focusing the power plan what did we learn from public comment? how do we incorporate it?
TRANSCRIPT
Focusing the Power Plan
What did we learn from public comment?
How do we incorporate it?
Northwest Power Planning Council
Issues for the Fifth Power Plan
• Issue paper identified 9 issues and asked– Are these the right issues?– Are they described accurately?– Are there others we should consider?– Where’s the priority?
Northwest Power Planning Council
1. Incentives for development of generation
-500
0
500
1000
1500
2000
MW
1994
1997
2000
2003
2006
2009
Net Capacity Additions
• 1990’s – low power prices, regulatory uncertainty, immature market -- power plant construction didn’t keep pace with load growth
• Price spikes of 2000-2001 resulted in new construction – most of which will be completed by 2003
• Then what? How do we assure adequate levels of development?
Northwest Power Planning Council
2. Increasing the price responsiveness of demand
• Most commodities, demand drops with higher prices – limiting how far prices rise
• Electricity – – Most demand does not see
effect of higher wholesale prices until after the fact
– Little discipline on prices
• How can we increase the price-responsiveness of demand in ways that are effective and acceptable?
Supply
Quantity
Who
lesa
l e P
r ic e
Non-price responsiveretail demand
Price responsiveretail demand
Pricemitigation
Northwest Power Planning Council
3. Sustaining economically-efficient investment inefficiency
• Investment in efficiency followed roller-coaster pattern– Low market prices – lower
than cost-effective investment– High prices – Crash programs
• Would sustained investment at cost-effective levels make sense?
• If so, how can region achieve it? Systems benefits charges, alternative rate setting …?
Northwest Utility Annual Northwest Utility Annual
Conservation SavingsConservation Savings
0
20
40
60
80
100
120
140
Sa
vin
gs
(a
MW
)
1990
1992
1994
1996
1998
2000
2002
2004
2006
2008
Approximate cost-Effective levels
*
* Estimated
Northwest Power Planning Council
4. Assessing supply adequacy and market performance
• 2000-2001 highlighted need for timely, accurate information to assess power supply adequacy and market performance
• Such information can now be difficult to obtain
• Council will assess data needed for planning and market assessment and make recommendations for obtaining that data
Northwest Power Planning Council
5. Fish operations and power
• 2000-2001 electricity crisis forced trade-offs that improved power supply at expense of fish
• Progress on preceding issues should reduce need for such trade-offs
• But conflicts likely to persist• Affects incentives for other resources
• Are there operational strategies and/or incentives to minimize impacts on fish recovery and mitigate impacts?
Northwest Power Planning Council
6. Transmission
• Transmission policy and planning critical to maintaining adequate, efficient, economic and reliable power system
• Separation of generation and transmission – Disaggregated decision-making
• • Regional Transmission Organization addressing issues, but will be several years before formed, if ever
• Council will address alternatives for transmission pricing, planning, and policy affecting Council’s mission
Northwest Power Planning Council
7. Value of/barriers toresource diversity
• Most new and planned generation natural gas fueled
• Would there be a value to a more diverse resource mix?
• Are there barriers to alternative generation and generation substitutes?
• If so, how could they be remedied – e.g. locational pricing, interconnection policies…?
Wind Other
Natural Gas
New and Planned NW Capacity*
*Operational, under-construction, permitted, permits pending and planned projects
Northwest Power Planning Council
8. Future role and Obligations of the BPA
• Many question Bonneville’s acquisition of new resources to serve growing loads in terms of:– Exposure to risk; effect on competitive
wholesale power market; obscuring real cost of serving growing demand
• Limiting acquisition authority means limiting ability to serve growing public agency loads
• Customer groups currently working on proposals for long term allocation of Bonneville’s existing power
• Council to evaluate pros and cons, make recommendation
Northwest Power Planning Council
9. Climate change risks to power system
• Climate change poses risks to the power system– Impact on hydro system
capability
– Impact of possible future climate change mitigation measures on power system costs, resource choices
• Plan will assess impacts and effect of strategies to address climate change impacts, e.g. carbon tax
Northwest Power Planning Council
Public comment
• Council received over 20 written comments• Took comment from 7 organizations at
meetings in Eugene and Boise• Power Committee held consultations with
Bonneville, utility groups, environmental groups, industrial customers, state regulators
• Individual members consulted with groups in their states
Northwest Power Planning Council
What did we hear?Don’t…
• Spend a lot of time on transmission EXCEPT– IRP for transmission – assess role of
conservation, demand management, distributed generation as alternatives to transmission investment
• Try to solve global climate change BUT– Should be considered as source of risk
Northwest Power Planning Council
1. Do…
• Describe and make sense of what happened over last few years –– The mix and tension between competition and
regulation
• Describe the current context, the situation in which utilities find themselves.
• Develop a vision for the future of the industry in the NW
• Explore how to get there
Northwest Power Planning Council
2. Do…
• Engage the Bonneville future issue– “Should be the centerpiece of the Plan”– Engage particularly on those issues central to
Council’s responsibilities• Conservation, fish and wildlife, potential effects on
the federal system
• The counter view – Don’t mess it up!
Northwest Power Planning Council
3. Do…
• Fish and Power
Industry – Evaluate cost-effectiveness of fish
measures
Fish advocates – Plan to reliably meet fish
requirements
?
Northwest Power Planning Council
4. Do…
• Produce the data – – Demand forecasts– Fuel price forecast– Electricity price forecasts– Resource characteristics, cost, potential– Development activity– Reliability assessment
• And do it regularly – not tied to plan cycle
Northwest Power Planning Council
The “Vision Thing”
• Where is it that this plan is trying to take the region?– The Act provides some direction, e.g.
• “Adequate, efficient, economic and reliable”;
• “Protect, mitigate and enhance”
• Priorities of the Act
– Should there be more?
• Important not to mix up ends with means
Northwest Power Planning Council
A “strawman” vision
• A Northwest power system that:– Provides electricity services at low cost – Provides equitable access to electricity services
throughout the region– Preserves low-cost hydro for the region– Uses hydro system efficiently– Provides electricity at low environmental impact– Supports recovery of threatened and endangered
species and Fish and Wildlife goals of Power Act
Northwest Power Planning Council
Example (cont.)
– Provides an acceptable level of power system adequacy and reliability, price stability
OR– Provides entities means of managing supply
and price risk– Implements least cost solutions to power and
transmission supply problems– Supports the development, demonstration and
deployment of promising new technologies
Northwest Power Planning Council
Vision (cont.)
• The dangers…– Can easily be pap doesn’t provide much
guidance– Can be polarizing
• The alternative…“When you come to a fork in the road, take it.” -- Yogi Berra
• Where to?
Northwest Power Planning Council
Future Industry Structure
Tying it together…
Vision (with Metrics)
FutureRoles,
ObligationsOf
BPA
Policy Environment:EPACTFERC RTOs, SMD,States Generation
Transmission
Efficiency
PriceResponsive
Demand
Fish,Environment
Recent History:What happened?Why?What did welearn?
Northwest Power Planning Council
It can’t be your father’s power plan
• World of the Power Act envisioned centralized planning and decisions, costs and risks borne by region’s consumers
• World of today and tomorrow – we can do centralized planning but – decision more likely resides with individual
actors • utilities, independent developers, end users…
– Same with costs and risks, differing risk tolerances
Northwest Power Planning Council
Analytically how…
Strategies• Resource
• Structural/Policy
Vision
Data• Resource characteristics, costs, potential, status, forecasts of demand, prices…
Scenarios
Factors outside our control • Physical/Economic e.g. water, loads, fuel prices• Policy, e.g. FERC and RTO, SMD, Climate
Analysis• Objective – measures of cost, risk, reliability• Qualitative – how well do strategies satisfy the non-quantifiable elements of the vision
Northwest Power Planning Council
Action Plan
• To effect preferred strategies…– Who needs to do– What– When