works intake
Notes;
1. Annual operation, maintenance and monitoring costs for FMC lands calculated for 11 year period.2. Annual operation, maintenance and monitoring costs for BNR lands calculated for 2 year period.3. When no remedial action is provided, groundwater monitoring program carried out for 20 year period.4. Present worth costs calculated at a net discount rate of six percent.
4.2 DESCRIPTION OF HYDRAULIC CONTAINMENT TECHNOLOGY
Hydraulic containment has been selected as
the most appropriate technology to restrict off-Site
contaminant migration to predefined limits. The following is
a discussion of the technology and the approach used to
assess the effectiveness of hydraulic containment.
To prevent effectively the off-site migration
of VOC contamination in the groundwater beneath the Site,
evaluated wells were located at contaminant "hot spots" in
the BNR and FMC lands. Where theoretically required,
additional wells were sited at intermediate distances between
the "hot spots". Therefore, for the FMC lands, an adequate
hydraulic containment system would consist of six wells with
uniform spacing of 190 feet, while for the BNR lands, two
wells spaced 170 feet apart would contain the flow system.
The approximate location of these wells is illustrated on
Figure 6. The aquifer properties for each site, as presented
in Table 6, were averaged over the area of influence of the
wells.
The area of capture for each of the wells was
defined as the distance to a point downgradient from the
proposed well where the ambient groundwater velocity was
equal, but opposite in direction to the velocity induced by
pumping. On the basis of this definition, the pumping rate
89
TABLE 6
AVERAGE AQUIFER PROPERTIES
BNR Lands FMC Lands
Transmissivity (f t2/<jay) 3450 780* (well 29)*
Aquifer Thickness (ft.) 15 70
Permeability (ft/day) 230* 11.1
Hydraulic Gradient 0.0016* 0.0065 (well 15)*
Groundwater Velocity (ft/yr) 134.3 26.43
* "Final Report - Phase I and II Investigation Programs",S.S. Papadopulos & Associates Inc., August 1984
of each well was determined. This resulted in a pumping rate
of 15.8 GPM for each of the six wells on the FMC lands, for a
total pumping rate of approximately 95 GPM. Similarly/ for
the BNR lands, a rate of 15.0 GPM for each well and a total
pumping rate of 30.0 GPM was determined to provide
containment. Solving the Jacobs (Groundwater, Freeze &
Cherry) equation for drawdown at a distance from a pumping
well gives a total of 2.14 feet of drawdown midway between
pumping wells on the FMC lands. Similarly, for the BNR
lands, a total drawdown of 0.70 feet midway between the
pumping wells was calculated.
Under the described conditions of pumping,
the flux of water passing off Site towards the river is zero
and the contaminant mass flux leaving the Site is zero.
Under these conditions, a 10~6 excess cancer risk
criterion is achieved at the Site boundary.
To achieve a groundwater contaminant
concentrations equivalent to the 10"̂ and 10"̂
excess cancer risk criteria at each of the evaluation
locations, flow rates of the extraction well systems
identified above were adjusted to provide partial hydraulic
containment. A number of assumptions were employed to
determine the pumping rates to effect partial hydraulic
containment in order to meet excess cancer risk criteria at
each evaluation location.
90
Contaminant concentrations measured at
existing wells were assumed to be representative of the total
volume of aquifer influenced by any pumping well constructed
at, or directly adjacent to the existing wells. It was
concluded in the Feasibility Study submitted to the Agencies
in January 1985 that on-site contamination is unlikely to be
distributed throughout the whole vertical thickness of the
aquifer. Similarly, the combined effects of dilution,
dispersion and retardation serve to significantly reduce
contaminant levels within a short distance from the source.
Therefore, assuming a uniform distribution of contaminants
over the volume of aquifer influenced by any one well leads
to a conservative estimate of the total contaminant mass.
If the VOCs in the groundwater were
uninfluenced by reaction with the porous media, the removal
of one pore volume of water by pumping would remove the
majority of the contaminant mass from the area of pumping
influence. However, since adsorption phenomena cause a
retardation in the rate of contaminant migration, more than a
single flushing of the aquifer would be required to reduce
VOC concentrations to desired levels. It was concluded from
field experiments conducted near Ottawa, Canada (Gloucester
Project, National Hydrology Research Institute) that flushing
of 27 pore volumes could effectively remove 90 percent of the
TCE mass within that aquifer.
91
Other studies being done at a hazardous waste
site in Ohio, lead to the conclusion that from 10 to 20 pore
volumes would be required to flush 99 percent of the VOC
contaminant mass from the aquifer. For purposes of this
report, it was assumed that 20 pore volumes would remove 99
percent of the aquifer VOC contaminant mass. An assumed
desorption decay curve has been constructed and is presented
in Figure 7. A site specific desorption decay curve should
be generated from laboratory simulations conducted on samples
of aquifer materials obtained from this site before final
design for a hydraulic containment system is undertaken.
Figure 7 shows that an estimated 16 percent
of the TCE mass is removed in the first pore volume pumped
from the aquifer. One pore volume was calculated by
determining the volume of the aquifer influenced by pumping
and then multiplying that volume by an assumed porosity of
0.30. A porosity of 0.30 is considered typical for the soil
types found at the Site. Sixteen percent of the total
contaminant mass in the volume of the aquifer influenced by
pumping was divided by the total volume pumped to arrive at
an average TCE concentration in the water pumped during
removal of the first pore volume. For the BNR lands, this
average concentration was calculated to be 4,000 ppb, and for
the FMC lands, an average concentration of 500 ppb was
calculated. These concentrations would decrease with
continued flushing as illustrated on Figure 7.
92
100
L
PERCENT TCE REMOVED
NORMALIZED TCE MASS
10
PORE VOLUMES
IS 20
CRA
figure 7ASSUMED RELATIONSHIP BETWEEN TCE REMOVAL
AND MASS vs. PORE VOLUMESFMC Northern Ordnance Plant
1918- 29/04/85
I The total contaminant mass was determined
from the average TCE concentrations in existing wells and
] extrapolated over that volume of the aquifer represented by
/ these wells. This total therefore does not consider the mass
of contaminant adsorbed onto the porous media within the
volume of the aquifer. It is expected however, that because
of the large volumes of aquifer considered as being
j represented by any one well, the resulting TCE concentration
, and mass is considered as conservative.
In order to meet the 10~5 excess cancer
risk criterion of 28 ppb for TCE, the pumping rates in the
1 extraction wells were reduced by a factor such that water
passing through the now incomplete hydraulic barrier would
have a concentration of 28 ppb. The reduced pumping rate was
I calculated by subtracting the design concentration from that
of the pumped water for each of the BNR and FMC systems.
| ^ This new value, when divided by the original concentration,
I yields the factor by which the pumping rate would be reduced
in the BNR and FMC hydraulic containment systems.
iBy this approach, the pumping rate of each
I well is similarly reduced to yield the desired contaminant
* concentrations by-passing the hydraulic containment system.
It is noted that different results would be achieved if the
total required reduction in pumping was obtained by reducing
the rate at any one well.
Ii 93
Existing research data suggest that VOC
concentrations in the groundwater decrease with travel
distance from the contaminant source. The Feasibility Study
inferred from the existing concentrations observed in wells
downgradient of the Site that the concentrations of TCE in
the groundwater are reduced by at least one to two orders of
magnitude in the County lands compared with concentrations at
the Site boundary. A further reduction of one order of
magnitude is achieved between the County lands and the
river.
This phenomenon, based on the observed
contaminant distribution downflow from Well 15, is also
applicable to the BNR lands. On the BNR lands, however, the
contaminants in the upper aquifer flow off site to the south
and then to the river by some undefined pathway. Dilution in
this aquifer is achieved through infiltration as well as by
mixing with waters from the lower aquifer where the
intervening clay layer is not present. Few data are
available to confirm concentration decreases downgradient in
this aquifer although the available data suggest that the one
to three order of magnitude reductions in contaminant levels
between the Site and the River may also be applicable to the
BNR lands.
A concentration of 280 ppb crossing the Site
boundary would, therefore, be reduced to 28 ppb (10~5
risk level) at the County lands and further reduced to
94
2.8 ppb (10~6 risk level) at the river. The pumping
rates required to achieve these concentrations are summarized
on Table 7.
4.3 EVALUATION LOCATIONS
4.3.1 Site Property Boundary
As described in Section 4.2, the hydraulic
containment system necessary to achieve the 10"̂ excess
cancer risk criterion at the Site boundary must prevent
off-site migration of groundwater contaminants from all
identified "hot spots". Obtaining the 10"̂ excess
cancer rate criterion at the Site boundary would essentially
require the same design, with only a slight reduction in
pumping rates to allow a small percentage of contaminants to
pass by the hydraulic containment system.
It was assumed in Section 4.2 that removal of
20 pore volumes of groundwater from beneath the Site will
effectively reduce existing contaminant mass within the
aquifer by 99 percent. On this basis, a total pumping rate
of 125 GPM has been determined in order to remove 20 pore
volumes from the FMC and BNR lands to maintain the 10~6
excess cancer risk criterion at the Site boundary. This
total pumping rate requires a pumping rate of 30 GPM to be
maintained at the BNR extraction wells for two years, and a
95
TABLE 7
SUMMARY OF REQUIRED PUMPING RATES FOR EXTRACTION WELLFOR HYDRAULIC CONTAINMENT SELECTED REMEDIAL ACTION ALTERNATIVE
PMC CORPORATIONMINNEAPOLIS, MINNESOTA
Pumping Ratesfor Hydraulic Containment
(GPM)Combined Hydraulic Containment for FMC Lands and BNR Lands
To achieve 20 pore
PMC LandsArea
95
90
90
45
45
0
0
BNR LandsArea
30
30
30
30
30
15
0
Pumping Rate(GPM)
125
120
120
75
75
15
0
Tr ich loroethyleneConcentration'
(ppb)
1340
1375
1375
1900
1900
4000
-
volume
Pumping Rate(GPM)
12595
12090
12090
7545
7545
15
0
flushings
Time( years )
first 2 yearsremaining 9 yearsfirst 2 years
remaining 9 years
first 2 yearsremaining 9 yearsfirst 2 years
remaining 9 years
first 2 yearsremaining 9 years
2 years-
RISK LEVEL AT RECEPTOR
10 at property boundary
10 at property boundary
10 at county lands
10 at county lands
10 at river shoreline
10 at river shoreline10~6 at river intake
1. Average concentration of trichloroethylene in first pore volume is 500 ppb. Pumping period is 11 years for 20 pore volume flushings.2. Average concentration of trIchloroethylene in first pore volume is 4000 ppb. Pumping period is 2 years for 20 pore volume flushings.3. Average concentration of trichloroethylene in combined extracted groundwater during first pore volume.
pumping rate of 95 GPM to be maintained at the FMC extraction
wells for 11 years. Pumping at these rates would result in
total extracted groundwater contaminant concentrations of
1,340 ppb TCE in the first extracted Site pore volume.
The pumping rate required to obtain the
10~5 excess cancer risk criterion at the Site boundary
would be reduced to 120 GPM from both the FMC and BNR lands.
A 20 pore volume extraction at this pumping rate would
require the BNR system to operate for two years at 30 GPM and
the FMC system to operate for 11 years at 90 GPM. Pumping at
this reduced rate would result in a total extracted
groundwater contaminant concentration of 1,375 ppb TCE in the
initial pore volume.
It is noted that the concentrations of TCE
identified above are determined on the basis of removal of
the first pore volume of groundwater. These concentrations
will reduce as subsequent pore volumes are removed. (See
Section 4.2).
On the basis of the estimated contaminant
concentrations in the extraction waters, and the proposed
extraction well pumping rates, an air stripping treatment
facility would be incorporated into the remedial system
design. The air stripping unit would be designed for either
the 125 GPM or the 120 GPM extraction well pumping rates with
a removal efficiency of 98 percent for TCE. Following
96
treatment by air stripping, effluent would ultimately be
discharged to the on-site storm sewer system. Section 4.4identifies permitting requirements for this proposedtreatment facility.
Implementation of the hydraulic containment
and treatment system necessary to obtain the 10 and
10~"5 excess cancer risk criteria at the Site boundarywould require a capital expenditure of $576,745 as shown onTable 5. This cost includes all facility construction costs,
a 25 percent contingency, and all engineering and inspectionnecessary to supervise the construction and implement the
system. In addition to the initial capital costs, annualoperation, maintenance and monitoring costs would be incurredfor an off-Site groundwater monitoring program to monitor the
efficiency of the hydraulic containment system. Annual costswould also be incurred for operation of the groundwater
treatment and discharge system. The annual costs are
estimated to be approximately $104,750 per year for the firsttwo years of system operation, falling to approximately$79,900 per year for the remaining nine years of system
operation. Thus, the present worth system costs to achieve
the 10~" and 10 risk levels assuming a netdiscount rate of six percent, are estimated to be $1,318,465and $1,314,525, respectively. The small cost differential
between these two risk level alternatives reflects the
reduced pumping rates for the 10~̂ risk level system. Asummary of estimated cost is presented in Table 5. Adetailed cost estimate breakdown for each alternative ispresented in Tables B.I and B.2 of Appendix B.
97
I 4.3.2 Anoka County Lands
J The remedial action to be implemented to
. achieve the 10~° excess cancer risk criterion at the
' Anoka County lands located between the Site and the
I Mississippi River, would be similar to that proposed to' _e
obtain the 10 excess cancer risk criterion at the Site
J boundary. All capital costs and annual operation,
maintenance and monitoring costs, are the same as estimated
' ^ in Section 4.3.1 for the 10~5 excess cancer risk
I criterion. A summary of these estimated costs is presented
in Table 5. Table B.3 presented in Appendix B provides a
| detailed cost estimate for this alternative.
The 10~5 excess cancer risk criterion at
f the Anoka County lands would be achieved by reducing the
pumping rate in the Site extraction well system, thus
j ^ allowing a larger percentage of contaminated groundwater to
. pass off site. This alternative provides for a reduction in
total pumping rates to 75 GPM. This revised pumping rate
| would include pumping from the BNR lands for 2 years at 30
GPM and pumping from the FMC lands for 11 years at 45 GPM.
( The resultant concentration of TCE in the extracted
groundwater at these pumping rates would be approximately
1,900 ppb for the first pore volume extracted.
98
This alternative would require the
construction of an air stripping facility designed for a
total flow of 75 GPM with a VOC removal efficiency of 99
percent. Following treatment by air stripping, treated
effluent would be discharged to the on-site storm sewer.
General permitting requirements for implementation of this
system are discussed in Section 4.4.
Capital construction costs to implement this
containment and treatment system are estimated to be
$576,745 as shown on Table 5. This cost includes all
construction costs to construct the system, a 25-percent
contingency, and all engineering required for design and
supervision of the construction and implementation of the
system. Additional costs associated with this alternative
include estimated annual operation, maintenance, and
monitoring costs on the order of ?97,850 for each of the
first two years of operation and $73,000 for each of the
remaining nine years. These annual costs represent costs
associated with implementing a groundwater monitoring program
to monitor the effectiveness of the containment system, and
costs for maintaining the pumping and treatment system on an
annual basis. A summary of the estimated costs is presented
in Table 5. The total present worth cost of this
alternative, assuming a six percent net discount rate is
estimated to be $1,264,045. Table B.4 presented in Appendix
B provides a detailed cost summary of this alternative.
99
4.3.3 Mississippi River Shoreline
The 10~° excess cancer risk critierion
at the Mississippi River shoreline would be achieved with a
system identical to that required to achieve the 10"̂
excess cancer risk criterion at the Anoka County lands. All
capital costs and annual operation, maintenance and
monitoring costs are the same as presented in Section 4.3.2.
A summary of these costs is presented in Table 5. Table B.5
presented in Appendix B provides a detailed cost summary for
this alternative.
The 10~5 excess cancer risk criterion at
the Mississippi River would be achieved by a hydraulic
containment system pumping at a rate of 15 GPM from the BNR
lands only, for a total of two years. On the basis of the
one and two orders of magnitude decrease in groundwater
contaminant concentrations from the Site to the County lands
and from the Site to the river, respectively, as discussed in
the "Feasibility Study", no containment at the FMC lands
would be required. Pumping from only the BNR lands would
result in an estimated TCE concentration of 4,000 ppb in the
extracted initial pore volume.
Figure 2 presented in Section 3, indicates
that at a pumping rate of 15 GPM, it is cost effective to
discharge all extraction waters directly to the on-site
sanitary sewer. Discharging extraction waters directly to
100
the sanitary sewer will require an Agreement with or permit
from the MWCC. Section 4.4 discusses permitting options for
this alternative.
Capital construction costs associated with
this alternative are estimated to be $184,520 as shown on
Table 5. This includes all construction costs, a 25 percent
contingency, and all engineering required to design and
supervise the construction and implement the program. Annual
operation, maintenance and monitoring costs would be $75,120,
providing for a groundwater monitoring program to monitor the
levels and distribution of contamination downgradient of the
FMC lands for 20 years, and all operation, maintenance and
monitoring of the BNR extraction system for two years. A
summary of these estimated costs is presented in Table 5.
The total present worth value of this alternative, assuming a
six percent net discount rate, has been estimated to be
$715,875. Table B.6 presented in Appendix B provides a
detailed cost summary for this alternative.
4.3.4 Minneapolis Water Works Intake
It was concluded in the Feasibility Study
that risk levels for TCE at the Water Works intake
attributable to the Site, meet or are less than the 10-6
101
excess cancer risk criterion and that no remedial action is
required to mitigate risk. Therefore, the costs associated
with this alternative are associated with a long-term
groundwater monitoring program to monitor the levels and
distribution of contaminants leaving the Site.
The present worth cost of this alternative,
assuming a six percent net discount rate, is estimated to be
$673,910. This cost is based on an annual estimated
monitoring cost of $53,000 for a period of 20 years.
Table B.7 presented in Appendix B provides a detailed cost
summary for the annual monitoring requirements.
4.3.5 Residuals Followng System Shutdown
The effectiveness of the hydraulic containment system is
•^. based upon the assumption that 99 percent of the contaminant
I mass is removed from the aquifer by the extraction of 20 pore
volumes. Therefore, only one percent of the contaminant mass
| remains within the aquifer after the 20 pore volumes have
been removed. Any prediction of the resultant concentration
[ of TCE in the groundwater after removal of 20 pore volumes
i would be speculative. However, the rate of desorption is
likely to be much lower with the reduced TCE mass in the
aquifer indicating that concentrations within the groundwater
would be expected to be extremely low.
102
On the basis of there being limited
information available on this subject, it is not known if
this residual mass can be removed in a cost-effective manner
or in an reasonable length of time. A study of the curves
presented on Figure 7 suggest that removal would not be
cost-effective or would not be completed in a reasonable
length of time. This is evidenced by the curve flattening
out at 99 percent removal of the TCE mass in the aquifer. An
effective assessment of this residual concentration can be
made only after system implementation and water quality
monitoring.
4.4 PERMITTING REQUIREMENTS
4.4.1 General
The remedial action alternatives discussed in
Section 4.3 include two treatment and disposal options for
extracted groundwater. These options are: treatment by air
stripping with ultimate discharge of treated effluent to the
on-site storm sewer system; and direct discharge of extracted
groundwater to the on-site MWCC sanitary sewer with no pre-
treatment. Implementation of these treatment and disposal
options would require that FMC apply for the following
permits (or agreements) with the appropriate Agencies:
i) Discharge to the Mississippi
River via the storm sewersubsequent to treatment by
air stripping
- NPDES Permit issued
by MPCA, Division ofWater Quality
ii) Direct discharge to - Permit or agreement
sanitary sewer system with arranged with MWCC,
no treatment most probably based
on VOC limits in the
discharged water
iii) Discharge to atmosphere - Air quality permit
from air stripping tower issued by MPCA,
Division of Air
Quality.
The following sections discuss these permitting requirements
for each of the treatment and disposal options.
4.4.2 Fresh Water Body Discharge
Discharge of treated effluent from the air
stripping tower to the on-site storm sewer system would
require the preparation and submission of an NPDES permit.
This permit would be issued by the MPCA. In general, NPDES
permit applications require that discharge outfalls from
treatment or manufacturing facilities meet specified
discharge levels of defined parameters, and that the owners
must monitor the discharge for compliance.
Neither the USEPA or the MPCA presently have
standards to control VOCs in discharges; however, the MPCA
104
has, in the past, suggested that the 10"̂ excess cancer
risk criterion for TCE (28 ppb) may be appropriate for
discharges in the vicinity of the Site. Therefore, for the
treated effluent at the FMC Site, it has been assumed that
discharge levels of TCE would be maintained at or below 28
ppb. Treatment facilities proposed for each of the
alternatives presented in Section 4.3 have been designed for
removal efficiencies such that a TCE concentration no greater
than 28 ppb in the effluent discharge would be maintained.
Regular periodic monitoring of the NPDES permitted discharge
for VOC's probably would be required during the period that
treated effluent is being discharged through the storm sewer
to the Mississippi River.
4.4.3 Sanitary Sewer Discharge
Recent discussions with representatives of
the MWCC, and prior discharge activities approved by the MWCC
during the CTF construction program, suggest that discharge
of extracted groundwater to the local sanitary sewer would be
allowed subject to limitations on VOC effluent concentrations
and discharge rate. On the basis of discussions with MWCC
representatives, it is believed that discharge of extracted
groundwater with a TCE concentration of 4,000 ppb (4 ppm)
would be approved following submittal of a detailed proposal
to the MWCC. Effluent concentrations in excess of 20,000 ppb
105
i
(20 ppm) may not be approved by the MWCC for discharge to the
sanitary sewer system. However, any level of TCE discharge
would require negotiation of an Agreement with the MWCC.
4.4.4 Air Stripping Tower Discharge
During recent discussions with
representatives of the MPCA, Division of Air Quality, it has
^ been noted that permitting guidelines for air discharges do
I not currently exist for VOC's. However, MPCA representatives
indicated that a discharge of less than 500 pounds per year
of the criteria pollutants may not require a permit
. application. VOC discharges greater than 500 pounds per
' year, but less than one ton per year will require submittal
I of a permit application. However, these systems and the
associated emissions may not have a permit issued. An
I example of a similar case in the Twin Cities area is the Air
Stripping system currently in use at the General Mills (GM)
remediation site. MPCA representatives have stated that the
I GM stripper has an annual VOC emission less than one ton and
was not issued an air permit.
I• Calculations to determine the total mass of
' VOC potentially discharged from the air stripping tower for
I each of the alternatives discussed in Section 4.3 show that
106
between 560 pounds per year and 160 pounds per year organics
would be discharged to the atmosphere based on influent
concentrations of TCE between 1,340 ppb and 1,900 ppb,
respectively. The relationship between TCE and total VOC
concentration was determined from data available from
groundwater sampling completed at the Site to date.
Therefore, on the basis of these calculations and the recent
discussions with the MPCA, no secondary treatment would be
required for the stripped VOC's. An air permit would
probably not be issued.
107
5.0 CONCLUSIONS
1) As directed by the Agencies, an evaluation of existing
remedial action technologies and alternatives which would
reduce the VOC contaminant discharge in the groundwater
at the Site boundary to the 10-6 excess cancer risk
criterion was carried out. It was concluded that on the
basis of technical feasibility, environmental, public
health and institutional impact and cost, that hydraulic
containment with some form of treatment and/or disposal
would be the appropriate remedial alternative.
2) The hydraulic containment alternative was evaluated in
detail at each of the Agencie's/stipulated evaluation
locations. Pumping rates oetween 30 GPM and 15 GPM at
the BNR lands and between 95 GPM and 45 GPM at the FMC
lands were determined for each location to achieve the
10-6 an<j io"5 excess cancer risk criteria
respectively. The stipulated evaluation locations were
the Site Boundary, the Anoka County lands, the
Mississippi River shoreline and the Minneapolis Water
Works intake.
3) The impact of Site contaminants at the Minneapolis Water
Works intake was less than the 10 excess cancer
risk criterion under existing conditions; the appropriate
response action was determined to be long-term monitoring
for this evaluated location.
108
L
4) On the basis of the pumping rates determined at each
evaluation location, it was concluded that treatment byair stripping and subsequent discharge to the Mississippi
River via the on-site storm sewer was the appropriate
method of handling extracted groundwater to obtain
the 10-6 ana iQ-5 excess cancer risk criteria at
all of the evaluation locations except for the 10"5
excess cancer risk criterion at the Mississippi River
shoreline. It was concluded that direct discharge to the
on-site sanitary sewer was the appropriate method of
disposal for the 10-5 excess cancer risk criterion at
the river shoreline.
5) Estimated total present worth costs for each of the
hydraulic containment alternatives evaluated ranged from
a high of $1,318,465 to achieve a 10-6 excess cancer
risk criterion at the Site Boundary to a low of $715,875
to achieve a 10-5 excess cancer risk criterion at the
Mississippi River.
6) The estimated total annual groundwater monitoring costs
were estimated to be $53,000. Initial capital costs of
$66,000 to construct new monitoring wells and implement
the program were estimated. The annual monitoring costs
would be incurred for a total of 11 years to achieve the
10-6 excess cancer risk criterion at all the
evaluation locations except the Water Works intake, and
to achieve the 10"5 excess cancer risk criterion at
the Site Boundary and the Anoka County lands. The annual
109
monitoring costs would be incurred for a minimum of 20
years for the 10~6 excess cancer risk criterion at
the Water Works intake and to achieve the 10~5 excess
cancer risk criterion at the Mississippi River shoreline
and the Water Works intake.
All of which is respectfully submitted,
CONESTOGA-ROVERS & ASSOCIATES LIMITED
Richard G. Shepherd, P. Eng,
Bruce A. Monteith, P. Eng.
110
APPENDIX A
DETAILED RELATIVE COST ESTIMATES OF
REMEDIAL ACTION TECHNOLOGIES
I
TABLE A.1
EXCAVATION OF CONTAMINATED SOILS FROM BNR LANDS WITHDISPOSAL IN CONTAINMENT FACILITY ON FMC LANDS
Estimated UnitItem Description Quantity Unit price Total Price
Capital Construction Cost Estimate
1. Mobilization and demobilization 1 L.S. $18,000.00 $ 18,000.
2. Strip 6" topsoil and stockpile(allow entire contaminated BNRlands, plus CF area, plusstockpile area) 7,700 C.Y. 2.40 18,480.
3* Excavate uncontaminatedoverburden within BNR lands to20' depth and stockpile 66,130 C.Y. 4.20 277,746.
4. Excavate overburden withinproposed CF area and stockpile 26,645 C.Y. 4.20 111,909.
5. Excavate shallow clay fronproposed CF area and stockpile 21,300 C.Y. 4.20 89,460.
6. Excavate clay from base ofproposed CF and constructclay side key walls 6,770 C.Y. 6.00 40,620.
7. Construct leak and leachatecollection system in base ofCF 780 L.F. 96.00 74,880.
8. Recompact in-situ clay onbottom and sides of CF 8,860 S.Y. 2.40 21,264.
9. Construct CF bottom and sides:a) 6" sand drainage blanket
above and below polyethyleneliner on CF bottom 2,500 C.Y. 11.40 28,500.
b) polyethylene liners 205,460 S.F. 1.20 246,552.c) filter fabric 98,430 S.F. 0.20 19,686.
10. Excavate saturated contaminatedsoils from BNR lands and placein CF (including dewatering ofexcavation and sidewallstailization 50,320 C.Y. 27.40 1,378,768.
continued....
Item
11
12.
13.
14.
15.
16.
TABLE A.1 (cont'd)
EXCAVATION OF CONTAMINATED SOILS FROM BNR LANDS WITHDISPOSAL IN CONTAINMENT FACILITY ON FMC LANDS
Description
Disposal of contaminated waterfrom excavated saturatedmaterial by direct dischargeto POTW
Construct CF cap and final covera) place 3' clay cap over CF
from on-site stockpilematerial
b) place 6" sand blanket belowliner and 16" sand blanketabove liner
c) polyethylene linerd) filter fabrice) place 18" common fill over
fabric from on-site stockpile
Fill BNR Lands excavation witha) balance of on-site stockpileb) remainder from off-site
borrow pit
Estimated UnitQuantity^ Unit Price
3,050 1,000 Gal. 1.80
•
10,720 C.Y. 4.80
6,050 C.Y. 11.40125,220 S.F. 1.20136,900 S.F. 1.00
8,235 C.Y. 3.30
103,335 C.Y. 3.00
29,430 C.Y. 8.40
Total Price
5,490.
51,456.
68,970.150,264.27,380.
27,175.
310,005.
247,212.
Spread 6" topsoil over alldisturbed areas from stockpile 7,700 C.Y. 4.15 31,955.
Seed and mulch all disturbedareas 10 Acres 1,800.00 18,000.
Health and Safety (includingpersonnel protective equipment andair monitoring) 1 L.S. 54,000.00 54,000.
continued....
I
TABLE A.1 (cont'd)
EXCAVATION OF CONTAMINATED SOILS FROM BNR LANDS WITHDISPOSAL IN CONTAINMENT FACILITY ON FMC LANDS
Estimated UnitItem Description Quantity Unit Price Total Price
SUBTOTAL $3,317,772.
Contingency(25% of SUBTOTAL) 829,443.
Engineering & Site Supervision(15% of SUBTOTAL) 497,665.
I -TOTAL ESTIMATED CAPITALCONSTRUCTION COST $4,644,880.
continued....
TABLE A.1 (cont'd)
EXCAVATION OF CONTAMINATED SOILS FROM BNR LANDS WITHDISPOSAL IN CONTAINMENT FACILITY ON FMC LANDS
Estimated unitItem Description Quantity unit price Total Price
Operation, Maintenance and Monitoring Capital Cost Estimate
1. Install new groundwatermonitoring wells at CTFfor long term monitoring(351 deep) 5 Each $ 3,000.00 $ 15,000.
SUBTOTAL CAPITAL COST ESTIMATE $ 15,000.
Operation, Maintenance and Monitoring Annual Cost Estimate
1. Groundwater monitoring program:a) 5 wells sampled 4 times per
year, 4 samples per well,including QA/QC
b) sampling eventsc) reporting and administration
9641
SamplesEachL.S.
$ 500500
5,000
.00
.00
.00
$ 4825
,000.,000.,000.
2. CF:a) cap maintenance (mowing,
retopsoiling, seeding, etc.) 1 L.S. 3,620.00 3,620.b) leachate collection and
maintenance of system (assumeddisposal to POTW) 1 L.S. 1,220.00 1,220.
c) miscellaneous maintenance,inspections and administration 12 Months 1,000.00 12,000•
SUBTOTAL ANNUAL COST ESTIMATE $ 71,840.
*PRESENT WORTH OF ANNUAL COST ESTIMATE $988,880.
* Based on a six percent net discount rate for a 30 year operation period.
I
L
TABLE A.1 (cont'd)
EXCAVATION OF CONTAMINATED SOILS FROM BNR LANDS WITHDISPOSAL IN CONTAINMENT FACILITY ON FMC LANDS
SUMMARY COST
Estimated UnitItem Description Quantity Unit Price Total price
TOTAL ESTIMATED CAPITAL CONSTRUCTION COST $4,644,880.
Estimated Operation, Maintenance and Monitoring Cost:a) Capital Cost $ 15,000.b) Present Worth of Annual Cost $988,880.
TOTAL ESTIMATED OPERATION, MAINTENANCE AND MONITORING COST $1,033,880.
TOTAL REMEDIAL ALTERNATIVE COST $5,648,760.
TABLE A.2a
PHYSICAL CONTAINMENT OF BNR LANDS
Item DescriptionEstimatedQuantity Unit
UnitPrice Total Price
Capital Construction Cost Estimate
a) Without Low Permeability Soil Cover
1. Mobilization and demobilization 1
2. Purchase BNR property 2
3. Strip 6" topsoil and stockpile(allow entire area withinslurry wall plus 20' beyond) 1,475
4. Construct soil-bentonitecontainment cutoff wall tounderlying confining clay(1,000' long, 36' averagedepth) 43,100
5. Disposal of contaminatedbentonite slurry at completionof construction operation:a) transport 600b) gate fees 600
6. Install extraction well to 35'depth 1
7. Construct pumphouse (completewith electrical supply, pumpingequipment, 12,000 gallon holdingtank, piping from extraction wellto holding tank and from holdingtank to sanitary sewer manhole,and flow meter) 1
8. Initial drawdown of water tablewithin soil-bentonite slurrywall and direct disposal toPOTW (pumping rate at 5 GPMfor 30 days)
9. Spread 6" topsoil from stockpileover all disturbed areas 1,475
L.S. $30,000.00 $ 30,000.
Acres 72,000.00 144,000.
C.Y.
S.F.
TonsTons
Each
200 1,000 Gal.
C.Y.
2.40
168.00102.00
8,160.00
L.S. 58,440.00
1.80
3,540.
6.00 258,600.
100,800.61,200.
8,160.
58,440.
360.
4.15 6,121.
continued...
TABLE A.2a (cont'd)
PHYSICAL CONTAINMENT OF BNR LANDS
Item DescriptionEstimatedQuantity Unit
UnitPrice Total Price
9. Seed and mulch all disturbedareas
10. Health and Safety (includingpersonnel protective equipmentand air monitoring)
Acres 1,800.00
L.S. 42,000.00
SUBTOTAL
Contingency(25% of SUBTOTAL)
Engineering & Site supervision(15% Of SUBTOTAL)
TOTAL ESTIMATED CAPITALCONSTRUCTION COST
3,600.
42,000.
$ 716,821.
179,205.
107,524.
$1,003,550.
continued....
TABLE A.2a (cont'd)
PHYSICAL CONTAINMENT OF BNR LANDS
Item DescriptionEstimatedQuantity Unit
unitPrice
Operation, Maintenance and Monitoring Capital Cost Estimate
1. install new groundwatermonitoring wells downgradientof site for long term
Total Price
monitoring (35 ' deep) 6 Each $ 3,000.00
SUBTOTAL CAPITAL COST ESTIMATE
Operation, Maintenance and Monitoring Annual Cost Estimate
1.
2.
Groundwater monitoring program:a) 12 wells sampled 4 times per
year, one sample per wellincluding QA/QC 58
b) sampling events 4c) reporting and administration 1
Physical containment system:a) pumping equipment and well
maintenance 1*b) physical testing of cut-off
wall 20c) disposal of collected extracted
groundwater (assumed disposalto POTW) 300 1,
d) miscellaneous maintenance andinspections 12
**SUBTOTAL ANNUAL COST ESTIMATE
***PRESENT WORTH OF ANNUAL COST ESTIMATE
Samples $ 500.00Each 500.00L.S. 3,000.00
Well 1,800.00
Samples 600.00
000 Gal. 1.80
Months 500.00
$ 18,000.
$ 18,000.
$ 29,000.2,000.3,000.
1,800.
12,000.
540.
6,000.
$ 54,340.
$536,185.
* physical testing of cut-off wall to be carried out for first five years only.** Reduces to $42,340. after five years.*** Based on a six percent net discount rate for a 20 year operation period.
L continued.
TABLE A.2a (cont'd)
PHYSICAL CONTAINMENT OF BNR LANDS
SUMMARY OF COST
Item DescriptionEstimatedQuantity Unit
UnitPrice Total Price
TOTAL ESTIMATED CAPITAL CONSTRUCTION COST
Estimated Operation, Maintenance and Monitoring Cost:a) Capital Costb) present Worth of Annual Cost
TOTAL ESTIMATED OPERATION, MAINTENANCE AND MONITORING COST
TOTAL REMEDIAL ALTERNATIVE COST
$1,003,550.
$ 18,000.$536,185.
$ 554,185.
$1,557,735.
TABLE A.2b
PHYSICAL CONTAINMENT OF BNR LANDS
Item PescriptionEstimatedQuantity Unit
UnitPrice Total Price
I
Capital Construction Cost Estimate
b) With Low Permeability Soil Cover
1. Mobilization and demobilization
Purchase BNR property2.
3.
4.
7.
9.
Strip 6" topsoil and stockpile(allow entire area withinslurry wall plus 20' beyond,plus stockpile area)
Excavate overburden within areato be capped, regrade tominimum 3% slopes, andstockpile
Construct clay working platformfor slurry wall constructionwith clay imported from off-siteborrow pit
Construct soil-bentonitecontainment cutoff wall tounderlying confining clay layer(1000* long, 32' average depth)
Disposal of contaminatedbentonite slurry at completionof construction operation:a) transportb) gate fees
Construct clay cap with clayimported from off-site borrowpit
Import sand for 6" thick sanddrainage blanket over clay cap
1
2
2,430
9,520
1,250
38,300
520520
4,930
1,230
L.S. $30,000.00 $ 30,000.
Acres 72,000.00 144,000.
C.Y.
C.Y.
C.Y.
S.F.
TonsTons
C.Y.
C.Y.
2.40
2.90
11.40
168.00102.00
5,832.
27,608.
14,250,
6.00 229,800.
87,36053,040
11.40 56,202.
11.40 14,022.
continued...
TABLE A.2b (cont'd)
PHYSICAL CONTAINMENT OF BNR LANDS
Estimated UnitItem Description Quantity unit price Total price
10. Place 3' of common fill oversand blanket from on-sitestockpile 9,040 C.Y. 3.30 29,832.
11. Install extraction well to 35'depth 1 Each 8,160.00 8,160.
12. Construct puraphouse (completewith electrical supply, pumpingequipment, 200 gallon holdingtank, piping from extractionwell to holding tank and fromholding tank to sanitary sewermanhole, and flow meter) 1 Each 44,280.00 44,280.
13. Initial drawdown of water tablewithin soil-bentonite slurrywall and direct disposal toPOTW (pumping rate at 5 GPMfor 30 days) 200 1,000 Gal. 1.80 360.
14. Spread 6" topsoil, from topsoilstockpile, over all disturbedareas 2,430 C.Y. 4.15 10,085.
15. Seed and mulch all disturbedareas 4 Acres 1,800.00 7,200.
16. Health and Safety (includingpersonnel protective equipmentand air monitoring) 1 L.S. 42,000.00 42,000.
continued....
TABLE A.2b (cont'd)
PHYSICAL CONTAINMENT OF BNR LANDS
Estimated UnitItem Description Quantity Unit Price Total Price
SUBTOTAL $ 804,031.
Contingency(25% Of SUBTOTAL) 201,009.
Engineering & Site Supervision(15% of SUBTOTAL) 120,605.
I
I
TOTAL ESTIMATED CAPITALCONSTRUCTION COST $1,125,645.
continued....
TABLE A.2b (cont'd)
PHYSICAL CONTAINMENT OF BNR LANDS
Estimated UnitItem Description Quantity Unit Price
Operation, Maintenance and Monitoring Capital Cost Estimate
1. Install new groundwatermonitoring wells downgradientof site for long termmonitoring (35' deep) 6 Each $ 3,000.00
SUBTOTAL CAPITAL COST ESTIMATE
Operation, Maintenance and Monitoring Annual Cost Estimate
1. Groundwater monitoring program:a) 12 wells sampled 4 times per
year, one sample per wellincluding QA/QC
b) sampling eventsc) reporting and administration
2. Physical containment system:a) pumping equipment and well
maintenance*b) physical testing of cut-off
wallc) disposal of collected extracted
groundwater (assumed disposalto POTW)
d) miscellaneous maintenance andinspections
e) cap maintenance and grasscutting
**SUBTOTAL ANNUAL COST ESTIMATE
***PRESENT WORTH OF ANNUAL COST ESTIMATE
Total Price
$ 18,000.
$ 18,000.
5841
1
20
10
12
1
SamplesEachL.S.
Well
Samples
1,000 Gal.
Months
L.S.
$ 500.00500.00
3,000.00
1,800.00
600.00
1.80
500.00
4,000.00
$ 29,900.2,000.3,000.
1,800.
12,000.
18.
6,000.
4,000.
$ 57,818.
$576,075.
* Physical testing of cut-off wall to be carried out for first five years only.** Reduces to $45,818. after five years.*** Based on a six percent net discount rate for a 20 year operation period.
L
TABLE A.2b (cont'd)
PHYSICAL CONTAINMENT OF BNR LANDS
SUMMARY OF COST
Estimated UnitItem Description Quantity Unit Price Total Price
TOTAL ESTIMATED CAPITAL CONSTRUCTION COST $1,125,645.
Estimated Operation, Maintenance and Monitoring Cost:a) Capital Cost $ 18,000.b) Present Worth of Annual Cost $576,075.
TOTAL ESTIMATED OPERATION, MAINTENANCE AND MONITORING COST $ 594,075.
TOTAL REMEDIAL ALTERNATIVE COST $1,719,720.
L
TABI£ A. 3
HYDRAULIC CONTAINMENT OF BNR LANDS
Item DescriptionEstimatedQuantity Unit
UnitPrice Total price
Capital Cost
1. Mobilization and demobilization
2. Secure easement on BNR property
3. Install extraction wells to 35'depth with discharge to adjacentmanhole
4. Disposal of contaminated soilfrom drilling operating cuttings
5. Construct gravity main pipingsystem to collect extractedgroundwater (including trenchexcavation, bedding, pipematerial, manholes, backfill,and electrical cable for wellpumps)
6. Construct pumphouse (includingpower supply, pumping equipment,piping to sanitary sewer manhole,and flow meter)
7. Supply and place gravel foraccess road to pumphouse
8. Site restoration
1 L.S. $12,000.00 $ 12,000.
0.4 Acres 72,000.00 28,800.
360
1
750
1
Each 10,560.00
L.S.
L.F.
L.F.
L.S.
3,000.00
72.00
L.S. 43,200.00
4.50
5,000.00
21,120.
3,000.
25,920,
43,200.
3,375.
5,000.
continued....
TABLE A.3 (cont'd)
HYDRAULIC CONTAINMENT OF BNR LANDS
Item DescriptionEstimatedQuantity Unit
UnitPrice Total Price
9. Health and Safety (includingpersonnel protective equipmentand air monitoring) L.S. 12,000.00
SUBTOTAL
Contingency(25% of SUBTOTAL)
Engineering & Site Supervision(15% of SUBTOTAL)
TOTAL ESTIMATED CAPITALCONSTRUCTION COST
12,000.
$154,415.
38,605.
23,160.
$216,180.
I
continued.
UnitPrice
TABLE A.3 (cont'd)
HYDRAULIC CONTAINMENT OF BNR LANDS
EstimatedItem Description Quantity Unit ___
Operation, Maintenance and Monitoring Capital Cost Estimate
1. Install new groundwatermonitoring wells downgradientof site for long termmonitoring (35* deep) 6 Each $ 3,000.00
SUBTOTAL CAPITAL COST ESTIMATE
Operation, Maintenance and Monitoring Annual Cost Estimate
1. Groundwater monitoring program:a) 12 wells sampled 4 times per
year, one sample per wellincluding QA/QC
b) sampling eventsc) reporting and administration
2. Hydraulic containment system:a) pumping equipment and well
maintenanceb) operation cost of system
(eg. power)c) disposal of collected
extracted groundwater(assumed disposal to POTW)
d) miscellaneous maintenanceand inspections
SUBTOTAL ANNUAL COST ESTIMATE
*PRESENT WORTH OF ANNUAL COST ESTIMATE
Total Price
$ 18,000.
$ 18,000.
5841
2
1
16,000
12
SamplesEachL.S.
Wells
L.S.
1,000 Gal.
Months
$ 500.00500.00
3,000.00
1,800.00
500.00
1.80
500.00
$ 29,000.2,000.3,000.
3,600.
500.
28,800.
6,000.
$ 72,900.
$133,625.
* Based on a six percent net discount rate for a 2 year operation period.
L
TABLE A.3 (cont'd)
HYDRAULIC CONTAINMENT OF BNR LANDS
SUMMARY OF COST
Estimated UnitItem Description Quantity Unit Price Total Price
TOTAL ESTIMATED CAPITAL CONSTRUCTION COST $216,180.
Estimated Operation, Maintenance and Monitoring Cost:a) Capital Cost $ 18,000.b) Present Worth of Annual Cost $133,625.
TOTAL ESTIMATED OPERATION, MAINTENANCE AND MONITORING COST $151,625.
TOTAL REMEDIAL ALTERNATIVE COST $367,805.
LII
TABLE A.4
PHYSICAL CONTAINMENT OF FMC LANDS
Item DescriptionEstimatedQuantity Unit
UnitPrice Total Price
L
Capital Construction Cost Estimate
1. Mobilization and demobilization
2.
3.
5.
6.
7.
8.
Strip 6" topsoil and stockpile(allow 50 foot wide strip alongcurtain wall) 2,610
Construct grout curtain cut-offwall to underlying confiningbedrock layer (2,990' long,135' average depth) 402,480
Disposal of contaminated drillcuttings from grout curtain wallconstruction:a) transport 820b) gate fees 820
Install extraction well to135' depth 1
Construct pumphouse (completewith electrical supply, pumpingequipment, 3,000 gallon holdingtank, piping from extraction wellto holding tank and from holdingtank to sanitary sewer manhole,and flow meter) 1
Initial drawdown of water tablewithin grout curtain wall anddirect disposal to POTW(pumping rate at 45 GPM for30 days)
Spread 6" topsoil fromstockpile over all disturbedareas 2,610
L.S. $36,000.00
C.Y.
S.F.
TonsTons
2.40
8.25
168.00102.00
Each 12,000.00
Each 35,160.00
1,945 1,000 Gal.
C.Y.
1.80
4.15
$ 36,000.
6,264.
3,320,460.
137,760,83,640
12,000.
35,160.
3,501.
10,832.
continued...
L
TABLE A.4 (cont'd)
PHYSICAL CONTAINMENT OF FMC LANDS
Item DescriptionEstimatedQuantity unit
UnitPrice Total price
9. Seed and mulch all disturbedareas
10. Health and Safety (includingpersonnel protective equipmentand air monitoring)
Acres 1,800.00
L.S. 60,000.00
SUBTOTAL
Contingency(25% of SUBTOTAL)
Engineering & Field Supervision(15% Of SUBTOTAL)
TOTAL ESTIMATED CAPITALCONSTRUCTION COST
7,200,
60,000.
$3,712,817.
928,205.
556,923.
$5,197,945.
continued.
UnitPrice
TABLE A.4 (cont'd)
PHYSICAL CONTAINMENT OF FMC LANDS
EstimatedItem Description Quantity Unit ____
Operation, Maintenance and Monitoring Capital Cost Estimate
1. Install new groundwatermonitoring wells downgradientof site for long termmonitoring (135* deep) 6 Each $ 8/000.00
SUBTOTAL CAPITAL COST ESTIMATE
Operation, Maintenance and Monitoring Annual Cost Estimate
1. Groundwater monitoring program:a) 12 wells sampled 4 times per
year, one sample per wellincluding QA/QC
b) sampling eventsc) reporting and administration
2. Physical containment system:a) pumping equipment and well
maintenance*b) physical testing of cut-off
wallc) disposal of collected extracted
groundwater (assumed disposalto POTW)
d) miscellaneous maintenance andinspections
**SUBTOTAL ANNUAL COST ESTIMATE
***PRESENT WORTH OF ANNUAL COST ESTIMATE
Total Price
48,000.
48,000.
5841
1
20
80
12
SamplesEachL.S.
Well
Samples
1,000 Gal.
Months
$ 500.00500.00
3,000.00
2,000.00
1,000.00
1.80
500.00
$ 29,000.2,000.3,000.
2,000.
20,000.
144.
6,000.
$ 62,144.
$567,630.
* Physical testing of cut-off wall to be carried out for first five years only.** Reduces to $42,144. after five years.*** Based on a six percent net discount rate for a 20 year operation period.
L
TABLE A.4 (cont'd)
PHYSICAL CONTAINMENT OF FMC LANDS
SUMMARY OF COST
Estimated UnitItem Description Quantity Unit Price Total Price
TOTAL ESTIMATED CAPITAL CONSTRUCTION COST $5,197,945.
Estimated Operation, Maintenance and Monitoring Cost:a) Capital Cost $ 48,000.b) Present Worth of Annual Cost $567,630.
TOTAL ESTIMATED OPERATION, MAINTENANCE AND MONITORING COST $ 615,630.
TOTAL REMEDIAL ALTERNATIVE COST $5,813,575.
LI
TABLE A.5
HYDRAULIC CONTAINMENT OF FMC LANDS
Item DescriptionEstimatedQuantity Unit
UnitPrice Total Price
Capital Construction Cost Estimate
1.- Mobilization and demobilization
2. Secure easement on BNR property
3. Install extraction wells to 135'depth with discharge to adjacentmanhole
4. Disposal of contaminated drillcuttings from extraction wellinstallation
Supply and place gravel foraccess road to treatmentfacility
0.2
1
Construct gravity main pipingsystem to collect extractedgroundwater (including trenchexcavation, bedding, pipe material,manholes, backfill, and electricalcable for well pumps) 950
Install 20,000 gallon bufferingtank 1
Construct building for collectioncenter and treatment system(including power supply, pumpingand piping from buffering tankto treatment system, piping fromtreatment system to storm sewerdischarge, and flow meter) 1
Supply and install complete airstripping treatment system 1
L.S.
Acres
Each
L.S.
L.F.
$12,000.00
72,000.00
14,400.00
10,000.00
72.00
L.S. 24,000.00
L.S. 46,800.00
L.S. 60,000.00
$ 12,000.
14,400.
86,400.
10,000.
68,400.
24,000.
500 L.F. 4.50
46,800.
60,000.
2,250.
continued..
TABLE A.5 (cont'd)
HYDRAULIC CONTAINMENT OF FMC LANDS
Item DescriptionEstimatedQuantity Unit
UnitPrice Total Price
10. Site restoration
11. Health and Safety (includingpersonnel protective equipmentand air monitoring)
L.S.
L.S.
9,000.00
18,000.00
SUBTOTAL
Contingency(25% of SUBTOTAL)
Engineering & site Supervision(15% Of SUBTOTAL)
TOTAL ESTIMATED CAPITALCONSTRUCTION COST
9,000.
18,000.
$351,250.
87,815.
52,690.
$491,755.
continued.
L
UnitPrice
TABLE A.5 (cont'd)
HYDRAULIC CONTAINMENT OF FMC LANDS
EstimatedItem Description Quantity Unit ____
Operation, Maintenance and Monitoring Capital Cost Estimate
1. Install new groundwatermonitoring wells downgradientof site for long termmonitoring (135' deep) 6 Each $ 8,000.00
SUBTOTAL CAPITAL COST ESTIMATE
Operation, Maintenance and Monitoring Annual Cost Estimate
Hydraulic containment system:a) pumping equipment and well
maintenance 6 Wellsb) operation cost of system
(eg. power) 1 L.S.c) disposal of collected
extracted groundwater(assumed on-site airstripping and disposal)to river 50,000 1,000 Gal.
d) analytical sampling oftreated effluent, 2 samplesper month 24 Samples
e) miscellaneous maintenanceand inspections 12 Months
SUBTOTAL ANNUAL COST ESTIMATE
*PRESENT WORTH OF ANNUAL COST ESTIMATE
2,000.00
1,000.00
0.25
500.00
500.00
Total Price
$ 48,000.
$ 48,000.
1 . Groundwatera)
b)c)
12 wellsyear , oneincludingsamplingreporting
monitoring program:sampled 4 times persample per wellQVQCeventsand administration
5841
SamplesEachL.S.
$ 500.500.
3,000.
000000
$ 2923
,000.,000.,000.
12,000.
1,000.
12,500.
12,000.
6,000.
$ 77.500.
$611,245.
Based on a six percent net discount rate for an 11 year operation period.
TABLE A.5 (cont'd)
HYDRAULIC CONTAINMENT OF FMC LANDS
SUMMARY OF COST
Estimated UnitItem Description Quantity Unit Price Total Price
TOTAL ESTIMATED CAPITAL CONSTRUCTION COST $ 491,755.
Estimated Operation, Maintenance and Monitoring Cost:a) Capital Cost $ 48,000.b) Present Worth of Annual Cost $611,245.
TOTAL ESTIMATED OPERATION, MAINTENANCE AND MONITORING COST $ 659,245.
TOTAL REMEDIAL ALTERNATIVE COST $1,151,000.
APPENDIX B
DETAILED RELATIVE COST ESTIMATES OF
PREFERRED REMEDIAL ACTION ALTERNATIVE
TABLE B.1
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE10~6 RISK LEVEL AT SITE BOUNDARY
Estimated UnitItem Description Quantity Unit Price Total Price
This alternative requires hydraulic containment of the FMC lands and the BNR lands,treatment by on-site air stripping, and discharge of treated effluent to the on-sitestorm sewer system.
Capital Construction Cost Estimate
1.
2.
3.
Mobilization and demobilization
Secure easement on BNR property
Install extraction wells withdischarge to proposed collectionsystem manhole:a) 35' depthb) 135' depth
1
0.4
26
L.S.
Acres
EachEach
$18,000.00
72,000.00
10,560.0014,400.00
$ 18,000.
28,800.
21,120.86,400.
4. Disposal of contaminated drillcuttings from well drillingoperation 1 L.S. 10,000.00 10,000.
5. Construct gravity main pipingsystem to collect extractedgroundwater (including trenchexcavation, bedding, pipematerials, manholes and electricalcable for well pumps) 1,120 L.F. 72.00 80,640.
6. Construct building for groundwaterpumping and treatment system(including power supply, pumpingand piping from buffering tank totreatment system, piping fromtreatment system to storm sewerdischarge, and flow meter) 1 L.S. 46,800.00 46,800.
7. Construct 20,000 gallongroundwater buffering tank 1 L.S. 25,000.00 25,000.
continued....
TABLE B.1 (cont'd)
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE10"6 RISK LEVEL AT SITE BOUNDARY
FMC CORPORATIONMINNEAPOLIS, MINNESOTA
Item DescriptionEstimatedQuantity Unit
UnitPrice Extension
8. Supply and install complete airstripping treatment system fordesign flow rate of 125 GPMand trichloroethylene removalefficiency of 98%
9. Construct access road withgravel surface to treatmentfacility and security fencearound treatment facility
10. Site restoration
11. Health and Safety during wellinstallation (including personnelprotective equipment and airmonitoring)
L.S. 55,000.00
L.S.
L.S.
L.S.
7,500.00
8,700.00
24,000.00
SUBTOTAL
Contingency(25% of SUBTOTAL)
Engineering & Site Supervision(15% of SUBTOTAL)
TOTAL ESTIMATED CAPITALCONSTRUCTION COST
55,000,
7,500,
8,700,
24,000.
$411,960.
102,990.
i
61,795.
$576,745.
continued....
TABLE B.1 (cont'd)
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE
10-6
RISK LEVEL AT SITE BOUNDARY
Item DescriptionEstimatedQuantity
Operation, Maintenance and Monitoring Capital Cost
1. Install new groundwatermonitoring wells downgradientof site for long term monitoringa) 135' deepb) 35' deep
SUBTOTAL
:66
UnitUnit Price
Estimate
Each $ 8,000.00Each 3,000.00
CAPITAL COST ESTIMATE
Operation, Maintenance and Monitoring Annual Cost
1.
2.
Groundwater monitoring program:a) 12 wells sampled 4 times per
year, one sample per wellincluding QA/QC
b) sampling eventsc) reporting and administration
Extraction and treatment system:a) pumping equipment and well
maintenanceb) utilities cost (eg. power)c) air stripping treatment
costsd) analytical sampling of
treated effluent, 2 samplesper month
e) miscellaneous maintenanceand inspections
SUBTOTAL ANNUAL COST ESTIMATE
*PRESENT WORTH OF ANNUAL COST
5841
61
50,000 1,
24
12
, FMC LANDS
ESTIMATE,
Estimate, FMC Lands
Samples $ 500.00Each 500.00L.S. 5,000.00
Wells 2,000.00L.S. 1,400.00
000 Gal. 0.25
Samples 500.00
Months 500.00
FMC LANDS
Total Price
$ 48,000.18,000.
$ 66,000.
$ 29,000.2,000.5,000.
12,000.1,400.
12,500.
12,000.
6,000.
$ 79,900.
$630,170.
continued....
TABLE B.1 (cont'd)
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE
10-6
RISK LEVEL AT SITE BOUNDARY
Item DescriptionEstimatedQuantity Unit
UnitPrice Total Price
Operation, Maintenance and Monitoring Annual Cost Estimate, BNR Lands
1. Groundwater monitoring program:a) 6 wells sampled 4 times per
year, one sample per wellincluding QA/QC 30 Samples $ 500.00
b) sampling events 4 Each 500.00c) reporting and administration
included under FMC lands
$ 15,000.2,000.
2. Extraction and treatment system:a) pumping equipment and well
maintenanceb) utilities cost (eg. power)c) air stripping treatment
costs 16,000
SUBTOTAL ANNUAL COST ESTIMATE, FMC LANDS
21
0
WellsL.S.
1,000 Gal.
1,800.00250.00
0.25
3,600.250.
4,000.
$ 24,850,
**PRESENT WORTH OF ANNUAL COST ESTIMATE, BNR LANDS $ 45,550.
* Based on a six percent net discount rate for an 11 year operation period.** Based on a six percent net discount rate for a 2 year operation period.
TABLE B.1 (cont'd)
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE
10~6 RISK LEVEL AT SITE BOUNDARY
SUMMARY OF COST
Estimated UnitItem Description Quantity Unit Price Total Price
TOTAL ESTIMATED CAPITAL CONSTRUCTION COST $ 576,745.
Estimated Operation, Maintenance and Monitoring Cost:a) Capital Cost $ 66,000.b) Present Worth of Annual Cost - FMC Lands $630,170.
- BNR Lands $ 45,550.
TOTAL ESTIMATED OPERATION, MAINTENANCE AND MONITORING COST $ 741,720.
TOTAL REMEDIAL ALTERNATIVE COST $1,318,465.
TABLE B.2
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE10~5 RISK LEVEL AT SITE BOUNDARY
Item DescriptionEstimatedQuantity Unit
UnitPrice Total Price
This alternative requires hydraulic containment of the FMC lands and the BNR lands/treatment by on-site air stripping, and discharge of treated effluent to the on-sitestorm sewer system.
Capital Construction Cost Estimate
1. Mobilization and demobilization
Secure easement on BNR property2.
3. Install extraction wells withdischarge to proposed collectionsystem manhole:a) 35' depthb) 135' depth
4. Disposal of contaminated drillcuttings from well drillingoperation
5. Construct gravity main pipingsystem to collect extractedgroundwater (including trenchexcavation, bedding, pipematerials, manholes and electricalcable for well pumps)
6. Construct building for groundwaterpumping and treatment system(including power supply, pumpingand piping from buffering tank totreatment system, piping fromtreatment system to storm sewerdischarge, and flow meter)
7. Construct 20,000 gallongroundwater buffering tank
1
0.4
26
1,120
L.S.
EachEach
L.S.
L.F.
L.S.
L.S.
$18,000.00
Acres 72,000.00
10,560.0014,400.00
10,000.00
72.00
46,800.00
25,000.00
18,000.
28,800.
21,120.86,400.
10,000.
80,640.
46,800.
25,000.
continued...
TABLE B.2 (cont'd)
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE10"5 RISK LEVEL AT SITE BOUNDARY
Item DescriptionEstimatedQuantity Unit
UnitPrice Total Price
10.
11.
Supply and install complete airstripping treatment system fordesign flow rate of 120 GPMand trichloroethylene removalefficiency of 98%
Construct access road withgravel surface to treatmentfacility and security fencearound treatment facility
Site restoration
Health and Safety during wellinstallation (includingpersonnel protectiveequipment and air monitoring)
L.S.
L.S.
L.S.
L.S.
55,000.00
7,500.00
8,700.00
24,000.00
SUBTOTAL
Contingency(25% Of SUBTOTAL)
Engineering & Site Supervision(15% of SUBTOTAL)
TOTAL ESTIMATED CAPITALCONSTRUCTION COST
55,000.
7,500.
8,700.
24,000.
$411,960.
102,990.
61,795.
$576,745.
continued....
L
TABLE B.2 (cont'd)
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE
10-5 RISK LEVEL AT SITE BOUNDARY
FMC CORPORATIONMINNEAPOLIS, MINNESOTA
ItemEstimated
Description Quantity
Operation, Maintenance and Monitoring Capital Cost
1. Install new groundwatermonitoring wells downgradientof site for long term monitoring:a) 135' deep 6b) 35' deep 6
UnitUnit Price
Estimate
Each $ 8,000.00Each 3,000.00
SUBTOTAL CAPITAL COST ESTIMATE
Operation, Maintenance and Monitoring Annual Cost
1.
2.
Groundwater monitoring program:a) 12 wells sampled 4 times per
year, one sample per wellincluding QA/QC 58
b) sampling events 4c) reporting and administration 1
Extraction and treatment system:a) pumping equipment and well
maintenance 6b) utilities cost (eg. power) 1c) air stripping treatment
costs 48,000 1,d) analytical sampling of
treated effluent, 2 samplesper month 24
e) miscellaneous maintenanceand inspections 12
SUBTOTAL ANNUAL COST ESTIMATE, FMC LANDS
*PRESENT WORTH OF ANNUAL COST ESTIMATE,
Estimate, FMC Lands
Samples $ 500.00Each 500.00L.S. 5,000.00
Wells 2,000.00L.S. 1,400.00
000 Gal. 0.25
Samples 500.00
Months 500.00
FMC LANDS
Total Price
$ 48,000.18,000.
$ 66,000.
$ 29,000.2,000.5,000.
12,000.1,400.
12,000.
12,000.
6,000.
$ 79,400.
$626,230.
continued....
TABLE B.2 (cont'd)
L
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE
10-5
RISK LEVEL AT SITE BOUNDARY
Item DescriptionEstimatedQuantity Unit
UnitPrice
500.00500.00
Operation, Maintenance and Monitoring Annual Cost Estimate, BNR Lands
1 . Groundwater monitoring program :a) 6 wells sampled 4 times per
year, one sample per wellincluding QA/QC 30 Samples $
b) sampling events 4 Eachc) reporting and administration
included under FMC lands
2. Extraction and treatment system:a) pumping equipment and well
maintenance 2 Wellsb) utilities cost (eg. power) 1 L.S.c) air stripping treatment
costs 16,000 1,000 Gal.
SUBTOTAL ANNUAL COST ESTIMATE, FMC LANDS
**PRESENT WORTH OF ANNUAL COST ESTIMATE, BNR LANDS
1,800.00250.00
0.25
Total Price
$ 15,000.2,000.
3,600.250.
4,000.
$ 24,850.
$ 45,550.
* Based on a six percent net discount rate for an 11 year operation period,** Based on a six percent net discount rate for a 2 year operation period.
TABLE B.2 (cont'd)
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE
10~ RISK LEVEL AT SITE BOUNDARY
SUMMARY OF COST
Estimated UnitItem Description Quantity Unit Price Total Price
TOTAL ESTIMATED CAPITAL CONSTRUCTION COST $ 576,745.
Estimated Operation, Maintenance and Monitoring Cost:a) Capital Cost $ 66,000.b) Present Worth of Annual Cost - FMC Lands $626,230.
- BNR Lands $ 45,550.
TOTAL ESTIMATED OPERATION, MAINTENANCE AND MONITORING COST $ 737,780.
TOTAL REMEDIAL ALTERNATIVE COST $1,314,525.
1
L
TABLE B.3
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE10~6 RISK LEVEL AT COUNTY LANDS ___
Item DescriptionEstimatedQuantity Unit
UnitPrice Total Price
This alternative requires partial hydraulic containment of the FMC lands and the BNRlands, treatment by on-site air stripping, and discharge of treated effluent to theon-site storm sewer system.
Capital Construction Cost Estimate
1. Mobilization and demobilization
Secure easement on BNR property2.
3.
1
0.4
Install extraction wells withdischarge to proposed collectionsystem manhole:- 35' depth- 135' depth
4. Disposal of contaminated drillcuttings from well drillingoperation
5. Construct gravity main pipingsystem to collect extractedgroundwater {including trenchexcavation, bedding, pipematerials, manholes, and electricalcable for well pumps)
6. Construct building for groundwaterpumping and treatment system(including power supply, pumpingand piping from buffering tank totreatment system, piping fromtreatment system to storm sewerdischarge, and flow meter)
7. Construct 20,000 gallongroundwater buffering tank
26
1,120
L.S. $18,000.00
Acres 72,000.00
EachEach
L.S.
L.F.
L.S.
L.S.
10,560.0014,400.00
10,000.00
72.00
46,800.00
25,000.00
18,000.
28,800.
21,120.86,400.
10,000.
80,640.
46,800.
25,000.
continued....
TABLE B.3 (cont'd)
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE10~6 RISK LEVEL AT COUNTY LANDS
Item DescriptionEstimatedQuantity Unit
UnitPrice Extension
8. Supply and install complete airstripping treatment system fordesign flow rate of 120 GPMand trichloroethylene removalefficiency of 98%
9. Construct access road withgravel surface to treatmentfacility and security fencearound treatment facility
10. Site restoration
11. Health and Safety during wellinstallation (including personnelprotective equipment and airmonitoring)
L.S.
L.S.
L.S.
L.S.
55,000.00
7,500.00
8,700.00
24,000.00
SUBTOTAL
Contingency(25% of SUBTOTAL)
Engineering & Site Supervision(15% of SUBTOTAL)
TOTAL ESTIMATED CAPITALCONSTRUCTION COST
55,000.
7,500.
8,700.
24,000.
$411,960.
102,990.
61,795.
$576,745.
continued...
TABLE B.3 (cont'd)
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE
10-6 RISK LEVEL AT COUNTY LANDS
ItemEstimated
Description Quantity
Operation, Maintenance and Monitoring Capital Cost
1. Install new groundwatermonitoring wells downgradientof site for long term monitoring:a) 135' deep 6b) 35' deep 6
UnitUnit Price
Estimate
Each $ 8,000.00Each 3,000.00
SUBTOTAL CAPITAL COST ESTIMATE
Operation, Maintenance and Monitoring Annual Cost
1.
2.
Groundwater monitoring program:a) 12 wells sampled 4 times per
year, one sample per wellincluding QA/QC 58
b) sampling events 4c) reporting and administration 1
Extraction and treatment system:a) pumping equipment and well
maintenance 6b) utilities cost (eg. power) 1c) air stripping treatment
costs 48,000 1,d) analytical sampling of
treated effluent, 2 samplesper month 24
e) miscellaneous maintenanceand inspections 12
SUBTOTAL ANNUAL COST ESTIMATE, FMC LANDS
*PRESENT WORTH OF ANNUAL COST ESTIMATE,
Estimate, FMC Lands
Samples $ 500.00Each 500.00L.S. 5,000.00
Wells 2,000.00L.S. 1,400.00
000 Gal. 0.25
Samples 500.00
Months 500.00
FMC LANDS
Total Price
$ 48,000.18,000.
$ 66,000.
$ 29,000.2,000.5,000.
12,000.1,400.
12,000.
12,000.
6,000.
$ 79,400.
$626,230.
continued....
L
TABLE B.3 (cont'd)
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE
10-6
RISK LEVEL AT COUNTY LANDS
Item DescriptionEstimatedQuantity Unit
UnitPrice Total Price
Operation, Maintenance and Monitoring Annual Cost Estimate, BNR Lands
1. Groundwater monitoring program:a) 6 wells sampled 4 times per
year, one sample per wellincluding QA/QC 30 Samples $ 500.00 $ 15,000.
b) sampling events 4 Each 500.00 2,000.c) reporting and administration
included under FMC lands
2. Extraction and treatment system:a) pumping equipment and well
maintenance 2 Wells 1,800.00 3,600.b) utilities cost (eg. power) 1 L.S. 250.00 250.c) air stripping treatment
costs 16,100 1,000 Gal. 0.25 4/000.
SUBTOTAL ANNUAL COST ESTIMATE, FMC LANDS $ 24,850.
**PRESENT WORTH OF ANNUAL COST ESTIMATE, BNR LANDS $45,550.
* Based on a six percent net discount rate for an 11 year operation period.** Based on a six percent net discount rate for a 2 year operation period.
(f[
TABLE B.3 (cont'd)
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE
10~ RISK LEVEL AT COUNTY LANDS
SUMMARY OF COST
Estimated UnitItem Description Quantity Unit Price Total Price
TOTAL ESTIMATED CAPITAL CONSTRUCTION COST $ 576,745.
Estimated Operation, Maintenance and Monitoring Cost:a) Capital Cost $ 66,000.b) Present Worth of Annual Cost - FMC Lands $626,230.
- BNR Lands $ 45,550.
TOTAL ESTIMATED OPERATION, MAINTENANCE AND MONITORING COST $ 737,780.
TOTAL REMEDIAL ALTERNATIVE COST $1,314,525.
I
I
I
TABLE B.4
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE10-5 RISK LEVEL AT COUNTY LANDS
Item DescriptionEstimatedQuantity Unit
UnitPrice Total Price
This alternative requires partial hydraulic containment of the FMC lands and the BNRlands, treatment by on-site air stripping, and discharge of treated effluent to theon-site storm sewer system.
Capital Construction Cost Estimate
1.
2.
3.
Mobilization and demobilization
Secure easement on BNR property
Install extraction wells withdischarge to proposed collectionsystem manhole :- 35' depth- 135' depth
1
0.4
26
L.S.
Acres
EachEach
$18,000.00
72,000.00
10,560.0014,400.00
$ 18,000
28,800
21,12086,400
4. Disposal of contaminated drillcuttings from well drillingoperation
5. Construct gravity main pipingsystem to collect extractedgroundwater (including trenchexcavation, bedding, pipematerials, manholes, and electricalcable for well pumps)
6. Construct building for groundwaterpumping and treatment system(including power supply, pumpingand piping from buffering tank totreatment system, piping fromtreatment system to storm sewerdischarge, and flow meter)
7. Construct 20,000 gallongroundwater buffering tank
1,120
L.S.
L.F.
L.S.
L.S.
10,000.00
72.00
46,800.00
25,000.00
10,000.
80,640.
46,800.
25,000.
continued..
i
I
I
TABLE B.4 (cont'd)
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE10-5 RJSK LEVEL AT COUNTY LANDS
Estimated UnitItem Description Quantity Unit Price Total Price
8. Supply and install complete airstripping treatment system fordesign flow rate of 75 GPMand trichloroethylene removalefficiency of 99% 1 L.S. 55,000.00 55,000.
9. Construct access road withgravel surface to treatmentfacility and security fencearound treatment facility 1 L.S. 7,500.00 7,500.
10. Site restoration 1 L.S. 8,700.00 8,700.
11. Health and Safety during wellinstallation (including personnelprotective equipment and airmonitoring) 1 L.S. 24,000.00 24,000.
SUBTOTAL $411,960.
Contingency(25% of SUBTOTAL) 102,990.
Engineering & Site Supervision(15% of SUBTOTAL) 61,795.
TOTAL ESTIMATED CAPITAL $576,745.CONSTRUCTION COST _______
continued....
TABLE B.4 (cont'd)
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE
10-5
RISK LEVEL AT COUNTY LANDS
ItemEstimated
Description Quantity
Operation, Maintenance and Monitoring Capital Cost
1. Install new groundwatermonitoring wells downgradientof site for long term monitoring:a) 135' deep 6b) 35' deep 6
UnitUnit Price
Estimate
Each $ 8,000.00Each 3,000.00
SUBTOTAL CAPITAL COST ESTIMATE
Operation, Maintenance and Monitoring Annual Cost
1.
2.
Groundwater monitoring program:a) 12 wells sampled 4 times per
year, one sample per wellincluding QA/QC 58
b) sampling events 4c) reporting and administration 1
Extraction and treatment system:a) pumping equipment and well
maintenance 6b) utilities cost (eg. power) 1c) air stripping treatment
costs 24,000 1,d) analytical sampling of
treated effluent, 2 samplesper month 24
e) miscellaneous maintenanceand inspections 12
SUBTOTAL ANNUAL COST ESTIMATE, FMC LANDS
*PRESENT WORTH OF ANNUAL COST ESTIMATE,
Estimate, FMC Lands
Samples $ 500.00Each 500.00L.S. 5,000.00
Wells 2,000.00L.S. 1,000.00
000 Gal. 0.25
Samples 500.00
Months 500 . 00
FMC LANDS
Total Price
$ 48,000.18,000.
$ 66,000.
$ 29,000.2,000.5,000.
12,000.1,000.
6,000.
12,000.
6,000.
$ 73,000.
$575,750.
continued....
TABLE B.4 (cont'd)
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE
10-5
RISK LEVEL AT COUNTY LANDS
Item DescriptionEstimatedQuantity Unit
UnitPrice Total Price
Operation, Maintenance and Monitoring Annual Cost Estimate, BNR Lands
1. Groundwater monitoring program:a) 6 wells sampled 4 times per
year, one sample per wellincluding QA/QC 30 Samples $ 500.00 $ 15,000.
b) sampling events 4 Each 500.00 2,000.c) reporting and administration
included under FMC lands
2. Extraction and treatment system:a) pumping equipment and well
maintenance 2 Wells 1,800.00 3,600.b) utilities cost (eg. power) 1 L.S. 250.00 250.c) air stripping treatment
costs 16,000 1,000 Gal. 0.25 4,000.
SUBTOTAL ANNUAL COST ESTIMATE, FMC LANDS
**PRESENT WORTH OF ANNUAL COST ESTIMATE, BNR LANDS $ 45,550.
* Based on a six percent net discount rate for an 11 year operation period.** Based on a six percent net discount rate for a 2 year operation period.
L
TABLE B.4 (cont'd)
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE
10~ RISK LEVEL AT COUNTY LANDS
SUMMARY OF COST
Estimated UnitItem Description Quantity Unit Price Total Price
TOTAL ESTIMATED CAPITAL CONSTRUCTION COST $ 576,745.
Estimated Operation, Maintenance and Monitoring Cost:a) Capital Cost $ 66,000.b) Present Worth of Annual Cost - FMC Lands $575,750.
- BNR Lands $ 45,550.
TOTAL ESTIMATED OPERATION, MAINTENANCE AND MONITORING COST $ 687,310.
TOTAL REMEDIAL ALTERNATIVE COST $1,264,045.
I
I
I
TABLE B.5
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE10-6 RISK LEVEL AT RIVER SHORELINE
Item DescriptionEstimatedQuantity Unit
UnitPrice Total Price
This alternative requires partial hydraulic containment of the FMC lands and the BNRlands, treatment by on-site air stripping, and discharge of treated effluent to theon-site storm sewer system.
Capital Construction Cost Estimate
1. Mobilization and demobilization
Secure easement on BNR property2.
3.
1
0.4
Install extraction wells withdischarge to proposed collectionsystem manhole:- 35' depth- 135' depth
4. Disposal of contaminated drillcuttings from well drillingoperation
5. Construct gravity main pipingsystem to collect extractedgroundwater (including trenchexcavation, bedding, pipematerials, manholes, and electricalcable for well pumps)
6. Construct building for groundwaterpumping and treatment system(including power supply, pumpingand piping from buffering tank totreatment system, piping fromtreatment system to storm sewerdischarge, and flow meter)
7. Construct 20,000 gallongroundwater buffering tank
26
1,120
L.S.
Acres
EachEach
L.S.
L.F.
L.S.
L.S.
$18,000.00
72,000.00
10,560.0014,400.00
10,000.00
72.00
46,800.00
25,000.00
18,000.
28,800.
21,120.86,400.
10,000.
80,640.
46,800.
25,000.
continued....
TABLE B.5 (cont'd)
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE10~6 RISK LEVEL AT RIVER SHORELINE
Estimated UnitItem Description Quantity Unit Price Total Price
8. Supply and install complete airstripping treatment system fordesign flow rate of 75 GPMand trichloroethylene removalefficiency of 99% 1 L.S. 55,000.00 55,000.
9. Construct access road withgravel surface to treatmentfacility and security fencearound treatment facility 1 L.S. 7,500.00 7,500.
10. Site restoration 1 L.S. 8,700.00 8,700.
11. Health and Safety during wellinstallation (including personnelprotective equipment andair monitoring) 1 L.S. 24,000.00 24,000.
SUBTOTAL $411,960.
Contingency(25% of SUBTOTAL) 102,990.
Engineering & Site Supervision(15% of SUBTOTAL) 61,795.
TOTAL ESTIMATED CAPITAL $576,745.CONSTRUCTION COST
continued....
TABLE B.5 (cont'd)
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE
10-6
RISK LEVEL AT RIVER SHORELINE
Item DescriptionEstimatedQuantity
Operation, Maintenance and Monitoring Capital Cost
1. Install new groundwatermonitoring wells downgradientof site for long term monitoringa) 135' deepb) 35' deep
SUBTOTAL
••
66
UnitUnit Price
Estimate
Each $ 8,000.00Each 3,000.00
CAPITAL COST ESTIMATE
Operation, Maintenance and Monitoring Annual Cost
1.
2.
Groundwater monitoring program:a) 12 wells sampled 4 times per
year, one sample per wellincluding QA/QC
b) sampling eventsc) reporting and administration
Extraction and treatment system:a) pumping equipment and well
maintenanceb) utilities cost (eg. power)c) air stripping treatment
costsd) analytical sampling of
treated effluent , 2 samplesper month
e) miscellaneous maintenanceand inspections
SUBTOTAL ANNUAL COST ESTIMATE
*PRESENT WORTH OF ANNUAL COST
5841
61
24,000 1,
24
12
, FMC LANDS
ESTIMATE,
Estimate, FMC Lands
Samples $ 500.00Each 500.00L.S. 5,000.00
Wells 2,000.00L.S. 1,000.00
000 Gal. 0.25
Samples 500.00
Months 500.00
FMC LANDS
Total Price
$ 48,000.18,000.
$ 66,000.
$ 29,000.2,000.5,000.
12,000.1,000.
6,000.
12,000.
6,000.
$ 73,000.
$575,750.
continued....
TABLE B.5 (cont'd)
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE
10-6 RISK LEVEL AT RIVER SHORELINE
Item DescriptionEstimatedQuantity Unit
UnitPrice Total Price
Operation, Maintenance and Monitoring Annual Cost Estimate, BNR Lands
1. Groundwater monitoring program:a) 6 wells sampled 4 times per
year, one sample per wellincluding QA/QC 30 Samples S 500.00 $ 15,000.
b) sampling events 4 Each 500.00 2,000.c) reporting and administration
included under FMC lands
2. Extraction and treatment system:a) pumping equipment and well
maintenance 2 Wells 1,800.00 3,600.b) utilities cost (eg. power) 1 L.S. 250.00 250.c) air stripping treatment
costs 16,000 1,000 Gal. 0.25 4,000.
SUBTOTAL ANNUAL COST ESTIMATE, FMC LANDS $ 24,850.
**PRESENT WORTH OF ANNUAL COST ESTIMATE, BNR LANDS $ 45,550.
* Based on a six percent net discount rate for an 11 year operation period.** Based on a six percent net discount rate for a 2 year operation period.
TABLE B.5 (cont'd)
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE
10~6 RISK LEVEL AT RIVER SHORELINE
SUMMARY OF COST
Estimated UnitItem Description Quantity Unit Price Total Price
TOTAL ESTIMATED CAPITAL CONSTRUCTION COST $ 576,745.
Estimated Operation, Maintenance and Monitoring Cost:a) Capital Cost $ 66,000.b) Present Worth of Annual Cost - FMC Lands $575,750.
- BNR Lands $ 45,550.
TOTAL ESTIMATED OPERATION, MAINTENANCE AND MONITORING COST $ 687,300.
TOTAL REMEDIAL ALTERNATIVE COST $1,264,045.
TABLE B.6
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE10~5 RISK LEVEL AT RIVER SHORELINE
Item DescriptionEstimatedQuantity Unit
UnitPrice Total Price
This alternative requires partial hydraulic containment of the BNR lands only, withdirect discharge to on-site sanitary sewer system. No on-site treatment is provided.
Capital Construction Cost Estimate
1. Mobilization and demobilization
Secure easement on BNR property2.
3.
4.
Install extraction wells to 35'depth with discharge to proposedcollection system manhole
Disposal of contaminated drillcuttings from well drillingoperation
5. Construct gravity main pipingsystem to collect extractedgroundwater (including trenchexcavation, bedding, pipematerials, manholes, and electricalcable for well pumps)
6. Construct pumphouse for groundwaterpumping (including powersupply, pumping equipment, pipingfrom collection system to pumphouse,and flow meter)
7. Construct gravity main frompumphouse to on-site sanitarysewer manhole
1
0.4
170
L.S. $ 9,000.00
Acres 72,000.00
Each
L.S.
L.F.
80
L.S.
L.F.
10,560.00
3,000.00
72.00
39,600.00
70.00
9,000.
28,800.
10,560.
3,000.
12,240.
39,600.
5,600.
continued....
TABLE B.6 (cont'd)
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE10~5 RISK LEVEL AT RIVER SHORELINE
Estimated UnitItem Description Quantity Unit Price Total Price
8. Construct access road withgravel surface to pumphouseand security fence aroundpumphouse 1 L.S. 7,500.00 7,500.
9. Site restoration 1 L.S. 3,500.00 3,500.
10. Health and Safety during wellinstallation (including personnelprotective equipment andair monitoring) 1 L.S. 12,000.00 12,000.
SUBTOTAL $131,800,
Contingency(25% of SUBTOTAL) 32,950.
Engineering & Site Supervision(15% of SUBTOTAL) 19,770.
TOTAL ESTIMATED CAPITAL $184,520,CONSTRUCTION COST
continued...
TABLE B.6 (cont'd)
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE
10 RISK LEVEL AT RIVER SHORELINE
Estimated UnitItem Description Quantity Unit Price Total price
Operation, Maintenance and Monitoring Capital Cost Estimate
1. Install new groundwatermonitoring wells downgradientof site for long term monitoring:a) 135' deep 6 Each $ 8,000.00 $ 48,000.b) 35' deep 6 Each 3,000.00 18,000.
SUBTOTAL CAPITAL COST ESTIMATE $ 66,000.
Operation, Maintenance and Monitoring Annual Cost Estimate, FMC Lands
1. Groundwater monitoring program:a) 12 wells sampled 4 times per
year, one sample per wellincluding QA/QC 58 Samples $ 500.00 $ 29,000.
b) sampling events 4 Each 500.00 2,000.c) reporting and administration 1 L.S. 3,000.00 3,000.
SUBTOTAL ANNUAL COST ESTIMATE, FMC LANDS $ 34,000.
*PRESENT WORTH OF ANNUAL COST ESTIMATE, FMC LANDS $389,980.
continued....
TABLE B.6 (cont'd)
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE
10~ RISK LEVEL AT RIVER SHORELINE
Item DescriptionEstimatedQuantity Unit
UnitPrice Total Price
Operation/ Maintenance and Monitoring Annual Cost Estimate, BNR Lands
Groundwater monitoring program:a) 6 wells sampled 4 times per
year, one sample per wellincluding QA/QC
b) sampling eventsc) reporting and administration
included under FMC lands
304
SamplesEach
500.00500.00
2. Extraction and disposal system:a) pumping equipment and well
maintenanceb) utilities cost (eg. power)c) disposal of collected
extracted groundwater(assumed disposal to POTW)
d) miscellaneous maintenanceand inspections
"PRESENT WORTH OP ANNUAL COST ESTIMATE, BNR LANDS
$ 15,000.2,000.
21
8,000 1,
12
BNR LANDS
WellsL.S.
000 Gal.
Months
1,800.00120.00
1.80
500.00
3,600.120.
14,400.
6,000.
$ 41,120.
$ 75,375.
* Based on a six percent net discount rate for an 20 year operation period.** Based on a six percent net discount rate for a 2 year operation period.
TABLE B.6 (cont'd)
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE
10~ RISK LEVEL AT RIVER SHORELINE
SUMMARY OF COST
Estimated UnitItem Description Quantity Unit Price Total Price
TOTAL ESTIMATED CAPITAL CONSTRUCTION COST $ 184,520.
Estimated Operation, Maintenance and Monitoring Cost:a) Capital Cost $ 66,000.b) Present Worth of Annual Cost - FMC Lands $389,980.
- BNR Lands $ 75,375.
TOTAL ESTIMATED OPERATION, MAINTENANCE AND MONITORING COST $ 531,355.
TOTAL REMEDIAL ALTERNATIVE COST $ 715,875.
TABLE B.7
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE10~6 RISK LEVEL AT RIVER INTAKE
Estimated UnitItem Description Quantity Unit Price Total Price
This alternative requires no hydraulic containment. Therefore, the initial capitalconstruction cost is zero.
Operation, Maintenance and Monitoring Capital Cost Estimate
1. Install new groundwatermonitoring wells downgradientof site for long term monitoring:a) 135' deep 6 Each $8,000.00 $ 48,000.b) 35' deep 6 Each 3,000.00 18,000.
SUB-TOTAL CAPITAL COST ESTIMATE $ 66,000.
Operation, Maintenance and Monitoring Annual Cost Estimate
1. Groundwater monitoring program:a) 18 wells sampled 4 times per
year, one sample per wellincluding QA/QC 88 Samples $ 500.00 $ 44,000.
b) sampling events 4 Each 1,000.00 4,000.c) reporting and administration 1 L.S. 5,000.00 ____5,000.
SUBTOTAL ANNUAL COST ESTIMATE
* PRESENT WORTH OF ANNUAL COST ESTIMATE $ 607,910.
* Based on a six percent net discount rate for a 20 year operation period.
L
TABLE B.7
HYDRAULIC CONTAINMENT REQUIRED TO ACHIEVE10~6 RISK LEVEL AT RIVER INTAKE
SUMMARY OF COST
TOTAL ESTIMATED CAPITAL CONSTRUCTION COST $ 0
Estimated Operation, Maintenance and Monitoring Cost:a) Capital Cost $ 66,000.b) Present Worth of Annual Cost $607,910.
TOTAL ESTIMATED OPERATION, MAINTENANCE AND MONITORING COST $ 673,910.
TOTAL REMEDIAL ALTERNATIVE COST $ 673,910.