for personal use only · 1.refer marketable reserves note (p21), jorc probable reserve (rom) of...

21
For personal use only

Upload: others

Post on 25-Oct-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

 

For

per

sona

l use

onl

y

Quarterly Report for the period ended 31 December 2011 

ASX Code: SMR    1 

Quarterly Overview   The December quarter saw Stanmore Coal make significant progress as  results were  received and collated  from  the  extensive  exploration  drilling  and  project  development  activities  undertaken during 2011.   

The  results of  a Pre‐Feasibility  Study  (PFS)  at The Range were  released during  the quarter which demonstrated improved project economics and operating parameters.  Capital costs have remained within  expectations while  operating  costs  have  fallen  relative  to  the  previous  Conceptual Mining Study  (CMS). An  initial 94Mt Marketable Reserve1  statement was delivered  for  the deposit which underpins  the  company’s  application  for  5Mtpa  of  capacity  at  the  Wiggins  Island  Coal  Export Terminal (WICET) for this project.  

The Range PFS concluded that the mine life would extend to 26 years (up from 18 in the CMS) with a Net Present Value of $846m for the owner mining case.  Production of a high quality export thermal coal  is planned to commence  in 2015 with a ramp up to  the  full production rate of 5Mtpa shortly thereafter. 

During the quarter the company also defined an  initial 95Mt JORC  Inferred Resource at  its Belview underground coking coal project.  Early coal quality tests indicate that this coal will be a high quality coking coal with a CSN of 7‐8 and ash of 6‐7%.  Further drilling is planned to test the additional 205 – 345Mt Exploration Target2. 

An initial 25.7Mt of JORC Indicated Resource was defined at Mackenzie along with a 45% increase in the  Total  JORC  Indicated  +  Inferred  Resource  to  143.2Mt.    The  latest  results  of  an  ongoing  coal quality program indicate considerable variability in yield across the deposit and optimisation work is underway to address beneficiation and metallurgical  issues that have been  identified.   Drilling and test work will continue to investigate the most likely economic targets within the 27km long project area. 

Stanmore  Coal  continues  to work  closely with  the  key  infrastructure  providers  in  relation  to  our application for port and rail capacity. WICET Expansion Phase 1 (WEXP1) is at the short listing phase and  the  company  continues  to  interact  positively  with  the  WICET  team  about  our  potential allocation. We  understand  formal  allocation  decisions  for WEXP1  are  scheduled  to  be made  by WICET by the end of the first quarter of 2012.  Meanwhile the Surat Basin Rail (SBR) project linking The Range project to Gladstone ports including WICET took a big step forward with the Queensland Government approval of the development scheme for the Surat Basin Infrastructure Corridor State Development Area.  

At the end of the quarter Stanmore Coal completed a Placement to  institutional and sophisticated investors at $0.74 per share to raise $14.1 million. Subsequent to the end of the quarter a further $10 million equity raising was confirmed from via a placement and Share Purchase Plan offered to existing shareholders at $0.74 per share.   

1.Refer Marketable Reserves Note (p21), JORC Probable Reserve (ROM) of 117.5Mt 2. Refer Exploration Target Note (p21)  

For

per

sona

l use

onl

y

Quarterly Report for the period ended 31 December 2011 

ASX Code: SMR    2 

Project Snapshot  Project  Status 

The Range  • PFS completed confirming 5Mtpa thermal coal mine with improved economics and operating parameters  

• 94 Mt JORC Marketable Reserve1, 229 Mt Total JORC Resource (151 Mt Indicated + 78Mt Inferred Resource) 

• Additional Exploration Target2 of 60‐70Mt defined • Yield increased from 63% to 80% as up to 42% of ROM coal can bypass the washplant • Drilling will continue in the new year to further define additional coal intersections to 

the west of the proposed pit and increase the Resource category to Measured  • Environmental Impact Study (EIS) is progressing well  

 Mackenzie   • Upgraded 143Mt JORC Indicated +Inferred Resource, of which 25.7Mt is at Indicated 

Resource status • Recent results of an ongoing coal quality program indicate significant variability in 

yield across the full deposit ‐ optimisation work is underway to address beneficiation and metallurgical issues identified 

• Drilling and test work continues to investigate most likely economic targets within the 27km long project area  

Tennyson  • Drilling has intersected multiple coal seams at a variety of depths however land access issues have provided some delay to additional drilling 

• Drilling, coal quality testing and geological modeling continues into the new year with the aim of defining an initial JORC Inferred Resource by mid‐2012 

• Exploration Target2 of 220 – 290Mt  

Belview  • 95Mt Initial JORC Inferred Resource defined  • Further drilling planned to confirm additional Exploration Target2 of 205 – 345Mt  • Initial clean coal laboratory results confirm Belview has the potential to produce a 

high quality coking coal (CSN of 8 and ash of 6.3%) • Drilling intersected the 6m Gemini seam and up to 3.5m Aries seam at all five drill 

sites along the western edge of the tenement  

Kerlong  • Exploration drilling and seismic program commenced  • Further expansion area (EPC 2176) granted during the quarter 

Wiggins Island Coal Export Terminal Expansion Phase 1 (WEXP1) 

• WEXP1 due diligence and allocation process progressed • $5.1m bank guarantees relating to acquisition of FFFA priority rights now refunded 

post financial close of Stage 1 • Formal port allocations and signing of Capacity Commitment Deeds scheduled for end 

1Q 2012  

Surat Basin Rail  • The Surat Basin Infrastructure Corridor State Development Area which contains the Surat Basin Rail route gained Queensland Government approval during the quarter 

• This approval will allow land acquisition and commencement of construction from late 2012 

• SBR due diligence process is well advanced and draft Rail Access Policy has been issued to Stanmore Coal 

1.Refer Marketable Reserves Note (p21), JORC Probable Reserve (ROM) of 117.5Mt 2. Refer Exploration Target Note (p21) 

For

per

sona

l use

onl

y

Quarterly Report for the period ended 31 December 2011 

ASX Code: SMR    3 

Project Review The Range Project EPC 1112, 2030 / MLA 55001 Stanmore Coal 100% ownership  Location: Surat Basin – 24km south‐east of Wandoan Area: 96km2 

JORC Resource: Total of 229 Mt high quality open pit thermal coal (151Mt Indicated + 78 Inferred Resource) JORC Marketable Reserves: 94 Mt (Note:1)  During the quarter Stanmore Coal announced positive results from the Pre‐feasibility Study (PFS) for The Range with  improved project economics relative those  in the Conceptual Mining Study carried completed in late 2010.   

The Range Project  is  located 25 kilometres south east of  the Wandoan  township, within  the Surat Basin.  It  is well  located relative to existing key  infrastructure and the planned Surat Basin Rail  line, which will provide a rail link to the coal ports at Gladstone. 

The project remains on track for first coal in 2015 subject to statutory approvals being attained and completion of third party infrastructure.  

The PFS considered both owner mining and contractor mining options to produce 5 Mtpa of export coal over a mine life of 26 years, the results of which are summarised below.   

Capital and Operating Costs The development capital cost estimates are shown below for both owner and contract mining cases. The introduction of a conveyor system for transport of coal from the mine site to the Surat Basin Rail has  increased capital expenditure by some $50m above  the cost of  the haul road proposed  in  the Conceptual Mining Study.  However, the conveyor system will reduce operating costs and lower the risk of disruption due to potential seasonal flooding of the haul road. 

Development Capital ($Am)  Owner Mining  Contract Mining 

Coal Handling & Prep Plant  134  134 

Surface Infrastructure  120  123 

Conveyer & Rail Loop  113  113 

Mining  Fleet  to  first  coal (2015) 

101   

Contingency  37  37 

Total   505  407 

Figure 1: Capital Expenditure 

In the owner operator case a further $85m of mining equipment will be purchased during 2016 / 17 from operating cash flow to enable ramp up to full production.   

For

per

sona

l use

onl

y

Quarterly Report for the period ended 31 December 2011 

ASX Code: SMR    4 

The estimated operating costs are outlined below. Operating cost  savings  relative  to  the previous Conceptual Mining Study relate mainly to: 

the introduction of a conveyor transport system to the rail head 

the identification of extensive seams of clean coal which do not need washing which has led to the introduction of a bypass circuit. The effective yield for the project has increased from 63% to 80% with the ability to pass 42% of the ROM coal through the bypass circuit creating an improvement in the operating costs per tonne of product coal 

Operating Costs  (First 17 years of production)  

  Owner Mining  Contract Mining 

Mining & processing cost (FOR)  $A/t  39.4  49.8 

With Rail & port costs (FOB)3  $A/t  71.9  81.7 

3. Plus State Government Royalty estimated at $6.80. Including overheads. 

Figure 2: Operating Costs 

Project Economics The financial modelling conducted as part of the study indicates strongly positive net present values for  both  the  owner mining  case  and  the  contractor  case  under  a  range  of  long  term  coal  price assumptions. 

    Owner Mining  Contract Mining 

NPV ($Am)4    846  703 

4. Based on Credit Suisse long term forecasts (US$120/t FOB Newcastle thermal coal price and exchange rate of 0.85 AUD/USD) and a nominal discount rate of 10.0% (WACC)  

Figure 3: Net Present Value of The Range Project 

A number of additional shallow coal seams have been intersected in holes during sterilisation drilling to the west of the main deposit which appear to be in the lower Juandah sequence.  Further drilling and laboratory testing is ongoing to confirm the extent and quality of these seams, and an additional Exploration Target2 of 60 – 70 million tonnes has been established in relation to this area.  

Site Layout and Services The original two pit design from the Conceptual Mining Study has consolidated to a single larger pit due to the definition of additional shallow coal from drilling conducted during the year. The siting of the Coal Handling and Preparation Plant  (CHPP) and associated  infrastructure has been chosen  to minimise haul distances for ROM coal and avoid sterilising any potential future coal deposits. 

The main power requirements are from the CHPP and two 800 tonne class electric hydraulic shovels.  Demand  is estimated to be between 12MW to 14MW and power  is  likely to come from the mains grid  through Powerlink and Ergon.   Alternatives such as site based, gas  fired electricity generators are  also  being  investigated  and will  be  considered  if  they  provide  a  better  economic  outcome. 

For

per

sona

l use

onl

y

Quarterly Report for the period ended 31 December 2011 

ASX Code: SMR    5 

Stanmore Coal is well advanced in its negotiations with potential water providers with the two main options being nearby coal seam gas projects and Sunwater.   

 

 

Figure 4: Mine Industrial Area Layout 

 Mine Plan and Mining Methods The mining layout and sequence is shown in Figure 4 above.  The mining schedule adopted in the PFS is  similar  to  that used  for  the Conceptual Mining  Study  and  is based on  taking  advantage of  the shallowest depth area  to  the  top of coal and orienting  the mining such  that  it advances down dip wherever possible. The  relatively benign  seam  configuration  lends  itself  to a number of potential mining strategies.   

The PFS contemplates a truck and shovel operation using 800t class excavators and a fleet of 345t ultraclass rear dump trucks.  

Coal and interburden mining will be undertaken by a smaller fleet of 250t excavators, 150t class rear dump trucks and front end loaders. Coal extraction activities are designed to ensure selective clean coal production and maximise CHPP bypass potential. 

For

per

sona

l use

onl

y

Quarterly Report for the period ended 31 December 2011 

ASX Code: SMR    6 

The  initial  production  workforce  of  approximately  400  people  will  be  accommodated  at  a combination of local housing and village accommodation in Wandoan. 

The mine life has increased from 18 years in the Conceptual Mining Study to 26 years largely on the basis of the enhanced yield which  leads to a more optimal use of the deposit. The ROM strip ratio averages 6.7 bcm/t over the first 17 years of the mine life. 

 

 

Figure 5: Mining Sequence Snapshot – 2027 

Coal Handling and Preparation Plant The  proposed  Coal  Handling  and  Preparation  Plant  (CHPP)  has  been  designed  at  a  feed  rate  of 750tph to allow for campaign washing operations alternated with bypass operations. The front end crushing  and  screening  system has been designed  to  accommodate both  the washed  and bypass coal streams.  The CHPP will incorporate proven technologies – dense medium cyclones and spirals for product beneficiation.  

The raw ash content of  individual coal plies  is as  low as 3.7% (with an average of 20.5% air dried). Favourable raw ash  levels over much of the resource allows 42% of ROM coal to bypass the wash plant and be direct shipped.   This  leads to 53% of product coal being direct shipped without wash plant losses.  As a result of this the overall effective yield is 80% while the coal that is washed has a yield of 64%. 

For

per

sona

l use

onl

y

Quarterly Report for the period ended 31 December 2011 

ASX Code: SMR    7 

Coal Product Transport A 25 kilometre overland conveyor is proposed to a train load‐out facility and rail loop at the planned Surat Basin Rail (SBR) link, due for completion in 2015.  The preferred tie‐in point to the SBR is north of  the  town of Wandoan which eliminates any  reliance on  rail construction beyond  the Wandoan mine tie in point.  

Coal will be stockpiled at the rail head and then loaded to trains for railing to the Wiggins Island Coal Export  Terminal  (WICET)  at  Gladstone.  Stanmore  Coal  is  a  participant  in  the  WICET  Stage  2 expansion process and has acquired 7Mtpa of priority capacity rights in the terminal expansion.  

Coal Quality  Surat Basin coals are currently being exported in significant tonnages to the Asian utility market. The Range  coal  features good energy  content, ability  to produce  low ash,  low  levels of  trace element impurities  by  international  standards,  low  sulphur  and  nitrogen  contents  and  excellent  burnout characteristics.  

Favourable washability characteristics allow flexibility in choice of product ash with a likely product range of 10% ‐ 14.4% ash. 

 

The Range Coal Quality Summary  Product 1  Product 2  Product 3 

Ash    % ad 10.0  12.0  14.4 

Volatile Matter    % ad 41.6  40.7  39.8 

Fixed Carbon    % ad 40.4  39.3  37.7 

Total Sulphur    % ad 0.4  0.4  0.4 

Nitrogen (ult)    % daf 1.1%  1.1%  1.1% 

Total Moisture    %  14%  13.5%  13% 

Gross Calorific Value     kcal/kg ad 6,375  6,217  6,026 

Gross Calorific Value    kcal/kg daf 7,774  7,771  7,777 

 Figure 6: Coal Quality 

The PFS case is based on maximising energy recovery from the resource by bypassing as much coal as possible and washing the remainder to an ash content of 13.0% (air dried). This leads to a product ash of 14.4%  (air dried) as shown  in Product 3 above. The optimal ash and energy content for the deposit will be determined  in the Definitive Feasibility Study  in conjunction with further marketing analysis. 

The  introduction of bypass coal which avoids the wash plant also provides a beneficial  lowering of lower total moisture content in the product coal.    

For

per

sona

l use

onl

y

Quarterly Report for the period ended 31 December 2011 

ASX Code: SMR    8 

Further Optimisation Potential  A number of areas were identified for further investigation with the potential to further improve the project economics. These include: 

Further  refinement  of  the  mining  method  and  fleet  to  maximise  the  use  of  cheaper overburden dozer push  

Revisiting  the optimal product ash and bypass  coal  configuration. The Range  coal has  the potential to be washed to an ash level of between 10% and 17% at varying yields. Additional market analysis is planned to identify the optimal product ash specifications 

Potential for in pit crushing and conveying systems for waste transport and Wirtgen surface miner to remove coal and thin interburden materials 

Potential  for  shared  infrastructure  costs on  the overland  conveyor and at  the  rail  loadout area 

Possible cost savings and washplant efficiency improvements from new technologies such as the use of reflux classifiers 

Successful drilling  to  the west of  the current proposed pit has  the potential  to extend  the resource base and mine life  

These will be investigated during the Definitive Feasibility Study which will commence in early 2012. 

 

 

 

 

   

For

per

sona

l use

onl

y

Quarterly Report for the period ended 31 December 2011 

ASX Code: SMR    9 

Mackenzie Coking Coal Project EPC 2081 Stanmore Coal 100% ownership  Location : 30km west of Blackwater Area: 512km2 

JORC Inferred Resource: 143Mt coal (25.7Mt Indicated + 117.5Mt Inferred)  

Stanmore Coal completed an interim review of the Mackenzie deposit during the quarter which has resulted in the definition of the first 25.7 million tonnes (Mt) of JORC Indicated Resource and a 45% increase of the Total JORC Resource to 143.2 Mt (25.7Mt Indicated + 117.5Mt Inferred).   

  November 2011  August 2010 

Indicated Resource  25.7 Mt  ‐ 

Inferred Resource  117.5 Mt  99.0 Mt 

Total  143.2 Mt  99.0 Mt 

Figure 7: Coal Quality 

Since  the  August  2010  review  a  further  53  holes  have  been  drilled  and  the  current model  now includes a total of 80 holes.   The coal sequence comprises two main coal seams being the Leo and Aquarius seams within the Burngrove Formation. The seams strike in a general North South direction over an approximate 27km strike length, and dip towards the west at approximately 2 degrees. The main coal seams occur at depths of between 10 and 110 metres. 

This  year’s  laboratory  analysis program has  incorporated pre‐treatment procedures  that  simulate the  mine  handling  and  coal  preparation  techniques.  Results  from  this  year’s  program,  when compared with  data  from  2010  obtained  from  the  south  of  the  deposit,  indicate  a  lowering  of average yield5 to 26% over all seams and over the entire 27km  length of the deposit for the target 15‐17% ash coking product.   Variability occurs across  the deposit and between  the various  seams with yields ranging from 11% to 71%.   Work  is continuing to complete the  laboratory program and determine which combination of seams  is  likely to produce an economic coking coal product.   The higher ash  seams are also being  investigated  to determine whether  they  could  form a  secondary thermal coal product. Further work  is under way  to address beneficiation and metallurgical  issues identified with the aim of improving the yield.  

Yield Optimisation Investigations  

Work is continuing on alternative processing methods that may improve product ash and recovery. This  additional  analysis  includes  optimising  pre‐treatment methods  and  extended  analysis  of  the fines fraction with the aim of increasing fines recovery and maximising potential coal yields. Further investigation of fine material via supplementary processing techniques is currently being undertaken with the aim of improving product yield.  

5. Note all yields and ash results reported include fines and exclude mining losses and dilution   

For

per

sona

l use

onl

y

Quarterly Report for the period ended 31 December 2011 

ASX Code: SMR    10 

A  Conceptual Mining  Study  is  planned  upon  the  successful  completion  of  this  work  to  confirm potential discrete mining zones within the project area and investigate the project economics within these zones. 

For

per

sona

l use

onl

y

Quarterly Report for the period ended 31 December 2011 

ASX Code: SMR    11 

Tennyson Thermal / Coking Coal Project EPC 1168  Stanmore Coal 100% ownership  Location: adjacent to Emerald Area: 131km2 

Exploration Target2: 220‐290 Mt underground thermal and potential metallurgical coal  The proposed drilling program at Tennyson was reviewed during the quarter and will now consist of eight holes  that will allow  the calculation of an  initial  JORC Resource. This program was originally planned  for  the December quarter but was  impacted by delays  in  complying with  the new  State regulations regarding land access for exploration. Holes completed to date have intersected multiple coal  seams at a variety of depths with  the Aries  seam  thickness averaging 2.5 metres,  the Corvus seam 2.6 metres and the Liskeard seam 2.1 metres.   

Modelling of  results  indicates  that  the Aries seam subcrops at around 150 metres and dips  to  the east, south and southwest to a maximum depth of around 490 metres.  Historic quality testing of the Aries seam  in the project area points to a raw ash of between 10 to 15 percent and  indicates that this seam could support a low ash, low sulphur export quality thermal coal with specific energies of up to 6680 kcal/kg.  

   For

per

sona

l use

onl

y

Quarterly Report for the period ended 31 December 2011 

ASX Code: SMR    12 

Belview Coking Coal Project EPC 1114 Stanmore Coal 100% ownership  Location: 10km south‐east of Blackwater Area: 131km2 

JORC Inferred Resource: 95Mt Additional Exploration Target2: 205 – 345Mt underground prime coking coal   During the December quarter Stanmore Coal defined an  initial JORC  Inferred Resource of 95 Mt  in the Gemini seam of  the Rangal Coal Measures.   The Gemini coal seam was previously mined as a hard coking coal at BHP’s historical Leichhardt mine 4km to the west of Belview. The key seams that have been intersected by Stanmore Coal in the Belview lease are the Aries, Gemini, Orion and Pisces seams.   

A further exploration program is planned for 2012 to extend the Inferred Resource and address core recovery issues encountered in a number of the drill holes. To date the Inferred Resource has been calculated from the Gemini seam only, based on testing of the central three holes of the  initial six hole program  completed  in  the western margin of  the  tenement.   An  increase  to  the  initial  JORC Inferred Resource is anticipated on completion of further drilling.  

Seam  Mean Thickness 

(m) 

Maximium Thickness 

(m) 

Minimum Thickness 

(m) 

Number of Intersections 

JORC Inferred (Mt) 

Additional 

Exploration Target2 (Mt) 

Aries  2.2  3.1  1.1  6    80‐120 

Gemini  5.5  6.8  1.9  6  95  25‐65 

Orion  5.6  8.2  3.1  5    40‐60 

Pisces Upper 

3.0  3.2  2.8  5    40‐60 

Pisces Lower 

2.5  3.4  1.2  5    20‐40 

Total          95  205‐345 

Figure 8: Coal Seam Details (Borehole Intersections) 

Gemini Seam Coal Quality 

Coal quality test work from the three holes tested to date has determined that the Gemini Seam is capable  of  producing  a  dual  product  comprising  a  high  quality  hard  coking  and  a  low  ash,  high energy thermal coal.   

Raw crucible swell numbers typically range from 1.5 to 9 and average 3.8. Average raw ash of 13.4% and  raw  energy  of  7,260  kcal  /  kg  (air  dried) was  achieved.  Coal  rank  and  average  coal  quality appears at this stage to remain fairly consistent with increases in depth.  

For

per

sona

l use

onl

y

Quarterly Report for the period ended 31 December 2011 

ASX Code: SMR    13 

Initial  clean  coal  laboratory  test  results  for  the  central  three  holes  demonstrate  a  substantial improvement in coking properties from washing with a combined coking and thermal product yield5 of 90%.  

Figure 9. Gemini Seam Clean Coal Results (average across full 6m seam)    

 

(ad – air dried), (daf – dry ash free) 

Coking  properties  increase  towards  the  base  of  the  coal  seam.  Should  the  deposit  be  selectively mined for the lower 2.5m of the seam an enhanced coking coal is achieved as shown below.   

Figure 10. Coking Coal Comparison 

6. Source: GSQ 2003 

Washed Results 

  Primary Hard Coking Product 

Secondary Thermal / Weak Coking Product 

Yield2    45%  45% 

Ash  ad  7.0%  10% 

Volatile Matter 

ad  21.1%  20.7% 

Fixed Carbon 

ad  70.5%  67.9% 

CSN  ad  7  2 

Total Sulphur 

ad  0.40%  0.35% 

Specific Energy  

kcal/kg ad 

7,880  7,570 

Specific Energy  

Kcal/kg daf 

8,603  8,544 

    Belview Gemini Seam  Other Bowen Basin Hard Coking Coals6 

    Entire 6m seam 

Lower 2.5m of seam only 

Blackwater Mine 

Curragh Mine 

Cook Mine 

Ash  ad  7.0%  6.3%  8.0%  7.0%  6.0% 

Volatile Matter 

ad  21.1%  21.2%  27%  21‐23%  27.5% 

CSN  ad  7  8  6  7‐8  7.5 

Total Sulphur 

ad  0.4%  0.4%  0.5%  0.5‐0.6%  0.35% 

Specific Energy  

kcal/kg ad 

7,880  7,965  7,643    7,834 

For

per

sona

l use

onl

y

Quarterly Report for the period ended 31 December 2011 

ASX Code: SMR    14 

The clean coal composites above from the first three holes tested demonstrate that the Belview coal has attractive coking coal characteristics and compares well to other nearby hard coking coal mines in the Bowen Basin. 

Further  coking  tests are being  conducted  including petrographic analysis  to  confirm  the  coal  rank and other coking properties. 

Aries Seam Coal Quality 

Initial clean coal composite  results  from  the  first of  the Aries seam samples similarly demonstrate very  attractive  coking  coal  qualities  and  the  potential  to  optimise  yield  by  the  production  of  a secondary high energy thermal product. 

Figure 11. Aries Seam Washability Results    

 

(ad – air dried) 

 

The company is planning to commission a scoping study to identify the potential project economics at Belview using modern underground mining methods.  

Aries Seam    Primary Hard Coking Product 

Secondary Thermal Product 

Yield    36.8%  31.2% 

Ash  ad  9%  15.3% 

Volatile Matter 

ad  21.4%  21.3% 

Fixed Carbon 

ad  68.4%  62.1% 

CSN  ad  8  1.5 

Total Sulphur 

ad  0.5%  0.4% 

Specific Energy  

kcal/kg ad 

7,656  6,856 

For

per

sona

l use

onl

y

Quarterly Report for the period ended 31 December 2011 

ASX Code: SMR    15 

   

For

per

sona

l use

onl

y

Quarterly Report for the period ended 31 December 2011 

ASX Code: SMR    16 

Kerlong Coking Coal Project EPCs 1552, 1769 and 2176 Stanmore Coal 100% ownership  Location: 19km north‐east of Moranbah Area: 29km2 + 13km2 (under application) 

Target: superior underground PCI/coking coal  

Stanmore  Coal  is  targeting  high  quality  underground  coking/PCI  coal  at  the  Kerlong  Coking  Coal Project which is eight kilometres north of the rail line to Dalrymple Bay Coal Terminal. Target seams mined nearby  include Burton  (Peabody), South Walker Creek  (BHP Mitsubishi), Carborough Downs (Vale) and Coppabella (Macarthur Coal). 

The Leichhardt  seam presents  the main economic  target at Kerlong. Although no coal exploration drilling data  currently exist within  the Kerlong project area,  there  is evidence  in  the broader area around the Kerlong Project to suggest that the Leichhardt seam is laterally extensive and maintains a suitable target thickness (~4 – 11 metres) for an underground operation. 

An initial exploration program at Kerlong has commenced and this will continue into 2012.  A 10km long 2D seismic survey was completed  in early December 2011 and the  final  interpretation results are expected in early February 2012. 

Stanmore Coal has been granted EPC 2176 which is adjacent to EPC 1769.  

 

For

per

sona

l use

onl

y

Quarterly Report for the period ended 31 December 2011 

ASX Code: SMR    17 

New Cambria Project EPCs 1113, 2039, 2371 Stanmore Coal 100% ownership  Location: 20km east of Blackwater Area: 117km2 

Target: open pit Yarrabee style low‐volatiles PCI coal   

The New Cambria Project is targeting the up‐thrust Rangal Coal Measures which contain low‐volatile, low  to medium  ash  PCI  coal with  open  cut mining  potential.  High  energy  coal  has  been mined historically  at  the  adjoining  Excel  Colliery  and  the  project  is  located  adjacent  to  the  rail  line  to Gladstone. Coal Seam Gas (CSG) co‐development discussions have commenced.  A seismic program is planned for the first half of 2012 which will identify potential drilling targets. 

 

For

per

sona

l use

onl

y

Quarterly Report for the period ended 31 December 2011 

ASX Code: SMR    18 

Port and Rail  Wiggins Island Coal Export Terminal Expansion Phase 1 Stanmore Coal is a participant in the WICET Expansion Phase 1 (WEXP1) process which is scheduled to  provide  a  30Mtpa  capacity  expansion  at WICET  by  2015. WICET  is  now  moving  to  shortlist qualifying  parties  for WEXP1  in  advance  of  successful  participants  signing  Capacity  Commitment Deeds  (CCD’s), which  is currently scheduled  for the end of the  first quarter of 2012. The company continues to interact positively with the WICET team about our potential allocation in the port.  

Stanmore Coal previously acquired seven million tonnes per annum (Mtpa) of priority capacity rights at  the WICET.  The  acquisition  of  these  priority  rights  increases  the  likelihood  of  the  Company securing its requested port allocation in WEXP1.  

The  cost  of  the  7Mtpa  of  FFFA  priority  rights  to  Stanmore  Coal  was  $1.05m.  In  addition,  the Company agreed to take over the bank guarantees and  interest payments of the vendors (totalling $5.77m) that relate to the FFFA priority rights.   With  financial close of WICET Stage 1 achieved on 30th September 2011 the bank guarantees securing Stanmore’s priority rights were released on 4th November 2011. WICET Stage 1 construction is now underway.  

 Other Ports Stanmore Coal has previously entered  into conditional agreements to ship up to 12 million tonnes per annum (Mtpa) of coal through the proposed Dudgeon Point Coal Terminal (DPCT) from 2016.  

In addition, Stanmore Coal continues to review all infrastructure options including a number of other proposed ports in the Gladstone region.  

 Rail During  the  quarter  the  Surat  Basin  Rail  (SBR)  project  reached  an  important milestone with  the granting  of  Queensland  Government  approval  for  the  development  scheme  for  the  State Development Area which contains the route for the planned line which will link The Range project to the Ports of Gladstone including the WICET terminal.  

Stanmore  Coal  has  applied  for  five million  tonnes  of  capacity  on  the  SBR  to  deliver  high  quality export thermal coal from the proposed The Range project. 

Granting of this approval will now allow the SBR joint venture to move to compulsory acquisition of key  land  along  the  proposed  route  and  will  allow  commencement  and  ultimate  completion  of construction in time for delivery of first coal in 2015. 

The SBR due diligence process is well advanced and draft Rail Access Policy was issued to Stanmore Coal in December 2011 to commence the formal negotiations for access to the rail line.  

 

For

per

sona

l use

onl

y

Quarterly Report for the period ended 31 December 2011 

ASX Code: SMR    19 

Corporate  Completion of Capital Raising 

During  the December quarter  Stanmore Coal  successfully  raised $14.1 million  via  a placement of approximately 19.1 million ordinary shares to  institutional and sophisticated  investors at $0.74 per share (“Placement”). 

The  Placement  was  oversubscribed  and  received  strong  support  from  existing  institutional shareholders as well as a number of new investors.  

Net proceeds of the Placement will be predominantly applied to fund a definitive feasibility study at the  Range,  continuing  exploration  at  other  key  projects,  initial  stage  funding  of  port  and  rail infrastructure commitments and general working capital requirements. 

Stanmore  Coal  also  offered  eligible  shareholders  the  opportunity  to  participate  in  a  partially underwritten Share Purchase Plan (“SPP”) to raise up to a further $10 million at the same issue price. The SPP was well subscribed for and subsequent to the end of the quarter, the company announced that the full $10 million had been successfully raised. 

 Permit Applications –   

Project  Tenement Number  Tenement Name  Date of 

Application  Type 

Brown River  EPCA 1546  Brown River  7/08/2008  Primary   EPCA 2062  May Creek  17/02/2010  Primary   EPCA 2113  Brown River North  6/05/2010  Secondary   EPCA 2520  Brown River East  3/5/2011  Priority Carnarvon  EPCA 1630  Carnarvon  28/10/2008  Secondary Altamondt  EPCA 2177  Altamondt  2/08/2010  Priority 

 Mining Lease Applications  

Project  Tenement Number  Tenement Name  Date of 

Application  Status 

The Range  MLA 55001  The Range  3/11/2010  EIS advised  Other granted Stanmore Coal EPCs:  

• EPC 1545 & 1567 ‐ Ironpot Creek  • EPC 1687 – Theresa Creek – Granted 28/07/2011 • EPC 1627 – Ten Mile Creek – Granted 12/08/2011 • EPC 1804 ‐ Yamala North 

 Desktop studies on these EPC’s are underway in advance of site exploration programs.     

For

per

sona

l use

onl

y

Quarterly Report for the period ended 31 December 2011 

ASX Code: SMR    20 

Contacts  For further information, please contact:  Mr Nick Jorss  Managing Director 07 3238 1000 

Mr Andrew Barber Investor Relations Manager 07 3212 9216 0418 783 701  

 

Competent Persons Statement 

The  information  in this report relating to exploration results and coal resources  is based on  information compiled by Mr Wes Nichols who  is  a member  of  the  Australasian  Institute  of Mining  and Metallurgy  and  is  a  full  time  employee  of Stanmore  Coal.      Mr  Nichols  is  a  qualified  geologist  and  has  sufficient  experience  that  is  relevant  to  the  style  of mineralisation and type of deposit under consideration and to the activity which he is undertaking, to qualify as Competent Person as defined  in  the 2004 Edition of  the  JORC Code.     Mr Nichols consents  to  the  inclusion  in  this document of  the matters based on the information, in the form and context in which it appears. 

The information in this report relating to coal reserves is based on information compiled by Mr Richard Hoskings who is a full time employee of Minserve Pty Ltd.   Mr Hoskings is a mining engineer, a member of the Australian Institute of Mining and Metallurgy (AusIMM) and has the relevant experience (30+ years) in relation to the mineralisation being reported to qualify as a Competent Person as defined in the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (The JORC Code 2004 Edition)”.  Mr Hoskings consents to the inclusion in the report of the matters based on the information, in the form and context in which it appears 

Note 1: Marketable Reserves Note 

The Marketable Coal Reserves of 94Mt is derived from a JORC compliant run of mine (ROM) Coal Reserve of 117.5Mt based on a 14.8% ash product and predicted yield of 80%. 

Note 2: Exploration Target Note 

All statements as to exploration targets of Stanmore Coal and statements as to potential quality and grade are conceptual in nature. There has been  insufficient exploration undertaken  to date  to define a  coal  resource and  identification of  a resource will be  totally dependent on  the outcome of  further exploration. Any statement contained  in  this  report as  to exploration  results or exploration  targets has been made consistent with  the  requirements of  the Australasian code  for reporting of exploration results, mineral resources and ore reserves (JORC Code). 

About Stanmore Coal Limited (ASX code: SMR) 

Stanmore Coal  is a growth focused, pure play coal exploration and development company with a number of prospective coal projects and exploration areas within Queensland’s Bowen and Surat Basins. Stanmore Coal is focused on the creation of  shareholder  value  via  the  identification  and  development  of  coal  deposits, with  a  focus  on  the  prime  coal  bearing regions of the east coast of Australia.  

Stanmore Coal holds 100% interests in its seven coal project areas, covering over 1,080 km2 in total. These projects include significant deposits of open pit coking and thermal coal and are typically well located for export infrastructure.  

  Stanmore Coal Limited ACN 131 920 968 Phone: +61 (7) 3238 1000 | Fax: +61 (7) 3212 6250 Email: [email protected]| Web: www.stanmorecoal.com.au  Street address: Level 11, 10 Market Street, Brisbane QLD 4000 Postal address: GPO Box 2602, Brisbane QLD 4001 

For

per

sona

l use

onl

y