formwork guide

Upload: tino3528

Post on 08-Aug-2018

232 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/22/2019 Formwork Guide

    1/37

    INDUSTRY GUIDE

    FOR FORMWORK

    CONSTRUCTION INDUSTRY SOUTh AUSTRAlIA

    JUNE 2012

  • 8/22/2019 Formwork Guide

    2/37

    1

    INDUSTRY GUIDE

    FOR FORMWORK

  • 8/22/2019 Formwork Guide

    3/372

    Awdt

    This guidance material has been developed by a tri-partite industry

    working party and has involved extensive consultation with industry

    and other special interest groups. The contribution of the following

    organisations is acknowledged:

    BuiltEnvironsPtyLtd

    Construction,Forestry,MiningandEnergyUnion

    HansenYunckenPtyLtd

    HindmarshAustralia

    MitconFormworkPtyLtd

    NewgenFormworkers

    SystemFormworkPtyLtd

    SafeWorkSA

    Diaa t :

    BovisLendLease

    WorkplaceHealthandSafetyQueensland

    SafeWorkSA

    Phtaph t :

    Construction,Forestry,MiningandEnergyUnion

    MitconFormworkPtyLtd

    SystemFormworkPtyLtd

    HindmarshAustralia

    Diai

    Information provided in this publication has been prepared by industry

    representatives and is designed to prevent injury to anyone engaged in

    erecting and dismantling formwork and associated equipment.

    This publication is correct at the time of printing and is provided as general

    information only. In utilising general information about workplace health

    andsafety,thespecicissuesrelevanttoyourworkplaceshouldalwaysbe

    considered.

    Theremaybeadditionalrisksataworkplacethathavenotbeenspecically

    addressedinthisguidance.UndertheSouthAustralianoccupational

    healthandsafetylaws,suchrisksmustbeidentiedandcontrolmeasures

    implemented and reviewed to eliminate or minimise exposure to these risks.

    Usersofthisguidancematerialshouldbeawarethatitisbasedoncurrent

    knowledge and construction methods within the industry and is not intended

    to exclude other methods or processes that can also meet the required

    safetystandards.Thisindustryguide,onanyparticularaspectoflegislation,

    is not to be taken as a statement of law. To ensure compliance with your

    legalobligationsyoumustrefertotherelevantActs,Regulationsand

    ApprovedCodesofPractice.Thispublicationmayrefertolegislationthathasbeenamendedorrepealed.Whenreadingthispublicationyoushouldalways

    refer to the latest laws.

    PrefAce

    ThisIndustryGuideforFormworkisbasedontheSouth

    AustralianOccupational Health, Saety and Welare

    Regulations 2010.GiventhatSouthAustraliaislikelytoadopttheharmonisedlegislation,itisrecommended

    that readers of this document also become familiar with

    therequirementsoftheWorkHealthandSafety(WHS)

    legislation once it comes into effect.

    SafeWorkSA,incollaborationwithmembersofthe

    ConstructionIndustry,hasproducedthisguidanceto

    provideemployers,self-employed,andemployeeswith

    practical advice on preventing injury to anyone engaged

    in erecting and dismantling formwork and associatedequipment.

    AspartoftheSAConstructionIndustryOHSCommittees

    strategytoaddressareasofhighrisk,itwasagreed

    that the creation of appropriate industry guidelines for

    erecting and dismantling formwork and associated

    equipment was a priority.

    It was further agreed that the codes of practice and

    guidelines,existinginotherstates(Queensland,NewSouthWalesandVictoria)andoperatingeffectively,could

    be utilised in the development of a similar resource for

    SouthAustralia.

    Th ti thi idt id a t:

    givepracticaladviceaboutwaysto

    aa xp t i aiatd

    with w ii th a,

    ti, atati ad diati

    w

    contributetothedevelopmentof

    itt hih tadad a w

    i th tti idt that

    a di t t pati at

    th wpa.

    It i t itdd that thi id appid t

    i-t hi.

  • 8/22/2019 Formwork Guide

    4/373

    conTenTs

    1. Itdti 4

    1.1 Fallsfromheightlimitationsofharness 4

    systems for formwork activity

    2. Di 5

    2.1 Safedesignofbuildingsinrelat iontoformwork 5

    2.1.1 Buildability 5

    2.1.2Materials 5

    2.2 Formworksystems 6

    2.2.1 Safeformworkdesignandverication 6

    2.2.2Formworkdesigncerticationrequirements 6

    2.2.3 Documentation 7

    2.2.4 Designvariations 8

    2.2.5 On-sitecoordinationandverication 83. cdiati ad adiitati 9

    3.1 Workprogram 9

    3.2 Housekeepingaccessandstorage 9

    3.2.1 Accessandegress 9

    3.2.2Materialstorage 9

    3.2.3 Rubbishstorageandremoval 9

    3.2.4 Storagetominimisemanualtaskrisks 9

    3.3 Training 10

    4. W t 10

    4.1 Formworkerectiontraditionalsystems 10 4.1.1 Foundations 11

    4.1.2 Falsedeck 11

    4.1.3 Erectingframes 11

    4.1.4 Installingbearers 12

    4.1.5 Installingjoists 12

    4.1.6 Fallprotectionfromtheformworkdeck 12

    4.1.7 Edgeprotectionontheformworkdeck 13

    4.1.7.1 Formworkconstructionzonephysicalbarriers 13

    4.1.7.2 Edgeprotectiononcompleteddecks 13

    4.1.8 Layingaformworkdeck 13

    4.1.8.1 Gettingstartedsafeaccess 13

    4.1.8.2 Typicalworksystemforaleadingedge 15

    4.1.8.3 Layingaformplydeck 15

    4.1.8.4 Layingametaldeck 16

    4.1.9 Cantileverrequirements 16

    4.1.10 Penetrations 16

    4.1.11 Workingzonesforformworkersandothers 17

    4.1.12 Changingoorlevels 18

    4.2 Formworkerectionmodularformworksystems 18

    4.2.1 Basicmodularsystems 18

    4.2.2 Training 18

    4.3 Strippingformwork 18

    4.3.1 Generalformworkstripping 18

    4.3.2 Safeworkmethodstatements 18

    4.3.3 Certicationpriortostripping 19

    4.3.4 Exclusionzone 19

    4.3.5 Dropstripping 19

    4.3.6 Bondreduction 19

    4.4 Craneandotherloadhandlingsystems 19

    4.4.1Loadingmaterialsduringformworkconstruction 19

    4.4.2 Slingingloads 19

    4.4.3 Liftinggear 20

    4.4.4 Liftingformworkmaterials 20

    4.4.5 Liftinglugs 20

    4.5 Useofladders 20

    5. spia qit wa ad 21

    5.1 Bracingforwindloading 21

    5.2 Accessplatforms 21

    5.3 Liftingmethods 21

    6. spia qit ip ad p 22

    6.1 Accessandegress 22

    6.2 Workplatforms 23

    6.3 Trailingscreensandplatforms 23

    6.4 Climbingtheform 23

    6.5 Training 24

    6.6 Healthissuesandamenities 24

    6.7 Engineeringissues 24

    6.8 Emergencyissues 25

    7. fai t 26

    7.1 Hazardcontrols 26

    7.2 Preventtheobjectfromfalling 26

    7.3 Perimetercontainmentscreens 26

    7.3.1 Screenheightatbuildingstep-ins 26

    7.3.2 Perimeterscreengaps 27

    8. Hath 27

    8.1 Noise 27

    8.2 Dustandatmosphericcontaminants 28

    8.3 Manualtasks 28

    APPenDIces 29

    Appendix1:Denitions 29

    Appdix 2: Taii 30

    Appendix3:Sampleengineerscerticationletters 31

    Appdix 4: ctti hit 33

    Appendix5:Samplestructural(pre-pour)certicate 34

    Appdix 6: Dt d i 35

    w t

  • 8/22/2019 Formwork Guide

    5/374

    1. Itdti

    Formworkisthesurface,supportsandframingusedtodenethe

    shapeofconcreteuntiltheconcreteisself-supporting(seeAS 3610-

    1995 Formwork or Concrete).

    Forthepurposesofthisguide,theformworkassemblyincludes:

    theformsonwhichconcreteispoured

    thesupportstowithstandtheloadsimposedbytheforms

    and concrete

    anybracingaddedtoensurestability.

    Hazardsassociatedwiththeerection,alterationordismantlingof

    formwork include:

    fallsfromheight

    fallingobjects

    formworkcollapse(before,duringandafterpouringofconcrete)

    slipsandtrips

    noise

    dust

    manualtasks

    sharpedgesonmetaldecks

    sunglare.

    Toproperlymanagerisks,apersonmust:

    identifyhazards

    assessrisksthatmayresultbecauseofthehazards decideoncontrolmeasurestoprevent,orminimise,

    the level of risk

    implementthecontrolmeasures

    monitorandreviewtheeffectivenessofthosemeasures.

    Controlmeasuresmustbeimplementedinanorderofpriorityand

    beforeworkcommences.Figure1belowillustratesthehierarchy

    of controls which represents the order of priority for controls where

    there is a risk that a person could fall.

    1.1 fAlls from HeIgHT lImITATIons of HArness

    sysTems for formWork AcTIvITy

    Whenerecting,alteringordismantlingformwork,theuseofthe

    following systems is not recommended:

    travelrestraintharnesssystemstopreventafall fallarrestharnesssystemstoarrestafall.

    Travel restraint harness systems are impractical for formwork as:

    thecontouroftheleadingedgeisconstantlychanging,requiring

    the length of the travel restraint line to be continually adjusted

    multiplelanyardanchoragepointsmayberequired

    thegreaterthenumberofworkersbuildingtheformworkdeck,

    the greater the likelihood of lines becoming tangled.

    Fall arrest systemsareprohibitedundertheSouthAustralian

    Occupational Health, Saety and Welare Regulations 2010(OHSWRegulations)insituationswherethereisinsufcientdistance

    availabletopreventapersonhittinganobject,thegroundoranother

    surface,otherthanaverticalsurface.Forexample:

    Whenerecting,alteringordismantlingformwork,theremaybe

    insufcientfreefalldistanceunderneaththeworkingarea,

    resultinginafallingpersonstrikingtheground,aframeorother

    obstruction prior to the fall being arrested.

    Afallingpersonmayrequireafreefalldistanceinexcessof

    6mforthefalltobesafelyarrestedbyaharnesssystem.In

    somesituations,thisdistancecanbesubstantiallyreducedbythe use of shorter lanyards and/or higher anchorage points.

    Theanchoragepointdesignloadrequiredforfallarrestsystems

    isrelativelyhigh.TheOHSWRegulationsspecifythateach

    anchorage point of the system must have a minimum capacity of

    15kNforonepersonfree-falling.

    Theerectionofformworkframesusingfallarrestharnesses

    requires the user to regularly disconnect from and reconnect to

    anchoragepoints,requiringtheuseofadoublelanyard.

    Figure 1 Hierarchy o controls Controlling the risk o alls

    Di ad pai

    Eliminatetherisk

    during the design and

    planning stage.

    Wh thi i t patia,

    1 t:

    Workonasolidconstructionwithsafeaccess/egress,edgeprotection,openingscoveredetc.

    Wh thi i t patia,

    2 t:

    Usefallpreventionsystemse.g.temporaryworkplatforms,scaffolds,perimeterguardrails,elevating work platforms.

    Wh thi i t patia, 3,

    thenlevel4ornally,level5controls:

    l 3useworkpositioningsystems,

    travel restraint systems

    l 4usefallarrestorcatchplatformsl 5useladdersoradministrationcontrolse.g.nogoareas,permitsystems,safe work systems.

  • 8/22/2019 Formwork Guide

    6/375

    cid th wi i a ha t:

    Ariskassessmentaddressingthehierarchyofcontrolsshouldbe

    usedtoidentifysatisfactoryalternativestoaharnessbasedon

    fall prevention measures.

    Implementingtheuseofsolidworkzonebarriersisone

    effectiveengineeringsolution.Refertosection4.1.7ofthisguide

    for further information.

    Trainingisrequiredbeforeapersonusesaharness.Fortraining

    requirementsundertheSouthAustralianOccupational Health,

    Saety and Welare Act 1986(OHSWAct),pleasereferto

    Appendix2.

    2. Di

    Undersection23aDutiesofdesignersandownersofbuildingsoftheOHSWAct,designersofbuildingstobeusedasworkplaceshave

    obligations for workplace health and safety.

    2.1 sAfe DesIgn of buIlDIngs In relATIon To formWork

    2.1.1 bidaiit

    Buildingdesigners,includingengineersandarchitects,must

    considerthebuildabilityofastructureorbuildingwiththeobjective

    of producing a design that minimises the risk of injury during

    construction.

    Thedesignofthenalconcretestructuremayhaveamajoreffectontheeaseofformworkconstructionandconsequently,onthesafetyof

    peopleduringconstruction.Generally,amorebasicandsimplenal

    concrete structure is safer to erect.

    Aformworkdesignershouldbeconsultedduringthedesignofany

    building to provide input on ways to minimise the risk of injury arising

    from formwork activities.

    The following design measures could be considered to minimise

    exposure to risk of injury during the construction of formwork:

    Reducevariationsintheoordepthi.e.constructaoorsothat it has one consistent depth. Decks that are a consistent

    depthareeasiertoerectthanvariabledepthoorsandreduce

    theriskofinjury.Deeperbeamsintroducedropdownsinto

    theoor,creatingtripandfallhazards,andrequiremoreworkto

    construct and strip after pouring.

    Wherebeamformsareessential,lightweighttemporaryaccess

    across the beam recess must be provided to prevent injury to

    workersfromsteppingintotheformduringconstruction(see

    Figure2above).

    Reducethenumberofcolumnsrequiredandwherecolumnsdo

    exist,eliminatecapitalsanddropdowns.

    Utiliseprecastcolumnsandbeams.Thiscanreducetherisks

    associatedwithxingreinforcement,erectingandstripping

    columnformworkandpouringconcreteon-site.Workactivities

    carried out in a factory environment are generally lower risk.

    Reducecantileveredoorsections.

    Planformanualtasks.Considerationshouldbegiventothe

    suitability of the design of different formwork systems that willreduce manual handling risks such as:

    - table forms

    - systems with lighter weights of materials to be handled

    - methodsofformworkerection,alterationanddismantling

    - improved access and egress for workers and movement

    of materials and equipment

    - methodsformovinglargeandheavycomponents,materials

    and equipment i.e. making allowances for a crane and other

    mechanical lifting devices to be used.

    2.1.2 matia

    Allmaterialsandequipmentusedinformworkconstructionmust

    betfortheintendedpurpose,meetdesignspecicationsandbe

    designedtoconformtorelevantAustralianStandards.Equipment

    must be manufactured in accordance with a quality assurance

    systemthatensurescompliancewiththedesignspecication.

    Evidenceverifyingthatformplysheetsandtimberbearersconform

    toAustralianStandardsshouldbekepton-site.Suchevidencemay

    include:

    apurchaseorderwhichdetailsthespecicationsofthe

    form ply sheets ordered

    formplysheetsbeingmarkedinaccordancewithAustralian

    Standards(seeAS/NZS 2269.0:2008 Plywood-Structural-

    Specifcation).

    Figure 2 Flat oor and temporary access as

    all protection or deep oor beams

  • 8/22/2019 Formwork Guide

    7/376

    Ifalternativeproducts,otherthantimberareused,anengineer

    should verify that they are adequate for purpose.

    2.2 formWork sysTems

    InAustralia,formworksystemsaregenerallydesignedto:

    AS 3610 Formwork or Concrete

    AS 3600 2009 Concrete Structures.

    2.2.1 Safeformworkdesignandverication

    Adesignerofformwork,eitheraformworkdesigneroranengineer

    (seeAppendix1fordenitions),isresponsibleforoverseeingthe

    safe design of the complete formwork structure. This includes

    designoftheformworksupportstructure,theformworkdeckand

    connection details.

    Whenspecifyingthedesignoftheformworksystem,aformworkdesigner must allow for all expected loads applied during the three

    phasesofconstructioni.e.duringformworkerection,duringconcrete

    pouring and after concrete pouring is complete until the structure is

    self-supporting. This includes loads applied by:

    theformworkdeck,supportingmembersandformworkframes

    anyfalsedecksthatmaybeprovided

    concretepouringtechniques(i.e.concreteskiporpump)

    theconcretepour,whichincludesboththeweightofthe

    concreteanddynamicfactorsapplied,includingtheconcrete

    pour rate and pour sequence workersontheformworkdeckandfalsedecks

    stackedmaterials

    crane-liftedmaterialsonboththecompleteandincomplete

    formwork deck

    environmentalloads,includingforcesduetowaterowing

    aroundtheformwork.Rainandrunoffcanhaveadetrimental

    effect if not considered by a designer

    wind,asdetailedinAS 1170.2:2011 Structural Design Actions

    Wind Actions:

    wind loading will vary depending on:

    - thesizeofform

    - the nature of the form

    - wind speed

    - windresistance(e.g.screens)

    - wind direction

    windloadingonverticalforms,particularlyforexternalwalls,

    columns,freestandingshutters,bladewallsandany

    platforms that may be subject to uplift

    vertical elements should be fully braced prior to and during

    stripping until such time as the construction provides

    adequate support against wind loading shadeclothusedonscreens,signageandoutsidescreens

    will increase the effective wind loading of an open structure

    the geographical location of the construction site will have a

    bearingontheseverityofwindonthestructure.Wind

    generally has less effect in built up or hilly areas

    AS 1170.2 Structural Design Actions Wind Actions

    speciesfourdifferentterraincategoriesthatshouldbe

    taken into consideration by a formwork designer as well asbasicwindspeedsfordifferentzonesinAustralia

    [practicallyallareasofSouthAustraliafallunderRegionA

    (normal)].

    Refertosection4StructuralDesignandDocumentationof

    AS 3610 Formwork or Concretefor further details on formwork load

    calculations.

    2.2.2 Formworkdesigncerticationrequirements

    This guide considers two types of formwork systems: ai and-ai.Aformworkdesignermaycertifyabasicformwork

    system,whereasonlyanengineermaycertifyanon-basicformwork

    system.

    Whilethisguiderecommendsthatonlyanengineermaycertifya

    non-basicformworksystem,itisrecognisedthatacompetentperson

    experiencedinformworkdesignanddocumentation,suchasa

    formworkdesigner,mayperformthemajorityofthedesignwork.

    Forbothbasicandnon-basicformworksystems,certicationshould

    conrmthattheformworkmeetstherequirementsofAS 3610

    1995 Formwork or Concreteand the construction drawings. Thiscerticationshouldalsoconrmthatotherformworkandproject

    documentationdetailedinsections2.2.3ofthisguide,havebeen

    completedasrequiredfortheproject.Sampleengineerscertication

    lettersareprovidedinAppendix3.

    bai w t

    Forthepurposesofthisguide,abasicformworksystemisthe

    formworkforaoor,wallorcolumnandincludes:

    standardformworkframeswhichhaveaknowntestedloading

    capacity and are spaced at no more than the recommended

    distancesapartforanormaloorthicknesswithbearers,joists

    and form board on top of them

    speciallymanufacturedanddesignedformworksystemswith

    proprietary formwork components and rated load calculations in

    linewiththemanufacturersspecications.

    Abasicformworksystemislimitedbythefollowingconditions:

    theheightoftheformworkmaybeuptoamaximumof6mto

    thesoftofthenewoorfromthesupportingoor

    wallsandcolumnsmaynotbegreaterthan6mfreestanding fromtheooronwhichtheformworkwillbesupportedtothetop

    surface of the concrete

    anyback-proppingisexcludedfrombasicformworksystemsand

    istobecertiedbyanengineer.

  • 8/22/2019 Formwork Guide

    8/377

    Eitheraformworkdesignerorengineermaycertifyabasicformwork

    system.Whereanyoftheseconditionsareexceededorback-

    proppingisinvolved,thesystemistobeclassiedasanon-basic

    formworksystemandmustbecertiedbyanengineer.

    n-ai w t

    Formworksystemsthatexceedthedescriptionofabasicformwork

    systemare,forthepurposesofthisguide,categorisedasnon-basic

    formworksystems.Forthepurposesofthisguide,onlyanengineer

    may certify:

    thedesignofanytemporaryorpermanentformworkstructures

    categorised as non-basic formwork systems

    anyback-proppingusedforeitherbasicornon-basic

    formwork systems.

    Non-basicformworksystemsincludeformworkstructuresforany

    oor,wallorcolumnhigherthan6m,orthreeframes,orthreetimesthe least base width of the scaffold.

    2.2.3 Dtati

    The extent of documentation required for any structure may vary

    depending on the complexity of the formwork and supporting

    structure design and the conditions in which it is to be constructed.

    The documentation requirements outlined below are provided as

    aguideonly,forsituationswherethereisacomplexconstruction

    processatheight,thatisconsideredtobehighrisk.Itisexpected

    that some elements of documentation may be reduced or omitted forsome more basic and lower risk construction applications.

    fw dawi

    Formworkdrawingsexplainthegeneralarrangementoftheformwork

    plans,elevationsandsections,identifyingandlocatingallmembers

    and components including bracing.

    Anengineershouldnominatethefollowingonthedrawingsorother

    documentation:

    maximumallowablepointloadingtobeappliedandany additionalproppingrequirementsatanyspecicloadingarea

    componenttypesandspacing

    maximumjackextensions

    bearerandjoisttimbertype,dimensionsandspacing

    propsizesandmaximumextensions

    methodsfortyingthestructuretogetherandspacingbetween

    ties(ifrequired)

    formplysize,thicknessandgrade.

    WhereeccentricloadingistobeappliedtoU-heads(i.e.single

    bearersarepositionedtoonesideoftheU-head),theformworkdrawings must state that this is permitted.

    oth w dtati

    The following information should be included in the formwork

    documentation:

    anynecessarypreparationofthefoundationsuchaslling,

    compaction and drainage anyfootingdesignassumptions,suchasfoundationmaterial

    description,safebearingvalues,limitationsonsettlementduring

    erectionofformwork,placementofconcreteanddismantlingof

    formwork.Referencetoinformationsourcessuchas

    geotechnical reports may also be included

    footingdetails,suchastypeandsizeoffootings,levelofsoft,

    concretemixdesignstrength,reinforcement,specication

    anddetailsofsitellingorcompaction,andprecautionsagainst

    washouts

    sufcientdetailstofullydescribeimportantorunusualfeatures

    oftheformworksystemdesign,includingdesignassumptions,

    particularlythoserelatingtostrength,stabilityandstiffness

    theareasoftheformsdesignedtocarrystackedloads,together

    withthemaximumallowableload,andtheminimumstrengthof

    concrete to be achieved prior to materials being stacked

    Safeworkmethodstatementsaddressing:

    the erection and stripping of the formwork assembly

    methods for securing single or multiple props

    methodsforeldadjustmentoftheformspriortoand

    during concrete placement

    verticalpourratesinmetresriseperhour,includingtherisksand implications of exceeding vertical pour rates

    sequenceofconcreteplacement,includingdirectionof

    intendedpouronrakingorslopingsurfaces(e.g.carpark

    ramps and minimum elapsed time between adjacent

    placements)

    wrecking strips and other details relating to stripping of

    the forms

    certicationofnon-proprietaryequipment

    referencetodocumentationforproprietaryitems

    whererequired,locationofweepholes,vibratorholes,clean-out

    holes and inspection openings acceptancecriteriaforsingleuseformwork.

    Pt dtati

    Otherprojectdocumentationshouldincludethefollowing

    information:

    detailsoffallandedgeprotectioni.e.perimeterscaffolding

    locationofanymandatoryjointsandanyspecialproceduresfor

    locating other joints

    detailsofanyinserts,waterstops,speciallyformedshapesor penetrationstobeconstructed,thelocationanddetailsofwhich

    are critical to the serviceability of the permanent structure

    informationonanyarchitecturalorstructuralcomponentdetails

    to be cast into the structural concrete

  • 8/22/2019 Formwork Guide

    9/378

    detailsofthecamberingofanyslabsorbeams

    informationaboutanypermanentformworksystems,together

    withlimitationsondeectionsandanyspecialrequirementsfor

    their erection and concreting

    limitationsontheuseofthepermanentstructurefortherestraint

    of formwork minimumstrippingstrengthortimes,strippingproceduresand

    requirements for health and safety

    detailedinformationontheeffectofpreorpost-tensioning

    procedures on the formwork and any special procedures to be

    adopted in the stripping of formwork

    detailsofback-proppingthatmayberequiredandminimum

    timeintervalsbetweenconcretepours,includingrequirements

    for propping of any composite construction

    requirementsfortheminimumnumberoflevelsofsupports

    relativetothetypeofformwork,thetimingandsequenceof

    oorpropping,andtheanticipatedtimebetweenconstructionof

    subsequentoorsformultistoreystructures.

    2.2.4 Di vaiati

    Allformworksystemdesignvariationsmustbecheckedbyaformwork

    designerforabasicsystem,oranengineerforanon-basicsystem.

    Thevariationsmustbecertied(inwriting)ascomplyingwith

    AS 3610 Formwork for Concreteor whether they need to be altered

    in accordance with written directions to comply withAS 3610.

    Potentialvariationsmayinclude:

    thenumberofformworkframesundertheformworkdeck

    typesandnumberofbracesorpropsotherthanindicatedon

    the formwork drawing

    typesand/orquantitiesoftiesontheformworkstructure

    spansonmemberssupportingtheformworkdeck

    back-proppingsystemsspeciedbyanengineer

    connectionsbetweentraditionalformworkand

    modular formwork.

    2.2.5 On-sitecoordinationandverication

    Complexprojectsrequireconstantandvigilantcoordinationbyan

    experiencedmanagementandsupervisoryteam.Withproperly

    scheduledandcoordinatedactivities,sub-contractorsareabletocarry

    outtheworkinanorderly,safe,andmoreproductiveway.

    Effectivecoordinationandtechnicalaccuracyalsorequirethat

    formwork,projectandvariationdocumentationarereadilyaccessible

    on-site.

    Wheneffectivesitecoordinationisnotimplementedoraconstruction

    teamdoesnothaveaccesstoessentialtechnicalinformation,the

    potential for failure increases.

    Vericationoftheformworkstructure

    Aneffectivequalitycontrolsystemmustbeimplementedforthe

    construction of formwork. The system should ensure that:

    materialsandcomponentsusedon-sitecomplywiththeformwork

    designspecications,drawingsanddocumentation

    damagedorexcessivelywornmaterialsandcomponentsarenot

    used,butareidentiedandsentoff-siteforrepairoraredestroyed.

    Theformworkstructurescompliancewithitsdesignmustbeveried

    anddocumented.Aconstructionchecklistmaybeusedasaguidefor

    thisprocess(refertoAppendix4forasamplechecklist).However,

    relying solely on a checklist does not necessarily verify compliance with

    relevantAustralianStandards.

    Thedesignvericationanddocumentationprocessmaybedelegated

    toacompetentpersonwho,ifnotanengineerorformworkdesigner,

    musthavetheexperience,trainingandknowledgetoperformon-site

    inspectionsoftheformworksystem(refertoAppendix1fordenitions).

    The competent person must be:

    experiencedinformworkconstruction

    competentininterpretingdrawings

    abletocertifythattheformworkstructuresatisesthedetails

    ontheformworkdrawings,specicationsandanyotherformwork

    documentation.

    Shouldthecompetentpersonon-sitenotbeaformworkdesigneroran

    engineer,thecompetentperson:

    mayonlyverifythattheformworkstructurecomplieswiththe

    designersspecicationsanddrawings

    maynotauthorisevariationstothedesign mustprovideanyconstructionchecklistreferralstoanengineer

    in writing

    mustprovidewritteninstructionstotheformworksupervisorfor

    any remedial actions that need to made to the formwork system

    prior to the concrete pour

    mustensurethatanyremedialactionrequiredhasoccurredprior

    totheconcretepour,includinganyitemsreferredtoanengineer.

    Pre-pourinspectionmustfocusonsuchmattersas:

    thelatestversionofstructuralandformworkarrangement

    drawings and details submitted

    correctspacingofframes,propsandtimbers

    correctjoistandbearersizes,andloading

    acceptablejackextensions

    adequatebracingtoensurestability.

    Pre-pourinspectionsarethelastreasonableopportunitytoensure

    compliancewiththeformworkdesignspecications.Suchinspection

    records form an important part of the site quality control system and

    mustbesigned-offbyanengineer,formworkdesignerorcompetent

    personfollowingthenalpre-pourinspection.Asamplepre-pour

    structuralinspectioncerticateisprovidedatAppendix5.

    c dt i w yt

    Appendix6illustratessomeofthemorecommondefectsthat

    are likely to occur in a formwork system. The list is intended to

  • 8/22/2019 Formwork Guide

    10/379

    give guidance to a competent person and is not considered to be

    exhaustive.Inanyindividualcase,theimportanceofitemsmayvary

    and only a competent person can assess their relative importance.

    3. cdiati ad adiitati

    3.1 Work ProgrAm

    Therisktoapersonshealthandsafetymustbeconsideredwhen

    designingaworkprogramforerecting,alteringordismantling

    formwork.Considerationshouldbegivento:

    edgeprotectionrequirementsandensuringthesearedesigned

    and constructed in a timely manner to be safe to use

    sequencingworktoensurethatsufcienttimeandresources

    are allowed for each work activity

    coordinatingtradestoallowworktobecompletedfreefrom

    obstruction.

    3.2 HousekeePIng Access AnD sTorAge

    Formworkconstructionresultsinaconstantlychangingwork

    environment,withrestrictedaccessthroughframesandformwork

    supports,oftenwithlargevolumesofmaterialandwaste.Forthis

    reason,itrequiresongoingmonitoringofhousekeepingpracticesto

    maintain a safe and productive workplace.

    Include housekeeping as an essential aspect of every job whether

    itbethroughworkinstructions,regularinspectionoftheworkplace,or site/task induction training. Instructions should include time and

    resources for the progressive clean up of work areas to prevent

    rubbishandredundantmaterialsfrombecomingatriphazardandto

    allow safe access for mechanical aids.

    3.2.1 A ad

    TheOHSWRegulationsrequirethattherebeclearaccessto

    andfromtheworkplaceinaccordancewithDivision1Access

    and egress.

    Clearaccessisimportantforthesafemovementofmaterials,

    equipment and anyone on-site. Designated access ways should be

    providedandanyoneon-siteshouldbedirectedtousethem.Access

    waysmustbekeptclearofanyrubbish,plantormaterials.

    Insomesituations,greenhazardtaping/buntingorothervisual

    methods can clearly show where access ways are located. This

    is particularly important where access is required through

    formwork frames.

    Emergencyaccessandegressmustbeprovidedtoallpartsofthe

    workplace. The following situations should be considered:

    stretcheraccessandegress

    peoplecarryingtoolsandequipment

    useofstairs

    provisionoftwomeansofegressatalltimes.

    3.2.2 matia ta

    TheOHSWRegulationsrequiresafestackingandstorageofplant

    andmaterialsataworkplace,asdetailedinDivision15Storage.

    Materialsmustbestoredinawaythatminimisesmanualtask

    hazards,triphazardsandthepotentialforhazardsfromfallingobjects.SmallercomponentssuchasU-heads,couplers,baseplates

    andZ-barsshouldbestoredinlabelledmaterialboxes,markedwith

    safeloadlimits(SLL).

    Wherepracticable,frames,formplysheets,bearersandjoists

    should be strapped in bundles or stacks and be located away from

    theedgeofthedeck,topreventmaterialsoranyoneaccessingthem

    from falling.

    Wallformsshouldbestackedinsuchawaythattheycannotslide,

    orrotateawayfromthesurfacetheyareplacedagainst.Anengineer

    shouldverify,inwriting,thatasurfacetobeusedforstackingforms

    iscapableofwithstandingtheimpactofallimposedloads,including

    windloading.Ifpurpose-madeA-framesarenotavailablefor

    storingwallformswhennotinuse,itispreferabletolaythemat

    ontheground,ratherthanleaningthemagainstotherstructures.

    Timbers,orothereffectivemeansofsupport,shouldbeusedunder

    forms where slings are to be used for lifting.

    3.2.3 rih ta ad a

    Rubbishstorageandremovalforformworkmayincludethe

    provision of rubbish skips and wheelbarrows that are moved as work

    progresses.However,rubbishskipsmayonlybepositionedwhere

    the supporting structure has adequate strength to support the total

    weight of the bin and its likely contents.

    3.2.4 sta t iii aa ta i

    Incorrect material delivery and storage practices can create

    signicantmanualhandlingrisks.Safeworkpracticesthatcanassist

    in minimising these risks include:

    ensuringthatformworkmaterialsaredeliveredascloseas

    practicable to the job

    designinganddesignatingasmallsectionoftheformworkdeck

    as a loading platform for ply and other components

    ensuringmechanicalaidsareusedtohandleloadswherever

    possible

    storingloadsontrolleystominimisedoublehandling,oron

    raised platforms to minimise manual lifting from ground level

    havinganadequatestoragespaceorlaydownareastosafely

    store materials/equipment and to minimise double handling.

  • 8/22/2019 Formwork Guide

    11/3710

    3.3 TrAInIng

    Anyonewhomaybeexposedtoworkplacehealthandsafety

    risks resulting from formwork construction must be provided with

    informationandtrainingthatisspecictotheformworksystemthat

    is being used. Training and information should include details of:

    theformworksystem,components,tasksandactivities

    thewaythemanufacturerordesigneroftheformworksystem

    intendedittobeerected,installed,used,moved,alteredor

    dismantled

    therangeofhazardsassociatedwiththeformworksystem,

    controlmeasurestominimiseexposuretotherisks,thecorrect

    use of controls and how to ensure controls are maintained

    anyspecialrequirementstoundertakeorparticipateinspecic

    tasks or activities

    anysafeworkmethodstatements,includingtheuseofmechanical aids and devices

    theuseandmaintenanceofequipment,includinganyspecic

    conditionsandprohibitionsonitsuse.Wherenecessary,

    referenceshouldbemadetooperatorsmanuals

    anyspecialsafetyinformationneeded,suchassafety

    precautions for working under certain conditions including hot

    workorconnedspacework

    personalprotectiveequipmentrequirements,including

    instructionsfortting,use,cleaning,maintenanceandstorage

    theavailabilityandcontentofthisindustryguidancedocument.

    FortrainingdetailsrefertoAppendix2.

    4. W t

    4.1 formWork erecTIon TrADITIonAl sysTems

    TheOHSWRegulationsdescribewhatmustbedonewherethere

    isariskapersoncouldfallinDivision13PreventionofFalls.

    Thelegislationalsorequiresthatahazardidenticationandrisk

    assessmentbeconductedand,wherenecessary,safeworkmethod

    statements documented.

    Formworkactivitiesmustcomplywithregulatoryrequirements

    fortheerectionofscaffolding.Formwork,likescaffolding,mustbe

    erectedsafelyandsystematically,andbetiedinprogressivelyto

    stabilise the structure.

    Apersonmustbeprovidedwithaworkingplatformatleast

    450mmwide(i.e.twoplanks)evenwhenthepotentialfalldistance

    is less than 2 m. It is not acceptable for a person to work from a

    single plank or bearer.

    Irrespectiveofwhichframingsystemisused,workersmustalways

    use working platforms that are two planks wide as a minimum.

    Whereapersonistoinstalljoists,thiscanbeachievedusingatwo-

    plankworkplatformfromunderneath,allowingtheverticaldistance

    between the formwork deck and the false deck to be increased. This

    isillustratedinFigure3below.

    Figure 3 Worker erecting ormwork on two planks

    >2.0

    vArIAble

  • 8/22/2019 Formwork Guide

    12/3711

    4.1.1 fdati

    Formworkmustbeerectedonastablebasetopreventtherisk

    ofcollapse.Suspendedslabsmustbeabletosafelysupportloads

    thatmaybeappliedbytheconcretepour,workersandcrane-lifted

    loads etc.

    Baseplatesmustbeprovidedunderpropsandstandardson

    formworkframesunlesstheproporstandardhasanintegralfoot,or

    an engineer documents that a base plate is unnecessary.

    Soleboardsdesignedtosuitthegroundconditionsmustalsobe

    usedunderpropsandstandardsonnaturalground,unlessan

    engineerstatesotherwise.Framesandpropsmustbelocatedon

    asoundbasethatwillnotsubside,failorwashaway.Theprincipal

    contractor is responsible for providing all information on ground

    conditions to the engineer or formwork designer.

    4.1.2 fa d

    In situations where a deck is being installed at a height that would

    require a person to stand at a height of 2 m or more to install bearers

    andjoists,acontinuousfalsedeckshouldbeprovided(seeFigure

    4below).Thisisafulldeckthatisthesameareaastheoorbeing

    formedbutupto2mbelowthetruedeck.Asindicatedinsection4.1

    above,thedistancebetweenthefalsedeckandthetruedeckcanbe

    increasedwhereaworkplatformisused.However,thefalldistance

    from the work platform to the false deck must not exceed 2 m.

    The false deck should be continuous both inside and between

    formworkframesandtypicallyconsistsofformply,scaffoldplanksor

    modularplatformsections.Aprotectedaccessopeningcanbeleftin

    the deck for lifting in materials.

    The use of a captive platform is preferable to lapped planks

    because a captive system cannot be accidentally dislodged and its

    constructionalsominimisestriphazards.Lappedplanksmayonly

    be used if they are secured against uplift and slippage. The false

    deckshouldbeconstructedsuchthatnogapexceeds225mmin

    width and gaps only exist where a vertical member of a frame passes

    through the deck.

    The false deck should be designed to have adequate strength to

    support:

    anyonerequiredtostandonthedeck

    materialsthatneedtobeonthedeck

    anymaterialsorworkersthatshouldhappentofall.

    The deck must be able to withstand:

    apointloadof2kNdistributedoveranareaof100x100mm

    (2kNisapproximatelyequivalenttoamassof200kg)

    auniformlydistributedloadof2kPa,whichisequivalenttoa

    mass of 200 kg per m2.

    Whenconsideringthedesignofthedeckforerecting,alteringor

    dismantlingformwork,theweightofthefalsedeckandanyadditional

    live loads must be applied to the analysis of the formwork support

    structure.

    The height between the false deck and the pouring deck should allow

    comfortable access for a person during stripping.

    4.1.3 eti a

    Anyoneinvolvedinerectingformworkframesmustbetrainedto

    dothissafely.Apersonsupervisingtheerectionofformworkframe

    systemsmustbeacompetentperson(asdenedinAppendix1).

    TheOHSWRegulationsprovidetherequirementsfortrainingand

    responsibilities of workers performing a class of high risk work.

    In cases where scaffold equipment is used as a formwork support

    structureanditispossibleforapersonorobjecttofall4mormore

    fromthescaffold,theOHSWRegulationsrequireapersontohold:

    aBasicScaffoldinglicence(SB)toerectproprietaryframes

    or

    anIntermediateScaffoldinglicence(SI)toerecttubeand

    ttingscaffold.

    Traineesarepermittedtoperformscaffoldwork,providedtheyare

    under the direct supervision of a competent person who holds the

    scaffolding licence necessary for the task.

    Formworkframesshouldbeerectedinaprogressivemannerto

    ensureboththeinstallerssafetyandthestabilityoftheoverall

    structure.Bracingistobeattachedtotheframesassoonas

    practicable. The risk of a fall from edges of formwork frames during

    theirerectionishigh.Inthissituation,itisnecessarytoinstalledge

    protection on the frames as they are erected.

    Conventionalformworkframesincludediagonallyhingedbracesthat

    crossinthemiddle.Whilethesebracesarenotconsideredtobe

    suitableedgeprotectionforacompletedformworkdeck,basedona

    riskassessment,theymayprovidereasonablefallprotectionduring

    frameerection.Suchfallprotectionexistsonlywhenbracesare

    installedimmediately,andinaprogressivemanner.

    Figure 4 A alse deck

    Gap not to exceed 225 mm

  • 8/22/2019 Formwork Guide

    13/3712

    Astheheightofformworkframesincreases,thereisagreaterneed

    toprovidelateralstabilitytotheframestructure.Allframingmustbe

    carried out so that it complies with on-site design documentation and

    anymanufacturersrequirements.

    4.1.4 Itai a

    Whenpositioningbearers,installersmustbelocatednomorethan

    2mfromtheoororthefallarrestingplatformlocatedimmediately

    belowthem.Forexample,bearerscanbeliftedontothetopofthe

    formwork frame by a person standing on a work platform erected

    withintheframeandnomorethan2mfromtheoororfalsedeck

    locatedimmediatelybelow(seeFigure5below).

    Bearersmustbepositionedsuchthattheywillnotfallfromthe

    frames. The common methods of ensuring this are to place the

    bearersinU-headsontopoftheframesandalsobyensuring

    cantileversareminimised.WhereonlysinglebearersareplacedintheU-head,thebearermustbeplacedandxedcentrallyinthe

    U-headunlessaformworkdesignerorengineerstatesotherwise.

    4.1.5 Itai it

    Whereafalsedeckisprovidedat2morlessbelowformworklevel,

    joists may be spread on the bearers with the worker standing on the

    false deck. If the height of the formwork deck being constructed is

    morethan2maboveacontinuousdeckorsurface,joistsmustbe

    spreadfromaworkplatform,atleasttwoplankswide,andlocated

    within 2 m of the surface underneath the deck being constructed(refertoFigure5).

    Oneexampleofaworksystemthatmaybeusedtodothisis

    as follows:

    The joists are lited by the workers and spread on top o the

    bearers into their approximate fnal positions whilst standing on a

    lower work platorm. The platorm below the deck must be

    positioned at a comortable height or handling joists (without

    introducing manual task risks) and not greater than

    2 m rom the alse deck.

    4.1.6 fa ptti th w d

    Continualmodicationoffallprotectionmeasuresisnecessary

    during formwork construction because the structure is constantly

    changing.Oneofthebiggestchallengesistoprovideadequatefall

    protection on the leading edge of the formwork deck.

    Wherethereisonlyoneleadingedge(i.e.theotheredgesareprovidedwithscaffoldingedgeprotection),theprovisionoffall

    protectionisrelativelystraightforward.However,wherethereare

    multiple leading edges and/or the deck is not at one consistent

    level,theprovisionoffallprotectioncanbedifculttoimplement.

    Designersofbuildingsarethereforeencouragedtodesignoorslabs

    thatareoneconsistentthickness(refertosection2.1.1Buildability).

    Leadingedgeandperimeterprotectionmustbeprovidedonedges

    where the potential fall distance is 2 m or more and a person is not

    preventedfrombeingwithin1.8moftheedge.Controlmeasuresare

    requiredwhereapersoncouldfall,fromanyheight,ontoanobject

    suchasframes,reinforcingsteelorarubbishskip.

    Figure 5 Setting U-heads, bearers and joists

    rom a two-plank platorm

    2.0

  • 8/22/2019 Formwork Guide

    14/3713

    4.1.7 ed ptti th w d

    4.1.7.1 fw tti z phia ai

    Aphysicalbarriershouldbeprovidedandmaintainedtoseparatethe

    formworkworkzonefromotherworkers.Thisbarriermustberigid,

    capable of maintaining its integrity in an upright position and capable

    ofsupportingsignageifrequired(seeFigures6aand6babove).

    The use o ags and tape or unsupported barriers is not

    acceptable.

    Wherethedesignoftheformworkiscomplexandtheproleof

    thedeckisconstantlychanging,constructionofleadingedge

    protectionmaycreatemorehazardsthanitwouldcontrol.Insuch

    cases,itmaybeimpracticaltoprovideedgeprotection,asanyone

    installing the edge protection would be exposed to the risk of falls.

    In some situations perimeter edge protection must be installed.

    Examplesinclude:

    wherethereisachangeindeckheightalongthesideofthedeck

    beingconstructed,(i.e.adropdownforabeam)andnojoistsor

    form ply have yet been installed at this different height

    wherealeadingedgeistobeleftunattendedandaccessonto

    thedeckisrequiredbyanyoneotherthanformworkers(i.e.the

    formwork deck has not been barricaded off and marked with

    keepoutsigns).

    4.1.7.2 ed ptti ptd d

    The most effective means of providing edge protection on a

    completed formwork deck is to install perimeter scaffolding.

    Scaffoldingiserectedpriortotheformworkand,therefore,prevents workers falling from the completed deck. The advantages

    ofthissystemarethatedgeprotectionforinstallersofthenal

    perimeterformplysheetsisalreadyinplace,thereisnorequirement

    toinstalledgeprotectionontheperimeter,andnoexposuretoarisk

    of falling.

    Insomeraresituations,itmaybeimpracticaltoprovideperimeter

    scaffolding.Insuchcases,edgeprotectionmustbeinstalledandthe

    work system used for this installation must include a control measure

    against the risk of a fall.

    Theuseofharnesssystemsisdiscouraged,becauseitdoes

    not provide an adequate level of protection from injury and is an

    impractical control for the risk of a fall from height in formwork

    erection(refertosection1.1ofthisguide).

    Insomesituations,edgeprotectioncanbesubstitutedwithan

    alternativemeasure,providedthismeasurepreventsapersonfalling

    fromtheedge.Onealternativeistheprovisionofabarricade,1.8m

    fromtheedgewithclearlyvisiblekeepoutsigns.

    Furtherguidanceonstanchions,guardrails(handrails)andmid

    railsforminimumstrengthandrigidityisspeciedinAS 1657 Fixed

    platorms, walkways, stairways and ladders Design, construction

    and installation.

    Wherescaffoldingisover4minheight,onlylicensedandauthorised

    scaffoldersmayerect,dismantleoralterthescaffolding.Anyscaffolding components that are temporarily removed must be

    replacedattheearliestopportunity.Anygapsbetweenacompleted

    oorandscaffolding,thatmayexistaftertheformworksupport

    systemisremoved,mustbecoveredwherethereisariskofa

    person or materials falling through.

    4.1.8 lai a w d

    4.1.8.1 gtti tatd a a

    Afterthesupportingframes,bearersandjoistsareinposition,the

    rstessentialconsiderationinlayingaformworkdeckisthatall

    building work conducted at height requires some type of perimeter

    protection.Thesecondessentialconsiderationisthat,forfall

    prevention,workersmuststayawayfromaleadingedge.Howthese

    essential elements are achieved is determined by the builder.

    Figure 6a General view Figure 6b Fixing detail

    Acceptable solid work zone barrier with No-Go zone below

  • 8/22/2019 Formwork Guide

    15/3714

    Therststepinlayingoutaformworkdeckistoprovidesafeaccess

    andaheavydutybaytoloadandstorematerials,particularlyapack

    offormply,attheformheight.Successfulsolutionswillbepartially

    guidedbythesiteitself,thesizeofthejoborthecontractors

    preferredsystem,andmaybeanengineeredsolution,ascaffold

    solutionoraformworksupportsystemsolution.Eachhasadvantagesand disadvantages.

    eid ti

    Generally,engineeredsolutionsareeconomicaltoassemble,

    disassemble,useandmaintain,andmaybedesignedforahigher

    load-carryingcapacity(withsufcientsupportframecapacity).They

    are more suitable for larger projects with more site room.

    Engineereddeckunitsarepositionedandliftedbymechanical

    aids,suchasmulti-purposetoolcarrier,forkliftorcrane,thus

    reducing the risk of injury from manual tasks. Drop-in hand railing

    systemsareeasilyinstalledatgroundlevel,reducingtheriskoffalls

    during erection.

    However,engineeredsolutionsgenerallyhaveahighercapitalcost

    todevelop,manufactureorpurchase.Engineeredsolutionsareless

    exiblebecausetheremustbeaclearaccesswayof450mm.This

    limitsavailablespaceforstorageofmaterialsonthedeck(seeFigure

    7below).

    sad ti

    Scaffoldsolutionsmaybemoreexibleintheirarrangementand

    would normally require a lower initial capital investment than

    engineered solutions. They are generally more suitable for smaller

    jobsandrestrictedsites.Scaffoldsystemloadingbaysaremanually

    erected,withtheplatformareaandhandrailsbeinginstalledat

    height,increasingtheriskoffallsduringerection.

    The load carrying capacity of scaffold-based systems is generally

    lowerthanengineeredsolutions,beingheldwithintheallowable

    limits forAS/NZS 1576.1:2010 Scaolding Part 1: General

    Requirements.However,scaffoldingmaybespecicallydesigned

    forhigherloads.Workplatformsdesignedforhigherloadsmust

    prominentlydisplayasignindicatingtheSLL.

    Scaffold-basedsystemsaregenerallymoreadaptableinallowing

    forincreasedsizeofstoreditems,notnecessarilybeinglimitedtothesizerequirementsof2400x1800mmformplysheets,whilst

    maintainingthenecessary600mmminimumaccesswidth.

    fw ppt t ti

    Packsofformplysheetsmaybeplaceddirectlyonthejoistsofa

    formworksupportsystemundercertaincircumstances.Asection

    of the formwork support system may be a nominated loading area

    providing:

    thenominatedloadingareaiscertiedbytheengineeror

    formwork designer

    themaximumSLLoftheareaismarkedontheformwork

    drawings,togetherwithadditionalproppingrequirements

    Figure 7 Engineered loading bay.

    Note: Drop-in handrails in place, liting eyes, orklit slots, and built-in bearers

  • 8/22/2019 Formwork Guide

    16/3715

    anynecessaryadditionalpropsareinstalledandinspectedprior

    to loading

    aperimeterscaffoldisinplaceforfallprotection

    theloadingareaissafelyaccessiblefromaperimeterscaffoldor

    other safe access structure

    alljoistsandbearersformingpartoftheloadingareaare adequatelysecuredinpositiontopreventafall,asdescribedin

    section4.1.8.3ofthisguide

    layingtheformplydeckproceedsasdescribedinsection

    4.1.8.3ofthisguide

    astartingpointforlayingthedeckisclosetotheformply

    stack so as to minimise worker exposure to the risks of injury

    from manually handling the form ply sheets.

    4.1.8.2 Tpia w t a adi d

    The following work system may be used to construct the formworkdeck for typical multi-level construction. The work system is

    specicallyintendedforsituationswheretheverticaldistance

    belowthedeckbeingconstructedisgreaterthan2m,butwiththe

    use of false decks may be used irrespective of the distance to the

    oorbelow.

    1. PlacebearersontheU-headsoftheformworkframesfromthe

    workingplatformprovidedimmediatelybelow.Securebearers

    topreventmovement,i.e.bynailingto,orwedgingin,the

    U-headsbeforejoistsareplacedontop.Noeccentric(un-

    centred)loadsshouldbeappliedtotheU-headsunless

    specicallyallowedbytheformworkdesigner.

    2. Placejoistsonthebearersinaprogressivemannerfromthe

    work platform located directly below the area to be worked

    on,andspacedat450mmcentres(maximum)orsothatthegap

    betweenjoistsdoesnotexceed400mm.Securethejoists

    against any movement should a worker fall onto them.

    3. Secureanycantileveredbearersandjoiststopreventupliftor

    dislodgement prior to anyone working on them.

    4. Layoutformply,orotherdeckmaterial,progressivelyas

    describedinsection4.1.8.3.Whereverpossible,thedirectionof

    theleadingedgeshouldbeperpendiculartothejoists,i.e.

    paralleltothebearers(referFigure8).

    Formplyshouldbeplacedonthejoistswiththeinstaller

    located behind the sheet as it is positioned whilst standing on

    the previously laid sheet or work platform provided. If this is

    doneconsistently,shouldapersontriporstumbletheywould

    fall onto the sheet and not from the leading edge.

    Planningshouldtakeintoaccounttheoptimumpositionfor

    theloadingbay,ordirectionofformplyplacementsothatlaying out of the sheets starts at the loading bay where the

    formplyisinitiallystacked,reducingtheneedformanual

    handling and carrying sheets.

    5. Coverorprotectallpenetrationsleftbehindtheleadingedge.

    Coversmustbesecurelyxedandclearlysignedtoindicatethey

    areprotectingapenetration(seesection4.1.10).

    6. Nailorotherwisesecureformplytothejoistsassoonas

    practicable.

    Iftimbershavenotbeenxed,edgeprotectioncomplying

    withOHSWRegulations2010(Division13Preventionof

    Falls),mustbeerectedleadingawayfromthesidesofthe

    leading edge.

    Onlypersonnelinvolvedintheconstructionoftheformwork

    maybelocatedintheformworkconstructionzone.Anyone

    not involved in this process should be excluded.

    Theleadingedgemustbefreeofoil,sawdustand

    obstructions to reduce the likelihood of slips and trips.

    4.1.8.3 lai a p d

    Aformworkdeckmustbelaidinaprogressivewaythatincludesa

    method of preventing falls below the deck. This control measure is

    particularly important in situations where a false deck has not been

    providedwithin2mbelowthelevelofthedecktobelaid,andthe

    potential fall distance is therefore greater than 2 m.

    Whereafalsedeckhasnotbeenprovidedwithin2m,formplymay

    only be spread on the joists where:

    aminimumoffourjoistsat450mmcentres(400mmgaps,

    totalling1.8m)arelocatedonbearersnexttotheperson,

    andthejoistsextendforatleast1.8mallround(seeFigure8).

    Therefore,intheeventofafall,thepersonwillfallontothejoists

    and be prevented from falling further

    layingtheformplysheetscommencesfromtheperimeter

    scaffolding or other edge protection that has been provided at

    theperimeteroftheformwork,e.g.attheloadingbaywheretheform ply is stacked

    theformplyislaidinfrontofthebodysothatifthereisa

    stumble,thefallislikelytobeontopofthesheetsbeinglaid

    Figure 8 Maximum spacing o timbers around worker

    where alse deck is over 2 m below

    400 mm

    1.8 m

    1.8 m

  • 8/22/2019 Formwork Guide

    17/3716

    joistsarexedtopreventsidewaysmovement.Insome

    situations,theremaybeapossibilityofapersonfallingthrough

    thejoistsifthejoistsspreadasthepersonsbodymakescontact

    with them during a fall. This is more likely to be a potential

    hazardwhenthepersonsfallisinthesamedirectionasthe

    layofthejoists.Fixingjoiststopreventsidewaysmovementwillminimise this possibility.

    4.1.8.4 lai a ta d

    Ametaldeckshouldbelaidinaprogressiveway.Whereafalsedeck

    has not been provided within 2 m below the level of the deck to be

    laid,metaldecksmayonlybelaidwheretheuseoffallprevention

    systemshavebeenprovided.Worksystemsfollowingthehierarchy

    ofcontrolsmustbeused.Examplesincludeelevatingworkplatforms,

    scaffolding,personalfallprotectionsystemsandanti-glaremeasures

    (refertoFigure9).

    4.1.9 cati qit

    AS/NZS 4576: 1995 Guidelines or Scaoldingrequires that

    the design of cantilevered scaffolds and the adequacies of their

    supportingstructuresmustbeveriedforcompliancewiththe

    relevant requirements ofAS/NZS 1576.1 Scaolding Part 1: General

    Requirementsbyacompetentperson,suchasanengineerwith

    experience in structural design.

    Cantileveredbearers,joistsandplysheetscanbehazardouswhen

    left unsecured. The weight of a person standing on the cantilevermaycausetilting,resultinginthepersonormaterialfalling.

    Formworksystemdesignersshouldminimisetheuseofcantilevers

    wherepossible.However,insomesituationswherecantilevered

    sectionsareunavoidable,theformworkdesignerorengineer

    must consider the potential for people and stored materials to

    causecantileverstopivot.Formworkdesignsmustindicatewhere

    cantilevers are to be positively secured so that the weight of a person

    or material does not cause the section to pivot.

    4.1.10 Ptati

    Anypenetrationwherethereisariskthatapersonoranobjectcould

    fallthroughmustbecoveredorsecurelyguarded.Openpenetrations,

    suchasstairwellvoidsorpenetrationstoallowforservices,create

    hazardsforanyoneonaformworkdeck.Apersonmayfallthrough

    largerpenetrations,sustaininjurybysteppingintoasmallerpenetration,

    oranobjectmayfallthroughtheopeningontoworkersbelow.All

    penetrations must include cast-in metal mesh as a backup system.

    Themeshshouldhaveasmallaperture(e.g.50x50mmmeshsize

    orsmaller),andbemadeofmaterialcapableofwithstandingthepotentialimposedload.Meshprovidedoverlargepenetrationsmay

    requireengineeringcerticationtoensureitcanwithstandpotential

    loadsincludingpeople,equipmentandmaterials.

    Whereholesarecutinthemeshforservicestopassthrough,the

    holeshouldbecuttotheproleoftheservicesothatmeshremains

    covering the penetration.

    Ungradedplywoodcoversarenotadequatebecause:

    thecovermaybeindistinguishablefromotherpiecesofply

    itmaybedifculttodetermineiftheplywoodisproperlysecured securedplywoodcoverscanbeunsecuredtogainaccessand

    subsequently may not be re-secured.

    Figure 9 Sae Work System or laying metal deck

    (Note:Fallpreventionsystems)

  • 8/22/2019 Formwork Guide

    18/3717

    Plywoodcoversmustbe:

    structurallygradedandsound

    aminimumof17mmthick

    paintedabrightcolour

    non-slip

    markedwiththewordsDAnger PeneTrATIon beloW.

    Thecovershouldbermlysecuredtotheconcreteanddesigned

    forpotentialloadsthatmaybeapplied.RefertoFigure10foran

    acceptablepenetrationprotectiondesign.Beforestrippingformwork,

    ensure the penetration that will be exposed is securely covered and

    protected.

    Penetrationsarealsohazardousbeforethedeckislaid.Joists

    placed up to the edge of the penetration must be secured so that the

    timbers cannot spread if a person falls on them.

    4.1.11 Wi z w ad th

    Theformworkconstructionzonemustbesufcientlylargetoensure

    that formwork areas are clearly separated from other work areas.

    Aformworkconstructiononlyzonemustbemaintainedbehind

    theleadingedge.Thiszonemustbeclearlydemarcatedbysignageandameshbarrier.Figure11illustratestheotherworkzone,the

    formworkzoneandthearearetainedasedgeprotection(fourjoists

    spaced1800mmbeyondthelaiddeck).

    Figure 10 Example o acceptable penetration protection

    *Reer to 4.1.7.1 Formwork construction zone physical barriers

    Figure 11 End view o deck showing working zones

    100 mm

    (min)

    100 mm

    (min)

    DAngerPeneTrATIon

    beloWSLL where required

    Zone for

    oTHer

    Workers

    formWork

    consTrucTIon

    Zone

    This distance may vary

    depending on work

    requirements

    Physicalbarrier*

    Dynabolt,orsimilar

    anchorage

    exap i

    Min17mmthick 50mmmeshcastincentrally

    FloorslabFloorslab

  • 8/22/2019 Formwork Guide

    19/3718

    4.1.12 Changingoorlevels

    Formworkdecksmaynotbeatacrosstheentireoor,dueto

    deepbeamsordropdowns(sometimescalledcapitals)around

    columns.Suchvariable,unevenoorsintroducetripandfallhazards

    duringformworkerection.Itispreferablethatthesehazardsare

    eliminatedatthedesignstage(seesection2.1.1Buildability).

    Fallandtriphazardssuchasthesearemosteffectivelymanaged

    by ensuring that lower level formwork supports and decks are

    progressively constructed before work commences on the higher-

    level areas of the deck.

    4.2 formWork erecTIon moDulAr

    formWork sysTems

    4.2.1 bai da t

    Thebasicprinciplesdiscussedinsection4.1ofthisguideontraditional systems apply to the erection of modular formwork

    systems.Althoughtheerectiontechniqueandmemberdimensions

    mayvarygreatlybetweentraditionalsystemsandmodularsystems,

    the principles of maximum potential fall distance and gap width at

    the working level are applicable:

    thewidthofanygaponaworkinglevelisnottoexceed

    400mmunlessafalsedeckhasbeenprovidedwithin2m

    of the working level

    workingplatformsusedformodularsystemsmustalsohave

    aminimumwidthof450mm.Bothmodularandtraditionalformworksystemsmustbedesigned

    to comply with the loadings and general principles ofAS 3610:

    Formwork or Concrete.

    Traditional formwork systems are sometimes used adjacent and

    connectedtomodularsystems,particularlyforunusuallyshaped

    areas.Wherethisisthecase,theformworkdrawingsshouldshow

    anyessentialconnectionordesigndetailsandbecertiedbyan

    engineerorformworkdesigner.However,componentsfromone

    proprietary type of formwork system should not be used as integral

    parts of other modular formwork systems unless the designer of themodular system states in writing that this is permitted.

    Modularformworksystemsareoftenmanufacturedfromaluminium

    insteadofsteelandarethereforelighterinweight.Beinglightweight,

    theyrequirelessphysicalefforttoerectthantraditionalsystems,and

    alsotheneedforrepetitivehammeringmaybeeliminated,reducing

    workersexposuretotheriskofinjuryfrommanualtasks.

    Becausemodularsystemsarelighterinweighttheymaybemore

    susceptible to overturning during erection when exposed to eccentric

    loading factors such as wind loading etc. This is generally an issue

    only prior to placement of the decking on the modular support

    system.Toeffectivelycontrolanyinstability,modularformwork

    systems must be progressively braced during erection in accordance

    withthemanufacturersinstructions.

    4.2.2 Taii

    Workersinvolvedintheerectionofmodularformworksystemsmust

    be trained in the safe erection and dismantling of the system and the

    inspectioncriteriaforcomponents,particularlyfordefectsthatwould

    preclude their use.

    The modular system supplier or designer should provide written

    instructions for the erection and dismantling of the system.

    Instructions should include safety instructions equivalent to those

    detailed in this guide.

    Trainingbythemodularformworksystemsupplierisencouraged.For

    trainingrequirementsrefertoAppendix2.

    4.3 sTrIPPIng formWork

    Strippingformworkcanbeoneofthemosthazardousphasesof

    concrete construction.

    Whilefallingobjectsaretheprimaryhazard,theremayalsobefall

    hazardsasaresultofoor,scaffoldorformworkcollapse,aswellas

    manualtaskhazardsfromapersonworkinginawkwardpostures,

    repetitivehandlingofmaterials,orlimitedtaskvariety.

    Workersmustbeinformedoftherisksandbeadequatelytrained,

    sothatstrippingoperationsarecarriedoutinanorderly,progressive

    manner,asoccurswithformworkerection.

    4.3.1 ga w tippi

    To reduce the risk of injury when stripping formwork/false work:

    installfully-deckedworkplatformsataheightnogreater

    than 2 m from ground level or the catch deck

    erectacatchdecknomorethan2mbelowtheworkarea

    suitablybarricadeandsignpostthestrippingarea

    (withbarriermeshasaminimum).

    4.3.2 sa w thd tatt

    Onlyanexperiencedandcompetentpersonshouldpreparesafe

    workmethodstatementsforthestrippingoperation.Properly

    prepared statements are very useful as a training tool for those

    who will be involved in this high risk activity. The safe work method

    statement should detail factors such as:

    thehazardsrelatedtothestrippingprocessandanyequipment

    and strategies to eliminate or minimise the risks

    thenumberofpeopleinthestrippingcrew

    thesequenceofstrippingactivitiese.g.detailinghowtheframes

    and/orothersupportsaretoberemovedandhowfarU-heads

    may be lowered

    whetherthesupportsystemmaybecompletelyremovedina

    zonepriortoremovaloftheformworkdeck,orwhetherthe

    supports are to be lowered slightly but still remain under the form

    ply while it is being removed

  • 8/22/2019 Formwork Guide

    20/3719

    whenback-proppingisrequiredoronlypartofthesupport

    systemistoberemoved,howthestructuralmembersareto

    remain in place and/or the type and layout of members that will

    replace the formwork system

    anyotherspecialrequirementsinvolvedinthestrippingand

    or building processes e.g. checking of back-propping afterpost-tensioning.

    4.3.3 Certicationpriortostripping

    Priortocommencementofthestrippingoperation,anengineermust

    providewrittencerticationthatformworkcanberemoved.This

    certicationshouldbebasedonanengineersspecicationsforthe

    building,thestrengthoftheconcretemixandthetimeperiodthat

    has elapsed since the pour.

    Anengineermayalsoberequiredtohaveinputintothestripping

    safe work method statement to ensure the concrete element

    doesnotfail,andmustprovidesufcientdetailonthestructural

    engineeringdrawingsasrequiredbysection17Formworkof

    AS 3600 Concrete Structures.

    Documentation from the concrete supplier verifying the concrete

    specicationshouldbeavailableonrequest.Aconcretesampling

    and testing procedure should be in place to verify that concrete

    meetsitsdesignspecicationforstrippingpurposes.Guidance

    on sampling and testing systems for concrete is provided in

    AS 1379:2007 Specifcation and Supply o Concrete.

    4.3.4 exi z

    Onlythoseinvolvedinthestrippingoperationarepermittedinan

    areatobestripped.Strippingareasmustbecordonedoffand

    signs displayed to keep non-essential personnel out of the area

    e.g. DAnger formWork sTrIPPIng In Progress

    AuTHorIseD Persons only.

    Itispreferabletorestrictaccesstothewholeoorwheresoft

    strippingistakingplace.Thiswouldnotonlybesafer,butalso

    reduces the quantity of signage and barricades required.

    Whereothertradesorsub-contractorsarerequiredtoworkonthe

    sameoorduringthestrippingofwalls,columnsorsmallsectionsof

    soft,theprincipalcontractororemployermustensurethatcontrols

    are applied to prevent non-essential personnel from entering the

    stripping area.

    4.3.5 Dp tippi

    Drop stripping is an unsafe method of work and cannot be supported

    by this guidance document. In cases where drop stripping is being

    considered,theformworkandsupportdesign,andtheconcreteelementdesign,shouldbereviewedbythedesignerandmodiedto

    eliminate drop stripping.

    4.3.6 bd dti

    Strippingofformworkmaybeaidedbyreducingthebondbetween

    theformmaterialandtheconcrete.Bondstrengthisdependenton

    thematerialcharacteristics,thesmoothnessoftheformmaterial

    and age of the concrete. The use of a liquid bond breaker on wall

    and column forms is one way of reducing the strength of the bond.

    However,theuseofbondbreakeronoorformsisnotencouraged

    becauseofthesliphazardthatmayresult.

    4.4 crAne AnD oTHer loAD HAnDlIng sysTems

    4.4.1 ladi atia di w tti

    Formworkstructuresarenotnecessarilysafetoacceptanyexcess

    loadinguntiltheyarefully-secured.Thatis,untilafterthedeckisin

    placewithtie-insandproppingcomplete,andanyproposedloading

    areacertied.

    Inpractice,someloadingoccursbeforeadeckiscompleted

    e.g. unloading pallets of ply and joists on a partially constructed

    formworkstructure,tocontinuethedeck.Thisisanunacceptable

    and dangerous practice which could lead to a full structural collapse

    ofthedeck,possiblyresultinginseriousorfatalinjury.Toensurethe

    integralsafetyofthedeck,materialsmayonlybestoredwhereand

    whenthedeckiscertiedasabletobeartheload.

    Formworkersandcranecrewsmustbemadeawareofthespecic

    locationsandloadsforcertiedloadingareas,andthatstacked

    materialsmaycreatepointloadings,whichaformworkstructuremaynot be designed to bear at that point.

    Tominimisetheriskofcollapseandotherhazards:

    loadsmustnotbeplacedontheformworkdeckifthe

    formwork documentation prohibits loading

    formworkdrawingsmustclearlyidentifythelocationsand

    SLLformaximum(pre-pour)pointloadingsforthedeck.These

    locationsmustbespeciedbyaformworkdesignerorengineer

    cranecrewsmaynotliftmaterialsontothedeckuntilthereisa

    designatedliftingzone

    cranecrewsmustbenotiedwhenanareaofdeckisreadyto

    takeaload,andspeciedloadsmayonlybeplacedinthearea/s

    designated and placed so that they cannot fall

    deliveryofmaterialstothesiteshouldbeplannedsothatloads

    are not lifted onto unsecured decks

    priortoworkersleavingthesite,materialsandequipmentshould

    be secured to prevent them being moved by wind.

    4.4.2 sii ad

    Slingingandun-slingingloadsatheightisalwaysahighriskactivity.

    Safeworkmethodsandfallpreventionsystemsareessentialforthis

    activity(refertosection4.1.8.1)

    Adogman,orotherpersonengagedinslingingloads,mustbe

    provided with adequate fall protection and a safe means of access

  • 8/22/2019 Formwork Guide

    21/3720

    when working at 2 m or more above the deck.

    The use of fall arrest systems for workers slinging formwork

    loadsisusuallyimpracticalandisnotrecommended.However,it

    maybereasonablypracticabletotplatformsandedgeprotection

    as fall protection.

    4.4.3 liti a

    Guidanceontheuseandinspectionofchains,wireropesand

    synthetic slings is provided in the following publications:

    AS 2759: 2004 Steel wire rope Use, operation and

    maintenance

    AS 3775.2: 2004 Chain slings Grade T Part 2: Care and use

    AS 1353.2: 1997 Flat synthetic webbing slings Part 2: Care

    and use.

    Basicitemsthatneedtobecheckedinclude:

    liftinggearistaggedandallrelevantinformationlisted

    (e.g.relevantinformationforachainslingisgradeofchain,

    safeworkingload,manufacturer,chainsizeandAustralian

    Standardmarking)

    liftinghookshaveoperablesafetylatches

    liftingeyesandinsertsarecompatible

    liftingslingsareserviceableandnotdamaged(i.e.haveno

    excessivewear,damagedstrands,cracks,deformationand/or

    severecorrosion)

    syntheticbreslingsaremaintainedingoodcondition,arerated fortheloadbeinglifted,haveasuitableslingingconguration

    and are protected from sharp edges.

    Itismostimportantthatallliftinggearincludingslings,hooks,wire

    ropes,pendantsandmaterialboxesareperiodicallyinspectedfor

    damage and wear. The period between inspections may depend on

    the severity of use with the exception of:

    chainslings,whereinspectionsmustnotexceed12months

    syntheticbreslings,whereinspectionfordamagemustbe

    undertaken before each use and full inspection at least every

    threemonths.Refertosection9ofAS 1353 .2: 1997 Flat

    synthetic webbing slings, part2:Careanduseforinspection

    itemsandsection11forDiscardCriteria.

    Documented maintenance records for the lifting gear should be

    available for inspection on-site.

    4.4.4 liti w atia

    Crane-liftedloadsmustbeslungandsecuredsothattheload

    (oranypartofit)cannotfall.

    Weightsofwall,liftorcolumnformsshouldbeprovidedon-sitewith formwork documentation and made available for inspection

    by all interested parties.

    SLLsmustbeclearlymarkedonbins.

    Liftingboxesintendedforliftingpeoplemustbedesign

    registeredwithSafeWorkSAandsuitablyconstructedforother

    material being lifted.

    Fourchains(oneineachcorner)mustbettedtoliftboxesto

    maintain stability.

    Liftingboxesmustbeinspected,maintained,andinspectionrecords kept.

    Specically-designedliftingboxesshouldbeusedtoliftsmaller

    components(e.g.spigots,U-heads,baseplatesandcouplers).

    Boxesmusthaveenclosedsidesorrobustmesh(withopenings

    lessthantheminimumsizeofmaterialsbeinglifted).

    Loadscontainedwithinliftingboxesshouldbesecured

    against movement.

    Materialsmustnotbestackedhigherthanthesideofthebox

    unless they are adequately secured.

    Formworksupportframesmusteitherbetiedtogetheror

    secured with lifting slings wrapped around the load.

    Loadsofjoistsorbearersshouldbestrappedtogether

    before lifting.

    Taglinesmustbeusedtocontrolloadsandforms,andmust

    bexedtotheload,nottheliftinggear.

    Formplyloadsshouldbestrappedtogetherandliftedina

    atposition.

    Ensure,wherepossible,thatallloadsaresupportedondunnage

    and the load is uniformly distributed over the supporting surface.

    Priortoliftinganyitems:

    removeanywasteconcreteetc.fromformsoranyother

    materials or equipment to be lifted to ensure the waste does not

    fall onto people below

    inspectallloadscloselytoensureallloosematerialsandtools

    have been removed.

    4.4.5 liti

    Chainslingsattachedtolugsorholescutintopartofaloadareoften

    usedtoliftbins,wall,liftwellorcolumnforms(insteadofwrapping

    theliftingslingsaroundtheload).Informationverifyingthestructural

    adequacy of the lifting points must be available.

    Anengineermustverify:

    thestructuraladequacyoftheliftinglug

    themeansofattachmenttotheload(usuallyweldedorbolted).

    4.5 use of lADDers

    Laddersmustbesecuredatthetoporbase,orwhenthisis

    impractical,heldrmlyatthebasebyanotherperson.

    Wherepracticable,alternativestoladderssuchasworkplatformsor

    stairaccesssystemsmustbeused.Fixedorpermanentladdersmustcomply withAS 1657 Fixed platorms, walkways, stairways and

    ladders Design, construction and installation.

  • 8/22/2019 Formwork Guide

    22/3721

    Whereladdersareprovidedasaccesstoalivedeck:

    theymustextendatleastonemetreabovetheaccessed

    surface,besecuredagainstmovementandbesetuponarm,

    level surface

    theymustbeofindustrialstandardwithaloadratingofat

    least 120 kg

    singleandextensionladdersmustbeplacedatanangleof

    between70degreesand80degreestothehorizontal

    (4up,1outrule),exceptinsomeraresituationswherethis

    is impractical

    singleladdersmustnotexceed6.1minlengthandextension

    laddersmustnotexceed7.5m.

    Otherissuesregardingthesafeuseofladdersinclude:

    metalormetalreinforcedladdersmustnotbeusedinthevicinity

    ofliveelectricalequipment.TheOfceoftheTechnicalRegulator (OTR)providesinformationoncompliancewithsafeworking

    distances in the vicinity of live electrical wires

    nevertouchaladderthatisincontactwithelectricalpowerlines

    apersonsfeetmustalwaysbemorethan1mfromthetopof

    the ladder

    laddersarenottobeusedonscaffoldingorelevatedwork

    platforms to gain extra height

    laddersmustnotbepositionedaboveoradjacenttoopeningsor

    edgeswhereapotentialfallcouldoccur.Aworkplatformwith

    edge protection should be used instead

    laddersshouldnotbeusedinaccesswaysorwherethereis pedestrian,vehicularormobileplanttrafcunlessarisk

    assessment has been undertaken and other precautions have

    been considered

    alwaysmaintainthreepointsofcontactwhenusingladders.

    5. spia qit wa ad

    5.1 brAcIng for WInD loADIng

    Wallandcolumnformsmustbedesignedtowithstandalllive

    anddeadloads,includingwindloadpriorto,during,andafterthe

    concrete pour. The bracing and forms must not be removed from

    thecastelementuntilitissufcientlymaturetosafelywithstand

    potential impact loads and wind loads.

    Priortostripping,anengineerorothercompetentpersonmust

    providewrittencerticationthattheformworkcanberemoved.

    Bracingmustbedesignedtosuititsapplicationandveriedbythe

    designer(refertosection2.2.1).Bracingelementsmustbedesigned

    and installed to resist both positive and negative wind generatedloads.Bracinganchorsshouldpreferablybecast-intypeorthrough-

    boltsthatextendthroughbothsidesoftheanchoringmedium.

    Drill-inanchorsofthefollowingtypemaybeused,providedtheyare

    installedinaccordancewiththemanufacturersinstructions:

    undercuttypeanchorthatdoesnotrelyonfrictiontofunction

    expansionanchorsofthehigh-loadslip,torquecontrolledtype

    coilbolts.Thecorrectoperationofcoilboltsisgreatlydependent

    on whether they are installed in accordance with a

    manufacturersspecications(e.g.drillingthecorrectsizedhole

    andapplyingthecorrecttorqueinconcreteofadequatestrength).

    Drill-intypeanchorsmayhaveaspecicinstallationtorqueset

    requirement to function correctly. Torque measurements should be

    madeusinganaccuratelyadjustabletorquewrench.Analternative

    method that may be used to verify the torque could be a calibrated

    rattlegun.Recordsverifyingthesettingtorqueforalldrill-intype

    anchorsshouldbeavailableon-site.Manufacturersnormallyspecify

    the minimum distance from a concrete edge that an expansion

    anchor may be installed.

    5.2 Access PlATforms

    Mobilescaffolding,purposebuiltworkplatformsorelevatingwork

    platforms may be suitable in providing the essential safe access to

    elevatedworkareasfordogmen,steelxersandconcreters.Edge

    protection must be provided on any access platform.

    Platformsmustbedesignedtoprovidesufcientaccessandworking

    spaceforthenumberofpersonnelrequiredforspecictasks,and

    must be positioned at a height and distance from the form so as to

    minimisereachingandstretchingmovementsandlimitapersons

    necessary exertion.

    Concretepouringsystemsmustprovideadequatesafeworking

    space,withedgeprotectionprovided,forallworkers.

    Castorsonmobileworkplatformsmustbelockedatalltimesexcept

    when they are being moved.

    Allplatformsmustbedesignedforstabilityandresistancetoany

    sideloadingthatmaybeappliedduringaconcretepour.Lightweight

    aluminium scaffolding may not have adequate stability when

    subjected to side loading and may require additional bracing.

    5.3 lIfTIng meTHoDs

    Wallandcolumnformsmayonlybeliftedwithapositivelifting

    system,suchasliftinglugsorbywrappingliftingslingsaround

    theformsuchthattheformcannotslipoutoftheslings.Purpose

    designedliftinglugsmustbeusedwhereverpracticable(referto

    section4.4.5).

    Anengineermustprovidedocumenteddesignsforwallandcolumn

    formliftingpoints,andthedesigndocumentationshouldbeavailable

    on-site.Whereliftinglugsareattachedtotheform,anengineermust

    specifythexingorwelddesign,andthemanufacturermustensure

    and certify that the attachment or weld complies with the design

    requirements.

  • 8/22/2019 Formwork Guide

    23/3722

    Formingliftingpointsbycuttingholeswithoxy-acetylenetorchesis

    unacceptable and must not be used as:

    theloadcarryingcapacitycannotbeguaranteed

    itmaydifculttoattachliftinggear

    positioningoftheholemaybeinaccurate

    theformmaybedamaged.

    6. spia qit ip ad p

    Thissectionappliestoslipforms,jumpformsandcrane-liftedforms

    that incorporate working platforms and enclosed cells in which

    people are required to work.

    Slipformsandjumpformsaretermsgiventoself-climbingformwork

    systemsspecicallyintendedtoconstructconcreteservicecores,walls and columns in high rise buildings and other concrete

    structuressuchassilosandchimneys.Inslipforms,theclimbing

    is usually carried out continuously during the concrete pour which

    maybecompletedtofullheightinonepouringoperation.Withjump

    forms,theclimbingisdoneinsteps,liftingthecompleteformunitto

    thenextlevelfollowingeachconcretepour.Thetermclimbingform

    isalsousedtodescribeeitheraslipformorjumpform.Climbing

    operations are usually powered by hydraulic rams or electric motors

    connected to climbing feet or screw shafts.

    Slipformsandjumpformsusuallyconsistofanumberofdecksand

    mayalsobettedwithtrailingscreensthataresuspendedfromthe

    form.Aswithperimeterscreens,trailingscreensmay:

    provideedgeprotection

    preventmaterialsfromfalling

    providesupportforworkplatforms,oracombinationof

    these uses.

    Notwoslipformsorjumpformswillnecessarilybeidentical,astheir

    designwillbebasedonthesizeandcongurationofthestructureor

    building under construction.

    The work systems and layout of some crane-lifted forms may also

    be similar to those associated with slip forms and jump forms. This

    may be the case for crane-lifted forms provided for the inside of lift

    shafts.Whilemostoftheinformationinthissectionappliestoslip

    formsandjumpforms,someoftheprinciplesmayalsoapplyto

    crane-lifted forms.

    Whendesigningandoperatingthesetypesofformsystems,the

    following issues must be addressed:

    providesafeaccesstoallareasandworkplatforms

    controlrisksassociatedwithworkingatheight developsafeworkmethodstatementsandusingthemtotrain

    workers in the safe operation of slip and climb form systems

    providesufcientworkingspaceandheadroom

    specifyandprovidesafeworkmethodstatementsformanual

    handlingofshuttersandothercomponents,e.g.theuseof

    cranes to lift shutters and provision of safe access for workers

    attaching slings to shutters

    ensureadequateventilationandlightinginallworkareas

    provideadequateamenitiesforworkersgiventhatslipformoperations often continue for extended shifts

    alwaysuseHotWorkPermitsforslipformandjumpformsystems

    ensuresufcientreextinguishersareprovided

    ensureemergencyprocedures,includingfortheretrievalofan

    injured or incapacitated person from any work area located

    withinthestructurearedeveloped,implementedandtrialled.

    It is acknowledged that it may not be practicable to provide an

    access system and working environment on a jump form or slip

    formthatisofthesamestandardaselsewhere.However,anyone

    incontrolofaproject,taskorworkersmustcomplywiththeirobligationsundertheOHSWAct.

    6.1 Access AnD egress

    Accesstoslipformandjumpformsystemsmaybeprovidedina

    variety of ways including one or more of the following:

    personnelandmaterialhoistsonthebuilding

    permanentstairsystemsinthebuilding

    atrailingstairsystemsuspendedfromtheslipformorjumpform

    atrailingladdersystem.

    Atrailingstairsystemispreferabletoaladdersystemasitiseasier

    toascendanddescend,andemergencyevacuationisgenerallysafer

    and easier on a stair system. The access area between the trailing

    accesssystemandthebuildingmustbeclearoftriphazardsand

    thereshouldbenogapsexceeding50mmwidebetweenplatforms.

    The formwork designer must ensure that a trailing access system is

    designed for additional loads that could be applied in an emergency

    evacuation situation. The design must ensure that not only the

    strengthoftheformsystemitselfisadequate,butalsotheformwork

    structure safely supports any applied loads from the access system.

    Atrailingstairaccesssystemshouldbedesignedforaloadof

    atleast2.5kPaunlessthedesignerspeciesotherwise.Where

    thedesignerspeciesalesserliveloadthan2.5kPa,thefollowing

    applies:

    asignstatingthemaximumloadlimitmustbexedtothe

    stairs in a visible position

    writtenproceduresmustbeimplementedtoensurethetotalload

    limit is not exceeded.

    Laddersmustbesecuredinplaceandbeplacedatanangle

    between70and80degreestothehorizontal,wherethisispractical.

    Accessopeningsforladdersonworkingdecksshouldbeprovided

    withtrapdoorsthatareclosedwhennotinuse,easilyopenedfrom

    above,anddonotcreateatriphazardonthedeck.

  • 8/22/2019 Formwork Guide

    24/3723

    Accesswaysshouldbekeptfreeofmaterialsandrubbishtoprevent

    objects falling to the level/s below.

    6.2 Work PlATforms

    Division13PreventionoffallsoftheOHSWRegulationsspecies

    requirements for work platforms. These requirements also apply to

    slipformsandjumpforms.However,thefollowingpointshighlight

    specicissuesthatmayapply:

    Whenplacingsteelorpouringconcreteintoaform,controls

    must be implemented that prevent a person falling into or from

    the form. The risk of this is higher when the form is greater

    than225mmwidepriortoplacementofreinforcingsteel.

    Workersmustalsobeprotectedfromtheriskofbeingimpaled

    onprojectingreinforcingbarsorotherobjects.Suitablecontrols

    may include edge protection on the internal side of the working

    platform,orreinforcementmeshtemporarilyplacedontopof theform,enablingthesteeltobefedthroughthemesh(see

    Figure12).

    Thedesignandconstructionofplatformsmustincludepositive

    xedsecuritysothatjammingormovementcannotoccurunder

    eccentric loads e.g. where work platforms have a trailing screen ononesideandaresupportedbyabuildingparapetontheother,

    uplift may occur from wind loading or where a platform is not

    levelandisunsecured.Ifthisoccurs,theplatformmayjamor

    otherwisemoveundertheunbalancedload,causingaperson

    to fall.

    Whereindividualcellsofaformareclimbedatdifferenttimes,

    edge protection must be provided separately on each cell.

    Safeworkmethodstatements,developedforallhigherrisk

    aspectsofslipformorjumpformsystemsandaccesssystems,

    will assist in ensuring safe systems are implemented and provide

    a sound training aid for workers engaged in this activity.

    6.3 TrAIlIng screens AnD PlATforms

    Trailing screens can provide edge protection and a means of

    preventing falling objects. They can also be designed to support

    lower,suspendedworkingplatformsforrepairingorpatching

    concrete,andtoprovideaccessforanyoneclimbingtheform.The

    formworkdesignerwillneedtospecicallyaddressanddocumentall

    issues for which the trailing screen system is designed. The design

    must address the following:

    Theremustbeasuitabledesignloadingforanyplatformson

    thetrailingsystem.Asaguide,platformsmustbedesignedto

    supportaminimumloadof2.5kPa.Adesignermayreduce

    this if the number of people is strictly limited and controls are

    implementedon-sitetoensurethespeciedloadisnot

    exceeded.Ifthedesignloadislessthan2.5kPa,thismustbe

    statedindocumentationkepton-siteandsignsmustbexedto

    the platforms stating the maximum load permitted in kilograms.

    Sitepersonnelmustbemadeawareofandcomplywiththe

    maximum loading that applies to the trailing platform.

    Strategiesmustbeimplementedtoadequatelycontrolthe

    riskfromfallingmaterials(seesection5forfurtherguidance).

    Allplatformsmustbesecuredtopreventupliftoranyother

    unplanned movement.

    Ariskassessmentofaformsystemmustincludetheneedfor,

    anduseof,laddersandedgeprotection.Thesystemmustmeet

    therequirementsoftheOHSWRegulations.

    Apersonmustnotrideontrailingplatformswhiletheplatformsare being crane-lifted. If access or work is required whilst a

    cranesupportsthetrailingplatform,anotherworksystemmust

    be devised. This could involve another crane with a registered

    workbox,oraseparateaccessscaffoldsystem.

    AnyworksystemchosenmustcomplywiththeOHSW

    Regulationsandincludesafeworkmethodstatementsbasedon

    riskassessment,withriskcontrolstrategiesbasedonapplication

    of the hierarchy of control.

    6.4 clImbIng THe form

    Climbingisusuallycarriedoutusingaseriesofclimbingdevices

    set up to lift at the same time and at the same rate. If the lifting

    system is not properly synchronised the form may become wedged

    onthestructure,orstructuralmembersmaybeoverloadedand

    become unstable.

    There should be a systematic approach to ensure that the form

    remains within level tolerances during the climbing process. The

    system may be automated or may rely on operators stopping each

    individualdevicecontrollingtheclimbingprocess.Whicheverprocess

    isused,thefollowingmustbeobserved:

    Asafeworkmethodstatementmustbedevelopedtotrain

    personnel and manage the climbing process.

    Figure 12 Mesh used as all protection

    on wall pour

  • 8/22/2019 Formwork Guide

    25/3724

    Onlythoseworkersdirectlyinvolvedwiththeclimbingprocess

    may be on the form during the climb.

    Anypotentialniporshearpointswhereapersoncouldbeinjured

    duringtheclimbmustbeidentiedandcontrolled.

    Allobstructionsandlooseitemsontheformaretoberemoved

    priortoclimbing.Aninspectionchecklistandsign-offprocedurefor this should be implemented. Items typically left on forms

    includeZ-bars,ferrulebolts,insertanchors,coversand

    hand tools.

    Itisimportanttoensurethedifferentpartsoftheformremain

    level during the climbing process.

    Electricalcables,waterandotherpiped