DETAILED OF THE CONSTRUCTION ESTIMATE CONCRETE MATERIALS : FOOTING 1 CLASS "A" MIXTURE FOOTING DEMINSION LENGTH: 1.2 m WIDTH: 1m THICK: 0.35 m VOL. OF FOOTING 0.42 cu.m. TOTAL VOLUME OF THE 12 FOOTING VOLUME= 5.04 cu.m. CEMENT: 5.04 x 9 = 45.36 bags SAND: 5.04 x 0.5 = 2.52 cu.m. GRAVEL: 5.04 x 1 = 5.04 cu.m. REINFORCE BARS MATERIALS : FOOTING 1 NET LENGTH : 1.2 - 0.075 + 0.075 = 1.05 m TOTAL NO. OF CUT BARS IN ONE FOOTING BY DIRECT COUNTING 6x 2 = 12 pcs TOTAL NO. OF BARS FOR THE 12 FOOTING 12 x 12 = 144 pcs @ 1.05 m SELECT THE STEEL BARS WHOSE LENGTH IS ECONOMICALLY CUT INTO 1.05 M 6 / 1.05 = 5.714 pcs Divide the result: 144 = 29 pcs of 16mm diameter bars 5 TIE WIRE NUMBER OF THE BAR INTERSECTION IN ONE FOOTING 6 x 6 = 36 ties TOTAL TIES FOR 12 FOOTINGS 12 x 36 = 432 ties Using 0.25 m length per = 432 x 0.250 = 108 meters One kilo of no. 16 G.I. wire is approxi 30 m 108 / 30 = 3.6 kilos

Upload: ramil-s-artates

Post on 25-Jan-2016

4 views

Category:

Documents


0 download

DESCRIPTION

estimates

TRANSCRIPT

Page 1: Formula Estimate

DETAILED OF THE CONSTRUCTION ESTIMATE

CONCRETE MATERIALS : FOOTING 1

CLASS "A" MIXTURE

FOOTING DEMINSION

LENGTH: 1.2 m

WIDTH: 1 m

THICK: 0.35 m

VOL. OF FOOTING 0.42 cu.m.

TOTAL VOLUME OF THE 12 FOOTING

VOLUME= 5.04 cu.m.

CEMENT: 5.04 x 9 = 45.36 bags

SAND: 5.04 x 0.5 = 2.52 cu.m.

GRAVEL: 5.04 x 1 = 5.04 cu.m.

REINFORCE BARS MATERIALS : FOOTING 1

NET LENGTH :

1.2 - 0.075 + 0.075 = 1.05 m

TOTAL NO. OF CUT BARS IN ONE FOOTING BY DIRECT COUNTING

6 x 2 = 12 pcs

TOTAL NO. OF BARS FOR THE 12 FOOTING

12 x 12 = 144 pcs @ 1.05 m

SELECT THE STEEL BARS WHOSE LENGTH IS ECONOMICALLY CUT INTO 1.05 M LONG

6 / 1.05 = 5.714 pcs

Divide the result:

144= 29 pcs of 16mm diameter bars

5

TIE WIRE

NUMBER OF THE BAR INTERSECTION IN ONE FOOTING

6 x 6 = 36 ties

TOTAL TIES FOR 12 FOOTINGS

12 x 36 = 432 ties

Using 0.25 m length per tie= 432 x 0.250 = 108 meters

One kilo of no. 16 G.I. wire is approximately 30 m

108 / 30 = 3.6 kilos

Page 2: Formula Estimate

CONCRETE MATERIALS : FOOTING 2

CLASS "A" MIXTURE

FOOTING DEMINSION

LENGTH: 1 m

WIDTH: 1 m

THICK: 0.35 m

VOL. OF FOOTING 0.35 cu.m.

TOTAL VOLUME OF THE 4 FOOTING

VOLUME= 1.4 cu.m.

CEMENT: 1.4 x 9 = 12.6 bags

SAND: 1.4 x 0.5 = 0.7 cu.m.

GRAVEL: 1.4 x 1 = 1.4 cu.m.

REINFORCE BARS MATERIALS : FOOTING 2

NET LENGTH :

1 - 0.075 + 0.075 = 0.85 m

TOTAL NO. OF CUT BARS IN ONE FOOTING BY DIRECT COUNTING

5 x 2 = 10 pcs

TOTAL NO. OF BARS FOR THE 4 FOOTING

10 x 4 = 40 pcs @ 0.85 m

SELECT THE STEEL BARS WHOSE LENGTH IS ECONOMICALLY CUT INTO 0.85 M LONG

6 / 0.85 = 7.0588 pcs

Divide the result:

40= 6 pcs of 16mm diameter bars

7

TIE WIRE

NUMBER OF THE BAR INTERSECTION IN ONE FOOTING

5 x 5 = 25 ties

TOTAL TIES FOR 4 FOOTINGS

4 x 25 = 100 ties

Using 0.25 m length per tie = 100 x 0.250 = 25 meters

One kilo of no. 16 G.I. wire is approximately 30 m

25 / 30 = 0.8 kilos

Page 3: Formula Estimate

COLUMN 1 TIES :

HEIGHT FROM GROUND LINE TO BEAM

HT. = 6.6 Mtrs. @ 0.2 m. spacing

- Divide:6.6 = 44 pcs0.2

- Total ties of the columns= 12

- Multiply:12 x 44 = 528 pcs

- Length of one lateral ties1.45 m. long cut from a 6.00 m. steel bars

6 = 5 pcsw= 0.275 1.45

- Result528 = 104 pcs- 10 mm ties bars

d= 0.45 10 pcs 5tiesl bars

- Tie wireno. of ties in a column

6 x 44 = 264

total wire for the 12 columns264 x 12 = 3168 pcs

multiply:3168 x 0.25 = 792 m

One kilo of no. 16 G.I. wire is approximately 35 m

792 / 35 = 22.6 kilos

Page 4: Formula Estimate

w= 0.275 12 column post

A= 7.5

d= 0.45 6bars

B= 0.200

TOTAL = 7.6 mtrs. Length

Result:no. of vertical bars 8 pcs of one column

Total of vertical bars = 99.94 pcs 16mm vertical bars