for the expansion of lucknow airport in respect of ... · urdu is also widely spoken. lucknow is...
TRANSCRIPT
PRE-FEASIBILITY REPORT
For the Expansion of Lucknow Airport in
Respect of Construction of New Integrated
Terminal Building at Amausi, Lucknow,
Uttar Pradesh.
Environment Consultant:
Greencindia Consulting Private Limited,
NCR, Ghaziabad, UP(NABET/EIA/1013/034)
Project Proponent:
AIRPORTS AUTHORITY OF INDIA, LUCKNOW
Table of Content For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
Table of Contents
S. No. Details Page No.
E. Executive Summary E-I – E-VI
1. Introduction 1-1 - 1-8
1.1 Background 1-1
1.2 Project Proponent 1-2
1.3 Type of Project 1-3
1.4 Airport Sector Profile 1-3
1.5 Air Connectivity Pattern 1-4
1.6 Need of The Project 1-5
1.7 Employment Generation 1-7
1.8 Structure of The Report 1-7
2. Project Description 2-1 – 2-21
2.1. Introduction 2-1
2.2. Types of Project 2-1
2.3. Location & Linkage 2-1
2.4. Site Selection & Alternatives 2-2
2.5. Project Magnitude 2-4
2.6. Description of The Proposed Project 2-4
2.6.1 Civil Works: 2-4
2.6.2 Car Parking 2-5
2.6.3 Demolition Work: 2-6
2.7. Construction Material 2-6
2.8. Resource Optimization 2-7
2.8.1 Water Saving Practices And Reduction 2-7
2.8.2 Water Use Reduction 2-10
2.8.3 Domestic Use for 24 Hours 2-10
2.8.4. Water Conservation In Landscaping 2-11
2.8.5. Water Use During Construction 2-13
2.9. Water Requirement & Supply 2-14
2.9.1 Water Source & Demand 2-14
2.10. Wastewater Generation and Treatment 2-18
2.11. Power Requirement & Supply 2-19
2.12. Solid Waste Management 2-20
Table of Content For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
S. No. Details Page No.
2.13. Fire Safety 2-20
2.14. Electrical Systems 2-20
2.15. Noise and Vibration Controls 2-21
3. Site Analysis 3-1 – 3-8
3.1 Introduction 3-1
3.2 Location & Connectivity 3-1
3.3 Physiography 3-1
3.4 Hydrogeology 3-1
3.5 Ground Water Status 3-2
3.6 Land Ownership 3-2
3.7 Topography 3-2
3.8 Existing Land Use Pattern 3-3
3.9 Existing Infrastructure 3-3
3.10 Geology & Soil 3-3
3.11 Meteorology & Climatology 3-4
1.1.1. Climatic Condition (30-Years IMD Data) 3-4
3.12 Seismicity 3-6
3.13 Wind Hazard 3-7
3.14 Social Infrastructure 3-8
4. Planning Consideration 4-1 – 4-8
4.1 Introduction 4-1
4.2 Planning Concept 4-1
4.3 Existing Features of Lucknow Airport 4-2
4.3.1. Terminal Building 4-2
4.3.2. Runway Orientation 4-2
4.3.3. Runway Length 4-2
4.3.4. Runway Geometry 4-2
4.3.5. Taxiway 4-3
4.3.6. Apron 4-3
4.3.7. Isolation Bay 4-3
4.3.8. Pavement 4-3
4.3.9. Parking Space 4-4
4.3.10. DVOR 4-4
Table of Content For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
S. No. Details Page No.
4.3.11. Perimeter Road/ Boundary Wall 4-4
4.3.12. Security Watch Tower 4-4
4.3.13. Fire Station 4-4
4.4 Civil Works for Expansion 4-4
4.4.1. Passenger Terminal Building 4-4
4.4.2. Departure Area 4-5
4.4.3. Security Hold Area 4-5
4.4.4. Food & Beverage Area 4-5
4.4.5. Arrival Area/ Baggage Claim Area 4-5
4.4.6. Common Concourse Area 4-5
4.4.7. Parking Area 4-6
4.4.8. Dismantling Works 4-6
4.5 Miscellaneous Civil Works 4-6
4.5.1. Electrical and Mechanical Works 4-7
4.5.2. Airport System 4-7
4.5.3. Support Amenities 4-7
5. Proposed Infrastructure 5-1 – 5-5
5.1 The Plan 5-1
5.2 Details of Proposed Infrastructure 5-1
5.2.1 Passenger Terminal Building 5-1
5.2.2 Departure Area 5-2
5.2.3 Security Hold Area 5-2
5.2.4 Duty Free/ Retail Area 5-2
5.2.5 Food & Beverage Area 5-2
5.2.6 Arrival Area/ Baggage Claim Area 5-2
5.2.7 Common Concourse Area 5-3
5.2.8 Parking Facilities 5-3
5.2.9 Dismantling Works 5-3
5.2.10 Miscellaneous Civil Works 5-3
5.2.11 Electrical And Mechanical Works 5-4
5.2.12 Airport System 5-4
5.2.13 Support Amenities 5-5
6. Rehabilitation & Resettlement Plan 6-1 – 6-1
Table of Content For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
S. No. Details Page No.
6.1 Introduction 6-1
7. Project Schedule & Cost Estimates 7-1 – 7-3
7.1 Introduction 7-1
7.2 Quantities 7-1
7.3 Rates 7-1
7.4 Contingencies 7-2
7.5 Works Tax 7-2
7.6 Labour Cess 7-2
7.7 Service Tax on Construction Cost 7-2
7.8 Project Management Costs 7-2
7.9 Price Escalation / Variation 7-2
7.10 Costs not Included 7-2
7.11 Financial Analysis 7-2
8. Final Recommendations 8-1 – 8-2
Table of Content For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
List of Tables
Table No. Details Page No.
Table E 1: Details of Site Location E-ii
Table 1 1: Passenger handles at major airports in India (in millions) 1-4
Table 1 2: Aircraft Movements of Lucknow Airport 1-6
Table 1 3: Passengers Movements at Lucknow Airport 1-6
Table 1 4: Passengers Movements at Lucknow Airport 1-6
Table 1 5: Freight Details of Lucknow Airport 1-6
Table 2 1: Details of Site Location 2-1
Table 2 2: Standards for Drinking Water as per BSI 2-9
Table 2 3: Standards for Drinking Water as per CPCB 2-9
Table 2 4: Estimation for Domestic Use Water Reduction 2-11
Table 2 5: Estimated Saving of Water 2-12
Table 2 6: Estimated of Water Requirement during Non- Rainy Season 2-16
Table 2 7: Estimated of Water Requirement during Rainy Season 2-17
Table 2 8: Design Characteristics of treated and Untreated Effluent 2-19
Table 3 1: Climatological data as per IMD Lucknow (Amausi) 1971–2000 3-4
Table 4 1: Categories of Aerodrome based on Aero-plane Reference Field Length 4-1
Table 4 3: Categories of Aerodrome based on Wing Span & Outer Main Gear
Wheel Span
4-1
Table 4 3: Dimension of various parameters of Proposed Airport 4-2
Table 4 3: Dimension of various parameters of Proposed Airport 4-2
Table 7 1: Cost estimation for the Proposed Development 7-1
Table of Content For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
List of Figures
Figure No. Details
Figure E.1 : Proposed Airports in Uttar Pradesh
Figure 1.1 : Proposed Airports in Uttar Pradesh
Figure 1.2 : Air Connectivity Pattern in India & Across India
Figure 2.1 : Site Location
Figure 2.2: Coordinates of Site
Figure 2.3: Project Layout
Figure 2.4 : Water Flow Chart during Non-Rainy Season
Figure 2.5 : Water Flow Chart during Rainy Season
Figure 3.1 : Summer Wind Pattern
Figure 3.2 : Annual Wind Pattern
Figure 3.3 : Seismicity of Proposed Project (Uttar Pradesh)
Executive Summary
PRE-FEASIBILITY REPORT FOR THE EXPANSION OF NEW INTEGRATED TERMINAL BUILDING OF LUCKNOW
INTERNATIONAL AIRPORT AT AMAUSI, LUCKNOW, UTTAR PRADESH.
PROJECT PROPONENT
AIRPORTS AUTHORITY OF INDIA,
LUCKNOW, U.P.
PAGE NO:
E-I
ENVIRONMENT CONSULTANT
GREENCINDIA CONSULTING PRIVATE
LIMITED NCR, GHAZIABAD
E. Executive Summary
INTRODUCTION:
Lucknow airport belongs to Airport Authority of India (AAI). Lucknow airport has already been
developed as one of the model airports by AAI to cater for operation of wide-bodied aircraft in all
weather conditions. Regionally this is a major airport in Northern India. It serves as the primary civilian
aviation hub for the metropolitan area of the cities of Lucknow and Kanpur. The airport is served by
many international and domestic carriers. This is possibly the second busiest airport in north India after
Delhi (and one of the first ten airports from the 35 Non-metro airports to be upgraded as per policy of
Govt. of India).
Lucknow is the largest city of the state of Uttar Pradesh, India. A major metropolitan city of India and
largest city in Uttar Pradesh, Lucknow is the administrative headquarters of the eponymous District and
Division and the capital of the state of Uttar Pradesh. Lucknow is popularly known as the City of
Nawabs. It is also known as the Golden City of the East, Shiraz-e-Hind and the Constantinople of India.
It is the third largest city in north, east and central India after Delhi and Kolkata and the second largest
city in north and central India after New Delhi. The Lucknow has always been known as a multicultural
city that flourished as a North Indian cultural and artistic hub and the seat of power of Nawabs in the
18th and 19th centuries. It continues to be an important center of governance, administration, education,
commerce, aerospace, finance, pharmaceuticals, technology, design, culture, tourism, music and
poetry.
Lucknow sits on the northwestern shore of the Gomti River. Hindi is the main language of the city and
Urdu is also widely spoken. Lucknow is the center of Shia Islam in India with the highest Shia Muslim
population in India. It is accessible from every part of India by air, rail and road.
The proposed project is a modernization/expansion project of domestic airport at Amausi, Lucknow,
Uttar Pradesh. Existing Lucknow airport is spread over an area of 1261.18 acres/ 510.38 Ha of land
which acquired by AAI. A total 0f 69.37 acres/ 28.07 Ha of land will be utilized for the modernization
project.
PRE-FEASIBILITY REPORT FOR THE EXPANSION OF NEW INTEGRATED TERMINAL BUILDING OF LUCKNOW
INTERNATIONAL AIRPORT AT AMAUSI, LUCKNOW, UTTAR PRADESH.
PROJECT PROPONENT
AIRPORTS AUTHORITY OF INDIA,
LUCKNOW, U.P.
PAGE NO:
E-II
ENVIRONMENT CONSULTANT
GREENCINDIA CONSULTING PRIVATE
LIMITED NCR, GHAZIABAD
Figure E-1 : Proposed Airports in Uttar Pradesh
The proposed airport is located adjacent to Lucknow in North Direction at Adjacent. The details of
location of the airport are given in Table E.1.
Table Error! No text of specified style in document.-1: Details of Site Location
Description Details
Project Site Guraura, Aurangabad Zagir & Bhaktikhera in Lucknow Tehsil
Location Amausi, Lucknow, Uttar Pradesh
Coordinates Points Latitude Longitude
A 26°46'31.0"N 80°52'53.1"E
B 26°46'08.0"N 80°53'36.7"E
C 26°45'45.3"N 80°53'36.6"E
D 26°45'45.9"N 80°54'40.9"E
E 26°45'40.9"N 80°54'53.0"E
F 26°45'37.3"N 80°54'52.9"E
G 26°45'21.7"N 80°54'10.1"E
H 26°45'04.2"N 80°53'01.0"E
PRE-FEASIBILITY REPORT FOR THE EXPANSION OF NEW INTEGRATED TERMINAL BUILDING OF LUCKNOW
INTERNATIONAL AIRPORT AT AMAUSI, LUCKNOW, UTTAR PRADESH.
PROJECT PROPONENT
AIRPORTS AUTHORITY OF INDIA,
LUCKNOW, U.P.
PAGE NO:
E-III
ENVIRONMENT CONSULTANT
GREENCINDIA CONSULTING PRIVATE
LIMITED NCR, GHAZIABAD
Description Details
I 26°44'59.3"N 80°52'33.4"E
J 26°45'34.9"N 80°52'00.3"E
K 26°45'40.3"N 80°52'00.3"E
Total Area in hectares Existing Airport: 1261.18 acres & For Expansion: 69.37 acres (The land for development is already available with the airport)
Access Road National Highway-25, Adjacent.
District Headquarter Lucknow 10.6 km
Nearest Town Lucknow - Adjacent
Nearest Railway Station Amausi Railway Station – 2.8km
Nearest Airport Lucknow Airport- Adjacent
Interlinked Project This is independent project. Neither the proposed project nor other project/s are directly or indirectly linked and/or related to this project
Source: (i) Primary Survey and Site visit, Greencindia Consulting Private Limited, NCR, Ghaziabad; (ii) Toposheet
no.63 B/9, 63 B/10, 63 B/13, 63 B/14, 63 F/1 & 63 F/2 Survey of India, Government of India.
The airport is existing & AAI is proposing the new terminal building & operating facilities after demolition
of terminal-1 & other facilities. The airport was constructed in 1986 to facilitate and operate
passengers. With an increasing number of passengers, AAI decided to upgrade the airport. On 17 July
2008, the Government of India officially renamed it Chaudhary Charan Singh Airport. It was granted
international status in May 2012.
Lucknow Airport, previously called Amausi International Airport is now renamed as Chaudhary Charan
Singh International Airport. It was constructed with the purpose of facilitating VVIPs; it was only in 2005
when the AAI took decision to upgrade the Airport owing to increased number of passengers and also
because of introduction of private operators in the sector.
A new terminal, equipped with latest technology, at Lucknow's Chaudhary Charan Singh Airport is
operative since June 2, 2012. It is being used both for arrivals and departures of domestic and
international flights. The new terminal is a three-tier building which can accommodate around 650
passengers at a time.
EXISTING FACILITIES:
Terminal Building of T1: 8,965 Sq. m & T2: 20,850 Sq. m area.
Runway of dimension 2742 m x 45 m suitable with orientation 09/27.
Runway Strip: 2862 mx150m.
RESA: At 09 End- 90 mx150 m & at 27 End- 115 mx150 m.
PRE-FEASIBILITY REPORT FOR THE EXPANSION OF NEW INTEGRATED TERMINAL BUILDING OF LUCKNOW
INTERNATIONAL AIRPORT AT AMAUSI, LUCKNOW, UTTAR PRADESH.
PROJECT PROPONENT
AIRPORTS AUTHORITY OF INDIA,
LUCKNOW, U.P.
PAGE NO:
E-IV
ENVIRONMENT CONSULTANT
GREENCINDIA CONSULTING PRIVATE
LIMITED NCR, GHAZIABAD
Apron size of 745 m x 150 m suitable for parking 14 Nos. Parking ways (12 Nos. of C Types
Aircraft+02E-Type Aircraft) & VIP Apron for 03 parking ways for King Air Type Aircraft.
Isolation Bays: 61 m x61 m
a) Taxi-A for VIP Apron-520 mx23 m, b) Taxi B&C-207 mx23 m, c) Taxi D 245 mx23 m, d) Taxi
e-223 m x23 m, e)Lima Taxi -88 mx23 m (for joining Main Apron &VIP Apron), f) Taxi M for
Isolation bay 61 mx23 m.
Perimeter Road/ Boundary Wall: Approximately 10475 m.
Fire Station- CAT –VIII
Car park: T1- 250 vehicles, T2- 350 vehicles+10 buses.
STP (Sewage Treatment Plant): Running Capacity of STP is 160 KLD. Capacity at TB-1 & TB-
2(SBT based green technology)
PROPOSED FACILITIES:
Construction of a new centrally air-conditioned Modular Integrated Terminal Building of
1,00,000.00 Sq. m (excluding 20,000 Sq. m Basement area).
Construction of multilevel car park for at least 1500 cars and surface parking for VIP cars
&10 buses, Separate car I scooter park area for AAI and airlines staff at appropriate
location.
Development of four-lane vehicular road from Terminal Building/ Car parking with canopy
covering two lanes in front of the Terminal Building on the city side and connecting the main
approach road to the city.
Provision of water supply pumping arrangement system, Water Filtration, water cooler &
R.O/U.V. Filters, Sewage Treatment Plant (STP), Effluent Treatment Plant (ETP) as per
norms and as per site conditions.
Sub-station, AC plant room and related service facilities. Provision should be made for the
AC Plant Room vertical through AHU rooms, backup generators for essential services etc.
in the lower ground floor.
Construction of multilevel car park for at least 1500 cars and surface parking for VIP cars
&10 buses, Separate car I scooter park area for AAI and airlines staff at appropriate
location. Multilevel Car Parking to be made for retailer in car parking area & it has to be
PRE-FEASIBILITY REPORT FOR THE EXPANSION OF NEW INTEGRATED TERMINAL BUILDING OF LUCKNOW
INTERNATIONAL AIRPORT AT AMAUSI, LUCKNOW, UTTAR PRADESH.
PROJECT PROPONENT
AIRPORTS AUTHORITY OF INDIA,
LUCKNOW, U.P.
PAGE NO:
E-V
ENVIRONMENT CONSULTANT
GREENCINDIA CONSULTING PRIVATE
LIMITED NCR, GHAZIABAD
developed on Built & Operate System and shall include its space planning and mode/for its
operations.
MISCELLANEOUS FACILITIES:
Airport Director's office with associated office space, Conference hall, Retiring rooms, toilet for
staff to be provided.
Development of four-lane vehicular road from Terminal Building/ Car parking with canopy
covering two lanes in front of the Terminal Building on the city side and connecting the main
approach road to the city.
Provision of VIP/ CIP lounges, provision of adequate number of chairs, furniture, furnishings
etc. in the departure lounge common concourse, check-in area, security hold area and arrival
lounge.
Provision of water supply pumping arrangement system, Water Filtration, water cooler & R.O/
U.V. Filters, Sewage Treatment Plant (STP), Effluent Treatment Plant (ETP) as per norms and
as per site conditions.
Sub-station, AC plant room and related service facilities. Provision should be made for the AC
Plant Room vertical through AHU rooms, backup generators for essential services etc. in the
lower ground floor.
Dismantling of terminal Building (T1), AC plant room, CCR hall, Substation, Existing Cargo
Building etc. falling the location of the propose Terminal Building and reconstruct the AC plant
room, CCR hall and Substation in the service area with adequate capacities considering the
overall demand.
ELECTRICAL WORKS & OTHER EQUIPMENTS/SERVICES:
Internal and external electrification for Terminal Building Complex, associated buildings, Car
Park & roads.
Augmentation of main power supply, Substation Equipment, DG Sets for Secondary Power
supply and associated ancillary buildings.
Provision of central air-conditioning & ventilation (HVAC) system & BMS for new terminal
building.
Provision of conveyor belts with In-line X-ray inspection System and other equipment at
departure area and inclined carousels at arrival hall.
PRE-FEASIBILITY REPORT FOR THE EXPANSION OF NEW INTEGRATED TERMINAL BUILDING OF LUCKNOW
INTERNATIONAL AIRPORT AT AMAUSI, LUCKNOW, UTTAR PRADESH.
PROJECT PROPONENT
AIRPORTS AUTHORITY OF INDIA,
LUCKNOW, U.P.
PAGE NO:
E-VI
ENVIRONMENT CONSULTANT
GREENCINDIA CONSULTING PRIVATE
LIMITED NCR, GHAZIABAD
Provision of fire detection & alarm system, provision for fire hydrants and water sprinklers
system as per standards along with fire extinguishers.
Escalators & Elevators with matching staircase.
Provision of Passenger Boarding Bridges (PBB) for the specified parking stands.
Provision of automatic sliding doors at exit and entry points of terminal.
COMMUNICATION, NAVIGATION & SURVEILLANCE (CNS) PLANNING WORKS:
Public address system and car calling system.
Surveillance Close circuit TV system (SCCTV) and provision of adequate number of close
circuit TV monitors, in the Security Control Room, Terminal Manager Room, APD Office etc.
Provision of Flight Information Display System (FIDS) with adequate number of Display Devices
in departure, arrival and security hold area for passenger facilitation.
Provision of adequate number of X-ray machines for scanning Registered Baggage (RB) I
Hand Baggage (HB), including provision of required number of ETDs, DFMDs & HHMDs, as
per BCAS norms.
Provision of adequate no. of VHF FM Sets (Walkie-Talkie, Base Stations & Mobile Stations).
Provision of Telephone Exchange I digital EPABXI IP EPABX system for Terminal Building including
telephone intercom instruments, wiring etc.
DEMOLITION WORK:
The demolition of old terminal building, power house, CCR room, cargo complex, cafeteria, AC plant
room & toilets are proposed. Due to this demolition, approx. 1,50,000 m3 debris will be generated which
will be disposed off by scientific method as per norms.
PROJECT COST:
The proposed completion schedule for the project is 6 month. The estimated cost of the project is
1,230.00 crores.
INTRODUCTION
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
11--11
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
11.. IINNTTRROODDUUCCTTIIOONN
1.1 BACKGROUND
Lucknow airport belongs to Airport Authority of India (AAI). Lucknow airport has already been
developed as one of the model airports by AAI to cater for operation of wide-bodied aircraft in all
weather conditions. Regionally this is a major airport in Northern India. It serves as the primary civilian
aviation hub for the metropolitan area of the cities of Lucknow and Kanpur. The airport is served by
many international and domestic carriers. This is possibly the second busiest airport in north India after
Delhi (and one of the first ten airports from the 35 Non-metro airports to be upgraded as per policy of
Govt. of India).
Lucknow is the largest city of the state of Uttar Pradesh, India. A major metropolitan city of India and
largest city in Uttar Pradesh, Lucknow is the administrative headquarters of the eponymous District and
Division and the capital of the state of Uttar Pradesh. Lucknow is popularly known as the City of
Nawabs. It is also known as the Golden City of the East, Shiraz-e-Hind and the Constantinople of India.
It is the third largest city in north, east and central India after Delhi and Kolkata and the second largest
city in north and central India after New Delhi. The Lucknow has always been known as a multicultural
city that flourished as a North Indian cultural and artistic hub and the seat of power of Nawabs in the
18th and 19th centuries. It continues to be an important center of governance, administration, education,
commerce, aerospace, finance, pharmaceuticals, technology, design, culture, tourism, music and
poetry.
Lucknow sits on the northwestern shore of the Gomti River. Hindi is the main language of the city and
Urdu is also widely spoken. Lucknow is the center of Shia Islam in India with the highest Shia Muslim
population in India. It is accessible from every part of India by air, rail and road.
Lucknow, along with Agra and Varanasi, is one of the 3 cities in the Uttar Pradesh Tourism's Heritage
Arc, which is a chain of survey triangulations created by the Government of Uttar Pradesh to boost
tourism in the state. Chaudhary Charan Singh International Airport is an airport serving Lucknow and
Uttar Pradesh in India. It is situated in Amausi in the city of Lucknow, India and is named after
Chaudhary Charan Singh, the 5th prime minister of India. It is the 12th busiest airport in India and is
also the second busiest and largest in North and Central India after IGI airport Delhi.
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
11--22
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
Figure 1-1 : Proposed Airports in Uttar Pradesh
1.2 PROJECT PROPONENT
The Government of India constituted the International Airports Authority of India (IAAI) in 1972 to
manage the nation's international airports while the National Airports Authority was constituted in 1986
to look after domestic airports. The organizations were merged in April 1995 by an Act of Parliament
and was named as Airports Authority of India (AAI). This new organization was to be responsible for
creating, upgrading, maintaining and managing civil aviation infrastructure both on the ground and air
space in the country.
It also manages a total of 125 Airports, including 18 International Airports, 7 Customs Airports, 78
Domestic Airports and 26 Civil Enclaves at Military Airfields. AAI also provides Air Traffic Management
Services (ATMS) over entire Indian Air Space and adjoining oceanic areas with ground installations at
all Airports and 25 other locations to ensure safety of Aircraft operations.
AAI has four training establishments viz. The Civil Aviation Training College (CATC) at Allahabad,
National Institute of Aviation Management and Research (NIAMAR) at Delhi and Fire Training Centers
(FTC) at Delhi & Kolkata. An Aerodrome Visual Simulator (AVS) has been provided at CATC and non-
radar procedural ATC simulator equipment is being supplied to CATC Allahabad and Hyderabad
Airport. AAI has a dedicated Flight Inspection Unit (FIU) with a fleet of three aircraft fitted with flight
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
11--33
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
inspection system to inspect Instrument Landing Systems up to Cat-III, VORs, DMEs, NDBs, VGSI
(PAPI, VASI) and RADAR (ASR/MSSR).
1.3 TYPE OF PROJECT
The proposed expansion of Lucknow Airport new integrated terminal building is in existing Lucknow
Airport spread over an area of 1261.18 acres/ 510.38 Ha and an area of 28.07 Ha./ 69.37 acres to be
constructed for Proposed Terminal Building and other expansion. The proposed project falls in
Category 7(a) of the Schedule vide EIA notification 2006 amended to date involving preparation of
Environment Impact Assessment study and Environment Management Plan. However general
condition is not applicable to this project. This project is independent and is not linked with other
projects’ which may attract directly or indirectly any provisions of schedule of EIA notification 2006
amended to date.
As per current traffic data, the domestic passengers handled are 2 million for domestic (2014-15) and
0.47 million for international (2014-15). The above building capacity are saturated, therefore it is
proposed to build a new integrated passenger terminal building to cater to the passenger's
convenience in future growth of Lucknow airport.
1.4 AIRPORT SECTOR PROFILE
India’s transformation from an agrarian economy to an urbanized one is an inevitable consequence of
GDP growth led by service sector and saturation of agricultural productivity. Air connectivity can ensure
integration of such urbanizing areas with the rest of the country and national economy. Development of
appropriate connectivity between robust urban agglomerations could check the influx of migrants to
large metro and provide for more balance regional development.
The civil air transport network has been called the Real World Wide Web. It has been observed that the
improvement in air connectivity has brought tremendous benefits to users of air transport services by:
Reducing time spent in transit,
Increasing the frequency of service,
Allowing for shorter waiting times and better targeting of departure and arrival times;
Improving the quality of service, such as reliability, punctuality and quality of the travel
experience.
Air traffic in India has increased over last five years. The compound annual growth rate (CAGR) of total
aircraft movement was 3.3% and of passengers 5.6% during year FY-2011 to FY-2014. Globally,
Indian civil aviation is ninth market. It stands fourth in domestic passenger volume.
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
11--44
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
Improvements in connectivity will effectively contribute to the economic performance of the wider
economy through enhancing its overall level of productivity. Table 1.1 shows the quantum of
passengers handle at major airports in India in last few years.
Table 1-1: Passenger handles at major airports in India (in millions)
Sl. No. Airports City State 2012-13 2013-14 2014-15
1. Delhi International Airport Limited
Delhi Delhi 34.4 36.9 41.0
2. Chhatrapati Shivaji International Airport
Mumbai Maharashtra 30.2 32.2 36.6
3. Chennai International Airport Chennai Tamil Nadu 12.8 12.9 14.3
4. Kempegowda International Airport
Bangalore Karnataka 12.0 12.8 15.4
5. Netaji Subhash Chandra Bose International Airport
Kolkata West
Bengal 10.1 10.1 10.9
6. GMR Hyderabad International Airport Limited
Hyderabad Telangana 8.4 8.8 10.5
Source: Airports Authority of India
1.5 AIR CONNECTIVITY PATTERN
In India, with its geographical spread interspersed with deserts, seas, forests and hilly terrain, regional
and remote area air connectivity can play a crucial role in this context. Establishing or relying on railway
/ road networks for connecting such parts of the country may not be time effective or even viable
(technically /financially).
Also, while railway and road networks may be viable connectivity options to other parts of the country
(not impacted by issues of terrain, security, etc.); air connectivity provides a key advantage in terms of
time saving.
The routes connecting Tier-2 towns / cities to Tier-3 towns / cities 1, only constitute about 7% of the air
transport market in India in terms of seat deployment. While routes can be configured innumerous
ways in terms of combination of frequencies, timing of the flights and aircraft sizes, a number of these
routes are likely to witness traffic that can be better serviced using small aircraft such that the aircraft
could be optimally utilized over the day as well as achieve viable PLF.
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
11--55
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
Figure 1-2 : Air Connectivity Pattern in India & Across India
1.6 NEED OF THE PROJECT
As per current traffic data the domestic passengers handle are 2 million for domestic (2014-15) and
0.47 million for international (2014-15). The above building capacity are saturated, therefore it is
proposed to build a new integrated passenger terminal building to cater to the passengers’’
convenience in future growth of Lucknow Airport.
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
11--66
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
There is growth of 23.9% in international passenger and 27.4% in domestic passenger reported by
authority of Lucknow Airport. To handle this much of influx of passenger the AAI Lucknow proposed to
construct a new integrated terminal building foe the existing Lucknow Airport.
The traffic details of Lucknow Airport showing in Table 1.2, 1.3, 1.4 & 1.5.
Table 1-2: Aircraft Movements of Lucknow Airport
Description Aircraft Movements (In Numbers)
Arrival Departure Total
International
Scheduled 1,446 1,436 2,882
Non Scheduled 73 72 145
Totals 1,519 1,508 3,027
Domestic
Scheduled 7,961 7,985 15,946
Non Scheduled 1,921 1,908 3,829
Totals 9,882 9,893 19,775 Source: Airports Authority of India, Lucknow
Table 1-3: Passengers Movements at Lucknow Airport
Category
Aircraft Movements (in No.)
For the month For April to December
December
2015
December
2014
%
Change 2015-16 2014-15
%
Change
International Passenger 55,473 43,687 27.0 4,26,125 3,43,799 23.9
Domestic Passenger 2,32,972 1,83,229 27.1 19,70,069 15,45,804 27.4
Source: Airports Authority of India, Lucknow
Table 1-4: Passengers Movements at Lucknow Airport
Description Passengers (In Numbers)
Dis Emb. Emb. Transit (Dom) Transit (Int) Total
International
Scheduled 2,27,756 2,42,766 34 0 4,70,556
Non Scheduled 1,621 2,070 6 1 3,698
Totals 2,29,377 2,44,836 40 1 4,74,254
Domestic
Scheduled 10,30,981 10,23,212 37,100 0 20,91,293
Non Scheduled 9,090 9,018 173 0 18,281
Totals 10,40,071 10,32,230 37,273 0 21,09,574 Source: Airports Authority of India, Lucknow
Table 1-5: Freight Details of Lucknow Airport
Description Cargo (Tonnes) Mail (Tonnes)
Un Loaded Loaded Total Un Loaded Loaded Total
International
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
11--77
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
Description Cargo (Tonnes) Mail (Tonnes)
Un Loaded Loaded Total Un Loaded Loaded Total
Scheduled 146.147 1,314.548 1,460.695 0.49 3.444 3.934
Totals 146.147 1,314.548 1,460.695 0.49 3.444 3.934
Domestic
Scheduled 1499.62 1,900.359 3,399.979 326.998 102.15 429.148
Non Scheduled 9.543 12.901 22.444 1 0.332 1.332
Totals 1,509.163 1,913.26 3422.423 327.998 102.482 430.48 Source: Airports Authority of India, Lucknow
1.7 EMPLOYMENT GENERATION
The direct employment during construction phase in proposed project will be 200-300 skilled, unskilled
and professional workforce including temporary and permanent employees shall be required. These
workforces shall be hired locally in order to generate the employment to the local people. While during
the project operation stage for the purposes of day-today professional and maintenance works about
2000 staff is existing in the airport which is sufficient for operation.
1.8 STRUCTURE OF THE REPORT
The report is divided into seven chapters excluding this chapter, the details of which are summarized
below:
Chapter 2: Project Description- This chapter discusses the layout drawing and design considerations
for construction of new terminal building and other facility with existing features like Runway, Apron,
Apron Shoulder, Taxi Track, Runway Shoulder, boundary wall, perimeter roads and parking facilities.
Chapter 3: Site Analysis- This chapter discusses the site profile, landform, and existing land use and
drainage pattern. The land details, climate and metrological parameters are also described in various
sections of the chapter.
Chapter 4: Planning Considerations- This chapter discusses the considerations of planning of
various features like new terminal building and other facility with existing features like Runway, Apron,
Apron Shoulder, Taxi Track, Runway Shoulder, boundary wall, perimeter roads and parking facilities
Chapter 5: Proposed Infrastructure- This chapter discusses the Concept Plan for aviation support
facilities and utilities also provides for the redevelopment & re-planning of existing airport. The Concept
Plan for the proposed airport defines the ultimate scope of the proposal and the development of
facilities in accordance with the requirements of traffic. Earlier discussion on Traffic Analysis and
Project Sizing are used as the basis for planning of the various components.
Chapter 6: Rehabilitation and Resettlement (R&R) Plan- This chapter discusses the R&R study due
to the proposed project area.
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
11--88
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
Chapter 7: Project Schedule & Cost Estimates- This Chapter describes the total investment and cost
regarding the project.
Chapter 8: Final Recommendations- This chapter summarizes the Analysis of Proposal of proposed
terminal building for Lucknow Airport, at Lucknow.
PROJECT
DESCRIPTION
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
22--11
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
22.. PPRROOJJEECCTT DDEESSCCRRIIPPTTIIOONN
2.1. INTRODUCTION
Chaudhary Charan Singh International Airport (LKO) is an airport serving Lucknow and Uttar Pradesh
in India. It is situated in Amausi in the city of Lucknow, India and is named after Chaudhary Charan
Singh, the 5th prime minister of India. It is the 12th busiest airport in India and is also the second
busiest and largest in North and Central India after IGI airport Delhi. There is all existing infrastructure
like runway with all allied facilities like terminal building, Apron, Apron Shoulder, Taxi Track, Runway
Shoulder, boundary wall, perimeter roads and parking facilities. Now AAI, Lucknow decided to
construct a new integrated terminal building and facilities.
The estimated cost of the project is 1,230.00 crores.
2.2. TYPES OF PROJECT
The proposed project is a modernization/expansion project of domestic airport at Amausi, Lucknow,
Uttar Pradesh. Existing Lucknow airport is spread over an area of 1261.18 acres/ 510.38 Ha of land
which acquired by AAI. A total 0f 69.37 acres/ 28.07 Ha of land will be utilized for the modernization
project.
The proposed project falls in Category 7(a) of the Schedule vide EIA notification 2006 amended to date
involving preparation of Environment Impact Assessment study and Environment Management Plan.
However general condition is not applicable to this project.
This project is independent and is not linked with other project/s which attracts directly or
indirectly any provisions of schedule of EIA notification 2006 amended to date.
2.3. LOCATION & LINKAGE
The proposed airport is located adjacent to Lucknow. The details of location of the airport are given in
Table 2.1. The location of site and the geographical coordinates of site superimposed on Topo sheet
are provided in Figure 2-1 & Figure 2-2 respectively.
Table 2-1: Details of Site Location
Description Details
Project Site Guraura, Aurangabad Zagir & Bhaktikhera in Lucknow Tehsil
Location Amausi, Lucknow, Uttar Pradesh
Coordinates Points Latitude Longitude
A 26°46'31.0"N 80°52'53.1"E
B 26°46'08.0"N 80°53'36.7"E
© GREENCINDIA Consulting Private Limited, 2017
±
Map of India State of Uttar Pradesh, India
Project Site Lucknow District, Uttar Pradesh
A B C D
A B
CD
Source: http://www.india-in-your-home.com/physical-map-of-india.html
Scale: Not to Scale
Source: http://updes.up.nic.in/spatrika/engspatrika/images/mandal1.jpg
Scale: Not to Scale
Source: http://www.onefivenine.com/images/DistrictMaps/526.jpg
Scale: Not to Scale
1. SoI Toposheet Nos 63 B/9, 63 B/10, 63 B/13, 63 B/14, 63 F/1 & 63 F/2
2. Project Layout Plan, AAI3. Google Satellite Imagery, 2016
Project Site
!P
Graphic Scale:
GREENCINDIA Consulting Private Limited
Environment Consultant:
1. SoI Toposheet Nos 63 B/9, 63 B/10, 63 B/13, 63 B/14, 63 F/1 & 63 F/2 2. Project Layout Plan, AAI3. Google Satellite Imagery, 2016
Drafted By: Approved By:Checked By:
Date
Revision
14/01/2017
00
(An ISO:9001 QMS, ISO: 14001 EMS & OHSAS: 18001 H&S MS Certified by BSI)QCI-NABET Accrediate Environment Consultant Certificate No. NABET/EIA/RA 014/041
Path: D:\GreenC\Projects I\Mapping\Lucknow\Re Shp\Location.mxd
Software Used:
1. ArcGIS 10.1, 2. AutoCAD 2012, 3. ER Mapper 7, 4. Erdas Imagine 10
Source:
Project:
Project Proponent:
Airports Authority of India, Lucknow
Location Map of the Project Site
Expansion of Lucknow Airport
Figure 2.1:
Amausi, District: Lucknow, Uttar Pradesh
0 2,200 4,400 6,600 8,8001,100 m
Key Map of Uttar Pradesh
Scale: Not to Scale
Source: http://updes.up.nic.in/spatrika/engspatrika/images/mandal1.jpg ¯
Project Site
!P
Legend
Project site
!P
Project Site
Settlements
Streams
Roads
Railway
Forest
Ponds
Vegetation
Contours
Locations
80°54'0"E
80°54'0"E
80°51'0"E
80°51'0"E26
°48
'0"N
26
°48
'0"N
26
°45
'0"N
26
°45
'0"N
© GREENCINDIA Consulting Private Limited, 2017
A
B
C D
±
E
F
G
Graphic Scale:
GREENCINDIA Consulting Private Limited
Environment Consultant:
1. SoI Toposheet Nos 63 B/9, 63 B/10, 63 B/13, 63 B/14, 63 F/1 & 63 F/2 2. Project Layout Plan, AAI3. Google Satellite Imagery, 2016
Drafted By: Approved By:Checked By:
Date
Revision
14/01/2017
00
(An ISO:9001 QMS, ISO: 14001 EMS & OHSAS: 18001 H&S MS Certified by BSI)QCI-NABET Accrediate Environment Consultant Certificate No. NABET/EIA/RA 014/041
Path: D:\GreenC\Projects I\Mapping\Lucknow\Re Shp\Co-ordinate.mxd
Software Used:
1. ArcGIS 10.1, 2. AutoCAD 2012, 3. ER Mapper 7, 4. Erdas Imagine 10
Source:
Project:
Project Proponent:
Airports Authority of India, Lucknow
Co-ordinates of the Project Site
Expansion of Lucknow Airport
Figure 2.2:
Amausi, District: Lucknow, Uttar Pradesh
0 700 1,400 2,100 2,800350 m
Key Map of Uttar Pradesh
Scale: Not to Scale
Source: http://updes.up.nic.in/spatrika/engspatrika/images/mandal1.jpg ¯
Project Site
!P
Legend
Project site
Settlements
Streams
Roads
Railway
Forest
Ponds
Vegetation
Contours
Locations
HI
J
K
Figure No. 2.3 (Project Layout)
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
22--22
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
Description Details
C 26°45'45.3"N 80°53'36.6"E
D 26°45'45.9"N 80°54'40.9"E
E 26°45'40.9"N 80°54'53.0"E
F 26°45'37.3"N 80°54'52.9"E
G 26°45'21.7"N 80°54'10.1"E
H 26°45'04.2"N 80°53'01.0"E
I 26°44'59.3"N 80°52'33.4"E
J 26°45'34.9"N 80°52'00.3"E
K 26°45'40.3"N 80°52'00.3"E
Total Area in hectares Existing Airport: 1261.18 acres & For Expansion: 69.37 acres (The land for development is already available with the airport)
Access Road National Highway-25, Adjacent.
District Headquarter Lucknow 10.6 km
Nearest Town Lucknow - Adjacent
Nearest Railway Station Amausi Railway Station – 2.8km
Nearest Airport Lucknow Airport- Adjacent
Interlinked Project This is independent project. Neither the proposed project nor other project/s are directly or indirectly linked and/or related to this project
Source: (i) Primary Survey and Site visit, Greencindia Consulting Private Limited, NCR, Ghaziabad; (ii) Toposheet no.63 B/9, 63 B/10, 63 B/13, 63 B/14, 63 F/1 & 63 F/2 Survey of India, Government of India.
2.4. SITE SELECTION & ALTERNATIVES
The airport is existing & AAI is expanding the only terminal building. The airport was constructed in
1986 to facilitate and operate passengers. With an increasing number of passengers, AAI decided to
upgrade the airport. On 17 July 2008, the Government of India officially renamed it Chaudhary Charan
Singh Airport. It was granted international status in May 2012.
Lucknow Airport, previously called Amausi International Airport is now renamed as Chaudhary Charan
Singh International Airport. It was constructed with the purpose of facilitating VVIPs; it was only in 2005
when the AAI took decision to upgrade the Airport owing to increased number of passengers and also
because of introduction of private operators in the sector.
A new terminal, equipped with latest technology, at Lucknow's Chaudhary Charan Singh Airport is
operative since June 2, 2012. It is being used both for arrivals and departures of domestic and
international flights. The new terminal is a three-tier building which can accommodate around 650
passengers at a time.
Existing facilities:
Terminal Building of T1: 8,965 Sqm & T2: 20,850 Sqm area.
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
22--33
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
Runway of dimension 2742 m x 45 m suitable with orientation 09/27.
Runway Strip: 2862 mx150m.
RESA: At 09 End- 90 mx150 m & at 27 End- 115 mx150 m.
Apron size of 745 m x 150 m suitable for parking 14 Nos. Parking ways (12 Nos. of C Types
Aircraft+02E-Type Aircraft) & VIP Apron for 03 parking ways for King Air Type Aircraft.
Isolation Bays: 61 m x61 m
a) Taxi-A for VIP Apron-520 mx23 m, b) Taxi B&C-207 mx23 m, c) Taxi D 245 mx23 m, d) Taxi
e-223 m x23 m, e)Lima Taxi -88 mx23 m (for joining Main Apron &VIP Apron), f) Taxi M for
Isolation bay 61 mx23 m.
Perimeter Road/ Boundary Wall: Approximately 10475 m.
Fire Station- CAT –VIII
Car park: T1- 250 vehicles, T2- 350 vehicles+10 buses.
STP (Sewage Treatment Plant): Running Capacity of STP is 160 KLD. Capacity at TB-1 & TB-
2(SBT based green technology)
Proposed facilities:
Construction of a new centrally air-conditioned Modular Integrated Terminal Building of
1,00,000.00 Sq. m (excluding 20,000 Sq. m Basement area).
Construction of multilevel car park for at least 1500 cars and surface parking for VIP cars
&10 buses, Separate car I scooter park area for AAI and airlines staff at appropriate
location.
Development of four-lane vehicular road from Terminal Building/ Car parking with canopy
covering two lanes in front of the Terminal Building on the city side and connecting the main
approach road to the city.
Provision of water supply pumping arrangement system, Water Filtration, water cooler &
R.O/U.V. Filters, Sewage Treatment Plant (STP), Effluent Treatment Plant (ETP) as per
norms and as per site conditions.
Sub-station, AC plant room and related service facilities. Provision should be made for the
AC Plant Room vertical through AHU rooms, backup generators for essential services etc.
in the lower ground floor.
Therefore it was decided by Airports Authority of India to modernize/expand the existing Airport in
Lucknow and no alternate site was required. The environment consideration of the site is discussed in
Chapter-3 of this report. However it observed from the satellite imagery and preliminary site visit
that there are no environmentally sensitive receptors within the proximity of the project site and
technically also site is suitable for the project.
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
22--44
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
2.5. PROJECT MAGNITUDE
Lucknow airport belongs to AAI. Lucknow airport has already been developed as one of the model
airports by AAI to cater for operation of wide-bodied aircraft in all weather conditions, Regionally this is
a major airport in Northern India, It serves as the primary civilian aviation hub for the metropolitan area
of the cities of Lucknow and Kanpur, The airport is served by many international and domestic carriers,
This is possibly the second busiest airport in north India after Delhi (and one of the first ten airports
from the 35 Non-metro airports to be upgraded as per policy of Govt. of India).
As per current traffic data, the domestic passengers handled are 2 million for domestic (2014-15) and
0.47 million for international (2014-15). The above building capacity are saturated, therefore it is
proposed to build a new terminal building to cater to the passenger's convenience in future growth of
Lucknow airport.
2.6. DESCRIPTION OF THE PROPOSED PROJECT
Construction of New Terminal Building and associated facilities will involve the following activities:
2.6.1 CIVIL WORKS:
Construction of a new centrally air-conditioned Modular Integrated Terminal Building of 1,00,000 Sq. m
(excluding 20000 Sq. m Basement area), considering fast growing air traffic and demand for better
passenger facilities an area of 15,000 Sq. m. kept for retail commercial outlets I retiring rooms and
airlines offices to tap future potential at the Airport. The building to be provided with aesthetically
appealing & soothing interior decoration matching the modern structure. Space planning to ensure that
no dead Space/ Area are created in the building.
The Terminal buildings Departure area, Arrival area, Security hold area and Concourse area are to be
provided with adequate nos. of toilets for gents, ladies and differently-abled persons and drinking
water. Suitable number of ramps to be provided for entry and exit of differently-abled persons in
departure and arrival area. Provision of battery operated buggies for senior citizens I differently-abled
persons as per requirement.
The design of terminal building will include Media planning, Retail area planning, F & B plan, etc.
Overall planning of Building will capture local architectural features and it will be part of design features
of terminal. The design should include the required arrangement for its regular maintenance so as to
make it in-built part of execution. Solar power generation viz solar lighting, solar roofing system etc. will
be provided. Maintenance friendly roofing & building facade system including provision of regular
cleaning with maintenance hoists, hooks etc. including cat walk I rope suspended platform I gondola
etc. will be provided.
Green building norms to be followed for 4 star rating of GRIHA.
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
22--55
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
2.6.2 CAR PARKING
Construction of multilevel car park for at least 1500 cars and surface parking for VIP cars &10 buses,
Separate car I scooter park area for AAI and airlines staff at appropriate location. Multilevel Car Parking
to be made for retailer in car parking area & it has to be developed on Built & Operate System and shall
include its space planning and mode/for its operations.
2.6.2.1. MISCELLANEOUS FACILITIES
Airport Director's office with associated office space, Conference hall, Retiring rooms, toilet for
staff to be provided.
Development of four-lane vehicular road from Terminal Building/ Car parking with canopy
covering two lanes in front of the Terminal Building on the city side and connecting the main
approach road to the city.
Provision of VIP/ CIP lounges, provision of adequate number of chairs, furniture, furnishings
etc. in the departure lounge common concourse, check-in area, security hold area and arrival
lounge.
Provision of water supply pumping arrangement system, Water Filtration, water cooler & R.O/
U.V. Filters, Sewage Treatment Plant (STP), Effluent Treatment Plant (ETP) as per norms and
as per site conditions.
Sub-station, AC plant room and related service facilities. Provision should be made for the AC
Plant Room vertical through AHU rooms, backup generators for essential services etc. in the
lower ground floor.
Dismantling of terminal Building (T1), AC plant room, CCR hall, Substation, Existing Cargo
Building etc. falling the location of the propose Terminal Building and reconstruct the AC plant
room, CCR hall and Substation in the service area with adequate capacities considering the
overall demand.
2.6.2.2. ELECTRICAL WORKS & OTHER EQUIPMENTS/SERVICES
Internal and external electrification for Terminal Building Complex, associated buildings, Car
Park & roads.
Augmentation of main power supply, Substation Equipment, DG Sets for Secondary Power
supply and associated ancillary buildings.
Provision of central air-conditioning & ventilation (HVAC) system & BMS for new terminal
building.
Provision of conveyor belts with In-line X-ray inspection System and other equipment at
departure area and inclined carousels at arrival hall.
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
22--66
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
Provision of fire detection & alarm system, provision for fire hydrants and water sprinklers
system as per standards along with fire extinguishers.
Escalators & Elevators with matching staircase.
Provision of Passenger Boarding Bridges (PBB) for the specified parking stands.
Provision of automatic sliding doors at exit and entry points of terminal.
2.6.2.3. COMMUNICATION, NAVIGATION & SURVEILLANCE (CNS) PLANNING
WORKS
Public address system and car calling system.
Surveillance Close circuit TV system (SCCTV) and provision of adequate number of close
circuit TV monitors, in the Security Control Room, Terminal Manager Room, APD Office etc.
Provision of Flight Information Display System (FIDS) with adequate number of Display Devices
in departure, arrival and security hold area for passenger facilitation.
Provision of adequate number of X-ray machines for scanning Registered Baggage (RB) I Hand
Baggage (HB), including provision of required number of ETDs, DFMDs & HHMDs, as per
BCAS norms.
Provision of adequate no. of VHF FM Sets (Walkie-Talkie, Base Stations & Mobile Stations).
Provision of Telephone Exchange I digital EPABXI IP EPABX system for Terminal Building
including telephone intercom instruments, wiring etc.
The project layout showing the component mentioned above are presented in Figure 2-3.
2.6.3 DEMOLITION WORK:
The demolition of old terminal building, power house, CCR room, cargo complex, cafeteria, AC plant
room & toilets are proposed. Due to this demolition, approx. 1,50,000 m3 debris will be generated which
will be disposed off by scientific method as per norms.
2.7. CONSTRUCTION MATERIAL
The major materials required for construction of the proposed project will be steel, aluminum, glass,
cement, bricks, metal, flooring tiles/stones, wood. Sanitary and hardware items, electrical fittings, water
etc. All the items to be used in me proposed project will be as per the National Building Code
specification. The construction material used in proposed project will be sourced from local approved
vendors through the contractor and the specification will be as per the conditions laid in contract. The
contractors work will monitor approved and certified by the Engineering-In Charge.
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
22--77
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
2.8. RESOURCE OPTIMIZATION
The resource optimization is always prerequisite for any development project and saving the precious.
This requires a new approach to viewing, evaluating, understanding, and communicating, which
ultimately requires new approaches to science, engineering, and economics. In quest towards resource
optimization in proposed project the tradition practices are substituted by modern practices involving
water reduction, rain water harvesting, energy conservation etc.
2.8.1 WATER SAVING PRACTICES AND REDUCTION
In India, the average domestic water consumption is 4.1% of the total water use. As per the Bureau of
Indian Standards, the per capita water requirement varies with building type. As per BIS, for residential
buildings with a population of 20,000 - 1,00,000. The per capita consumption is 100-150 LPCD and for
those with population above 1,00,000, the consumption is 150-200 LPCD. Out of the 150 to 200 liters
per head per day, 45 liters per head per day may be taken for flushing requirements and the remaining
quantity for other domestic purposes. For the other types of buildings, the water requirement varies
between 30 to 340 LPCD.
Water usage for applications such as flushing, bathing and washing is as high as 93% of water demand
in any building. However, measures can be adopted to reduce this demand through use of water
efficient practices and devices (efficient plumbing fixtures). These would result in significant saving of
water and contribute towards protection of the environment. Some of the common practices and
devices that can save water are covered below:
Monitoring water use: Use of water meter conforming to ISO standards should be installed at the inlet
point of water uptake and at the discharge point to monitor the daily water consumption. This would
also enable the user to identify if there are any points of leakages.
Use of water saving devices/ fixtures: About 40% of all water used indoors is in the bathroom and
toilets and more than 10% of that used is in the kitchen. The conventional fixtures used in toilets use
water at the rate of 12-15 liters per flush. In normal scenario, the taps and showerheads in buildings
consume water at the rate of 20 liters of water per minute. The flow rates of these fixtures depend on
the pressure at which these are operated. However there exists the opportunity to lower the
consumption through the use of following efficient fixtures:
Low flow flushing systems: Water consumption is more for flushing applications in any building. Use
of more efficient water saving toilets having dual flush system can result in a saving of at least 50% of
water. Dual flush systems can be installed in order to allow different volume of water for flushing liquids
and solids. To facilitate efficient cleaning at low volume, it is possible to install suitable water closets.
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
22--88
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
Sensor based fixtures: Sensors based fixtures functions only in the presence of user. Various types
of sensor based technologies are magic eye sensor for urinals, solenoid self operating valves etc.
Infrared and ultrasonic sensors discharge a set amount of water only when the taps are being used
thus resulting in water saving as compared to manually operated valves. In addition to its advantage in
reducing water consumption, sensor operated taps also result in better hygiene particularly in a public
place.
Urinals: By using automated flushing urinals usage of water is very high. By replacing these with
sensor-based urinals such as magic eye sensor, the water use is reduced to 0.4 liters per flush. In
place of conventional urinals, if the low flow urinals are used, water saving amounts to 3 liters per flush.
Waterless Urinals: Waterless urinals are an efficient technique to save water. The system works
without any water but with the use of biodegradable liquid in the cartridge fitted at the bottom of the
urinal. Each cartridge is adequate for 7000 uses.
Water Taps: A normal tap works at a flow rate as high as 20 lpm. Use of low flow faucets along with
other water saving devices such as auto control valves, pressure reducing devices, aerators and
pressure inhibitors for constant flow, magic eye solenoid valve, and self operating valves can result in
25 – 50% of water savings.
Tap aerators: Tap aerators can be effective by facilitating cleaning through increasing the pressure at
which the water is delivered even at low flow rates. Installation of flow regulators can be done where
the aerators cannot be installed.
Auto control valves: Automatic shut-off valves can be used to control the flow of water for a preset
time limit and with use, which is linked to the release of the lever or handle.
Pressure reducing device: The reducers can be used to control the pressure in the water line, which
will affect the discharge rate and also to maintain uniform flow at different levels. A pressure reduction
device can be installed when the pressure in the line exceeds 50-60 psi. It is observed that a reduction
of pressure from 80 to 65 and 50 psi can result in a reduction of water flow of 10% and 25%,
respectively.
Dual Plumbing System: Introduction of dual pipe in the buildings for use of water with different water
quality namely ground water with high hardness, municipal supply water, treated soft water and
recycled water can result in optimal use of water for different applications thus saving on the high
quality water. Installation of dual pipe plumbing for using recycled water / rain water can save the
potable water from municipal supply or ground water. There can be two lines, one fresh water for
drinking, cooking and bathing etc and other for supply of recycled water for flushing, landscape
irrigation, car washing, thermal conditioning etc. These results in saving of more than one-third of fresh
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
22--99
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
water demand and life of existing sewerage can be improved and also promotes decentralized
treatment system. This system needs space for establishment and initial investment and retrofitting.
Water Quality: In addition to providing adequate water supply for building occupants, quality of water
is also a key concern. Bureau of Indian Standards has recommended a set of parameters, which
should be complied with. These are given in Table 2.2.
Table 2-2: Standards for Drinking Water as per BSI
S. No. Parameters Units Drinking Water IS:10500-2012
Acceptable Limit Permissible Limit
1 Colour Hazen 5 15
2 pH value - 6.5-8.5 No Relaxation
3 Turbidity NTU 1 5
4 Total Dissolved Solids Mg/l 500 2000
5 Anionic Detergents as MBAS Mg/l 0.2 1
6 Boron (as B) Mg/l 0.5 1
7 Calcium (as Ca) Mg/l 75 200
8 Chloride (as Cl) Mg/l 250 1500
9 Copper (as Cu) Mg/l 0.05 1.5
10 Fluride (as F) Mg/l 1 1.5
11 Iron (as Fe) Mg/l 0.3 No relaxation
12 Nitrate (as No3 ) Mg/l 45 No relaxation
13 Phenolic Compounds Mg/l 0.001 0.002
14 Sulfate (as SO4) Mg/l 200 400
15 Total Alkalinity (as CaCO3) Mg/l 200 600
16 Total Hardness (as CaCO3) Mg/l 200 600
17 Zinc (as Zn) Mg/l 5 15
18 Cyanide 9as CN0 Mg/l 0.05 No Relaxation
19 Lead (as Pb) Mg/l 0.01 No Relaxation
20 Total Arsenic (as As) Mg/l 0.01 0.05
21 Total Chromium (as Cr) Mg/l 0.05 No Relaxation Source: IS: 10500:1991, Bureau of India Standards, New Delhi
Further as per the CPCB, water quality standards for different classes of inland waters have been given
for different applications which should be followed (Table 2.3).
Table 2-3: Standards for Drinking Water as per CPCB
S. No.
Characteristics Unit Designated use class of inland waters
A B C D E
1. Dissolved Oxygen, minimum mg/l 6 5 4 4 -
2. pH - 6.5-8.5 6.5-8.5 6.0-9.0 6.5-8.5 6.0-8.5
3. BOD (5days at 200c) mg/l 2 3 3 - -
4. Total Coliform organisms, max
MPN/ 100 ml
50 500 5000 - -
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
22--1100
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
S. No.
Characteristics Unit Designated use class of inland waters
A B C D E
5. Colour Hazen 10 300 300 - -
6. Chlorides (as CL), max mg/l 250 - 600 - 600
7. Sodium Absorption ratio, max
- - - - - 600
8. Boron (as B) mg/l - - - - 2
9. Sulphate(as So4) mg/l 400 - 400 - 1000
10. Nitrates (as No3), max mg/l 20 - 50 - -
11. Free ammonia (as NH3) mg/l - - - 1.2 -
12. Conductivity at 250c, max microhm/cm - - - 1000 2250
13. Arsenic (as As), max mg/l 0.05 0.2 0.2 - -
14. Iron (as Fe) mg/l 0.3 - 50 - -
15. Fluorides (as F) mg/l 1.5 1.5 1.5 - -
16. Lead (as Pb), max mg/l 0.1 - 0.1 - -
17. Copper (as Cu) mg/l 1.5 - 1.5 - -
18. Zinc (as Zn), max mg/l 1.5 - 1.5 - -
19. Manganese (as Mn) mg/l 0.5 - - - -
20. Total Dissolved Solids mg/l 500 - 1500 - 2100
21. Total hardness (as CaCO3)
mg/l 300 - - - -
22. Magnesium (as Mg) mg/l 100 - - - -
23. Chlorides (as Cl) mg/l 250 600 - - 600
24. Cyanides(as CN) mg/l 0.5 0.5 0.5 - - Source: IS: 10500:1991, Bureau of India Standards, New Delhi Notes: A= Drinking Water Source without conventional treatment but after disinfection; B= Outdoor bathing (Organised); C= Drinking water source after conventional treatment and disinfection; D= Propagation of Wild life and Fisheries; E= Irrigation, Industrial Cooling, Controlled Waste disposal Source: Central Pollution Control Board, Government of India, New Delhi.
2.8.2 Water Use Reduction
To estimate the reduction in water use achieved by the building by following the mitigation measures,
use following steps: (i) Step 1: Estimate total water demand based on the occupancy and type of
building; (ii) Step 2: List various efficient fixtures and other measures and (iii) Step 3: Calculate demand
reduction as compared to the BIS per capita water consumption.
2.8.3 Domestic Use for 24 hours
Under normal conditions, water consumption per person for flushing is 45 liters (9 liter/flush with 5
numbers of uses). With efficient fixture (3 and 6 liter/flush), water use is 21 liter (3 liter /flush with 3
uses and 6 liter /flush with 2 uses). Water use per person for washing with normal fixture with a flow
rate of 20 liters per minute is 40 liter (assuming use for 2 minutes), while with efficient fixture (flow rate
of 7.5 lpm) is 15 liters (Table 2.4).
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
22--1111
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
Table 2-4: Estimation for Domestic Use Water Reduction
Sl. No.
Category Normative Water
consumption (in lpcd) Normative in Water
Consumption (in lpcd ) Reduction
(in % )
1 Drinking Water 07 07 -
2 Bathing 20 20 -
3 Flushing 45 21 53
4 Washing 40 15 62
5 Miscellaneous 23 23 -
Total Per Capita
Requirement 123 86 36
Source: Manual on Construction Projects, Central Pollution Control Board, Government of India, New Delhi
2.8.4. Water Conservation in Landscaping
Landscape forms an important part of the building environment. This is constituted by combination of
vegetation, paving and various other landscape features such as water bodies. The vegetation includes
lawns, shrubs, herbs and trees. In general, the water demand for lawns and shrubs are higher as
compared to trees, which does not require or require less water after establishment. In addition, native
species also require less water.
Estimation of Water Demand for Landscape
The water requirement of the landscape can be estimated using the following equation:
Water Requirement (lpd) = (Canopy area (m2) x Evapo-transpiration rate (mpd) x plant factor x 1000)
Irrigation Efficiency
Monthly Evapotranspiration rate (ET0): The potential evapo-transpiration rate (PET) is the
climate factor, refers to the amount of water required by the plant for healthy growth (depending
on the climate). Evapo-transpiration rate determines the rate at which plants lose water through
evaporation. It is affected by humidity and temperature at a given time. These rates vary with
the season and are different for different months.
Canopy area is the area covered by shrubs, grass covers, and for trees it is the plan view and
is assumed as 25 m2 per tree.
The plant factors are categorized as- (i) 1 for evergreen fruit trees, small shrubs, lush ground
covers; (ii) 0.7 for Newly planted native plants in semiarid and arid regions; ornamental or
shade trees and shrubs native to more humid areas (iii) 0.4 for plants native to the areas.
Measures for Reducing Water Demand for Landscape:
The water consumption for the gardening depends on the type of plant species and the plant factors.
As the plant factor for native species and trees is the minimum, one of the options to reduce the water
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
22--1122
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
demand for gardening is to include more native species and low water consuming species. Other
options include use of efficient fixtures for watering, following certain best practices to minimize losses
and optimize consumption.
Efficient Irrigation Equipment:
Drip irrigation: To save water, drip irrigation is an efficient technique as it prevents loss of water due
to evaporation, run–off and percolation. Further, it has a better control and facilitates uniform water
distribution. However, this system cannot be used for lawns and ground covers but for non –native turf
and other non-xerophytes plants.
Sprinkler irrigation: Sprinkler irrigation system requires a network of pipes and pumping system to
maintain sufficient pressure for uniform distribution. It is best suited for areas with sandy soils which
have high infiltration rates. To prevent water logging, the system should be designed in such a way that
infiltration rate exceeds the application rate. Sprinklers which can produce fine sprays are more
efficient as compared to those that produce large water droplets. The efficiencies of irrigation systems
differ widely. Further, to improve the efficiency certain measures can be followed, which includes use of
a pressure regulator for pressures greater than 30 psi which will significantly reduce the loss during
watering.
Efficient central systems: An auto irrigation system with programmed time schedule can be installed
for optimal use of water. To avoid over watering particularly during the rainy season, a rain shut-off
device and soil moisture sensor should be used. It is also advisable to group the plants based on their
water needs to minimize water loss.
Fixed time schedule for watering: Time schedule for watering of plants plays an important role in
saving water. Irrigation should be done during the coolest time of the day (early mornings and
evenings) to avoid loss due to evaporation and wind drift. Also, the frequency of irrigation should be
reduced during the winters. Regular flushing of the irrigation lines and other parts should be done. The
use of combination of mitigation options can result in savings of water as indicated in Table 2.3. The
table indicates the reduction in water that is possible by stepwise reduction in areas of high water
consuming species. By reducing the lawn area by 50% and replacing it with shrubs, it is possible to
achieve 32 % savings and by further introducing native species to the level of 25%, further increase in
savings of 42% is achieved.
Table 2-5: Estimated Saving of Water
S. No.
% 100% Lawn
50% Lawn: 50% Shrubs
50% Lawn: 25% Shrubs: 25% Native
100% native
1 Saving in % - 32 42 64 Source: Manual on Construction Projects, Central Pollution Control Board, Government of India, New Delhi
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
22--1133
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
2.8.5. Water Use during Construction
Water used shall be clean and reasonably free from injurious quantities of deleterious materials such
as oils, acids, alkalis, salts and microbial growth. Generally, potable water shall be used. Where water
can be shown to contain any sugar or an excess of acid, alkali or salt, that water should not be used.
As a guide, the following concentrations may be taken to represent the maximum permissible limits of
deleterious materials in water.
Limits of acidity: To neutralize 200 ml sample of water, it should not require more than 2 ml of 0.1 N
caustic soda solutions.
Limits of Alkalinities: To neutralize 200 ml sample of water it should not acquire more than 0.1 ml of
0.1 N hydrochloric acid.
Percentage of solids should not exceed:
Organic 200 ppm (0.02%)
Inorganic 3000 ppm (0.30%)
Sulphate 500 ppm (0.05%)
Alkali chlorides 1000 ppm (0.1%)
Measures for reducing water demand during construction
To avoid wastage of curing water, following guidelines are to be followed:
Curing water should be sprayed on concrete structures; free flow of water should not be
allowed for curing.
After liberal curing on the first day, all concrete structures should be painted with curing
chemical to save water. This will stop daily water curing hence save water.
Concrete structures should be covered with thick cloth/gunny bags and then water should be
sprayed on them. This would avoid water rebound and will ensure sustained and complete
curing.
Ponds should be made using cement and sand mortar to avoid water flowing away from the flat
surface while curing.
Water ponding should be done on all sunken slabs; this would also highlight the importance of
having an impervious form work.
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
22--1144
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
2.9. WATER REQUIREMENT & SUPPLY
2.9.1 Water Source & Demand
At the present time Lucknow Airport using the ground water and source of required water for the
proposed project will be same. Water supply for the Terminal Building is direct water supply through
pump and for Terminal Building 2 use the underground sump (800KLD).
During the construction stage, water will be sourced primarily through tankers arranged by the
contractors as per PWD specifications. Table 2.6 provides the water requirement details during rainy &
non rainy seasons.
Figure 2-4 : Water Flow Chart during Non-Rainy Season
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
22--1155
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
Figure 2-5 : Water Flow Chart during Rainy Season
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow International Airport at Amausi,
Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
22--1166
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
Table 2-6: Estimated of Water Requirement during Non- Rainy Season
S.no
Parameters Quantity
Water Requirement in LPCD
Water Requirement in KLD**
Wastewater Generation (KLD)
Sewage Treatment Plan (20% excess)
in KLD
Fre
sh
Rec
ycle
d
Fre
sh
Rec
ycle
d
To
tal
Fre
sh
80%
Rec
ycle
d
95%
To
tal
A OPERATION PHASE
a Passengers-numbers. 12000 10 15 120.0 180.0 300.0 96.0 171.0 267.0
SBT Technology
450
b Visitors-numbers. 10000 7 - 70.0 0.0 70.0 56.0 0.0 56.0
c Airport Staff-numbers 2000 24 21 48.0 42.0 90.0 38.4 39.9 78.3
d Residential Area-population 0 65 21 0.0 0.0 0.0 0.0 0.0 0.0
e Kitchen, floor washing & Restaurant -seats
250 52 18 13.0 4.5 17.5 10.4 4.3 14.7
f Landscaping-m2 56146.0 -
20.5 147.9 168.4 0 0 0.0
g HVAC -TR 160 23760 0 23.8
23.8 0 0 0.0
Total Water Demand in KLD 295.3 374.4 669.7 200.8 215.2 374.4
B CONSTRUCTION PHASE
a Daily Labour 300 45 0 13.5 0.0 13.5 10.8 0.0 10.8
Septic Tanks & Toilets
b Residential Labour 0 86 0 0.0 0.0 0.0 0.0 0.0 0.0
C Officials 0 45 0 0.0 0.0 0.0 0.0 0.0 0.0
Total Water Demand in KLD 13.5 0.0 13.5 10.8 0.0 10.8 Source: Source: Technical Report Lucknow Airport
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow International Airport at Amausi,
Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
22--1177
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
Table 2-7: Estimated of Water Requirement during Rainy Season
S.no
Parameters Quantity
Water Requirement in LPCD
Water Requirement in KLD**
Wastewater Generation (KLD)
Sewage Treatment Plan (20% excess)
in KLD
Fre
sh
Rec
ycle
d
Fre
sh
Rec
ycle
d
To
tal
Fre
sh
80%
Rec
ycle
d
95%
To
tal
A OPERATION PHASE
a Passengers-numbers. 12000 10 15 120.0 180.0 300.0 96.0 171.0 267.0
SBT Technology
450
b Visitors-numbers. 10000 7 - 70.0 0.0 70.0 56.0 0.0 56.0
c Airport Staff-numbers 2000 24 21 48.0 42.0 90.0 38.4 39.9 78.3
d Residential Area-population 0 65 21 0.0 0.0 0.0 0.0 0.0 0.0
e Kitchen, floor washing & Restaurant -seats
250 52 18 13.0 4.5 17.5 10.4 4.3 14.7
f Landscaping-m2 56146.0 -
0.0 0.0 0.0 0 0 0.0
g HVAC -TR 160
23760
23.8 23.8 0 0 0.0
Total Water Demand in KLD 251.0 250.3 501.3 200.8 215.2 374.4
B CONSTRUCTION PHASE
a Daily Labour 300 45 0 13.5 0.0 13.5 10.8 0.0 10.8
Septic Tanks & Toilets
b Residential Labour 0 86 0 0.0 0.0 0.0 0.0 0.0 0.0
C Officials 0 45 0 0.0 0.0 0.0 0.0 0.0 0.0
Total Water Demand in KLD 13.5 0.0 13.5 10.8 0.0 10.8 Source: Source: Technical Report Lucknow Airport
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
22--1188
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE LLIIMMIITTEEDD
NNCCRR,, GGHHAAZZIIAABBAADD
2.9.2. WATER STORAGE
Since the hours of supply may not be continuous, it is recommended to go for 3 days bulk storage at
the main receiving tanks, wherein the domestic water will receive the desired level of treatment. Further
to bulk storage, individual Buildings / Utility will have their own storage tanks catering to a day’s
requirement.
2.9.3. Water Distribution
Treated water will be pumped into the main header pipe to distribute water to the storage tanks located
in the individual building / utilities i.e. Terminal Building, Maintenance Building, ATC Tower,
Commercial Building, Shopping Area and Admin Office Building.
Storage tanks in individual buildings will have solenoid controls to regulate & control the inflow. From
these storage tanks water will be pumped into the internal plumbing system of respective buildings
through variable speed hydro-pneumatic pumps.
The Terminal buildings, especially, will witness periodic peak flow surge along with relatively very low
demand periods. It is recommended for optimization of energy to go for multiple pump configurations to
offset such variance in demand. It is proposed to integrate the water system with Building Management
controls.
2.9.4. Water Storage
Since the hours of supply may not be continuous, it is recommended to go for 2 days bulk storage at
the main receiving tanks, wherein the domestic water will receive the desired level of treatment. Further
to bulk storage, individual Buildings/ Utility will have their own storage tanks catering to a day’s
requirement. Besides the above, 2 Fire reserve storage tanks of 10,00,000 liters capacity is available.
2.10. WASTEWATER GENERATION AND TREATMENT
The main source of drainage generation will be the discharges from toilets (water closet), urinals, sinks,
pantry’s, kitchen and other similar utilities. Capacity of 160 KLD SBT based green technology already
installed for existing Lucknow Airport at Terminal Building 1 and 2. However civil structures available
for the capacity of 300 KLD for future expansion.
The total water requirement in operation phase will be 501.3 KLD & 13.5 KLD for construction phase
and the waste water generation amount is 374.4 KLD in operation phase & 10.8 KLD in construction
Phase. The wastewater will be treated in 450 KLD Soil Bio filter Technology (SBT).
The SBT technology has following advantages:
It provides primary, secondary and tertiary treatment all in one unit, in a single evergreen facility
open to atmosphere.
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
22--1199
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE LLIIMMIITTEEDD
NNCCRR,, GGHHAAZZIIAABBAADD
It is very simple to operate, maintain.
It does not require skilled man-power.
It is cost competitive particular with reference to O&M cost.
No pre-treatment
No chemical usage
Absence of any moving part
Odour-free
Low energy requirement and
Green environment are its unique features.
The process can be run on batch or continuous mode.
No sludge production
Mechanical aeration is not required.
The overall time of operation is 6-7 hours per day. The soil biotechnology system bed is dried
prior to next cycle of use.
Soil Bio- technology is a terrestrial system for wastewater treatment which is based on the principle of
trickling filter. In this system, combination of physical processes like sedimentation, infiltration and
biochemical processes are carried out to remove the suspended solids, organic and inorganic contents
of the wastewater. Suitable mineral constitution, culture containing native micro-flora and bio- indicator
plants are the key components of the system. It is also known as Constructed Soil Filter (CSF). SBT
systems are constructed from RCC, stone-masonry or soil bunds. It consists of raw water tank,
bioreactor containment, treated water tank, piping and pumps.
Current STP meets the standards especially for pH, BOD and suspended solids (SS) parameters,
depicted below:
Table 2-8: Design Characteristics of treated and Untreated Effluent
Sl. no. Parameters Untreated Effluent Treated Effluent
1 pH 7.5-8.5 6.0-8.5
2 BOD5 250-400 mg/L <20 mg/L
3 Suspended Solids 200-450 mg/L <10 mg/L
4 COD 600-800 mg/L <60 mg/L
5 Oil & Grease -50 mg/L <5 mg/L Source: Technical Report Lucknow Airport
2.11. POWER REQUIREMENT & SUPPLY
Total electrical load of existing airport is 3100 KVA, drawn from the grid of State Electricity Board of
Uttar Pradesh. There are 11 (750 KVA= 5 no., 320 KVA= 4 no. & 200 KVA= 2 no.) DG sets available in
existing airport for power backup. The electrical supply system includes HT panel, DG set, Transformer
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
22--2200
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE LLIIMMIITTEEDD
NNCCRR,, GGHHAAZZIIAABBAADD
and other LT panels. The essential electrical services shall be backed with DG sets along with PLC
panel. All the electrical HT & LT cables shall be laid as per the stipulations of CPWD specifications.
2.12. SOLID WASTE MANAGEMENT
In Construction phase: Solid waste during construction phase will be collected and disposed as per
established laws and Procedures. The Organic waste will be treated at site.
In Operation phase: Twin bin waste collection system– green bins for bio-degradable wastes and blue
bins for non-biodegradable wastes shall be provided. Waste collection shall be done and temporarily
stored at identified locations before disposing as per established laws and procedures as per Lucknow
Municipality waste disposal site.
Hazardous waste shall be treated in accordance with Hazardous Waste Management Rules 2008,
Batteries waste shall be handled in accordance with Batteries Management Rules, 2010 and E waste
as per E waste Guidelines, 2008.
Bio Medical Waste shall be collected and disposed in accordance with Bio Medical Waste
(Management and Handling) Rules, 1998
2.13. FIRE SAFETY
On the present day Lucknow Airport has existing facility of CAT VIII fire station. Further, there is a
proposal of construction of fire station of CAT IX & sub fire station of CAT IV, which shall be taken up
shortly.
2.14. ELECTRICAL SYSTEMS
The cooling requirements for the proposed project have been estimated on the basis of the
following design assumptions.
Internal and external electrification for Terminal Building Complex, associated buildings, Car
Park and roads.
Augmentation of main power supply, Substation Equipment, DG Sets for Secondary Power
supply and associated ancillary buildings.
Sub-station, A/C plant room and related service facilities. Provision should be made for the AC
Plant Room vertical through AHU rooms, backup generators for essential services, etc in the
lower ground floor.
Provision of central air-conditioning & ventilation (HVAC) system & BMS for New Terminal
Building.
Provision of conveyor belts with In-line X-ray inspection System and other equipment at
departure area and inclined carousels at Arrival hall.
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
22--2211
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE LLIIMMIITTEEDD
NNCCRR,, GGHHAAZZIIAABBAADD
Provision of fire detection & alarm system, provision for fire hydrants and water sprinklers
system as per standards along with fire extinguishers.
Escalators & Elevators with matching stair case.
Provision for Passenger Boarding Bridges (PBB) for the specified parking stands.
Provision of automatic sliding doors at exit and entry points of terminal.
Provision of adequate number of Signage of world class standard, inside and outside the
terminal building, car park area & City side approach road and air side area for guidance of
passengers and visitors.
2.15. NOISE AND VIBRATION CONTROLS
The air conditioning contractor must take all necessary precautions to have minimum noise generation
and its transmission. Minimum vibration as permitted by IS relevant code shall be ensured. A few
points for guidance only are given below:
Double fire retardant flexible connections shall be provided from air discharge to outlet of air-
handler to the duct.
Vibration isolation pads of suitable thickness commensurate to loading for isolation of vibration
shall be provided under all equipment. In consultation with manufacturer for proper selection of
vibration isolators
Flexible conduit connections of minimum diameter of 50mm to motors shall be provided. All
loops should be large enough to allow connections to remain flexible.
All conduit connection where conduits are 60mm or larger shall be made of 1.2-meter minimum
length conduit installed in the shape of U and grossly slack to provide maximum vibration
isolation.
The floor supported piping shall be mounted on pipe supports with 7.5mm ribbed neoprene
pads between the base plate of the pipes and the floors.
All items suspended from false ceiling shall be isolated on separate hangers.
In case of ducts, conduits, pipes & tubes the annular space between construction and
penetrating element shall be sealed with sand cement plaster.
The supply duct starting from air handling unit & plenum shall be provided with 12 mm thick
acoustic lining as indicated in the tender drawings.
The air-conditioning contractor shall take all other precautions or shall make his own
arrangements even if not specified in the tender documents for eliminating high noise levels &
shall minimize vibrations in all mechanical equipment without any additional cost.
81°0'0"E
81°0'0"E
80°57'0"E
80°57'0"E
80°54'0"E
80°54'0"E
80°51'0"E
80°51'0"E
80°48'0"E
80°48'0"E26
°51
'0"N
26
°51
'0"N
26
°48
'0"N
26
°48
'0"N
26
°45
'0"N
26
°45
'0"N
26
°42
'0"N
26
°42
'0"N
26
°39
'0"N
26
°39
'0"N
© GREENCINDIA Consulting Private Limited, 2017
±
Graphic Scale:
GREENCINDIA Consulting Private Limited
Environment Consultant:
1. SoI Toposheet Nos 63 B/9, 63 B/10, 63 B/13, 63 B/14, 63 F/1 & 63 F/2 2. Project Layout Plan, AAI3. Google Satellite Imagery, 2016
Drafted By: Approved By:Checked By:
Date
Revision
14/01/2017
00
(An ISO:9001 QMS, ISO: 14001 EMS & OHSAS: 18001 H&S MS Certified by BSI)QCI-NABET Accrediate Environment Consultant Certificate No. NABET/EIA/RA 014/041
Path: D:\GreenC\Projects I\Mapping\Lucknow\Re Shp\Study Area Map.mxd
Software Used:
1. ArcGIS 10.1, 2. AutoCAD 2012, 3. ER Mapper 7, 4. Erdas Imagine 10
Source:
Project:
Project Proponent:
Airports Authority of India, Lucknow
Study Area Map
Expansion of Lucknow Airport
Figure 2.1:
Amausi, District: Lucknow, Uttar Pradesh
0 1,900 3,800 5,700 7,600950 m
Key Map of Uttar Pradesh
Scale: Not to Scale
Source: http://updes.up.nic.in/spatrika/engspatrika/images/mandal1.jpg ¯
Project Site
!P
Settlements
Streams
Roads
Railway
Forest
Ponds
Vegetation
Contours
Locations
Legend
Project site
Study Area Map
81°3'0"E
81°3'0"E
81°0'0"E
81°0'0"E
80°57'0"E
80°57'0"E
80°54'0"E
80°54'0"E
80°51'0"E
80°51'0"E
80°48'0"E
80°48'0"E
80°45'0"E
80°45'0"E
80°42'0"E
80°42'0"E26
°54
'0"N
26
°54
'0"N
26
°51
'0"N
26
°51
'0"N
26
°48
'0"N
26
°48
'0"N
26
°45
'0"N
26
°45
'0"N
26
°42
'0"N
26
°42
'0"N
26
°39
'0"N
26
°39
'0"N
26
°36
'0"N
© GREENCINDIA Consulting Private Limited, 2017
±
Graphic Scale:
GREENCINDIA Consulting Private Limited
Environment Consultant:
1. SoI Toposheet Nos 63 B/9, 63 B/10, 63 B/13, 63 B/14, 63 F/1 & 63 F/2 2. Project Layout Plan, AAI3. Google Satellite Imagery, 2016
Drafted By: Approved By:Checked By:
Date
Revision
14/01/2017
00
(An ISO:9001 QMS, ISO: 14001 EMS & OHSAS: 18001 H&S MS Certified by BSI)QCI-NABET Accrediate Environment Consultant Certificate No. NABET/EIA/RA 014/041
Path: D:\GreenC\Projects I\Mapping\Lucknow\Re Shp\Env Sen Map.mxd
Software Used:
1. ArcGIS 10.1, 2. AutoCAD 2012, 3. ER Mapper 7, 4. Erdas Imagine 10
Source:
Project:
Project Proponent:
Airports Authority of India, Lucknow
Environment Sensitive Locations
Expansion of Lucknow Airport
Figure 0.00:
Amausi, District: Lucknow, Uttar Pradesh
0 2,600 5,200 7,800 10,4001,300 m
Key Map of Uttar Pradesh
Scale: Not to Scale
Source: http://updes.up.nic.in/spatrika/engspatrika/images/mandal1.jpg ¯
Project Site
!P
Settlements
Streams
Roads
Railway
Forest
Ponds
Vegetation
Contours
Locations
Legend
Project site
15 km Buffer
Goura RF13.3, SE
Gomti River10.8km, NE
Sai Nadi13.0, SSW
Musabagh PF11.5km, NNW
SITE ANALYSIS
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
33--11
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
33.. SSIITTEE AANNAALLYYSSIISS
3.1 INTRODUCTION
Site analysis is a pre-design research activity which focuses on existing and potential conditions on and
around the building site. It is an inventory of the site factors and forces, and how they coexist and
interact. The purpose of the analysis is to provide thorough information about the site assets and
liabilities prior to starting the design process. The typical site analysis includes the site location and
size, neighborhood context, zoning, legal aspects, geology, physiographic (natural and man-made
features), hydrology, soils, vegetation, wildlife, climate, culture, pedestrian and vehicular circulation,
access, utilities, historic factors, density, sensory stimuli, and any other factor deemed appropriate for
the particular site. This chapter discusses the site Profile, landform, and existing land use and drainage
pattern. The land details, climate and Metrological parameters are also described in various sections of
this chapter.
3.2 LOCATION & CONNECTIVITY
The site selected for new terminal building & commercial facilities is proposed at existing land of
Lucknow International Airport which is located adjacent with National Highway 25 (Lucknow-Shivpuri).
The nearest railway station is at Amausi, 2.8 km away from the proposed site.
3.3 PHYSIOGRAPHY
The Lucknow airport is existing and the proposed project is only for development of new terminal
building and commercial facilities by demolishing terminal -1. All infrastructures are available there.
Surrounding to the exiting airport, the land-use is agricultural and settlement.
3.4 HYDROGEOLOGY
Around 85% of the land-area of Lucknow City is situated on the Central Ganga alluvial plain, and
stretches across both banks of the Gomti River– which is an entirely lowland river naturally dependent
on groundwater discharge for its dry-weather flow. The city is underlain by a large thickness of
Quaternary alluvial sands (at best of medium-grade) with occasional inter-bedded silty clay.
Ground water occurs in the pore spaces of the unconsolidated alluvium sediments in the zone of
saturation under phreatic and semi confined conditions. In deeper aquifer it occurs under semi confined
to confined conditions.
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
33--22
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
3.5 GROUND WATER STATUS
On the basis of NHS1 & piezometers Pre-monsoon Depth to water in Post-monsoon is revealed that
shallowest water level less than 2 m & between 2-5 m occurs in the eastern part of district in the
Gosainganj block along the Sharda Sahyak Canal. Depth to water between 5 to 10 m occurs in the
northern & southern part of districts in part of Bakshi-Ka-Talab, Chinhat & Mohanlal ganj blocks. The
western part of the district depth to water ranges between 10-20 meters in Mal, Malihabad, part of of
Bakshi-Ka-Talab. Kakori, Sarojini Nagar & part of Chinhat blocks. Minimum water level of 1.80 mbgl
was observed at Gosainganj and maximum of 32.60 mbgl was observed at Gulistan Colony in the
Lucknow town. In the urban areas depth to water generally remains more than 20 mbgl.
Depth to water level in Post-monsoon period reveals that shallower water level less than 2 m and
between 2-5 m occurs in the north eastern part of the district (part of Gosainganj, Mohanlalganj &
Bakshi-Ka-Talab blocks) and in a small patch in the NW part of district (part of Mal block along the
canal). Depth to water level between 5-10 m generally remains in the northern & southern part of the
district (part of Mohanlalganj, Sarojini Nagar, Bakshi-Ka-Talab, Mal & Malihabad). In the central part of
district depth to water varies between 10 and 20 m below ground level. More than 20 m depth to water
has been observed in the city area in parts of Chinhat & Sarojini Nagar blocks. Minimum depth to water
1.21 mbgl has been observed at Nagram & whereas maximum depth to water 32.11 mbgl has been
observed Gulistan Colony in Lucknow City area during Post-monsoon period. The overall level of
development of Lucknow district is 81.21%.
3.6 LAND OWNERSHIP
Total 1261.18 acres land belongs to the existing Lucknow Airport. The 69.37 acres of land required
which is also available for the proposed construction of Lucknow Airport. No additional land needs to
be purchased.
3.7 TOPOGRAPHY
The existing airport site is 4.2 km long in east-west direction & 2.0 km in north south direction at. The
total land proposed to be acquired for development of airport is 69.37 acres.
The identified site is located in plain surface with 123m (in East) to 128m (in West). The site is having
gentle slope from West to East. The site is developed as existing airport. All infrastructures are
available there. Surrounding this airport area land use is agricultural and settlement.
1 Ground water brochure of lucknow district, Uttar Pradesh
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
33--33
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
3.8 EXISTING LAND USE PATTERN
The land use pattern indicates the manner in which different parts of land in the study area is being
utilized. It is an important indicator of environmental setting and human activity and a degree of inter-
play between these two important parameters. The land is being used for existing airport purpose.
3.9 EXISTING INFRASTRUCTURE
The said project is modernization of Lucknow Airport in terms of new terminal building & commercial
facilities. It is well connected and just adjacent to National Highway No.-25 (Lucknow-Shivpuri
Highway) in West and North-West direction. Lucknow city is located adjacent to North direction which is
also adjacent to project.
3.10 GEOLOGY & SOIL
The district forms a part of Ganga basin with flat
alluvial terrain. General elevation varies from 103 m
to 130 m above mean sea level. The general slope of
the district is south-east. Geo-morphologically the
district is divided into two geomorphic units (i) Older
flood plains & (ii) Active flood plain. Older flood plains
are represented by two level of terraces viz erosional
terrace (Te) occupying at higher level and
Depositional terrace (Td) at lower depressions. Older
flood plain exists between elevation of 103 and 110
mamsl. Both the terraces are developed on the either
side of Gomti River. Erosional Terrace is also
developed along Sai Nadi. Active flood plains are
restricted to present day bank line of the rivers.
These are represented by land forms like point bars
channel bars and lateral bars. Quaternary sediments
have been divided upto older & newer alluvium. The
older alluvium is comprised of grey to brown colored
silt clay and sand with or without Kankar of middle to late Pleistocene age. The Newer alluvium overlies
the older alluvium and has been sub divided into terrace alluvium and channel alluvium & belongs to
Holocene age. The newer alluvium comprises of light Khaki grey silt, clay and fine to medium and
coarse grained grey sand which is micaceous in nature.
Soil- Soils in the district exhibits a wide variation in composition texture and appearance. The major
position of the district is occupied by soils locally known as "Bhur" or "Silty Sand" on the ridges.
"Matiyar" or "Clay Soils" occurs along topographic lows and "Dumat or Loamy soils" in the level lands.
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
33--44
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
Clay is dominant in the areas where "Reh" (Usar) prevails. Along the river valleys, a very fertile soil
called "Dumat" is prevalent which is youngest.
3.11 METEOROLOGY & CLIMATOLOGY
The data obtained from the Meteorological Department of India for Lucknow (Amausi) observatory has
been utilized. The maximum rainfall over 24 hours occurred during the period 1961-1990 is 272.4 mm
in July 1960 and the average number of rainy days is about 46.8 in a year.
1.1.1. Climatic Condition (30-years IMD Data)
Summary of 30 years average data is presented in the table 3.1 below:
Table 3-1: Climatological data as per IMD Lucknow (Amausi) 1971–2000
Sl. No. Parameters Description of the Season
1 Rainfall in mm
Total Annual average Rainfall is 990.1 mm
Winter (Dec to Feb)
Months Total rainfall (in mm)
December 12.6
January 20.2
February 16
Total 48.8
Summer (Mar to May)
March 10
April 5
May 18.4
Total 33.4
Monsoon (June to Sept)
June 122.9
July 269.9
August 255.3
September 211.5
Total 859.6
Post-Monsoon (Oct to Dec)
October 40.9
November 7.4
December 12.6
Total 60.9
2 Temperature (Mean Daily Temp. in 0C)
Months Max Min Avg
Winter (Dec to Feb)
Dec 24.6 8.4 16.5
Jan 22.5 7.5 15.0
Feb 25.8 9.8 17.8
Average 24.3 8.6 16.4
Summer (Mar to May)
Mar 32.0 14.5 23.3
Apr 38.0 20.5 29.3
May 40.0 24.6 32.3
Average 36.7 19.9 28.3
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
33--55
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
Sl. No. Parameters Description of the Season
Monsoon (June to Sept)
June 38.4 26.7 32.6
Jul 33.9 26.0 30.0
Aug 33.2 25.6 29.4
Sep 33.1 24.1 28.6
Average 34.7 25.6 30.1
Post-Monsoon (Oct to Dec)
Oct 32.8 19.1 26.0
Nov 29.2 12.8 21.0
Dec 24.6 8.4 16.5
Average 28.9 13.4 21.2
3 Relative Humidity
in per cent
Winter (Dec to Feb)
Month 08.30 hrs 17:30 hrs
Dec 83 61
Jan 86 57
Feb 75 45
Average 67.8 54.3
Summer (Mar to May)
Mar 59 32
Apr 42 24
May 48 29
Average 39.0 28.3
Monsoon (June to Sept)
Jun 64 48
July 82 73
Aug 85 77
Sep 83 74
Average 73.3 68.0
Post-Monsoon (Oct to Dec)
Oct 75 63
Nov 75 59
December 83 61
Average 69.3 61.0
4 Wind-speed
Winter (Dec to Feb)
Month Speed (kmph)
Dec 1.9
Jan 3
Feb 4
Average 2.9
Summer (Mar to May)
Mar 5.4
Apr 6.9
May 6
Average 6.1
Monsoon (June to Sept)
Jun 4.9
July 4.2
Aug 4
Sep 3.2
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
33--66
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
Sl. No. Parameters Description of the Season
Average 4.1
Post-Monsoon (Oct to Dec)
Oct 1.9
Nov 1.5
Dec 1.9
Average 1.8 Source: Climatological Normals 1971 – 2000, Indian Meteorological Department, Govt. of India, New Delhi
The wind rose for the entire year is given below
Figure 3-1 : Summer Wind Pattern Figure 3-2 : Annual Wind Pattern
The Climate of the district is normally good and healthy. January, February and March months are
usually pleasant with moderate winds. May is hottest months of the year; during these months the wind
shifts to West and South-East with increased force. During the succeeding four months the wind blows
from Western and North-Western side in Major parts of the district and brings fair quantum of rainfall.
3.12 SEISMICITY
Lucknow falls on zone III seismic zone which is moderate damage risk zone (MSK VII).
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
33--77
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
Figure 3-3 : Seismicity of Proposed Project (Uttar Pradesh)
3.13 WIND HAZARD
As per the meteorological information gathered from the Meteorological Department of India, the
following is also observed:
Hail : On an average hail observed on only 0.6 days in period of year Thunder : On an average thunder observed on only 46.9 days in period of year. Fog : On an average fog observed 23.1 days in the area round period of year. Dust Storm : On an average Dust Storm observed on only 7.5 days in period of year. Squall : On an average 1.2 days Squall being ever been observed in period of year.
On the bases of these observation, following suggestions are as:
The project is coming under Very High Damage Risk Zone-A (Vb=55 m/s) as per Wind &
Cyclone hazard map of India.
Building strong engineered structures to withstand wind speed.
Proper plantation will be developed to prevent soil erosion.
Future critical facilities will not be located in areas of accelerated winds.
The roofs of existing critical facilities should be retrofitted to a higher standard to ensure wind
resistance.
Building openings such as windows and doors also suffer damage from high velocity winds.
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
33--88
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
These openings if not constructed of wood or metal should be protected with shutters or
temporary covers of adequate design
3.14 SOCIAL INFRASTRUCTURE
a. Social Infrastructure available
The all types of social infrastructure and facilities are available at Lucknow which is located near from
the Lucknow Airport.
Hospital with ambulance;
Banks;
Post office;
Bus station;
Fire station;
Secondary school;
Police station;
Shopping complex;
Sports infrastructure;
Community halls;
Primary health care centres.
PLANNING
CONSIDERATION
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
44--11
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
4. PPLLAANNNNIINNGG CCOONNSSIIDDEERRAATTIIOONN
4.1 INTRODUCTION
The purpose of this chapter is to present the Planning Concepts for Lucknow Airport, in terms of both
their vision and reasoning. Therefore, several basic assumptions have been established, which are
intended to direct the future planning of the Airport. These assumptions are supported by the aviation
activity forecasts and include a commitment for continued airport operation, which supports local and
regional needs.
Airport planning and design primarily depends upon availability of land, its topography, orientation,
accessibility, etc. Traffic is the other major factor that decides the size of runway, terminal building and
other related infrastructure required for the proposed airport. The site and traffic studies have been
discussed in the preceding chapters. Based on the site and traffic studies the planning and conceptual
design of the proposed airport is discussed in this chapter.
4.2 PLANNING CONCEPT
The airport is not only for interstate transportation but also national and international transportation and
also carriage transport. Aerodrome code of Lucknow airport is 4D. Aerodrome Reference Code is
defined by the characteristics of the aircraft intended to use the airport. The parameters to categorize
the Aerodrome reference code by ICAO are mentioned in Table 4.1
Table 4-1: Categories of Aerodrome based on Aeroplane Reference Field Length
Source: ICAO
Table 4-2: Categories of Aerodrome based on Wing Span & Outer Main Gear Wheel Span
Source: ICAO
Code Number Aero plane reference field length
1 Less than 800m
2 800m up to 1200m but not including 1200m
3 1200m up to 18000m but not including 1800m
4 Over 1800m
Code Letter Wing span Outer main gear wheel span
A Up to and not including 15m Up to and not including 4.5m
B 15m up to and not including 24m 4.5m up to and not including 6m
C 24m up to and not including 36m 6m up to and not including 9m
D 36m up to and not including 52m 9m up to and not including 14m
E 52mup to and not including 65m 9m up to and not including 14m
F 65m up to and not including 80m 14m up to and not including 16m
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
44--22
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
4.3 EXISTING FEATURES OF LUCKNOW AIRPORT
4.3.1. TERMINAL BUILDING
Terminal Building (T1):
In 1995 Terminal Building 1 was constructed at Lucknow Airport for 500 (Pax). Presently Terminal
Building 1 holds an area of 8,965 Sq. m. with 10 numbers of Checking Counter facilities. Currently in
Terminal Building has 10 Numbers of Check-in-counter-10, 6 numbers of Immigration Counter, 1
Departure Counter, 6 Arrival Counters and 4 Custom Counters.
Terminal Building (T2):
In 2012 Terminal Building 2 was constructed at Lucknow Airport for 500 (Pax). Presently Terminal
Building 2 holds an area of 20,850 Sq. m. with 16 numbers of Checking Counter and 3 Frisking
Counter.
4.3.2. Runway Orientation
The orientation of the runway for Lucknow airport is 09-27, West-East direction. The data on intensity
and prevailing wind directions for Lucknow, noted from climatological tables by Meteorological
Department of India for nearest observatory at Lucknow have been analyzed.
4.3.3. Runway Length
There is one runway with the following dimensions:
Table 4-3: Dimension of various parameters of Proposed Airport
Name Dimension
Length 2742 m
Width 45 m
Runway Strip 2862 x 150 m
Runway End Safety Area( RESA) 09 End-90 x 150 m, 27 End -115 x 150 mtr
Threshold displaced 157 m at 09 end Source: Technical Report Lucknow Airport
4.3.4. Runway Geometry
The runway is for Code 4D. The width of the runway is 45 m and length of 2742 m. The orientation of
the runway for Lucknow airport is 09-27, West-East direction. The permissible values of slopes as per
ICAO are given in Table 4.4 below:
Table 4-4: Dimension of various parameters of Proposed Airport
Name Slope Permissible
Runway Longitudinal
1.25% (Max.) with Max. slope of 0.8% in the last quarters on both ends and overall slope not to exceed 1.00%
Transverse 1.50% (Max.) 1.00% (Min.)
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
44--33
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
Name Slope Permissible
Runway Strip
Longitudinal 1.50% (Max.)
Transverse 2.50% (Max.)
Taxiway
Longitudinal 1.50% (Max.)
Transverse 1.50% (Max.)
Taxiway Strip
Transverse 2.50% (Max. Downward) 0.50% (Max. Upward)
Apron Longitudinal 1.00% (Max.)
Transverse 1.00% (Max.) Source: ICAO
4.3.5. Taxiway
The taxiway system is planned with the flexibility for future demand. Space for a parallel taxiway along
the length of the runways is provided. The initial phase will only have an apron taxiway and two
perpendicular exit taxiways connecting the apron. Details of dimension of taxiway are given below:
Taxi A- for VIP Apron- 252 x 23m.
Taxi B&C- 207 x 23 m
Taxi D- 245 x 23 m
Taxi E- 223 x 23 m
Lima Taxi – 88 x 23 m (for joining the Main Apron & VIP Apron)
Taxi M- Isolation bay 61 x 23 m
4.3.6. Apron
There is two types of Apron exists at Lucknow airport. Apron having dimension of 985m x 140m, for 14
bays and VIP Apron capacity of 4 bays for C-90/ B-200 aircraft.
4.3.7. Isolation Bay
Isolation Bay is constructed with the dimension of 61 m x 61 m. Available for C Type Aircraft at Right
side on 09 End.
4.3.8. Pavement
Aprons and aircraft stands shall be constructed as rigid pavement. Concrete pavements are necessary
on aprons since fuel spillage during re-fueling is likely to occur. Flexible pavements are not able to
withstand fuel spillage or high temperatures of summer in combination with static loads from aircraft
without being damaged.
Taxiways can be constructed both as rigid and flexible pavements. Both pavement types have
advantages and disadvantages but none of the disadvantages are of such a character that one type is
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
44--44
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
preferred over other. It should therefore be left to the detailed design to find the most economically
beneficial pavement type.
4.3.9. Parking Space
In Lucknow Airport presently Terminal Building has a capacity of 250 vehicles and Terminal Building
has capacity of 350 vehicles with 10 no of Buses parking.
4.3.10. DVOR
Available. VOR check point –b-287°/0.6NM for LKN VOR.
4.3.11. Perimeter Road/ Boundary Wall
Approximately 10,475 m peripheral road is present at this airport.
4.3.12. Security Watch Tower
Total 14 Nos. of security watch tower exists in this airport (4Nos. of Watch Tower and 10 Nos. of Watch
Paints due Height Restrictions).
4.3.13. Fire Station
CAT –VIII level fire station presently available at Lucknow Airport.
4.4 CIVIL WORKS FOR EXPANSION
4.4.1. Passenger Terminal Building
A new passenger terminal is planned to be completed with an area of 1, 00,000 Sq. m Construction of
a new centrally air-conditioned Modular Integrated Terminal Building of 1,00,000 Sq. m (excluding
20000 Sq. m Basement area). Considering fast growing air traffic and demand for better passenger
facilities an area of 15,000 Sq. m kept for retail commercial outlets/ retiring rooms and airlines offices to
tap future potential at the Airport. The building to be provided with aesthetically appealing & soothing
interior decoration matching the modern structure. Space planning to ensure that no dead space/ Area
is created in the building. The Terminal buildings Departure area, Arrival area, Security hold area and
Concourse area are to be provided with adequate nos. of toilets for gents, ladies and differently-abled
persons and drinking water. Suitable number of ramps to be provided for entry and exit of differently-
abled persons in departure and arrival area. Provision of battery operated buggies for senior citizens I
differently-abled persons as per requirement.
The design of Terminal building will include Media planning, Retail area planning, F & B plan, etc.
Overall planning of Building will capture local architectural features and it will be part of design features
of terminal. The design should include the required arrangement for its regular maintenance so as to
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
44--55
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
make it in-built part of execution. Solar power generation viz solar lighting, solar roofing system, etc.
will be provided. Maintenance friendly roofing & building facade system including provision of regular
cleaning with maintenance hoists, hooks, etc. including cat walk/ rope suspended platform/ gondola
etc. will be provided.
4.4.2. Departure Area
The Terminal building with provision of Departure concourse, Check-in area with adequate number of
Check-in counters, immigration counters, back-up offices for airlines, baggage conveyor belts,
facilitation counter, weighing machines, counters etc.
4.4.3. Security Hold area
Security Hold area with Aerobridges and Bus Lounge with adequate seating arrangements and
separate security check & holding area and associated facilities.
The passenger frisking area in Security Hold with adequate space for locating required number
of DFMDs, frisking platforms, Inspection table for manual checking of hand baggage and
adequate space I rooms for Security staff. X-ray machine for hand baggage, isolated Smoking
area with proper ventilation in the security hold area.
Duty free/ Retail Area Creation of Retails lands Shops without affecting the passenger movement.
4.4.4. Food & Beverage Area
4.4.5. Arrival Area/ Baggage Claim Area
In ground floor Baggage Claim Area having adequate number of Baggage Conveyor Belts of
adequate size to be provided, space for storing baggage trolleys, mishandled baggage and
counters/ space for airlines and back up offices, and associated facilities.
Adequate space should be provided in the ground floor for required number of immigration &
custom counters, back-up offices, space for storing' baggage trolleys, space for storage of
mishandled baggage for airlines.
4.4.6. Common Concourse Area
Common concourse area in the ground floor to have provision for snack bar, travel requisite, Bank/
ATM, post office, TR and Curio stall, drinking water, Meet-and-Greet area, first-aid room, facilitation
counters, space for care taker office with store, Terminal Manager office with supporting office for AAI
and airlines, Conference Room and other facilities at suitable location.
Airport Director's office with associated office space, Conference hall, Retiring rooms, toilet for staff to
be provided.
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
44--66
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
4.4.7. Parking Area
Construction of multilevel car park for at least 1500 cars and surface parking for VIP cars &10 buses,
Separate car/ scooter park area for AAI and airlines staff at appropriate location. Multilevel Car Parking
to be made for retailer in car parking area & it has to be developed on Built & Operate System and shall
include its space planning and mode/for its operations.
Development of four-lane vehicular road from Terminal Building/ Car parking with canopy covering two
lanes in front of the Terminal Building on the city side and connecting the main approach road to the
city.
4.4.8. Dismantling Works
Dismantling of terminal Building (T-1), AC plant room, CCR hall, Substation. Existing Cargo Building,
etc. falling in the location of the propose Terminal Building and reconstruct the AC plant room, CCR hall
and Substation in the service area with adequate capacities considering the overall demand. New
integrated terminal Building will be of capacity of capacity 1,15,000 Sq. m. (including 20,000 Sq. m.
basement area) with new commercial facilities. This will be adequate to handle 4000 peak hour
passengers (3200 Domestic and 800 International) with the recommended area specifications and to
match the level of services B as per IATA recommendations (growth trend indicate a traffic of 0.89
million International passengers and 4.66 million Domestic passenger by 2025-26).
4.5 MISCELLANEOUS CIVIL WORKS
Development of four-lane vehicular road from Terminal Building/ Car parking with canopy covering
two lanes in front of the Terminal Building on the city side and connecting the main approach road
to the city.
Provision of VIP/CIP lounges, provision of adequate number of chairs, furniture, furnishings etc. in
the departure lounge common concourse, check-in area, and security hold area and arrival lounge.
Provision of water supply pumping arrangement system, Water Filtration, water cooler & R.O/ U.V.
Filters, Sewage Treatment Plant (STP), Effluent Treatment Plant (ETP) as per norms and as per
site conditions.
Horticulture-landscaping, drainage system, water supply, rain harvesting etc.
Driver's canteen and toilet facility on the city side.
Sub-station, AC plant room and related service facilities. Provision should be made for the AC Plant
Room vertical through AHU rooms, backup generators for essential services, etc. in the lower
ground floor.
Provision of acoustics for effective functioning of PA system.
Providing city side compound wall depicting local architecture and with proper gates.
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
44--77
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
4.5.1. Electrical and Mechanical Works
Internal and external electrification for Terminal Building Complex, associated buildings, Car Park
and roads.
Augmentation of main power supply, Substation Equipment, DG Sets for Secondary Power supply
and associated ancillary buildings.
Provision of central air-conditioning & ventilation (HVAC) system & BMS for New Terminal Building.
Provision of conveyor belts with In-line X-ray inspection System and other equipment at departure
area and inclined carousels at Arrival hall.
Provision of fire detection & alarm system, provision for fire hydrants and water sprinklers system
as per standards along with fire extinguishers.
Escalators & Elevators with matching staircase.
Provision of Passenger Boarding Bridges (PBB) for the specified parking stands.
. Provision of automatic sliding doors at exit and entry points of terminal.
Provision of adequate number of Signage of world class standard, inside and outside the terminal
building, car park area & City side approach road and air side area for guidance of passengers and
visitors.
4.5.2. Airport System
Passive and Active networking components such as OFC, UTP cabling, Routers, Core & Access
switches and accessories. Provision of Raceways, cable trays, and conducting and cabling.
Server room and adequate space for keeping network switches along with electrical power points &
UPS.
Access Control System as per BCAS requirement.
Provision of Internet, VPN bandwidth, Wi-Fi system.
Public address system and car calling system.
Surveillance Close circuit TV system (SCCTV) and provision of adequate number of close circuit
TV monitors, in the Security Control Room, Terminal Manager Room, APD Office etc.
Provision of Flight Information Display System (FIDS) with adequate number of Display Devices in
departure, arrival and security hold area for passenger facilitation.
Provision of adequate number of X-ray machines for scanning Registered Baggage (RB) I Hand
Baggage (HB),' including provision of required number of ETDs, DFMDs & HHMDs, as per BCAS
norms.
Provision of adequate no. of VHF FM Sets (Walkie-Talkie, Base Stations & Mobile Stations).
Provision of Telephone Exchange I digital EPABXI IP EPABX system for Terminal Building
including telephone intercom instruments, wiring etc.
4.5.3. SUPPORT AMENITIES
The following facilities will be available in the proposed airport
Baggage handling system
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
44--88
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
Passenger boarding bridges
Flight information and displays
Sewage treatment facility
Firefighting system
Security equipments
Bookshop
Restaurant
PROPOSED
INFRASTRUCTURE
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
55--11
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
5. PPRROOPPOOSSEEDD IINNFFRRAASSTTRRUUCCTTUURREE
5.1 THE PLAN
The Concept Plan for the Lucknow Airport defines the ultimate scope of the proposal and the
development of facilities in accordance with the requirements of traffic. Earlier discussion on Traffic
Analysis and Project Sizing are used as the basis for planning of the various components.
It is the overall objective of this effort to produce a balanced airside and landside complex to serve
forecast aviation demands. However, before defining and evaluating specific alternatives, airport
development objectives need to be outlined. The primary goal of the Master Plan is to define a
development concept which allows for the airport to be marketed, developed, and safely operated for
the betterment of the region and its users. With this in mind, the following development objectives have
been defined for this planning effort:
Maintain an attractive, efficient, and safe aviation facility in accordance with government, state, and
local regulations.
Develop facilities to efficiently serve general aviation users and encourage increased use of the
airport, including business and corporate activity.
Provide sufficient airside and landside capacity, efficiency, and safety through additional facility
improvements which will meet the long term planning horizon level of demand for the airport and
region.
Ensure that any recommended future development is environmentally compatible.
Enhance local economic development through maximizing the use of available property.
Identify opportunities for approved non-aeronautical use of certain areas on the airport to further
diversify airport facility revenue generating potentials.
The proposed project involves construction and development of a number of facilities which are given
below:
5.2 DETAILS OF PROPOSED INFRASTRUCTURE
5.2.1 Passenger Terminal Building
A new passenger terminal is planned to be completed with an area of 1,00,000 Sq. m. Construction of
a new centrally air-conditioned Modular Integrated Terminal Building of 1,00,000 Sq. m (excluding
20000 Sq. m Basement area). Considering fast growing air traffic and demand for better passenger
facilities an area of 15,000 Sq. m. kept for retail commercial outlets/ retiring rooms and airlines offices
to tap future potential at the Airport. The building to be provided with aesthetically appealing & soothing
interior decoration matching the modern structure. Space planning to ensure that no dead space/ Area
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
55--22
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
is created in the building. The Terminal buildings Departure area, Arrival area, Security hold area and
Concourse area are to be provided with adequate nos. of toilets for gents, ladies and differently-abled
persons and drinking water. Suitable number of ramps to be provided for entry and exit of differently-
abled persons in departure and arrival area. Provision of battery operated buggies for senior citizens &
differently-abled persons as per requirement.
The design of Terminal building will include Media planning, Retail area planning, F & B plan, etc.
Overall planning of Building will capture local architectural features and it will be part of design features
of terminal. The design should include the required arrangement for its regular maintenance so as to
make it in-built part of execution. Solar power generation viz solar lighting, solar roofing system, etc.
will be provided. Maintenance friendly roofing & building facade system including provision of regular
cleaning with maintenance hoists, hooks, etc. including cat walk/ rope suspended platform/ gondola
etc. will be provided.
5.2.2 Departure Area
The Terminal building with provision of Departure concourse, Check-in area with adequate number of
Check-in counters, immigration counters, back-up offices for airlines, baggage conveyor belts,
facilitation counter, weighing machines, counters etc.
5.2.3 Security Hold area
Security Hold area with Aerobridges and Bus Lounge with adequate seating arrangements and
separate security check & holding area and associated facilities.
The passenger frisking area in Security Hold with adequate space for locating required number of
DFMDs, frisking platforms, Inspection table for manual checking of hand baggage and adequate
space I rooms for Security staff. X-ray machine for hand baggage, isolated Smoking area with
proper ventilation in the security hold area.
5.2.4 Duty free/ Retail Area
Creation of duty free Retail Area/ Retails lands Shops without affecting the passenger movement.
5.2.5 Food & Beverage Area
5.2.6 Arrival Area/ Baggage Claim Area
In ground floor Baggage Claim Area having adequate number of Baggage Conveyor Belts of
adequate size to be provided, space for storing baggage trolleys, mishandled baggage and
counters/ space for airlines and back up offices, and associated facilities.
Adequate space should be provided in the ground floor for required number of immigration &
custom counters, back-up offices, space for storing' baggage trolleys, space for storage of
mishandled baggage for airlines.
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
55--33
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
5.2.7 Common Concourse Area
Common concourse area in the ground floor to have provision for snack bar, travel requisite, Bank/
ATM, post office, TR and Curio stall, drinking water, Meet-and-Greet area, first-aid room, facilitation
counters, space for care taker office with store, Terminal Manager office with supporting office for AAI
and airlines, Conference Room and other facilities at suitable location.
Airport Director's office with associated office space, Conference hall, Retiring rooms, toilet for staff to
be provided.
5.2.8 Parking Facilities
Construction of multilevel car park for at least 1500 cars and surface parking for VIP cars &10 buses,
Separate car/ scooter park area for AAI and airlines staff at appropriate location. Multilevel Car Parking
to be made for retailer in car parking area & it has to be developed on Built & Operate System and shall
include its space planning and mode/for its operations. .
Development of four-lane vehicular road from Terminal Building/ Car parking with canopy covering two
lanes in front of the Terminal Building on the city side and connecting the main approach road to the
city.
5.2.9 Dismantling Works
Dismantling of Terminal Building (T1), AC plant room, CCR hall, Substation. Existing Cargo Building
etc. falling the location of the propose Terminal Building and reconstruct the AC plant room, CCR hall
and Substation in the service area with adequate capacities considering the overall demand. Inplace of
this mantling, new Integrated terminal Building will be constructed having area of 1,15,000 Sq. m.
(including 20,000 Sq. m. basement area). This will be adequate to handle 4000 peak hour passengers
(3200 Domestic and 800 International) with the recommended area specifications and to match the
level of services B as per IATA recommendations (growth trend indicate a traffic of 0.89 million
International passengers and 4.66 million Domestic passenger by 2025-26).
5.2.10 Miscellaneous civil works
Development of four-lane vehicular road from Terminal Building/ Car parking with canopy covering
two lanes in front of the Terminal Building on the city side and connecting the main approach road
to the city.
Provision of VIP/CIP lounges, provision of adequate number of chairs, furniture, furnishings etc. in
the departure lounge common concourse, check-in area, and security hold area and arrival lounge.
Provision of water supply pumping arrangement system, Water Filtration, water cooler & R.O/ U.V.
Filters, Sewage Treatment Plant (STP), Effluent Treatment Plant (ETP) as per norms and as per
site conditions.
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
55--44
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
Horticulture-landscaping, drainage system, water supply, rain harvesting etc.
Driver's canteen and toilet facility on the city side.
Sub-station, AC plant room and related service facilities. Provision should be made for the AC Plant
Room vertical through AHU rooms, backup generators for essential services, etc in the lower
ground floor.
Provision of acoustics for effective functioning of PA system.
Providing city side compound wall depicting local architecture and with proper gates.
5.2.11 Electrical and Mechanical Works
Internal and external electrification for Terminal Building Complex, associated buildings, Car Park
and roads.
Augmentation of main power supply, Substation Equipment, DG Sets for Secondary Power supply
and associated ancillary buildings.
Provision of central air-conditioning & ventilation (HVAC) system & BMS for New Terminal Building.
Provision of conveyor belts with In-line X-ray inspection System and other equipment at departure
area and inclined carousels at Arrival hall.
Provision of fire detection & alarm system, provision for fire hydrants and water sprinklers system
as per standards along with fire extinguishers.
Escalators & Elevators with matching staircase.
Provision of Passenger Boarding Bridges (PBB) for the specified parking stands.
. Provision of automatic sliding doors at exit and entry points of terminal.
Provision of adequate number of Signage of world class standard, inside and outside the terminal
building, car park area & City side approach road and air side area for guidance of passengers and
visitors.
5.2.12 Airport System
Passive and Active networking components such as OFC, UTP cabling, Routers, Core & Access
switches and accessories. Provision of Raceways, cable trays, and conducting and cabling.
Server room and adequate space for keeping network switches along with electrical power points &
UPS.
Access Control System as per BCAS requirement.
Provision of Internet, VPN bandwidth, Wi-Fi system.
Public address system and car calling system.
Surveillance Close circuit TV system (SCCTV) and provision of adequate number of close circuit
TV monitors, in the Security Control Room, Terminal Manager Room, APD Office etc.
Provision of Flight Information Display System (FIDS) with adequate number of Display Devices in
departure, arrival and security hold area for passenger facilitation.
Provision of adequate number of X-ray machines for scanning Registered Baggage (RB) I Hand
Baggage (HB),' including provision of required number of ETDs, DFMDs & HHMDs, as per BCAS
norms.
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
55--55
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
Provision of adequate no. of VHF FM Sets (Walkie-Talkie, Base Stations & Mobile Stations).
Provision of Telephone Exchange I digital EPABXI IP EPABX system for Terminal Building
including telephone intercom instruments, wiring etc.
5.2.13 SUPPORT AMENITIES
The following facilities will be available in the proposed airport
Baggage handling system
Passenger boarding bridges
Flight information and displays
Sewage treatment facility
Firefighting system
Security equipments
Bookshop
Restaurant
REHABILITATION &
RESETTLEMENT
PLAN
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
66--11
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
66.. RREEHHAABBIILLIITTAATTIIOONN && RREESSEETTTTLLEEMMEENNTT PPLLAANN
6.1 INTRODUCTION
Total 69.37 acres area is required for the proposed new terminal building which is already available in existing
Lucknow Airport with land area of 1261.18 acres belongs to Airports Authority of India, Lucknow. No
rehabilitation is proposed because the land is already available with Lucknow Airport.
PROJECT
SCHEDULE &
COST ESTIMATES
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
77--11
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
77.. PPRROOJJEECCTT SSCCHHEEDDUULLEE && CCOOSSTT EESSTTIIMMAATTEESS
7.1 INTRODUCTION
The proposed completion schedule for the project is 6 month. The estimated cost of the project is
1,230.00 crores. The budgetary cost estimates for the project have been prepared as per following
details.
Table 7-1: Cost estimation for the Proposed Development
S. No. Description Amount
1 Civil Work 5,598,779,650.50
2 Electrical Work 2,248,386,277.00
Total (Civil + Electrical) 7,847,165,927.50 A
3 Art Work 78,471,659.28
4 Construction of Flyover in front of Terminal 200,000,000.00
5 IT Works 25,000,000.00
6 Airport System Works 710,745,000.00
7 Baggage Trollies and Airport Terminal Chairs 78,471,659.28
Total 1,092,688,318.56 B
Total (A+B) 8,939,854,246.06
Say 893.99 Crores C
8 Add labour cess, PF & ESI reimbursement, service tax reimbursement, Work Contract Tax, Contingency, Consultancy and Anticipated cost escalation etc.
336.01 Crores D
Grand Total (C+D) 1230.00 Crores
7.2 QUANTITIES
Quantities of the civil work as terminal building including departure area, security hold area, food &
beverages area, arrival/baggage claim area, electrical work, IT system development, new AC plant etc.
and demolition of old terminal building-1 of Lucknow airport are calculated based on preliminary
planning, design and assessment of requirements based on codes and specifications. Detail designs
not done at this stage.
7.3 RATES
The rates of civil work of new terminal building is based on the rates of schedule, 2013-14 for Lucknow
district. Additional provisions for superior specifications have also been made in the estimate. The
estimates of remaining items / facilities are based on market enquiries.
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
77--22
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
7.4 CONTINGENCIES
For the purpose of estimation, Contingencies @ 3% of the total cost of the works has been added.
7.5 WORKS TAX
Works Tax has been added to the total cost of the project (including contingencies) is applicable on
construction projects in Uttar Pradesh. However the same has not been included in the cost estimates
being a statutory government levy.
7.6 LABOUR CESS
Labour Cess @ 1% of the total cost of the project (including contingencies) is applicable on
construction projects all over India. However the same has not been included in the cost estimates
being a statutory government levy.
7.7 SERVICE TAX ON CONSTRUCTION COST
Service Tax @ 14% on the 40% of construction cost of the project is applicable on construction
projects all over India. However the same has not been included in the cost estimates being a statutory
government levy.
7.8 PROJECT MANAGEMENT COSTS
For the purpose of estimation no consultancy charges for design and PMC have been added as the
project is envisaged to be developed under PPP model.
7.9 PRICE ESCALATION / VARIATION
No price escalation has been added in the estimates as the financial analysis has been done on NPV
basis.
7.10 COSTS NOT INCLUDED
The cost of land acquisition, rehabilitation (if any), environmental mitigation (if any), obstruction removal
as proposed in the report, cutting of trees, utility shifting from the proposed Airport site, WCT, Labour
cess, service tax on construction cost, escalation, consultancy for design and PMC (including
applicable ST/cess) and cost of Fire tender/ambulance etc. has not been included in the estimate.
7.11 FINANCIAL ANALYSIS
Operating cost estimates have been worked out using benchmarks for similar airports operated by
Airports Authority of India (AAI).
Construction is likely to start in 2016, as clearance from Ministry of Defense, approval of Standing
Committee, detailed designing’s of the project and environment clearance are yet to be obtained.
The project is likely to be completed end of 2017.
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
77--33
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
Traffic data is taken from the traffic survey conducted by agency appointed by RITES. Useful life of
the asset is 30 years, with rate of depreciation considered as 10%.
For discounted cash flow the rate is taken as 10%.
Staff cost have been raised by 20% yearly to meet the adjustment for inflation (DA) and increments
to staff.
Non-aeronautical revenues forecast include lease rental income from the Concessionaire, in the
vicinity of the airport.
Operating expenses have been estimated based on benchmarks for comparable Indian airports,
expected traffic growth and adjusted for inflation. .
Following additional assumptions have been considered in the financial analysis.
Estimated capital expenditure of INR 878.25 crore on the basis of initial estimate.
Non-aeronautical revenues forecast include lease rental income from the Concessionaire, in the vicinity of the airport.
FINAL
RECOMMENDATIONS
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
22--11
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
88.. FFIINNAALL RREECCOOMMMMEENNDDAATTIIOONNSS
Lucknow Airport is an operational airport and need to be upgraded State Govt. and AAI wants to
modernization/ expansion and upgrade of Lucknow Airport to cater the need of the visitors coming to
Lucknow & surrounding areas. The land for the project will be provided by State Govt. at free of cost
and without encumbrances.
As per current traffic data, the domestic passengers handled are 2 million for domestic (2014-15) and 0,47 million for international (2014-15). The above building capacity are saturated, therefore it is proposed to build a new terminal building to cater to the passenger's convenience in future growth of Lucknow airport.
Airports Authority of India committed to inclusive growth and sustainable development in not only the
communities it operates in, but also in contributing towards nation building. The focus of the activities
are mainly on three major dimensions of human development which include expansion of sustainable
livelihood opportunities, improving the status of health and education and broadening the range of
choices by creating rural infrastructure. The aim is to walk with the communities, help people look
ahead, make the right choices and secure a bright and beautiful future, together.
The easy and speedy access of the location also attracts the investment from high profile players of the
market. The probability of the investment by the builders and hoteliers is also likely due to the proposed
development of the airport. Hence, the project would act as a boon for development of the region and
direct and indirect benefits will be drawn from the projects. Following evaluation of the benefits are
listed below:
Employment potential -skilled; semi-skilled and unskilled labour both during construction and
operational phases of the project with specific attention to employment potential of local
population as well as necessity for imparting any specialized skills to them to be eligible for
such employment in the project on a long term basis i.e., during operational and maintenance
stages of the project.
Other tangible benefits like improved standards of living, health, education etc.
Improvements in the physical infrastructure by way of addition of project infrastructure, ancillary
industries that may come up on account of the project.
The general evaluation of the site indicates that the following:
Land will be provided by State Govt. free of cost and without encumbrances after
removing of obstructions.
Pre-Feasibility Report For the Expansion of New Integrated Terminal Building of Lucknow
International Airport at Amausi, Lucknow, Uttar Pradesh.
PPRROOJJEECCTT PPRROOPPOONNEENNTT
AAIIRRPPOORRTTSS AAUUTTHHOORRIITTYY OOFF IINNDDIIAA,,
LLUUCCKKNNOOWW,, UU..PP..
PPAAGGEE NNOO::
22--22
EENNVVIIRROONNMMEENNTT CCOONNSSUULLTTAANNTT
GGRREEEENNCCIINNDDIIAA CCOONNSSUULLTTIINNGG PPRRIIVVAATTEE
LLIIMMIITTEEDD NNCCRR,, GGHHAAZZIIAABBAADD
As already there is an operational airport therefore an adequate access exists to
sources of bulk services including water, power and telecommunications.
In summary, the conditions appear to be feasible for modernization/expansion and up gradation of
Lucknow Airport for handling increasing traffic.
ANNEX- GRID MAP