folly beach 1-yr post-construction monitoring report nicole elko, ph.d. september 8, 2015
TRANSCRIPT
Folly Beach 1-yr Post-Construction Monitoring Report
Nicole Elko, Ph.D.
September 8, 2015
Purpose
• Monitor sediment placed during 2014 federal renourishment– Planning, budgeting, and design
• Life-cycle analysis– How long will the project last?
• Meet USACE requirements
• USACE CONTRACT• Great Lakes Dredge & Dock
• 1.4 M cy sand• $30.7 M (15% City cost)
• January – June 2014
• MONITORING• August 2014• June 2015
2014 Federal Project recap
OCRM Monuments
USACE O&M Manual
Beach Nourishment Performance Evaluation
“periodic nourishment will be initiated upon a mutual agreement between the Government and the Local Sponsor based on the results of annual inspections and surveys. Periodic nourishment is deemed necessary when 25% of the length of the project storm berm has reached a 15 foot width at elevation 9.0 NGVD. At this time an approximate high tide beach width of 60-75 feet will exist.”
8.0 ft NAVD88
1. 8-ft berm & MHW width2. Volume remaining
PEL(Perpetual Easement Line)
200 ft wi-20 ftaverage+
65 ft wi-1.5 fttapers19%
5 of 26 profiles = 19%
Life Cycle Analysis8-ft berm & MHW
Shoreline Length
# of Monuments
Shoreline length/# of Monuments required to meet trigger
5798 ft 7 monuments
# of years until trigger is met 4 yrs 3 yrs
Year trigger will be met: 2019 2018
Rudimentary – based on only 2 points
SW-15 to -30 cy/ft
Volumetric Analysis
Total volume placed by 2014 project (cy) 1,400,000
Total volume in place: Aug 2014 (cy) 1,093,513
Volume change Aug 2014 - June 2015 (cy) -334,862
Volume remaining in June 2015 (cy) 758,652
Just over half of the placed volume remains
Life Cycle AnalysisVolume trends
4yrs
Life Cycle AnalysisVolume trends
3yrs
Life Cycle AnalysisVolume trends
0yrs
Summary of Volume Trends
• If trends continue, performance may be better than 3-4 yrs predicted
Sum
mary
of
Monit
ori
ng • Between Aug 2014 & Jun 2015
– 20 ft shoreline (MHW) erosion– “8-ft berm” eroded 1.5 ft– Lost 15-30 cy/ft volume
• As of June 2015, on average,– beach is 200 ft wide– “8-ft berm” is 65 ft wide– ~half nourishment volume remains
• USACE trigger– “8-ft berm” < 15ft at 5 of 26 profiles (19%)– Trigger will be met in 3 to 4 years (2018-19)
Folly Beach 1-yr Post-Construction Monitoring Report
Nicole Elko, Ph.D.
September 8, 2015