for pre-bid meeting presentation
TRANSCRIPT
PLANT FIBER OPTIC NETWORK
REPLACEMENT PROJECT CONTRACT NO. 4240
Mandatory Pre-Bid Meeting
February 26, 2015 (Thursday)
Meeting Objective
• General overview and introduction to the FOR Project
• Contract Documents and Addenda dictate
• Any bidder’s requests for clarifications/changes shall
be in writing via email to [email protected]
• Any clarifications/changes impacting the documents
will be issued as addenda
Agenda
• Introductions
• EchoWater Project Overview
• FOR Project Overview
• Owner Controlled Insurance Program (OCIP)
• Wage Requirements
• Proposed Products Form
• Site Access/Security
• Training
• Scheduling Requirements
• NTP
• Site Tour Logistics
Introductions
• Vick Kyotani – Program Manager
• Theresa Rearick – Project Manager
• Ronald Kwok – District Engineering
• CMID - Construction Manager
EchoWater Project Overview
• Site Preparation (SP)
• Flow Equalization Basins (FEQ)
• Disinfection Chemical Storage & Feed System (DCS)
• Nitrifying Sidestream Treatment (NST)
• RAS Pumping System (RAS)
• Building Relocations (Bufferlands)
• Main Electrical Switchgear Expansion (MESE)
• Fiber Optic Network Replacement (FOR)
• Biological Nutrient removal (BNR)
• Tertiary Treatment Facility (TTF)
Key EchoWater Project Milestones
Project Approval to
Advertise Bid Due Date
Construction
NTP
Complete Construction
(including start-up and
testing)
Site Preparation 12/10/14 2/10/15 3/12/15 9/15/16
Flow Equalization 12/10/14 2/5/15 3/11/15 2/28/18
Bufferlands Building 12/10/14 1/29/15 3/16/15 2/8/16
Plant Fiber Optic Cable Network
Replacement 2/11/15 3/19/15 4/8/15 1/22/16
Disinfection Chemical Storage 6/10/15 7/16/15 9/14/15 10/17/16
Return Activated Sludge Pumping 3/25/15 5/21/15 6/23/15 7/11/19
Nitrifying Sidestream Treatment 5/13/15 7/17/15 11/9/15 8/10/17
Main Electrical Substation
Expansion 5/13/15 6/18/15 7/22/15 2016
Biological Nutrient Removal/Primary
Effluent Pumping Station 10/28/15 2/5/16 4/16/16 12/20/20
Tertiary Treatment Facilities 7/24/17 11/22/17 1/18/18 11/9/22
FOR Project Overview
• Description of Work
• Storm Water Pollution Control
• Contractor and Subcontractor Qualifications
• Work Restrictions/Coordination
• Project Milestones/Liquidated Damages
• Available Support Documentation
• Addenda
FOR Description of Work • Five (5) main fiber optic panels, each housing multiple 144-fiber
termination subpanels
• Ten (10) 48-fiber termination panels at locations within the existing
facility
• Installation of 2-96 strand single mode fiber optic cables between the
5 main panels (5 segments)
• Installation of 48-strand single mode fiber optic cables to the remote
panels (10 segments)
• Installation of two replacement hybrid multimode/single mode fiber
optic cables
• Installation of jumper cables per Contract schedule
• Underground ductbank between the Maintenance and Administration
Buildings
• Installation of conduits and cable tray
• Installation of 5 Owner furnished Cisco switches
Storm Water Pollution Control
• Section 01 57 23
• Water Pollution Control
Plan (WPCP) required
• BMPs required
• Project will not require an
NOI, WDID, or use of the
State SMART system
Contractor & Subcontractor Qualifications
• Contractor Qualifications
– Spec Section 00 45 13 requires C-7 license
• Subcontractor Qualifications
– Spec Section 00 45 15 requires C-10 license
• Exception will be added by Addendum:
• Contractor can meet 00 45 15
• Subcontractor can meet 00 45 13
Work Restrictions/Coordination
• Spec Section 01 14 00 – Work Restrictions
– Milestones and Constraints
– Concurrent EchoWater Project Construction
• Flow Equalization Basins (FEQ)
• Site Preparation (SP)
• Bufferlands Building
• Disinfection Chemical Storage (DCS)
• Main Electrical Substation Expansion (MESE)
– Coordination with Plant Operations
Project Milestones/Liquidated Damages
Contract
Milestone Substantial Completion Date LD’s
1 November 1, 2015 $2,000 per day
2 January 22, 2016 $7,000 per day
Section 01 14 00 and Section 01 14 20
Warranty – 1 Year from Field Acceptance of ALL WORK.
Available Support Documentation
• Spec Section 00 21 13 – Instructions to Bidders
https://www.dropbox.com/sh/tp05cet7hoauhxp/AADPNz
oJADQMXTR_aqIUCYR0a?dl=0
o Drawing CAD files
o OCIP Procedures Manual
o Pre-Construction Schedule
Owner Controlled Insurance Program (OCIP)
• OCIP covers: – Workers’ Compensation, Employers’ Liability, General Liability and Excess
– District will provide Builder’s Risk and Contractor’s Pollution Liability
• OCIP does not cover: – Hazardous waste abatement contractors or companies without on-site
dedicated payroll
• All contractors are required to exclude insurance costs for coverages provided by Regional San
• OCIP Safety Program Key Requirements – OCIP Safety Manual, Specs Appendix A
• 6 ft. fall protection, Section 12
• Project Orientation, Section 1.11
• Drug Screening, Section 1.11 and 5.3
• Full-time dedicated safety manager required for GC, Section 1.3 and 1.5
• Subcontractors required to assign designated safety representative, Section 1.4 and 1.5
• Return to Work Program, Section 4.2
Wage Requirements
• Spec Section 00 21 13 – Instructions to Bidders
– Pursuant to Section 1770, and following, of the California
Labor Code, the Contractor shall pay not less than the
prevailing rate of per diem wages as determined by the
Director of the California Department of Industrial Relations.
– Copies of the prevailing rate of per diem wages are on file at
the office of the Sacramento County/Labor Compliance
Section
Proposed Products Form
• Spec section 00 43 33
lists equipment that
the contractor shall
identify the
manufacturer/ supplier
with the bid.
Site Access/Security Site Access:
Franklin
Blvd/Sims Rd
Entrance and
Main Gate
Security:
All onsite
Contractor and
Subcontractors
will be badged
Training
• Plant Orientation
• Safety
• Environmental
• PMWeb
– Submittals
– RFIs
– Access Requests
– Daily Reports
– Pay Requests
PMWeb
• Comprehensive web based project management system.
• Required for use by contractor, District, engineer, and CM personnel for construction management.
• District will supply program licensing, training and tech support.
• As PMWeb is used for transmission of all construction correspondence, RFIs, submittals, etc. it is strongly recommended that personnel authoring these be trained in the software.
Scheduling Requirements
• Spec Section 01 32 16 – Construction Progress
Schedule
• Pre-Construction Scheduling Conference within 5
calendar days after NTP
• Payment tied to schedule
NTP Schedule
• Bid Opening – March 19, 2015
• Approval to Award – April 8, 2015
• Documents Required for NTP
o Signed/Executed Agreement
o Bonds
o Insurance Certificates
• Contractor NTP – May 8, 2015
• Training & Enrollment in OCIP required for onsite work
• District Access Requests (01 14 16)
NTP Schedule
• Bid Documents – No pre-qualifications required
– Contract Allowances - 1 stated with preset $ Amount
• Bid Form (00 41 00)
• Bid Form – Stipulated Sum (Single-Prime Contract) (00 41 13)
• Bid Security Form (00 43 13)
• Proposed Products Form (00 43 33)
• Proposed Subcontractors Form (00 45 12)
• Bidder’s Information (00 45 12)
• Noncollusion Affidavit (00 45 19)
NTP Schedule
• Three apparent low bidders shall submit the following no
later than 4 pm on the third business day following bid
opening (00 41 00):
– Bidder’s Qualifications (00 45 13)
– Bidder’s Safety Performance (00 45 14)
– Bidder’s Subcontractor Qualifications (00 45 15)
– Iran Contracting Act Disclosure Form (00 45 41)
– Certification of Exclusion of OCIP Insurance Costs Form (00 73 16)
Site Visit Logistics
• Site Tour is part of Mandatory Pre-bid Meeting
• Stop 1: Administration Building
• Stop 2: PCC Annex
• Stop 3: ACC 1
• Stop 4: ACC 14
• Stop 5: Maintenance Building
• Stop 6: Return to Administration Building