formula memorization trick cv=ev-ac sv=ev-pv cpi=ev/ac spi=ev/pv eac=bac/cpi etc=eac-ac vac=bac-eac...

9
Formula Memorization Trick CV = EV - AC SV = EV - PV CPI = EV / AC SPI = EV / PV EAC = BAC / CPI ETC = EAC - AC VAC = BAC - EAC When memorizing the formulas I have found it best to look for patterns. When I see the correct pattern I know the formula is correct. AC = ACWP PV = BCWS EV = BCWP

Upload: jonathan-jefferson

Post on 15-Dec-2015

216 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Formula Memorization Trick CV=EV-AC SV=EV-PV CPI=EV/AC SPI=EV/PV EAC=BAC/CPI ETC=EAC-AC VAC=BAC-EAC When memorizing the formulas I have found it best to

Formula Memorization TrickFormula Memorization Trick

CV = EV - AC

SV = EV - PV

CPI = EV / AC

SPI = EV / PV

EAC = BAC / CPI

ETC = EAC - AC

VAC = BAC - EAC

When memorizing theformulas I have found it best to look for patterns. When I see the correct pattern I know the formula is correct.AC = ACWPPV = BCWSEV = BCWP

Page 2: Formula Memorization Trick CV=EV-AC SV=EV-PV CPI=EV/AC SPI=EV/PV EAC=BAC/CPI ETC=EAC-AC VAC=BAC-EAC When memorizing the formulas I have found it best to

Formula Memorization TrickFormula Memorization Trick

Ok lets build this. First is to see the pattern of 2 subtractions, 3 divides, 2 subtractions

CV = EV - AC

SV = EV - PV

CPI = EV / AC

SPI = EV / PV

EAC = BAC / CPI

ETC = EAC - AC

VAC = BAC - EAC

Page 3: Formula Memorization Trick CV=EV-AC SV=EV-PV CPI=EV/AC SPI=EV/PV EAC=BAC/CPI ETC=EAC-AC VAC=BAC-EAC When memorizing the formulas I have found it best to

Formula Memorization TrickFormula Memorization Trick

Next see the pattern of Variance and Index. Cost, Schedule and Cost, Schedule.

CV = EV - AC

SV = EV - PV

CPI = EV / AC

SPI = EV / PV

EAC = BAC / CPI

ETC = EAC - AC

VAC = BAC - EAC

Page 4: Formula Memorization Trick CV=EV-AC SV=EV-PV CPI=EV/AC SPI=EV/PV EAC=BAC/CPI ETC=EAC-AC VAC=BAC-EAC When memorizing the formulas I have found it best to

Formula Memorization TrickFormula Memorization Trick

Next see the pattern of Earned Value (EV). This used to be BCWP.

CV = EV - AC

SV = EV - PV

CPI = EV / AC

SPI = EV / PV

EAC = BAC / CPI

ETC = EAC - AC

VAC = BAC - EAC

Page 5: Formula Memorization Trick CV=EV-AC SV=EV-PV CPI=EV/AC SPI=EV/PV EAC=BAC/CPI ETC=EAC-AC VAC=BAC-EAC When memorizing the formulas I have found it best to

Formula Memorization TrickFormula Memorization Trick

Next see the pattern of Actual Cost (AC) and Planned Value (PV) and how they alternate. Skip a line and its AC again.

CV = EV - AC

SV = EV - PV

CPI = EV / AC

SPI = EV / PV

EAC = BAC / CPI

ETC = EAC - AC

VAC = BAC - EAC

Page 6: Formula Memorization Trick CV=EV-AC SV=EV-PV CPI=EV/AC SPI=EV/PV EAC=BAC/CPI ETC=EAC-AC VAC=BAC-EAC When memorizing the formulas I have found it best to

Formula Memorization TrickFormula Memorization Trick

Next see the pattern of Estimated at Completion (EAC).As well as Budget at Completion (BAC)

CV = EV - AC

SV = EV - PV

CPI = EV / AC

SPI = EV / PV

EAC = BAC / CPI

ETC = EAC - AC

VAC = BAC - EAC

Page 7: Formula Memorization Trick CV=EV-AC SV=EV-PV CPI=EV/AC SPI=EV/PV EAC=BAC/CPI ETC=EAC-AC VAC=BAC-EAC When memorizing the formulas I have found it best to

Formula Memorization TrickFormula Memorization Trick

Not much left. Notice that CPI is divisor of EAC so find CPI skip a line and place it at the end of EAC formula.

CV = EV - AC

SV = EV - PV

CPI = EV / AC

SPI = EV / PV

EAC = BAC / CPI

ETC = EAC - AC

VAC = BAC - EAC

ETC and VAC don’t really match to anything, you just have to know where they go.

Page 8: Formula Memorization Trick CV=EV-AC SV=EV-PV CPI=EV/AC SPI=EV/PV EAC=BAC/CPI ETC=EAC-AC VAC=BAC-EAC When memorizing the formulas I have found it best to

Formula Memorization TrickFormula Memorization Trick

This may look confusing but it worked great for me and I have had others tell me it worked for them as well.

CV = EV - AC

SV = EV - PV

CPI = EV / AC

SPI = EV / PV

EAC = BAC / CPI

ETC = EAC - AC

VAC = BAC - EAC

Page 9: Formula Memorization Trick CV=EV-AC SV=EV-PV CPI=EV/AC SPI=EV/PV EAC=BAC/CPI ETC=EAC-AC VAC=BAC-EAC When memorizing the formulas I have found it best to

Other Formulas to KnowOther Formulas to Know

• Communication Channels: N(N-1)/2

• Pert Mean: (Pessimistic + 4*Most Likely + Optimistic) / 6

• Standard Deviation: (Pessimistic – Optimistic) / 6

• Variance: ((Pessimistic – Optimistic) / 6) squared

• Present Value or PV: Future Value / (1+ rate of return) to the power of n. Where n = periods of time.